SlideShare a Scribd company logo
1 of 49
Download to read offline
This document has been approved for use by agen-
cies of the Department of Defense and for listing in
the DoD Index of Specifications and Standards.
ACI 304R-89
Guide for Measuring, Mixing,
Transporting, and Placing Concrete (Reapproved 1997)
Reported by ACI Committee 304
James L. Cope,* chairman
Raymond A. Ayres*
Joseph C. Carson
Thomas R. Clapp
Wayne J. Costa*
Robert M. Eshbach*
J. R. Florey
Donald E. Graham*
Terence C. Holland* Stanley H. Lee*
Robert A. Kelsey Kurt R. Melby*
Gordon M. Kidd Richard W. Narva
John C. King* Leo P. Nicholson
William C. Krell* James S. Pierce*
Bruce A. Lamberton William J. Sim*
This guide presents information on the handling, measuring, and
batching of all the materials used in making normal weight, light-
weight structural and heavyweight concrete. It covers both weight
and volumetric measuring, mixing in central mix plants and truck
mixers and concrete placing using buckets, buggies, pumps and
conveyors. Underwater concrete placing and preplaced aggregate
concrete are also covered. The guide outlines procedures for ob-
taining good quality concrete in completed structures.
Keywords: absorption; admixtures; aggregate gradation; aggregates; aggre-
gate size; air entrainment; batching; bleeding (concrete); cement content; ce-
ments; chutes; coarse aggregates; concrete construction; concretes; consol-
idation; construction joints; conveying; conveyors; curing; density (mass/
volume); falsework; fine aggregates; fineness modulus; formwork (construc-
tion); grout; grouting; heat of hydration; heavyweight aggregates; laitance;
lightweight aggregate concretes; lightweight aggregates; mass concrete; mate-
rials handling; mixers; mixing; mixing time; mix proportioning; moisture
content; placing; pozzolans; preplaced aggregate concrete; pumped concrete;
quality control; ready-mixed concrete; retempering; segregation; slipform
construction; stockpiling; temperature; transit mixers, tremie concrete; un-
derwater construction; vibration; water; water-cement ratio; workability.
CONTENTS
Chapter 1 - Introduction, page 304R-2
1.1-Scope
1.2-Objective
1.3-Other considerations
Jack H. Skinner, III
James H. Sprouse
Paul R. Stodola*
William X. Sypher
R. E. Tobin*
Francis C.* Wilson
Chapter 2 - Control, handling, and storage of
materials, page 304R-3
2.1-General considerations
2.2-Aggregates
2.3-Cement
Chapter 3 - Measurement and batching,
page 304R-6
3.1-General requirements
3.2-Bins and weigh hatchers
3.3-Plant type
3.4-Cementitious materials
3.5-Water measurement
3.6-Measurement of admixtures
3.7-Measurement of materials for small jobs
3.8-Other considerations
Chapter 4 - Mixing and transporting,
page 304R-11
4.1-General requirements
4.2-Mixing equipment
4.3-Central mixed concrete
4.4-Truck mixed concrete
4.5-Charging and mixing
4.6-Mix temperature
4.7-Discharging
4.8-Mixer performance
4.9-Maintenance
4.10-General considerations for transporting concrete
I ACI Committee Reports, Guides, Standard Practices, and Commen-
taries are intended for guidance in designing, planning, executing, or I
inspecting construction and in preparing specifications. Reference to
these documents shall not be made in the Project Documents. If items
found in these documents are desired to be a part of the Project Docu-
ments, they should be phrased in mandatory language and incorpo-
rated into the Project Documents.
*Member of the task group which prepared this report.
Copyright © 1989, American Concrete Institute.
All rights reserved including rights of reproduction and use in any form or
by any means, including the making of copies by any photo process, or by any
electronic or mechanical device, unless permission in writing is obtained from
the copyright proprietors.
304R-2 MANUAL OF CONCRETE PRACTICE
Chapter 5-Placing concrete, page 304R-14
5.1-General considerations
5.2-Planning
5.3-Reinforcement and embedded items
5.4-Placing
Chapter 6-Forms, joint preparation, and
finishing, page 304R-21
6.l-Forms
6.2-Joint preparation
6.3-Finishing unformed surfaces
Chapter 7-Preplaced aggregate structural and
mass concrete, page 304R-23
7.1-General considerations
7.2-Materials
7.3-Grout mix proportioning
7.4-Temperature control
7.5-Forms
7.6-Grout pipe systems
7.7-Coarse aggregate placement
7.8-Grout mixing and pumping
7.9-Joint construction
7.10-Finishing
7.11-Quality control
Chapter 8-Concrete placed under water,
page 304R-28
8.l-General considerations
8.2-Materials
8.3-Mixture proportioning
8.4-Concrete production and testing
8.5-Tremie equipment and placement procedure
8.6-Direct pumping
8.7-Concrete characteristics
8.8-Precautions
8.9-Special applications
8.10-New developments
Chapter 9-Pumping concrete, page 304R-32
9.1-General considerations
9.2-Pumping equipment
9.3-Pipelines and accessories
9.4-Proportioning pumpable concrete
9.5-Field practices
9.6-Field control
Chapter 10-Conveying concrete, page 304R-37
10.1-General considerations
10.2-Conveyor requirements
10.3-Conveyor types and functions
10.4-Conveyor charging
10.5-Discharge control
10.6-Maintenance
Chapter 11-Heavyweight and radiation shielding
concrete, page 304R-41
11.1-General considerations
11.2-Materials
11.3-Concrete characteristics
11.4-Mixing equipment
11.5-Formwork
11.6-Placement
11.7-Quality control
Chapter 12-Lightweight concrete, page 304R-44
12.1-General considerations
12.2-Measuring and batching
12.3-Mixing
12.4-Job controls
Chapter 13-References, page 304R-47
13.1-Recommended references
13.2-Cited references
CHAPTER 1 -INTRODUCTION
1.1-Scope
This guide outlines procedures for obtaining good
results in measuring and mixing ingredients for con-
crete, transporting it to the site and placing it. The
first six chapters are general in nature and have broad
application to all types of projects and concrete. The
following, specialized chapters, deal with preplaced
aggregate concrete, underwater placing, pumping,
and conveying on belts. The concluding chapters
deal with heavyweight, radiation shielding and
lightweight concrete.
1.2-Objective
In preparing this guide, the committee followed
this philosophy.
1. Progress in improvement of concrete construc-
tion will be better served by the presentation of high
standards rather than “common practices.”
2. In many cases, if not most, practices resulting in
the production and placement of high quality con-
crete can be performed as economically as those re-
sulting in poor concrete. Many of the practices
recommended in this document improve concrete
uniformity as well as quality so that effort and in-
vestment are rewarded by a smoother operation and
higher production rates, both of which offset poten-
tial additional cost.
3. It is assumed that anyone planning to use this
guide will have a basic knowledge of the general
practices involved in concrete work. If more specific
information on measuring, mixing, transporting, and
placing concrete is desired, the reader should refer to
the list of references given at the end of this docu-
ment, and particularly to References 2 and 6 and
ASTM C 94, ACI 311 and 318 and EM 1110-2-2000.
Committee 304 generally agrees with the information
given in these references although some exceptions
in emphasis and detail may be noted, To portray
more clearly certain principles involved in achieving
maximum uniformity, homogeneity, and quality of
concrete in place, illustrations of good and poor
practices are also included.
1.3-Other considerations
All concerned with concrete work should be aware
of the importance of maintaining the unit water con-
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-3
tent as low as possible consistent with placing re-
quirements.
1,5
Even though the water-cement ratio is
kept constant, an increase in unit water increases the
potential for drying shrinkage cracking, and with
this cracking, the concrete may lose a portion of its
durability and other desirable characteristics, such
as monolithic properties and low permeability. In-
discriminate addition of water which increases the
water-cement ratio adversely affects both strength
and durability. The more a form is filled with the
right combination of solids and the less it is filled
with water, the better will be the resulting concrete.
Only as much cement should be used as is re-
quired to obtain adequate strength, durability,
placability, workability, and other essential proper-
ties. Reducing cement content is particularly impor-
tant in massive sections subject to restraint as the
temperature rise associated with the hydration of ce-
ment may result in cracking as a result of volume
change (ACI 207.1R and 207.2R). Only as much water
and fine aggregate should be used as is required to
obtain suitable workability for proper placing and
consolidation by means of vibration.
CHAPTER 2-CONTROL, HANDLING,
AND STORAGE OF MATERIALS
2.1 -General considerations
Coarse and fine aggregates, cement, pozzolans and
chemical admixtures must be properly stored, batched
and handled to maintain quality.
2.2-Aggregates
Fine and coarse aggregates should be of good qual-
ity, uncontaminated and uniform in grading and
moisture content. Unless this is accomplished
through appropriate specifications (ASTM C 33) and
effective selection, preparation, and handling of ag-
gregates (Fig, 2.2.la and b), the production of uni-
form concrete will be difficult1
(see ACI 221R).
2.2.1 Coarse aggregate - Coarse aggregate should
be controlled to minimize segregation and undersize
material.
2.2.1.1. Sizes - A practical method of reducing
segregation to a minimum in coarse aggregate is to
separate the material into several size fractions and
batch these fractions separately. As the range of sizes
in each fraction is decreased and the number of size
separations is increased, segregation is further re-
duced. Effective control of segregation and undersize
materials is most easily accomplished when the ratio
of maximum to minimum size in each fraction is
held to not more than four for aggregates smaller than
1 in. (25 mm) and to two for larger sizes. Examples of
some appropriate aggregate fraction groupings are as
follows:
Example 1
Sieve Designations
No. 4 to ¾ in. (4.75 mm to 19.0 mm)
¾ in to 1½ in. (19.0 mm to 37.5 mm)
1½ in. to 3 in. (37.5 mm to 75 mm)
3 in. to 6 in. (75 mm to 150 mm)
Example 2
Sieve Designations
1½ in. to ¾ in. (37.5 mm to 19.0 mm)
1 in. to No. 4 (25.0 mm to 4.75 mm)
3
/8in. to No. 8 (9.5 mm to 2.36 mm)
2.2.1.2 Control of undersize material - Under-
size material for a given aggregate fraction is defined
as that material which will pass a sieve having an
opening five-sixths of the nominal minimum size of
each aggregate fraction.2
In Example 1 above, that
would be material passing the following sieves: No. 5
(4.0 mm), 5
/8 in. (16.0 mm), 1¼ in. (31.5 mm) and 2½
in. (63 mm). For effective control of gradation, it is
essential that handling operations do not signifi-
cantly increase the undersize materials in aggregates
prior to their use in concrete (Fig. 2.2,1a-d). The gra-
dation of aggregate as it enters the concrete mixer
should be uniform and within specification limits.
Sieve analyses of coarse aggregate should be made
with sufficient frequency to assure that grading re-
quirements are being met. When two or more aggre-
gate sizes are being used, changes in the proportions
of the sizes should be made as required to improve
the overall grading of the combined aggregate. When
specification limits for grading cannot be met consis-
tently, special handling methods should be in-
stituted. Materials tend to segregate during
transportation and reblending may be desirable. Re-
screening the coarse aggregate, as it is charged to the
bins at the batch plant, to waste or remove undersize
materials will effectively eliminate undesirable fines
when usual storage and handling methods are not
satisfactory. Undersize materials in the smaller
coarse aggregate fractions can be consistently re-
duced to as low as two percent by rescreening (see
Fig. 2.2.ld).
2.2.2. Fine aggregate (sand) - Fine aggregate
should be controlled to minimize variations in gra-
dation, with special attention to keeping finer frac-
tions uniform and exercising care to avoid excessive
removal of fines during processing.
If the ratio of fine to coarse aggregate is adjusted in
accordance with ACI 211.1 recommendations for
mix proportioning, a wide range of fine aggregate
gradings can be used.3
However, variations in grading
during production of concrete must be minimized,
and the ASTM C 33 requirement that the fineness
modulus of the fine aggregate be maintained within
0.20 of the design value should be met.
304R-4 MANUAL OF CONCRETE PRACTICE
INCORRECT METHODS OF STOCKPILING AGGREGATES
CAUSE SEGREGATION AND BREAKAGE
a.
PREFERABLE
OBJECTIONABLE
CRANE OR OTHER MEANS OF PLACING MATERIAL IN
PILE IN UNITS NOT LARGER THAN A TRUCK LOAD
WHICH REMAIN WHERE PLACED AND DO NOT RUN
DOWN SLOPE.
METHODS WHICH PERMIT THE AGGREGATE TO ROLL
DOWN THE SLOPE AS IT IS ADDED TO THE PILE
OR PERMlT HAULING EQUIPMENT TO OPERATE OVER
THE SAME LEVEL REPEATEDLY
LIMITED ACCEPTABILITY-GENERALLY OBJECTIONABLE
PILE BUlLT RADIALLY IN HORIZONTAL LAYERS BY BULLDOZER OR FRONT LOADER STACKING PROGRESSIVE LAYERS ON
BULLD0ZER OR FRONT LOADER WORKING FROM MATERIALS AS SLOPE NOT FLATTER THAN 3:1. UNLESS MATERIALS
DROPPED FROM CONVEYOR BELT. A ROCK LADDER MAY STRONGLY RESIST BREAKAGE, THESE METHODS ARE
BE NEEDED IN SETUP. ALSO OBJECTIONABLE.
b. C.
CORRECT
CHlMNEY SURROUNDING MATERlAL FALLlNG
FROM END Of CONVEYOR BELT TO PREVENT
WIND FROM SEPARATING FINE AND COARSE
MATERIALS. OPENINGS PROVIDED AS REQUIRED
TO DISCHARGE MATERIALS AT VARIOUS
ELEVATIONS ON THE PILE.
INCORRECT
FREE FALL OF MATERIAL FROM HIGH END WHEN STOCKPILING LARGE SIZED AGGREGATES
OF STACKER PERMITTING WIND TO SEPARATE FROM ELEVATED CONVEYORS, BREAKAGE IS
FINE FROM COARSE MATERIAL MINlMlZED BY USE OF A ROCK LADDER.
UNFINISHED OR FINE AGGREGATE STORAGE FINISHED AGGREGATE STORAGE
(DRY MATERIALS)
NOTE: IF EXCESSIVE FINES CANNOT BE AVOIDED IN COARSE AGGREGATE FRACTlONS BY STOCKPILING METHODS USED, FINISH
SCREENING PRIOR TO TRANSFER TO BATCH PLANT BINS WILL BE REQUIRED.
Fig. 2.2. 1a-c Correct and incorrect methods of handling and storing aggregates
MEASURING, MIXING, TRANSPORTING, AND PLACING
Fig. 2.2.1d Batching plant rescreen arrangement
The amount and nature of material finer than the
No. 200 screen (75 µm sieve) should be given special
attention. As recognized in ASTM C 33, if this mate-
rial is dust of fracture, essentially free of clay or
shale, greater percentages of materials finer than the
No. 200 screen (75 µm sieve) are permissible. How-
ever, if the reverse is the case, permissible quantities
should be significantly reduced. The California sand
equivalent test is sometimes used to determine quan-
titatively the type, amount and activity of this fine
material1
(see ASTM D 2419). Excessive quantities of
minus No. 200 screen (75 µm sieve) fines increase
the mixing water requirement, rate of slump loss,
and drying shrinkage and decrease strength.
Attempts should not be made to blend two sizes of
fine aggregate by placing alternate amounts in bins or
stockpiles or in cars or trucks as loaded. Satisfactory
results are obtained when different size fractions are
blended as they flow into a stream from regulating
gates or feeders. However, the most positive method
of control for a wide range of plant and job condi-
tions is separate storage, handling, and batching of
the coarse and fine fractions.
2.2.3 Storage - Stockpiling of coarse aggregate
should be kept to a minimum because even under
ideal conditions fines tend to settle and accumulate.
However, when stockpiling is necessary, use of cor-
rect methods minimize problems with fines, segrega-
tion, aggregate breakage, and excessive variation in
gradation. Stockpiles should be built up in horizon-
tal or gently sloping layers, not by end dumping.
Trucks, loaders and dozers, or other equipment
should not be operated on the stockpiles because, in
addition to breaking the aggregate, they frequently
track dirt onto the piles (Fig. 2.2.1a-c). A hard base
with good drainage should be provided to prevent
contamination from underlying material and overlap
of the different sizes should be prevented by suitable
walls or ample spacing between piles. The wind
should not be permitted to separate dry fine aggre-
gate and stockpiles should not be contaminated by
swinging aggregate filled buckets or clams over the
other stockpiled aggregate sizes.
Storage bins should be kept as full as practical to
minimize breakage and changes in grading as mate-
rials are withdrawn, Materials should be deposited
into the bins vertically and directly over the bin out-
let (see Fig 3.2b). Particular attention must be paid to
the storage of special concrete aggregates including
lightweight, high density and architectural-finish ag-
gregates. Contamination of these special materials
will have compounding effects on other properties of
the concrete in which they are to be used (see Chap-
ters 11 and 12).
2.2.4 Moisture control - Effort must be made to in-
sure, as practically as possible, a uniform and stable
moisture content in the aggregate as batched. The use
of aggregates having varying amounts of free water is
one of the most frequent causes for loss in control of
concrete consistency (slump). In some cases it may
be necessary to wet the coarse aggregate in the stock-
piles or on the delivery belts to compensate for high
absorption, or to provide cooling. When this is done
the coarse aggregates must be dewatered to prevent
transfer of excessive free water to the bins.
Adequate time for drainage of free water from fine
aggregate must be provided prior to its transfer to the
batch plant bins. The storage time required depends
304R-6 MANUAL OF CONCRETE PRACTICE
primarily on the grading and particle shape of the
aggregate. Experience has shown that a free moisture
content of as high as 6 percent and occasionally as
high as 8 percent can be stable in fine aggregate.
However, tighter controls may be required for certain
jobs. The use of moisture meters to indicate varia-
tions in the moisture of the fine aggregate as batched,
and the use of moisture compensators for rapid batch
weight adjustments can minimize the influence of
moisture variations in the fine aggregate.4,5
2.2.5 Samples for test - Samples representing the
various aggregate sizes batched should be obtained
as closely as possible to the point of their introduc-
tion into the concrete. The difficulty in obtaining
representative samples increases with the size of the
aggregate. Therefore, sampling devices require care-
ful design if meaningful test results are to be ob-
tained, Methods of sampling aggregates are outlined
in detail in ASTM D 75.
It is good practice to maintain a running average
on from 5 to 10 previous gradation tests, dropping
the results of the oldest and adding the most recent
to the total on which the average is calculated. This
average gradation can then be used for both quality
control and for proportioning purposes.
2.3-Cement
All cement should be stored in weathertight, prop-
erly ventilated structures to prevent absorption of
moisture.
Storage facilities for bulk cement should include
separate compartments for each type of cement used.
The interior of a cement silo should be smooth with a
minimum bottom slope of 50 deg from the horizontal
for a circular silo and 55 to 60 deg for a rectangular
silo, Silos should be equipped with nonclogging air
diffuser flow pads through which small quantities of
dry, oil-free, low-pressure air, approximately 3 to 5
psi (21 to 34 kPa) may be introduced intermittently
to loosen cement which has settled tightly in the
silos. Storage silos should be drawn down fre-
quently, preferably once per month, to prevent ce-
ment caking.
Each bin compartment from which cement is
batched should include a separate gate, screw con-
veyor, air slide, rotary feeder, or other conveyance
which effectively combines characteristics of con-
stant flow with precise cut off to obtain accurate
batching of cement.
Care must be used to prevent cement being trans-
ferred to the wrong silo, whether by faulty pro-
cedures or equipment. Fugitive dust should be
controlled during loading and transferring.
Bags of cement should be stacked on pallets or
similar platforms to permit proper circulation of air.
For a storage period of less than 60 days, it is recom-
mended that the bags be stacked no higher than 14
layers, and for long periods, no higher than 7 layers.
AS an additional precaution, it is recommended that,
insofar as practical, the oldest cement be used first.
2.4-Admixtures
Fly ash, ground slag and other finely divided or
powdered admixtures should be handled, conveyed
and stored in the same manner as cement (see ACI
212.2R). However, fly ash bins should be completely
separate from cement bins, without common walls,
which might allow fly ash to leak into the cement
bin. Care must be taken to assure that fly ash is not
loaded into a cement bin by mistake on delivery (see
Section 3.4.1).
In practice, most chemical admixtures are deliv-
ered in liquid form. Care should be taken to protect
liquid admixtures from freezing. If frozen, proper re-
blending or mixing of the admixture should be done
before it is used in concrete. Manufacturers’ recom-
mendations should be followed.
Long term storage of liquid admixtures in vented
tanks should be avoided. Evaporation of a portion of
the liquid could adversely affect the admixtures’ per-
formance (see ACI 212).
CHAPTER 3-MEASUREMENT AND BATCHING
3.1 - General requirements
3.1.1. Objectives - An important objective in pro-
ducing concrete is to obtain uniformity and homo-
geneity as indicated by such physical properties as
unit weight, slump, air content, strength, and air-free
unit weight of mortar in individual batches and suc-
cessive batches of the same mixture proportions 2,6,7
(ASTM C 94, CE-CW-03305). During measurement
operations aggregates should be handled to maintain
the desired grading, and all materials should be
measured within the tolerances required for desired
reproducibility of the concrete mix selected. Another
important objective of successful batching is the
proper sequencing and blending of the ingredients.6,7
Visual observation of each material being batched is
helpful to achieving this objective.
3.1.2 Tolerances - Most engineering organiza-
tions, both public and private, issue specifications
containing detailed requirements for manual, semi-
automatic, partially automatic and automatic batch-
ing equipment for concrete2
(CE-CW-03305, ASTM C
94 and AASHTO). Batching equipment currently
marketed will operate within the usual specified
batch weight tolerances when the equipment is
maintained in good mechanical condition. A fre-
quently used document for specifying batching and
scale accuracy is the "Concrete Plant Standards of
the Concrete Plant Manufacturer’s Bureau."8,9
Batch-
ing tolerances frequently used are given in Table
3.1.2.
Other commonly used requirements include beam
or scale divisions of 0.1 percent of total capacity and
batching interlock of 0.3 percent of total capacity at
zero balance;8
quantity of admixture weighed never
to be so small that 0.4 percent of full scale capacity
MEASURING, MIXING, TRANSPORTING, AND PLACING
exceeds 3 percent of the required weight; isolation of
batching equipment from plant vibration; protection
of automatic controls from dust and weather; and
frequent checking and cleaning of scale and beam
pivot points. With good inspection and plant opera-
tion, batching equipment can be expected to perform
consistently within the required tolerances.
3.2-Bins and weigh batchers
Batch plant bins and components should be of
adequate size to accommodate the productive capac-
ity of the plant, Compartments in bins should ade-
quately separate the various concrete materials, and
the shape and arrangement of aggregate bins should
be conducive to the prevention of aggregate segrega-
tion and breakage. The aggregate bins should be de-
signed so material cannot hang up in the bins or spill
from one compartment to another.
Weigh hatchers should be charged with easy oper-
ating clamshell or undercut radial-type bin gates.
Gates used to charge semiautomatic and fully-
automatic hatchers should be power operated and
equipped with a suitable “dribble” control to obtain
the desired weighing accuracy. Weigh hatchers
should be accessible for obtaining representative
samples, and they should be arranged to obtain the
proper sequencing and blending of aggregates during
charging of the mixer.
Illustrations showing the proper design and ar-
rangement of batch plant bins and weigh hatchers are
given in Fig. 3.2.
3.3-Plant type
Factors affecting the choice of the proper batching
systems are (1) size of job; (2) required production
rate; and (3) required standards of batching
performance.
The productive capacity of a batch plant is deter-
mined by a combination of such items as the mate-
rials handling system, bin size, hatcher size, and
mixer size and number.
Available weight-batch equipment falls into three
general categories: manual, semiautomatic, partial-
automatic or fully-automatic.8
Available volumetric
equipment includes portable and stationary units
equipped with either continuous or batch mixers.
3.3.1 Manual weigh batching - As the name im-
plies, all operations of weighing and batching of the
concrete ingredients are controlled manually. Man-
ual plants are acceptable for small jobs having low
batching rate requirements. As the job size increases,
automation of batching operations is rapidly justi-
fied. Attempts to increase the capacity of manual
plants by rapid batching may result in excessive
weighing inaccuracies.
3.3.2 Semiautomatic weigh batching - In this sys-
tem aggregate bin gates for charging hatchers are
opened by manually operated push-buttons or
switches. Gates are closed automatically when the
designated weight of material has been delivered.
With satisfactory plant maintenance the batching ac-
curacy should meet the tolerances given in Section
3.1.2. The system must contain interlocks which pre-
vent hatcher charging and discharging from occur-
ring simultaneously. In other words, when the
hatcher is being charged, it cannot be discharged,
and when it is being discharged, it cannot be
charged. Visual confirmation of the scale reading for
each material being weighed is essential.
3.3.3 Automatic weigh batching - Automatic
weigh batching of all materials is activated by a sin-
gle starter switch. However, interlocks interrupt the
batching cycle when the scale does not return to 0.3
percent of zero balance or when preset weighing tol-
erances detailed in Section 3.1.2 are exceeded.
3.3.3.1 Cumulative automatic weigh batching-
Interlocked sequential controls are required for this
type of batching. Weighing will not begin, and it will
be automatically interrupted, when preset tolerances
304R-8 MANUAL OF CONCRETE PRACTICE
Fig. 3.2 Correct and incorrect methods of batching
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-9
in any of the successive weighings exceed values
such as those given in Section 3.1.2. The charging
cycle will not begin when the hatcher discharge gate
is open, and the hatcher discharge cycle will not be-
gin when hatcher charging gates are open or when
any of the indicated material weights are not within
applicable tolerances. Presetting of desired batch
weights is done by such devices as punched cards,
digit switches or rotating dials and computers. Set-
ting of weights, starting the batch cycle, and dis-
charging the batch are all manually controlled. Mix
and batch-size selectors, aggregate moisture meters,
manually controlled fine aggregate moisture com-
pensators, and graphic or digital devices for record-
ing the batch weight of each material are
supplementary equipment that should be required
for good plant control.4,5
This type of batching system
provides greater accuracy for high speed production
than either the manual or semiautomatic systems. It
may have a single graphic recorder for each scale or a
series of scales may simultaneously record on a sin-
gle graphic chart. Also, the chart for each scale
should not be less than 4 in. (100 mm) wide and have
one line for each 2 percent of scale capacity, but not
more than 25 lines per in. (one line per millimeter).
The recorder reading should agree with the reading
shown on the scale within one gradation of the
recorder.
A digital recorder may have a single measuring
device for each scale or a series of measuring devices
may record on the same tape or ticket. This type of
recorder shall reproduce the reading of the scale
within 0.1 percent of the scale capacity or one incre-
ment of any volumetric batching device.
A digital batch documentation recorder should re-
cord information on each material in the mixture
along with the concrete mixture identification, size
of batch, and production facility identification. Re-
quired information may be preprinted, written, or
stamped on the document. The recorder should pro-
duce the number of documents needed and may
identify the load by a batch count number or a ticket
serial number. The recorder, if interlocked to an auto-
matic batching system, should show a single indica-
tion of all batching systems meeting zero or empty
balance interlocks.
Recorders should produce two or more tickets
with the data previously stated and space for the
identification of the job or project, location of place-
ment, sand moisture content, the delivery vehicle,
driver’s signature, purchaser’s representative’s sig-
nature, and the amount of water added at the project
site.
3.3.3.2 Individual automatic weigh batching -
This system provides separate scales and hatchers for
each aggregate size and for each other material
batched. The weighing cycle is started by a single
start switch, and individual hatchers are charged si-
multaneously. Interlocks for interrupting weighing
and discharge cycles when tolerances are exceeded;
mixture selectors; aggregate moisture meters and
compensators; and recorders differ only in detail
from those described for cumulative automatic
batching systems.
3.3.4 Volumetric batching - When aggregates or
cementitious materials are batched by volume the
method of batching is considered volumetric. It is
normally a continuous operation coupled with con-
tinuous mixing. Accurate volumetric batching is
achieved by passing material through a calibrated ro-
tary vane feeder, conveying material through a cali-
brated gate opening or by any other method that
would provide a known volume in a calibrated unit
time.
Volumetric batching is suitable for the production
of most concretes, provided the equipment is oper-
ated in accordance with ASTM C 685, and with the
same attention to detail as that required for weigh
batching. The available equipment is highly mobile,
requires little or no set-up time, and often serves as
its own material transport. In many cases it is
equipped with a continuous mixer (see Chapter 4,
and can be adjusted to change the mixture propor-
tions almost instantaneously.
3.3.4.1 Calibration - When recent experience
with a specific piece of equipment and the materials
to be used is not available, calibration of the equip-
ment is required. The calibration should be per-
formed in accordance with ASTM C 686 and the
recommendation of the manufacturer. The purpose of
this calibration is to provide the operator (and the
purchaser) with the necessary meter, gauge, revolu-
tion counter readings, and control settings needed to
produce the product desired.
3.3.4.2 Operation - As with any equipment op-
eration it is essential that personnel responsible for
control be knowledgeable in all phases of its use.
Operators must understand the ramifications of mak-
ing adjustments because any change in the system
could have an adverse affect on concrete quality. Ad-
ditionally, care should be exercised to insure that
ingredients used in production are the same, and in
the same state, as those used for calibration. The
equipment should be recalibrated when there is a
change in material source or condition, when there is
a change of operation, and/or when a significant
change in proportions is noted.
Because of the potential for variability, the mix
should be checked for air content, slump and yield at
least once per day of production or at intervals not
exceeding 100 cu yd (80 m3
) of production.
3.4-Cementitious materials
3.4.1 Batching - For high production requiring
rapid and accurate batching it is recommended that
bulk cementitious materials be weighed with auto-
