SlideShare a Scribd company logo
1 of 11
Download to read offline
ACI 309.2R-98 became effective August 19, 1998. This document supercedes ACI
309.2R-90.
Copyright © 1998, American Concrete Institute.
All rights reserved including rights of reproduction and use in any form or by any
means, including the making of copies by any photo process, or by electronic or
mechanical device, printed, written, or oral, or recording for sound or visual reproduc-
tion or for use in any knowledge or retrieval system or device, unless permission in
writing is obtained from the copyright proprietors.
ACI Committee Reports, Guides, Standard Practices, and
Commentaries are intended for guidance in planning, design-
ing, executing, and inspecting construction. This document
is intended for the use of individuals who are competent
to evaluate the significance and limitations of its content
and recommendations and who will accept responsibility
for the application of the material it contains. The American
Concrete Institute disclaims any and all responsibility for the
stated principles. The Institute shall not be liable for any loss
or damage arising therefrom.
Reference to this document shall not be made in contract
documents. If items found in this document are desired by
the Architect/Engineer to be a part of the contract docu-
ments, they shall be restated in mandatory language for in-
corporation by the Architect/Engineer.
309.2R-1
This report provides guidelines for identifying and controlling visible
effects of consolidation on precast or cast-in-place formed concrete sur-
faces. It includes a summary of direct and indirect causes of such imperfec-
tions. An outline to assist in the reporting on surfaces and photographs to
illustrate typical concrete surface blemishes are also included.
Surface blemishes in concrete may be minimized by proper planning dur-
ing the design and specification stages. Of equal importance is the employ-
ment of properly trained and motivated supervisory and non-supervisory
construction personnel to achieve the intended concrete finishes and sur-
face textures.
The report emphasizes significant consolidation factors that minimize
undesirable surface effects. The reader is cautioned that other potential
causes of such effects may exist beyond those listed in this report. There are
documents in which a feature designated as a defect is one that must be
prevented, avoided, corrected, remmediated or otherwise dealt with. The
term “defect,” as formerly used in this report, covers blemishes and depar-
tures from perfection that are not features, and must be avoided or repaired
whenever they occur. Some surfaces can tolerate them to some or any
degree; other surfaces cannot. It is the responsibility of the specifier to
indicate in the contract documents what constitutes acceptable and unac-
ceptable blemishes for the various surfaces to be produced under the terms
of a given contract. Terms used in this report are as defined in ACI 116 R.
Keywords :aggregates; bugholes; concretes; consistency; consolidation;
construction joints; discoloration; formwork (construction); mix propor-
tioning; placing; preplaced-aggregate concrete; quality control; surface
defects; temperature; vibration; voids; workability.
CONTENTS
Chapter 1—General
Chapter 2—Factors causing blemishes
2.1—Design of structural members
2.2—Specifications
2.3—Forms
2.4—Properties of fresh concrete
2.5—Placement
2.6—Consolidation
2.7—Special construction conditions
Chapter 3—Surface blemishes
3.1—Honeycomb
3.2 —Air voids in surfaces
3.3— Form streaking
Identification and Control of Visible Effects of
Consolidation on Formed Concrete Surfaces
ACI 309.2R-98
Reported by ACI Committee 309
H. Celik Ozyildirim
Chairman
Neil A. Cumming Kenneth C. Hover Larry D. Olson
Timothy P. Dolen Gary R. Mass Steven A. Ragan
Jerome H. Ford Bryant Mather Donald L. Schlegel
Steven H. Gebler Richard E. Miller Brad K. Violetta
Glen A. Heimbruch
Revising Committee:
Jerome H. Ford
Chairman
Dan Bonikowsky Gary R. Mass Steven A. Ragan
Neil A. Cumming Bryant Mather Donald L. Schlegel
Timothy P. Dolen Richard E. Miller Brad K. Violetta
Steven H. Gebler H. Celik Ozyildirim
309.2R-2 MANUAL OF CONCRETE PRACTICE
3.4—Aggregate transparency
3.5—Subsidence cracking
3.6—Color variation
3.7—Sand streaking
3.8—Layer lines
3.9—Form offsets
3.10—Cold joints
Chapter 4—Minimizing surface effects
Chapter 5—Consolidation of preplaced-aggregate
concrete
Chapter 6—Conclusion
Chapter 7—Surface condition outline
Chapter 8—References
8.1—Recommended references
8.2—Cited references
CHAPTER 1—GENERAL
A formed concrete surface, uniformly smooth or deeply
textured and essentially free of blemishes and color varia-
tion, is difficult to attain. Since repairs to a defective surface
are costly and seldom fully satisfactory, the need for repairs
should be minimized by establishing and maintaining the
quality of the concrete operation and by adhering to accept-
able consolidation procedures. Standards for surface finishes
are beyond the scope of this report. Guidance for establish-
ing appropriate standards is offered by the International
Council for Building Research (CIB) (1975), which classi-
fies formed surface finishes as follows:
• Special—High standards of appearance required (ACI
303R);
• Elaborate—Definite requirements for visual appear-
ance;
• Ordinary—Appearance is of some importance; and
• Rough—No special requirements for finish.
Concrete construction procedures do not always provide
the control necessary to consistently obtain blemish free con-
crete indicated by a special category.
To achieve any concrete finish, the designer and the con-
tractor must use materials as well as design and construction
practices that will keep surface effects within acceptable lim-
its. There is a definite need for understanding the causes of
unacceptable blemishes and effects encountered in concrete
construction and a need for applying more effective mea-
sures to minimize or eliminate them. This report addresses
those needs and its major emphasis is on consolidation-
related effects.
The most serious effects resulting from ineffective consol-
idation procedures are: honeycomb, subsidence cracks, cold
joints, and excessive surface voids. A detailed description of
the blemishes and their causes are provided in Table 1. Some
imperfections may not conform to contract documents and
may be considered as defective work.
CHAPTER 2—FACTORS CAUSING EFFECTS
Causes of consolidation-related effects on formed con-
crete surfaces (Table 1) include:
A. Design and construction-related causes
• Difficult placement due to design of a member
• Improper selection of horizontal construction joint
location
• Improper design, manufacture, installation, shipping,
preparation and maintenance of forms
• Improper selection of concrete mixture proportions
• Failure to adjust concrete mixture proportions to suit
placement condition
• Improper placement practices
• Improper consolidation practices
• Improper steel detailing
B. Equipment-related causes
• Improper equipment
• Improper equipment maintenance
• Equipment failure (crane, pump, concrete plant)
• Interruption of utility service
C. Material-related causes
• Improper selection of release agent
• Cement characteristics
• Variation in mixture constituents
• Inappropriate use of admixtures
D. Environmental causes
• Extreme weather conditions
Examples of some of the more common blemishes are illus-
trated in Fig. 1 through 10.
2.1—Design of structural members
The common problems requiring consideration during de-
sign and planning are congested reinforcement (particularly
splices), narrow sections, or complex form configurations.
Conditions that require closed top forming, embedments,
and battered forms also require consideration during design
and planning.
To produce properly consolidated concrete with the de-
sired appearance, the placement and consolidation of the
concrete must be understood. The designer must have a
working knowledge of the concrete placement process. The
designer and the constructor should communicate during the
early phases of the concreting process. Early recognition of
problem areas is important to provide time to take remedial
measures, such as staggering splices, grouping reinforcing
steel, modifying stirrup spacing, increasing the section size,
and selecting locations of horizontal construction joints.
When unfavorable conditions exist that could contribute to
substandard surfaces, one or more of the following actions
should be taken:
1. Redesign the member;
2. Redesign the reinforcing steel;
3. Provide adequate access for consolidation at horizontal
construction joints;
4. Modify mixture proportions;
5. Use mock-up tests to develop a procedure; and/or
6. Alert the constructor to critical conditions.
309.2R-3CONSOLIDATION-RELATED SURFACE DEFECTS
Defects Causes
Name Description Fig.
Design of
Members
1
Forms
2
Construction
Conditions
3
Properties of
Fresh Concrete
4
Placement
5
Consolidation
6
Honeycomb
Stony zone
with air voids;
lacking in
fines. Due to
segregation
1
Highly
congested
reinforcement,
narrow
section, inter-
nal interfer-
ence,
reinforcement
splices,
restricted
access for
vibration, high
monolithic
lifts
Leaking at
joints, severe
grout loss
Premature
setting
reinforcement
too close to
forms, lack of
access for
vibration,
congestion due
to splices
Insufficient
fines, low
workability,
early
stiffening,
excessive
mixing, too
largeaggregate
for placing
conditions
Excessive free
fall, excessive
lift of concrete
in forms, drop
chute omitted,
or insufficient
length, too
small a tremie,
segregation
due to
horizontal
movement
Vibrator too
small,
frequency and
amplitude
inappropriate,
too short
immersion
time, exces-
sive spacing
between
immersions,
inadequate
penetration
insufficient
number of
vibrators
Air surface
voids
Small individ-
ual holes,
irregular,
ranging up to 1
in. (25mm) in
diameter
2
Battered or
interfering
construction
Form face
impermeable,
poor wetting
characteris-
tics, formwork
too flexible,
use of
improper form
release agent
Excessive
release agent,
high tempera-
ture of con-
crete.
Low FM of
fine aggregate,
lean, fine
aggregate with
a high FM, low
workability,
excessive
cement or
pozzolan, par-
ticle degrada-
tion, excessive
sand, high air
content
Too slow,
caused by
inadequate
pumping rate,
undersized
bucket
Too large an
amplitude,
external
vibration
inadequate,
head of
vibrator
partially
immersed
Form-
streaking
Fine aggregate
or coarse
aggregate tex-
tured areas
lacking
cement, usu-
ally associated
with dark color
on adjacent
surface
3
Leaking at
joints, tie
holes, caused
by loose hard-
ware or over
sized tie holes
Usuallycaused
by horizontal
concrete
movement
Excess water
or high slump
Improper tim-
ing between
placing and
vibrating
Excessive
amplitude or
frequency for
form design
Aggregate
transparency
Dark or light
areas of
similar size
and shape to
that of the
coarse aggre-
gate, mottled
appearance
4
Too flexible,
high-density
surface finish
Low fine-
aggregate con-
tent, gap-
graded aggre-
gate dry or
porous aggre-
gate, exces-
sive coarse
aggregate,
excessive
slump with
lightweight
concrete
Excessive
external
vibration;
overvibration
of lightweight
concrete
Subsidence
cracking
Short cracks
varying in
width, more
often horizon-
tal than verti-
cal
5
Interference to
access, lack of
adequate cover
Poor thermal
insulation,
irregular shape
restraining set-
tlement, exces-
sive
absorbency
Insufficient
delay between
top-out of
columns and
placement of
slab or beam,
low humidity
Low fine
aggregate,
high water
content, too
high slump,
Poorly propor-
tioned mixes
Too rapid
Insufficient
vibration and
lack of
revibration
Table 1—Summary of primary causes of surface effects
2.2—Specifications
Acceptable specifications for concrete and concrete con-
struction are essential to ensure proper construction practices.
Practical and workable specifications that allow for unusual
and complex job conditions are needed.
Specifications should be sufficiently broad in scope to per-
mit adjustments of mixture proportions and batch adjust-
ments needed to produce uniformly workable concrete that
will respond readily to vibration. Concrete may still vary due
to changes in aggregate grading, ambient and concrete tem-
perature, air content, and batch quantities, even though these
changes are within specification limits. Accepted mixture
proportions may need adjustments to produce the desired
concrete characteristics and to minimize consolidation prob-
lems. However, the mixture should be adjusted with care to
maintain the design intent and to avoid other problems, such
as excessive cracking. The specifications should require
mixing, transporting, handling, and placing that can result in
adequate consolidation and minimize chances for surface
blemishes. Moreover, the specifications should call for
vibrators of proper size and characteristics, as recommended
in ACI 309R. Small-diameter vibrators should be required to
supplement larger-diameter vibrators where access is limited.
309.2R-4 MANUAL OF CONCRETE PRACTICE
2.3—Forms
Some surface blemishes are caused by inadequacies of the
formwork. Examples are leakage at joints, inadequate facing
material, excessive overload on previously placed concrete
(ACI 303R), inadequate anchorage, poorly braced and ex-
cessively flexible forms, improper use of release agents, and
oversized and unsealed tie holes. Surface blemishes also re-
sult from overuse of forms, poor storage practices, inade-
quate cleaning, and improper patching and repair of the
forms.
The number of visible surface voids (bug holes) may be re-
duced by using absorptive forms; however, smooth forms in
combination with the correct selection of a form release-
agent allow air voids at formed surfaces to move upward
more freely. ACI 303R discusses the use of release agents.
Some dry resin-based release agents used on steel forms
will greatly increase the number of bug holes. An excessive
amount of release agent collecting in the bottom of the form
may result in discoloration of the concrete and may create
weak areas. Inadequately cleaned forms, or those which have
been reused too many times, can contribute significantly to
the formation of surface blemishes. When any of these
conditions occurs, the concrete surface may peel during form
removal.
The finish should be observed as the form is stripped so
that appropriate corrective measures, if needed, can be im-
plemented promptly. Inward sloping forms have a tendency
to trap or restrict the movement of entrapped air and bleed
water to the surface, and increase the occurrence of surface
effects. Form strength, design, and other form requirements
are covered in ACI 347R.
2.4—Properties of fresh concrete
The composition, consistency, workability, and tempera-
ture of fresh concrete has a significant bearing on the ease
with which a concrete mixture may be placed and consoli-
dated. For critical surface finishes, the effect of each ingre-
