SlideShare a Scribd company logo
1 of 33
Project Report on
CASE STUDY ON TUNNELING IN HARD ROCKS
By
Ma.Mayur .U. Rahangdale
(202030018)
M. Tech (Construction Management)
2020 - 2021
Guided by
Prof. (Dr.) S.Y. Mhaske
Department of Civil and Environmental Engineering
Veermata Jijabai Technological Institute
(Autonomous Institute Affiliated to University of Mumbai)
Mumbai 400 019
2020 – 2021
2
STATEMENT BY THE CANDIDATE
We wish to state that the work embodied in this report titled “CASE STUDY ON
TUNNELING IN HARD ROCKS” forms my contribution to the work carried out under the
guidance of Prof. (DR.) S.Y. Mhaske at the Veermata Jijabai Technological Institute.
This work has not submitted for any other degree or diploma of any university/ institute.
Wherever references have been made to previous works of others, it has been clearly
indicated.
Signature of the Candidate
MA.MAYUR .U. RAHANGDALE
(202030018)
3
CERTIFICATE
This is to certify that MA.MAYUR .U. RAHANGDALE (202030018) the studentof
M-Tech.(Construction Management) Veermata Jijabai Technological Institute, Mumbai have
Successfully completed the project entitled “CASE STUDY ON TUNNELING IN HARD
ROCKS” During the academic year 2020-2021, Under the guidance of Prof.(Dr.) S.Y.
Mhaske.
Prof. (Dr.) S.Y. Mhaske DR. S.Y. MHASKE
(PROJECT GUIDE) PROF & HEAD
CIVIL & ENVIRONMENTAL
ENGG. DEPT
4
ACKNOWLEDGEMENT
It is obvious that the development of project needs the support of many
people. Getting idea of analyzing a project, finalizing it as best one for me and above all
developing it successfully always is a job more than dozen of people. It is great pleasure for
me to acknowledge the assistance and contribution of my own effort. I had always been
grateful for the support that I got from all my surroundings with respect knowledge and
support.
I am very grateful to my Parents who have always being supportive of the
strange new twist and turns our life has taken. They are the one who have been the pioneer of
success and achievement in life and of course they have supported us rather directly or
indirectly in developing our project.
I sincerely acknowledge to my project guide Prof. (Dr.) S.Y. Mhaske whose
continuous encouragement and support enabled the project to materialized and contributed to
its success.
Finally, I thankful to all my Friends for their constant inspiration, support and
encouragement.
MA.MAYUR .U. RAHANGDALE
(202030018)
5
ABSTRACT
Tunnels are very important structures which are being used in various constructions; like in
road, railway for defense purpose and laying of pipelines etc. Tunnels have different shapes
on the basis of their uses and the ground conditions and the availability of materials. All
tunnels have various degrees of complexity depending on function and safety needs or the
code requirements at the time of construction, but most tunnels employ one or many
functional systems, such as lighting, ventilation, drainage, fire detectors and alarms, fire
suppression, communications and traffic control. With the limited access and confined
conditions within a tunnel; the operation, maintenance and inspection of a tunnel must be
thoroughly regimented to provide an adequate level of safety for the traveling public.
Construction of different types of tunnels includes some very basic operations or steps which
are to be followed in sequence in order to build or to construct a tunnel. This are called basic
tunneling operations. These tunneling operations may differ in comparison to older times and
this modern time. This report provides information on tunnels and various tunneling
operations involved in hard rock and also provide information related to various shapes of
tunnels, their types, tunnel boring machine etc. case study is also there related to tunneling in
hard rock.
6
TABLE OF CONTENTS
Chapter 1
Introduction
1.1 General…...........................................................................................................9
1.2 Objective of study…..........................................................................................9
Chapter 2
Literature review
2.1 Why Necessity of tunnel arises?…................................................................. 10
2.2 Factors to be considered in tunneling: ............................................................11
2.3 Tunnel Alignment...........................................................................................11
2.4 Selection of Tunnel alignment depends on.………,…...................................11
Chapter 3
Advantages and disadvantages of tunnels
3.1 Advantages of Tunnel.................................................................................... 12
3.2 Disadvantages ................................................................................................12
Chapter 4
Classification of Tunnels
4.1 On Purpose…................................................................................................13
4.2 On types of Ground …...................................................................................13
4.3 On the position and alignment...................................................................... 13
7
Chapter 5
Shapes of Tunnels
5.1 Circular Shape Tunnel… .......................................................................... 15
5.2 D Shape Tunnel….....................................................................................15
5.3 Rectangular Shape Tunnel…..................................................................... 15
5.4 Egg- Shape Tunnel….................................................................................15
5.4 Elliptical Shape Tunnel…..........................................................................16
5.5 Horse shoe Tunnel… .................................................................................16
5.6 Pilot Tunnel…............................................................................................16
Chapter 6
Tunneling in Hard Rock
6.1 Methods…..................................................................................................17
6.2 Tunnel Boring Machine………………………………………………….19
6.3 Hard Rock TBMs…………………………………………………….......19
6.4 Drilling Blasting and Hauling of Muck…………………………………..20
6.5 Theory of drilling and Blasting…………………………………………..20
6.6 Drilling Equipment’s……………………………………………………..21
6.7 Blasting………………………………………………………………….. 25
6.8 Types of Explosive……………………………………………………….25
Chapter 7
Case Study on Maroshi –Ruperal water tunnel Mumbai
7.1 Introduction……………………………………………………………...29
7.2 Construction Process…………………………………………………….31
7.3 Conclusion………………………………………………………………32
References
8
List of Figures
Figure
No
Description Page
4.1.1 Saddle or base Tunnel 13
4.1.2 Spiral Tunnel 14
5.1.1 Shapes of Tunnel 16
6.1.1 Heading and Benching Method 17
6.1.2 Drift Method 18
6.3.1 Hard rock tbms 19
6.4.1 Detonator 20
6.5.1 Placement of Explosive 21
6.8.1 Explosive 26
7.1.1 Longitudinal section and plan of tunnel from Maroshi to
Ruperal College.
30
7.2.1 Cutters position on cutter head of 3.6 m diameter 31
7.2.2 View of excavated tunnel face using TBM 31
9
Chapter 1
Introduction
1.1 General
Tunnel is an artificial underground passage, especially one built through a hill or under a
building, road, or river. Tunnels are not only structures constructed of concrete, steel,
masonry, and timber (to a very limited degree) or bored in rock, but also use numerous
functional systems to perform roles for the tunnels to function properly.
To construct any tunnel through river or through a hill, or an underground tunnel, there is
certain operation or steps which are to be followed or to be performed, which are called
various tunneling operations.
A Tunnel is a underground passageway completely enclosed except for openings for exit
commonly at each end.
Tunnel construction for transport routes is becoming increasingly important worldwide.
Transport is accelerated and optimum protection is provided for the environment and the
landscape. Many tunnels are considered technological masterpiece and governments have
honored tunnel engineers as heroes. Constructing a tunnel, however, is one of the most
complex challenges in the field of civil engineering.
1.2 Objective of study
Tunnels are underground passages used for transportation. They could be used for
carrying freights and passengers, water, sewage; etc. Tunnels are more economical than
open cuts beyond certain depths. Tunnels avoid disturbing or interfering with surface life
and traffic during construction. Tunnels prove to be cheaper than bridges or open cuts to
carry public utility services like water, sewer and gas. Feasibility of these constructions in
natural materials, such as rock and soil, causes the geological conditions to play a major
role in their stability. Aspects of major importance and that are decisive for the feasibility
of a tunnel project is geological conditions, construction time and costs. The objective of
this lesson is to provide the general aspects of importance in tunnels, their types and
methods of tunneling.
10
Chapter 2
Literature review
2.1 Why Necessity of tunnel arises?
Maintenance cost of tunnel is much less than that of bridge or a heavy cut.
The main reason behind provision of a tunnel is to eliminate a circuitous route for
reaching the other side of hill (the length of the railway line will be considerably
reduced).
In large cities, tunneling would provide the most rapid and unobstructed transportation
(leading to reduction in traffic congestion)
Tunnels provide flat gradients in hilly areas.
Economics of tunneling is a broad question and in general depends the relative cost of
open cut vs. tunneling. Generally when depth of cut is over 18 m, tunneling is advisable.
From view point of economy and traffic safety, the tunneling operation is desirable under
the following conditions…
a. To allow rapid and unobstructed transport facilities in big the congested cities.
b. To avoid acquisition of valuable land.
c. To avoid long circuitous routes around a mountain or spur.
d. To avoid sliding of open cut sides in softer soils.
e. To connect two terminal stations separated by mountain.
f. To divert water for generation of power.
g. To carry public utility services like oil, gas, water etc. across the stream or a
mountain.
h. To avoid the steep gradients in mountains and thereby maintain a high speed.
i. When the provision of the bridge over the river is costlier and in convenient.
j. It is preferred on routes of strategic importance because a tunnel is hidden in
ground.