matic, rather than semiautomatic or manual, equip-
ment. All equipment should provide access for
inspection and permit sampling at any time. The
304-10 MANUAL OF CONCRETE PRACTICE
bins and weigh hatchers should be equipped with
aeration devices and/or vibrators to aid in the smooth
and complete discharge of the batch. Return to zero
and weighing tolerance interlocks described in Sec-
tion 3.1.2 should be used. Cement should be batched
separately and kept separate from all ingredients be-
fore discharging. When both cement and pozzolan or
slag are to be batched, separate silos should be used.
However, they may be batched cumulatively, if the
cement is weighed first.
3.4.2 Discharging - Effective precautions should
be taken to prevent loss of cementitious materials
during mixer charging. At multiple-stop plants,
losses should be minimized by discharging the ce-
mentitious materials through a rubber drop chute. At
one-stop plants, cement and pozzolan can be suc-
cessfully charged along with the aggregate through
rubber telescopic dropchutes. For plant mixers, a
pipe should be used to discharge the cementitious
materials to a point near the center of the mixer after
the water and aggregates have started to enter the
mixer. Proper and consistent sequencing and blend-
ing of the various ingredients into the mixer during
the charging operation will contribute significantly
toward the maintenance of batch-to-batch uniformity
and perhaps reduced mixing time when confirmed
by mixer performance tests6,10
(see ASTM C 94).
3.5-Water measurement
3.5.1 Batching equipment - On large jobs and in
central batching and mixing plants where high pro-
duction is required, accurate water measurement can
only be obtained by the use of automatic weigh
hatchers or meters. Equipment and methods used
should, under all operating conditions, be capable of
routine measurement within the one percent toler-
ance specified in Section 3.1.2. Tanks or vertical cyl-
inders with center siphon discharge can be
permitted as an auxiliary part of the weighing, but
should not be used as the direct means of measure-
ment. For accurate measurement a digital gallon (li-
ter) meter should be used. Water glass measurement
is the least desirable. All equipment for water meas-
urement should be designed for easy calibration so
that accuracy of measurement can be quickly
verified.
3.5.2 Aggregate moisture determination and com-
pensation - Measurement of the correct total mixing
water depends on accurately knowing the quantity
and variation of moisture in the aggregate (particu-
larly in the sand) as it is batched. Aggregate which is
not saturated surface dry will absorb mix water from
the concrete, Sand moisture meters are frequently
used in plants, and when properly maintained do
satisfactorily indicate changes in sand moisture con-
tent. Moisture compensating equipment can also be
used which will, by a single setting, reproportion
water and fine aggregate weight; for a change in ag-
gregate moisture content. Compensators are usually
used on the sand, but occasionally they also are used
on the smallest coarse aggregate size fraction. The
moisture setting on the compensators is made manu-
ally with the calibrated dials, buttons, or levers pro-
vided. To date, the results obtained from moisture
meters have not been sufficiently accurate to warrant
interlocking them with compensators for automatic
operation. However, their individual use is recom-
mended, and when used in conjunction with regu-
larly performed conventional moisture control tests,
they can be useful tools for maintaining satisfactory
control of the mixing water content.
3.5.3 Total mixing water - Uniformity in the meas-
urement of total mixing water involves, in addition to
the accurate weighing of added water, control of such
additional water sources as mixer wash water, ice,
and free moisture in aggregates. One specified toler-
ance (ASTM C 94) for accuracy in measurement of
total mixing water, for all sources, is ±3 percent.
Use of admixtures in concrete is a universally ac-
cepted practice. Batching tolerances (Section 3.1.2)
and charging and discharge interlocks described pre-
viously for other mixture ingredients should also be
provided for admixtures. Batching and dispensing
equipment used should be readily capable of calibra-
tion. When timer activated dispensers are used for
large volume admixtures such as calcium chloride,
visual graduated check tubes should be used in con-
junction with the batching operation.
3.6-Measurement of admixtures
For additional information on recommended prac-
tices in the use and dispensing of admixtures in con-
crete, the reader is referred to the ACI 212.2R.
3.7-Measurement of materials for small jobs
If the concrete volume on a job is small, it may not
be practical to establish and maintain a batch plant
and mixer at the construction site. In such cases it
may be preferable to use ready mixed concrete or
mobile volumetric batching and continuous mixing
equipment. If neither is available, precautions must
be taken to properly measure and batch concrete ma-
terials mixed on the jobsite. Bags of cementitious ma-
terials should be protected from moisture and
fractional bags should not be used unless they are
weighed. The water measuring device should be ac-
curate and dependable, and the mixer capacity
should not be exceeded.
In addition to accurate measurement of materials,
correct operating procedures must also be used if
concrete uniformity is to be maintained. Care should
be taken to insure that the batched materials are
properly sequenced and blended so that they are
charged uniformly into the mixture.6,7
The batching
plant control room, if possible, should be arranged
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-11
with the plant operator’s station located in a position
where the operator can closely and clearly see the
scales and measuring devices during batching of the
concrete, as well as the charging, mixing, and dis-
charging of the mixes, without leaving his operating
console, Some common batching deficiencies to be
avoided are:
1. Overlapping of batches.
2. Loss of materials.
3. Loss or hanging up of a portion of one batch, or
its inclusion with another.
CHAPTER 4-MIXING AND TRANSPORTING
4.1 -General requirements
Thorough mixing is essential for the production of
uniform quality concrete. Therefore, equipment and
methods used should be capable of effectively mix-
ing concrete materials containing the largest spec-
ified aggregate to produce uniform mixtures of the
lowest slump practical for the work. Recommenda-
tions on maximum aggregate size and slump to be
used for various types of construction are given in
ACI 211.1 for concretes made with ASTM C150 and
C595 cements, and in ACI 223 for concretes made
with ASTM C845 expansive hydraulic cements. Suf-
ficient mixing as well as transporting and placing
capacity should be provided so that unfinished con-
crete lifts can be maintained plastic and free from
cold joints.
4.2-Mixing equipment
Mixers are either stationary parts of central mix
plants or portable equipment. Satisfactorily de-
signed mixers have a blade arrangement and drum
shape which insure an end-to-end exchange of mate-
rials parallel to the axis of rotation or a rolling, fold-
ing, and spreading movement of the batch over itself
as it is being mixed. For additional descriptions of
some of the various mixer types, refer to the "Con-
crete Plant Mixer Standards of the Mixer Manufac-
turers Division of the Concrete Plant Manufacturers
Bureau."11,67
The more common types of mixing equipment are:
4.2.1 Tilting drum mixer - This is a revolving
drum mixer that discharges by tilting the axis of the
drum. In the mixing mode, the drum axis can be
either horizontal or at an angle to the horizontal.
4.2.2 Non-tilting drum mixer - This is a revolving
drum mixer which is charged, mixes and discharges
with the axis of the drum horizontal.
4.2.3 Vertical shaft mixer - This is often called a
turbine or pan type mixer. Mixing is done with rotat-
ing blades or paddles, mounted on a vertical shaft, in
either a stationary pan or one rotating in the opposite
direction to the blades. The batch can be easily ob-
served and rapidly adjusted, if necessary. Rapid mix-
ing and low overall profile are other significant
advantages. This mixer does an excellent job of mix-
ing relatively dry concretes and is often used for lab-
oratory mixing and by concrete p r o d u c t s
manufacturers.
4.2.4 Puddle mixer - This mixer uses horizontal
blades and is suitable for harsh, stiff concrete mix-
tures. It is used primarily in the production of con-
crete block units.
4.2.5 Truck mixers - There are two types of revolv-
ing drum truck mixers in use today-rear discharge
and front discharge. The rear discharge, inclined axis
mixer predominates. Both utilize fins attached to the
drum to mix concrete in the mixing mode and the
same fins discharge the concrete when drum rotation
is reversed.
4.3-Central mixed concrete
Central mixed concrete is mixed completely in a
stationary mixer and then transferred to another
piece of equipment for delivery. This transporting
equipment can be a ready-mix truck operating as an
agitator or it may be an open top truck body with or
without an agitator. The tendency of concrete to seg-
regate limits the distance it may be hauled in equip-
ment not equipped with an agitator.
Sometimes the central mixer will partially mix the
concrete with the final mixing and transporting done
in a revolving drum truck mixer, This process is often
called “shrink-mixing” as it reduces the volume of
the “as charged” mixture. The total volume that a
truck can handle is limited to 63 percent of the drum
volume.
4.4-Truck mixed concrete
Truck mixing is a process by which previously
proportioned concrete materials from a batch plant
are charged into a ready-mix truck for mixing and
delivery to the construction project. To achieve thor-
ough mixing, total absolute volume of all ingredients
batched in a revolving drum truck mixer should not
exceed 63 percent of the drum volume.15
(see ASTM
C 94).
4.5-Charging and mixing
The method and sequence of charging mixers is of
great importance in determining whether the con-
crete will be properly mixed.
For central plant mixers, obtaining a preblending
or ribboning effect as the stream of materials flow
into the mixer is essential.6,7,10
In truck mixers all loading procedures must be de-
signed to avoid packing of the material, particularly
sand and cement, in the head of the drum during
charging, The probablity of packing is decreased by
304-R12 MANUAL OF CONCRETE PRACTICE
placing about 10 percent of the coarse aggregate and
water in the mixer drum before the sand and cement.
The handling of water deserves special attention.
Generally about one-fourth to one-third of the water
should be added to the discharge end of the drum
after all other ingredients have been charged. Water
charging pipes must be of proper design and of suffi-
cient size so that water enters at a point well inside
the mixer and charging is complete within the first
25 percent of the mixing time.10
Refer to Section
4.5.3.1 for additional discussion of mixing water.
Chemical admixtures should be charged to the
mixer at the same point in the mixing sequence
batch after batch. Liquid admixtures should be
charged with the water or on damp sand, and
powdered admixtures should be ribboned into the
mixer with other dry ingredients. When more than
one admixture is used, each should be batched sepa-
rately unless premixing is shown to be permissible
and they should be properly diluted before they en-
ter the mixer.
4.5.1 Central mixing-Procedures for charging
central mixers are less restrictive than those neces-
sary for truck mixers. This is because a revolving
drum central mixer is not charged as full as a truck
mixer and the blading and mixing action is quite
different. In a truck mixer there is very little folding
action compared to that in a stationary mixer. How-
ever, batch size should not exceed the manufacturers’
rated capacity as marked on the mixer name plate.
The mixing time required should be based upon
the ability of the mixer to produce uniform concrete
throughout the batch and from batch to batch. Manu-
facturers’ recommendations and usual specifica-
tions, such as 1 min for 1 cu yd (¾ m3
) plus ¼ min for
each additional cubic yard (cubic meter) of capacity
can be used as satisfactory guides for establishing
initial mixing time. However, final mixing times
used should be based on the results of mixer per-
formance tests made at frequent intervals throughout
the life of the job2,6,12
(see ASTM C 94 and CE-CRD-
CSS). The mixing time should be measured from the
time all ingredients are in the mixer. Batch timers
with audible indicators used in combination with
interlocks which prevent under or over mixing of the
batch and discharge prior to completion of a preset
mixing time should be provided on automatic plants
and are also desirable on manual plants. The mixer
should be designed for starting and stopping under
full load.
4.5.2 Truck mixing - Generally, 70 to 100 revolu-
tions at mixing speed are specified for truck mixing.
With optimum charging sequences many truck mix-
ers are able to produce uniformly mixed concrete in
30 to 40 revolutions.
ASTM C 94 limits the total number of revolutions
to a maximum of 300. This is to limit grinding soft
aggregates, loss of slump, wear on the mixer and
other undesirable effects on concrete in hot weather.
Final mixing may be done at the producer’s yard,
enroute to a project or, more commonly, it is done at
the project site.
If additional time elapses after mixing and before
discharge, the drum speed is reduced to the agitation
speed or stopped. Then prior to discharging, the
mixer should be operated at mixing speed for ap-
proximately 30 revolutions to enhance uniformity.
4.5.2.1 Extending transportation time - These
procedures are often called “dry batching” and were
evolved to accommodate long hauls and unavoidable
delays in placing by attempting to postpone the mix-
ing of cement with water. However, when cement and
damp aggregate come in contact with each other, free
moisture on the aggregate does result in some cement
hydration. Therefore, materials cannot be held in this
manner indefinitely.
In one method, the dry materials are batched into
the ready-mix truck and transported to the jobsite
where all of the mixing water is added. Water must be
added under pressure, preferably at both front and
rear of the drum with it revolving at mixing speed,
and then mixing is completed with the usual 70 to
100 revolutions. The total volume of concrete that
can be transported in truck mixers by this method is
the same as for regular truck mixing, 63 percent of
the drum vo1ume15
(see ASTM C 94).
4.5.3 Water
4.5.3.1 Mixing water - The water required for
proper concrete consistency (slump) is affected by
such things as amount and rate of mixing, length of
haul, time of unloading and ambient temperature
conditions. In cool weather or for short hauls and
prompt delivery, such problems as loss or variation
in slump, excessive mixing water requirements, and
discharging, handling and placing problems rarely
exist. However, the reverse is true when rate of deliv-
ery is slow or irregular, haul distances are long and
weather is warm. Loss of workability during warm
weather can be minimized by expediting delivery
and placement and by controlling the concrete tem-
perature. It may also be desirable to use a retarder to
prolong the time the concrete will respond to vibra-
tion after is is placed. When feasible all mixing water
should be batched at the central plant. However, in
hot weather it is desirable to withhold some of the
mixing water until the mixer arrives at the job. Then
with the remaining required water added, an addi-
tional 30 revolutions at mixing speed is required to
adequately incorporate the additional water into the
mixture, When loss of slump or workability cannot
be offset by these measures, the procedures de-
scribed in Section 4.5.2.1 may also be considered.
4.5.3.2 Addition of water on the job - The max-
imum water-cement ratio should never be exceeded.
If all the water allowed by the specification has not
been added at the start of mixing it may be permissi-
ble to add the remaining allowable water at the point
of delivery. It should be noted that once part of a
batch has been unloaded, it becomes impractical to
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-13
determine what water-cement ratio is produced by
additional water.
The production of concrete of excessive slump or
adding water in excess of the proportioned water-
cement ratio to compensate for slump loss resulting
from delays in delivery or placing should be prohib-
ited. Persistent requests for the addition of water
should be investigated.
Where permitted a high-range water-reducer (su-
perplasticizer) can be added to the concrete to in-
crease slump while maintaining a low water-cement
ratio.13,14
Addition may be made by the concrete sup-
plier or the contractor by a variety of techniques.
When this admixture is used, vibration for consol-
idation may be reduced. However, in walls and slop-
ing formed concrete some vibration is necessary to
remove air trapped in the form. This admixture may
also increase form pressure.
4.5.3.3 Wash water - Most producers find it nec-
essary to rinse off the rear fins between loads with
the entire mixer washed and discharged only at the
end of the day. Hot weather and unusual mix designs
may require washing and discharge of wash water
after every load. Rinse water must not be allowed to
remain in the mixer unless it can be accurately com-
pensated for in the succeeding batch. Pollution con-
trol regulations make it increasingly difficult to wash
out after every load and have created an interest in
systems to reclaim and reuse both wash water and
returned concrete aggregates.
ASTM C 94 describes the reuse of wash water
based on prescribed tests. Particular attention is nec-
essary when admixtures are being used because the
required dosages may change dramatically. When
wash water is used, admixtures should be batched
into a limited quantity of clean water or onto damp
sand.
4.6-Mix temperature
Batch-to-batch uniformity of concrete from a
mixer, particularly with regard to slump, water re-
quirement, and air content, also depends on the uni-
formity of the concrete temperature. It is, therefore,
important that maximum and minimum concrete
temperatures be controlled throughout all seasons of
the year. Recommendations on control of concrete
temperatures are discussed in detail in ACI 305R and
306R.
Mixers must be capable of discharging concrete of
the lowest slump suitable for the structure being con-
structed without segregation (separation of coarse ag-
gregate from the mortar). Prior to discharge of
concrete transported in truck mixers, the drum
should again be rotated at mixing speed for about 30
revolutions to reblend possible stagnant spots near
the discharge end into the batch (see Fig. 5.1a and b).
4.8-Mixer performance
The performance of mixers is usually determined
by a series of uniformity tests made on samples taken
from two or three locations within the concrete batch
after it has been mixed for a given time period2,12
(see
ASTM C 94 and CE-CRD-C55). Mixer performance
requirements are based on allowable differences in
test results of samples from any two locations or be-
tween individual locations and the average of all lo-
cations. The NRMCA has a description of these
procedures and is an excellent reference.10,12
Among the many tests used to check mixer per-
formance, the following are the most common: air
content, slump, unit weight of air-free mortar, coarse
aggregate content and compressive strength.
Another important aspect of mixer performance is
batch-to-batch uniformity of the concrete which is
also affected by the uniformity of materials and their
measurement as well as by the efficiency of the
mixer. Visual observation of the concrete during mix-
ing and discharge from the mixer is an important aid
in maintaining a uniform mixture, particularly uni-
form consistency. Some recording consistency
meters, such as those operating from the amperage
draw on the electric motor drives for revolving drum
mixers, have also proved to be useful. However, the
most positive control method for maintaining batch-
to-batch uniformity is a regularly scheduled program
of tests of the fresh concrete including unit weight,
air content, slump, and temperature. Although
strength tests provide an excellent measure of the
efficiency of the quality control procedures that are
employed, the strength test results are available too
late to be of practical use in controlling day to day
production.
Mixers should be properly maintained to prevent
mortar and dry material leakage. Inner mixer sur-
faces should be kept clean and worn blades replaced.
Mixers not meeting the performance tests referenced
in Section 4.8 should be taken out of service until
necessary maintenance and repair results in correc-
tion of their deficient performance.
4.10-General considerations for transporting
concrete
4.10.1 General - Concrete can be transported by a
variety of methods and equipment, such as truck
mixers, open top truck bodies with and without agi-
tators, buckets hauled by truck or railroad car, by
pipeline, hose or conveyor belts. The method of
transportation used should efficiently deliver the
concrete to the point of placement without signifi-
cantly altering its desired properties with regard to
water-cement ratio, slump, air content and homoge-
neity. Each method of transportation has advantages
under particular conditions such as: mixture ingre-
304R-14 MANUAL OF CONCRETE PRACTICE
dients and proportions, type and accessibility of
placement, required delivery capacity, location of
batch plant, weather conditions, and others. These
various conditions should be carefully reviewed in
selecting the type of transportation best suited for
economically obtaining quality concrete in place.
4.10.2 Revolving drum - By this method, the truck
mixer previously described serves as an agitating
transportation unit. The drum is rotated at charging
speed during loading and is reduced to agitating
speed or stopped after loading is complete. The
elapsed time before discharging the concrete can be
the same as for truck mixing and the volume carried
may be increased to 80 percent of the drum capacity
(see ASTM C 94).
4.10.3 Truck body with and without an agitator -
Units used in this form of transportation usually
consist of an open-top body mounted on a truck,
although bottom dump trucks have been used suc-
cessfully. The metal body should have smooth
streamlined contact surfaces and is usually designed
for discharge of the concrete at the rear when the
body is tilted. A discharge gate and vibrators
mounted on the body should be provided at the
point of discharge for control of flow. An agitator aids
in the discharge and ribbon blends the concrete as it
is unloaded. Water should never be added to con-
crete in the truck body because no mixing is per-
formed by the agitator.
Use of protective covers for truck bodies during
periods of inclement weather, proper cleaning of all
contact surfaces, and smooth haul roads contribute
significantly to the quality and operational effi-
ciency of this form of transportation. The maximum
delivery time usually specified is 30 to 45 min, al-
though weather conditions may require shorter, or
permit longer, times.
4.10.4 Concrete buckets on trucks or railroad
cars - This is a common method of transportation of
mass concrete from the batch plant to a location close
to the placement area. A crane then lifts the bucket to
the final point of placement. Occasionally transfer
cars operating on railroad tracks are used to transport
the concrete from the batch plant to buckets operat-
ing from cableways. Discharge of the concrete from
the transfer cars into the bucket, which may be from
the bottom or by some form of tilting, must be closely
controlled to prevent segregation. Delivery time for
bucket transportation is the same as for other non-
agitating units; usually 30 to 45 min.
4.10.5 Other methods - Transportation of concrete
by pumping methods and by belt conveyors will be
discussed in Chapters 9 and 10, respectively. Heli-
copter deliveries have been used in difficult to reach
areas, where other transporting equipment could not
be used. This system usually employs one of the
other methods to transport the concrete to the heli-
copter which then lifts the concrete in a lightweight
bucket to the area of placement.
CHAPTER 5-PLACING CONCRETE
5.1 -General considerations
Chapter 4 described some equipment and pro-
cedures for transporting concrete from the batching
or batching and mixing plant to the placing site. This
chapter presents guides for transferring concrete
from the transporting equipment to its final position
in the structure under construction.
Placement of concrete is accomplished with buck-
ets, hoppers, manual or motor propelled buggies,
chutes and drop pipes, conveyor belts, pumps, trem-
ies, and paving equipment. Figure 5.1 shows a
number of handling and placing methods discussed
in this chapter and gives examples of both satisfac-
tory and unsatisfactory construction procedures.
Placement of concrete by the preplaced aggregate
method and by pumps and conveyors are discussed
in Chapters 7, 9, and 10 respectively, In addition,
placing methods peculiar to underwater, heavy-
weight, and lightweight concreting are noted in
Chapters 8, 11, and 12 respectively. Another effective
placement technique for both mortar and concrete is
the shotcrete process in which thin layers are applied
pneumatically where forming is inconvenient or im-
practical, access or location provides difficulties or
normal casting techniques cannot be employed (see
ACI 506).
5.2-Planning
A basic requirement in all concrete handling is
that both quality and uniformity of the concrete, in
terms of water-cement ratio, slump, air content, and
homogeneity, must be preserved. The selection of
handling equipment should be based on its ca-
pability to efficiently handle concrete of the most
advantageous proportions that can be readily consol-
idated in place with vibration. Equipment which re-
quires adjustment in mixture proportions beyond
ranges recommended by ACI 211.1 should not be
used.
Advance planning should assure producing an
adequate and consistent supply of concrete. Suffici-
ent placing capacity should be provided so that the
concrete can be kept plastic and free of cold joints
while it is being placed. All equipment for placing
should be clean and in proper repair. The placing
equipment should be arranged to deliver the con-
crete to its final position without objectionable segre-
gation. The equipment should be adequately and
properly arranged so that placing may proceed with-
out undue delays and manpower should be suffi-
cient to assure the proper placing, consolidating, and
finishing of the concrete. If the concrete is to be
placed at night, the lighting system should be suffi-
cient to illuminate the inside of the forms and to
provide a safe work place.
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-15
Fig. 5.1 Correct and incorrect methods of handling concrete
304R-16 MANUAL OF CONCRETE PRACTICE
Concrete placement should not be started when
there is a probability of freezing temperatures occur-
ring, unless adequate facilities for cold weather pro-
tection have been provided (see ACI 306R). Facilities
for prompt commencement of curing or for the ap-
plication of sealing compound should be in read-
iness for use at the proper time (see ACI 308). Where
practical, it is advantageous to have radio or tele-
phone communications between the site of major
placements and the batching and mixing plant to
better control delivery schedules and prevent exces-
sive delays and waste of concrete.
It is advisable that the concrete be delivered to the
site at a uniform rate compatible with the manpower
and equipment being used in the placing and finish-
ing processes. Where an interruption in the concret-
ing process could be a problem, consideration
should be given to the provision of backup
equipment.
A final detailed inspection of the foundation, con-
struction joints, forms, water stops, reinforcement
and other items of the placement should be made
immediately before the concrete is placed. A method
of documenting such inspection should be devel-
oped and approved by all parties prior to the start of
work. All of these features should be carefully exam-
ined to make sure they are in accordance with the
drawings, specifications and good practice.
5.3-Reinforcement and embedded items
At the time of concrete placement, reinforcing
steel and embedded items should be clean and free
from mud, oil and other coatings that may adversely
affect bonding capacity. Most reinforcing steel is cov-
ered with either mill scale or rust of some severity
and such coatings are considered satisfactory pro-
vided that loose rust and mill scale are removed and
that the minimum dimensions of the steel are not
less than required in ACI 318.
Care should be taken to ensure that all reinforcing
steel is of the proper size and length and that it is
placed in the correct position and spliced in accor-
dance with the plans. Adequate concrete cover of the
reinforcing steel must be maintained.
Mortar coating on embedded items within a lift to
be completed within a few hours need not be re-
moved, but loose dried mortar on embedded items
projecting into future lifts should be removed prior
to placing those lifts.
The method of holding waterstop in the forms
should ensure that it cannot bend to form cavities
during concreting.
Bars and embedded items should be held securely
in the proper position by suitable supports and ties
to prevent displacement during concreting. Concrete
blocks are sometimes used for support of the steel.
Metal bar chairs with or without plastic protected
ends or plastic bar chairs are more commonly used.
Whatever system is used, there must be assurance
that the supports will be adequate to carry expected
loads before and during placement and will not stain
exposed concrete surfaces, displace excessive quan-
tities of concrete, nor allow bars to move from their
proper positions.16
In some cases when reinforced concrete is being
placed, it may be advantageous to have a competent
person in attendance to adjust and correct the posi-
tion of any reinforcement which may be displaced.
Structural engineers should identify critical areas
where such additional supervision would be
advantageous.
5.4-Placing
5.4.1 Precautions - Equipment should be arranged
so that the concrete has an unrestricted vertical drop
to the point of the placement or into the container
receiving it. The stream of concrete should not be
separated by permitting it to fall freely over rods,
spacers, reinforcement or other embedded materials.
If forms are sufficiently open and clear so that the
concrete is not disturbed in a vertical fall into place,
direct discharge without the use of hoppers, trunks
or chutes is usually desirable. Concrete should be
deposited at or near its final position in the place-
ment because it has a tendency to segregate when it
has to be flowed laterally into place.
If monolithic placement of a deep beam, wall, or
column with a slab or soffit above is desired, a delay
should be scheduled to permit settlement of the deep
concrete before the slab or soffit concrete is placed.
The length of delay will depend upon the tem-
perature and setting characteristics of the concrete
used (usually about 1 hr), but concreting should be-
gin soon enough to permit a knitting of the new layer
with the old layer by vibration.
5.4.2 Equipment - When choosing placing equip-
ment consideration must be given to the ability of the
equipment to place the concrete in the correct loca-
tion economically and without altering its quality.
The selection of equipment is influenced by the
method of concrete production. Certain types of
equipment such as buckets, hoppers, buggies, etc.
will suit batch production while other equipment
such as belt conveyors and pumps are more suitable
for continuous production.
5.4.2.1 Buckets and hoppers - The use of prop-
erly designed bottom dump buckets permits the
placement of concrete at the lowest practical slump
consistent with consolidation by vibration. The
bucket should be self-cleaning upon discharge and