dient of the mixture may require special consideration.
Placing conditions should also be considered during mixture
proportioning.
Mixture adjustments should be made to the proportions to
maintain workability when materials and field conditions
change, provided that critical properties, such as durability
and strength, are maintained.
Defects Causes
Name Description Fig.
Design of
Members
1
Forms
2
Construction
Conditions
3
Properties of
Fresh Concrete
4
Placement
5
Consolidation
6
Color
variation
Variations in
color of the
surface,
visible within
a few hours
after removing
the formwork
6
Heavy rein-
forcement
close to forms
Variation in
absorptive
capacity of
surface, reac-
tion with form
face, chemical
reaction with
release agents,
leakage of
forms at joints
and tie holes
Non-uniform
color of mate-
rials, inconsis-
tent grading,
variation in
proportions,
incomplete
mixing. Cal-
cium chloride
can cause
darker color.
Too high a
slump. Over-
manipulation
Segregation
slump too high
Vibrator too
close to form,
vibration next
to forms vari-
able
Sand streaking
Variation in
color or shade
due to separa-
tion of fine
particles
7
Form leakage
Excess water
at bottom of
form forced up
along form
face by
hydraulic
pressure
Low tempera-
ture, wet mix-
tures
Lean “over-
sanded”
mixtures and
harsh, wet
mixtures
deficient in
fines
Too rapid for
type of
mixture
Excessive
vibration.
Excessive
amplitude.
Over-
manipulation
Layer lines
(pore lines)
Dark colored
zones between
concrete layers
8 Internal
interference
Insufficient
planning, high
temperature
Wet mixture
with tendency
to bleed
Slow place-
ment, lack of
equipment or
manpower
Lack of vibra-
tion, failure to
penetrate into
previous layer
Cold joints
Voids, honey-
comb and
color varia-
tions along
boundaries of
lifts, top layer
of concrete not
adequately
bonded to sub-
strate
9
Insufficient
space to insert
vibrator
Poor planning
or insufficient
backup equip-
ment,
substrate
concrete has
set.
Too dry, early
stiffening,
slump loss
Delayed
delivery, lifts
too thick
Failure to
vibrate into
lower lift.
Insufficient
vibration
Form offsets
Abrupt to
gradualsurface
irregularities
10
Construction
joint at change
in direction of
formwork
Inadequate
formwork
design for rate
of placement
Poor form
anchorage and
inadequate
bulkheads
Excessive
retardation of
time of setting
of concrete
Rate too high
Excessive
amplitude,
non-uniform
spacing of
immersion
horizontal
movement of
concrete
Table 1—continued
309.2R-5CONSOLIDATION-RELATED SURFACE DEFECTS
A review by the designer is essential to ensure that
strength levels, nominal maximum aggregate size, and
slump requirements for different structural elements are met.
Concrete ingredients should be evaluated and proportions
should be selected well in advance of the concreting opera-
tion to achieve the desired properties for the fresh concrete.
Sticky mixtures may occur if the fine aggregate grading in
the 1.18 mm to 300 µm (No. 16 to 50) size range approaches
the upper limits specified by ASTM C 33, or if high cement
contents are used. Some pozzolans also may cause mixtures
to be more cohesive. Thus, the passage of entrapped air may
be restricted and air voids may be trapped at the interface be-
tween the concrete and the form. If fine aggregate contains
the proper amount of materials in the 600 to 300 µm (No. 30
to 50) size range, little bleeding will occur in the resulting
concrete. As a result, placement and consolidation of the
concrete will be facilitated, thereby minimizing surface
effects.
Soft aggregates may degrade and produce additional fines.
In some instances, the fines may make the mixture more co-
hesive and increase the difficulty of removing entrapped air.
This is particularly true at high cementitious materials con-
tents. In other instances, the additional fines can significantly
increase the water demand, resulting in lower strength, in-
creased shrinkage, and crazing of smooth formed surfaces.
Experience indicates that a concrete at a given consistency
will generally flow more easily at lower temperatures than at
higher temperatures.
When chemical and especially mineral admixtures are
used, their effect on placement and consolidation should be
evaluated when mixture proportions are being established.
All of the factors discussed above need to be considered to
obtain a concrete mixture with the desired composition,
consistency, and workability to facilitate its placement and
consolidation.
2.5—Placement
Concrete should be placed as quickly as possible with a
minimum amount of segregation and spattering on the
forms. Once the coarse aggregate is separated from the mor-
tar by poor handling and placement practice, it is virtually
impossible to work the mortar back into the voids and restore
a dense mass by vibration. Segregation and separation cause
honeycomb. Spattered mortar on the form produces color
variations and poor surface texture. Placing concrete too
slowly may allow workability to be lost and can produce lay-
er lines or cold joints due to improper consolidation. The rate
of placement and vibration factors (intensity and spacing)
should be selected to minimize entrapped air in the concrete.
If concrete is deposited in thick layers of more than 300
mm (12 in.), more air may be trapped than if it is placed in a
thinner, even layer since the air has to travel farther to es-
cape. Where mixtures of dry or stiff consistencies are re-
quired, the placement rate should be slower to permit
adequate consolidation so as to avoid bug holes and honey-
combing. However, in the case of a sanitary treatment struc-
ture with steel forms, an increase in lift thickness from 0.6 to
1.2 m (2 to 4 ft) reduced bug holes by 50 percent when an air
content of 5 percent was specified.
2.6—Consolidation
Concrete consists of coarse aggregate particles in a matrix
of mortar, and irregularly distributed pockets of entrapped
air. If the concrete is air entrained, an additional evenly dis-
tributed system of entrained air bubbles is present. The vol-
ume of entrapped air in unconsolidated concrete may vary
from about 5 to 20 percent depending on the workability of
the mixture, size and shape of the form, amount of reinforc-
ing steel, and method of depositing the concrete. The pur-
pose of consolidation is to remove as much of this entrapped
air as practical.
Vibration is the most common method of consolidation. It
causes very rapid movement of the concrete mixture parti-
cles and briefly liquefies the mixture, thus reducing the inter-
nal friction. When vibrated, concrete becomes fluid and
through the action of gravity seeks a lower level and denser
condition as entrapped air rises to the surface and is expelled.
It compacts laterally against the form and around the rein-
forcing steel. In practice, vibration is normally continued un-
til the entire placement acquires a uniform appearance and
its surface just starts to glisten or large bubbles cease to ap-
pear. A film of cement paste should be discernible between
the concrete and the forms. These visual indicators are not
necessarily an accurate indication of good consolidation.
ACI 309R provides guidance on judging the adequacy of
vibration.
Undervibration is far more common than overvibration,
and may be caused by the following:
1. Use of an undersized, underpowered, or poorly main-
tained vibrator;
2. Excessive or haphazard spacing of vibrator insertions;
3. Inadequate vibration during each insertion;
4. Failure of the vibrator to penetrate into the preceding
layer; and/or
5. Vibrator in the wrong position relative to the form.
Common imperfections resulting from under-vibration are
honeycomb, excessive entrapped air voids, and layer lines.
Overvibration can occur if vibration is continued for a pro-
longed time (several times the recommended time period).
Overvibration is generally the result of using oversized
equipment, improper procedures, high slump, or improperly
proportioned mixtures. It may result in segregation, exces-
sive form deflection, sand streaking, and form damage.
Backstrom et al. (1958) found that air content of concrete is
decreased by increasing periods of vibration, but little ef-
fect is noted on spacing factor of air-entrained concrete. In
concrete of nominal 6.5 percent air the air content dropped
from 6.7 to 1.2 after 2, 6, 12, 20, 30, and 60 sec of vibration,
but the spacing factor was unchanged as was the number of
cycles to 25 percent loss in mass.
The consequences of overvibration will be minimized if a
well-proportioned mixture with a proper slump is used. The
behavior of fresh concrete during vibration is discussed in
ACI 309.1R.
309.2R-6 MANUAL OF CONCRETE PRACTICE
2.7—Special construction conditions
No matter how carefully a concrete finish is specified, the
resultant quality depends on careful construction site organi-
zation and the use of well-trained and skilled workmen.
Competent supervision is essential to assure that the con-
struction forces properly handle and assemble the forms and
methodically place and consolidate the concrete. Supervisors
must be alert to unfavorable conditions during the installa-
tion of forms and reinforcement and immediately bring these
conditions to the attention of the designer. The designer
should also locate horizontal construction joints at points of
maximum access for placement and consolidation exists.
Combining lifts may restrict access for proper consolidation
and increase the likelihood of surface effects.
Formed concrete surfaces under box outs and battered
forms require special considerations for placement. The mix-
ture may have to be adjusted to produce a readily flowable
concrete that is capable of completely filling the formed area.
For large surface areas, it may be necessary to cut holes in a
battered form to provide access for vibrating the concrete.
With thin layers and careful vibration, the air bubbles can be
drawn up the side of the form. Experience shows that sloped
concrete steeper than about 20 deg from horizontal should be
formed and the concrete thoroughly vibrated to minimize
surface voids. Sloping forms at angles of about 45 deg from
horizontal or less may be erected as temporary forms that are
removed after initial setting for later hand finishing of the
concrete.
Large mass-concrete sections placed in irregularly shaped
forms may have surface blemishes due to non-uniform or
widely spaced locations for tremies, pipes, or chutes. Poorly
planned and executed procedures can cause the concrete to
build up in piles. This will promote segregation, cold joints,
layer lines, honeycomb, and subsidence cracks. To obtain ac-
ceptable results, placing methods must be well planned and
well supervised.
CHAPTER 3—SURFACE BLEMISHES
Surface blemishes that can result from ineffective consol-
idation procedures are discussed below.
3.1—Honeycomb
Honeycomb (Fig. 1) is a condition of irregular voids due
to failure of the mortar to effectively fill the spaces between
coarse aggregate particles. Where bridging of the coarse ag-
gregate particles or stiffness of the mixture is a cause of hon-
eycomb, vibration may assist in overcoming the bridging by
increasing the flowability of the concrete. Factors that may
contribute to honeycombing are: congested reinforcement,
segregation resulting in insufficient paste content, and im-
proper fine aggregate to total aggregate ratio, improper plac-
ing techniques, rapid stiffening of hot concrete, difficult
construction conditions, and insufficient consolidation ef-
fort. Changes in construction practices and in mixture pro-
portions to improve workability and the use of water-
reducing admixtures to increase slump may assist in reduc-
ing or preventing honeycombing.
3.2—Air voids in formed surfaces
Bug holes (Fig. 2) are small regular or irregular cavities,
ranging from nearly invisible to 25 mm (1 in.) but usually not
exceeding 15 mm (9
/16 in.) in diameter, that result from en-
trapment of air bubbles in the surface of formed concrete
during placement and consolidation. Bug holes on vertical
faces are more likely to occur in sticky or stiff concrete mix-
tures of low workability that may have an excessive fine ag-
gregate content or entrapped air content, or both. Also, the
use of vibrators with too high of an amplitude or the lack of
complete insertion of the vibrator head may result in an in-
creased quantity of air-voids. Air voids vary in size from mi-
croscopic to about 25 mm (1 in.). Excess water normally
manifests itself in other textural effects such as bleeding
channels or sand streaks on vertical formed surfaces. Bleed
water voids can form at the top of a column and on battered
formed surfaces. Surface voids can be minimized by the pro-
cedures discussed in Section 4.
3.3—Form streaking
Form streaking (Fig. 3) is caused by mortar leaking through
form joints and tie holes and may be aggravated by overvibra-
tion from vibrators that are too powerful, or by using forms
that vibrate excessively during consolidation.
Placing excessively wet or high-slump concrete mixtures
will result in more mortar washing out through tie holes and
loose fitting forms. Special care is sometimes required when
Fig. 1—Honeycomb.
309.2R-7CONSOLIDATION-RELATED SURFACE DEFECTS
high-range water-reducing admixtures are used, as they tend
to increase leakage at form joints.
3.4—Aggregate transparency
Aggregate transparency (Fig. 4) is a condition character-
ized by a mottled appearance on the surface that results from
deficiencies in the mortar. It may occur when concrete mix-
tures have low fine aggregate content, dry or porous aggre-
gates, or high slump with some lightweight and normal-
weight aggregates. Also, high density or glossy form surfac-
es may cause aggregate transparency.
3.5—Subsidence cracking
Subsidence cracking (Fig. 5) results from the development
of tension when the concrete settles closed to after time of
initial setting. Cracks are caused because the upper concrete
bridges between the forms while the lower concrete settles.
These cracks may occur when there is an insufficient inter-
val between placing the concrete in the columns and placing
the concrete for the slabs or beams. They may also occur ad-
jacent to block-outs or over reinforcing bars with shallow
cover.
To prevent subsidence cracking, the concrete can be revi-
brated. Revibration is most effective when done at the latest
time at which the vibrator head will readily penetrate the
concrete under its own weight. Subsidence cracking over re-
inforcing bars can be controlled by increasing concrete cov-
er during the design phase and by using low-slump concrete
that is well-consolidated.
3.6—Color variation
Color variation (Fig. 6) may occur within a placement if
the concrete is not uniform or is incompletely mixed.
Vibrators inserted too close to the form can cause color
variation by marring the form surface. External vibration
used haphazardly may also cause color variation. Further-
more, color variations may result from nonuniform absorp-
