SlideShare a Scribd company logo
1 of 1
Download to read offline
KIERAN PELLING
Project Engineer
Kieran’s engineering background and practical approach provide the technical
foundations required to manage design from concept through to implementation on
site in a smooth and targeted manner. His experience has provided him with an
appreciation for the different roles within a Design and Construct management team,
a set of skills that place him in a pivotal role between the design and contracts team
and a construction site.
Project Responsibilities
As Project Engineer, Kieran is responsible for design and engineering coordination
to construct the project to client requirements while meeting quality, time and cost
objectives. His responsibilities also include buildability analysis, preparing method
statements and client liaison.
Career Overview
In 2008, Kieran was employed by Brookfield Multiplex on a 3 month work experience
rotation as an introduction to the construction industry. Assigned to the Sydney
Water Corporate Headquarters, he was exposed to the different facets of a Design
and Construct project, completing such tasks as safety, quality and environmental management, site supervision of
the basement car park fit out works and defects completion.
After returning to his university studies for two semesters to complete his thesis, Kieran recommenced work with
Brookfield Multiplex working on the Sydney Water Field Operations Facility, Potts Hill. Here Kieran assisted in
design quality management and coordination and defects rectification.
Following this, Kieran worked on the 5 Star The Darling hotel, part of The Star casino upgrade works, and for two
years he covered a variety of different roles on the project. He gained first hand site experience in managing
subcontractors and material handling for the detailed excavation and structure, including the installation and
running of different structure systems. He then managed the onsite installation of the facade which included a
typical curtain wall and a 12 storey raked edge shop front glazing nose. Kieran’s final role on The Star included the
design coordination, procurement, authority approvals and site management of The Darling day spa ($8m); all in all
giving him a well-rounded appreciation of a project from start to finish.
Following The Star project, Kieran was assigned as a Site Engineer on the Charles Perkins Centre, a project for
the University of Sydney in Camperdown. Kieran was involved from the tender stage, including providing
information for DA requirements; site set up of an office for 40 people and 500 workers; managed the approval and
erection of two tower cranes; planning of the structure build; hoists, lifting penetrations, concrete placing booms,
three jump form systems and loading platforms; the scope and letting of the scaffold package; design management
of structure and structural steel; and the erection of a 35T structural steel café; as well as managing the design
coordination, subcontractor scopes and planning for a 1,000m2 cafe and 14,000m2 of landscaping works.
After the completion of The Charles Perkins Centre, Kieran assisted in the delivery of Macquarie Group’s newly
refurbished headquarters at 50 Martin Place in Sydney’s CBD. Here he managed the refurbishment of the
Commonwealth Bank Banking Chamber, a heritage interior that included extensive marble and bronze works. The
Banking Chamber was required to remain fully operational throughout construction with the Bank stipulating low
levels of noise and vibration throughout the works. As testament to the success of the Brookfield Multiplex
approach to working in operational environments, there were no complaints during this time.
Kieran then worked on tenders within the head office New Business team where he developed detailed
construction methodologies for potential projects. Following the successful conversion of Mark Moran at Vaucluse,
a high end residential aged care project, Kieran joined the site team as Project Engineer. His earlier involvement in
the planning for the project provided him with a thorough understanding of the project as he worked with the design
team to bring the architectural concept from preliminary stages to a fully coordinated design. He has now guided a
relatively inexperienced team through the construction of 40000m2 of concrete structure and led the procurement
and installation of 140T of structural steel which included an atrium steel support structure, a spiral stair, and an
independent café structure.
Qualifications
» Bachelor of Engineering, Civil Engineering, University of Sydney
Referees
Hung Nguyen
Taylor Thomson and Whitting
T. 0416 160 988
Laurent Stewart
Webber Design
T. 0433 777 434
Projects
» Mark Moran at Vaucluse Aged Care Facility, NSW ($100m)
» 50 Martin Place, Sydney ($147m)
» Charles Perkins Centre, University of Sydney, Camperdown ($252m)
» The Star – Casino Expansion & The Darling Hotel, Pyrmont ($273m)
» Sydney Water Field Operations Facility, Potts Hill ($51m)
» Sydney Water Corporate Headquarters, Parramatta ($159m)

More Related Content

What's hot

Allen Campbell_NR (003) - Copy
Allen Campbell_NR (003) - CopyAllen Campbell_NR (003) - Copy
Allen Campbell_NR (003) - CopyAllen Campbell
 
modernization resume
modernization resumemodernization resume
modernization resumeSteve Woody
 
Dimitri's Project Portfolio
Dimitri's Project PortfolioDimitri's Project Portfolio
Dimitri's Project Portfoliodkakaletris
 
Paul Hartzog Resume, 2015
Paul Hartzog Resume, 2015Paul Hartzog Resume, 2015
Paul Hartzog Resume, 2015Paul Hartzog
 
NEW NWAOBI DAVID RESUME FOR 2015
NEW NWAOBI DAVID RESUME FOR 2015NEW NWAOBI DAVID RESUME FOR 2015
NEW NWAOBI DAVID RESUME FOR 2015chinedu nwaobi
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2john rhynold
 