k. To save the maintenance cost which is generally lesser for tunnel compared to a
bridge and an open cut.
11
2.2 Factors to be considered in tunneling:
The following factors should be taken into consideration when selecting the method:
- Tunnel dimensions,
- Tunnel geometry
- Length of tunnel,
- Total volume to be excavated
- Geological and rock mechanical conditions
- Ground water level and expected water inflow
- Vibration restrictions &
- Allowed ground settlements.
2.3 Tunnel Alignment
Tunnel alignment is an important aspect in engineering constructions.
The primary objectives of the tunnel alignments are to:
• Reduce transit trip times;
• Increase quality and reliability of service; and
• Minimize impacts of surface transit operations in sensitive locations.
2.4 Selection of Tunnel alignment depends on
• Topography of area & points of entrance and exit,
• Selection of site of tunnel to be made considering two points.
• Alignment Restraints
• Environmental Considerations.
12
Chapter 3
Advantages and disadvantages of tunnels
3.1 Advantages of Tunnel
• For carrying public utilities like water or gas, railway lines or roads across a stream or
mountain, tunnels may be cheaper than bridge or open cut.
• It is more efficient than bridges (as during wars it is much difficult to destroy a tunnel
compared to bridge).
• It is generally assumed that when the cut required will have a vertical depth exceeding 20
m; it is less expensive to build a tunnel.
• Tunnels avoid disturbing or interfering with surface life and traffic during construction
• Tunnels avoid traffic conjunction and provide rapid transportation in crowed cities.
• Tunnels connect two terminals stations by shortest route.
• Tunnels carry water to generate power.
• If tunnels are provided with easy gradients, the cost of hauling is decreased.
• Tunnels provide protection from bombing during aerial warfare.
• Tunnels avoid acquisition of costly land property.
• Tunnels provide protection against weathering actions like wind, rain, sun etc.
3.2 Disadvantages
• The initial cost of construction of a tunnel is high as compared to an open cut.
• Construction of tunnels requires long time in completing as compared to open cut.
• Specialized equipment and methods are required for execution of the work.
• It is necessary to have skilled labors and technical supervision of high order for
construction of the tunnels.
13
Chapter 4
Classification of tunnels
1) On purpose
a) Traffic Purpose Tunnel
• Railway tunnels :- to carry Railway traffic.
• Highway tunnels :- tunnels used to carry roadway traffic
• Pedestrian tunnels: - tunnels used to cross pedestrian traffic.
• Navigation tunnels: - tunnels used to navigate from one point to another.
• Subway tunnels: - Tunnels constructed under the ground for public traffic.
b) Water Conduit Purpose :-
• Penstock for hydroelectric Power plant.
• Water Supply Tunnel.
• Sewer Tunnels.
2) On type of ground
• Tunneling in hard rock.
• Tunneling in soft rock.
• Tunneling in quick sand.
3) On the position and alignment.
i) Saddle or base tunnel.
• The tunnel that is constructed in between two valley’s in order to minimize the length of
tunnel such type of tunnel are called as saddle or base tunnel.
• During the design of saddled or base tunnel the important point is taken into
consideration is that the natural slope of valley should not be greater than the ruling
gradient of the road.
14
ii) Spiral Tunnel
• In narrow valleys the additional length for minimum permissible radius is obtained by
forming a loop into the interior of mountain, such tunnel is called a spiral tunnel.
iii) Off –Spur Tunnels
• The tunnels that are made to short cut minor local obstacles such type of tunnels are
called as off – spur tunnel.
• The off- spur tunnels are very short in length
iv) Slope Tunnel
• To ensure the safe operation of steep mountains the slope tunnels are used.
• They are constructed from the economic point of view.
Fig – Spiral tunnel
15
Chapter 5
Shapes of tunnels
1) Circular shape tunnel
• The circular shape tunnel is usually used for water and sewage conduit.
• These types of tunnels are best for resisting external or internal forces.
• It provides large cross- sectional area for least perimeter.
• It is usually used for non –cohesive soils.
• It is not advised for traffic tunnel because large filling is required for flat base.
• This shape is more difficult for placement of concrete lining.
2) D- Shape Tunnel
• It is the types of tunnel which has a roof as a segment of the circle whose sides are
vertical and floor is flat.
• D- Shape Tunnel is commonly used for sub- ways or the navigational purpose.
• The D-shape tunnels are usually used in hard rock.
• In D- shape tunnel the segmental arch roof transfers the load to the vertical straight
column support and then to the base.
3) Rectangular Shape Tunnel
• This type of tunnel which has a horizontal slab with the vertical supports.
• The BM and stresses exerted at the roof must be resisted by using steel girder to form
the roof lining.
• These tunnels are not used now a day’s .They are only used in the subways.
• These tunnels are usually constructed in hard rocks.
• Very difficult in lining.
4) Egg –Shaped Tunnel
• It is used for the sewer.
• Egg –shape of the tunnel provides a self-cleansing velocity to the water.
16
5) Elliptical Shape Tunnel
• These tunnels are the type of the tunnels which are usually used to carry the fluid with
large viscosity.
• The elliptical Section with major axis vertical gives suitable section.
6) Horse –Shoe Tunnel
• This Shape tunnel consists of segmental roof with the inverts. The segmental roof and
the inverts resist the external pressure coming on them.
• They are suitable for soft rock.
• This shape is very commonly used for railway and highways in all countries.
7) Pilot Tunnel
• It is the type of tunnel whose diameter is less than the actual tunnel to be constructed
and is usually to connect the two tunnels which are constructed in a single mountain.
• Also used in emergency purpose.
• Also used to safeguard the equipment’s of the construction at the end of the day.
17
Chapter 6
Tunneling in Hard Rock
6.1 Methods
1) Heading and Benching Method (top and bottom or up and down method)
• This method involves the driving of the top portion in advance of the bottom
portion.
• It is used when the tunnel section is very large and quality of rock is satisfactory.
• In this method the top heading excavation is usually 3 to 4 m ahead of the bench
excavation.
2) Drift Method
• Rock tunneling is sometimes carried out first in smaller section of the proposed
tunnel and then widened .This method is called as drift method.
• In drift method, the total c/s of tunnel is divided into n no. of square section .Each
section is about 2.5 to 3 m2 in area (face area).
• By converting the tunnel into small c/s part any part is selected for the excavation
which may be central part, top part, side part or bottom part.
18
• And through this part the excavation is done from start to the end .Such excavation is
called as drift.
• The drift provides the ventilation or light during the excavation of the remaining part
of the tunnel.
3) Full face method :-
• In full face method, workers excavate the entire diameter of tunnel at the same time.
• In this method the mucking track could be placed progressively along with the
excavation.
• In this method tunneling is continuous.
• Full face method was limited to small tunnels only, but now with the improvements
and development in tunneling equipment more and more large tunnel can be driven
by this method.
• One of the machine which is usually used for cutting the full –face of the tunnel is
called as Tunnel Boring Machine.
19
6.2 Tunnel Boring Machine
• The use of tunnel boring machine is on increasing way, because instead of drilling
and blasting this method can be used conveniently.
• In case of tunnel boring machine the rock damage is less, cut material is handled
systematically, safety of workers is great.
• The cost of tunnel lining is reduced and the operation is continuous with the help of
TBM.
• With the help of TBM ,the face area that can be cut is about 20 m2
• The diameter of TBM is up to 6m.
6.3 HARD ROCK TBMS:
• The Hard rock, either shielded or open-type TBMs are used to excavate rocks with
the help of disc cutters which are mounted on the cutter head.
• The rocks (muck) get chipped away as the disc cutter compresses stress fractures on
it.
• Now the excavated rocks are transferred to the belt conveyor through the cutter head
openings.
• These rocks are then run through multiple conveyors to get them removed from the
tunnel.
20
6.4 Drilling, Blasting and hauling of muck
Before the invention of the TBM drilling and blasting was the only method of
excavating the material through hard rock.
For drilling and blasting we follow following steps.
• Small diameter drill is made with the help of different drilling equipment.
• The drill hole is clean for placing the explosive and packing of explosive with clay.
• Plantation of certain explosive material is done in the drill hole.
• Detonating the explosive.
• Fumes are released from the explosive.
• Final excavation or mucking of material is done.
6.5 Theory of drilling and blasting
• A drill hole normal to the face when exploded with proper charge will break out a gap
inclined at approximately 45 degree to the face.
• If two similar holes are kept side by side and fixed together they will blast a large
quantity of rock which will be about 2.25 times greater than the single faces.
• If three explosive with three similar holes are kept side by side and fixed together
than it will break 3.5 times greater than quantity of rock than that for single face.
• An inclined cut hole is more efficient than the hole that is drilled normal to the face.
Therefore, an inclined angle of 45 degree is made to the face of the rock and hole is
drilled .With the help of this inclined hole, the angle of crack also increases it the
about 54 degree 44 min to the axis of the hole.
21
6.6 Drilling Equipment’s
• Drilling is the process of making holes using drilling equipment. The drilling
equipment varies w.r.t size of project, kind of rock, depth and size of hole, nature
of terrain, etc.
• The drilling equipment can be divided into two parts.
1) Percussion Drills
• A drill holes the drill bit and rotates it in partial manner/angle (90 or 120 degree) to
provide axial force for making a hole.
• Percussion drill breaks the rock by impact from the repeated blows.
