Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 1
Chapter 1
INTRODUCTION
1.1 GENERAL
Trenchless technology is the techniques for utility line installation, replacement,
rehabilitation, inspection, location and leak detection with minimum excavation from the
ground surface. It also makes it possible to install the utilities under rivers canals and other
obstacles with no disruption of flow and with minimum and no damage to the environment. It
can enhance forest roadway culvert applications by minimizing excavation and maybe less
costly than conventional open-cut excavation.
These techniques are currently used in urban areas in an age where environmental
degradation has become an ever-increasing concern. It involves creating new networks or
repairing existing ones by minimizing the impact on surface sites. This reduces the
inconvenience caused to the users by “open trench” work, which requires an excavation along
the full length of the area worked on.
It is necessary first it specify a definition which helps better determine the field of
application of this work. Of course, the “trenchless” is opposite of “open trench” work, but it
is also used for the installation of networks of small diameter, which are called
“inaccessible”, particularly where a worker cannot get into the networks in normal working
condition: it is generally accepted that the upper limit is approximately 1,200 mm in
diameter. We are interested in understand structures where the construction requires remote
controlled techniques because the site can neither be accessed from the surface (“trenchless”)
nor accessed from the inside (inaccessible).
1.2 OPEN TRENCH METHOD
It is a traditional method of trenching for laying the utility lines below the surface. In present
days, there are many disadvantages and difficulties in adopting this method, mainly in urban
areas.
These are described below:
 As the open trench is going to create obstruction roads, busy areas, diversions have to be
provided before the start of any digging word.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 2
 As the obstruction is created, the traffic has to be rerouted causing traffic jams.
 The original users of the road have to undergo hardships in the form of additional mileage
as well as time.
 Many a times, while cutting deep trenches in congested areas appear in the adjacent
buildings.
 Another difficulty, which is encountered very often is the damage caused to other service
lines or cables present underground, providing temporary supports to these lines during
the construction is a cumbersome and costly affair.
 Trenches left open overnight should be fenced and barricaded. Hand of mechanical signs
should be used where necessary.
 While cutting open trenches, trees, shrubs, gardens etc. may have to be destroyed
damaging the environment.
 If any rehabilitation or renovation is required, the trenches once cut and refilled should
again be cut throughout and refilled causing difficulties to the public; that is, cutting and
refilling is required at frequent times
1.3 NEED FOR TRENCHLESS TECHNOLOGY
1. The disadvantages and difficulties encountered in conventional trenching methods have
resulted in thinking of the need for Trenchless Technology.
2. The advantages of the no-dig technology are also responsible for the need for this
technology to be adopted in mainly urban areas
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 3
Chapter 2
REVIEW OF LITERATURE
2.1 GENERAL
A critical literature review is presented which were contributed to the area of relevant topics
in relation to Trenchless technology. This review includes views, opinions, and suggestions
of scholars.
2.2 TRENCHLESS TECHNOLOGY
Mainak and Aarohi (2015) stated in their study that trenchless technology includes a wide
variety of methods, materials, and equipment capable of doing large scale works using
Tunnel Boring Machine or even small scale work like laying of pipes with or without the
entry of workers. This method is also very useful in seismic prone zone, places with hard
rock strata, high ground water level and can be helpful in reducing soil erosion in regions
with high rainfall. The method has also proven to be very useful for the army installations.
This method will prove to be very economic and time saving and will become a boon to a
third world and highly populated country like India.
Sai and Munasir, (2016) stated in their study that trenchless technology helps in installing,
repairing and replacing of water pipes, gas and petroleum pipes, and telecommunication
cables without disrupting the traffic, normal lifestyle and has minimal impact on economic
activity in congested areas and to the environment. This method is also very useful in seismic
prone zone, places with hard rock strata, high ground water level and can be helpful in
reducing soil erosion in regions with high rainfall. The method has also proven to be very
useful for the army installations. This method will prove to be very economic and time saving
and will become a boon to a third world and highly populated country like India.
Onkar and Kadam (2016) stated that Depending upon the specific situation trenchless
method can be cost-effective alternative to the more conventional open excavation. Fully
trenchless or partially trenchless technologies offer many benefits as a methodology for
rehabilitating or renewing pipelines. But in open cut excavation the social and environmental
impacts and the cost has considered. This study shortly discusses the comparisons of cost and
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 4
the factors that impact on a project and as per importance rating system developed between
open cut and trenchless techniques
2.3 SUMMARY
The above literature review not only helped in identification of the gap in the present body of
knowledge but has also enabled to establish relationship of the present study with what
already exist. Many studies and investigations were made by many scholars on Trenchless
Technology. This topic is selected on the basis of review of many research studies conducted
in abroad and in India. This literature review gives clear idea related to Trenchless
Technology. The main intention of the study is to investigate about the new trends in civil
engineering.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 5
Chapter 3
CLASSIFICATION OF TRENCHLESS TECHNOLOGY
Trenchless technology methods systems have been categorized into two groups:
1. New installation
2. Rehabilitation and Renovation
3.1. NEW INSTALLATION
Methods for installation of a new pipeline or duct, including dealing with service connection
are:
1. Micro Tunneling
2. Horizontal Directional Drilling
3. Short Drive System
4. Guided Drilling
3.1.1 Micro Tunnelling
Controlled excavation – steerable –Less than 1000mm diameter –Medium length Micro
tunnelling is a term which is used to describe remotely controlled mechanical tunnelling
systems where the spoil is removed from the cutting head within the new pipeline which is
advanced by pipe jacking.
Figure 3.1: Micro Tunnelling
Micro tunnelling (Figure 3.1) machines have now been developed to work from drive shafts
in almost all types of ground conditions. The cutting head has to be carefully selected to deal
with the expected ground conditions, with the appropriate cutting tools and crushing devices
for the range of gravels, sands, slits, and clays.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 6
The only excavating required from the service is to drive and receptions shafts. Spoil may be
removed from the face by an auger running through the newly installed pipeline to a skip in
the base of the drive shaft. Alternatively, water or bentonite may be used to convert the soil
into slurry at the cutting face. The slurry is less then pumped to the surface where the solids
are separated before disposal.
Micro tunnelling is used extensively in sewerage work where surface disruption has to be
minimized. Machines are now available to drive 100mm or more in soft ground for sizes
100mm diameter upwards. From drive shafts of less than 3mm diameter.
Micro tunnelling system has been developed in which temporary steel tubes are jacked in and
removed at the next manhole position, the new pipeline following in the established bore. In
micro tunnelling, the only indication on the surface is the presence of a control container with
A Hoist for Lowering Pipes into the Drive Shafts. Noise Levels And Traffic Disruption Are
minimized.
3.1.2 Horizontal Directional Drilling
Steerable heavy, powerful rig-Large size range –Long distances
Horizontal drilling systems (Figure 3.2) are nowadays widely used for installing pressure
pipes under Major obstacles such a motorway intersection, large rivers and airport runways.
Figure 3.2: Horizontal Directional Drilling
A small rotating and steerable drill bit is launched from the surface at an angle 10-15 and is
used to drill 90mm mud filled diameter hole. During the drilling operation a 125mm diameter
wash over pipe is drilled over the pilot string and following some 100mm behind the head.
Alternate drilling then continues on the pilot string is removed and the bore is enlarged by a
rotating barrel reamer attached to and pulled back by the wash over pipe, drilling mud being
used to llushed away the cuttings and to support the reamed hole. Subsequent caming
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 7
continues until the required diameter is achieved. The product pipe is less than attached to the
reaming head and pulled through the bore drives of more than 1.5km and of up to 1200mm
diameter have been carried out.
3.1.3 Short Drive Systems