concrete flow should start upon opening of the dis-
charge gate. Discharge gates should have a clear
opening equal to at least fives times the maximum
aggregate size being used. Side slopes should be at
least 60 deg from the horizontal.
Control of the bucket and its gate opening should
be done in such a manner as to ensure a steady
stream of concrete discharged against previously
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-17
Fig. 5.4 (a-d) Correct and incorrect methods of placing concrete
MANUAL OF CONCRETE PRACTICE
Fig. 5.4 (e-h) Correct and incorrect methods of placing concrete
MEASURING, MIXING, TRANSPORTlNG, AND PLACING 304R-19
placed concrete where possible. Stacking concrete by
discharging the bucket too close to the lift surface
and discharging buckets while traveling are common
causes of segregation.
In order to prevent contamination, spilled concrete
should not be shoveled back into buckets or hoppers
for subsequent use, and freshly finished concrete
should be protected by not swinging buckets directly
over it.
To expedite the placing schedule the use of two
buckets or more per crane is recommended.
5.4.2.2. Manual or motor propelled buggies-
Buggies should run on smooth rigid runways inde-
pendently supported and set well above reinforcing
steel. Concrete being transferred by buggies tends to
segregate during motion and planking should be but-
ted rather than lapped to maintain a smooth surface
to prevent separation of concrete materials in transit.
The recommended maximum horizontal delivery
distance to transfer concrete by manual buggies is
200 ft (60 m) and for power buggies 1000 ft (300 m),
Manual buggies range in capacity from 6 to 8 cu ft
(0.2 m3
) with placing capacity averaging from 3 to 5
cu yd (2 to 4 m3
) per hour. Power buggies are avail-
able in sizes from 9 to 12 cu ft (0.3 m3
) with placing
capacity ranging from 15 to 20 cu yd (11 to 15 m3
) per
hour depending upon the distance traveled.
5.4.2.3 Chutes and drop chutes - Chutes are fre-
quently used for transferring concrete from upper to
lower elevations. They should have rounded corners,
be constructed of metal or be metal lined, and should
have sufficient capacity to avoid overflow. The slope
should be constant and steep enough to permit con-
crete of the slump required to flow continuously
down the chute without segregation.
The flow of the concrete at the end of a chute
should be controlled to prevent segregation.
Drop chutes are circular pipes used for transferring
concrete vertically from higher to lower elevations.
The pipe should have a diameter of at least eight
times the maximum aggregate size at the top 6 to 8 ft
(2 to 3 m) of the chute, but may be tapered to approx-
imately six times the maximum aggregate size below.
It should be plumb, secure, and positioned so that
the concrete will drop vertically.
Plastic or rubber drop chutes or tremies may be
used and may be shortened by cutting them in lieu of
raising as the placement progresses. With the use of
plastic drop chutes care should be taken to ensure
that such chutes do not fold over or kink.
5.4.2.4 Paving equipment - The use of large
mixers, high capacity spreaders, and slipform pavers
has made it possible to place large volumes of con-
crete pavement at a rapid rate. Most of the same prin-
ciples of quality control are required for successful
paving as in other forms of concrete placement. Due
to the speed of placement, routine inspection pro-
cedures need to be more frequent so that detected
deviations from acceptable quality can be corrected.
Some of the more frequent problems which can
detrimentally affect the desired quality of the con-
crete in paving are also common in other types of
placement; namely, poor batch-to-batch mixing uni-
formity, variation in slump and air content, and im-
proper distribution of the mortar in aggregate
throughout the placement.
Placing of concrete with paving equipment is cov-
ered in ACI 316.
5.4.2.5 Slipforming - By this method concrete is
placed in prefabricated forms which are slipped past
the point of placement as soon as the concrete has
gained dimensional stability and rigidity to retain its
design shape.
Careful, consistent concrete control with suitable
mixture adjustments for changing ambient tem-
peratures are required.
5.5-Consolidation
Internal vibration is the most effective method of
consolidating plastic concrete for most applications.
The effectiveness of an internal vibrator depends
mainly upon the head diameter, frequency and am-
plitude. Detailed recommendations for equipment
and procedures for consolidation are given in ACI
309.
Vibrators should not be used to move concrete lat-
erally. They should be inserted and withdrawn ver-
tically at close intervals, using a systematic pattern of
vibration to ensure that all concrete has been ade-
quately consolidated.
As long as a running vibrator will sink into the
concrete by its own weight, it is not too late for the
concrete to benefit from revibration which should
improve compressive and bond strengths. There is no
evidence of detrimental effects either to embedded
reinforcement or to concrete in partially hardened
lifts when they are revibrated by consolidation
efforts on fresh concrete above.
In unusually difficult and obstructed placements
supplemental form vibration may be used. In these
circumstances care should be taken to avoid exces-
sive operation of the vibration units which would
cause a weak paste surface layer.
On vertical surfaces where air void holes are objec-
tionable, experience has shown that the voids can be
reduced by using additional vibration. However, ex-
tra vibration, spading or mechanical manipulation of
concrete will not consistently remove air void holes
from surfaces molded under sloping forms.
The use of experienced and competent vibrator op-
erators working with well-maintained vibrators and
with a sufficient supply of standby units are essen-
tial to satisfactory and successful consolidation of
fresh concrete.
5.6-Mass concreting
The equipment and method used for placing mass
concrete should avoid separation of coarse aggregate
304R-20 MANUAL OF CONCRETE PRACTICE
Fig. 5.5 Correct and incorrect methods of consolidation
MEASURING, MIXING, TRANSPORTlNG, AND PLACING 304R-21
from the concrete. Although scattered pieces of
coarse aggregate are not objectionable, clusters and
pockets of coarse aggregate are objectionable and
must be scattered prior to placing concrete over
them. Segregated aggregate will not be eliminated by
subsequent placing and consolidation operations.
are to be placed upon them. Fluid pressure on forms
should be correlated to the capacity and type of plac-
ing equipment, the planned rate of placing concrete,
the slump, temperature and stiffening characteristics
of the concrete.
Concrete should be placed in horizontal layers not
exceeding 2 ft (610 mm) in depth and inclined layers
and cold joints should be avoided. For monolithic
construction each concrete layer should be placed
while the underlying layer is still responsive to
vibration, and layers should be sufficiently shallow
to permit the two layers to be knitted by proper
vibration.
The step method of placement should be used in
massive structures where large areas are involved in
order to minimize the occurrence of cold joints. In
this method the lift is built up in a series of horizon-
tal stepped layers 12 to 18 in. (300 to 450 mm) thick.
Concrete placing on each layer extends for the full
width of the block, and the placing operations pro-
gress from one end of the lift towards the other, ex-
posing only small areas of concrete at a time. As the
placement progresses, part of the lift will be com-
pleted while concreting continues on the remainder.
For a more complete discussion of mass concrete
and the necessary thermal considerations see ACI
207.1R.
CHAPTER 6-FORMS, JOINT PREPARATION,
AND FINISHING
Form panel joints, corners, connections, and
seams should be mortar tight. Consolidation will liq-
uefy the mortar in concrete, allowing it to leak from
any openings in the formwork, leaving voids, sand
streaks, or rock pockets. When forms are set for suc-
ceeding lifts, bulges and offsets at horizontal joints
can be avoided by resetting forms with only 1 in, (25
mm) of sheathing overlapping the concrete below the
line made by the grade strip from the previous lift
and by securely tying and bolting the forms close to
the joint. Rustification strips (formed grooves) can
also be used to obscure construction joints and im-
prove appearance when they are well arranged.2
The
form ties used should result in the minimum prac-
tical hole size and their design should permit re-
moval without spalling surrounding concrete.
Leakage of mortar around ties should be prevented,
and filling of cone holes or other holes left by form
ties should be done in a manner which results in a
secure, sound, nonshrinking, inconspicuous patch2
(see ACI 311). Prior to concreting, forms should be
protected from deterioration, weather, and shrinkage
by proper oiling or by effective wetting. Form sur-
faces should be clean and of uniform texture, and
when reuse is permitted, they should be carefully
cleaned, oiled, and reconditioned if necessary.
6.1 -Forms
Forms are the molds into which concrete is placed
and falsework is the structural support and the nec-
essary bracing required for temporary support during
construction. Formwork is the total system of sup-
port for freshly placed concrete, including forms and
falsework. Formwork design should be established
prior to erection, and shop drawings containing con-
struction details, sequence of concrete placing and
loading values used in the design should be ap-
proved before commencement of construction. Shop
drawings should be available on site during form-
work erection and when placing the concrete.
Steel forms should be thoroughly cleaned but
never sandblasted nor abraded to bright metal. If
“peeling” of concrete is encountered when using
steel forms, leaving the cleaned, oiled forms in the
sun for a day, vigorously rubbing the affected areas
with liquid paraffin, or applying a thin coating of
lacquer will usually eliminate the problem, Some-
times peeling is the result of abrasion of certain form
areas from impact during placement. Improvement
can be made by temporarily protecting form areas
subject to abrasion with plywood or metal sheets.
Design and construction of concrete forms should
comply with ACI 347. The design and construction
of concrete formwork should be reviewed to mini-
mize costs without sacrificing either safety or qual-
ity. Because workmanship in concrete construction
is frequently judged by the appearance of the con-
crete after removal of the forms, proper performance
of formwork while bearing the plastic concrete
weight and live construction loading is of vital
importance.
Form faces should be treated with a releasing agent
to prevent concrete sticking to the forms and thereby
aid in stripping. The releasing agent may also act as a
sealer or protective coating for the forms to prevent
absorption of water from the concrete into the form-
work. Form coatings must be carefully chosen for
compatibility with the contact surfaces of the forms
being used and with subsequent coatings to be ap-
plied to the concrete surfaces. Form coatings that are
satisfactory on wood are not always suitable for steel
forms, e.g., steel forms would require a coating
which acts primarily as a releasing agent, while
plywood will benefit from a coating that also seals
the forms against moisture penetration.
Forms should be built with sufficient strength and Ample access should be provided within the
rigidity to carry the mass and fluid pressure of con- forms for proper cleanup, placement, consolidation
crete and of the materials, equipment or runways that and inspection of the concrete.
304R-22 MANUAL OF CONCRETE PRACTICE
For the sake of appearance, it is important that
proper attention be paid to the mark made by a con-
struction joint on exposed formed surfaces of con-
crete. Irregular construction joints should not be
permitted. A straight line, preferably horizontal,
should be obtained by filling forms to a grade strip.
Rustication strips, either a vee or a beveled rec-
tangular strip, can be used as a grade strip and to
form a groove at the construction joint when
appropriate.
6.2-Joint preparation
Construction joints occur wherever concreting is
stopped or delayed so that fresh concrete subse-
quently placed against hardened concrete cannot be
knitted to the previous placement. Horizontal con-
struction joints will occur at the levels between lifts
while vertical joints occur where the structure is of
such length that it is not feasible to place the entire
length in one continuous operation. In general, the
preparation of a vertical construction joint for ac-
ceptable performance and appearance is the same as
for horizontal joints.
The surfaces of all construction joints should be
cleaned and properly prepared so as to assure ade-
quate bond with concrete placed on it or adjacent to
it and to obtain required watertightness.2,17,18
Several
methods of cleanup are available depending on the
size of the area to be cleaned, age of the concrete,
skill of workmen, and availability of equipment. It is
not difficult to obtain a satisfactory joint when high
quality low-slump concrete has been properly
placed. Removal of sound mortar or concrete to ex-
pose coarse aggregate or to create roughness is not
justified. For most construction joints, it is necessary
only to remove laitance and expose the sand and
sound surface mortar.
When large quantities of bleed water and fines are
brought to the construction joint surface, concrete at
the surface will be so inferior that obtaining adequate
cleanup is difficult. This problem is compounded
when high-slump concrete is used. In such cases,
green cutting, sand blasting, or high-pressure water
jets will be required to correctly prepare the joint.
Green cutting is the removal of all laitance and
inferior surface concrete by means of a strong jet of
water or air-water at approximately 100 psi (0.7 MPa).
It must not be started until the concrete has hardened
sufficiently to prevent the jet from ravelling the sur-
face below the desired depth. Care must be taken to
see that the cutting is done at the proper time, not too
early so as to avoid too much cutting, and not too late
in order to obtain sufficient removal of the surface
laitance. Green cutting is usually performed 4 to 12
hours after placement and can be successfully used
where the quality of the concrete at the joint is good.
Sandblasting is used to prepare the surface of the
construction joint after the concrete has hardened
and preferably just before forms are erected for the
next placement.2,17,18
Wet sandblasting is usually pre-
ferred due to the objectionable dust associated with
the dry process. This method produces excellent re-
sults on horizontal joint surfaces, particularly on
those placed with 2 in. (50 mm) (or less) slump con-
crete using internal vibrators.
Another method for cleaning construction joints
utilizes a water jet under a minimum pressure of
6,000 psi (40 MPa). As with the sandblast method,
cleanup is delayed until the concrete is sufficiently
hard so that only the surface skin of mortar is re-
moved and no undercutting of coarse aggregate parti-
cles occurs.
Cloudy pools of water which will leave a weak film
on the surface when they dry should be removed by
thorough washing after the main cleanup operation
is completed. Cleaned joint surfaces should be con-
tinuously moist cured until the next concrete place-
ment or until the specified time of curing has been
fulfilled. Before placing new concrete at the joint, the
surface should be restored to the clean condition ex-
isting immediately following initial cleanup. If the
surface has been properly cured, very little final
cleaning will be necessary prior to placement.
Hand tools such as wire brushes, wire brooms,
hand picks, or bush-hammers may be used to remove
dirt, laitance, and soft mortar but are only practical
for small areas.
Retarding agents may be used to treat concrete sur-
faces after the finishing operations and before the
concrete has set. Manufacturer’s instructions for ap-
plication and coverage rate should be followed. Sub-
sequent removal of the unhardened surface mortar is
completed with other cleanup methods such as
water jets, air-water jets, or hand tools. Concrete sur-
faces treated with retarder should be cleaned as soon
as practical after initial set, the longer the delay, the
less retarded surface layer will be removed.
The clean concrete joint surface should be satu-
rated, surface dry at the time new concrete is placed
on it. Surface moisture weakens the joint by increas-
ing the water-cement ratio of the newly placed con-
crete. Care must be taken to ensure that the first layer
of concrete on the construction joint is adequately
consolidated for good bond.
6.3-Finishing unformed surfaces
To obtain a durable surface on unformed concrete,
proper procedures must be carefully followed, The
concrete used should be of the lowest practical
slump that can be properly consolidated, preferably
by means of internal vibration. Following consolida-
tion, the operations of screeding, floating, and first
troweling should be performed in such a manner that
the concrete will be worked and manipulated as little
as possible in obtaining the desired result. Over-
manipulation brings excessive fines and water to the
top which impairs the quality of the finished surface
causing such undesirable effects as checking, craz-
ing, and dusting. For the same reason, each step in
the finishing operation, from the first floating to the
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-23
final floating or troweling, should be delayed as long
as possible while still permitting the desired grade
and surface smoothness to be obtained. Free water is
not as likely to appear and accumulate between fin-
ishing operations if proper mixture proportions and
consistency are used. However, if free water does ac-
cumulate, it should be removed by blotting with
mats, draining, or pulling off with a loop of hose, so
the surface loses its water sheen before the next fin-
ishing operation is performed. Under no circum-
stances should any finishing tool be used in an area
before accumulated water has been removed, nor
should neat cement or mixtures of sand and cement
be worked into the surface to dry such areas.
It is possible to obtain satisfactory results from cor-
rectly designed mortar topping placed on a n d
worked into base concrete before the base concrete
sets, The mortar consistency, consolidation, and fin-
ishing should be as described above. However, a con-
crete of correct proportions, consistency, and texture
placed and finished monolithically with the base
concrete is preferable to a mortar topping.
For a detailed discussion and recommendations on
concrete floor and slab finishing, see ACI 302.lR.
Several special floor finishes which are installed
over hardened concrete surfaces, such as terrazzo,
require special techniques and are not covered in this
guide.
CHAPTER 7-PREPLACED AGGREGATE
STRUCTURAL AND MASS CONCRETE
7.1 - General considerations
In this method of construction, forms are first
filled with clean coarse aggregate. The voids in this
coarse aggregate are then filled with structural qual-
ity grout to produce preplaced aggregate (PA) con-
crete. This type of concrete is particularly useful
where concrete is to be placed under water, where
structures are heavily reinforced for seismic or other
reasons, where structural concrete or masonry is to
be repaired, or where concrete of low volume change
is required.2,19,20,21,22,23
(see CE EM-1110-2-2000).
Preplaced aggregate concrete differs from conven-
tionally placed concrete in that it contains a higher
percentage of coarse aggregate; consequently, the
properties of the coarse aggregate appear to have a
greater effect on the properties of the concrete. For
example, the modulus of elasticity is slightly higher
than that of conventional concrete. Also, because of
point-to-point contact of the coarse aggregate, drying
shrinkage is about one-half the magnitude of that in
conventionally placed concrete.23,24
However, struc-
tural design for PA concrete is the same as for con-
ventionally placed concrete2
(see CE EM-1110-2-
2000).
Structural formwork is usually more expensive
than that required for conventionally placed con-
crete because greater care is needed to prevent grout
leaks. However, in underwater construction, higher
placing rates at lower cost have been achieved by this
method than by conventional placing methods.
Since PA concrete construction is specialized in
nature, it is advisable that the work be undertaken by
qualified personnel experienced in this method of
construction.
7.2.1 Cement - Grout can be made with any one of
the non-air-entraining types of cement that complies
with ASTM C 150 or ASTM C 595. Use of air en-
trained cements combined with gas-forming fluid-
ifiers could result in excessive quantities of
entrained air in the mortar resulting in reduced
strengths. When air-entrainment is required to an ex-
tent higher than that provided by the gas-forming
fluidifier, air-entraining agent should be added
separately.
7.2.2 Coarse aggregate - Coarse aggregate should
be washed, free of surface dust and fines, in confor-
mance with the requirements of ASTM C 33, except
as to grading.
The void content of the aggregate should be as low
as possible and is usually attained when the coarse
aggregate is graded uniformly from the smallest al-
lowable particle size to the largest size.22
Void con-
tent will range from approximately 35 percent for
well-graded aggregate between ¾ in. (19 mm) and 6
to 8 in. (150 to 200 mm) to as high as 50 percent for
single-sized aggregate. Void contents as low as 25
percent have been attained experimentally by delib-
erate gap grading.
Gradings 1 or 2, Table 7.2, are recommended for
general use. Where reinforcement is crowded or the
placement is in relatively shallow patches, up to 10
percent passing the ½ in. (12.5 mm) sieve with not
more than 2 percent passing the 3
/8 in. (9.5 mm) sieve
(Grading 1) may be used. Where special circum-
stances dictate the use of coarser sand, Grading 3 is
acceptable.
7.2.3 Fine aggregate - Sand should conform to
ASTM C 33 except that grading should be as shown
in Table 7.2. Fine aggregate that does not fall within
these grading limits is useable provided results fall
within the requirements of Section 7.3.
7.2.4 Pozzolan - Pozzolans conforming to ASTM C
618, Class N or F, may be used. Class F has been used
in the great majority of installations since it improves
pumpability of the fluid grout and extends grout han-
dling time. Data from Class C fly ash use and testing
are lacking.
7.2.5 Admixtures
7.2.5.1 Grout fluidifier - This admixture is com-
monly used to offset the effects of bleeding, to reduce
the water-cementitous materials (cement plus
pozzolan) ratio for a given fluidity, and to retard stiff-
ening. It normally consists of a water-reducing agent,
304R-24 MANUAL OF CONCRETE PRACTICE
TABLE 7.2-GRADATION LIMITS FOR COARSE AND FINE AGGREGATES
FOR PREPLACED AGGREGATE CONCRETE
a suspending agent, aluminum powder, and a chem-
ical buffer to assure properly timed reaction of the
aluminum powder with alkalies in portland cement.
Normal dosage of grout fluidifier is 1 percent by
weight of the total cementitous material in the grout
mixture.
7.2.5.2 Calcium chloride - A small quantity
may be desirable to promote early strength develop-
ment. However, calcium chloride in excess of 1 per-
cent, by weight of cementitious materials, will
depress the expansive action of the aluminum
powder, Pretesting for expansion, bleeding, rate of
hardening, and strength in PA concrete cylinders is
recommended (see ASTM C 953).
7.3-Grout mix proportioning
7.3.1 Cementitious materials - Usually, the pro-
portion of portland cement to pozzolan is in the
range of 2.5:1 to 3.5:1 by weight. Ratios as low as
1.3:1 (equal bulk volumes) for lean mass concrete
and as high as 12:1 for extra high strength have been
used. The water to cementitious materials ratio will
normally range from 0.42 to 0.50.
7.3.2 Fine aggregate - Compressive strength,
pumpability21,22
and void penetrability requirements
control the amount of fine aggregate that can be used
in the grout. For structural grade PA concrete, the
ratio of cementitious material to sand will usually be
in the ratio of 1:1, by weight. For massive placements
where the minimum size of coarse aggregate is ¾ in.
(19 mm), the ratio may be increased to 1:1.5, With
Grading 3, the ratio may be further increased to ap-
proximately 1:3.
7.3.3 Proportioning requirements - Materials
should be proportioned in accordance with ASTM C
938 to produce a grout of required consistency that
will provide the strength of PA concrete cylinders
specified in ASTM C 943. For optimum results,
bleeding should be less than the total expansion.
7.3.4 Consistency of grout - The flow cone de-
scribed in ASTM C 939 is used to determine consis-
tency when using fine aggregate from Grading 1 and
2, Table 7.2. For most work, such as walls and struc-
tural repairs, a 22 ± 2 sec flow is usually satisfactory.
For massive sections and underwater work, the flow
may be as low as 20 ± 2 sec or as high as 24 ± 2 sec.
Where special care can be taken in the execution of
work and higher strengths are required, flows as high
as 35 to 40 sec may be used.
7.4-Temperature control
For mass concrete placements, temperature rise in
PA concrete may be limited by one or more of the
following procedures:
(1) Chilling coarse aggregate before placement.
(2) Chilling coarse aggregate in place.
(3) Chilling the grout with chilled mixing water.
The use of shaved and crushed ice as part of the mix
water has been effective in producing grout tem-
peratures as low as 35 to 40 F (2 to 4 C).
(4) Reducing the cement content to the minimum
for obtaining the desired properties. See ACI 207.2R
and ACI 224R for more detail.
7.5-Forms
Forming materials for PA concrete are similar to
those for conventionally placed concrete. However,
the forms need to be tight enough to prevent grout
leakage and to resist higher lateral pressures (see ACI
347). After the forms are erected, shored, properly
braced and set to line and grade, all small openings
should be caulked. All joints between adjacent pan-
els must be sealed on the inside of the form with
tape. Specifications may require that a layer of water
1 to 2 ft (0.3 to 0.6 m) deep be maintained above the
rising grout surface to insure saturation of the coarse
aggregate particles. In such cases the forms must be
essentially watertight.
MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-25
7.6-Grout pipe systems
7.6.1 Delivery pipes - The most reliable grout de-
livery system consists of a single line. However to
provide for continuous grout flow, a wye fitting may
be incorporated. The grout should be injected
through only one leg of the wye at a time. A manifold
system should not be used, since distribution of
grout within the aggregate mass may vary apprecia-
bly from insert to insert.
The delivery line should be of sufficient diameter
to permit grout velocity at the planned operating rate
to range between 2 and 4 ft/sec (0.6 and 1.2 m/sec).
Too low a velocity will permit segregation and even-
tual line blockage. Too high a velocity may force the
fluid grout to cascade over adjacent aggregate rather
than penetrate from the bottom upward. Cascading
will usually result in ungrouted pockets of coarse
aggregate.
High-pressure grout hose, 400 psi (3 mPa) or
higher, is commonly used for delivery lines. A hose
diameter of 1¼ or 1½ in. (30 or 40 mm) is preferred
for distances up to 500 ft (150 m), but 1 in. (25 mm)
can sometimes be used. For longer distances, up to
approximately 1000 ft (300 m), 2 in. (50 mm) diame-
ter is preferred.
7.6.2 Grout insert pipes - Insert pipes to inject the
grout into the aggregate mass are normally Schedule
40 pipe, ¾ to 1¼ in. (20 to 30 mm) diameter, for
normal structural concrete and up to l½ in. (40 mm)
for mass concrete. The grout insert pipes should ex-
tend vertically to within 6 in. (150 mm) of the bottom
of the aggregate mass, or they may extend horizon-
tally through the formwork at different elevations.
When inserts are required for use in depths of aggre-
gate exceeding approximately 50 ft (15 m), flush-
coupled Schedule 120 pipe or flush-coupled casing
is recommended. For very deep placements, such as
caissons in deep water, telescoping inserts may be
required.
The spacing of insert pipes will range from 4 to 12
ft (1.2 to 3.7 m), with 5 or 6 ft (1.5 or 1.8 m) being
common. As a guide for layout of insert pipes, it can
be assumed that the grout surface will assume a ver-
tical to horizontal slope of 1:4 in the dry and 1:6
under water.
All valves in the pipe system should be plug or
ball type, quick opening, and easily taken apart for
cleaning. Valves over 1 in. (25 mm) in diameter
should be stem lubricated.
7.6.3 Vent pipes - Vent pipes should be used
where water or air may be entrapped by the rising
grout surface, such as beneath a blockout or under
some embedments. Grout is usually injected through
insert pipes until it returns through these vent pipes.
7.7-Coarse aggregate placement
7.7.1 Preparation for placement - Coarse aggregate
should not be flushed with water after placement in
the forms.21,22
This will cause fines to accumulate in
the lower strata of aggregate. No amount of washing
or flushing will remove such accumulated fines,
which if present will produce honeycomb, and un-
bonded joint, or a very poor bottom surface. When it
is necessary to flood the coarse aggregate to obtain
saturation or precooling, 2 2
the water should be in-
jected through the insert pipes so that the water rises
gently through the coarse aggregate.
For underwater placement, all loose fine material
should be removed from the foundation area before
placement of aggregate to prevent subsequent coating
of the aggregate or filling of voids with stirred-up
sediment. Where the concrete will bear on piles, it is
only necessary to remove soft material a sufficient
depth below pipe encasement depth to provide for a
filter cloth on the mud plus a carefully dropped layer
of aggregate on top of the cloth to stabilize it and
form a base for the bulk of the coarse aggregate to
follow.
7.7.2 Aggregate placement - coarse aggregate
should be washed and screened immediately before
placing in the forms. For structural concrete work,
aggregate is commonly delivered to the forms in con-
crete buckets and placed through a flexible elephant
trunk to prevent segregation and breakage of the ag-
gregate. A pipe having a diameter at least four times
the maximum aggregate size has been used for lower-
ing aggregate preplaced under water to depths rang-
ing from 50 to 1000 ft (15 to 300 m).20
The pipe is
normally lowered to bottom contact, then gradually
filled. Discharge is then controlled by raising the
pipe only enough to permit discharge at a controlla-
ble rate. Where coarse aggregate is being placed
through water, it may be discharged directly into the
water from bottom dump barges or self-unloading
ships.19
Coarse aggregate may also be blown into place
around tunnel liners by using 6 in. (150 mm) or
larger pipe and large volumes of low pressure air.20
In most placements, there is little to be gained
from attempts to consolidate the coarse aggregate in
place by rodding or vibration. Rodding and the use of
compressed air lances may be desirable, however, to
achieve placement into heavily reinforced areas and
in the construction of overhead repairs.
Around closely spaced piping, reinforcement, and
penetrations, such as in some nuclear shielding sit-
uations where uniform high density and homogene-
ity are desired, hand placement in shallow lifts may
be required.
7.7.3 Contamination - In underwater construction
where organic contamination is known or suspected
to exist, the water should be sampled and tested to
determine the rate of sludge build-up on immersed
aggregate and its possible influence on the quality of
the concrete. Normally, where moderate contamina-
tion is present, the aggregate should be grouted
within a day or two after placement. If contaminants
are present in such quantity or of such character that
the harmful effects cannot be eliminated or con-
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi
304 r 89 - guide to measuring, mixing, transporting and placi