• The popular varieties of percussion type of drills are
22
a) Jack hammer
b) Tripod Drills
c) Stop Hammer
d) Drifter
e) Churn drills
f) Piston drills
g) Wagon drills
a) Jack Hammer
• It is the air operated percussion types of drill which is portable and hand operated.
• It is most used for drilling vertical holes.
• The weight of the jack hammer varies from 10- 40 kg.
• It can drill the hole up to 5 m depth.
• The impact blow action of the jack hammer is about 2200 blows/min.
b) Tripod Drills
• This are similar to the jack hammer, expect that it is mounted on tripod to provide
sufficient stability.
• Tripods are usually very low and require drill changes every 1m or so.
• They are not much in use except for very hard rock.
23
c) Stop Hammers
• This is modification of jack hammer which are mounted on certain vehicle to hold
the drill against the work and are usually used for up holes.
d) Drifters
• The drifter is an air operated precaution type of drill similar to the jack hammer but
is so large that it needs mechanically mounting.
• They are used for drilling down ,horizontal or up holes
• They can drill up to of 12 cm diameter holes.
e) Churn Drills ( Well drills )
• They are also called are well drills.
• Churn drill can drill hole up to 15 cm diameter.
• Churn Drill can drill at any angle and has the penetrating depth up to 100 m.
• They are operated by steam or gasoline.
f) Piston Drill
• The piston drill is securely fastened and traveled the full length of the piston
stroke.
• It can drill a hole of 6 cm in diameter and can drill a hole up to 10 to 20 m long.
• The impact blowing action is about 200 blows per minute.
24
g) Wagon drill
• The wagon drill is the drifter mounted on a vehicle to provide portability in drilling
the holes.
• They are used extensively to drill the holes up to 12 cm in diameter and up to 10 m
in depth.
• Their performance is better than jack hammer.
• They can be used to drill the hole at any angle from down to up.
2) Abrasion drill
• The abrasion drill is a type of drill which grinds the rock up to small particles
through abrasion effect of bit that rotates in the hole.
• The common examples of abrasion drill are
a) Blast hole drills
b) Short drills
c) Diamond drills
a) Blast hole drill :-
• This is the type of rotary drill which works on the system of compressed air and
disintegrates the rock as it rotates over it.
• The type of abrasion drill is used for drilling the hole up to 100 m in depth.
25
b) Short drills
• This is the rotary abrasion type of drill which has the rough surface at the bottom
and makes the hole in certain rock by crushing it.
• Short drill can drill a hole up to 75 in diameter and up to depth of 200 m.
c) Diamond drill
• Diamond drill is a rotary abrasion types of drills whose bit consists of metal matrix
in which they are embedded a large number of diamonds.
• Diamond drills are uneconomical, hence are used in less quantity.
6.7 Blasting
• The blasting is the operation performs to loose the rock so that it can be excavated
or removed from its existing position.
• Blasting is accomplished by discharging an explosive that has been placed in a
hole specifically drill for this purpose.
• During the blasting operation the drilled holes are made and cleaned, the charge of
explosive is placed at the bottom of blast hole or drill holes; remaining portion of
the hole is filled with the clay and tampered.
• The size of the explosive ranges from 2.5 to 20 cm in diameter and its length is
about 20-60 cm and tampered.
6.8 Types of Explosive
a) Straight Dynamite
• It is the first type of explosive with which all high explosives are compared for
strength.
• Its primary constituent is nitro- glycerin varying from 15-60%
26
• They are highly water resistance and a desirable property for sub- marine blasting.
• Because of bad fumes they have been replaced by other types.
b) Ammonia Dynamite
• It contains equal parts of nitro- glycerin and nitrate of ammonia as the explosive
material.
• They come in the strength of 15-40%, but are not so sensitive as straight
dynamites.
• They are suitable for soft rock and fairly water resistance and their fumes are not
so bad.
c) Gelatin Dynamites
• They are of two types
 Straight Gelatin dynamites
 Extra or special Gelatin dynamites
• Both this type of gelatin dynamites consists of jelly of nitroglycerin and nitro-
cotton.
27
• In extra or special gelatin, part of nitro-glycerin is replaced by nitrate of ammonia.
• Both these types are highly water resistance and their fumes are good.
• Their jelly like plastic consistency permits solid loading in a hole.
• They are quick and have high shattering effect.
• Because of these characteristics they are chosen for most rock tunneling work.
d) Semi –Gelatin Dynamite
• In a recent development, consisting principally the complex compound of nitrate
of ammonia with same gelatin, nitro- glycerin, nitro – cotton, semi –gelatin is
formed.
• Semi- gelatins are bulkier than the straight or extra gelatin.
• They are water resistant and fume quality is good.
• Because of their low density, they are cheaper than extra or gelatin dynamite used
in soft rock and lime –stone work.
e) Blasting Gelatin
• Blasting Gelatin are also a recent, fast, strong explosive.
• They have the consistency same like soft rubber and it is fully water proof.
• It is adaptable for wet work.
• Its fumes are extremely bad and its strength is about 100%
28
f) Other High Explosives
• Several Special high explosives are made, developed for special condition
especially for disintegration of hard rock.
• Some of the other explosive are
• TNT – Tri –Nitro- Toluene
• RDX –Rapid detorating explosive
• Pent – Penta Eny thital
29
Chapter 7
Case Study on Maroshi - Ruparel water tunnel Mumbai
7.1 Introduction
• Mumbai’s water network is crumbling under the strain. Its mains system is at least 80
years old, the majority of it laid in the colonial era. Though the city has seen some
water distribution projects post-independence, they were still more than 60 years old.
• Much of the system works through surface pipelines, which are prone to leakages and
theft. This highly pressurized network is further hindered by passage under slum land,
which adds even more complication to their maintenance. Likewise, Mumbai’s main
water line runs beneath the runway of Mumbai international airport, making it doubly
difficult to maintain, while a major burst could affect the movement of air traffic into
and out of the city.
• Hindustan Construction Company (HCC) was awarded the Contract of Maroshi-
Ruparel College Tunnel Project by the Municipal Corporation of Mumbai in
September 2007 with a Contract value of Rs 415.10 crore. This is a Water Supply
Project executed under Jawaharlal Nehru National Urban Renewal Mission
(JNNURM) and is funded by the Government of India, Government of Maharashtra &
Municipal Corporation of Greater Mumbai.
• The tunnel stretch is divided into three sections namely, Maroshi-Vakola (5.83 km
long), Vakola-Mahim (4.55 km long) and Mahim-Ruparel College (1.86 km long).
Maroshi-Vakola tunnel stretch is the longest section of the Maroshi to Ruparel College
water tunnel.
• The Maroshi-Ruparel tunnel work consists of construction of tunnel having 3.60 m
diameter and 12.24 km long using Tunnel Boring Machine from Maroshi connecting
to Ruparel College. The tunnel is connected with Shafts at Maroshi, Vakola and
Mahim. The shafts are 12 m in diameter and about 80.00 m deep equivalent to a to 26-
30
storey building deep into the ground. It will be through these shafts that localities will
get water supply.
• The BMC began the underground tunnel project to stop leakage and water thefts from
the water pipelines .The other focus of the project is to replace the water pipelines that
are centuries old and have corroded at several spots ,causing sewage water to mix with
drinking water.
• The Vakola-Mahim section passes below the Mahim creek while the Maroshi-Vakola
section crosses both of Mumbai airport’s runways at around 70 meters below ground
level. The tunneling work was carried out without disturbing any operations on the
ground level.
31
• The tunnel boring was extremely challenging due to heavy seepages and varying rock
strata. During monsoon, the tunnel seepage had increased to about 25,000 m3 per day.
Extensive grouting was carried out to control the same.
7.2 PROCESS
First, a shaft with a diameter of 10 meters was constructed at a depth of between 70
and 80 meters. This served so that contractors could deliver all the necessary plant,
machinery and equipment, including tunnel boring machines (TBMs), locomotives,
water pumps and concrete mixers, through it to reach the 70-metre depth required for
the boring and drilling.
This was done by the gripping of jacks and alignment of TBM cutter heads for boring
at a width of 3.6 meters through the earth.
The concrete lining is cast on site rather than being pre-cast elsewhere. Once a stretch
of boring is complete, an epoxy-coated reinforcement layer is fixed into place; the
shutters and bulkheads are then set to pour ready-mix concrete using the agitator cars.
32
7.3 Conclusion
• After completion, the tunnel improved the water situation in south and central Mumbai
by supplying 1,100 million liters daily. The tunnel replaced the old upper Vaitarna and
Vaitarna mains in this section. It improved the water supply to Vakola, Mahim, Dadar
and Malabar Hill significantly.
• This project is part of the rehabilitation and improvement of the drinking water
conveyance / distribution system from Bhandup Treatment Works to Western Suburbs
and Southwest part of the Mumbai city.
• BMC town planners expect the new tunnel to have a number of advantages over the
existing surface pipeline, because it travels at such great depth, meaning that the structure
cannot be tampered with, as is the case with surface pipelines. In addition, there are fewer
chances of leakages and water theft, and most importantly, the tunnel is not expected to
require major maintenance over the next 100 years. And since the entire distribution
system is made of concrete, it will not corrode, invariably happens with surface pipelines.
• The project is also designed to withstand earthquakes.
33
References
a) Harbor Dock and Tunnel Engineering Textbook by R srinivasa.
b) Textbook of Tunnel Engineering by S.C.Saxena
c) Textbook of Tunnel Engineering by Rangwala
d) www.google.com
e) Performance characteristics of tunnel boring machine in basalt and pyroclastic
rocks of Deccan traps –Research paper by Prasnna Jain, A.K. Naithani, T.N.
Singh.