 Auger Boring utilizes a rotating head to excavate the soil, which is transported by auger
flights operating in a casing to the drive pit. The head is recovered at an exit pit or in the
trench cut for the adjacent length of pipeline. Auger boring (Figure 3.3) is used in the
range of 100-1000mm diameter.
Figure 3.3: Auger boring
 Impact Moling in which a percussive mole is launched from a drive pit to displace the
soil and from a bore is widely used. The new conduct is normally drawn in behind the
mole. They are used to install services for all utilities.
Figure 3.4: Impact Moling
 Rod Pushing is a technique in which a bore of about 50mm diameter is formed by
displacement. A rod is advanced by a straight hydraulic push and the pilot hole may be
back reamed to the required size. The technique is used for the installation of pipes and
conduits up to 15mm diameter over lengths of 30-40mm.
 Pipe ramming and Thrust boring are similar processes where a casting, usually steel, is
driven through the ground from the drive pit to the exit pit. Accumulating spoil is
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 8
removed by compressed air and water after completing the bore. Pipe ramming is suitable for
most types of soil but not suitable where there are solid rock formations. It is said to be a cost
saving alternative to open trenching, angering or pipe jacking methods. Usually pipes up to
2000mm diameter can be laid using this technique depending upon the equipment uses.
3.1.4 Guided Drilling
Steerable small rig-Sallow drilling-Medium length.
Guide drilling employs an excavation or soil displacement with compact lightweight rig for rapid
mobilization. Small diameter jets mechanized cutting tools or displacement heads attached to a
flexible drill string are positioned to form a bore as the head is thrust forward. The drilling head is
launched from the surface at an inclined angle. Controlling the orientation of a slant face at the
head affects steering in both vertical and horizontal planes. Monitoring of the alignment takes
place using a transmitter in the head and a locating device at ground level. I having established
the pilot bore; back reaming equipment is drawn through the hole to enable it to accept the
product pipe, duct, or cable using an impact mole.
3.2 RENOVATION AND REHABILITATION
Methods including are:
a) Pipe bursting
b) Pipe eating
c) Retaining the existing pipe
d) Localized repair
3.2.1 Pipe Bursting
New for old without trenching – Size for size and upsize capability
In this method an existing pipeline can be replaced with a pipeline of the same or larger
dimension without opening up the ground. It is especially useful in areas where the load on
the system is more than the existing pipe can handle and replacement is required. The method
uses a mole as a bursting head that is drawn through the existing pipe crushing it as it moves
forward and replacing it with a new PE (polyethylene) pipe. The main advantage of this
system is that a small power source can be used to drive the mole with minimum time.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 9
Upsizing from 100mm diameter to 225mm diameter is now well established, and pipes of up
to 600mm diameter have been replaced. Figure 3.5 shows pipe busting technique.
Figure 3.5: Pipe Bursting
3.2.2 Pipe Eating
New for old without trenching – Enlargement - Steerable
Pipe eating (Figure 3.6) is an online micro tunnelled replacement technique. The existing
defective pipeline is crushed and removed through the new pipeline. Lateral connections must be
disconnected in advance and may be replaced by rider sewers or reconnected by angled drilling.
Figure 3.6: Pipe Eating
3.2.3 Relining the Existing Pipes
This method requires access, usually by manholes, at both ends of pipe. A flexible liner is places
into the defective pipe and with the use of water under pressure finds its own way and can pass
bends of 90o
. In places where joints have moved or sections are missing, but the passage is
available, the liner creates a smooth transition. When the liner is in place, it is heat cured to create
a rigid, tough, and smooth inner surface.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 10
3.2.4 Localised Repair
 Resin injection and chemical grouting at trouble spots
Local defects may be found in pipes due to cracking or joint failures. Systems are
available for resin injection to seal localized defects in the range 100mm-600mm
diameter. Chemical grouting with urethane and similar materials are used in sewer
rehabilitation. Remote and man entry grouting of defective joints and cracks may prevent
infiltration in pipelines.
This is an inexpensive method of rehabilitating existing systems up to several hundred
meters of length every day from manhole to manhole.
 Pipe Slip lining is another method used that involves inserting new smaller pipes in to
older, damaged sewers thereby replacing the old pipe. But the new pipe is reduced in
diameter.
 Modified slip lining often called close fit lining utilize the properties of PE or PVC to
allow temporary reduction in diameter or change in shape prior to insertion in the
defective pipe. The method includes Roll down, Swage lining and deformed lining. The
inserted pipe is subsequently expanded to form a tight fit against the wall of the original
pipe, thus avoiding the need for annular grouting as in conventional slip lining. For Roll
down and Swage lining, temporary reduction in diameter is achieved either by
mechanical rolling (Roll down) or drawing through a reduction die (Swage lining). For
Deformed linings, the pipe is deformed and folded immediately after extrusion and is
coiled on a drum. After insertion in the defective pipe, the lining is expanded using steam
and a re-rounding device to form a close fit. These systems are suitable where the
existing line is of good shape. As compared to conventional slip lining, in this method
there is little or no loss of hydraulic capacity.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 11
Chapter 4
TECHNIQUES OF TRENCHLESS TECHNOLOGY IN
INDIA
The main Trenchless techniques which are in use in India are described below.
4.1 DIRECTIONAL DRILLING
Directional drilling involves steerable tunnelling systems for both small and diameter lines.
In most cases, it is a two-stage process. The first stage consists of drilling a small diameter
pilot hole along the desired centre line of a proposed line and in the second stage, the pilot
hole is enlarged to the desired diameter to accommodate the utility line and to pull the utility
line through the enlarged hole. Figure 4.1 shows Directional drilling method.
Figure 4.1: Directional Drilling
The pilot hole is approximately 3 inches in diameter and is drilled with a specially built rig up
with an inclined carriage typically adjusted to between 5 and 30 degrees, which push the drill
rods into the ground. However the optimum angle is 12 degrees. As the pilot hole is being
drilled, bentonite-drilling mud is pumped down the center of the drill rods. The drill head
consists of either a jetting head or drill bit. In the case of a jetting head, small diameter high-
pressure jets of bentonite actually cut the soil and facilitate spoil removal by washing the
cuttings to the surface where they settle out in a reception pit. In case of drill bit, the bit is
driven by a down hole mud motor located just behind the drill bit from energy derived from
the pumped drilling fluid. Before the start of back reaming the pipeline has to be positioned
on rollers in line with the hole to minimize any axial load on the line.
4.1.1 Advantages
1. The major advantage is the speed of installation combined with the minimum
environmental and social impact.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 12
2. Long and complicated crossings can be accomplished with a great degree of accuracy
since it is possible to monitor and control the drilling operation so that utilities can be fit
into small corridors where little place is available between existing utilities.
3. Another advantage is that sufficient depth can be accomplished to avoid other utilities.
4. Limitation of access and reception pits is another advantage.
4.1.2 Disadvantage
1. Special equipment and very high degrees of operation skill is required.
2. As the cost of the equipment and the operation are high, bore length should be sufficient
in order for it to be economical.
3. Mainly steel pipe is being installed by the method.
4.2 RAMMING
In this method, the pipe is rammed through the soil by using a device attached to the end of
the pipe to drive the pipe through the soil. In this method, the tool does not create a borehole.
It acts as a hammer to drive the pipe through the soil. Compressed air supplied from an air
compressor is generally used as a power source. When ramming pipe, the leading edge cuts a
borehole, the spoils enters the pipe and is compacted as it is being forced to the rear of the
pipe. After the whole length of the pipe is rammed in place, the tool is removed and the pipe
is cleaned out. Figure 4.2 shows Ramming Technique.
Figure 4.2: Ramming
The type of pipe installed by the pipe ramming method is limited to steel due to the
application of cyclic impact loads on the pipe. The size of the pipe ranges from 2 inches to 55
inches. This method is capable of installing pipes to over 200 feet (60 meters) in length.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 13
4.2.1 Advantages
The pipe ramming is an effective method for installing medium size pipes. The method is
economic since the equipment cost is not very high and the operation is simple. The pipe can