More Related Content

What's hot

Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girdersMD.Yeasin Mostafiz
 
STRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELER
STRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELERSTRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELER
STRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELERBahzad5
 
Machine Foundation Design - An Introduction
Machine Foundation Design - An IntroductionMachine Foundation Design - An Introduction
Machine Foundation Design - An IntroductionLawrence Galvez
 
Plastic Analysis
Plastic AnalysisPlastic Analysis
Plastic AnalysisAayushi5
 
Anchorage and lap splicing Detailing of slabs, columns, beams, footings
Anchorage and lap splicing Detailing of slabs, columns, beams, footingsAnchorage and lap splicing Detailing of slabs, columns, beams, footings
Anchorage and lap splicing Detailing of slabs, columns, beams, footingskarthickcivic
 
T beam design by WSD method
T beam design by WSD methodT beam design by WSD method
T beam design by WSD methodkhandakermehedi
 
Module 1 Behaviour of RC beams in Shear and Torsion
Module 1   Behaviour of RC beams in Shear and TorsionModule 1   Behaviour of RC beams in Shear and Torsion
Module 1 Behaviour of RC beams in Shear and TorsionVVIETCIVIL
 
06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...
06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...
06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...Hossam Shafiq II
 
Structural Analysis (Solutions) Chapter 9 by Wajahat
Structural Analysis (Solutions) Chapter 9 by WajahatStructural Analysis (Solutions) Chapter 9 by Wajahat
Structural Analysis (Solutions) Chapter 9 by WajahatWajahat Ullah
 
Structural Analysis 8th Edition Solutions Manual
Structural Analysis 8th Edition Solutions ManualStructural Analysis 8th Edition Solutions Manual
Structural Analysis 8th Edition Solutions ManualBahzad5
 

What's hot (20)

ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8 ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 
STRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELER
STRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELERSTRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELER
STRUCTURAL ANALYSIS NINTH EDITION R. C. HIBBELER
 
Design notes for seismic design of building accordance to Eurocode 8
Design notes for seismic design of building accordance to Eurocode 8 Design notes for seismic design of building accordance to Eurocode 8
Design notes for seismic design of building accordance to Eurocode 8
 
1 tension
1  tension1  tension
1 tension
 
Machine Foundation Design - An Introduction
Machine Foundation Design - An IntroductionMachine Foundation Design - An Introduction
Machine Foundation Design - An Introduction
 
Foundation analysis and design
  Foundation analysis and design  Foundation analysis and design
Foundation analysis and design
 
Structures and Materials- Section 3 Stress-Strain Relationships
Structures and Materials- Section 3 Stress-Strain RelationshipsStructures and Materials- Section 3 Stress-Strain Relationships
Structures and Materials- Section 3 Stress-Strain Relationships
 
8110-1-1997.pdf
8110-1-1997.pdf8110-1-1997.pdf
8110-1-1997.pdf
 
Plastic Analysis
Plastic AnalysisPlastic Analysis
Plastic Analysis
 
Anchorage and lap splicing Detailing of slabs, columns, beams, footings
Anchorage and lap splicing Detailing of slabs, columns, beams, footingsAnchorage and lap splicing Detailing of slabs, columns, beams, footings
Anchorage and lap splicing Detailing of slabs, columns, beams, footings
 
Shear wall and its design guidelines
Shear wall and its design guidelinesShear wall and its design guidelines
Shear wall and its design guidelines
 
BS 8110, PART-3, 1985
BS 8110, PART-3, 1985BS 8110, PART-3, 1985
BS 8110, PART-3, 1985
 
T beam design by WSD method
T beam design by WSD methodT beam design by WSD method
T beam design by WSD method
 
Design of floor slab
Design of floor slabDesign of floor slab
Design of floor slab
 
Aci 355.4 m
Aci 355.4 mAci 355.4 m
Aci 355.4 m
 
Module 1 Behaviour of RC beams in Shear and Torsion
Module 1   Behaviour of RC beams in Shear and TorsionModule 1   Behaviour of RC beams in Shear and Torsion
Module 1 Behaviour of RC beams in Shear and Torsion
 
06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...
06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...
06-Strength of Double Angle Welded Tension Members (Steel Structural Design &...
 