Sean Singh Resume (1)
Sean Singh Resume (1)Sean Singh Resume (1)
Sean Singh Resume (1)Sean Singh
 
CPR Draft OCT 10_2016_Chronological_Resume (1)
CPR Draft OCT 10_2016_Chronological_Resume (1)CPR Draft OCT 10_2016_Chronological_Resume (1)
CPR Draft OCT 10_2016_Chronological_Resume (1)Dan Mikalaski
 
David Smith 2016 CV
David Smith 2016 CVDavid Smith 2016 CV
David Smith 2016 CVDavid Smith
 
Resume of Jesus Rodriguez
Resume of Jesus RodriguezResume of Jesus Rodriguez
Resume of Jesus RodriguezJesus Rodriguez
 
Treveton, Luke - Resume new
Treveton, Luke - Resume newTreveton, Luke - Resume new
Treveton, Luke - Resume newluke treveton
 

What's hot (18)

Allen Campbell_NR (003) - Copy
Allen Campbell_NR (003) - CopyAllen Campbell_NR (003) - Copy
Allen Campbell_NR (003) - Copy
 
modernization resume
modernization resumemodernization resume
modernization resume
 
Resume with System 3
Resume with System 3Resume with System 3
Resume with System 3
 
JEarle_2016
JEarle_2016JEarle_2016
JEarle_2016
 
Dimitri's Project Portfolio
Dimitri's Project PortfolioDimitri's Project Portfolio
Dimitri's Project Portfolio
 
Paul Hartzog Resume, 2015
Paul Hartzog Resume, 2015Paul Hartzog Resume, 2015
Paul Hartzog Resume, 2015
 
Connelly Darren (CV1)
Connelly Darren (CV1)Connelly Darren (CV1)
Connelly Darren (CV1)
 
NEW NWAOBI DAVID RESUME FOR 2015
NEW NWAOBI DAVID RESUME FOR 2015NEW NWAOBI DAVID RESUME FOR 2015
NEW NWAOBI DAVID RESUME FOR 2015
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2
 
Sean Singh Resume (1)
Sean Singh Resume (1)Sean Singh Resume (1)
Sean Singh Resume (1)
 
CPR Draft OCT 10_2016_Chronological_Resume (1)
CPR Draft OCT 10_2016_Chronological_Resume (1)CPR Draft OCT 10_2016_Chronological_Resume (1)
CPR Draft OCT 10_2016_Chronological_Resume (1)
 
David Smith 2016 CV
David Smith 2016 CVDavid Smith 2016 CV
David Smith 2016 CV
 
Resume of Jesus Rodriguez
Resume of Jesus RodriguezResume of Jesus Rodriguez
Resume of Jesus Rodriguez
 
CV 2015 Christo Van Jaarsveld
CV 2015 Christo Van JaarsveldCV 2015 Christo Van Jaarsveld
CV 2015 Christo Van Jaarsveld
 
GERRY PANTIG MANICLANG
GERRY PANTIG MANICLANGGERRY PANTIG MANICLANG
GERRY PANTIG MANICLANG
 
Resume sol_2016
Resume sol_2016Resume sol_2016
Resume sol_2016
 
Treveton, Luke - Resume new
Treveton, Luke - Resume newTreveton, Luke - Resume new
Treveton, Luke - Resume new
 
REFLetter_OMB
REFLetter_OMBREFLetter_OMB
REFLetter_OMB
 

Viewers also liked

Como tratar las estrías
Como tratar las estríasComo tratar las estrías
Como tratar las estríasLucia Ortega
 
Cosmelan: Tratamiento para las manchas en la piel
Cosmelan: Tratamiento para las manchas en la pielCosmelan: Tratamiento para las manchas en la piel
Cosmelan: Tratamiento para las manchas en la pielClinica Estetica Suarez
 
Semana 11 dermocosmetica
Semana 11 dermocosmeticaSemana 11 dermocosmetica
Semana 11 dermocosmeticaEDWIN POMATANTA
 
Usos de la quimica en la industria cosmetologica
Usos de la quimica en la industria cosmetologicaUsos de la quimica en la industria cosmetologica
Usos de la quimica en la industria cosmetologicaAna Cuellar Diosdado
 
QuíMica De Los CosméTicos
QuíMica De Los CosméTicosQuíMica De Los CosméTicos
QuíMica De Los CosméTicosgueste23e
 
Paginas de matematicas
Paginas de matematicasPaginas de matematicas
Paginas de matematicasespanol
 

Viewers also liked (8)

Como tratar las estrías
Como tratar las estríasComo tratar las estrías
Como tratar las estrías
 
Guía de tratamientos peeling Medik8 para el cliente
Guía de tratamientos peeling Medik8 para el clienteGuía de tratamientos peeling Medik8 para el cliente
Guía de tratamientos peeling Medik8 para el cliente
 
Cosmelan: Tratamiento para las manchas en la piel
Cosmelan: Tratamiento para las manchas en la pielCosmelan: Tratamiento para las manchas en la piel
Cosmelan: Tratamiento para las manchas en la piel
 