be installed in one piece or segments. This can be used in almost all types of soils. The
method does not require any thrust reaction structure.
4.2.2 Disadvantages
The major disadvantage is that there is no control over the line and grade and in case of
obstructions like boulders, the pipe may be deflected. Then work should be stopped
immediately. For small diameter pipelines, the method is economical, but for large diameter
pipes, the equipment cost is high.
4.3 MOLING
Moling is a method, which forms the borehole by compressing the earth that immediately
surrounds the compacting device which is an underground piercing (mole) is propelled by a
power source. The tool is streamlined into a bullet or shape. The method is restricted to
relatively small diameter lines in compressible soil conditions. Figure 4.3 shows Moling
Technique.
Figure 4.3: Moling
Compressed air or hydraulic fluid, transmitted to the toot through the flexible hoses, imparts
energy at a blow frequency of 100 to 600 strokes per minute to a reciprocating piston located
inside the nose of the tool. This action results in the tool propelling itself through the ground.
It is applicable in most ground conditions from loose sand to firm clay. The method required
the use of boring and receiving pit. After the operation the unit can be backed out of the
borehole. The tool is removed and the cable is attached to the air hose and pulled back
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 14
through the borehole. In the case of rigid pipe, it can simply be pushed through the open
borehole. Any type of pipe or cable can be installed by the method.
Pipe size is generally limited to 6 inches or less. However, modern techniques in mole
manufacturing have increased the ability to make the bores of large sizes. Even though 200
feet (60 meter) bores have been successfully made by this method, the span lengths were
limited to 60 feet (18 meter) with 40 feet being optimum. Again span lengths have increased
with modern advances in mole design.
4.3.1 Advantages
It is a rapid, economic, and effective method of installing small diameter lines. Any type of
utility line can be installed using the method. The stability of the soil around the borehole is
increased due to compaction. The investment in equipment is minimized.
4.3.2 Disadvantages
Compaction methods are limited in their length by reliability because basic systems are
unintelligent, unguided tools that tend to bury themselves, surface in the middle road or
damage existing utility lines.
4.4 AUGER BORING
The auger horizontal earth boring is a process of simultaneously jacking casing through the
earth while removing the spoil inside the casing by means of a rotating flight auger. The
auger is a flighted tube having dual functions, firstly it has couplings at each end that transmit
torque to the cutting head from the power source located in the bore pit and secondly, it
serves to transfer spoil back to the machine. Figure 4.4 Shows Auger Boring.
Figure 4.4: Auger Boring
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 15
4.4.1 Augur Blades
This method requires bore pit both at the entry and exit points of the bore. The auger-boring
machine consists of the boring machine, casing pipe, cutting head and augers as the major
components. The power source creates the torque, which rotates the auger, which in turn
rotates the cutting head. The cutting head cuts the soil and the soil is transported to the
machine through the casing by means of the auger, which acts as a screw conveyor. Figure
4.5 shows Auger Blades.
Figure 4.5: Auger Blades
The pipe size that can be installed by this method ranges from 4 inches (100mm) to over 60
inches (1500 mm). However, the most common size range is 8 inches(200 mm) to 36
inches(900 mm) and the average bore length ranges between 53 meter and 68 meter, though
with experience and the use of latest techniques up to 180 meter of boring is possible using
auger boring.
4.4.2 Advantages
The major advantage is that the casing is installed at the same time as the borehole excavation
takes place. This method can be used in a wide variety of soil types.
4.4.3 Disadvantages
This method requires different sized cutting heads and auger sizes or each casing diameter,
which increases the investment in equipment. The investment in bore, pit construction, and
the initial setup is also required. In case of soils containing large boulders, this method cannot
be used advantageously.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 16
4.5 ADVANTAGES OF TRENCHLESS TECHNOLOGY
1. Less disturbing – By open cut method disturb local properties over agricultural land or
disturbing local highways. But by use of Trenchless technology come out from these
problems like landscape damage.
2. Less time – open cut method is time consuming method. In this method time is required
for the excavation and refilling of trenches. This process also means time is taken in site
restoration, spoils storage and traffic control.
3. Enhanced safety compared to steep excavations – by steep excavation Landslides can
be occurs. Where the mud is likely to subside due to steep walls or water aggravation,
protection needs to be taken with specialist equipment. By trenchless technology
provided safety to the workers as there are no steep trenches involved in this work.
4. Save time and cost related to survey and design – open cut method consist of
preliminary survey, detailed survey etc. In detailed survey consist of the depth of the
cut, the ground conditions where the trenches will run and also how much dewatering
will need to take place, ensuring that conditions are safe to work. But in trenchless
technique saved time and cost related to survey.
5. Encountering fewer unknowns in the ground – in open cut method, approximately
70% of the cost required for excavating and replacing the ground during the process. As
per unknowns come in the excavation or digging cost of excavation increases. By use of
Trenchless technology reduced this problem.
6. Minimize chance of disturbing existing utilities – at the time of open cut most
important problem come in front of is disruption to above surface activities. As well as
at the time of digging has to avoid existing utilities. Trenchless technology comes with
the ability to install new pipelines and rehabilitate existing pipelines with limited
disturbance to traffic and business activities, reduce damage to existing paved surfaces.
7. Problem to the public such as noise and air pollution – The indirect social costs of
open cut projects consist of unhealthy, inconvenience to traffic, and noise pollution. But
these problems can play a big part of local communities. These problems can be
overcome with trenchless technology without the need for road closures, noise
pollution.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 17
Chapter 5
CASE STUDY
Case Study: Khan Market, New Delhi, OFC (Optical Fiber Cable)
Project Name: Horizontal Directional Drilling.
Client: Mahanagar Telephone Nigam Limited (MTNL)
Requirements: Installation of 20cm diameter optical fiber cable to supply 4G line.
Distance: 100m
Crossing: Underneath the road and old Museum.
Pit Size: Launch pit 4.5m x 1.5m
Constraints: Fully enclosed Garden at the centre of the museum with all plant and equipment having
to be transported through the public galleries to the job site. Cable to be installed to connect the
enclosed garden to a service area in a basement 12m away. The cable route would be beneath the
public gallery with installation being completed during the museum‟s opening hours. Space in the
basement was extremely limited making any method requiring access to both ends of the bore
impossible. The cable needed to be installed just 200mm below the buildings foundations. Figure
5.1 shows Pipe Ramming in underneath the road and old Museum in Khan Market, New
Delhi, and OFC
Ground Conditions: Hard packed soil and gravel.
Installation Time: 2 Days
Figure 5.1: Pipe ramming in underneath the road and old Museum in Khan Market,
New Delhi, and OFC
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 18
SUMMARY
1. The open cut trenching methods create road closures, traffic delays, noises and
general disruption.
2. This makes repair and rehabilitation of subsurface utilities difficult, particularly in
areas congested with traffic and buildings.
3. Lack of repair and rehabilitation of the pipeline for the water disruption and sewage
systems lead to leakages and waste water seepages, resulting in the contamination of
water distribution system and groundwater.
4. These problems often give rise to related health and environmental impacts.
Trenchless Technology- A Review 2017-18
Dept. of Civil Engineering, BIT, Mangalore Page 19
REFERENCE
1. Hemishkumar, P., Jayeshkumar, P., Bhavsar, J. J., (2014), “, pp. 1-13. A Study On
Trenchless Technology: Eliminate The Need For Excavation”, National Conference
On-trends And Challenges Of Civil Engineering In Today's Transforming World
2. Onkar, K. C and Kadam, V. S., (2016), “Comparative Study Of Traditional Method
And Innovative Method For Trenchless Technology: A Review”, Internationa
Research Journal Of Engineering And Technology,Volume. 03, Issue. 05, pp. 1104-
1107.
3. Umesh, D and Norman, J., (2011), “Trenchless technology – An Overview”,
International Conference on Underground Space Technology, Bangalore, pp. 1-10.
4. Mainak, M P and Arohi, K M., (2015), “Trenchless Technology”, Civil Engineering
Systems and Sustainable Innovations, pp. 156-163.
5. Sai, K. D and Munasir, M., (2016), “Study of Trenchless Technology”, International
Journal of Scientific Research in Science Engineering and Technology, Volume. 02,
Issue. 06, pp. 43-48.