More Related Content

What's hot

Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavementRandhir Kumar
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFShankar Ramasamy
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineeringSaurabh Samant
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
Grouting
GroutingGrouting
Groutingastraeaeos
 
SOIL EXPLORATION
SOIL EXPLORATIONSOIL EXPLORATION
SOIL EXPLORATIONserinsara
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Muhammad Irfan
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSramgsvhce
 
Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...Subash thangaraj
 
1 st 20 year road plan
1 st 20 year road plan1 st 20 year road plan
1 st 20 year road plan12cl0viren
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test pptsayan sarkar
 
Dredging equipment
Dredging equipmentDredging equipment
Dredging equipmentSwarna Rajan
 

What's hot (20)

Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Pile load test
Pile load testPile load test
Pile load test
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Grouting
GroutingGrouting
Grouting
 
SOIL EXPLORATION
SOIL EXPLORATIONSOIL EXPLORATION
SOIL EXPLORATION
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Sub grade preperation
Sub grade preperationSub grade preperation
Sub grade preperation
 
Soil penetration tests
Soil penetration testsSoil penetration tests
Soil penetration tests
 
Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...
 
1 st 20 year road plan
1 st 20 year road plan1 st 20 year road plan
1 st 20 year road plan
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
 
Dredging equipment
Dredging equipmentDredging equipment
Dredging equipment
 

Similar to Tunnel Engineering Report (VJTI MUMBAI)

A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
 
Trenchless Technology Technical Seminar Report
Trenchless Technology Technical Seminar ReportTrenchless Technology Technical Seminar Report
Trenchless Technology Technical Seminar ReportAkshathaBhandary
 
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGEMECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGEEditorIJAERD
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET Journal
 
Numerical simulation and optimization of pile design
Numerical simulation and optimization of pile designNumerical simulation and optimization of pile design
Numerical simulation and optimization of pile designIRJET Journal
 
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET Journal
 
IRJET- Review on Design / Study of Pedestrian Bridge in Shirdi Area
IRJET-  	  Review on Design / Study of Pedestrian Bridge in Shirdi AreaIRJET-  	  Review on Design / Study of Pedestrian Bridge in Shirdi Area
IRJET- Review on Design / Study of Pedestrian Bridge in Shirdi AreaIRJET Journal
 
Building Service Assignment
Building Service Assignment Building Service Assignment
Building Service Assignment XinYee Khoo
 
Sustainable Stormwater Management
Sustainable Stormwater Management Sustainable Stormwater Management
Sustainable Stormwater Management Shane Ah
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESA Makwana
 
Intelligent Bridge Seismic Monitoring System Based on Neuro Genetic Hybrid
Intelligent Bridge Seismic Monitoring System Based on Neuro Genetic HybridIntelligent Bridge Seismic Monitoring System Based on Neuro Genetic Hybrid
Intelligent Bridge Seismic Monitoring System Based on Neuro Genetic HybridTELKOMNIKA JOURNAL
 
SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...
SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...
SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...IRJET Journal
 
JMRC TRAINING FINAL REPORT
JMRC TRAINING FINAL   REPORT JMRC TRAINING FINAL   REPORT
JMRC TRAINING FINAL REPORT Rohit kumar nagar
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...Mary Montoya
 
Dynamic Analysis of Bridge with different spans of bridge piers applying push...
Dynamic Analysis of Bridge with different spans of bridge piers applying push...Dynamic Analysis of Bridge with different spans of bridge piers applying push...
Dynamic Analysis of Bridge with different spans of bridge piers applying push...IRJET Journal
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHA Makwana
 
An experimental study on durability of high strength self compacting concrete...
An experimental study on durability of high strength self compacting concrete...An experimental study on durability of high strength self compacting concrete...
An experimental study on durability of high strength self compacting concrete...eSAT Journals
 

Similar to Tunnel Engineering Report (VJTI MUMBAI) (20)

