SlideShare a Scribd company logo
1 of 43
400kV GIS SUBSTATION
ERECTION SEQUENCE
Presented By
Anbarasu B
Project Engineer
400kV GIS Substation
Mobilization of GIS cart Unpacking of GIS cart
CB ready for placing at the
position
Alignment of CB with 0mm
error
Final alignment of CB
Current transformer under testing
CT placed on temporary
support
Disconnecting ready erect
over CT
Lifting of DS and CT after
couplingReplacing of gasket
CT and DS erected on CB After completion of all CT
& DS
Walkway platform shifted
inside the GIS
Platform during assembling
at ground floor
Platform erection over CB
After completion of walkway
platform
Diagonal bus placed on temporary support
AFTER COMPLETION OF DIAGONAL
BUS
Internal bus placed over DS
for compensation unit
After erection of
compensation unit
Main Bus support erection Main bus enclosure internal
inspection
ERECTION OF MAIN BUS ENCLOSURE
Full body cover for internal
inspection
Connecting of internal
conductor parts
Erection of Branch bus DS
with branch bus
Erection of branch DS with
branch VT
Main bus VT and Fast earth
switch erection with main bus
After completion main bus
VT and FES
Circuit breaker inter inspection and absorbent replacement
Replacement of absorbent
Connection of DS & ES
operating inter link rod
Vacuuming of
gas chamber
CB and all SF6 gas filling
Erection GIB support Lifting of GIB after inter inspection
and fixing of conductor
Erection of Gas insulated bus and its supports
Erection of SF6 toAir bushing
Erection of LA Erection of CVT and Line trap
High voltage testing kit erection
SF6 Gas Leakage test Damaged branch bus enclosure
under leak test after repairing
Suspension string lifting for erection
Assembling of tension string LIFTING OF TENSION STRING
INSULATOR AND
CONDUCTOR
After completion of lifting of
insulator string and its hardware
After completion of
conductor stringing
Erection of 220V and 48V battery bank
Power and control cable laying
Cable termination
CABLE TRAY ERECTION AND
FABRICATION
Panel base frame fabrication and erection
400kv gis substation erection sequence

More Related Content

What's hot

220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Gis substation
Gis substationGis substation
Gis substationAsif Eqbal
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training pptShubham Patel
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSoumya Raj Poddar
 
33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdfSagarRana91
 
220 KV Switchyard general overview
220 KV Switchyard general overview220 KV Switchyard general overview
220 KV Switchyard general overviewThien Huynh
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSPradeep Avanigadda
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmissionprasantakcs
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid SubstationAng Sovann
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substationpk130992
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substationsvishalgohel12195
 

What's hot (20)

220kv substation
220kv substation220kv substation
220kv substation
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Gas insulated substation.
Gas insulated substation.Gas insulated substation.
Gas insulated substation.
 
Electric substation
Electric substation Electric substation
Electric substation
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Gis substation
Gis substationGis substation
Gis substation
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
66 kv substation
66 kv substation66 kv substation
66 kv substation
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Tl book
Tl bookTl book
Tl book
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
 
33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf
 
220 KV Switchyard general overview
220 KV Switchyard general overview220 KV Switchyard general overview
220 KV Switchyard general overview
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 

Similar to 400kv gis substation erection sequence

Big Bowl centrifuge install Ensco 107
Big Bowl centrifuge install Ensco 107Big Bowl centrifuge install Ensco 107
Big Bowl centrifuge install Ensco 107Roy Catto
 
Estimation of bridges and automations copy
Estimation of bridges and automations   copyEstimation of bridges and automations   copy
Estimation of bridges and automations copykjanand
 
Bridge & Road Construction .pptx
Bridge & Road Construction .pptxBridge & Road Construction .pptx
Bridge & Road Construction .pptxMosaddekHaqueReyad
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptxDILIP KUMAR M.Tech (ACT)
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Crosstown TO
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
New Sands Retreatment Plant 2
New Sands Retreatment Plant 2New Sands Retreatment Plant 2
New Sands Retreatment Plant 2Simba Munyaradzi
 
Standard erection manual (pressure parts)
Standard erection manual (pressure parts)Standard erection manual (pressure parts)
Standard erection manual (pressure parts)Ashutosh Sachan
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020 Crosstown TO
 
M station Additional HCl Storage TanKs
 M station Additional HCl Storage TanKs M station Additional HCl Storage TanKs
M station Additional HCl Storage TanKsAhmad Moharram
 
Hydrology Report Modification.pdf
Hydrology Report Modification.pdfHydrology Report Modification.pdf
Hydrology Report Modification.pdfAbdulHameed354302
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsAmer Abdul Aziz
 
Difficult Run Force Main Rehabilitation
Difficult Run Force Main RehabilitationDifficult Run Force Main Rehabilitation
Difficult Run Force Main RehabilitationFairfax County
 

Similar to 400kv gis substation erection sequence (16)

Big Bowl centrifuge install Ensco 107
Big Bowl centrifuge install Ensco 107Big Bowl centrifuge install Ensco 107
Big Bowl centrifuge install Ensco 107
 
Closure Report
Closure ReportClosure Report
Closure Report
 
Engineered Spring Supports V.2
Engineered Spring Supports V.2Engineered Spring Supports V.2
Engineered Spring Supports V.2
 
Estimation of bridges and automations copy
Estimation of bridges and automations   copyEstimation of bridges and automations   copy
Estimation of bridges and automations copy
 
Bridge & Road Construction .pptx
Bridge & Road Construction .pptxBridge & Road Construction .pptx
Bridge & Road Construction .pptx
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
New Sands Retreatment Plant 2
New Sands Retreatment Plant 2New Sands Retreatment Plant 2
New Sands Retreatment Plant 2
 
Standard erection manual (pressure parts)
Standard erection manual (pressure parts)Standard erection manual (pressure parts)
Standard erection manual (pressure parts)
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Metroppt
MetropptMetroppt
Metroppt
 
M station Additional HCl Storage TanKs
 M station Additional HCl Storage TanKs M station Additional HCl Storage TanKs
M station Additional HCl Storage TanKs
 
Hydrology Report Modification.pdf
Hydrology Report Modification.pdfHydrology Report Modification.pdf
Hydrology Report Modification.pdf
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
 
Difficult Run Force Main Rehabilitation
Difficult Run Force Main RehabilitationDifficult Run Force Main Rehabilitation
Difficult Run Force Main Rehabilitation
 

Recently uploaded

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 

400kv gis substation erection sequence