tion, nonuniform application of the release agent, or both.
3.7—Sand streaking
Sand streaking (Fig. 7) is a streak of exposed fine aggre-
gate in the surface of the formed concrete caused by heavy
bleeding along the form.
It frequently results from the use of harsh, wet mixtures,
particularly those deficient in the 300 to 150 µm (No. 50 to
No. 100) and smaller sizes. Streaking tendencies increase
when the ratio of fine aggregate to cementitious materials in-
creases, such as in lean mixtures. Although the characteris-
tics of Portland cement and pozzolans, if used, have some
influence on bleeding, the grading of the fine aggregate is of
greater importance. Sand streaking is controlled by the use of
tight forms, proper mixture proportioning, and using well-
graded fine aggregate to minimize bleeding. Streaking can
be aggravated by excessive vibration, overmanipulation of
the vibrator, the use of a vibrator with excessive amplitude;
or excess water at the bottom of the form forced up along the
form face by hydraulic pressure.
3.8—Layer lines
Layer lines (Fig. 8) are dark horizontal lines on formed sur-
faces that indicate the boundary between concrete placements.
Fig. 2—Air surface voids. Fig. 3—Form streaking.
309.2R-8 MANUAL OF CONCRETE PRACTICE
Layer lines are caused by premature stiffening or insufficient
consolidation of the previous layer of concrete due to lack of
penetration of the vibrator into that layer, or the use of a mor-
tar bonding layer between placements.
3.9—Form offsets
Form offsets (Fig. 9) are usually caused by inadequate
stiffness or anchorage of the forms and can be aggravated by
an excessive rate of placement or by using an excessively
powerful vibrator, or both.
3.10—Cold joints
Cold joints (Fig. 10) can often be avoided by contingency
planning, backup equipment, working to keep the concrete
surface alive, the use of retarding admixtures, and working
the vibrator into lower lifts.
CHAPTER 4—MINIMIZING SURFACE EFFECTS
A number of studies have been made to determine how to
achieve better consolidation resulting in fewer surface blem-
ishes (Shilstone, 1977; Stamenkovic, 1973; Samuelson,
1970; and Reading, 1972). To minimize the size and number
of bug holes and all other effects, the following practices
should be followed:
• Vibration period should be of sufficient duration;
• Vibrator insertions should be properly spaced and over-
lapped and the vibrator removed slowly;
• Each concrete layer should be consolidated from the
bottom upward;
• Vibration periods should be increased on withdrawal
when using impermeable forms that permit air trapped
at the form surface to escape through joints as between;
• Inward sloping forms and other complex design details
should be avoided;
• Depth of placement layers should be limited;
• Vibrator should penetrate into the previous layer;
• Tightening devices and gaskets to prevent leakage at
form joints should be provided as necessary; and
• Placing ports should be designed into the forms as nec-
essary.
Where practical, bug holes can be minimized by the use of
a 65-mm-(21
/2-in.-)-diameter vibrator of high frequency with
Fig. 4—Aggregate transparency.
Fig. 5—Subsidence cracking
Fig. 6—Color variation.
309.2R-9CONSOLIDATION-RELATED SURFACE DEFECTS
medium to low amplitude. The vibrator should be immersed
in the concrete around the perimeter of the form without
damaging the form. Where reinforcement is placed near the
form wall, the vibrator must be inserted inside the reinforce-
ment. Care should be taken to ensure that the vibrator has a
sufficient radius of action to liquefy the concrete at the form.
Form vibration may be used to supplement the internal vi-
bration. However, doing so may cause a major increase in
form pressure. An alternate procedure is to use a high-fre-
quency, low-amplitude form vibrator. Vibration procedures
should be evaluated at the beginning of a project to deter-
mine the vibration time for each type of vibrator for a given
mixture. Guidance on the selection of appropriate vibration
amplitudes, frequencies, and equipment is given in ACI
309R.
In areas where surface air voids are most prevalent, revi-
bration may be used to reduce them. Revibration is more ef-
fective if it is done at the latest possible time at which the
vibrator head will readily penetrate the concrete under its
own weight. Greater benefits are obtained with higher slump
concrete mixtures, especially in the upper portion of a place-
ment where excessive entrapped air voids are most preva-
lent. However, this practice may increase laitance that must
be removed from horizontal construction joints. And may
create color non-uniformity.
Other measures, such as altering mixture proportions, us-
ing high-range water-reducing admixtures, and using small-
er nominal maximum size aggregate to improve workability
Fig. 7—Sand streaking.
Fig. 8—Layer lines.
Fig. 9—Form offsets.
Fig. 10—Cold joints.
309.2R-10 MANUAL OF CONCRETE PRACTICE
should also be considered as methods of minimizing surface
effects, provided that design requirements are met. These
measures have often been successful, particularly when try-
ing to consolidate concrete in congested areas. Further guid-
ance can be obtained from ACI 309R.
CHAPTER 5—CONSOLIDATION OF PREPLACED-
AGGREGATE CONCRETE
The causes and cures of blemishes in concrete produced
by the preplaced-aggregate (PA) concrete method (ACI
304.1R, Chapter 7) are different from conventionally mixed
and placed concrete in certain aspects.
The rate of grout rise in preplaced aggregate should be
about 0.3 m/min (1 ft/min) with a maximum of 0.6 m/min (2
ft/min). If the supply is too rapid, the grout will rise faster
through the large voids and cascade into the smaller ones,
trapping air. The result is spotty honeycombing. To avoid the
occurrence of layer lines, the lower ends of the grout injec-
tion ports should always be maintained at least 0.3 to 0.6 m
(1 to 2 ft) below the grout surface.
Grout will not penetrate pockets of fine aggregate; fines
that collect against side or bottom forms will produce honey-
combing. Also, care should be taken to ensure that coarse ag-
gregate fills the space between the reinforcement and forms,
and that no large voids are left that will be subsequently filled
with grout. Large surface areas of grout not subdivided by
coarse aggregate may show crazing from drying shrinkage.
Coarse aggregate should be saturated when placed and at
the time it is grouted. If rewetting in the forms is required, a
fog spray may be applied sparingly to dampen the upper 0.3
m (1 ft) or so. If the entire mass of aggregate needs re-wet-
ting, the forms should be inundated with water from the bot-
tom, then drained off slowly. Large quantities of water
applied to the top of the aggregate will wash fines to the bot-
tom, resulting in a poor surface or honeycomb.
Light vibration of forms with external vibrators permit the
grout to cover the points of coarse aggregate in contact with
the form. Overvibration of the form should be avoided, how-
ever, as it will induce bleeding that may result in sand streak-
ing. Some trial and error may be required to determine the
optimum amount of form vibration. Form design must be in
conformance with increased pressure. Bolted connections in
formwork require lock washers or double nutting. Formwork
under external vibration requires positive attachment to foot-
ing or previous placement.
Where the appearance of formed surfaces is important, a
test section of comparable height should be produced, the
surface examined, and adjustments made to grading, placing,
and consolidation procedures adjusted to obtain an accept-
able result.
CHAPTER 6—CONCLUSION
Faulty design and construction practices can result in
blemishes in formed concrete surfaces. To keep these effects
within tolerable limits, an awareness of their causes and their
cures is essential. The causes of these effects may lie in
initial design concepts, specification, materials selection,
proportioning, placement, consolidation, or workmanship.
Frequently, the services of a specialist in concrete and con-
crete construction can be used to assist in obtaining concrete
surfaces conforming to the higher standards. The execution
of the work by well-trained work crews under competent su-
pervision will ensure a concrete surface meeting the require-
ments of the owner or designer.
CHAPTER 7—SURFACE CONDITION OUTLINE
The following is an outline of items that should be consid-
ered by designers and constructors when reporting on the
condition of a concrete surface and the possible causes of ef-
fects. By following this checklist and referring to earlier
chapters in this document, the designer or constructor should
then be in a position to identify the cause and correct most
types of surface effects.
1—Description of structure
1.1—Name, location, type, and size
1.2—Owner, project engineer, contractor
1.3—Design
1.3.1—Architect and/or engineer
1.4—Photographs
1.4.1—General view
2—Description of wall, beam, or column showing blemishes.
2.1—Location, size
2.2—Type of concrete
2.2.1—Architectural
2.2.2—Structural
3—Effect
3.1—Name
3.1.1—Description
3.1.2—Photographs
4—Causes
4.1—Design of member
4.1.1—Reinforcement (spacing and size)
4.1.2—Width, depth
4.1.3—Configuration
4.2—Forms
4.2.1—Method
4.2.2—Shape
4.2.3—Anchorage
4.2.4—Insulation
4.2.5—Material type, new or used
4.2.6—Form coatings
4.2.7—Texture and finish
4.2.8—Tightness
4.2.9—Structural adequacy
4.3—Construction conditions
4.3.1—Temperature
4.3.2—Wind
4.3.3—Humidity
4.3.4—Precipitation
4.3.5—Placing accessibility
4.3.6—Precautions, covered in 4.5
4.4—Properties of fresh concrete
4.4.1—Proportions
4.4.2—Workability
309.2R-11CONSOLIDATION-RELATED SURFACE DEFECTS
4.4.3—Grading of aggregate
4.4.4—Slump
4.4.5—Nominal maximum size aggregate
4.4.6—Cohesiveness
4.4.7—Air content
4.4.8—Time of setting
4.5—Placement
4.5.1—Rate
4.5.2—Conditions
4.5.3—Adequacy of equipment
4.6—Consolidation
4.6.1—Frequency
4.6.2—Amplitude
4.6.3—Physical size
4.6.4—Schedule of insertions
4.6.5—Number of vibrators
4.6.6—Depth of penetration
4.6.7—Length of vibration
CHAPTER 8—REFERENCES
8.1—ACI and ASTM Standards
The documents of the various standards-producing orga-
nizations referred to in this report are listed below with their
serial designation.
American Concrete Institute
ACI 116R Cement and Concrete Terminology
ACI 303R Guide to Cast-In-Place Architectural Con-
crete Practice
ACI 304.1R Guide For the Use of Prepackaged-Aggre-
gate Concrete for Structural and Mass
Concrete Applications
ACI 309R Guide for Consolidation of Concrete
ACI 309.1R Behavior of Fresh Concrete During Vi-
bration
ACI 347R Guide to Formwork for Concrete
American Society for Testing Materials
ASTM C 33 Specification for Concrete Aggregates
The above publications may be obtained from:
American Concrete Institute
P.O. Box 9094
Farmington Hills, MI 48333-9094
American Society for Testing Materials
100 Barr Harbor Drive
West Conshohocken, PA 19428-2959
8.2—Cited references
Backstrom, J. E.; Burrows, R. W.; Mielenz, R. C.; and Wolkodorff, V. E.
(1958). “Origin, Evolution and Effects of the Air Void System in Concrete,
Part 3-Influence of Water-Cement Ratio and Compaction,” ACI JOURNAL,
Proceedings V. 55, Sept., pp. 359-375.
International Council for Building Research (1975). “Tolerances on
Blemishes of Concrete,” CIB Report No. 24, International Council for
Building Research Studies and Documentation, Rotterdam, 8 pp.
Mather, B. (1987). “The Warmer the Concrete the Faster the Cement
Hardens,” Concrete International, V. 9, No. 8, August, pp. 29-33.
Shilstone, J. M. (1977). “Surface Blemishes in Formed Concrete," Pro-
ceedings, RILEM/ASTM/CIB Symposium on Performance Evaluation of
External Vertical Surfaces of Buildings (Otaniemi, Espoo, Aug.-Sept.
1977), Technical Research Centre of Finland, Espoo, Finland, pp. 3-7.
Stamenkovic, H. (1973). “Surface Voids Can Be Controlled,” Concrete
Construction, V. 18, No. 12, Dec., pp. 597-598, 600.
Samuelson, P. (1970). “Voids in Concrete Surfaces,” ACI JOURNAL, Pro-
ceedings V. 67, No. 22, Nov., pp. 868-874.
Reading, T. J. (1972). “The Bug Hole Problem,” ACI JOURNAL, Pro-
ceedings V. 69, No. 3, Mar., pp. 165-177.
8.3—Bibliography
King, J. C. (1971). “Special Concretes and Mortars,” Handbook of
Heavy Construction, 2nd Edition, McGraw-Hill Book Co., New York, pp.
22-1 to 22-17.
Fiorato, A. E. (1973). Geometric Imperfections in Concrete Structures
(A Literature Survey), National Swedish Institute for Building Research,
Stockholm, Sweden.
Harding, M. A. (1995). “Vibrating Concrete in Wall Forms,” Concrete
Construction, V. 40, No. 2, Feb., pp. 180-184.
Harrell, T. R., and Goswick, G. M. (1987). “Tunnel Concrete—Consoli-
dation Achieved by a Harmonic Blend of Internal and External Vibration,”
Consolidation of Concrete, SP-96, American Concrete Institute, Farming-
ton Hills, Mich., pp. 102-118.
Holland, T. C.; Husbands, T. B.; Buck, A. D.; and Wong, G. S. (1980).
Concrete Deterioration in Spillway Warm-Water Chute, Raystown Dam.
Pennsylvania (Final Report), U. S. Army Engineer Waterways Experiment
Station, Vicksburg, Miss., Structures Lab. WES/MP/SL-80-19; CTIAC-42,
55 pp.
Houston, B. J. (1967). Methods of Reducing the Size and Number of
Voids on Formed Concrete Surfaces, Report No. TR 6-788, U. S. Army
Engineer Waterways Experiment Station, Vicksburg, Miss., 36 pp.
Hurd, M. K. (1993). “Patterned Form Liners for Architectural Concrete,”
Concrete Construction, V. 38, No. 5, May 5, 5 pp.
Kennedy, T. B. (1960). Investigation of Methods of Finishing Formed
Concrete Surfaces, Report No. TR 6-559, U.S. Army Engineer Waterways
Experimental Station, Vicksburg, Miss., 19 pp.
Kenney, A. R. (1984). “Problems and Surface Blemishes in Architectural
Cast-in-Place Concrete,” Concrete International, V. 6, No. 1, Jan., pp. 50-55.
Kenney, A. R., and Kenney, B. P. (1986). “Problems and Repairs in Tilt-
Up Construction,” Concrete International, V. 8, No. 6, Jun., pp. 41-50.
Mass, G. R. (1987). “Consolidation of Concrete,” Lewis H. Tuthill Inter-
national Symposium on Concrete and Concrete Construction, SP-104,
Gant T. Halvorsen, ed., American Concrete Institute, Farmington Hills,
Mich., pp. 185-204.
Reading, T. J. (1985), “Deleterious Affects of Wood Forms on Concrete
Surfaces, Concrete International, V. 7, No. 11, Nov., pp. 57-62.
Sansalone, M., and Carino, N. J. (1988). “Impacted-Echo Method:
Detecting Honeycombing, Depth of Surface-Opening Cracks, and
Ungrouted Ducts (Final Report),” Concrete International, V. 10, No. 4,
Apr., pp. 38-46.
Shilstone, J. M. (1979). “Surface Blemishes in Formed Concrete,” Con-
crete Construction, V. 24, No. 11, Nov., pp. 719 and 765.
Smith, John R. (1984). “Architectural Concrete: Defects Demand Dis-
cretion,” Concrete International, V. 6 No. 1, Jan., pp. 64-66.
Watanaba, T., and Uomoto, T. (1993). “Monitoring Concrete Placing by
Infrared Image Analysis,” Doboku Gakkai Rombun-Hokokushu/ Proceed-
ings of the Japan Society of Civil Engineers, No. 478, Part 50-21, pp. 55-59.