A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
Trenchless Technology Technical Seminar Report
Trenchless Technology Technical Seminar ReportTrenchless Technology Technical Seminar Report
Trenchless Technology Technical Seminar Report
 
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGEMECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
MECHANIZED CONSTRUCTION TECHNIQUES FOR URBAN ROAD BRIDGE
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
 
Numerical simulation and optimization of pile design
Numerical simulation and optimization of pile designNumerical simulation and optimization of pile design
Numerical simulation and optimization of pile design
 
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
 
Final ppt (1).pptx
Final ppt (1).pptxFinal ppt (1).pptx
Final ppt (1).pptx
 
Ijciet 08 02_040
Ijciet 08 02_040Ijciet 08 02_040
Ijciet 08 02_040
 
IRJET- Review on Design / Study of Pedestrian Bridge in Shirdi Area
IRJET-  	  Review on Design / Study of Pedestrian Bridge in Shirdi AreaIRJET-  	  Review on Design / Study of Pedestrian Bridge in Shirdi Area
IRJET- Review on Design / Study of Pedestrian Bridge in Shirdi Area
 
BS ASSIGNMENT
BS ASSIGNMENTBS ASSIGNMENT
BS ASSIGNMENT
 
Building Service Assignment
Building Service Assignment Building Service Assignment
Building Service Assignment
 
Sustainable Stormwater Management
Sustainable Stormwater Management Sustainable Stormwater Management
Sustainable Stormwater Management
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
Intelligent Bridge Seismic Monitoring System Based on Neuro Genetic Hybrid
Intelligent Bridge Seismic Monitoring System Based on Neuro Genetic HybridIntelligent Bridge Seismic Monitoring System Based on Neuro Genetic Hybrid
Intelligent Bridge Seismic Monitoring System Based on Neuro Genetic Hybrid
 
SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...
SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...
SEISMIC ANALYSIS OF LONG SPAN BRIDGE AND EXTERNAL SUBSTRUCTURE RETROFITING TE...
 
JMRC TRAINING FINAL REPORT
JMRC TRAINING FINAL   REPORT JMRC TRAINING FINAL   REPORT
JMRC TRAINING FINAL REPORT
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
Dynamic Analysis of Bridge with different spans of bridge piers applying push...
Dynamic Analysis of Bridge with different spans of bridge piers applying push...Dynamic Analysis of Bridge with different spans of bridge piers applying push...
Dynamic Analysis of Bridge with different spans of bridge piers applying push...
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
An experimental study on durability of high strength self compacting concrete...
An experimental study on durability of high strength self compacting concrete...An experimental study on durability of high strength self compacting concrete...
An experimental study on durability of high strength self compacting concrete...
 

More from Mayur Rahangdale

Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Mayur Rahangdale
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)Mayur Rahangdale
 
Linear Equation in one variable.pptx
Linear Equation in one variable.pptxLinear Equation in one variable.pptx
Linear Equation in one variable.pptxMayur Rahangdale
 
Water Absorption of Bricks
Water Absorption of BricksWater Absorption of Bricks
Water Absorption of BricksMayur Rahangdale
 
Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)Mayur Rahangdale
 
Water quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOTWater quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOTMayur Rahangdale
 
Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...Mayur Rahangdale
 
GPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster ManagementGPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster ManagementMayur Rahangdale
 
Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)Mayur Rahangdale
 
Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)Mayur Rahangdale
 
Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)Mayur Rahangdale
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Mayur Rahangdale
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Mayur Rahangdale
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...Mayur Rahangdale
 
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...Mayur Rahangdale
 
Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)Mayur Rahangdale
 
Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...Mayur Rahangdale
 
G cans project report
G cans project reportG cans project report
G cans project reportMayur Rahangdale
 
Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Mayur Rahangdale
 
Steel Structure Design
Steel Structure DesignSteel Structure Design
Steel Structure DesignMayur Rahangdale
 

More from Mayur Rahangdale (20)

Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Linear Equation in one variable.pptx
Linear Equation in one variable.pptxLinear Equation in one variable.pptx
Linear Equation in one variable.pptx
 
Water Absorption of Bricks
Water Absorption of BricksWater Absorption of Bricks
Water Absorption of Bricks
 
Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)
 
Water quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOTWater quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOT
 
Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...
 
GPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster ManagementGPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster Management
 
Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)
 
Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)
 
Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
 
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
 
Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)
 
Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...
 
G cans project report
G cans project reportG cans project report
G cans project report
 
Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.
 
Steel Structure Design
Steel Structure DesignSteel Structure Design
Steel Structure Design
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 

Tunnel Engineering Report (VJTI MUMBAI)