Structural Analysis (Solutions) Chapter 9 by Wajahat
Structural Analysis (Solutions) Chapter 9 by WajahatStructural Analysis (Solutions) Chapter 9 by Wajahat
Structural Analysis (Solutions) Chapter 9 by Wajahat
 
Structural Analysis 8th Edition Solutions Manual
Structural Analysis 8th Edition Solutions ManualStructural Analysis 8th Edition Solutions Manual
Structural Analysis 8th Edition Solutions Manual
 

Similar to 304 r 89 - guide to measuring, mixing, transporting and placi

201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concrete201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concreteMOHAMMED SABBAR
 
304.6 r 91 - guide for the use of volumetic-measuring and con
304.6 r 91 - guide for the use of volumetic-measuring and con304.6 r 91 - guide for the use of volumetic-measuring and con
304.6 r 91 - guide for the use of volumetic-measuring and conMOHAMMED SABBAR
 
309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concrete309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concreteMOHAMMED SABBAR
 
211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportions211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportionsMOHAMMED SABBAR
 
Study on Compressive Strength of Pervious Concrete for Utilisation as Pavenent
Study on Compressive Strength of Pervious Concrete for Utilisation as PavenentStudy on Compressive Strength of Pervious Concrete for Utilisation as Pavenent
Study on Compressive Strength of Pervious Concrete for Utilisation as PavenentIRJET Journal
 
IRJET- Durability Properties of Excavated Soil Concrete
IRJET- Durability Properties of Excavated Soil ConcreteIRJET- Durability Properties of Excavated Soil Concrete
IRJET- Durability Properties of Excavated Soil ConcreteIRJET Journal
 
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...IRJET Journal
 
Strength behaviour of foundry sand on modified high strength concrete
Strength behaviour of foundry sand on modified high strength concreteStrength behaviour of foundry sand on modified high strength concrete
Strength behaviour of foundry sand on modified high strength concreteeSAT Journals
 
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...IJERA Editor
 
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...IJERA Editor
 
EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...
EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...
EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...IRJET Journal
 
STABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASH
STABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASHSTABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASH
STABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASHIRJET Journal
 
STUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETE
STUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETESTUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETE
STUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETEAbhilash Chandra Dey
 
Tunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdfTunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdfHugoPaulin1
 
304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweight304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweightMOHAMMED SABBAR
 
Mechanical and Statistical Study of Seawater Mixed Concrete
Mechanical and Statistical Study of Seawater Mixed ConcreteMechanical and Statistical Study of Seawater Mixed Concrete
Mechanical and Statistical Study of Seawater Mixed ConcreteIRJET Journal
 

Similar to 304 r 89 - guide to measuring, mixing, transporting and placi (20)

aci 211_1_91.pdf
aci 211_1_91.pdfaci 211_1_91.pdf
aci 211_1_91.pdf
 
aci 211_1_91.pdf
aci 211_1_91.pdfaci 211_1_91.pdf
aci 211_1_91.pdf
 
201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concrete201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concrete
 
304.6 r 91 - guide for the use of volumetic-measuring and con
304.6 r 91 - guide for the use of volumetic-measuring and con304.6 r 91 - guide for the use of volumetic-measuring and con
304.6 r 91 - guide for the use of volumetic-measuring and con
 
309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concrete309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concrete
 
211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportions211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportions
 
Study on Compressive Strength of Pervious Concrete for Utilisation as Pavenent
Study on Compressive Strength of Pervious Concrete for Utilisation as PavenentStudy on Compressive Strength of Pervious Concrete for Utilisation as Pavenent
Study on Compressive Strength of Pervious Concrete for Utilisation as Pavenent
 
IRJET- Durability Properties of Excavated Soil Concrete
IRJET- Durability Properties of Excavated Soil ConcreteIRJET- Durability Properties of Excavated Soil Concrete
IRJET- Durability Properties of Excavated Soil Concrete
 
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
 
Strength behaviour of foundry sand on modified high strength concrete
Strength behaviour of foundry sand on modified high strength concreteStrength behaviour of foundry sand on modified high strength concrete
Strength behaviour of foundry sand on modified high strength concrete
 
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
 
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
Mechanical Properties of Concrete with Marine Sand as Partial Replacement of ...
 
EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...
EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...
EFFECT ON MECHANICAL PROPERTIES OF CONCRETE USING FINE AGGREGATE AS PARTIAL R...
 
STABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASH
STABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASHSTABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASH
STABILIZATION OF EXPANSIVE SOIL USING WATER HYACINTH ASH
 
STUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETE
STUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETESTUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETE
STUDY OF MECHANICAL AND DURABILITY PROPERTIES OF GEOPOLYMER CONCRETE
 
Nitish+chalhotra(800922007)
Nitish+chalhotra(800922007)Nitish+chalhotra(800922007)
Nitish+chalhotra(800922007)
 
Nitish+chalhotra(800922007) (1)
Nitish+chalhotra(800922007) (1)Nitish+chalhotra(800922007) (1)
Nitish+chalhotra(800922007) (1)
 
Tunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdfTunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdf
 
304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweight304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweight
 
Mechanical and Statistical Study of Seawater Mixed Concrete
Mechanical and Statistical Study of Seawater Mixed ConcreteMechanical and Statistical Study of Seawater Mixed Concrete
Mechanical and Statistical Study of Seawater Mixed Concrete
 

More from MOHAMMED SABBAR

309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested 309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested MOHAMMED SABBAR
 
309.2 r 98 - identification and control visible effects of co
309.2 r 98 - identification and control visible effects of co309.2 r 98 - identification and control visible effects of co
309.2 r 98 - identification and control visible effects of coMOHAMMED SABBAR
 
309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibration309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibrationMOHAMMED SABBAR
 
308 92 standard practice for curing concrete (reapproved 1
308 92   standard practice for curing concrete (reapproved 1308 92   standard practice for curing concrete (reapproved 1
308 92 standard practice for curing concrete (reapproved 1MOHAMMED SABBAR
 
308.1 98 sandard specification for curing concrete
308.1 98   sandard specification for curing concrete308.1 98   sandard specification for curing concrete
308.1 98 sandard specification for curing concreteMOHAMMED SABBAR
 
306.1 90 standard specification for cold weather concretin
306.1 90   standard specification for cold weather concretin306.1 90   standard specification for cold weather concretin
306.1 90 standard specification for cold weather concretinMOHAMMED SABBAR
 
304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyors304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyorsMOHAMMED SABBAR
 
304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transpor304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transporMOHAMMED SABBAR
 
304.2 r 96 - placing concrete by pumping methods
304.2 r 96 - placing concrete by pumping methods304.2 r 96 - placing concrete by pumping methods
304.2 r 96 - placing concrete by pumping methodsMOHAMMED SABBAR
 
303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete prac303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete pracMOHAMMED SABBAR
 
303.1 97 standard specification for-cast-in-place architec
303.1 97   standard specification for-cast-in-place  architec303.1 97   standard specification for-cast-in-place  architec
303.1 97 standard specification for-cast-in-place architecMOHAMMED SABBAR
 
234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concrete234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concreteMOHAMMED SABBAR
 
233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituen233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituenMOHAMMED SABBAR
 
232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concrete232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concreteMOHAMMED SABBAR
 
224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structures224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structuresMOHAMMED SABBAR
 
224.2 r 92 - cracking of concrete members in direct tension
224.2 r 92 - cracking of concrete members in direct tension224.2 r 92 - cracking of concrete members in direct tension
224.2 r 92 - cracking of concrete members in direct tensionMOHAMMED SABBAR
 
223 98 standard practice for the use of shrinkge-compensat
223 98   standard practice for the use of shrinkge-compensat223 98   standard practice for the use of shrinkge-compensat
223 98 standard practice for the use of shrinkge-compensatMOHAMMED SABBAR
 
222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concrete222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concreteMOHAMMED SABBAR
 
221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reac221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reacMOHAMMED SABBAR
 
214 77 recommended practice for evaluation of strength tes
214 77   recommended practice for evaluation of strength tes214 77   recommended practice for evaluation of strength tes
214 77 recommended practice for evaluation of strength tesMOHAMMED SABBAR
 

More from MOHAMMED SABBAR (20)

309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested 309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested
 
309.2 r 98 - identification and control visible effects of co
309.2 r 98 - identification and control visible effects of co309.2 r 98 - identification and control visible effects of co
309.2 r 98 - identification and control visible effects of co
 
309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibration309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibration
 
308 92 standard practice for curing concrete (reapproved 1
308 92   standard practice for curing concrete (reapproved 1308 92   standard practice for curing concrete (reapproved 1
308 92 standard practice for curing concrete (reapproved 1
 
308.1 98 sandard specification for curing concrete
308.1 98   sandard specification for curing concrete308.1 98   sandard specification for curing concrete
308.1 98 sandard specification for curing concrete
 
306.1 90 standard specification for cold weather concretin
306.1 90   standard specification for cold weather concretin306.1 90   standard specification for cold weather concretin
306.1 90 standard specification for cold weather concretin
 
304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyors304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyors
 
304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transpor304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transpor
 
304.2 r 96 - placing concrete by pumping methods
304.2 r 96 - placing concrete by pumping methods304.2 r 96 - placing concrete by pumping methods
304.2 r 96 - placing concrete by pumping methods
 
303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete prac303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete prac
 
303.1 97 standard specification for-cast-in-place architec
303.1 97   standard specification for-cast-in-place  architec303.1 97   standard specification for-cast-in-place  architec
303.1 97 standard specification for-cast-in-place architec
 
234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concrete234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concrete
 
233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituen233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituen
 
232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concrete232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concrete
 
224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structures224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structures
 
224.2 r 92 - cracking of concrete members in direct tension
224.2 r 92 - cracking of concrete members in direct tension224.2 r 92 - cracking of concrete members in direct tension
224.2 r 92 - cracking of concrete members in direct tension
 
223 98 standard practice for the use of shrinkge-compensat
223 98   standard practice for the use of shrinkge-compensat223 98   standard practice for the use of shrinkge-compensat
223 98 standard practice for the use of shrinkge-compensat
 
222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concrete222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concrete
 
221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reac221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reac
 
214 77 recommended practice for evaluation of strength tes
214 77   recommended practice for evaluation of strength tes214 77   recommended practice for evaluation of strength tes
214 77 recommended practice for evaluation of strength tes
 