More Related Content

What's hot

207.2 r 95 - effect on restraint, volume change and reinforce
207.2 r 95 - effect on restraint, volume change and reinforce207.2 r 95 - effect on restraint, volume change and reinforce
207.2 r 95 - effect on restraint, volume change and reinforceMOHAMMED SABBAR
 
IRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete Beams
IRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete BeamsIRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete Beams
IRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete BeamsIRJET Journal
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Shanmugasundaram N
 
Design structural steel_design_and_construction
Design structural steel_design_and_constructionDesign structural steel_design_and_construction
Design structural steel_design_and_constructionDurim Bajrami
 
211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportions211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportionsMOHAMMED SABBAR
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSShanmugasundaram N
 
Zamil steel design manual
Zamil steel design manualZamil steel design manual
Zamil steel design manualThTrnthqunh
 
Plain and-reinforced-concrete(IS 456 2000)
Plain and-reinforced-concrete(IS 456 2000)Plain and-reinforced-concrete(IS 456 2000)
Plain and-reinforced-concrete(IS 456 2000)Parvez Alam
 
224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structures224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structuresMOHAMMED SABBAR
 
is 456 amendment 4
is 456 amendment 4is 456 amendment 4
is 456 amendment 4jemmabarsby
 
Design with structural_steel_-_a_guide_for_architects
Design with structural_steel_-_a_guide_for_architectsDesign with structural_steel_-_a_guide_for_architects
Design with structural_steel_-_a_guide_for_architectsĐức Tính Nguyễn
 
213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concretMOHAMMED SABBAR
 

What's hot (19)

207.2 r 95 - effect on restraint, volume change and reinforce
207.2 r 95 - effect on restraint, volume change and reinforce207.2 r 95 - effect on restraint, volume change and reinforce
207.2 r 95 - effect on restraint, volume change and reinforce
 
AC 434 DESIGN CRITERIA - RUREDIL
AC 434 DESIGN CRITERIA - RUREDILAC 434 DESIGN CRITERIA - RUREDIL
AC 434 DESIGN CRITERIA - RUREDIL
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
117 90
117 90117 90
117 90
 
IRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete Beams
IRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete BeamsIRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete Beams
IRJET- Analysis and Synthesis of Extrnally Plated Reinforced Concrete Beams
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
 
Is 456 2000
Is 456 2000Is 456 2000
Is 456 2000
 
Design structural steel_design_and_construction
Design structural steel_design_and_constructionDesign structural steel_design_and_construction
Design structural steel_design_and_construction
 
211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportions211.5 r 96 - guide for submittal of concrete proportions
211.5 r 96 - guide for submittal of concrete proportions
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
 
Concrete repair
Concrete repairConcrete repair
Concrete repair
 
Zamil steel design manual
Zamil steel design manualZamil steel design manual
Zamil steel design manual
 
Plain and-reinforced-concrete(IS 456 2000)
Plain and-reinforced-concrete(IS 456 2000)Plain and-reinforced-concrete(IS 456 2000)
Plain and-reinforced-concrete(IS 456 2000)
 
Is code 456 2000
Is code 456 2000Is code 456 2000
Is code 456 2000
 
456
456456
456
 
224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structures224 r 90 - control of cracking in concrete structures
224 r 90 - control of cracking in concrete structures
 
is 456 amendment 4
is 456 amendment 4is 456 amendment 4
is 456 amendment 4
 
Design with structural_steel_-_a_guide_for_architects
Design with structural_steel_-_a_guide_for_architectsDesign with structural_steel_-_a_guide_for_architects
Design with structural_steel_-_a_guide_for_architects
 
213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret213 r 87 - guide for structural lightweight aggregate concret
213 r 87 - guide for structural lightweight aggregate concret
 

Similar to 309.2 r 98 - identification and control visible effects of co

ACI 347R-14_Guía de encofrados para hormigón.pdf
ACI 347R-14_Guía de encofrados para hormigón.pdfACI 347R-14_Guía de encofrados para hormigón.pdf
ACI 347R-14_Guía de encofrados para hormigón.pdfMarianoAcimut
 
309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concrete309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concreteMOHAMMED SABBAR
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measuressabnisajit
 
Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...
Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...
Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...ecmaida
 
An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...IRJET Journal
 
309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested 309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested MOHAMMED SABBAR
 
ACI 318 - 02 (Ingles)
ACI 318 - 02 (Ingles)ACI 318 - 02 (Ingles)
ACI 318 - 02 (Ingles)TheJamez
 
A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...
A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...
A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...IRJET Journal
 
Causes, Detection And Repair Of Cracks in Building
Causes, Detection And Repair Of Cracks in BuildingCauses, Detection And Repair Of Cracks in Building
Causes, Detection And Repair Of Cracks in BuildingIRJET Journal
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergiesAnkit Patel
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET Journal
 
Investigating the causes and remedies for porosity defects in the casting pro...
Investigating the causes and remedies for porosity defects in the casting pro...Investigating the causes and remedies for porosity defects in the casting pro...
Investigating the causes and remedies for porosity defects in the casting pro...bijejournal
 
ACI 318 - 99 (Ingles)
ACI 318 - 99 (Ingles)ACI 318 - 99 (Ingles)
ACI 318 - 99 (Ingles)TheJamez
 
IRJET- Case Study on Diagnosis and Repair of Failuers in RCC Building
IRJET- Case Study on Diagnosis and Repair of Failuers in RCC BuildingIRJET- Case Study on Diagnosis and Repair of Failuers in RCC Building
IRJET- Case Study on Diagnosis and Repair of Failuers in RCC BuildingIRJET Journal
 
Design corrosion
Design   corrosion Design   corrosion
Design corrosion Ali Zamel
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...Alexander Decker
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...Alexander Decker
 
Analysis of Foundation Failure in Concrete Structure
Analysis of Foundation Failure in Concrete StructureAnalysis of Foundation Failure in Concrete Structure
Analysis of Foundation Failure in Concrete StructureIRJET Journal
 

Similar to 309.2 r 98 - identification and control visible effects of co (20)

Aci 309.2 r 98
Aci 309.2 r 98Aci 309.2 r 98
Aci 309.2 r 98
 
ACI 347R-14_Guía de encofrados para hormigón.pdf
ACI 347R-14_Guía de encofrados para hormigón.pdfACI 347R-14_Guía de encofrados para hormigón.pdf
ACI 347R-14_Guía de encofrados para hormigón.pdf
 
309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concrete309 r 96 - guide for consolidation of concrete
309 r 96 - guide for consolidation of concrete
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measures
 
Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...
Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...
Aci 222.3 r 11 guide to design and construction practices to mitigate corrosi...
 