  • 1. Project Report on CASE STUDY ON TUNNELING IN HARD ROCKS By Ma.Mayur .U. Rahangdale (202030018) M. Tech (Construction Management) 2020 - 2021 Guided by Prof. (Dr.) S.Y. Mhaske Department of Civil and Environmental Engineering Veermata Jijabai Technological Institute (Autonomous Institute Affiliated to University of Mumbai) Mumbai 400 019 2020 – 2021
  • 2. 2 STATEMENT BY THE CANDIDATE We wish to state that the work embodied in this report titled “CASE STUDY ON TUNNELING IN HARD ROCKS” forms my contribution to the work carried out under the guidance of Prof. (DR.) S.Y. Mhaske at the Veermata Jijabai Technological Institute. This work has not submitted for any other degree or diploma of any university/ institute. Wherever references have been made to previous works of others, it has been clearly indicated. Signature of the Candidate MA.MAYUR .U. RAHANGDALE (202030018)
  • 3. 3 CERTIFICATE This is to certify that MA.MAYUR .U. RAHANGDALE (202030018) the studentof M-Tech.(Construction Management) Veermata Jijabai Technological Institute, Mumbai have Successfully completed the project entitled “CASE STUDY ON TUNNELING IN HARD ROCKS” During the academic year 2020-2021, Under the guidance of Prof.(Dr.) S.Y. Mhaske. Prof. (Dr.) S.Y. Mhaske DR. S.Y. MHASKE (PROJECT GUIDE) PROF & HEAD CIVIL & ENVIRONMENTAL ENGG. DEPT
  • 4. 4 ACKNOWLEDGEMENT It is obvious that the development of project needs the support of many people. Getting idea of analyzing a project, finalizing it as best one for me and above all developing it successfully always is a job more than dozen of people. It is great pleasure for me to acknowledge the assistance and contribution of my own effort. I had always been grateful for the support that I got from all my surroundings with respect knowledge and support. I am very grateful to my Parents who have always being supportive of the strange new twist and turns our life has taken. They are the one who have been the pioneer of success and achievement in life and of course they have supported us rather directly or indirectly in developing our project. I sincerely acknowledge to my project guide Prof. (Dr.) S.Y. Mhaske whose continuous encouragement and support enabled the project to materialized and contributed to its success. Finally, I thankful to all my Friends for their constant inspiration, support and encouragement. MA.MAYUR .U. RAHANGDALE (202030018)
  • 5. 5 ABSTRACT Tunnels are very important structures which are being used in various constructions; like in road, railway for defense purpose and laying of pipelines etc. Tunnels have different shapes on the basis of their uses and the ground conditions and the availability of materials. All tunnels have various degrees of complexity depending on function and safety needs or the code requirements at the time of construction, but most tunnels employ one or many functional systems, such as lighting, ventilation, drainage, fire detectors and alarms, fire suppression, communications and traffic control. With the limited access and confined conditions within a tunnel; the operation, maintenance and inspection of a tunnel must be thoroughly regimented to provide an adequate level of safety for the traveling public. Construction of different types of tunnels includes some very basic operations or steps which are to be followed in sequence in order to build or to construct a tunnel. This are called basic tunneling operations. These tunneling operations may differ in comparison to older times and this modern time. This report provides information on tunnels and various tunneling operations involved in hard rock and also provide information related to various shapes of tunnels, their types, tunnel boring machine etc. case study is also there related to tunneling in hard rock.
  • 6. 6 TABLE OF CONTENTS Chapter 1 Introduction 1.1 General…...........................................................................................................9 1.2 Objective of study…..........................................................................................9 Chapter 2 Literature review 2.1 Why Necessity of tunnel arises?…................................................................. 10 2.2 Factors to be considered in tunneling: ............................................................11 2.3 Tunnel Alignment...........................................................................................11 2.4 Selection of Tunnel alignment depends on.………,…...................................11 Chapter 3 Advantages and disadvantages of tunnels 3.1 Advantages of Tunnel.................................................................................... 12 3.2 Disadvantages ................................................................................................12 Chapter 4 Classification of Tunnels 4.1 On Purpose…................................................................................................13 4.2 On types of Ground …...................................................................................13 4.3 On the position and alignment...................................................................... 13
  • 7. 7 Chapter 5 Shapes of Tunnels 5.1 Circular Shape Tunnel… .......................................................................... 15 5.2 D Shape Tunnel….....................................................................................15 5.3 Rectangular Shape Tunnel…..................................................................... 15 5.4 Egg- Shape Tunnel….................................................................................15 5.4 Elliptical Shape Tunnel…..........................................................................16 5.5 Horse shoe Tunnel… .................................................................................16 5.6 Pilot Tunnel…............................................................................................16 Chapter 6 Tunneling in Hard Rock 6.1 Methods…..................................................................................................17 6.2 Tunnel Boring Machine………………………………………………….19 6.3 Hard Rock TBMs…………………………………………………….......19 6.4 Drilling Blasting and Hauling of Muck…………………………………..20 6.5 Theory of drilling and Blasting…………………………………………..20 6.6 Drilling Equipment’s……………………………………………………..21 6.7 Blasting………………………………………………………………….. 25 6.8 Types of Explosive……………………………………………………….25 Chapter 7 Case Study on Maroshi –Ruperal water tunnel Mumbai 7.1 Introduction……………………………………………………………...29 7.2 Construction Process…………………………………………………….31 7.3 Conclusion………………………………………………………………32 References
  • 8. 8 List of Figures Figure No Description Page 4.1.1 Saddle or base Tunnel 13 4.1.2 Spiral Tunnel 14 5.1.1 Shapes of Tunnel 16 6.1.1 Heading and Benching Method 17 6.1.2 Drift Method 18 6.3.1 Hard rock tbms 19 6.4.1 Detonator 20 6.5.1 Placement of Explosive 21 6.8.1 Explosive 26 7.1.1 Longitudinal section and plan of tunnel from Maroshi to Ruperal College. 30 7.2.1 Cutters position on cutter head of 3.6 m diameter 31 7.2.2 View of excavated tunnel face using TBM 31
  • 9. 9 Chapter 1 Introduction 1.1 General Tunnel is an artificial underground passage, especially one built through a hill or under a building, road, or river. Tunnels are not only structures constructed of concrete, steel, masonry, and timber (to a very limited degree) or bored in rock, but also use numerous functional systems to perform roles for the tunnels to function properly. To construct any tunnel through river or through a hill, or an underground tunnel, there is certain operation or steps which are to be followed or to be performed, which are called various tunneling operations. A Tunnel is a underground passageway completely enclosed except for openings for exit commonly at each end. Tunnel construction for transport routes is becoming increasingly important worldwide. Transport is accelerated and optimum protection is provided for the environment and the landscape. Many tunnels are considered technological masterpiece and governments have honored tunnel engineers as heroes. Constructing a tunnel, however, is one of the most complex challenges in the field of civil engineering. 1.2 Objective of study Tunnels are underground passages used for transportation. They could be used for carrying freights and passengers, water, sewage; etc. Tunnels are more economical than open cuts beyond certain depths. Tunnels avoid disturbing or interfering with surface life and traffic during construction. Tunnels prove to be cheaper than bridges or open cuts to carry public utility services like water, sewer and gas. Feasibility of these constructions in natural materials, such as rock and soil, causes the geological conditions to play a major role in their stability. Aspects of major importance and that are decisive for the feasibility of a tunnel project is geological conditions, construction time and costs. The objective of this lesson is to provide the general aspects of importance in tunnels, their types and methods of tunneling.
  • 10. 10 Chapter 2 Literature review 2.1 Why Necessity of tunnel arises? Maintenance cost of tunnel is much less than that of bridge or a heavy cut. The main reason behind provision of a tunnel is to eliminate a circuitous route for reaching the other side of hill (the length of the railway line will be considerably reduced). In large cities, tunneling would provide the most rapid and unobstructed transportation (leading to reduction in traffic congestion) Tunnels provide flat gradients in hilly areas. Economics of tunneling is a broad question and in general depends the relative cost of open cut vs. tunneling. Generally when depth of cut is over 18 m, tunneling is advisable. From view point of economy and traffic safety, the tunneling operation is desirable under the following conditions… a. To allow rapid and unobstructed transport facilities in big the congested cities. b. To avoid acquisition of valuable land. c. To avoid long circuitous routes around a mountain or spur. d. To avoid sliding of open cut sides in softer soils. e. To connect two terminal stations separated by mountain. f. To divert water for generation of power. g. To carry public utility services like oil, gas, water etc. across the stream or a mountain. h. To avoid the steep gradients in mountains and thereby maintain a high speed. i. When the provision of the bridge over the river is costlier and in convenient. j. It is preferred on routes of strategic importance because a tunnel is hidden in ground. k. To save the maintenance cost which is generally lesser for tunnel compared to a bridge and an open cut.