Recently uploaded

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

304 r 89 - guide to measuring, mixing, transporting and placi

  • 1. This document has been approved for use by agen- cies of the Department of Defense and for listing in the DoD Index of Specifications and Standards. ACI 304R-89 Guide for Measuring, Mixing, Transporting, and Placing Concrete (Reapproved 1997) Reported by ACI Committee 304 James L. Cope,* chairman Raymond A. Ayres* Joseph C. Carson Thomas R. Clapp Wayne J. Costa* Robert M. Eshbach* J. R. Florey Donald E. Graham* Terence C. Holland* Stanley H. Lee* Robert A. Kelsey Kurt R. Melby* Gordon M. Kidd Richard W. Narva John C. King* Leo P. Nicholson William C. Krell* James S. Pierce* Bruce A. Lamberton William J. Sim* This guide presents information on the handling, measuring, and batching of all the materials used in making normal weight, light- weight structural and heavyweight concrete. It covers both weight and volumetric measuring, mixing in central mix plants and truck mixers and concrete placing using buckets, buggies, pumps and conveyors. Underwater concrete placing and preplaced aggregate concrete are also covered. The guide outlines procedures for ob- taining good quality concrete in completed structures. Keywords: absorption; admixtures; aggregate gradation; aggregates; aggre- gate size; air entrainment; batching; bleeding (concrete); cement content; ce- ments; chutes; coarse aggregates; concrete construction; concretes; consol- idation; construction joints; conveying; conveyors; curing; density (mass/ volume); falsework; fine aggregates; fineness modulus; formwork (construc- tion); grout; grouting; heat of hydration; heavyweight aggregates; laitance; lightweight aggregate concretes; lightweight aggregates; mass concrete; mate- rials handling; mixers; mixing; mixing time; mix proportioning; moisture content; placing; pozzolans; preplaced aggregate concrete; pumped concrete; quality control; ready-mixed concrete; retempering; segregation; slipform construction; stockpiling; temperature; transit mixers, tremie concrete; un- derwater construction; vibration; water; water-cement ratio; workability. CONTENTS Chapter 1 - Introduction, page 304R-2 1.1-Scope 1.2-Objective 1.3-Other considerations Jack H. Skinner, III James H. Sprouse Paul R. Stodola* William X. Sypher R. E. Tobin* Francis C.* Wilson Chapter 2 - Control, handling, and storage of materials, page 304R-3 2.1-General considerations 2.2-Aggregates 2.3-Cement Chapter 3 - Measurement and batching, page 304R-6 3.1-General requirements 3.2-Bins and weigh hatchers 3.3-Plant type 3.4-Cementitious materials 3.5-Water measurement 3.6-Measurement of admixtures 3.7-Measurement of materials for small jobs 3.8-Other considerations Chapter 4 - Mixing and transporting, page 304R-11 4.1-General requirements 4.2-Mixing equipment 4.3-Central mixed concrete 4.4-Truck mixed concrete 4.5-Charging and mixing 4.6-Mix temperature 4.7-Discharging 4.8-Mixer performance 4.9-Maintenance 4.10-General considerations for transporting concrete I ACI Committee Reports, Guides, Standard Practices, and Commen- taries are intended for guidance in designing, planning, executing, or I inspecting construction and in preparing specifications. Reference to these documents shall not be made in the Project Documents. If items found in these documents are desired to be a part of the Project Docu- ments, they should be phrased in mandatory language and incorpo- rated into the Project Documents. *Member of the task group which prepared this report. Copyright © 1989, American Concrete Institute. All rights reserved including rights of reproduction and use in any form or by any means, including the making of copies by any photo process, or by any electronic or mechanical device, unless permission in writing is obtained from the copyright proprietors.
  • 2. 304R-2 MANUAL OF CONCRETE PRACTICE Chapter 5-Placing concrete, page 304R-14 5.1-General considerations 5.2-Planning 5.3-Reinforcement and embedded items 5.4-Placing Chapter 6-Forms, joint preparation, and finishing, page 304R-21 6.l-Forms 6.2-Joint preparation 6.3-Finishing unformed surfaces Chapter 7-Preplaced aggregate structural and mass concrete, page 304R-23 7.1-General considerations 7.2-Materials 7.3-Grout mix proportioning 7.4-Temperature control 7.5-Forms 7.6-Grout pipe systems 7.7-Coarse aggregate placement 7.8-Grout mixing and pumping 7.9-Joint construction 7.10-Finishing 7.11-Quality control Chapter 8-Concrete placed under water, page 304R-28 8.l-General considerations 8.2-Materials 8.3-Mixture proportioning 8.4-Concrete production and testing 8.5-Tremie equipment and placement procedure 8.6-Direct pumping 8.7-Concrete characteristics 8.8-Precautions 8.9-Special applications 8.10-New developments Chapter 9-Pumping concrete, page 304R-32 9.1-General considerations 9.2-Pumping equipment 9.3-Pipelines and accessories 9.4-Proportioning pumpable concrete 9.5-Field practices 9.6-Field control Chapter 10-Conveying concrete, page 304R-37 10.1-General considerations 10.2-Conveyor requirements 10.3-Conveyor types and functions 10.4-Conveyor charging 10.5-Discharge control 10.6-Maintenance Chapter 11-Heavyweight and radiation shielding concrete, page 304R-41 11.1-General considerations 11.2-Materials 11.3-Concrete characteristics 11.4-Mixing equipment 11.5-Formwork 11.6-Placement 11.7-Quality control Chapter 12-Lightweight concrete, page 304R-44 12.1-General considerations 12.2-Measuring and batching 12.3-Mixing 12.4-Job controls Chapter 13-References, page 304R-47 13.1-Recommended references 13.2-Cited references CHAPTER 1 -INTRODUCTION 1.1-Scope This guide outlines procedures for obtaining good results in measuring and mixing ingredients for con- crete, transporting it to the site and placing it. The first six chapters are general in nature and have broad application to all types of projects and concrete. The following, specialized chapters, deal with preplaced aggregate concrete, underwater placing, pumping, and conveying on belts. The concluding chapters deal with heavyweight, radiation shielding and lightweight concrete. 1.2-Objective In preparing this guide, the committee followed this philosophy. 1. Progress in improvement of concrete construc- tion will be better served by the presentation of high standards rather than “common practices.” 2. In many cases, if not most, practices resulting in the production and placement of high quality con- crete can be performed as economically as those re- sulting in poor concrete. Many of the practices recommended in this document improve concrete uniformity as well as quality so that effort and in- vestment are rewarded by a smoother operation and higher production rates, both of which offset poten- tial additional cost. 3. It is assumed that anyone planning to use this guide will have a basic knowledge of the general practices involved in concrete work. If more specific information on measuring, mixing, transporting, and placing concrete is desired, the reader should refer to the list of references given at the end of this docu- ment, and particularly to References 2 and 6 and ASTM C 94, ACI 311 and 318 and EM 1110-2-2000. Committee 304 generally agrees with the information given in these references although some exceptions in emphasis and detail may be noted, To portray more clearly certain principles involved in achieving maximum uniformity, homogeneity, and quality of concrete in place, illustrations of good and poor practices are also included. 1.3-Other considerations All concerned with concrete work should be aware of the importance of maintaining the unit water con-
  • 3. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-3 tent as low as possible consistent with placing re- quirements. 1,5 Even though the water-cement ratio is kept constant, an increase in unit water increases the potential for drying shrinkage cracking, and with this cracking, the concrete may lose a portion of its durability and other desirable characteristics, such as monolithic properties and low permeability. In- discriminate addition of water which increases the water-cement ratio adversely affects both strength and durability. The more a form is filled with the right combination of solids and the less it is filled with water, the better will be the resulting concrete. Only as much cement should be used as is re- quired to obtain adequate strength, durability, placability, workability, and other essential proper- ties. Reducing cement content is particularly impor- tant in massive sections subject to restraint as the temperature rise associated with the hydration of ce- ment may result in cracking as a result of volume change (ACI 207.1R and 207.2R). Only as much water and fine aggregate should be used as is required to obtain suitable workability for proper placing and consolidation by means of vibration. CHAPTER 2-CONTROL, HANDLING, AND STORAGE OF MATERIALS 2.1 -General considerations Coarse and fine aggregates, cement, pozzolans and chemical admixtures must be properly stored, batched and handled to maintain quality. 2.2-Aggregates Fine and coarse aggregates should be of good qual- ity, uncontaminated and uniform in grading and moisture content. Unless this is accomplished through appropriate specifications (ASTM C 33) and effective selection, preparation, and handling of ag- gregates (Fig, 2.2.la and b), the production of uni- form concrete will be difficult1 (see ACI 221R). 2.2.1 Coarse aggregate - Coarse aggregate should be controlled to minimize segregation and undersize material. 2.2.1.1. Sizes - A practical method of reducing segregation to a minimum in coarse aggregate is to separate the material into several size fractions and batch these fractions separately. As the range of sizes in each fraction is decreased and the number of size separations is increased, segregation is further re- duced. Effective control of segregation and undersize materials is most easily accomplished when the ratio of maximum to minimum size in each fraction is held to not more than four for aggregates smaller than 1 in. (25 mm) and to two for larger sizes. Examples of some appropriate aggregate fraction groupings are as follows: Example 1 Sieve Designations No. 4 to ¾ in. (4.75 mm to 19.0 mm) ¾ in to 1½ in. (19.0 mm to 37.5 mm) 1½ in. to 3 in. (37.5 mm to 75 mm) 3 in. to 6 in. (75 mm to 150 mm) Example 2 Sieve Designations 1½ in. to ¾ in. (37.5 mm to 19.0 mm) 1 in. to No. 4 (25.0 mm to 4.75 mm) 3 /8in. to No. 8 (9.5 mm to 2.36 mm) 2.2.1.2 Control of undersize material - Under- size material for a given aggregate fraction is defined as that material which will pass a sieve having an opening five-sixths of the nominal minimum size of each aggregate fraction.2 In Example 1 above, that would be material passing the following sieves: No. 5 (4.0 mm), 5 /8 in. (16.0 mm), 1¼ in. (31.5 mm) and 2½ in. (63 mm). For effective control of gradation, it is essential that handling operations do not signifi- cantly increase the undersize materials in aggregates prior to their use in concrete (Fig. 2.2,1a-d). The gra- dation of aggregate as it enters the concrete mixer should be uniform and within specification limits. Sieve analyses of coarse aggregate should be made with sufficient frequency to assure that grading re- quirements are being met. When two or more aggre- gate sizes are being used, changes in the proportions of the sizes should be made as required to improve the overall grading of the combined aggregate. When specification limits for grading cannot be met consis- tently, special handling methods should be in- stituted. Materials tend to segregate during transportation and reblending may be desirable. Re- screening the coarse aggregate, as it is charged to the bins at the batch plant, to waste or remove undersize materials will effectively eliminate undesirable fines when usual storage and handling methods are not satisfactory. Undersize materials in the smaller coarse aggregate fractions can be consistently re- duced to as low as two percent by rescreening (see Fig. 2.2.ld). 2.2.2. Fine aggregate (sand) - Fine aggregate should be controlled to minimize variations in gra- dation, with special attention to keeping finer frac- tions uniform and exercising care to avoid excessive removal of fines during processing. If the ratio of fine to coarse aggregate is adjusted in accordance with ACI 211.1 recommendations for mix proportioning, a wide range of fine aggregate gradings can be used.3 However, variations in grading during production of concrete must be minimized, and the ASTM C 33 requirement that the fineness modulus of the fine aggregate be maintained within 0.20 of the design value should be met.
  • 4. 304R-4 MANUAL OF CONCRETE PRACTICE INCORRECT METHODS OF STOCKPILING AGGREGATES CAUSE SEGREGATION AND BREAKAGE a. PREFERABLE OBJECTIONABLE CRANE OR OTHER MEANS OF PLACING MATERIAL IN PILE IN UNITS NOT LARGER THAN A TRUCK LOAD WHICH REMAIN WHERE PLACED AND DO NOT RUN DOWN SLOPE. METHODS WHICH PERMIT THE AGGREGATE TO ROLL DOWN THE SLOPE AS IT IS ADDED TO THE PILE OR PERMlT HAULING EQUIPMENT TO OPERATE OVER THE SAME LEVEL REPEATEDLY LIMITED ACCEPTABILITY-GENERALLY OBJECTIONABLE PILE BUlLT RADIALLY IN HORIZONTAL LAYERS BY BULLDOZER OR FRONT LOADER STACKING PROGRESSIVE LAYERS ON BULLD0ZER OR FRONT LOADER WORKING FROM MATERIALS AS SLOPE NOT FLATTER THAN 3:1. UNLESS MATERIALS DROPPED FROM CONVEYOR BELT. A ROCK LADDER MAY STRONGLY RESIST BREAKAGE, THESE METHODS ARE BE NEEDED IN SETUP. ALSO OBJECTIONABLE. b. C. CORRECT CHlMNEY SURROUNDING MATERlAL FALLlNG FROM END Of CONVEYOR BELT TO PREVENT WIND FROM SEPARATING FINE AND COARSE MATERIALS. OPENINGS PROVIDED AS REQUIRED TO DISCHARGE MATERIALS AT VARIOUS ELEVATIONS ON THE PILE. INCORRECT FREE FALL OF MATERIAL FROM HIGH END WHEN STOCKPILING LARGE SIZED AGGREGATES OF STACKER PERMITTING WIND TO SEPARATE FROM ELEVATED CONVEYORS, BREAKAGE IS FINE FROM COARSE MATERIAL MINlMlZED BY USE OF A ROCK LADDER. UNFINISHED OR FINE AGGREGATE STORAGE FINISHED AGGREGATE STORAGE (DRY MATERIALS) NOTE: IF EXCESSIVE FINES CANNOT BE AVOIDED IN COARSE AGGREGATE FRACTlONS BY STOCKPILING METHODS USED, FINISH SCREENING PRIOR TO TRANSFER TO BATCH PLANT BINS WILL BE REQUIRED. Fig. 2.2. 1a-c Correct and incorrect methods of handling and storing aggregates
  • 5. MEASURING, MIXING, TRANSPORTING, AND PLACING Fig. 2.2.1d Batching plant rescreen arrangement The amount and nature of material finer than the No. 200 screen (75 µm sieve) should be given special attention. As recognized in ASTM C 33, if this mate- rial is dust of fracture, essentially free of clay or shale, greater percentages of materials finer than the No. 200 screen (75 µm sieve) are permissible. How- ever, if the reverse is the case, permissible quantities should be significantly reduced. The California sand equivalent test is sometimes used to determine quan- titatively the type, amount and activity of this fine material1 (see ASTM D 2419). Excessive quantities of minus No. 200 screen (75 µm sieve) fines increase the mixing water requirement, rate of slump loss, and drying shrinkage and decrease strength. Attempts should not be made to blend two sizes of fine aggregate by placing alternate amounts in bins or stockpiles or in cars or trucks as loaded. Satisfactory results are obtained when different size fractions are blended as they flow into a stream from regulating gates or feeders. However, the most positive method of control for a wide range of plant and job condi- tions is separate storage, handling, and batching of the coarse and fine fractions. 2.2.3 Storage - Stockpiling of coarse aggregate should be kept to a minimum because even under ideal conditions fines tend to settle and accumulate. However, when stockpiling is necessary, use of cor- rect methods minimize problems with fines, segrega- tion, aggregate breakage, and excessive variation in gradation. Stockpiles should be built up in horizon- tal or gently sloping layers, not by end dumping. Trucks, loaders and dozers, or other equipment should not be operated on the stockpiles because, in addition to breaking the aggregate, they frequently track dirt onto the piles (Fig. 2.2.1a-c). A hard base with good drainage should be provided to prevent contamination from underlying material and overlap of the different sizes should be prevented by suitable walls or ample spacing between piles. The wind should not be permitted to separate dry fine aggre- gate and stockpiles should not be contaminated by swinging aggregate filled buckets or clams over the other stockpiled aggregate sizes. Storage bins should be kept as full as practical to minimize breakage and changes in grading as mate- rials are withdrawn, Materials should be deposited into the bins vertically and directly over the bin out- let (see Fig 3.2b). Particular attention must be paid to the storage of special concrete aggregates including lightweight, high density and architectural-finish ag- gregates. Contamination of these special materials will have compounding effects on other properties of the concrete in which they are to be used (see Chap- ters 11 and 12). 2.2.4 Moisture control - Effort must be made to in- sure, as practically as possible, a uniform and stable moisture content in the aggregate as batched. The use of aggregates having varying amounts of free water is one of the most frequent causes for loss in control of concrete consistency (slump). In some cases it may be necessary to wet the coarse aggregate in the stock- piles or on the delivery belts to compensate for high absorption, or to provide cooling. When this is done the coarse aggregates must be dewatered to prevent transfer of excessive free water to the bins. Adequate time for drainage of free water from fine aggregate must be provided prior to its transfer to the batch plant bins. The storage time required depends
  • 6. 304R-6 MANUAL OF CONCRETE PRACTICE primarily on the grading and particle shape of the aggregate. Experience has shown that a free moisture content of as high as 6 percent and occasionally as high as 8 percent can be stable in fine aggregate. However, tighter controls may be required for certain jobs. The use of moisture meters to indicate varia- tions in the moisture of the fine aggregate as batched, and the use of moisture compensators for rapid batch weight adjustments can minimize the influence of moisture variations in the fine aggregate.4,5 2.2.5 Samples for test - Samples representing the various aggregate sizes batched should be obtained as closely as possible to the point of their introduc- tion into the concrete. The difficulty in obtaining representative samples increases with the size of the aggregate. Therefore, sampling devices require care- ful design if meaningful test results are to be ob- tained, Methods of sampling aggregates are outlined in detail in ASTM D 75. It is good practice to maintain a running average on from 5 to 10 previous gradation tests, dropping the results of the oldest and adding the most recent to the total on which the average is calculated. This average gradation can then be used for both quality control and for proportioning purposes. 2.3-Cement All cement should be stored in weathertight, prop- erly ventilated structures to prevent absorption of moisture. Storage facilities for bulk cement should include separate compartments for each type of cement used. The interior of a cement silo should be smooth with a minimum bottom slope of 50 deg from the horizontal for a circular silo and 55 to 60 deg for a rectangular silo, Silos should be equipped with nonclogging air diffuser flow pads through which small quantities of dry, oil-free, low-pressure air, approximately 3 to 5 psi (21 to 34 kPa) may be introduced intermittently to loosen cement which has settled tightly in the silos. Storage silos should be drawn down fre- quently, preferably once per month, to prevent ce- ment caking. Each bin compartment from which cement is batched should include a separate gate, screw con- veyor, air slide, rotary feeder, or other conveyance which effectively combines characteristics of con- stant flow with precise cut off to obtain accurate batching of cement. Care must be used to prevent cement being trans- ferred to the wrong silo, whether by faulty pro- cedures or equipment. Fugitive dust should be controlled during loading and transferring. Bags of cement should be stacked on pallets or similar platforms to permit proper circulation of air. For a storage period of less than 60 days, it is recom- mended that the bags be stacked no higher than 14 layers, and for long periods, no higher than 7 layers. AS an additional precaution, it is recommended that, insofar as practical, the oldest cement be used first. 2.4-Admixtures Fly ash, ground slag and other finely divided or powdered admixtures should be handled, conveyed and stored in the same manner as cement (see ACI 212.2R). However, fly ash bins should be completely separate from cement bins, without common walls, which might allow fly ash to leak into the cement bin. Care must be taken to assure that fly ash is not loaded into a cement bin by mistake on delivery (see Section 3.4.1). In practice, most chemical admixtures are deliv- ered in liquid form. Care should be taken to protect liquid admixtures from freezing. If frozen, proper re- blending or mixing of the admixture should be done before it is used in concrete. Manufacturers’ recom- mendations should be followed. Long term storage of liquid admixtures in vented tanks should be avoided. Evaporation of a portion of the liquid could adversely affect the admixtures’ per- formance (see ACI 212). CHAPTER 3-MEASUREMENT AND BATCHING 3.1 - General requirements 3.1.1. Objectives - An important objective in pro- ducing concrete is to obtain uniformity and homo- geneity as indicated by such physical properties as unit weight, slump, air content, strength, and air-free unit weight of mortar in individual batches and suc- cessive batches of the same mixture proportions 2,6,7 (ASTM C 94, CE-CW-03305). During measurement operations aggregates should be handled to maintain the desired grading, and all materials should be measured within the tolerances required for desired reproducibility of the concrete mix selected. Another important objective of successful batching is the proper sequencing and blending of the ingredients.6,7 Visual observation of each material being batched is helpful to achieving this objective. 3.1.2 Tolerances - Most engineering organiza- tions, both public and private, issue specifications containing detailed requirements for manual, semi- automatic, partially automatic and automatic batch- ing equipment for concrete2 (CE-CW-03305, ASTM C 94 and AASHTO). Batching equipment currently marketed will operate within the usual specified batch weight tolerances when the equipment is maintained in good mechanical condition. A fre- quently used document for specifying batching and scale accuracy is the "Concrete Plant Standards of the Concrete Plant Manufacturer’s Bureau."8,9 Batch- ing tolerances frequently used are given in Table 3.1.2. Other commonly used requirements include beam or scale divisions of 0.1 percent of total capacity and batching interlock of 0.3 percent of total capacity at zero balance;8 quantity of admixture weighed never to be so small that 0.4 percent of full scale capacity
  • 7. MEASURING, MIXING, TRANSPORTING, AND PLACING exceeds 3 percent of the required weight; isolation of batching equipment from plant vibration; protection of automatic controls from dust and weather; and frequent checking and cleaning of scale and beam pivot points. With good inspection and plant opera- tion, batching equipment can be expected to perform consistently within the required tolerances. 3.2-Bins and weigh batchers Batch plant bins and components should be of adequate size to accommodate the productive capac- ity of the plant, Compartments in bins should ade- quately separate the various concrete materials, and the shape and arrangement of aggregate bins should be conducive to the prevention of aggregate segrega- tion and breakage. The aggregate bins should be de- signed so material cannot hang up in the bins or spill from one compartment to another. Weigh hatchers should be charged with easy oper- ating clamshell or undercut radial-type bin gates. Gates used to charge semiautomatic and fully- automatic hatchers should be power operated and equipped with a suitable “dribble” control to obtain the desired weighing accuracy. Weigh hatchers should be accessible for obtaining representative samples, and they should be arranged to obtain the proper sequencing and blending of aggregates during charging of the mixer. Illustrations showing the proper design and ar- rangement of batch plant bins and weigh hatchers are given in Fig. 3.2. 3.3-Plant type Factors affecting the choice of the proper batching systems are (1) size of job; (2) required production rate; and (3) required standards of batching performance. The productive capacity of a batch plant is deter- mined by a combination of such items as the mate- rials handling system, bin size, hatcher size, and mixer size and number. Available weight-batch equipment falls into three general categories: manual, semiautomatic, partial- automatic or fully-automatic.8 Available volumetric equipment includes portable and stationary units equipped with either continuous or batch mixers. 3.3.1 Manual weigh batching - As the name im- plies, all operations of weighing and batching of the concrete ingredients are controlled manually. Man- ual plants are acceptable for small jobs having low batching rate requirements. As the job size increases, automation of batching operations is rapidly justi- fied. Attempts to increase the capacity of manual plants by rapid batching may result in excessive weighing inaccuracies. 3.3.2 Semiautomatic weigh batching - In this sys- tem aggregate bin gates for charging hatchers are opened by manually operated push-buttons or switches. Gates are closed automatically when the designated weight of material has been delivered. With satisfactory plant maintenance the batching ac- curacy should meet the tolerances given in Section 3.1.2. The system must contain interlocks which pre- vent hatcher charging and discharging from occur- ring simultaneously. In other words, when the hatcher is being charged, it cannot be discharged, and when it is being discharged, it cannot be charged. Visual confirmation of the scale reading for each material being weighed is essential. 3.3.3 Automatic weigh batching - Automatic weigh batching of all materials is activated by a sin- gle starter switch. However, interlocks interrupt the batching cycle when the scale does not return to 0.3 percent of zero balance or when preset weighing tol- erances detailed in Section 3.1.2 are exceeded. 3.3.3.1 Cumulative automatic weigh batching- Interlocked sequential controls are required for this type of batching. Weighing will not begin, and it will be automatically interrupted, when preset tolerances
  • 8. 304R-8 MANUAL OF CONCRETE PRACTICE Fig. 3.2 Correct and incorrect methods of batching
  • 9. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-9 in any of the successive weighings exceed values such as those given in Section 3.1.2. The charging cycle will not begin when the hatcher discharge gate is open, and the hatcher discharge cycle will not be- gin when hatcher charging gates are open or when any of the indicated material weights are not within applicable tolerances. Presetting of desired batch weights is done by such devices as punched cards, digit switches or rotating dials and computers. Set- ting of weights, starting the batch cycle, and dis- charging the batch are all manually controlled. Mix and batch-size selectors, aggregate moisture meters, manually controlled fine aggregate moisture com- pensators, and graphic or digital devices for record- ing the batch weight of each material are supplementary equipment that should be required for good plant control.4,5 This type of batching system provides greater accuracy for high speed production than either the manual or semiautomatic systems. It may have a single graphic recorder for each scale or a series of scales may simultaneously record on a sin- gle graphic chart. Also, the chart for each scale should not be less than 4 in. (100 mm) wide and have one line for each 2 percent of scale capacity, but not more than 25 lines per in. (one line per millimeter). The recorder reading should agree with the reading shown on the scale within one gradation of the recorder. A digital recorder may have a single measuring device for each scale or a series of measuring devices may record on the same tape or ticket. This type of recorder shall reproduce the reading of the scale within 0.1 percent of the scale capacity or one incre- ment of any volumetric batching device. A digital batch documentation recorder should re- cord information on each material in the mixture along with the concrete mixture identification, size of batch, and production facility identification. Re- quired information may be preprinted, written, or stamped on the document. The recorder should pro- duce the number of documents needed and may identify the load by a batch count number or a ticket serial number. The recorder, if interlocked to an auto- matic batching system, should show a single indica- tion of all batching systems meeting zero or empty balance interlocks. Recorders should produce two or more tickets with the data previously stated and space for the identification of the job or project, location of place- ment, sand moisture content, the delivery vehicle, driver’s signature, purchaser’s representative’s sig- nature, and the amount of water added at the project site. 3.3.3.2 Individual automatic weigh batching - This system provides separate scales and hatchers for each aggregate size and for each other material batched. The weighing cycle is started by a single start switch, and individual hatchers are charged si- multaneously. Interlocks for interrupting weighing and discharge cycles when tolerances are exceeded; mixture selectors; aggregate moisture meters and compensators; and recorders differ only in detail from those described for cumulative automatic batching systems. 3.3.4 Volumetric batching - When aggregates or cementitious materials are batched by volume the method of batching is considered volumetric. It is normally a continuous operation coupled with con- tinuous mixing. Accurate volumetric batching is achieved by passing material through a calibrated ro- tary vane feeder, conveying material through a cali- brated gate opening or by any other method that would provide a known volume in a calibrated unit time. Volumetric batching is suitable for the production of most concretes, provided the equipment is oper- ated in accordance with ASTM C 685, and with the same attention to detail as that required for weigh batching. The available equipment is highly mobile, requires little or no set-up time, and often serves as its own material transport. In many cases it is equipped with a continuous mixer (see Chapter 4, and can be adjusted to change the mixture propor- tions almost instantaneously. 3.3.4.1 Calibration - When recent experience with a specific piece of equipment and the materials to be used is not available, calibration of the equip- ment is required. The calibration should be per- formed in accordance with ASTM C 686 and the recommendation of the manufacturer. The purpose of this calibration is to provide the operator (and the purchaser) with the necessary meter, gauge, revolu- tion counter readings, and control settings needed to produce the product desired. 3.3.4.2 Operation - As with any equipment op- eration it is essential that personnel responsible for control be knowledgeable in all phases of its use. Operators must understand the ramifications of mak- ing adjustments because any change in the system could have an adverse affect on concrete quality. Ad- ditionally, care should be exercised to insure that ingredients used in production are the same, and in the same state, as those used for calibration. The equipment should be recalibrated when there is a change in material source or condition, when there is a change of operation, and/or when a significant change in proportions is noted. Because of the potential for variability, the mix should be checked for air content, slump and yield at least once per day of production or at intervals not exceeding 100 cu yd (80 m3 ) of production. 3.4-Cementitious materials 3.4.1 Batching - For high production requiring rapid and accurate batching it is recommended that bulk cementitious materials be weighed with auto- matic, rather than semiautomatic or manual, equip- ment. All equipment should provide access for inspection and permit sampling at any time. The