More Related Content

What's hot

Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Mayur Rahangdale
 
Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Mayur Rahangdale
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.Himanshu Rao
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
metro system and engineering.pptx
metro system and engineering.pptxmetro system and engineering.pptx
metro system and engineering.pptxBalpreetSingh47890
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal DesignVijai Krishnan V
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Artificial intelligence in civil engineering
Artificial intelligence in civil engineering Artificial intelligence in civil engineering
Artificial intelligence in civil engineering Aseena Latheef
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...Malyar Talash
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingHamed Zarei
 

What's hot (20)

TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
pothole repairs
pothole repairspothole repairs
pothole repairs
 
metro system and engineering.pptx
metro system and engineering.pptxmetro system and engineering.pptx
metro system and engineering.pptx
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal Design
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Artificial intelligence in civil engineering
Artificial intelligence in civil engineering Artificial intelligence in civil engineering
Artificial intelligence in civil engineering
 
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
4-Vertical and Horizontal Alignment Coordination(by Malyar Talash: Highway De...
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Skybus ppt
Skybus pptSkybus ppt
Skybus ppt
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
 
Presentation1
Presentation1Presentation1
Presentation1
 
Well foundation pdf
Well foundation pdfWell foundation pdf
Well foundation pdf
 
PERMEABLE PAVEMENT
PERMEABLE PAVEMENTPERMEABLE PAVEMENT
PERMEABLE PAVEMENT
 

Similar to Trenchless Technology Technical Seminar Report

trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdfpawankumar491710
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologykumarrajagp
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfKARTHIKGOUD64
 
A new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyA new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyPatricia Faria
 
trenchless technology
trenchless technologytrenchless technology
trenchless technologyHemish Patel
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologyAlexASquare1
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologyAlexASquare1
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT Deepak Kumar
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET Journal
 
Study on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavementStudy on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavementeSAT Publishing House
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringSahl Buhary
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional BoringWe-Bore-It
 
Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...eSAT Journals
 
Vacuum Excavation Services Bay Area Unleashing The Power Of Precision Digging
Vacuum Excavation Services Bay Area Unleashing The Power Of Precision DiggingVacuum Excavation Services Bay Area Unleashing The Power Of Precision Digging
Vacuum Excavation Services Bay Area Unleashing The Power Of Precision DiggingTec
 
IRJET- Review of Stormwater Management using Pervious Concrete in Pavements
IRJET-  	  Review of Stormwater Management using Pervious Concrete in PavementsIRJET-  	  Review of Stormwater Management using Pervious Concrete in Pavements
IRJET- Review of Stormwater Management using Pervious Concrete in PavementsIRJET Journal
 
Trenchlesstechnology jan2011
Trenchlesstechnology jan2011Trenchlesstechnology jan2011
Trenchlesstechnology jan2011AlexASquare1
 

Similar to Trenchless Technology Technical Seminar Report (20)

transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
A new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyA new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technology
 
trenchless technology
trenchless technologytrenchless technology
trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
 
Study on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavementStudy on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavement
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
 
Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...
 