  • 11. 11 2.2 Factors to be considered in tunneling: The following factors should be taken into consideration when selecting the method: - Tunnel dimensions, - Tunnel geometry - Length of tunnel, - Total volume to be excavated - Geological and rock mechanical conditions - Ground water level and expected water inflow - Vibration restrictions & - Allowed ground settlements. 2.3 Tunnel Alignment Tunnel alignment is an important aspect in engineering constructions. The primary objectives of the tunnel alignments are to: • Reduce transit trip times; • Increase quality and reliability of service; and • Minimize impacts of surface transit operations in sensitive locations. 2.4 Selection of Tunnel alignment depends on • Topography of area & points of entrance and exit, • Selection of site of tunnel to be made considering two points. • Alignment Restraints • Environmental Considerations.
  • 12. 12 Chapter 3 Advantages and disadvantages of tunnels 3.1 Advantages of Tunnel • For carrying public utilities like water or gas, railway lines or roads across a stream or mountain, tunnels may be cheaper than bridge or open cut. • It is more efficient than bridges (as during wars it is much difficult to destroy a tunnel compared to bridge). • It is generally assumed that when the cut required will have a vertical depth exceeding 20 m; it is less expensive to build a tunnel. • Tunnels avoid disturbing or interfering with surface life and traffic during construction • Tunnels avoid traffic conjunction and provide rapid transportation in crowed cities. • Tunnels connect two terminals stations by shortest route. • Tunnels carry water to generate power. • If tunnels are provided with easy gradients, the cost of hauling is decreased. • Tunnels provide protection from bombing during aerial warfare. • Tunnels avoid acquisition of costly land property. • Tunnels provide protection against weathering actions like wind, rain, sun etc. 3.2 Disadvantages • The initial cost of construction of a tunnel is high as compared to an open cut. • Construction of tunnels requires long time in completing as compared to open cut. • Specialized equipment and methods are required for execution of the work. • It is necessary to have skilled labors and technical supervision of high order for construction of the tunnels.
  • 13. 13 Chapter 4 Classification of tunnels 1) On purpose a) Traffic Purpose Tunnel • Railway tunnels :- to carry Railway traffic. • Highway tunnels :- tunnels used to carry roadway traffic • Pedestrian tunnels: - tunnels used to cross pedestrian traffic. • Navigation tunnels: - tunnels used to navigate from one point to another. • Subway tunnels: - Tunnels constructed under the ground for public traffic. b) Water Conduit Purpose :- • Penstock for hydroelectric Power plant. • Water Supply Tunnel. • Sewer Tunnels. 2) On type of ground • Tunneling in hard rock. • Tunneling in soft rock. • Tunneling in quick sand. 3) On the position and alignment. i) Saddle or base tunnel. • The tunnel that is constructed in between two valley’s in order to minimize the length of tunnel such type of tunnel are called as saddle or base tunnel. • During the design of saddled or base tunnel the important point is taken into consideration is that the natural slope of valley should not be greater than the ruling gradient of the road.
  • 14. 14 ii) Spiral Tunnel • In narrow valleys the additional length for minimum permissible radius is obtained by forming a loop into the interior of mountain, such tunnel is called a spiral tunnel. iii) Off –Spur Tunnels • The tunnels that are made to short cut minor local obstacles such type of tunnels are called as off – spur tunnel. • The off- spur tunnels are very short in length iv) Slope Tunnel • To ensure the safe operation of steep mountains the slope tunnels are used. • They are constructed from the economic point of view. Fig – Spiral tunnel
  • 15. 15 Chapter 5 Shapes of tunnels 1) Circular shape tunnel • The circular shape tunnel is usually used for water and sewage conduit. • These types of tunnels are best for resisting external or internal forces. • It provides large cross- sectional area for least perimeter. • It is usually used for non –cohesive soils. • It is not advised for traffic tunnel because large filling is required for flat base. • This shape is more difficult for placement of concrete lining. 2) D- Shape Tunnel • It is the types of tunnel which has a roof as a segment of the circle whose sides are vertical and floor is flat. • D- Shape Tunnel is commonly used for sub- ways or the navigational purpose. • The D-shape tunnels are usually used in hard rock. • In D- shape tunnel the segmental arch roof transfers the load to the vertical straight column support and then to the base. 3) Rectangular Shape Tunnel • This type of tunnel which has a horizontal slab with the vertical supports. • The BM and stresses exerted at the roof must be resisted by using steel girder to form the roof lining. • These tunnels are not used now a day’s .They are only used in the subways. • These tunnels are usually constructed in hard rocks. • Very difficult in lining. 4) Egg –Shaped Tunnel • It is used for the sewer. • Egg –shape of the tunnel provides a self-cleansing velocity to the water.
  • 16. 16 5) Elliptical Shape Tunnel • These tunnels are the type of the tunnels which are usually used to carry the fluid with large viscosity. • The elliptical Section with major axis vertical gives suitable section. 6) Horse –Shoe Tunnel • This Shape tunnel consists of segmental roof with the inverts. The segmental roof and the inverts resist the external pressure coming on them. • They are suitable for soft rock. • This shape is very commonly used for railway and highways in all countries. 7) Pilot Tunnel • It is the type of tunnel whose diameter is less than the actual tunnel to be constructed and is usually to connect the two tunnels which are constructed in a single mountain. • Also used in emergency purpose. • Also used to safeguard the equipment’s of the construction at the end of the day.
  • 17. 17 Chapter 6 Tunneling in Hard Rock 6.1 Methods 1) Heading and Benching Method (top and bottom or up and down method) • This method involves the driving of the top portion in advance of the bottom portion. • It is used when the tunnel section is very large and quality of rock is satisfactory. • In this method the top heading excavation is usually 3 to 4 m ahead of the bench excavation. 2) Drift Method • Rock tunneling is sometimes carried out first in smaller section of the proposed tunnel and then widened .This method is called as drift method. • In drift method, the total c/s of tunnel is divided into n no. of square section .Each section is about 2.5 to 3 m2 in area (face area). • By converting the tunnel into small c/s part any part is selected for the excavation which may be central part, top part, side part or bottom part.
  • 18. 18 • And through this part the excavation is done from start to the end .Such excavation is called as drift. • The drift provides the ventilation or light during the excavation of the remaining part of the tunnel. 3) Full face method :- • In full face method, workers excavate the entire diameter of tunnel at the same time. • In this method the mucking track could be placed progressively along with the excavation. • In this method tunneling is continuous. • Full face method was limited to small tunnels only, but now with the improvements and development in tunneling equipment more and more large tunnel can be driven by this method. • One of the machine which is usually used for cutting the full –face of the tunnel is called as Tunnel Boring Machine.
  • 19. 19 6.2 Tunnel Boring Machine • The use of tunnel boring machine is on increasing way, because instead of drilling and blasting this method can be used conveniently. • In case of tunnel boring machine the rock damage is less, cut material is handled systematically, safety of workers is great. • The cost of tunnel lining is reduced and the operation is continuous with the help of TBM. • With the help of TBM ,the face area that can be cut is about 20 m2 • The diameter of TBM is up to 6m. 6.3 HARD ROCK TBMS: • The Hard rock, either shielded or open-type TBMs are used to excavate rocks with the help of disc cutters which are mounted on the cutter head. • The rocks (muck) get chipped away as the disc cutter compresses stress fractures on it. • Now the excavated rocks are transferred to the belt conveyor through the cutter head openings. • These rocks are then run through multiple conveyors to get them removed from the tunnel.
  • 20. 20 6.4 Drilling, Blasting and hauling of muck Before the invention of the TBM drilling and blasting was the only method of excavating the material through hard rock. For drilling and blasting we follow following steps. • Small diameter drill is made with the help of different drilling equipment. • The drill hole is clean for placing the explosive and packing of explosive with clay. • Plantation of certain explosive material is done in the drill hole. • Detonating the explosive. • Fumes are released from the explosive. • Final excavation or mucking of material is done. 6.5 Theory of drilling and blasting • A drill hole normal to the face when exploded with proper charge will break out a gap inclined at approximately 45 degree to the face. • If two similar holes are kept side by side and fixed together they will blast a large quantity of rock which will be about 2.25 times greater than the single faces. • If three explosive with three similar holes are kept side by side and fixed together than it will break 3.5 times greater than quantity of rock than that for single face. • An inclined cut hole is more efficient than the hole that is drilled normal to the face. Therefore, an inclined angle of 45 degree is made to the face of the rock and hole is drilled .With the help of this inclined hole, the angle of crack also increases it the about 54 degree 44 min to the axis of the hole.
  • 21. 21 6.6 Drilling Equipment’s • Drilling is the process of making holes using drilling equipment. The drilling equipment varies w.r.t size of project, kind of rock, depth and size of hole, nature of terrain, etc. • The drilling equipment can be divided into two parts. 1) Percussion Drills • A drill holes the drill bit and rotates it in partial manner/angle (90 or 120 degree) to provide axial force for making a hole. • Percussion drill breaks the rock by impact from the repeated blows. • The popular varieties of percussion type of drills are