  • 10. 304-10 MANUAL OF CONCRETE PRACTICE bins and weigh hatchers should be equipped with aeration devices and/or vibrators to aid in the smooth and complete discharge of the batch. Return to zero and weighing tolerance interlocks described in Sec- tion 3.1.2 should be used. Cement should be batched separately and kept separate from all ingredients be- fore discharging. When both cement and pozzolan or slag are to be batched, separate silos should be used. However, they may be batched cumulatively, if the cement is weighed first. 3.4.2 Discharging - Effective precautions should be taken to prevent loss of cementitious materials during mixer charging. At multiple-stop plants, losses should be minimized by discharging the ce- mentitious materials through a rubber drop chute. At one-stop plants, cement and pozzolan can be suc- cessfully charged along with the aggregate through rubber telescopic dropchutes. For plant mixers, a pipe should be used to discharge the cementitious materials to a point near the center of the mixer after the water and aggregates have started to enter the mixer. Proper and consistent sequencing and blend- ing of the various ingredients into the mixer during the charging operation will contribute significantly toward the maintenance of batch-to-batch uniformity and perhaps reduced mixing time when confirmed by mixer performance tests6,10 (see ASTM C 94). 3.5-Water measurement 3.5.1 Batching equipment - On large jobs and in central batching and mixing plants where high pro- duction is required, accurate water measurement can only be obtained by the use of automatic weigh hatchers or meters. Equipment and methods used should, under all operating conditions, be capable of routine measurement within the one percent toler- ance specified in Section 3.1.2. Tanks or vertical cyl- inders with center siphon discharge can be permitted as an auxiliary part of the weighing, but should not be used as the direct means of measure- ment. For accurate measurement a digital gallon (li- ter) meter should be used. Water glass measurement is the least desirable. All equipment for water meas- urement should be designed for easy calibration so that accuracy of measurement can be quickly verified. 3.5.2 Aggregate moisture determination and com- pensation - Measurement of the correct total mixing water depends on accurately knowing the quantity and variation of moisture in the aggregate (particu- larly in the sand) as it is batched. Aggregate which is not saturated surface dry will absorb mix water from the concrete, Sand moisture meters are frequently used in plants, and when properly maintained do satisfactorily indicate changes in sand moisture con- tent. Moisture compensating equipment can also be used which will, by a single setting, reproportion water and fine aggregate weight; for a change in ag- gregate moisture content. Compensators are usually used on the sand, but occasionally they also are used on the smallest coarse aggregate size fraction. The moisture setting on the compensators is made manu- ally with the calibrated dials, buttons, or levers pro- vided. To date, the results obtained from moisture meters have not been sufficiently accurate to warrant interlocking them with compensators for automatic operation. However, their individual use is recom- mended, and when used in conjunction with regu- larly performed conventional moisture control tests, they can be useful tools for maintaining satisfactory control of the mixing water content. 3.5.3 Total mixing water - Uniformity in the meas- urement of total mixing water involves, in addition to the accurate weighing of added water, control of such additional water sources as mixer wash water, ice, and free moisture in aggregates. One specified toler- ance (ASTM C 94) for accuracy in measurement of total mixing water, for all sources, is ±3 percent. Use of admixtures in concrete is a universally ac- cepted practice. Batching tolerances (Section 3.1.2) and charging and discharge interlocks described pre- viously for other mixture ingredients should also be provided for admixtures. Batching and dispensing equipment used should be readily capable of calibra- tion. When timer activated dispensers are used for large volume admixtures such as calcium chloride, visual graduated check tubes should be used in con- junction with the batching operation. 3.6-Measurement of admixtures For additional information on recommended prac- tices in the use and dispensing of admixtures in con- crete, the reader is referred to the ACI 212.2R. 3.7-Measurement of materials for small jobs If the concrete volume on a job is small, it may not be practical to establish and maintain a batch plant and mixer at the construction site. In such cases it may be preferable to use ready mixed concrete or mobile volumetric batching and continuous mixing equipment. If neither is available, precautions must be taken to properly measure and batch concrete ma- terials mixed on the jobsite. Bags of cementitious ma- terials should be protected from moisture and fractional bags should not be used unless they are weighed. The water measuring device should be ac- curate and dependable, and the mixer capacity should not be exceeded. In addition to accurate measurement of materials, correct operating procedures must also be used if concrete uniformity is to be maintained. Care should be taken to insure that the batched materials are properly sequenced and blended so that they are charged uniformly into the mixture.6,7 The batching plant control room, if possible, should be arranged
  • 11. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-11 with the plant operator’s station located in a position where the operator can closely and clearly see the scales and measuring devices during batching of the concrete, as well as the charging, mixing, and dis- charging of the mixes, without leaving his operating console, Some common batching deficiencies to be avoided are: 1. Overlapping of batches. 2. Loss of materials. 3. Loss or hanging up of a portion of one batch, or its inclusion with another. CHAPTER 4-MIXING AND TRANSPORTING 4.1 -General requirements Thorough mixing is essential for the production of uniform quality concrete. Therefore, equipment and methods used should be capable of effectively mix- ing concrete materials containing the largest spec- ified aggregate to produce uniform mixtures of the lowest slump practical for the work. Recommenda- tions on maximum aggregate size and slump to be used for various types of construction are given in ACI 211.1 for concretes made with ASTM C150 and C595 cements, and in ACI 223 for concretes made with ASTM C845 expansive hydraulic cements. Suf- ficient mixing as well as transporting and placing capacity should be provided so that unfinished con- crete lifts can be maintained plastic and free from cold joints. 4.2-Mixing equipment Mixers are either stationary parts of central mix plants or portable equipment. Satisfactorily de- signed mixers have a blade arrangement and drum shape which insure an end-to-end exchange of mate- rials parallel to the axis of rotation or a rolling, fold- ing, and spreading movement of the batch over itself as it is being mixed. For additional descriptions of some of the various mixer types, refer to the "Con- crete Plant Mixer Standards of the Mixer Manufac- turers Division of the Concrete Plant Manufacturers Bureau."11,67 The more common types of mixing equipment are: 4.2.1 Tilting drum mixer - This is a revolving drum mixer that discharges by tilting the axis of the drum. In the mixing mode, the drum axis can be either horizontal or at an angle to the horizontal. 4.2.2 Non-tilting drum mixer - This is a revolving drum mixer which is charged, mixes and discharges with the axis of the drum horizontal. 4.2.3 Vertical shaft mixer - This is often called a turbine or pan type mixer. Mixing is done with rotat- ing blades or paddles, mounted on a vertical shaft, in either a stationary pan or one rotating in the opposite direction to the blades. The batch can be easily ob- served and rapidly adjusted, if necessary. Rapid mix- ing and low overall profile are other significant advantages. This mixer does an excellent job of mix- ing relatively dry concretes and is often used for lab- oratory mixing and by concrete p r o d u c t s manufacturers. 4.2.4 Puddle mixer - This mixer uses horizontal blades and is suitable for harsh, stiff concrete mix- tures. It is used primarily in the production of con- crete block units. 4.2.5 Truck mixers - There are two types of revolv- ing drum truck mixers in use today-rear discharge and front discharge. The rear discharge, inclined axis mixer predominates. Both utilize fins attached to the drum to mix concrete in the mixing mode and the same fins discharge the concrete when drum rotation is reversed. 4.3-Central mixed concrete Central mixed concrete is mixed completely in a stationary mixer and then transferred to another piece of equipment for delivery. This transporting equipment can be a ready-mix truck operating as an agitator or it may be an open top truck body with or without an agitator. The tendency of concrete to seg- regate limits the distance it may be hauled in equip- ment not equipped with an agitator. Sometimes the central mixer will partially mix the concrete with the final mixing and transporting done in a revolving drum truck mixer, This process is often called “shrink-mixing” as it reduces the volume of the “as charged” mixture. The total volume that a truck can handle is limited to 63 percent of the drum volume. 4.4-Truck mixed concrete Truck mixing is a process by which previously proportioned concrete materials from a batch plant are charged into a ready-mix truck for mixing and delivery to the construction project. To achieve thor- ough mixing, total absolute volume of all ingredients batched in a revolving drum truck mixer should not exceed 63 percent of the drum volume.15 (see ASTM C 94). 4.5-Charging and mixing The method and sequence of charging mixers is of great importance in determining whether the con- crete will be properly mixed. For central plant mixers, obtaining a preblending or ribboning effect as the stream of materials flow into the mixer is essential.6,7,10 In truck mixers all loading procedures must be de- signed to avoid packing of the material, particularly sand and cement, in the head of the drum during charging, The probablity of packing is decreased by
  • 12. 304-R12 MANUAL OF CONCRETE PRACTICE placing about 10 percent of the coarse aggregate and water in the mixer drum before the sand and cement. The handling of water deserves special attention. Generally about one-fourth to one-third of the water should be added to the discharge end of the drum after all other ingredients have been charged. Water charging pipes must be of proper design and of suffi- cient size so that water enters at a point well inside the mixer and charging is complete within the first 25 percent of the mixing time.10 Refer to Section 4.5.3.1 for additional discussion of mixing water. Chemical admixtures should be charged to the mixer at the same point in the mixing sequence batch after batch. Liquid admixtures should be charged with the water or on damp sand, and powdered admixtures should be ribboned into the mixer with other dry ingredients. When more than one admixture is used, each should be batched sepa- rately unless premixing is shown to be permissible and they should be properly diluted before they en- ter the mixer. 4.5.1 Central mixing-Procedures for charging central mixers are less restrictive than those neces- sary for truck mixers. This is because a revolving drum central mixer is not charged as full as a truck mixer and the blading and mixing action is quite different. In a truck mixer there is very little folding action compared to that in a stationary mixer. How- ever, batch size should not exceed the manufacturers’ rated capacity as marked on the mixer name plate. The mixing time required should be based upon the ability of the mixer to produce uniform concrete throughout the batch and from batch to batch. Manu- facturers’ recommendations and usual specifica- tions, such as 1 min for 1 cu yd (¾ m3 ) plus ¼ min for each additional cubic yard (cubic meter) of capacity can be used as satisfactory guides for establishing initial mixing time. However, final mixing times used should be based on the results of mixer per- formance tests made at frequent intervals throughout the life of the job2,6,12 (see ASTM C 94 and CE-CRD- CSS). The mixing time should be measured from the time all ingredients are in the mixer. Batch timers with audible indicators used in combination with interlocks which prevent under or over mixing of the batch and discharge prior to completion of a preset mixing time should be provided on automatic plants and are also desirable on manual plants. The mixer should be designed for starting and stopping under full load. 4.5.2 Truck mixing - Generally, 70 to 100 revolu- tions at mixing speed are specified for truck mixing. With optimum charging sequences many truck mix- ers are able to produce uniformly mixed concrete in 30 to 40 revolutions. ASTM C 94 limits the total number of revolutions to a maximum of 300. This is to limit grinding soft aggregates, loss of slump, wear on the mixer and other undesirable effects on concrete in hot weather. Final mixing may be done at the producer’s yard, enroute to a project or, more commonly, it is done at the project site. If additional time elapses after mixing and before discharge, the drum speed is reduced to the agitation speed or stopped. Then prior to discharging, the mixer should be operated at mixing speed for ap- proximately 30 revolutions to enhance uniformity. 4.5.2.1 Extending transportation time - These procedures are often called “dry batching” and were evolved to accommodate long hauls and unavoidable delays in placing by attempting to postpone the mix- ing of cement with water. However, when cement and damp aggregate come in contact with each other, free moisture on the aggregate does result in some cement hydration. Therefore, materials cannot be held in this manner indefinitely. In one method, the dry materials are batched into the ready-mix truck and transported to the jobsite where all of the mixing water is added. Water must be added under pressure, preferably at both front and rear of the drum with it revolving at mixing speed, and then mixing is completed with the usual 70 to 100 revolutions. The total volume of concrete that can be transported in truck mixers by this method is the same as for regular truck mixing, 63 percent of the drum vo1ume15 (see ASTM C 94). 4.5.3 Water 4.5.3.1 Mixing water - The water required for proper concrete consistency (slump) is affected by such things as amount and rate of mixing, length of haul, time of unloading and ambient temperature conditions. In cool weather or for short hauls and prompt delivery, such problems as loss or variation in slump, excessive mixing water requirements, and discharging, handling and placing problems rarely exist. However, the reverse is true when rate of deliv- ery is slow or irregular, haul distances are long and weather is warm. Loss of workability during warm weather can be minimized by expediting delivery and placement and by controlling the concrete tem- perature. It may also be desirable to use a retarder to prolong the time the concrete will respond to vibra- tion after is is placed. When feasible all mixing water should be batched at the central plant. However, in hot weather it is desirable to withhold some of the mixing water until the mixer arrives at the job. Then with the remaining required water added, an addi- tional 30 revolutions at mixing speed is required to adequately incorporate the additional water into the mixture, When loss of slump or workability cannot be offset by these measures, the procedures de- scribed in Section 4.5.2.1 may also be considered. 4.5.3.2 Addition of water on the job - The max- imum water-cement ratio should never be exceeded. If all the water allowed by the specification has not been added at the start of mixing it may be permissi- ble to add the remaining allowable water at the point of delivery. It should be noted that once part of a batch has been unloaded, it becomes impractical to
  • 13. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-13 determine what water-cement ratio is produced by additional water. The production of concrete of excessive slump or adding water in excess of the proportioned water- cement ratio to compensate for slump loss resulting from delays in delivery or placing should be prohib- ited. Persistent requests for the addition of water should be investigated. Where permitted a high-range water-reducer (su- perplasticizer) can be added to the concrete to in- crease slump while maintaining a low water-cement ratio.13,14 Addition may be made by the concrete sup- plier or the contractor by a variety of techniques. When this admixture is used, vibration for consol- idation may be reduced. However, in walls and slop- ing formed concrete some vibration is necessary to remove air trapped in the form. This admixture may also increase form pressure. 4.5.3.3 Wash water - Most producers find it nec- essary to rinse off the rear fins between loads with the entire mixer washed and discharged only at the end of the day. Hot weather and unusual mix designs may require washing and discharge of wash water after every load. Rinse water must not be allowed to remain in the mixer unless it can be accurately com- pensated for in the succeeding batch. Pollution con- trol regulations make it increasingly difficult to wash out after every load and have created an interest in systems to reclaim and reuse both wash water and returned concrete aggregates. ASTM C 94 describes the reuse of wash water based on prescribed tests. Particular attention is nec- essary when admixtures are being used because the required dosages may change dramatically. When wash water is used, admixtures should be batched into a limited quantity of clean water or onto damp sand. 4.6-Mix temperature Batch-to-batch uniformity of concrete from a mixer, particularly with regard to slump, water re- quirement, and air content, also depends on the uni- formity of the concrete temperature. It is, therefore, important that maximum and minimum concrete temperatures be controlled throughout all seasons of the year. Recommendations on control of concrete temperatures are discussed in detail in ACI 305R and 306R. Mixers must be capable of discharging concrete of the lowest slump suitable for the structure being con- structed without segregation (separation of coarse ag- gregate from the mortar). Prior to discharge of concrete transported in truck mixers, the drum should again be rotated at mixing speed for about 30 revolutions to reblend possible stagnant spots near the discharge end into the batch (see Fig. 5.1a and b). 4.8-Mixer performance The performance of mixers is usually determined by a series of uniformity tests made on samples taken from two or three locations within the concrete batch after it has been mixed for a given time period2,12 (see ASTM C 94 and CE-CRD-C55). Mixer performance requirements are based on allowable differences in test results of samples from any two locations or be- tween individual locations and the average of all lo- cations. The NRMCA has a description of these procedures and is an excellent reference.10,12 Among the many tests used to check mixer per- formance, the following are the most common: air content, slump, unit weight of air-free mortar, coarse aggregate content and compressive strength. Another important aspect of mixer performance is batch-to-batch uniformity of the concrete which is also affected by the uniformity of materials and their measurement as well as by the efficiency of the mixer. Visual observation of the concrete during mix- ing and discharge from the mixer is an important aid in maintaining a uniform mixture, particularly uni- form consistency. Some recording consistency meters, such as those operating from the amperage draw on the electric motor drives for revolving drum mixers, have also proved to be useful. However, the most positive control method for maintaining batch- to-batch uniformity is a regularly scheduled program of tests of the fresh concrete including unit weight, air content, slump, and temperature. Although strength tests provide an excellent measure of the efficiency of the quality control procedures that are employed, the strength test results are available too late to be of practical use in controlling day to day production. Mixers should be properly maintained to prevent mortar and dry material leakage. Inner mixer sur- faces should be kept clean and worn blades replaced. Mixers not meeting the performance tests referenced in Section 4.8 should be taken out of service until necessary maintenance and repair results in correc- tion of their deficient performance. 4.10-General considerations for transporting concrete 4.10.1 General - Concrete can be transported by a variety of methods and equipment, such as truck mixers, open top truck bodies with and without agi- tators, buckets hauled by truck or railroad car, by pipeline, hose or conveyor belts. The method of transportation used should efficiently deliver the concrete to the point of placement without signifi- cantly altering its desired properties with regard to water-cement ratio, slump, air content and homoge- neity. Each method of transportation has advantages under particular conditions such as: mixture ingre-
  • 14. 304R-14 MANUAL OF CONCRETE PRACTICE dients and proportions, type and accessibility of placement, required delivery capacity, location of batch plant, weather conditions, and others. These various conditions should be carefully reviewed in selecting the type of transportation best suited for economically obtaining quality concrete in place. 4.10.2 Revolving drum - By this method, the truck mixer previously described serves as an agitating transportation unit. The drum is rotated at charging speed during loading and is reduced to agitating speed or stopped after loading is complete. The elapsed time before discharging the concrete can be the same as for truck mixing and the volume carried may be increased to 80 percent of the drum capacity (see ASTM C 94). 4.10.3 Truck body with and without an agitator - Units used in this form of transportation usually consist of an open-top body mounted on a truck, although bottom dump trucks have been used suc- cessfully. The metal body should have smooth streamlined contact surfaces and is usually designed for discharge of the concrete at the rear when the body is tilted. A discharge gate and vibrators mounted on the body should be provided at the point of discharge for control of flow. An agitator aids in the discharge and ribbon blends the concrete as it is unloaded. Water should never be added to con- crete in the truck body because no mixing is per- formed by the agitator. Use of protective covers for truck bodies during periods of inclement weather, proper cleaning of all contact surfaces, and smooth haul roads contribute significantly to the quality and operational effi- ciency of this form of transportation. The maximum delivery time usually specified is 30 to 45 min, al- though weather conditions may require shorter, or permit longer, times. 4.10.4 Concrete buckets on trucks or railroad cars - This is a common method of transportation of mass concrete from the batch plant to a location close to the placement area. A crane then lifts the bucket to the final point of placement. Occasionally transfer cars operating on railroad tracks are used to transport the concrete from the batch plant to buckets operat- ing from cableways. Discharge of the concrete from the transfer cars into the bucket, which may be from the bottom or by some form of tilting, must be closely controlled to prevent segregation. Delivery time for bucket transportation is the same as for other non- agitating units; usually 30 to 45 min. 4.10.5 Other methods - Transportation of concrete by pumping methods and by belt conveyors will be discussed in Chapters 9 and 10, respectively. Heli- copter deliveries have been used in difficult to reach areas, where other transporting equipment could not be used. This system usually employs one of the other methods to transport the concrete to the heli- copter which then lifts the concrete in a lightweight bucket to the area of placement. CHAPTER 5-PLACING CONCRETE 5.1 -General considerations Chapter 4 described some equipment and pro- cedures for transporting concrete from the batching or batching and mixing plant to the placing site. This chapter presents guides for transferring concrete from the transporting equipment to its final position in the structure under construction. Placement of concrete is accomplished with buck- ets, hoppers, manual or motor propelled buggies, chutes and drop pipes, conveyor belts, pumps, trem- ies, and paving equipment. Figure 5.1 shows a number of handling and placing methods discussed in this chapter and gives examples of both satisfac- tory and unsatisfactory construction procedures. Placement of concrete by the preplaced aggregate method and by pumps and conveyors are discussed in Chapters 7, 9, and 10 respectively, In addition, placing methods peculiar to underwater, heavy- weight, and lightweight concreting are noted in Chapters 8, 11, and 12 respectively. Another effective placement technique for both mortar and concrete is the shotcrete process in which thin layers are applied pneumatically where forming is inconvenient or im- practical, access or location provides difficulties or normal casting techniques cannot be employed (see ACI 506). 5.2-Planning A basic requirement in all concrete handling is that both quality and uniformity of the concrete, in terms of water-cement ratio, slump, air content, and homogeneity, must be preserved. The selection of handling equipment should be based on its ca- pability to efficiently handle concrete of the most advantageous proportions that can be readily consol- idated in place with vibration. Equipment which re- quires adjustment in mixture proportions beyond ranges recommended by ACI 211.1 should not be used. Advance planning should assure producing an adequate and consistent supply of concrete. Suffici- ent placing capacity should be provided so that the concrete can be kept plastic and free of cold joints while it is being placed. All equipment for placing should be clean and in proper repair. The placing equipment should be arranged to deliver the con- crete to its final position without objectionable segre- gation. The equipment should be adequately and properly arranged so that placing may proceed with- out undue delays and manpower should be suffi- cient to assure the proper placing, consolidating, and finishing of the concrete. If the concrete is to be placed at night, the lighting system should be suffi- cient to illuminate the inside of the forms and to provide a safe work place.
  • 15. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-15 Fig. 5.1 Correct and incorrect methods of handling concrete
  • 16. 304R-16 MANUAL OF CONCRETE PRACTICE Concrete placement should not be started when there is a probability of freezing temperatures occur- ring, unless adequate facilities for cold weather pro- tection have been provided (see ACI 306R). Facilities for prompt commencement of curing or for the ap- plication of sealing compound should be in read- iness for use at the proper time (see ACI 308). Where practical, it is advantageous to have radio or tele- phone communications between the site of major placements and the batching and mixing plant to better control delivery schedules and prevent exces- sive delays and waste of concrete. It is advisable that the concrete be delivered to the site at a uniform rate compatible with the manpower and equipment being used in the placing and finish- ing processes. Where an interruption in the concret- ing process could be a problem, consideration should be given to the provision of backup equipment. A final detailed inspection of the foundation, con- struction joints, forms, water stops, reinforcement and other items of the placement should be made immediately before the concrete is placed. A method of documenting such inspection should be devel- oped and approved by all parties prior to the start of work. All of these features should be carefully exam- ined to make sure they are in accordance with the drawings, specifications and good practice. 5.3-Reinforcement and embedded items At the time of concrete placement, reinforcing steel and embedded items should be clean and free from mud, oil and other coatings that may adversely affect bonding capacity. Most reinforcing steel is cov- ered with either mill scale or rust of some severity and such coatings are considered satisfactory pro- vided that loose rust and mill scale are removed and that the minimum dimensions of the steel are not less than required in ACI 318. Care should be taken to ensure that all reinforcing steel is of the proper size and length and that it is placed in the correct position and spliced in accor- dance with the plans. Adequate concrete cover of the reinforcing steel must be maintained. Mortar coating on embedded items within a lift to be completed within a few hours need not be re- moved, but loose dried mortar on embedded items projecting into future lifts should be removed prior to placing those lifts. The method of holding waterstop in the forms should ensure that it cannot bend to form cavities during concreting. Bars and embedded items should be held securely in the proper position by suitable supports and ties to prevent displacement during concreting. Concrete blocks are sometimes used for support of the steel. Metal bar chairs with or without plastic protected ends or plastic bar chairs are more commonly used. Whatever system is used, there must be assurance that the supports will be adequate to carry expected loads before and during placement and will not stain exposed concrete surfaces, displace excessive quan- tities of concrete, nor allow bars to move from their proper positions.16 In some cases when reinforced concrete is being placed, it may be advantageous to have a competent person in attendance to adjust and correct the posi- tion of any reinforcement which may be displaced. Structural engineers should identify critical areas where such additional supervision would be advantageous. 5.4-Placing 5.4.1 Precautions - Equipment should be arranged so that the concrete has an unrestricted vertical drop to the point of the placement or into the container receiving it. The stream of concrete should not be separated by permitting it to fall freely over rods, spacers, reinforcement or other embedded materials. If forms are sufficiently open and clear so that the concrete is not disturbed in a vertical fall into place, direct discharge without the use of hoppers, trunks or chutes is usually desirable. Concrete should be deposited at or near its final position in the place- ment because it has a tendency to segregate when it has to be flowed laterally into place. If monolithic placement of a deep beam, wall, or column with a slab or soffit above is desired, a delay should be scheduled to permit settlement of the deep concrete before the slab or soffit concrete is placed. The length of delay will depend upon the tem- perature and setting characteristics of the concrete used (usually about 1 hr), but concreting should be- gin soon enough to permit a knitting of the new layer with the old layer by vibration. 5.4.2 Equipment - When choosing placing equip- ment consideration must be given to the ability of the equipment to place the concrete in the correct loca- tion economically and without altering its quality. The selection of equipment is influenced by the method of concrete production. Certain types of equipment such as buckets, hoppers, buggies, etc. will suit batch production while other equipment such as belt conveyors and pumps are more suitable for continuous production. 5.4.2.1 Buckets and hoppers - The use of prop- erly designed bottom dump buckets permits the placement of concrete at the lowest practical slump consistent with consolidation by vibration. The bucket should be self-cleaning upon discharge and concrete flow should start upon opening of the dis- charge gate. Discharge gates should have a clear opening equal to at least fives times the maximum aggregate size being used. Side slopes should be at least 60 deg from the horizontal. Control of the bucket and its gate opening should be done in such a manner as to ensure a steady stream of concrete discharged against previously