Vacuum Excavation Services Bay Area Unleashing The Power Of Precision Digging
Vacuum Excavation Services Bay Area Unleashing The Power Of Precision DiggingVacuum Excavation Services Bay Area Unleashing The Power Of Precision Digging
Vacuum Excavation Services Bay Area Unleashing The Power Of Precision Digging
 
IRJET- Review of Stormwater Management using Pervious Concrete in Pavements
IRJET-  	  Review of Stormwater Management using Pervious Concrete in PavementsIRJET-  	  Review of Stormwater Management using Pervious Concrete in Pavements
IRJET- Review of Stormwater Management using Pervious Concrete in Pavements
 
Trenchlesstechnology jan2011
Trenchlesstechnology jan2011Trenchlesstechnology jan2011
Trenchlesstechnology jan2011
 

More from AkshathaBhandary

1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf
1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf
1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdfAkshathaBhandary
 
Disaster Management Technical Seminar
Disaster Management Technical SeminarDisaster Management Technical Seminar
Disaster Management Technical SeminarAkshathaBhandary
 
Highway Vertical Alignment
Highway Vertical AlignmentHighway Vertical Alignment
Highway Vertical AlignmentAkshathaBhandary
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
 
Highway Horizontal Alignment
Highway Horizontal AlignmentHighway Horizontal Alignment
Highway Horizontal AlignmentAkshathaBhandary
 
Bid Submission and Evaluation
Bid Submission and EvaluationBid Submission and Evaluation
Bid Submission and EvaluationAkshathaBhandary
 
Internship Report Construction Site and Office Work
Internship Report Construction Site and Office WorkInternship Report Construction Site and Office Work
Internship Report Construction Site and Office WorkAkshathaBhandary
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro projectAkshathaBhandary
 

More from AkshathaBhandary (13)

1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf
1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf
1. 1 Stabilization of Laterite Soil Using Waste Paper Sludge.pdf
 
Disaster Management Technical Seminar
Disaster Management Technical SeminarDisaster Management Technical Seminar
Disaster Management Technical Seminar
 
Highway Vertical Alignment
Highway Vertical AlignmentHighway Vertical Alignment
Highway Vertical Alignment
 
Highway Alignment
Highway AlignmentHighway Alignment
Highway Alignment
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 
Highway Horizontal Alignment
Highway Horizontal AlignmentHighway Horizontal Alignment
Highway Horizontal Alignment
 
Sight Distance
Sight DistanceSight Distance
Sight Distance
 
Valuation 08.04.2020
Valuation 08.04.2020Valuation 08.04.2020
Valuation 08.04.2020
 
Tender
TenderTender
Tender
 
Contract management
Contract managementContract management
Contract management
 
Bid Submission and Evaluation
Bid Submission and EvaluationBid Submission and Evaluation
Bid Submission and Evaluation
 
Internship Report Construction Site and Office Work
Internship Report Construction Site and Office WorkInternship Report Construction Site and Office Work
Internship Report Construction Site and Office Work
 
Internship Report on metro project
Internship Report on metro projectInternship Report on metro project
Internship Report on metro project
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 