  • 22. 22 a) Jack hammer b) Tripod Drills c) Stop Hammer d) Drifter e) Churn drills f) Piston drills g) Wagon drills a) Jack Hammer • It is the air operated percussion types of drill which is portable and hand operated. • It is most used for drilling vertical holes. • The weight of the jack hammer varies from 10- 40 kg. • It can drill the hole up to 5 m depth. • The impact blow action of the jack hammer is about 2200 blows/min. b) Tripod Drills • This are similar to the jack hammer, expect that it is mounted on tripod to provide sufficient stability. • Tripods are usually very low and require drill changes every 1m or so. • They are not much in use except for very hard rock.
  • 23. 23 c) Stop Hammers • This is modification of jack hammer which are mounted on certain vehicle to hold the drill against the work and are usually used for up holes. d) Drifters • The drifter is an air operated precaution type of drill similar to the jack hammer but is so large that it needs mechanically mounting. • They are used for drilling down ,horizontal or up holes • They can drill up to of 12 cm diameter holes. e) Churn Drills ( Well drills ) • They are also called are well drills. • Churn drill can drill hole up to 15 cm diameter. • Churn Drill can drill at any angle and has the penetrating depth up to 100 m. • They are operated by steam or gasoline. f) Piston Drill • The piston drill is securely fastened and traveled the full length of the piston stroke. • It can drill a hole of 6 cm in diameter and can drill a hole up to 10 to 20 m long. • The impact blowing action is about 200 blows per minute.
  • 24. 24 g) Wagon drill • The wagon drill is the drifter mounted on a vehicle to provide portability in drilling the holes. • They are used extensively to drill the holes up to 12 cm in diameter and up to 10 m in depth. • Their performance is better than jack hammer. • They can be used to drill the hole at any angle from down to up. 2) Abrasion drill • The abrasion drill is a type of drill which grinds the rock up to small particles through abrasion effect of bit that rotates in the hole. • The common examples of abrasion drill are a) Blast hole drills b) Short drills c) Diamond drills a) Blast hole drill :- • This is the type of rotary drill which works on the system of compressed air and disintegrates the rock as it rotates over it. • The type of abrasion drill is used for drilling the hole up to 100 m in depth.
  • 25. 25 b) Short drills • This is the rotary abrasion type of drill which has the rough surface at the bottom and makes the hole in certain rock by crushing it. • Short drill can drill a hole up to 75 in diameter and up to depth of 200 m. c) Diamond drill • Diamond drill is a rotary abrasion types of drills whose bit consists of metal matrix in which they are embedded a large number of diamonds. • Diamond drills are uneconomical, hence are used in less quantity. 6.7 Blasting • The blasting is the operation performs to loose the rock so that it can be excavated or removed from its existing position. • Blasting is accomplished by discharging an explosive that has been placed in a hole specifically drill for this purpose. • During the blasting operation the drilled holes are made and cleaned, the charge of explosive is placed at the bottom of blast hole or drill holes; remaining portion of the hole is filled with the clay and tampered. • The size of the explosive ranges from 2.5 to 20 cm in diameter and its length is about 20-60 cm and tampered. 6.8 Types of Explosive a) Straight Dynamite • It is the first type of explosive with which all high explosives are compared for strength. • Its primary constituent is nitro- glycerin varying from 15-60%
  • 26. 26 • They are highly water resistance and a desirable property for sub- marine blasting. • Because of bad fumes they have been replaced by other types. b) Ammonia Dynamite • It contains equal parts of nitro- glycerin and nitrate of ammonia as the explosive material. • They come in the strength of 15-40%, but are not so sensitive as straight dynamites. • They are suitable for soft rock and fairly water resistance and their fumes are not so bad. c) Gelatin Dynamites • They are of two types  Straight Gelatin dynamites  Extra or special Gelatin dynamites • Both this type of gelatin dynamites consists of jelly of nitroglycerin and nitro- cotton.
  • 27. 27 • In extra or special gelatin, part of nitro-glycerin is replaced by nitrate of ammonia. • Both these types are highly water resistance and their fumes are good. • Their jelly like plastic consistency permits solid loading in a hole. • They are quick and have high shattering effect. • Because of these characteristics they are chosen for most rock tunneling work. d) Semi –Gelatin Dynamite • In a recent development, consisting principally the complex compound of nitrate of ammonia with same gelatin, nitro- glycerin, nitro – cotton, semi –gelatin is formed. • Semi- gelatins are bulkier than the straight or extra gelatin. • They are water resistant and fume quality is good. • Because of their low density, they are cheaper than extra or gelatin dynamite used in soft rock and lime –stone work. e) Blasting Gelatin • Blasting Gelatin are also a recent, fast, strong explosive. • They have the consistency same like soft rubber and it is fully water proof. • It is adaptable for wet work. • Its fumes are extremely bad and its strength is about 100%
  • 28. 28 f) Other High Explosives • Several Special high explosives are made, developed for special condition especially for disintegration of hard rock. • Some of the other explosive are • TNT – Tri –Nitro- Toluene • RDX –Rapid detorating explosive • Pent – Penta Eny thital
  • 29. 29 Chapter 7 Case Study on Maroshi - Ruparel water tunnel Mumbai 7.1 Introduction • Mumbai’s water network is crumbling under the strain. Its mains system is at least 80 years old, the majority of it laid in the colonial era. Though the city has seen some water distribution projects post-independence, they were still more than 60 years old. • Much of the system works through surface pipelines, which are prone to leakages and theft. This highly pressurized network is further hindered by passage under slum land, which adds even more complication to their maintenance. Likewise, Mumbai’s main water line runs beneath the runway of Mumbai international airport, making it doubly difficult to maintain, while a major burst could affect the movement of air traffic into and out of the city. • Hindustan Construction Company (HCC) was awarded the Contract of Maroshi- Ruparel College Tunnel Project by the Municipal Corporation of Mumbai in September 2007 with a Contract value of Rs 415.10 crore. This is a Water Supply Project executed under Jawaharlal Nehru National Urban Renewal Mission (JNNURM) and is funded by the Government of India, Government of Maharashtra & Municipal Corporation of Greater Mumbai. • The tunnel stretch is divided into three sections namely, Maroshi-Vakola (5.83 km long), Vakola-Mahim (4.55 km long) and Mahim-Ruparel College (1.86 km long). Maroshi-Vakola tunnel stretch is the longest section of the Maroshi to Ruparel College water tunnel. • The Maroshi-Ruparel tunnel work consists of construction of tunnel having 3.60 m diameter and 12.24 km long using Tunnel Boring Machine from Maroshi connecting to Ruparel College. The tunnel is connected with Shafts at Maroshi, Vakola and Mahim. The shafts are 12 m in diameter and about 80.00 m deep equivalent to a to 26-
  • 30. 30 storey building deep into the ground. It will be through these shafts that localities will get water supply. • The BMC began the underground tunnel project to stop leakage and water thefts from the water pipelines .The other focus of the project is to replace the water pipelines that are centuries old and have corroded at several spots ,causing sewage water to mix with drinking water. • The Vakola-Mahim section passes below the Mahim creek while the Maroshi-Vakola section crosses both of Mumbai airport’s runways at around 70 meters below ground level. The tunneling work was carried out without disturbing any operations on the ground level.
  • 31. 31 • The tunnel boring was extremely challenging due to heavy seepages and varying rock strata. During monsoon, the tunnel seepage had increased to about 25,000 m3 per day. Extensive grouting was carried out to control the same. 7.2 PROCESS First, a shaft with a diameter of 10 meters was constructed at a depth of between 70 and 80 meters. This served so that contractors could deliver all the necessary plant, machinery and equipment, including tunnel boring machines (TBMs), locomotives, water pumps and concrete mixers, through it to reach the 70-metre depth required for the boring and drilling. This was done by the gripping of jacks and alignment of TBM cutter heads for boring at a width of 3.6 meters through the earth. The concrete lining is cast on site rather than being pre-cast elsewhere. Once a stretch of boring is complete, an epoxy-coated reinforcement layer is fixed into place; the shutters and bulkheads are then set to pour ready-mix concrete using the agitator cars.
  • 32. 32 7.3 Conclusion • After completion, the tunnel improved the water situation in south and central Mumbai by supplying 1,100 million liters daily. The tunnel replaced the old upper Vaitarna and Vaitarna mains in this section. It improved the water supply to Vakola, Mahim, Dadar and Malabar Hill significantly. • This project is part of the rehabilitation and improvement of the drinking water conveyance / distribution system from Bhandup Treatment Works to Western Suburbs and Southwest part of the Mumbai city. • BMC town planners expect the new tunnel to have a number of advantages over the existing surface pipeline, because it travels at such great depth, meaning that the structure cannot be tampered with, as is the case with surface pipelines. In addition, there are fewer chances of leakages and water theft, and most importantly, the tunnel is not expected to require major maintenance over the next 100 years. And since the entire distribution system is made of concrete, it will not corrode, invariably happens with surface pipelines. • The project is also designed to withstand earthquakes.
  • 33. 33 References a) Harbor Dock and Tunnel Engineering Textbook by R srinivasa. b) Textbook of Tunnel Engineering by S.C.Saxena c) Textbook of Tunnel Engineering by Rangwala d) www.google.com e) Performance characteristics of tunnel boring machine in basalt and pyroclastic rocks of Deccan traps –Research paper by Prasnna Jain, A.K. Naithani, T.N. Singh.