An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...An Empirical Investigation into the Origins and Causes of Variation Orders in...
An Empirical Investigation into the Origins and Causes of Variation Orders in...
 
309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested 309.3 r 92 - guide to consolidation of concrete in congested
309.3 r 92 - guide to consolidation of concrete in congested
 
Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...
Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...
Analysis Of Concreting Process’s Productivity In The Distrito Federal: Charac...
 
ACI 318 - 02 (Ingles)
ACI 318 - 02 (Ingles)ACI 318 - 02 (Ingles)
ACI 318 - 02 (Ingles)
 
A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...
A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...
A Review on Causes, Prevention, Repair and Maintenance of Cracks in Building ...
 
Causes, Detection And Repair Of Cracks in Building
Causes, Detection And Repair Of Cracks in BuildingCauses, Detection And Repair Of Cracks in Building
Causes, Detection And Repair Of Cracks in Building
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergies
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case Study
 
Investigating the causes and remedies for porosity defects in the casting pro...
Investigating the causes and remedies for porosity defects in the casting pro...Investigating the causes and remedies for porosity defects in the casting pro...
Investigating the causes and remedies for porosity defects in the casting pro...
 
ACI 318 - 99 (Ingles)
ACI 318 - 99 (Ingles)ACI 318 - 99 (Ingles)
ACI 318 - 99 (Ingles)
 
IRJET- Case Study on Diagnosis and Repair of Failuers in RCC Building
IRJET- Case Study on Diagnosis and Repair of Failuers in RCC BuildingIRJET- Case Study on Diagnosis and Repair of Failuers in RCC Building
IRJET- Case Study on Diagnosis and Repair of Failuers in RCC Building
 
Design corrosion
Design   corrosion Design   corrosion
Design corrosion
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
 
Analysis of Foundation Failure in Concrete Structure
Analysis of Foundation Failure in Concrete StructureAnalysis of Foundation Failure in Concrete Structure
Analysis of Foundation Failure in Concrete Structure
 

More from MOHAMMED SABBAR

309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibration309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibrationMOHAMMED SABBAR
 
304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweight304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweightMOHAMMED SABBAR
 
304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyors304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyorsMOHAMMED SABBAR
 
304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transpor304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transporMOHAMMED SABBAR
 
303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete prac303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete pracMOHAMMED SABBAR
 
234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concrete234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concreteMOHAMMED SABBAR
 
233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituen233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituenMOHAMMED SABBAR
 
232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concrete232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concreteMOHAMMED SABBAR
 
223 98 standard practice for the use of shrinkge-compensat
223 98   standard practice for the use of shrinkge-compensat223 98   standard practice for the use of shrinkge-compensat
223 98 standard practice for the use of shrinkge-compensatMOHAMMED SABBAR
 
222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concrete222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concreteMOHAMMED SABBAR
 
221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reac221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reacMOHAMMED SABBAR
 
214 77 recommended practice for evaluation of strength tes
214 77   recommended practice for evaluation of strength tes214 77   recommended practice for evaluation of strength tes
214 77 recommended practice for evaluation of strength tesMOHAMMED SABBAR
 
214.3 r 88 - simplified version of the recommended practice f
214.3 r 88 - simplified version of the recommended practice f214.3 r 88 - simplified version of the recommended practice f
214.3 r 88 - simplified version of the recommended practice fMOHAMMED SABBAR
 
211.4 r 93 guide for selecting proportions for high-strength
211.4 r 93 guide for selecting proportions for high-strength 211.4 r 93 guide for selecting proportions for high-strength
211.4 r 93 guide for selecting proportions for high-strength MOHAMMED SABBAR
 
207.1 r 96 - mass concrete
207.1 r 96 - mass concrete207.1 r 96 - mass concrete
207.1 r 96 - mass concreteMOHAMMED SABBAR
 
201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concrete201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concreteMOHAMMED SABBAR
 

More from MOHAMMED SABBAR (16)

309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibration309.1 r 93 - behavior of fresh concrete during vibration
309.1 r 93 - behavior of fresh concrete during vibration
 
304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweight304.5 r 91 - batching, mixing, and job control of lightweight
304.5 r 91 - batching, mixing, and job control of lightweight
 
304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyors304.4 r 95 - placing concrete with belt conveyors
304.4 r 95 - placing concrete with belt conveyors
 
304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transpor304.3 r 96 - heavyweight concrete measuring, mixing, transpor
304.3 r 96 - heavyweight concrete measuring, mixing, transpor
 
303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete prac303 r 91 - guide to cast-in place architectural concrete prac
303 r 91 - guide to cast-in place architectural concrete prac
 
234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concrete234 r 96 - guide for the use of silica flume in concrete
234 r 96 - guide for the use of silica flume in concrete
 
233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituen233 r 95 - ground granulated blast-furnace slag as constituen
233 r 95 - ground granulated blast-furnace slag as constituen
 
232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concrete232.2 r 96 - use of fly ash in concrete
232.2 r 96 - use of fly ash in concrete
 
223 98 standard practice for the use of shrinkge-compensat
223 98   standard practice for the use of shrinkge-compensat223 98   standard practice for the use of shrinkge-compensat
223 98 standard practice for the use of shrinkge-compensat
 
222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concrete222 r 96 - corrosion of metals in concrete
222 r 96 - corrosion of metals in concrete
 
221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reac221.1 r 98 - state-of-the-art report on alkali-aggregate reac
221.1 r 98 - state-of-the-art report on alkali-aggregate reac
 
214 77 recommended practice for evaluation of strength tes
214 77   recommended practice for evaluation of strength tes214 77   recommended practice for evaluation of strength tes
214 77 recommended practice for evaluation of strength tes
 
214.3 r 88 - simplified version of the recommended practice f
214.3 r 88 - simplified version of the recommended practice f214.3 r 88 - simplified version of the recommended practice f
214.3 r 88 - simplified version of the recommended practice f
 
211.4 r 93 guide for selecting proportions for high-strength
211.4 r 93 guide for selecting proportions for high-strength 211.4 r 93 guide for selecting proportions for high-strength
211.4 r 93 guide for selecting proportions for high-strength
 
207.1 r 96 - mass concrete
207.1 r 96 - mass concrete207.1 r 96 - mass concrete
207.1 r 96 - mass concrete
 
201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concrete201.2 r 92 - guide to durable concrete
201.2 r 92 - guide to durable concrete
 

Recently uploaded

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 

Recently uploaded (20)