Trenchless Technology Technical Seminar Report

  • 1. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 1 Chapter 1 INTRODUCTION 1.1 GENERAL Trenchless technology is the techniques for utility line installation, replacement, rehabilitation, inspection, location and leak detection with minimum excavation from the ground surface. It also makes it possible to install the utilities under rivers canals and other obstacles with no disruption of flow and with minimum and no damage to the environment. It can enhance forest roadway culvert applications by minimizing excavation and maybe less costly than conventional open-cut excavation. These techniques are currently used in urban areas in an age where environmental degradation has become an ever-increasing concern. It involves creating new networks or repairing existing ones by minimizing the impact on surface sites. This reduces the inconvenience caused to the users by “open trench” work, which requires an excavation along the full length of the area worked on. It is necessary first it specify a definition which helps better determine the field of application of this work. Of course, the “trenchless” is opposite of “open trench” work, but it is also used for the installation of networks of small diameter, which are called “inaccessible”, particularly where a worker cannot get into the networks in normal working condition: it is generally accepted that the upper limit is approximately 1,200 mm in diameter. We are interested in understand structures where the construction requires remote controlled techniques because the site can neither be accessed from the surface (“trenchless”) nor accessed from the inside (inaccessible). 1.2 OPEN TRENCH METHOD It is a traditional method of trenching for laying the utility lines below the surface. In present days, there are many disadvantages and difficulties in adopting this method, mainly in urban areas. These are described below:  As the open trench is going to create obstruction roads, busy areas, diversions have to be provided before the start of any digging word.
  • 2. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 2  As the obstruction is created, the traffic has to be rerouted causing traffic jams.  The original users of the road have to undergo hardships in the form of additional mileage as well as time.  Many a times, while cutting deep trenches in congested areas appear in the adjacent buildings.  Another difficulty, which is encountered very often is the damage caused to other service lines or cables present underground, providing temporary supports to these lines during the construction is a cumbersome and costly affair.  Trenches left open overnight should be fenced and barricaded. Hand of mechanical signs should be used where necessary.  While cutting open trenches, trees, shrubs, gardens etc. may have to be destroyed damaging the environment.  If any rehabilitation or renovation is required, the trenches once cut and refilled should again be cut throughout and refilled causing difficulties to the public; that is, cutting and refilling is required at frequent times 1.3 NEED FOR TRENCHLESS TECHNOLOGY 1. The disadvantages and difficulties encountered in conventional trenching methods have resulted in thinking of the need for Trenchless Technology. 2. The advantages of the no-dig technology are also responsible for the need for this technology to be adopted in mainly urban areas
  • 3. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 3 Chapter 2 REVIEW OF LITERATURE 2.1 GENERAL A critical literature review is presented which were contributed to the area of relevant topics in relation to Trenchless technology. This review includes views, opinions, and suggestions of scholars. 2.2 TRENCHLESS TECHNOLOGY Mainak and Aarohi (2015) stated in their study that trenchless technology includes a wide variety of methods, materials, and equipment capable of doing large scale works using Tunnel Boring Machine or even small scale work like laying of pipes with or without the entry of workers. This method is also very useful in seismic prone zone, places with hard rock strata, high ground water level and can be helpful in reducing soil erosion in regions with high rainfall. The method has also proven to be very useful for the army installations. This method will prove to be very economic and time saving and will become a boon to a third world and highly populated country like India. Sai and Munasir, (2016) stated in their study that trenchless technology helps in installing, repairing and replacing of water pipes, gas and petroleum pipes, and telecommunication cables without disrupting the traffic, normal lifestyle and has minimal impact on economic activity in congested areas and to the environment. This method is also very useful in seismic prone zone, places with hard rock strata, high ground water level and can be helpful in reducing soil erosion in regions with high rainfall. The method has also proven to be very useful for the army installations. This method will prove to be very economic and time saving and will become a boon to a third world and highly populated country like India. Onkar and Kadam (2016) stated that Depending upon the specific situation trenchless method can be cost-effective alternative to the more conventional open excavation. Fully trenchless or partially trenchless technologies offer many benefits as a methodology for rehabilitating or renewing pipelines. But in open cut excavation the social and environmental impacts and the cost has considered. This study shortly discusses the comparisons of cost and
  • 4. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 4 the factors that impact on a project and as per importance rating system developed between open cut and trenchless techniques 2.3 SUMMARY The above literature review not only helped in identification of the gap in the present body of knowledge but has also enabled to establish relationship of the present study with what already exist. Many studies and investigations were made by many scholars on Trenchless Technology. This topic is selected on the basis of review of many research studies conducted in abroad and in India. This literature review gives clear idea related to Trenchless Technology. The main intention of the study is to investigate about the new trends in civil engineering.
  • 5. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 5 Chapter 3 CLASSIFICATION OF TRENCHLESS TECHNOLOGY Trenchless technology methods systems have been categorized into two groups: 1. New installation 2. Rehabilitation and Renovation 3.1. NEW INSTALLATION Methods for installation of a new pipeline or duct, including dealing with service connection are: 1. Micro Tunneling 2. Horizontal Directional Drilling 3. Short Drive System 4. Guided Drilling 3.1.1 Micro Tunnelling Controlled excavation – steerable –Less than 1000mm diameter –Medium length Micro tunnelling is a term which is used to describe remotely controlled mechanical tunnelling systems where the spoil is removed from the cutting head within the new pipeline which is advanced by pipe jacking. Figure 3.1: Micro Tunnelling Micro tunnelling (Figure 3.1) machines have now been developed to work from drive shafts in almost all types of ground conditions. The cutting head has to be carefully selected to deal with the expected ground conditions, with the appropriate cutting tools and crushing devices for the range of gravels, sands, slits, and clays.
  • 6. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 6 The only excavating required from the service is to drive and receptions shafts. Spoil may be removed from the face by an auger running through the newly installed pipeline to a skip in the base of the drive shaft. Alternatively, water or bentonite may be used to convert the soil into slurry at the cutting face. The slurry is less then pumped to the surface where the solids are separated before disposal. Micro tunnelling is used extensively in sewerage work where surface disruption has to be minimized. Machines are now available to drive 100mm or more in soft ground for sizes 100mm diameter upwards. From drive shafts of less than 3mm diameter. Micro tunnelling system has been developed in which temporary steel tubes are jacked in and removed at the next manhole position, the new pipeline following in the established bore. In micro tunnelling, the only indication on the surface is the presence of a control container with A Hoist for Lowering Pipes into the Drive Shafts. Noise Levels And Traffic Disruption Are minimized. 3.1.2 Horizontal Directional Drilling Steerable heavy, powerful rig-Large size range –Long distances Horizontal drilling systems (Figure 3.2) are nowadays widely used for installing pressure pipes under Major obstacles such a motorway intersection, large rivers and airport runways. Figure 3.2: Horizontal Directional Drilling A small rotating and steerable drill bit is launched from the surface at an angle 10-15 and is used to drill 90mm mud filled diameter hole. During the drilling operation a 125mm diameter wash over pipe is drilled over the pilot string and following some 100mm behind the head. Alternate drilling then continues on the pilot string is removed and the bore is enlarged by a rotating barrel reamer attached to and pulled back by the wash over pipe, drilling mud being used to llushed away the cuttings and to support the reamed hole. Subsequent caming