  • 17. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-17 Fig. 5.4 (a-d) Correct and incorrect methods of placing concrete
  • 18. MANUAL OF CONCRETE PRACTICE Fig. 5.4 (e-h) Correct and incorrect methods of placing concrete
  • 19. MEASURING, MIXING, TRANSPORTlNG, AND PLACING 304R-19 placed concrete where possible. Stacking concrete by discharging the bucket too close to the lift surface and discharging buckets while traveling are common causes of segregation. In order to prevent contamination, spilled concrete should not be shoveled back into buckets or hoppers for subsequent use, and freshly finished concrete should be protected by not swinging buckets directly over it. To expedite the placing schedule the use of two buckets or more per crane is recommended. 5.4.2.2. Manual or motor propelled buggies- Buggies should run on smooth rigid runways inde- pendently supported and set well above reinforcing steel. Concrete being transferred by buggies tends to segregate during motion and planking should be but- ted rather than lapped to maintain a smooth surface to prevent separation of concrete materials in transit. The recommended maximum horizontal delivery distance to transfer concrete by manual buggies is 200 ft (60 m) and for power buggies 1000 ft (300 m), Manual buggies range in capacity from 6 to 8 cu ft (0.2 m3 ) with placing capacity averaging from 3 to 5 cu yd (2 to 4 m3 ) per hour. Power buggies are avail- able in sizes from 9 to 12 cu ft (0.3 m3 ) with placing capacity ranging from 15 to 20 cu yd (11 to 15 m3 ) per hour depending upon the distance traveled. 5.4.2.3 Chutes and drop chutes - Chutes are fre- quently used for transferring concrete from upper to lower elevations. They should have rounded corners, be constructed of metal or be metal lined, and should have sufficient capacity to avoid overflow. The slope should be constant and steep enough to permit con- crete of the slump required to flow continuously down the chute without segregation. The flow of the concrete at the end of a chute should be controlled to prevent segregation. Drop chutes are circular pipes used for transferring concrete vertically from higher to lower elevations. The pipe should have a diameter of at least eight times the maximum aggregate size at the top 6 to 8 ft (2 to 3 m) of the chute, but may be tapered to approx- imately six times the maximum aggregate size below. It should be plumb, secure, and positioned so that the concrete will drop vertically. Plastic or rubber drop chutes or tremies may be used and may be shortened by cutting them in lieu of raising as the placement progresses. With the use of plastic drop chutes care should be taken to ensure that such chutes do not fold over or kink. 5.4.2.4 Paving equipment - The use of large mixers, high capacity spreaders, and slipform pavers has made it possible to place large volumes of con- crete pavement at a rapid rate. Most of the same prin- ciples of quality control are required for successful paving as in other forms of concrete placement. Due to the speed of placement, routine inspection pro- cedures need to be more frequent so that detected deviations from acceptable quality can be corrected. Some of the more frequent problems which can detrimentally affect the desired quality of the con- crete in paving are also common in other types of placement; namely, poor batch-to-batch mixing uni- formity, variation in slump and air content, and im- proper distribution of the mortar in aggregate throughout the placement. Placing of concrete with paving equipment is cov- ered in ACI 316. 5.4.2.5 Slipforming - By this method concrete is placed in prefabricated forms which are slipped past the point of placement as soon as the concrete has gained dimensional stability and rigidity to retain its design shape. Careful, consistent concrete control with suitable mixture adjustments for changing ambient tem- peratures are required. 5.5-Consolidation Internal vibration is the most effective method of consolidating plastic concrete for most applications. The effectiveness of an internal vibrator depends mainly upon the head diameter, frequency and am- plitude. Detailed recommendations for equipment and procedures for consolidation are given in ACI 309. Vibrators should not be used to move concrete lat- erally. They should be inserted and withdrawn ver- tically at close intervals, using a systematic pattern of vibration to ensure that all concrete has been ade- quately consolidated. As long as a running vibrator will sink into the concrete by its own weight, it is not too late for the concrete to benefit from revibration which should improve compressive and bond strengths. There is no evidence of detrimental effects either to embedded reinforcement or to concrete in partially hardened lifts when they are revibrated by consolidation efforts on fresh concrete above. In unusually difficult and obstructed placements supplemental form vibration may be used. In these circumstances care should be taken to avoid exces- sive operation of the vibration units which would cause a weak paste surface layer. On vertical surfaces where air void holes are objec- tionable, experience has shown that the voids can be reduced by using additional vibration. However, ex- tra vibration, spading or mechanical manipulation of concrete will not consistently remove air void holes from surfaces molded under sloping forms. The use of experienced and competent vibrator op- erators working with well-maintained vibrators and with a sufficient supply of standby units are essen- tial to satisfactory and successful consolidation of fresh concrete. 5.6-Mass concreting The equipment and method used for placing mass concrete should avoid separation of coarse aggregate
  • 20. 304R-20 MANUAL OF CONCRETE PRACTICE Fig. 5.5 Correct and incorrect methods of consolidation
  • 21. MEASURING, MIXING, TRANSPORTlNG, AND PLACING 304R-21 from the concrete. Although scattered pieces of coarse aggregate are not objectionable, clusters and pockets of coarse aggregate are objectionable and must be scattered prior to placing concrete over them. Segregated aggregate will not be eliminated by subsequent placing and consolidation operations. are to be placed upon them. Fluid pressure on forms should be correlated to the capacity and type of plac- ing equipment, the planned rate of placing concrete, the slump, temperature and stiffening characteristics of the concrete. Concrete should be placed in horizontal layers not exceeding 2 ft (610 mm) in depth and inclined layers and cold joints should be avoided. For monolithic construction each concrete layer should be placed while the underlying layer is still responsive to vibration, and layers should be sufficiently shallow to permit the two layers to be knitted by proper vibration. The step method of placement should be used in massive structures where large areas are involved in order to minimize the occurrence of cold joints. In this method the lift is built up in a series of horizon- tal stepped layers 12 to 18 in. (300 to 450 mm) thick. Concrete placing on each layer extends for the full width of the block, and the placing operations pro- gress from one end of the lift towards the other, ex- posing only small areas of concrete at a time. As the placement progresses, part of the lift will be com- pleted while concreting continues on the remainder. For a more complete discussion of mass concrete and the necessary thermal considerations see ACI 207.1R. CHAPTER 6-FORMS, JOINT PREPARATION, AND FINISHING Form panel joints, corners, connections, and seams should be mortar tight. Consolidation will liq- uefy the mortar in concrete, allowing it to leak from any openings in the formwork, leaving voids, sand streaks, or rock pockets. When forms are set for suc- ceeding lifts, bulges and offsets at horizontal joints can be avoided by resetting forms with only 1 in, (25 mm) of sheathing overlapping the concrete below the line made by the grade strip from the previous lift and by securely tying and bolting the forms close to the joint. Rustification strips (formed grooves) can also be used to obscure construction joints and im- prove appearance when they are well arranged.2 The form ties used should result in the minimum prac- tical hole size and their design should permit re- moval without spalling surrounding concrete. Leakage of mortar around ties should be prevented, and filling of cone holes or other holes left by form ties should be done in a manner which results in a secure, sound, nonshrinking, inconspicuous patch2 (see ACI 311). Prior to concreting, forms should be protected from deterioration, weather, and shrinkage by proper oiling or by effective wetting. Form sur- faces should be clean and of uniform texture, and when reuse is permitted, they should be carefully cleaned, oiled, and reconditioned if necessary. 6.1 -Forms Forms are the molds into which concrete is placed and falsework is the structural support and the nec- essary bracing required for temporary support during construction. Formwork is the total system of sup- port for freshly placed concrete, including forms and falsework. Formwork design should be established prior to erection, and shop drawings containing con- struction details, sequence of concrete placing and loading values used in the design should be ap- proved before commencement of construction. Shop drawings should be available on site during form- work erection and when placing the concrete. Steel forms should be thoroughly cleaned but never sandblasted nor abraded to bright metal. If “peeling” of concrete is encountered when using steel forms, leaving the cleaned, oiled forms in the sun for a day, vigorously rubbing the affected areas with liquid paraffin, or applying a thin coating of lacquer will usually eliminate the problem, Some- times peeling is the result of abrasion of certain form areas from impact during placement. Improvement can be made by temporarily protecting form areas subject to abrasion with plywood or metal sheets. Design and construction of concrete forms should comply with ACI 347. The design and construction of concrete formwork should be reviewed to mini- mize costs without sacrificing either safety or qual- ity. Because workmanship in concrete construction is frequently judged by the appearance of the con- crete after removal of the forms, proper performance of formwork while bearing the plastic concrete weight and live construction loading is of vital importance. Form faces should be treated with a releasing agent to prevent concrete sticking to the forms and thereby aid in stripping. The releasing agent may also act as a sealer or protective coating for the forms to prevent absorption of water from the concrete into the form- work. Form coatings must be carefully chosen for compatibility with the contact surfaces of the forms being used and with subsequent coatings to be ap- plied to the concrete surfaces. Form coatings that are satisfactory on wood are not always suitable for steel forms, e.g., steel forms would require a coating which acts primarily as a releasing agent, while plywood will benefit from a coating that also seals the forms against moisture penetration. Forms should be built with sufficient strength and Ample access should be provided within the rigidity to carry the mass and fluid pressure of con- forms for proper cleanup, placement, consolidation crete and of the materials, equipment or runways that and inspection of the concrete.
  • 22. 304R-22 MANUAL OF CONCRETE PRACTICE For the sake of appearance, it is important that proper attention be paid to the mark made by a con- struction joint on exposed formed surfaces of con- crete. Irregular construction joints should not be permitted. A straight line, preferably horizontal, should be obtained by filling forms to a grade strip. Rustication strips, either a vee or a beveled rec- tangular strip, can be used as a grade strip and to form a groove at the construction joint when appropriate. 6.2-Joint preparation Construction joints occur wherever concreting is stopped or delayed so that fresh concrete subse- quently placed against hardened concrete cannot be knitted to the previous placement. Horizontal con- struction joints will occur at the levels between lifts while vertical joints occur where the structure is of such length that it is not feasible to place the entire length in one continuous operation. In general, the preparation of a vertical construction joint for ac- ceptable performance and appearance is the same as for horizontal joints. The surfaces of all construction joints should be cleaned and properly prepared so as to assure ade- quate bond with concrete placed on it or adjacent to it and to obtain required watertightness.2,17,18 Several methods of cleanup are available depending on the size of the area to be cleaned, age of the concrete, skill of workmen, and availability of equipment. It is not difficult to obtain a satisfactory joint when high quality low-slump concrete has been properly placed. Removal of sound mortar or concrete to ex- pose coarse aggregate or to create roughness is not justified. For most construction joints, it is necessary only to remove laitance and expose the sand and sound surface mortar. When large quantities of bleed water and fines are brought to the construction joint surface, concrete at the surface will be so inferior that obtaining adequate cleanup is difficult. This problem is compounded when high-slump concrete is used. In such cases, green cutting, sand blasting, or high-pressure water jets will be required to correctly prepare the joint. Green cutting is the removal of all laitance and inferior surface concrete by means of a strong jet of water or air-water at approximately 100 psi (0.7 MPa). It must not be started until the concrete has hardened sufficiently to prevent the jet from ravelling the sur- face below the desired depth. Care must be taken to see that the cutting is done at the proper time, not too early so as to avoid too much cutting, and not too late in order to obtain sufficient removal of the surface laitance. Green cutting is usually performed 4 to 12 hours after placement and can be successfully used where the quality of the concrete at the joint is good. Sandblasting is used to prepare the surface of the construction joint after the concrete has hardened and preferably just before forms are erected for the next placement.2,17,18 Wet sandblasting is usually pre- ferred due to the objectionable dust associated with the dry process. This method produces excellent re- sults on horizontal joint surfaces, particularly on those placed with 2 in. (50 mm) (or less) slump con- crete using internal vibrators. Another method for cleaning construction joints utilizes a water jet under a minimum pressure of 6,000 psi (40 MPa). As with the sandblast method, cleanup is delayed until the concrete is sufficiently hard so that only the surface skin of mortar is re- moved and no undercutting of coarse aggregate parti- cles occurs. Cloudy pools of water which will leave a weak film on the surface when they dry should be removed by thorough washing after the main cleanup operation is completed. Cleaned joint surfaces should be con- tinuously moist cured until the next concrete place- ment or until the specified time of curing has been fulfilled. Before placing new concrete at the joint, the surface should be restored to the clean condition ex- isting immediately following initial cleanup. If the surface has been properly cured, very little final cleaning will be necessary prior to placement. Hand tools such as wire brushes, wire brooms, hand picks, or bush-hammers may be used to remove dirt, laitance, and soft mortar but are only practical for small areas. Retarding agents may be used to treat concrete sur- faces after the finishing operations and before the concrete has set. Manufacturer’s instructions for ap- plication and coverage rate should be followed. Sub- sequent removal of the unhardened surface mortar is completed with other cleanup methods such as water jets, air-water jets, or hand tools. Concrete sur- faces treated with retarder should be cleaned as soon as practical after initial set, the longer the delay, the less retarded surface layer will be removed. The clean concrete joint surface should be satu- rated, surface dry at the time new concrete is placed on it. Surface moisture weakens the joint by increas- ing the water-cement ratio of the newly placed con- crete. Care must be taken to ensure that the first layer of concrete on the construction joint is adequately consolidated for good bond. 6.3-Finishing unformed surfaces To obtain a durable surface on unformed concrete, proper procedures must be carefully followed, The concrete used should be of the lowest practical slump that can be properly consolidated, preferably by means of internal vibration. Following consolida- tion, the operations of screeding, floating, and first troweling should be performed in such a manner that the concrete will be worked and manipulated as little as possible in obtaining the desired result. Over- manipulation brings excessive fines and water to the top which impairs the quality of the finished surface causing such undesirable effects as checking, craz- ing, and dusting. For the same reason, each step in the finishing operation, from the first floating to the
  • 23. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-23 final floating or troweling, should be delayed as long as possible while still permitting the desired grade and surface smoothness to be obtained. Free water is not as likely to appear and accumulate between fin- ishing operations if proper mixture proportions and consistency are used. However, if free water does ac- cumulate, it should be removed by blotting with mats, draining, or pulling off with a loop of hose, so the surface loses its water sheen before the next fin- ishing operation is performed. Under no circum- stances should any finishing tool be used in an area before accumulated water has been removed, nor should neat cement or mixtures of sand and cement be worked into the surface to dry such areas. It is possible to obtain satisfactory results from cor- rectly designed mortar topping placed on a n d worked into base concrete before the base concrete sets, The mortar consistency, consolidation, and fin- ishing should be as described above. However, a con- crete of correct proportions, consistency, and texture placed and finished monolithically with the base concrete is preferable to a mortar topping. For a detailed discussion and recommendations on concrete floor and slab finishing, see ACI 302.lR. Several special floor finishes which are installed over hardened concrete surfaces, such as terrazzo, require special techniques and are not covered in this guide. CHAPTER 7-PREPLACED AGGREGATE STRUCTURAL AND MASS CONCRETE 7.1 - General considerations In this method of construction, forms are first filled with clean coarse aggregate. The voids in this coarse aggregate are then filled with structural qual- ity grout to produce preplaced aggregate (PA) con- crete. This type of concrete is particularly useful where concrete is to be placed under water, where structures are heavily reinforced for seismic or other reasons, where structural concrete or masonry is to be repaired, or where concrete of low volume change is required.2,19,20,21,22,23 (see CE EM-1110-2-2000). Preplaced aggregate concrete differs from conven- tionally placed concrete in that it contains a higher percentage of coarse aggregate; consequently, the properties of the coarse aggregate appear to have a greater effect on the properties of the concrete. For example, the modulus of elasticity is slightly higher than that of conventional concrete. Also, because of point-to-point contact of the coarse aggregate, drying shrinkage is about one-half the magnitude of that in conventionally placed concrete.23,24 However, struc- tural design for PA concrete is the same as for con- ventionally placed concrete2 (see CE EM-1110-2- 2000). Structural formwork is usually more expensive than that required for conventionally placed con- crete because greater care is needed to prevent grout leaks. However, in underwater construction, higher placing rates at lower cost have been achieved by this method than by conventional placing methods. Since PA concrete construction is specialized in nature, it is advisable that the work be undertaken by qualified personnel experienced in this method of construction. 7.2.1 Cement - Grout can be made with any one of the non-air-entraining types of cement that complies with ASTM C 150 or ASTM C 595. Use of air en- trained cements combined with gas-forming fluid- ifiers could result in excessive quantities of entrained air in the mortar resulting in reduced strengths. When air-entrainment is required to an ex- tent higher than that provided by the gas-forming fluidifier, air-entraining agent should be added separately. 7.2.2 Coarse aggregate - Coarse aggregate should be washed, free of surface dust and fines, in confor- mance with the requirements of ASTM C 33, except as to grading. The void content of the aggregate should be as low as possible and is usually attained when the coarse aggregate is graded uniformly from the smallest al- lowable particle size to the largest size.22 Void con- tent will range from approximately 35 percent for well-graded aggregate between ¾ in. (19 mm) and 6 to 8 in. (150 to 200 mm) to as high as 50 percent for single-sized aggregate. Void contents as low as 25 percent have been attained experimentally by delib- erate gap grading. Gradings 1 or 2, Table 7.2, are recommended for general use. Where reinforcement is crowded or the placement is in relatively shallow patches, up to 10 percent passing the ½ in. (12.5 mm) sieve with not more than 2 percent passing the 3 /8 in. (9.5 mm) sieve (Grading 1) may be used. Where special circum- stances dictate the use of coarser sand, Grading 3 is acceptable. 7.2.3 Fine aggregate - Sand should conform to ASTM C 33 except that grading should be as shown in Table 7.2. Fine aggregate that does not fall within these grading limits is useable provided results fall within the requirements of Section 7.3. 7.2.4 Pozzolan - Pozzolans conforming to ASTM C 618, Class N or F, may be used. Class F has been used in the great majority of installations since it improves pumpability of the fluid grout and extends grout han- dling time. Data from Class C fly ash use and testing are lacking. 7.2.5 Admixtures 7.2.5.1 Grout fluidifier - This admixture is com- monly used to offset the effects of bleeding, to reduce the water-cementitous materials (cement plus pozzolan) ratio for a given fluidity, and to retard stiff- ening. It normally consists of a water-reducing agent,
  • 24. 304R-24 MANUAL OF CONCRETE PRACTICE TABLE 7.2-GRADATION LIMITS FOR COARSE AND FINE AGGREGATES FOR PREPLACED AGGREGATE CONCRETE a suspending agent, aluminum powder, and a chem- ical buffer to assure properly timed reaction of the aluminum powder with alkalies in portland cement. Normal dosage of grout fluidifier is 1 percent by weight of the total cementitous material in the grout mixture. 7.2.5.2 Calcium chloride - A small quantity may be desirable to promote early strength develop- ment. However, calcium chloride in excess of 1 per- cent, by weight of cementitious materials, will depress the expansive action of the aluminum powder, Pretesting for expansion, bleeding, rate of hardening, and strength in PA concrete cylinders is recommended (see ASTM C 953). 7.3-Grout mix proportioning 7.3.1 Cementitious materials - Usually, the pro- portion of portland cement to pozzolan is in the range of 2.5:1 to 3.5:1 by weight. Ratios as low as 1.3:1 (equal bulk volumes) for lean mass concrete and as high as 12:1 for extra high strength have been used. The water to cementitious materials ratio will normally range from 0.42 to 0.50. 7.3.2 Fine aggregate - Compressive strength, pumpability21,22 and void penetrability requirements control the amount of fine aggregate that can be used in the grout. For structural grade PA concrete, the ratio of cementitious material to sand will usually be in the ratio of 1:1, by weight. For massive placements where the minimum size of coarse aggregate is ¾ in. (19 mm), the ratio may be increased to 1:1.5, With Grading 3, the ratio may be further increased to ap- proximately 1:3. 7.3.3 Proportioning requirements - Materials should be proportioned in accordance with ASTM C 938 to produce a grout of required consistency that will provide the strength of PA concrete cylinders specified in ASTM C 943. For optimum results, bleeding should be less than the total expansion. 7.3.4 Consistency of grout - The flow cone de- scribed in ASTM C 939 is used to determine consis- tency when using fine aggregate from Grading 1 and 2, Table 7.2. For most work, such as walls and struc- tural repairs, a 22 ± 2 sec flow is usually satisfactory. For massive sections and underwater work, the flow may be as low as 20 ± 2 sec or as high as 24 ± 2 sec. Where special care can be taken in the execution of work and higher strengths are required, flows as high as 35 to 40 sec may be used. 7.4-Temperature control For mass concrete placements, temperature rise in PA concrete may be limited by one or more of the following procedures: (1) Chilling coarse aggregate before placement. (2) Chilling coarse aggregate in place. (3) Chilling the grout with chilled mixing water. The use of shaved and crushed ice as part of the mix water has been effective in producing grout tem- peratures as low as 35 to 40 F (2 to 4 C). (4) Reducing the cement content to the minimum for obtaining the desired properties. See ACI 207.2R and ACI 224R for more detail. 7.5-Forms Forming materials for PA concrete are similar to those for conventionally placed concrete. However, the forms need to be tight enough to prevent grout leakage and to resist higher lateral pressures (see ACI 347). After the forms are erected, shored, properly braced and set to line and grade, all small openings should be caulked. All joints between adjacent pan- els must be sealed on the inside of the form with tape. Specifications may require that a layer of water 1 to 2 ft (0.3 to 0.6 m) deep be maintained above the rising grout surface to insure saturation of the coarse aggregate particles. In such cases the forms must be essentially watertight.
  • 25. MEASURING, MIXING, TRANSPORTING, AND PLACING 304R-25 7.6-Grout pipe systems 7.6.1 Delivery pipes - The most reliable grout de- livery system consists of a single line. However to provide for continuous grout flow, a wye fitting may be incorporated. The grout should be injected through only one leg of the wye at a time. A manifold system should not be used, since distribution of grout within the aggregate mass may vary apprecia- bly from insert to insert. The delivery line should be of sufficient diameter to permit grout velocity at the planned operating rate to range between 2 and 4 ft/sec (0.6 and 1.2 m/sec). Too low a velocity will permit segregation and even- tual line blockage. Too high a velocity may force the fluid grout to cascade over adjacent aggregate rather than penetrate from the bottom upward. Cascading will usually result in ungrouted pockets of coarse aggregate. High-pressure grout hose, 400 psi (3 mPa) or higher, is commonly used for delivery lines. A hose diameter of 1¼ or 1½ in. (30 or 40 mm) is preferred for distances up to 500 ft (150 m), but 1 in. (25 mm) can sometimes be used. For longer distances, up to approximately 1000 ft (300 m), 2 in. (50 mm) diame- ter is preferred. 7.6.2 Grout insert pipes - Insert pipes to inject the grout into the aggregate mass are normally Schedule 40 pipe, ¾ to 1¼ in. (20 to 30 mm) diameter, for normal structural concrete and up to l½ in. (40 mm) for mass concrete. The grout insert pipes should ex- tend vertically to within 6 in. (150 mm) of the bottom of the aggregate mass, or they may extend horizon- tally through the formwork at different elevations. When inserts are required for use in depths of aggre- gate exceeding approximately 50 ft (15 m), flush- coupled Schedule 120 pipe or flush-coupled casing is recommended. For very deep placements, such as caissons in deep water, telescoping inserts may be required. The spacing of insert pipes will range from 4 to 12 ft (1.2 to 3.7 m), with 5 or 6 ft (1.5 or 1.8 m) being common. As a guide for layout of insert pipes, it can be assumed that the grout surface will assume a ver- tical to horizontal slope of 1:4 in the dry and 1:6 under water. All valves in the pipe system should be plug or ball type, quick opening, and easily taken apart for cleaning. Valves over 1 in. (25 mm) in diameter should be stem lubricated. 7.6.3 Vent pipes - Vent pipes should be used where water or air may be entrapped by the rising grout surface, such as beneath a blockout or under some embedments. Grout is usually injected through insert pipes until it returns through these vent pipes. 7.7-Coarse aggregate placement 7.7.1 Preparation for placement - Coarse aggregate should not be flushed with water after placement in the forms.21,22 This will cause fines to accumulate in the lower strata of aggregate. No amount of washing or flushing will remove such accumulated fines, which if present will produce honeycomb, and un- bonded joint, or a very poor bottom surface. When it is necessary to flood the coarse aggregate to obtain saturation or precooling, 2 2 the water should be in- jected through the insert pipes so that the water rises gently through the coarse aggregate. For underwater placement, all loose fine material should be removed from the foundation area before placement of aggregate to prevent subsequent coating of the aggregate or filling of voids with stirred-up sediment. Where the concrete will bear on piles, it is only necessary to remove soft material a sufficient depth below pipe encasement depth to provide for a filter cloth on the mud plus a carefully dropped layer of aggregate on top of the cloth to stabilize it and form a base for the bulk of the coarse aggregate to follow. 7.7.2 Aggregate placement - coarse aggregate should be washed and screened immediately before placing in the forms. For structural concrete work, aggregate is commonly delivered to the forms in con- crete buckets and placed through a flexible elephant trunk to prevent segregation and breakage of the ag- gregate. A pipe having a diameter at least four times the maximum aggregate size has been used for lower- ing aggregate preplaced under water to depths rang- ing from 50 to 1000 ft (15 to 300 m).20 The pipe is normally lowered to bottom contact, then gradually filled. Discharge is then controlled by raising the pipe only enough to permit discharge at a controlla- ble rate. Where coarse aggregate is being placed through water, it may be discharged directly into the water from bottom dump barges or self-unloading ships.19 Coarse aggregate may also be blown into place around tunnel liners by using 6 in. (150 mm) or larger pipe and large volumes of low pressure air.20 In most placements, there is little to be gained from attempts to consolidate the coarse aggregate in place by rodding or vibration. Rodding and the use of compressed air lances may be desirable, however, to achieve placement into heavily reinforced areas and in the construction of overhead repairs. Around closely spaced piping, reinforcement, and penetrations, such as in some nuclear shielding sit- uations where uniform high density and homogene- ity are desired, hand placement in shallow lifts may be required. 7.7.3 Contamination - In underwater construction where organic contamination is known or suspected to exist, the water should be sampled and tested to determine the rate of sludge build-up on immersed aggregate and its possible influence on the quality of the concrete. Normally, where moderate contamina- tion is present, the aggregate should be grouted within a day or two after placement. If contaminants are present in such quantity or of such character that the harmful effects cannot be eliminated or con-