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

309.2 r 98 - identification and control visible effects of co

  • 1. ACI 309.2R-98 became effective August 19, 1998. This document supercedes ACI 309.2R-90. Copyright © 1998, American Concrete Institute. All rights reserved including rights of reproduction and use in any form or by any means, including the making of copies by any photo process, or by electronic or mechanical device, printed, written, or oral, or recording for sound or visual reproduc- tion or for use in any knowledge or retrieval system or device, unless permission in writing is obtained from the copyright proprietors. ACI Committee Reports, Guides, Standard Practices, and Commentaries are intended for guidance in planning, design- ing, executing, and inspecting construction. This document is intended for the use of individuals who are competent to evaluate the significance and limitations of its content and recommendations and who will accept responsibility for the application of the material it contains. The American Concrete Institute disclaims any and all responsibility for the stated principles. The Institute shall not be liable for any loss or damage arising therefrom. Reference to this document shall not be made in contract documents. If items found in this document are desired by the Architect/Engineer to be a part of the contract docu- ments, they shall be restated in mandatory language for in- corporation by the Architect/Engineer. 309.2R-1 This report provides guidelines for identifying and controlling visible effects of consolidation on precast or cast-in-place formed concrete sur- faces. It includes a summary of direct and indirect causes of such imperfec- tions. An outline to assist in the reporting on surfaces and photographs to illustrate typical concrete surface blemishes are also included. Surface blemishes in concrete may be minimized by proper planning dur- ing the design and specification stages. Of equal importance is the employ- ment of properly trained and motivated supervisory and non-supervisory construction personnel to achieve the intended concrete finishes and sur- face textures. The report emphasizes significant consolidation factors that minimize undesirable surface effects. The reader is cautioned that other potential causes of such effects may exist beyond those listed in this report. There are documents in which a feature designated as a defect is one that must be prevented, avoided, corrected, remmediated or otherwise dealt with. The term “defect,” as formerly used in this report, covers blemishes and depar- tures from perfection that are not features, and must be avoided or repaired whenever they occur. Some surfaces can tolerate them to some or any degree; other surfaces cannot. It is the responsibility of the specifier to indicate in the contract documents what constitutes acceptable and unac- ceptable blemishes for the various surfaces to be produced under the terms of a given contract. Terms used in this report are as defined in ACI 116 R. Keywords :aggregates; bugholes; concretes; consistency; consolidation; construction joints; discoloration; formwork (construction); mix propor- tioning; placing; preplaced-aggregate concrete; quality control; surface defects; temperature; vibration; voids; workability. CONTENTS Chapter 1—General Chapter 2—Factors causing blemishes 2.1—Design of structural members 2.2—Specifications 2.3—Forms 2.4—Properties of fresh concrete 2.5—Placement 2.6—Consolidation 2.7—Special construction conditions Chapter 3—Surface blemishes 3.1—Honeycomb 3.2 —Air voids in surfaces 3.3— Form streaking Identification and Control of Visible Effects of Consolidation on Formed Concrete Surfaces ACI 309.2R-98 Reported by ACI Committee 309 H. Celik Ozyildirim Chairman Neil A. Cumming Kenneth C. Hover Larry D. Olson Timothy P. Dolen Gary R. Mass Steven A. Ragan Jerome H. Ford Bryant Mather Donald L. Schlegel Steven H. Gebler Richard E. Miller Brad K. Violetta Glen A. Heimbruch Revising Committee: Jerome H. Ford Chairman Dan Bonikowsky Gary R. Mass Steven A. Ragan Neil A. Cumming Bryant Mather Donald L. Schlegel Timothy P. Dolen Richard E. Miller Brad K. Violetta Steven H. Gebler H. Celik Ozyildirim
  • 2. 309.2R-2 MANUAL OF CONCRETE PRACTICE 3.4—Aggregate transparency 3.5—Subsidence cracking 3.6—Color variation 3.7—Sand streaking 3.8—Layer lines 3.9—Form offsets 3.10—Cold joints Chapter 4—Minimizing surface effects Chapter 5—Consolidation of preplaced-aggregate concrete Chapter 6—Conclusion Chapter 7—Surface condition outline Chapter 8—References 8.1—Recommended references 8.2—Cited references CHAPTER 1—GENERAL A formed concrete surface, uniformly smooth or deeply textured and essentially free of blemishes and color varia- tion, is difficult to attain. Since repairs to a defective surface are costly and seldom fully satisfactory, the need for repairs should be minimized by establishing and maintaining the quality of the concrete operation and by adhering to accept- able consolidation procedures. Standards for surface finishes are beyond the scope of this report. Guidance for establish- ing appropriate standards is offered by the International Council for Building Research (CIB) (1975), which classi- fies formed surface finishes as follows: • Special—High standards of appearance required (ACI 303R); • Elaborate—Definite requirements for visual appear- ance; • Ordinary—Appearance is of some importance; and • Rough—No special requirements for finish. Concrete construction procedures do not always provide the control necessary to consistently obtain blemish free con- crete indicated by a special category. To achieve any concrete finish, the designer and the con- tractor must use materials as well as design and construction practices that will keep surface effects within acceptable lim- its. There is a definite need for understanding the causes of unacceptable blemishes and effects encountered in concrete construction and a need for applying more effective mea- sures to minimize or eliminate them. This report addresses those needs and its major emphasis is on consolidation- related effects. The most serious effects resulting from ineffective consol- idation procedures are: honeycomb, subsidence cracks, cold joints, and excessive surface voids. A detailed description of the blemishes and their causes are provided in Table 1. Some imperfections may not conform to contract documents and may be considered as defective work. CHAPTER 2—FACTORS CAUSING EFFECTS Causes of consolidation-related effects on formed con- crete surfaces (Table 1) include: A. Design and construction-related causes • Difficult placement due to design of a member • Improper selection of horizontal construction joint location • Improper design, manufacture, installation, shipping, preparation and maintenance of forms • Improper selection of concrete mixture proportions • Failure to adjust concrete mixture proportions to suit placement condition • Improper placement practices • Improper consolidation practices • Improper steel detailing B. Equipment-related causes • Improper equipment • Improper equipment maintenance • Equipment failure (crane, pump, concrete plant) • Interruption of utility service C. Material-related causes • Improper selection of release agent • Cement characteristics • Variation in mixture constituents • Inappropriate use of admixtures D. Environmental causes • Extreme weather conditions Examples of some of the more common blemishes are illus- trated in Fig. 1 through 10. 2.1—Design of structural members The common problems requiring consideration during de- sign and planning are congested reinforcement (particularly splices), narrow sections, or complex form configurations. Conditions that require closed top forming, embedments, and battered forms also require consideration during design and planning. To produce properly consolidated concrete with the de- sired appearance, the placement and consolidation of the concrete must be understood. The designer must have a working knowledge of the concrete placement process. The designer and the constructor should communicate during the early phases of the concreting process. Early recognition of problem areas is important to provide time to take remedial measures, such as staggering splices, grouping reinforcing steel, modifying stirrup spacing, increasing the section size, and selecting locations of horizontal construction joints. When unfavorable conditions exist that could contribute to substandard surfaces, one or more of the following actions should be taken: 1. Redesign the member; 2. Redesign the reinforcing steel; 3. Provide adequate access for consolidation at horizontal construction joints; 4. Modify mixture proportions; 5. Use mock-up tests to develop a procedure; and/or 6. Alert the constructor to critical conditions.
  • 3. 309.2R-3CONSOLIDATION-RELATED SURFACE DEFECTS Defects Causes Name Description Fig. Design of Members 1 Forms 2 Construction Conditions 3 Properties of Fresh Concrete 4 Placement 5 Consolidation 6 Honeycomb Stony zone with air voids; lacking in fines. Due to segregation 1 Highly congested reinforcement, narrow section, inter- nal interfer- ence, reinforcement splices, restricted access for vibration, high monolithic lifts Leaking at joints, severe grout loss Premature setting reinforcement too close to forms, lack of access for vibration, congestion due to splices Insufficient fines, low workability, early stiffening, excessive mixing, too largeaggregate for placing conditions Excessive free fall, excessive lift of concrete in forms, drop chute omitted, or insufficient length, too small a tremie, segregation due to horizontal movement Vibrator too small, frequency and amplitude inappropriate, too short immersion time, exces- sive spacing between immersions, inadequate penetration insufficient number of vibrators Air surface voids Small individ- ual holes, irregular, ranging up to 1 in. (25mm) in diameter 2 Battered or interfering construction Form face impermeable, poor wetting characteris- tics, formwork too flexible, use of improper form release agent Excessive release agent, high tempera- ture of con- crete. Low FM of fine aggregate, lean, fine aggregate with a high FM, low workability, excessive cement or pozzolan, par- ticle degrada- tion, excessive sand, high air content Too slow, caused by inadequate pumping rate, undersized bucket Too large an amplitude, external vibration inadequate, head of vibrator partially immersed Form- streaking Fine aggregate or coarse aggregate tex- tured areas lacking cement, usu- ally associated with dark color on adjacent surface 3 Leaking at joints, tie holes, caused by loose hard- ware or over sized tie holes Usuallycaused by horizontal concrete movement Excess water or high slump Improper tim- ing between placing and vibrating Excessive amplitude or frequency for form design Aggregate transparency Dark or light areas of similar size and shape to that of the coarse aggre- gate, mottled appearance 4 Too flexible, high-density surface finish Low fine- aggregate con- tent, gap- graded aggre- gate dry or porous aggre- gate, exces- sive coarse aggregate, excessive slump with lightweight concrete Excessive external vibration; overvibration of lightweight concrete Subsidence cracking Short cracks varying in width, more often horizon- tal than verti- cal 5 Interference to access, lack of adequate cover Poor thermal insulation, irregular shape restraining set- tlement, exces- sive absorbency Insufficient delay between top-out of columns and placement of slab or beam, low humidity Low fine aggregate, high water content, too high slump, Poorly propor- tioned mixes Too rapid Insufficient vibration and lack of revibration Table 1—Summary of primary causes of surface effects 2.2—Specifications Acceptable specifications for concrete and concrete con- struction are essential to ensure proper construction practices. Practical and workable specifications that allow for unusual and complex job conditions are needed. Specifications should be sufficiently broad in scope to per- mit adjustments of mixture proportions and batch adjust- ments needed to produce uniformly workable concrete that will respond readily to vibration. Concrete may still vary due to changes in aggregate grading, ambient and concrete tem- perature, air content, and batch quantities, even though these changes are within specification limits. Accepted mixture proportions may need adjustments to produce the desired concrete characteristics and to minimize consolidation prob- lems. However, the mixture should be adjusted with care to maintain the design intent and to avoid other problems, such as excessive cracking. The specifications should require mixing, transporting, handling, and placing that can result in adequate consolidation and minimize chances for surface blemishes. Moreover, the specifications should call for vibrators of proper size and characteristics, as recommended in ACI 309R. Small-diameter vibrators should be required to supplement larger-diameter vibrators where access is limited.