  • 7. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 7 continues until the required diameter is achieved. The product pipe is less than attached to the reaming head and pulled through the bore drives of more than 1.5km and of up to 1200mm diameter have been carried out. 3.1.3 Short Drive Systems  Auger Boring utilizes a rotating head to excavate the soil, which is transported by auger flights operating in a casing to the drive pit. The head is recovered at an exit pit or in the trench cut for the adjacent length of pipeline. Auger boring (Figure 3.3) is used in the range of 100-1000mm diameter. Figure 3.3: Auger boring  Impact Moling in which a percussive mole is launched from a drive pit to displace the soil and from a bore is widely used. The new conduct is normally drawn in behind the mole. They are used to install services for all utilities. Figure 3.4: Impact Moling  Rod Pushing is a technique in which a bore of about 50mm diameter is formed by displacement. A rod is advanced by a straight hydraulic push and the pilot hole may be back reamed to the required size. The technique is used for the installation of pipes and conduits up to 15mm diameter over lengths of 30-40mm.  Pipe ramming and Thrust boring are similar processes where a casting, usually steel, is driven through the ground from the drive pit to the exit pit. Accumulating spoil is
  • 8. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 8 removed by compressed air and water after completing the bore. Pipe ramming is suitable for most types of soil but not suitable where there are solid rock formations. It is said to be a cost saving alternative to open trenching, angering or pipe jacking methods. Usually pipes up to 2000mm diameter can be laid using this technique depending upon the equipment uses. 3.1.4 Guided Drilling Steerable small rig-Sallow drilling-Medium length. Guide drilling employs an excavation or soil displacement with compact lightweight rig for rapid mobilization. Small diameter jets mechanized cutting tools or displacement heads attached to a flexible drill string are positioned to form a bore as the head is thrust forward. The drilling head is launched from the surface at an inclined angle. Controlling the orientation of a slant face at the head affects steering in both vertical and horizontal planes. Monitoring of the alignment takes place using a transmitter in the head and a locating device at ground level. I having established the pilot bore; back reaming equipment is drawn through the hole to enable it to accept the product pipe, duct, or cable using an impact mole. 3.2 RENOVATION AND REHABILITATION Methods including are: a) Pipe bursting b) Pipe eating c) Retaining the existing pipe d) Localized repair 3.2.1 Pipe Bursting New for old without trenching – Size for size and upsize capability In this method an existing pipeline can be replaced with a pipeline of the same or larger dimension without opening up the ground. It is especially useful in areas where the load on the system is more than the existing pipe can handle and replacement is required. The method uses a mole as a bursting head that is drawn through the existing pipe crushing it as it moves forward and replacing it with a new PE (polyethylene) pipe. The main advantage of this system is that a small power source can be used to drive the mole with minimum time.
  • 9. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 9 Upsizing from 100mm diameter to 225mm diameter is now well established, and pipes of up to 600mm diameter have been replaced. Figure 3.5 shows pipe busting technique. Figure 3.5: Pipe Bursting 3.2.2 Pipe Eating New for old without trenching – Enlargement - Steerable Pipe eating (Figure 3.6) is an online micro tunnelled replacement technique. The existing defective pipeline is crushed and removed through the new pipeline. Lateral connections must be disconnected in advance and may be replaced by rider sewers or reconnected by angled drilling. Figure 3.6: Pipe Eating 3.2.3 Relining the Existing Pipes This method requires access, usually by manholes, at both ends of pipe. A flexible liner is places into the defective pipe and with the use of water under pressure finds its own way and can pass bends of 90o . In places where joints have moved or sections are missing, but the passage is available, the liner creates a smooth transition. When the liner is in place, it is heat cured to create a rigid, tough, and smooth inner surface.
  • 10. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 10 3.2.4 Localised Repair  Resin injection and chemical grouting at trouble spots Local defects may be found in pipes due to cracking or joint failures. Systems are available for resin injection to seal localized defects in the range 100mm-600mm diameter. Chemical grouting with urethane and similar materials are used in sewer rehabilitation. Remote and man entry grouting of defective joints and cracks may prevent infiltration in pipelines. This is an inexpensive method of rehabilitating existing systems up to several hundred meters of length every day from manhole to manhole.  Pipe Slip lining is another method used that involves inserting new smaller pipes in to older, damaged sewers thereby replacing the old pipe. But the new pipe is reduced in diameter.  Modified slip lining often called close fit lining utilize the properties of PE or PVC to allow temporary reduction in diameter or change in shape prior to insertion in the defective pipe. The method includes Roll down, Swage lining and deformed lining. The inserted pipe is subsequently expanded to form a tight fit against the wall of the original pipe, thus avoiding the need for annular grouting as in conventional slip lining. For Roll down and Swage lining, temporary reduction in diameter is achieved either by mechanical rolling (Roll down) or drawing through a reduction die (Swage lining). For Deformed linings, the pipe is deformed and folded immediately after extrusion and is coiled on a drum. After insertion in the defective pipe, the lining is expanded using steam and a re-rounding device to form a close fit. These systems are suitable where the existing line is of good shape. As compared to conventional slip lining, in this method there is little or no loss of hydraulic capacity.
  • 11. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 11 Chapter 4 TECHNIQUES OF TRENCHLESS TECHNOLOGY IN INDIA The main Trenchless techniques which are in use in India are described below. 4.1 DIRECTIONAL DRILLING Directional drilling involves steerable tunnelling systems for both small and diameter lines. In most cases, it is a two-stage process. The first stage consists of drilling a small diameter pilot hole along the desired centre line of a proposed line and in the second stage, the pilot hole is enlarged to the desired diameter to accommodate the utility line and to pull the utility line through the enlarged hole. Figure 4.1 shows Directional drilling method. Figure 4.1: Directional Drilling The pilot hole is approximately 3 inches in diameter and is drilled with a specially built rig up with an inclined carriage typically adjusted to between 5 and 30 degrees, which push the drill rods into the ground. However the optimum angle is 12 degrees. As the pilot hole is being drilled, bentonite-drilling mud is pumped down the center of the drill rods. The drill head consists of either a jetting head or drill bit. In the case of a jetting head, small diameter high- pressure jets of bentonite actually cut the soil and facilitate spoil removal by washing the cuttings to the surface where they settle out in a reception pit. In case of drill bit, the bit is driven by a down hole mud motor located just behind the drill bit from energy derived from the pumped drilling fluid. Before the start of back reaming the pipeline has to be positioned on rollers in line with the hole to minimize any axial load on the line. 4.1.1 Advantages 1. The major advantage is the speed of installation combined with the minimum environmental and social impact.
  • 12. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 12 2. Long and complicated crossings can be accomplished with a great degree of accuracy since it is possible to monitor and control the drilling operation so that utilities can be fit into small corridors where little place is available between existing utilities. 3. Another advantage is that sufficient depth can be accomplished to avoid other utilities. 4. Limitation of access and reception pits is another advantage. 4.1.2 Disadvantage 1. Special equipment and very high degrees of operation skill is required. 2. As the cost of the equipment and the operation are high, bore length should be sufficient in order for it to be economical. 3. Mainly steel pipe is being installed by the method. 4.2 RAMMING In this method, the pipe is rammed through the soil by using a device attached to the end of the pipe to drive the pipe through the soil. In this method, the tool does not create a borehole. It acts as a hammer to drive the pipe through the soil. Compressed air supplied from an air compressor is generally used as a power source. When ramming pipe, the leading edge cuts a borehole, the spoils enters the pipe and is compacted as it is being forced to the rear of the pipe. After the whole length of the pipe is rammed in place, the tool is removed and the pipe is cleaned out. Figure 4.2 shows Ramming Technique. Figure 4.2: Ramming The type of pipe installed by the pipe ramming method is limited to steel due to the application of cyclic impact loads on the pipe. The size of the pipe ranges from 2 inches to 55 inches. This method is capable of installing pipes to over 200 feet (60 meters) in length.
  • 13. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 13 4.2.1 Advantages The pipe ramming is an effective method for installing medium size pipes. The method is economic since the equipment cost is not very high and the operation is simple. The pipe can be installed in one piece or segments. This can be used in almost all types of soils. The method does not require any thrust reaction structure. 4.2.2 Disadvantages The major disadvantage is that there is no control over the line and grade and in case of obstructions like boulders, the pipe may be deflected. Then work should be stopped immediately. For small diameter pipelines, the method is economical, but for large diameter pipes, the equipment cost is high. 4.3 MOLING Moling is a method, which forms the borehole by compressing the earth that immediately surrounds the compacting device which is an underground piercing (mole) is propelled by a power source. The tool is streamlined into a bullet or shape. The method is restricted to relatively small diameter lines in compressible soil conditions. Figure 4.3 shows Moling Technique. Figure 4.3: Moling Compressed air or hydraulic fluid, transmitted to the toot through the flexible hoses, imparts energy at a blow frequency of 100 to 600 strokes per minute to a reciprocating piston located inside the nose of the tool. This action results in the tool propelling itself through the ground. It is applicable in most ground conditions from loose sand to firm clay. The method required the use of boring and receiving pit. After the operation the unit can be backed out of the borehole. The tool is removed and the cable is attached to the air hose and pulled back
  • 14. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 14 through the borehole. In the case of rigid pipe, it can simply be pushed through the open borehole. Any type of pipe or cable can be installed by the method. Pipe size is generally limited to 6 inches or less. However, modern techniques in mole manufacturing have increased the ability to make the bores of large sizes. Even though 200 feet (60 meter) bores have been successfully made by this method, the span lengths were limited to 60 feet (18 meter) with 40 feet being optimum. Again span lengths have increased with modern advances in mole design. 4.3.1 Advantages It is a rapid, economic, and effective method of installing small diameter lines. Any type of utility line can be installed using the method. The stability of the soil around the borehole is increased due to compaction. The investment in equipment is minimized. 4.3.2 Disadvantages Compaction methods are limited in their length by reliability because basic systems are unintelligent, unguided tools that tend to bury themselves, surface in the middle road or damage existing utility lines. 4.4 AUGER BORING The auger horizontal earth boring is a process of simultaneously jacking casing through the earth while removing the spoil inside the casing by means of a rotating flight auger. The auger is a flighted tube having dual functions, firstly it has couplings at each end that transmit torque to the cutting head from the power source located in the bore pit and secondly, it serves to transfer spoil back to the machine. Figure 4.4 Shows Auger Boring. Figure 4.4: Auger Boring
  • 15. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 15 4.4.1 Augur Blades This method requires bore pit both at the entry and exit points of the bore. The auger-boring machine consists of the boring machine, casing pipe, cutting head and augers as the major components. The power source creates the torque, which rotates the auger, which in turn rotates the cutting head. The cutting head cuts the soil and the soil is transported to the machine through the casing by means of the auger, which acts as a screw conveyor. Figure 4.5 shows Auger Blades. Figure 4.5: Auger Blades The pipe size that can be installed by this method ranges from 4 inches (100mm) to over 60 inches (1500 mm). However, the most common size range is 8 inches(200 mm) to 36 inches(900 mm) and the average bore length ranges between 53 meter and 68 meter, though with experience and the use of latest techniques up to 180 meter of boring is possible using auger boring. 4.4.2 Advantages The major advantage is that the casing is installed at the same time as the borehole excavation takes place. This method can be used in a wide variety of soil types. 4.4.3 Disadvantages This method requires different sized cutting heads and auger sizes or each casing diameter, which increases the investment in equipment. The investment in bore, pit construction, and the initial setup is also required. In case of soils containing large boulders, this method cannot be used advantageously.
  • 16. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 16 4.5 ADVANTAGES OF TRENCHLESS TECHNOLOGY 1. Less disturbing – By open cut method disturb local properties over agricultural land or disturbing local highways. But by use of Trenchless technology come out from these problems like landscape damage. 2. Less time – open cut method is time consuming method. In this method time is required for the excavation and refilling of trenches. This process also means time is taken in site restoration, spoils storage and traffic control. 3. Enhanced safety compared to steep excavations – by steep excavation Landslides can be occurs. Where the mud is likely to subside due to steep walls or water aggravation, protection needs to be taken with specialist equipment. By trenchless technology provided safety to the workers as there are no steep trenches involved in this work. 4. Save time and cost related to survey and design – open cut method consist of preliminary survey, detailed survey etc. In detailed survey consist of the depth of the cut, the ground conditions where the trenches will run and also how much dewatering will need to take place, ensuring that conditions are safe to work. But in trenchless technique saved time and cost related to survey. 5. Encountering fewer unknowns in the ground – in open cut method, approximately 70% of the cost required for excavating and replacing the ground during the process. As per unknowns come in the excavation or digging cost of excavation increases. By use of Trenchless technology reduced this problem. 6. Minimize chance of disturbing existing utilities – at the time of open cut most important problem come in front of is disruption to above surface activities. As well as at the time of digging has to avoid existing utilities. Trenchless technology comes with the ability to install new pipelines and rehabilitate existing pipelines with limited disturbance to traffic and business activities, reduce damage to existing paved surfaces. 7. Problem to the public such as noise and air pollution – The indirect social costs of open cut projects consist of unhealthy, inconvenience to traffic, and noise pollution. But these problems can play a big part of local communities. These problems can be overcome with trenchless technology without the need for road closures, noise pollution.
  • 17. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 17 Chapter 5 CASE STUDY Case Study: Khan Market, New Delhi, OFC (Optical Fiber Cable) Project Name: Horizontal Directional Drilling. Client: Mahanagar Telephone Nigam Limited (MTNL) Requirements: Installation of 20cm diameter optical fiber cable to supply 4G line. Distance: 100m Crossing: Underneath the road and old Museum. Pit Size: Launch pit 4.5m x 1.5m Constraints: Fully enclosed Garden at the centre of the museum with all plant and equipment having to be transported through the public galleries to the job site. Cable to be installed to connect the enclosed garden to a service area in a basement 12m away. The cable route would be beneath the public gallery with installation being completed during the museum‟s opening hours. Space in the basement was extremely limited making any method requiring access to both ends of the bore impossible. The cable needed to be installed just 200mm below the buildings foundations. Figure 5.1 shows Pipe Ramming in underneath the road and old Museum in Khan Market, New Delhi, and OFC Ground Conditions: Hard packed soil and gravel. Installation Time: 2 Days Figure 5.1: Pipe ramming in underneath the road and old Museum in Khan Market, New Delhi, and OFC
  • 18. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 18 SUMMARY 1. The open cut trenching methods create road closures, traffic delays, noises and general disruption. 2. This makes repair and rehabilitation of subsurface utilities difficult, particularly in areas congested with traffic and buildings. 3. Lack of repair and rehabilitation of the pipeline for the water disruption and sewage systems lead to leakages and waste water seepages, resulting in the contamination of water distribution system and groundwater. 4. These problems often give rise to related health and environmental impacts.
  • 19. Trenchless Technology- A Review 2017-18 Dept. of Civil Engineering, BIT, Mangalore Page 19 REFERENCE 1. Hemishkumar, P., Jayeshkumar, P., Bhavsar, J. J., (2014), “, pp. 1-13. A Study On Trenchless Technology: Eliminate The Need For Excavation”, National Conference On-trends And Challenges Of Civil Engineering In Today's Transforming World 2. Onkar, K. C and Kadam, V. S., (2016), “Comparative Study Of Traditional Method And Innovative Method For Trenchless Technology: A Review”, Internationa Research Journal Of Engineering And Technology,Volume. 03, Issue. 05, pp. 1104- 1107. 3. Umesh, D and Norman, J., (2011), “Trenchless technology – An Overview”, International Conference on Underground Space Technology, Bangalore, pp. 1-10. 4. Mainak, M P and Arohi, K M., (2015), “Trenchless Technology”, Civil Engineering Systems and Sustainable Innovations, pp. 156-163. 5. Sai, K. D and Munasir, M., (2016), “Study of Trenchless Technology”, International Journal of Scientific Research in Science Engineering and Technology, Volume. 02, Issue. 06, pp. 43-48.