  • 4. 309.2R-4 MANUAL OF CONCRETE PRACTICE 2.3—Forms Some surface blemishes are caused by inadequacies of the formwork. Examples are leakage at joints, inadequate facing material, excessive overload on previously placed concrete (ACI 303R), inadequate anchorage, poorly braced and ex- cessively flexible forms, improper use of release agents, and oversized and unsealed tie holes. Surface blemishes also re- sult from overuse of forms, poor storage practices, inade- quate cleaning, and improper patching and repair of the forms. The number of visible surface voids (bug holes) may be re- duced by using absorptive forms; however, smooth forms in combination with the correct selection of a form release- agent allow air voids at formed surfaces to move upward more freely. ACI 303R discusses the use of release agents. Some dry resin-based release agents used on steel forms will greatly increase the number of bug holes. An excessive amount of release agent collecting in the bottom of the form may result in discoloration of the concrete and may create weak areas. Inadequately cleaned forms, or those which have been reused too many times, can contribute significantly to the formation of surface blemishes. When any of these conditions occurs, the concrete surface may peel during form removal. The finish should be observed as the form is stripped so that appropriate corrective measures, if needed, can be im- plemented promptly. Inward sloping forms have a tendency to trap or restrict the movement of entrapped air and bleed water to the surface, and increase the occurrence of surface effects. Form strength, design, and other form requirements are covered in ACI 347R. 2.4—Properties of fresh concrete The composition, consistency, workability, and tempera- ture of fresh concrete has a significant bearing on the ease with which a concrete mixture may be placed and consoli- dated. For critical surface finishes, the effect of each ingre- dient of the mixture may require special consideration. Placing conditions should also be considered during mixture proportioning. Mixture adjustments should be made to the proportions to maintain workability when materials and field conditions change, provided that critical properties, such as durability and strength, are maintained. Defects Causes Name Description Fig. Design of Members 1 Forms 2 Construction Conditions 3 Properties of Fresh Concrete 4 Placement 5 Consolidation 6 Color variation Variations in color of the surface, visible within a few hours after removing the formwork 6 Heavy rein- forcement close to forms Variation in absorptive capacity of surface, reac- tion with form face, chemical reaction with release agents, leakage of forms at joints and tie holes Non-uniform color of mate- rials, inconsis- tent grading, variation in proportions, incomplete mixing. Cal- cium chloride can cause darker color. Too high a slump. Over- manipulation Segregation slump too high Vibrator too close to form, vibration next to forms vari- able Sand streaking Variation in color or shade due to separa- tion of fine particles 7 Form leakage Excess water at bottom of form forced up along form face by hydraulic pressure Low tempera- ture, wet mix- tures Lean “over- sanded” mixtures and harsh, wet mixtures deficient in fines Too rapid for type of mixture Excessive vibration. Excessive amplitude. Over- manipulation Layer lines (pore lines) Dark colored zones between concrete layers 8 Internal interference Insufficient planning, high temperature Wet mixture with tendency to bleed Slow place- ment, lack of equipment or manpower Lack of vibra- tion, failure to penetrate into previous layer Cold joints Voids, honey- comb and color varia- tions along boundaries of lifts, top layer of concrete not adequately bonded to sub- strate 9 Insufficient space to insert vibrator Poor planning or insufficient backup equip- ment, substrate concrete has set. Too dry, early stiffening, slump loss Delayed delivery, lifts too thick Failure to vibrate into lower lift. Insufficient vibration Form offsets Abrupt to gradualsurface irregularities 10 Construction joint at change in direction of formwork Inadequate formwork design for rate of placement Poor form anchorage and inadequate bulkheads Excessive retardation of time of setting of concrete Rate too high Excessive amplitude, non-uniform spacing of immersion horizontal movement of concrete Table 1—continued
  • 5. 309.2R-5CONSOLIDATION-RELATED SURFACE DEFECTS A review by the designer is essential to ensure that strength levels, nominal maximum aggregate size, and slump requirements for different structural elements are met. Concrete ingredients should be evaluated and proportions should be selected well in advance of the concreting opera- tion to achieve the desired properties for the fresh concrete. Sticky mixtures may occur if the fine aggregate grading in the 1.18 mm to 300 µm (No. 16 to 50) size range approaches the upper limits specified by ASTM C 33, or if high cement contents are used. Some pozzolans also may cause mixtures to be more cohesive. Thus, the passage of entrapped air may be restricted and air voids may be trapped at the interface be- tween the concrete and the form. If fine aggregate contains the proper amount of materials in the 600 to 300 µm (No. 30 to 50) size range, little bleeding will occur in the resulting concrete. As a result, placement and consolidation of the concrete will be facilitated, thereby minimizing surface effects. Soft aggregates may degrade and produce additional fines. In some instances, the fines may make the mixture more co- hesive and increase the difficulty of removing entrapped air. This is particularly true at high cementitious materials con- tents. In other instances, the additional fines can significantly increase the water demand, resulting in lower strength, in- creased shrinkage, and crazing of smooth formed surfaces. Experience indicates that a concrete at a given consistency will generally flow more easily at lower temperatures than at higher temperatures. When chemical and especially mineral admixtures are used, their effect on placement and consolidation should be evaluated when mixture proportions are being established. All of the factors discussed above need to be considered to obtain a concrete mixture with the desired composition, consistency, and workability to facilitate its placement and consolidation. 2.5—Placement Concrete should be placed as quickly as possible with a minimum amount of segregation and spattering on the forms. Once the coarse aggregate is separated from the mor- tar by poor handling and placement practice, it is virtually impossible to work the mortar back into the voids and restore a dense mass by vibration. Segregation and separation cause honeycomb. Spattered mortar on the form produces color variations and poor surface texture. Placing concrete too slowly may allow workability to be lost and can produce lay- er lines or cold joints due to improper consolidation. The rate of placement and vibration factors (intensity and spacing) should be selected to minimize entrapped air in the concrete. If concrete is deposited in thick layers of more than 300 mm (12 in.), more air may be trapped than if it is placed in a thinner, even layer since the air has to travel farther to es- cape. Where mixtures of dry or stiff consistencies are re- quired, the placement rate should be slower to permit adequate consolidation so as to avoid bug holes and honey- combing. However, in the case of a sanitary treatment struc- ture with steel forms, an increase in lift thickness from 0.6 to 1.2 m (2 to 4 ft) reduced bug holes by 50 percent when an air content of 5 percent was specified. 2.6—Consolidation Concrete consists of coarse aggregate particles in a matrix of mortar, and irregularly distributed pockets of entrapped air. If the concrete is air entrained, an additional evenly dis- tributed system of entrained air bubbles is present. The vol- ume of entrapped air in unconsolidated concrete may vary from about 5 to 20 percent depending on the workability of the mixture, size and shape of the form, amount of reinforc- ing steel, and method of depositing the concrete. The pur- pose of consolidation is to remove as much of this entrapped air as practical. Vibration is the most common method of consolidation. It causes very rapid movement of the concrete mixture parti- cles and briefly liquefies the mixture, thus reducing the inter- nal friction. When vibrated, concrete becomes fluid and through the action of gravity seeks a lower level and denser condition as entrapped air rises to the surface and is expelled. It compacts laterally against the form and around the rein- forcing steel. In practice, vibration is normally continued un- til the entire placement acquires a uniform appearance and its surface just starts to glisten or large bubbles cease to ap- pear. A film of cement paste should be discernible between the concrete and the forms. These visual indicators are not necessarily an accurate indication of good consolidation. ACI 309R provides guidance on judging the adequacy of vibration. Undervibration is far more common than overvibration, and may be caused by the following: 1. Use of an undersized, underpowered, or poorly main- tained vibrator; 2. Excessive or haphazard spacing of vibrator insertions; 3. Inadequate vibration during each insertion; 4. Failure of the vibrator to penetrate into the preceding layer; and/or 5. Vibrator in the wrong position relative to the form. Common imperfections resulting from under-vibration are honeycomb, excessive entrapped air voids, and layer lines. Overvibration can occur if vibration is continued for a pro- longed time (several times the recommended time period). Overvibration is generally the result of using oversized equipment, improper procedures, high slump, or improperly proportioned mixtures. It may result in segregation, exces- sive form deflection, sand streaking, and form damage. Backstrom et al. (1958) found that air content of concrete is decreased by increasing periods of vibration, but little ef- fect is noted on spacing factor of air-entrained concrete. In concrete of nominal 6.5 percent air the air content dropped from 6.7 to 1.2 after 2, 6, 12, 20, 30, and 60 sec of vibration, but the spacing factor was unchanged as was the number of cycles to 25 percent loss in mass. The consequences of overvibration will be minimized if a well-proportioned mixture with a proper slump is used. The behavior of fresh concrete during vibration is discussed in ACI 309.1R.
  • 6. 309.2R-6 MANUAL OF CONCRETE PRACTICE 2.7—Special construction conditions No matter how carefully a concrete finish is specified, the resultant quality depends on careful construction site organi- zation and the use of well-trained and skilled workmen. Competent supervision is essential to assure that the con- struction forces properly handle and assemble the forms and methodically place and consolidate the concrete. Supervisors must be alert to unfavorable conditions during the installa- tion of forms and reinforcement and immediately bring these conditions to the attention of the designer. The designer should also locate horizontal construction joints at points of maximum access for placement and consolidation exists. Combining lifts may restrict access for proper consolidation and increase the likelihood of surface effects. Formed concrete surfaces under box outs and battered forms require special considerations for placement. The mix- ture may have to be adjusted to produce a readily flowable concrete that is capable of completely filling the formed area. For large surface areas, it may be necessary to cut holes in a battered form to provide access for vibrating the concrete. With thin layers and careful vibration, the air bubbles can be drawn up the side of the form. Experience shows that sloped concrete steeper than about 20 deg from horizontal should be formed and the concrete thoroughly vibrated to minimize surface voids. Sloping forms at angles of about 45 deg from horizontal or less may be erected as temporary forms that are removed after initial setting for later hand finishing of the concrete. Large mass-concrete sections placed in irregularly shaped forms may have surface blemishes due to non-uniform or widely spaced locations for tremies, pipes, or chutes. Poorly planned and executed procedures can cause the concrete to build up in piles. This will promote segregation, cold joints, layer lines, honeycomb, and subsidence cracks. To obtain ac- ceptable results, placing methods must be well planned and well supervised. CHAPTER 3—SURFACE BLEMISHES Surface blemishes that can result from ineffective consol- idation procedures are discussed below. 3.1—Honeycomb Honeycomb (Fig. 1) is a condition of irregular voids due to failure of the mortar to effectively fill the spaces between coarse aggregate particles. Where bridging of the coarse ag- gregate particles or stiffness of the mixture is a cause of hon- eycomb, vibration may assist in overcoming the bridging by increasing the flowability of the concrete. Factors that may contribute to honeycombing are: congested reinforcement, segregation resulting in insufficient paste content, and im- proper fine aggregate to total aggregate ratio, improper plac- ing techniques, rapid stiffening of hot concrete, difficult construction conditions, and insufficient consolidation ef- fort. Changes in construction practices and in mixture pro- portions to improve workability and the use of water- reducing admixtures to increase slump may assist in reduc- ing or preventing honeycombing. 3.2—Air voids in formed surfaces Bug holes (Fig. 2) are small regular or irregular cavities, ranging from nearly invisible to 25 mm (1 in.) but usually not exceeding 15 mm (9 /16 in.) in diameter, that result from en- trapment of air bubbles in the surface of formed concrete during placement and consolidation. Bug holes on vertical faces are more likely to occur in sticky or stiff concrete mix- tures of low workability that may have an excessive fine ag- gregate content or entrapped air content, or both. Also, the use of vibrators with too high of an amplitude or the lack of complete insertion of the vibrator head may result in an in- creased quantity of air-voids. Air voids vary in size from mi- croscopic to about 25 mm (1 in.). Excess water normally manifests itself in other textural effects such as bleeding channels or sand streaks on vertical formed surfaces. Bleed water voids can form at the top of a column and on battered formed surfaces. Surface voids can be minimized by the pro- cedures discussed in Section 4. 3.3—Form streaking Form streaking (Fig. 3) is caused by mortar leaking through form joints and tie holes and may be aggravated by overvibra- tion from vibrators that are too powerful, or by using forms that vibrate excessively during consolidation. Placing excessively wet or high-slump concrete mixtures will result in more mortar washing out through tie holes and loose fitting forms. Special care is sometimes required when Fig. 1—Honeycomb.
  • 7. 309.2R-7CONSOLIDATION-RELATED SURFACE DEFECTS high-range water-reducing admixtures are used, as they tend to increase leakage at form joints. 3.4—Aggregate transparency Aggregate transparency (Fig. 4) is a condition character- ized by a mottled appearance on the surface that results from deficiencies in the mortar. It may occur when concrete mix- tures have low fine aggregate content, dry or porous aggre- gates, or high slump with some lightweight and normal- weight aggregates. Also, high density or glossy form surfac- es may cause aggregate transparency. 3.5—Subsidence cracking Subsidence cracking (Fig. 5) results from the development of tension when the concrete settles closed to after time of initial setting. Cracks are caused because the upper concrete bridges between the forms while the lower concrete settles. These cracks may occur when there is an insufficient inter- val between placing the concrete in the columns and placing the concrete for the slabs or beams. They may also occur ad- jacent to block-outs or over reinforcing bars with shallow cover. To prevent subsidence cracking, the concrete can be revi- brated. Revibration is most effective when done at the latest time at which the vibrator head will readily penetrate the concrete under its own weight. Subsidence cracking over re- inforcing bars can be controlled by increasing concrete cov- er during the design phase and by using low-slump concrete that is well-consolidated. 3.6—Color variation Color variation (Fig. 6) may occur within a placement if the concrete is not uniform or is incompletely mixed. Vibrators inserted too close to the form can cause color variation by marring the form surface. External vibration used haphazardly may also cause color variation. Further- more, color variations may result from nonuniform absorp- tion, nonuniform application of the release agent, or both. 3.7—Sand streaking Sand streaking (Fig. 7) is a streak of exposed fine aggre- gate in the surface of the formed concrete caused by heavy bleeding along the form. It frequently results from the use of harsh, wet mixtures, particularly those deficient in the 300 to 150 µm (No. 50 to No. 100) and smaller sizes. Streaking tendencies increase when the ratio of fine aggregate to cementitious materials in- creases, such as in lean mixtures. Although the characteris- tics of Portland cement and pozzolans, if used, have some influence on bleeding, the grading of the fine aggregate is of greater importance. Sand streaking is controlled by the use of tight forms, proper mixture proportioning, and using well- graded fine aggregate to minimize bleeding. Streaking can be aggravated by excessive vibration, overmanipulation of the vibrator, the use of a vibrator with excessive amplitude; or excess water at the bottom of the form forced up along the form face by hydraulic pressure. 3.8—Layer lines Layer lines (Fig. 8) are dark horizontal lines on formed sur- faces that indicate the boundary between concrete placements. Fig. 2—Air surface voids. Fig. 3—Form streaking.
  • 8. 309.2R-8 MANUAL OF CONCRETE PRACTICE Layer lines are caused by premature stiffening or insufficient consolidation of the previous layer of concrete due to lack of penetration of the vibrator into that layer, or the use of a mor- tar bonding layer between placements. 3.9—Form offsets Form offsets (Fig. 9) are usually caused by inadequate stiffness or anchorage of the forms and can be aggravated by an excessive rate of placement or by using an excessively powerful vibrator, or both. 3.10—Cold joints Cold joints (Fig. 10) can often be avoided by contingency planning, backup equipment, working to keep the concrete surface alive, the use of retarding admixtures, and working the vibrator into lower lifts. CHAPTER 4—MINIMIZING SURFACE EFFECTS A number of studies have been made to determine how to achieve better consolidation resulting in fewer surface blem- ishes (Shilstone, 1977; Stamenkovic, 1973; Samuelson, 1970; and Reading, 1972). To minimize the size and number of bug holes and all other effects, the following practices should be followed: • Vibration period should be of sufficient duration; • Vibrator insertions should be properly spaced and over- lapped and the vibrator removed slowly; • Each concrete layer should be consolidated from the bottom upward; • Vibration periods should be increased on withdrawal when using impermeable forms that permit air trapped at the form surface to escape through joints as between; • Inward sloping forms and other complex design details should be avoided; • Depth of placement layers should be limited; • Vibrator should penetrate into the previous layer; • Tightening devices and gaskets to prevent leakage at form joints should be provided as necessary; and • Placing ports should be designed into the forms as nec- essary. Where practical, bug holes can be minimized by the use of a 65-mm-(21 /2-in.-)-diameter vibrator of high frequency with Fig. 4—Aggregate transparency. Fig. 5—Subsidence cracking Fig. 6—Color variation.
  • 9. 309.2R-9CONSOLIDATION-RELATED SURFACE DEFECTS medium to low amplitude. The vibrator should be immersed in the concrete around the perimeter of the form without damaging the form. Where reinforcement is placed near the form wall, the vibrator must be inserted inside the reinforce- ment. Care should be taken to ensure that the vibrator has a sufficient radius of action to liquefy the concrete at the form. Form vibration may be used to supplement the internal vi- bration. However, doing so may cause a major increase in form pressure. An alternate procedure is to use a high-fre- quency, low-amplitude form vibrator. Vibration procedures should be evaluated at the beginning of a project to deter- mine the vibration time for each type of vibrator for a given mixture. Guidance on the selection of appropriate vibration amplitudes, frequencies, and equipment is given in ACI 309R. In areas where surface air voids are most prevalent, revi- bration may be used to reduce them. Revibration is more ef- fective if it is done at the latest possible time at which the vibrator head will readily penetrate the concrete under its own weight. Greater benefits are obtained with higher slump concrete mixtures, especially in the upper portion of a place- ment where excessive entrapped air voids are most preva- lent. However, this practice may increase laitance that must be removed from horizontal construction joints. And may create color non-uniformity. Other measures, such as altering mixture proportions, us- ing high-range water-reducing admixtures, and using small- er nominal maximum size aggregate to improve workability Fig. 7—Sand streaking. Fig. 8—Layer lines. Fig. 9—Form offsets. Fig. 10—Cold joints.
  • 10. 309.2R-10 MANUAL OF CONCRETE PRACTICE should also be considered as methods of minimizing surface effects, provided that design requirements are met. These measures have often been successful, particularly when try- ing to consolidate concrete in congested areas. Further guid- ance can be obtained from ACI 309R. CHAPTER 5—CONSOLIDATION OF PREPLACED- AGGREGATE CONCRETE The causes and cures of blemishes in concrete produced by the preplaced-aggregate (PA) concrete method (ACI 304.1R, Chapter 7) are different from conventionally mixed and placed concrete in certain aspects. The rate of grout rise in preplaced aggregate should be about 0.3 m/min (1 ft/min) with a maximum of 0.6 m/min (2 ft/min). If the supply is too rapid, the grout will rise faster through the large voids and cascade into the smaller ones, trapping air. The result is spotty honeycombing. To avoid the occurrence of layer lines, the lower ends of the grout injec- tion ports should always be maintained at least 0.3 to 0.6 m (1 to 2 ft) below the grout surface. Grout will not penetrate pockets of fine aggregate; fines that collect against side or bottom forms will produce honey- combing. Also, care should be taken to ensure that coarse ag- gregate fills the space between the reinforcement and forms, and that no large voids are left that will be subsequently filled with grout. Large surface areas of grout not subdivided by coarse aggregate may show crazing from drying shrinkage. Coarse aggregate should be saturated when placed and at the time it is grouted. If rewetting in the forms is required, a fog spray may be applied sparingly to dampen the upper 0.3 m (1 ft) or so. If the entire mass of aggregate needs re-wet- ting, the forms should be inundated with water from the bot- tom, then drained off slowly. Large quantities of water applied to the top of the aggregate will wash fines to the bot- tom, resulting in a poor surface or honeycomb. Light vibration of forms with external vibrators permit the grout to cover the points of coarse aggregate in contact with the form. Overvibration of the form should be avoided, how- ever, as it will induce bleeding that may result in sand streak- ing. Some trial and error may be required to determine the optimum amount of form vibration. Form design must be in conformance with increased pressure. Bolted connections in formwork require lock washers or double nutting. Formwork under external vibration requires positive attachment to foot- ing or previous placement. Where the appearance of formed surfaces is important, a test section of comparable height should be produced, the surface examined, and adjustments made to grading, placing, and consolidation procedures adjusted to obtain an accept- able result. CHAPTER 6—CONCLUSION Faulty design and construction practices can result in blemishes in formed concrete surfaces. To keep these effects within tolerable limits, an awareness of their causes and their cures is essential. The causes of these effects may lie in initial design concepts, specification, materials selection, proportioning, placement, consolidation, or workmanship. Frequently, the services of a specialist in concrete and con- crete construction can be used to assist in obtaining concrete surfaces conforming to the higher standards. The execution of the work by well-trained work crews under competent su- pervision will ensure a concrete surface meeting the require- ments of the owner or designer. CHAPTER 7—SURFACE CONDITION OUTLINE The following is an outline of items that should be consid- ered by designers and constructors when reporting on the condition of a concrete surface and the possible causes of ef- fects. By following this checklist and referring to earlier chapters in this document, the designer or constructor should then be in a position to identify the cause and correct most types of surface effects. 1—Description of structure 1.1—Name, location, type, and size 1.2—Owner, project engineer, contractor 1.3—Design 1.3.1—Architect and/or engineer 1.4—Photographs 1.4.1—General view 2—Description of wall, beam, or column showing blemishes. 2.1—Location, size 2.2—Type of concrete 2.2.1—Architectural 2.2.2—Structural 3—Effect 3.1—Name 3.1.1—Description 3.1.2—Photographs 4—Causes 4.1—Design of member 4.1.1—Reinforcement (spacing and size) 4.1.2—Width, depth 4.1.3—Configuration 4.2—Forms 4.2.1—Method 4.2.2—Shape 4.2.3—Anchorage 4.2.4—Insulation 4.2.5—Material type, new or used 4.2.6—Form coatings 4.2.7—Texture and finish 4.2.8—Tightness 4.2.9—Structural adequacy 4.3—Construction conditions 4.3.1—Temperature 4.3.2—Wind 4.3.3—Humidity 4.3.4—Precipitation 4.3.5—Placing accessibility 4.3.6—Precautions, covered in 4.5 4.4—Properties of fresh concrete 4.4.1—Proportions 4.4.2—Workability
  • 11. 309.2R-11CONSOLIDATION-RELATED SURFACE DEFECTS 4.4.3—Grading of aggregate 4.4.4—Slump 4.4.5—Nominal maximum size aggregate 4.4.6—Cohesiveness 4.4.7—Air content 4.4.8—Time of setting 4.5—Placement 4.5.1—Rate 4.5.2—Conditions 4.5.3—Adequacy of equipment 4.6—Consolidation 4.6.1—Frequency 4.6.2—Amplitude 4.6.3—Physical size 4.6.4—Schedule of insertions 4.6.5—Number of vibrators 4.6.6—Depth of penetration 4.6.7—Length of vibration CHAPTER 8—REFERENCES 8.1—ACI and ASTM Standards The documents of the various standards-producing orga- nizations referred to in this report are listed below with their serial designation. American Concrete Institute ACI 116R Cement and Concrete Terminology ACI 303R Guide to Cast-In-Place Architectural Con- crete Practice ACI 304.1R Guide For the Use of Prepackaged-Aggre- gate Concrete for Structural and Mass Concrete Applications ACI 309R Guide for Consolidation of Concrete ACI 309.1R Behavior of Fresh Concrete During Vi- bration ACI 347R Guide to Formwork for Concrete American Society for Testing Materials ASTM C 33 Specification for Concrete Aggregates The above publications may be obtained from: American Concrete Institute P.O. Box 9094 Farmington Hills, MI 48333-9094 American Society for Testing Materials 100 Barr Harbor Drive West Conshohocken, PA 19428-2959 8.2—Cited references Backstrom, J. E.; Burrows, R. W.; Mielenz, R. C.; and Wolkodorff, V. E. (1958). “Origin, Evolution and Effects of the Air Void System in Concrete, Part 3-Influence of Water-Cement Ratio and Compaction,” ACI JOURNAL, Proceedings V. 55, Sept., pp. 359-375. International Council for Building Research (1975). “Tolerances on Blemishes of Concrete,” CIB Report No. 24, International Council for Building Research Studies and Documentation, Rotterdam, 8 pp. Mather, B. (1987). “The Warmer the Concrete the Faster the Cement Hardens,” Concrete International, V. 9, No. 8, August, pp. 29-33. Shilstone, J. M. (1977). “Surface Blemishes in Formed Concrete," Pro- ceedings, RILEM/ASTM/CIB Symposium on Performance Evaluation of External Vertical Surfaces of Buildings (Otaniemi, Espoo, Aug.-Sept. 1977), Technical Research Centre of Finland, Espoo, Finland, pp. 3-7. Stamenkovic, H. (1973). “Surface Voids Can Be Controlled,” Concrete Construction, V. 18, No. 12, Dec., pp. 597-598, 600. Samuelson, P. (1970). “Voids in Concrete Surfaces,” ACI JOURNAL, Pro- ceedings V. 67, No. 22, Nov., pp. 868-874. Reading, T. J. (1972). “The Bug Hole Problem,” ACI JOURNAL, Pro- ceedings V. 69, No. 3, Mar., pp. 165-177. 8.3—Bibliography King, J. C. (1971). “Special Concretes and Mortars,” Handbook of Heavy Construction, 2nd Edition, McGraw-Hill Book Co., New York, pp. 22-1 to 22-17. Fiorato, A. E. (1973). Geometric Imperfections in Concrete Structures (A Literature Survey), National Swedish Institute for Building Research, Stockholm, Sweden. Harding, M. A. (1995). “Vibrating Concrete in Wall Forms,” Concrete Construction, V. 40, No. 2, Feb., pp. 180-184. Harrell, T. R., and Goswick, G. M. (1987). “Tunnel Concrete—Consoli- dation Achieved by a Harmonic Blend of Internal and External Vibration,” Consolidation of Concrete, SP-96, American Concrete Institute, Farming- ton Hills, Mich., pp. 102-118. Holland, T. C.; Husbands, T. B.; Buck, A. D.; and Wong, G. S. (1980). Concrete Deterioration in Spillway Warm-Water Chute, Raystown Dam. Pennsylvania (Final Report), U. S. Army Engineer Waterways Experiment Station, Vicksburg, Miss., Structures Lab. WES/MP/SL-80-19; CTIAC-42, 55 pp. Houston, B. J. (1967). Methods of Reducing the Size and Number of Voids on Formed Concrete Surfaces, Report No. TR 6-788, U. S. Army Engineer Waterways Experiment Station, Vicksburg, Miss., 36 pp. Hurd, M. K. (1993). “Patterned Form Liners for Architectural Concrete,” Concrete Construction, V. 38, No. 5, May 5, 5 pp. Kennedy, T. B. (1960). Investigation of Methods of Finishing Formed Concrete Surfaces, Report No. TR 6-559, U.S. Army Engineer Waterways Experimental Station, Vicksburg, Miss., 19 pp. Kenney, A. R. (1984). “Problems and Surface Blemishes in Architectural Cast-in-Place Concrete,” Concrete International, V. 6, No. 1, Jan., pp. 50-55. Kenney, A. R., and Kenney, B. P. (1986). “Problems and Repairs in Tilt- Up Construction,” Concrete International, V. 8, No. 6, Jun., pp. 41-50. Mass, G. R. (1987). “Consolidation of Concrete,” Lewis H. Tuthill Inter- national Symposium on Concrete and Concrete Construction, SP-104, Gant T. Halvorsen, ed., American Concrete Institute, Farmington Hills, Mich., pp. 185-204. Reading, T. J. (1985), “Deleterious Affects of Wood Forms on Concrete Surfaces, Concrete International, V. 7, No. 11, Nov., pp. 57-62. Sansalone, M., and Carino, N. J. (1988). “Impacted-Echo Method: Detecting Honeycombing, Depth of Surface-Opening Cracks, and Ungrouted Ducts (Final Report),” Concrete International, V. 10, No. 4, Apr., pp. 38-46. Shilstone, J. M. (1979). “Surface Blemishes in Formed Concrete,” Con- crete Construction, V. 24, No. 11, Nov., pp. 719 and 765. Smith, John R. (1984). “Architectural Concrete: Defects Demand Dis- cretion,” Concrete International, V. 6 No. 1, Jan., pp. 64-66. Watanaba, T., and Uomoto, T. (1993). “Monitoring Concrete Placing by Infrared Image Analysis,” Doboku Gakkai Rombun-Hokokushu/ Proceed- ings of the Japan Society of Civil Engineers, No. 478, Part 50-21, pp. 55-59.