Caso clinico gingivoabrasión peeling mancha melánica encía
Caso clinico gingivoabrasión peeling mancha melánica encíaCaso clinico gingivoabrasión peeling mancha melánica encía
Caso clinico gingivoabrasión peeling mancha melánica encía
 
Semana 11 dermocosmetica
Semana 11 dermocosmeticaSemana 11 dermocosmetica
Semana 11 dermocosmetica
 
Usos de la quimica en la industria cosmetologica
Usos de la quimica en la industria cosmetologicaUsos de la quimica en la industria cosmetologica
Usos de la quimica en la industria cosmetologica
 
QuíMica De Los CosméTicos
QuíMica De Los CosméTicosQuíMica De Los CosméTicos
QuíMica De Los CosméTicos
 
Paginas de matematicas
Paginas de matematicasPaginas de matematicas
Paginas de matematicas
 

Similar to Kieran Pelling BM CV

Mike Okey CV FM1 Linked in
Mike Okey  CV FM1 Linked inMike Okey  CV FM1 Linked in
Mike Okey CV FM1 Linked inMike Okey
 
Mustafa Hafizi Portfolio 2016
Mustafa Hafizi Portfolio 2016Mustafa Hafizi Portfolio 2016
Mustafa Hafizi Portfolio 2016Mustafa Hafizi.
 
Brent Maskell Resume May 2016
Brent Maskell Resume May 2016Brent Maskell Resume May 2016
Brent Maskell Resume May 2016Brent Maskell
 
Hans Goetze Cv Project Director Portfolio Large Ici 14oct2011
Hans Goetze Cv Project Director Portfolio Large Ici  14oct2011Hans Goetze Cv Project Director Portfolio Large Ici  14oct2011
Hans Goetze Cv Project Director Portfolio Large Ici 14oct2011Hans Goetze
 
Profile-RPR-Pheng
Profile-RPR-PhengProfile-RPR-Pheng
Profile-RPR-PhengNick Pheng
 
Peter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally
 
CVnz - Andrew Nash
CVnz - Andrew NashCVnz - Andrew Nash
CVnz - Andrew NashAndrew Nash
 
S nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGS nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGsiavashn
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016Kim Barry
 
RESUME OF PROFESSIONAL EXPERIENCE
RESUME OF PROFESSIONAL EXPERIENCERESUME OF PROFESSIONAL EXPERIENCE
RESUME OF PROFESSIONAL EXPERIENCEJackie Mims-Rivera
 
Grizzle 2012 Resume
Grizzle 2012 ResumeGrizzle 2012 Resume
Grizzle 2012 Resumebbgrizzle
 
Joyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee
 
Joyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee
 
Kathy Karras Resume
Kathy Karras ResumeKathy Karras Resume
Kathy Karras ResumeKathy Karras
 
Luke Morrison resume
Luke Morrison resumeLuke Morrison resume
Luke Morrison resumeLuke Morrison
 
Antonio J Mendes MASc_Resume
Antonio J Mendes MASc_ResumeAntonio J Mendes MASc_Resume
Antonio J Mendes MASc_ResumeTony Mendes
 
James Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to OilJames Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to OilJames Nolan
 
Hammam Mostafa CV 2015 - Copy
Hammam Mostafa CV 2015 - CopyHammam Mostafa CV 2015 - Copy
Hammam Mostafa CV 2015 - CopyHammam solaiman
 

Similar to Kieran Pelling BM CV (20)

Mike Okey CV FM1 Linked in
Mike Okey  CV FM1 Linked inMike Okey  CV FM1 Linked in
Mike Okey CV FM1 Linked in
 
Mustafa Hafizi Portfolio 2016
Mustafa Hafizi Portfolio 2016Mustafa Hafizi Portfolio 2016
Mustafa Hafizi Portfolio 2016
 
Brent Maskell Resume May 2016
Brent Maskell Resume May 2016Brent Maskell Resume May 2016
Brent Maskell Resume May 2016
 
Hans Goetze Cv Project Director Portfolio Large Ici 14oct2011
Hans Goetze Cv Project Director Portfolio Large Ici  14oct2011Hans Goetze Cv Project Director Portfolio Large Ici  14oct2011
Hans Goetze Cv Project Director Portfolio Large Ici 14oct2011
 
Long Resume
Long ResumeLong Resume
Long Resume
 
Profile-RPR-Pheng
Profile-RPR-PhengProfile-RPR-Pheng
Profile-RPR-Pheng
 
Peter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally Aquenta CV
Peter Dally Aquenta CV
 
CVnz - Andrew Nash
CVnz - Andrew NashCVnz - Andrew Nash
CVnz - Andrew Nash
 
Nibor company profile presentation
Nibor company profile presentationNibor company profile presentation
Nibor company profile presentation
 
S nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNGS nikkhah CV Oil Gas CSG LNG
S nikkhah CV Oil Gas CSG LNG
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016
 
RESUME OF PROFESSIONAL EXPERIENCE
RESUME OF PROFESSIONAL EXPERIENCERESUME OF PROFESSIONAL EXPERIENCE
RESUME OF PROFESSIONAL EXPERIENCE
 
Grizzle 2012 Resume
Grizzle 2012 ResumeGrizzle 2012 Resume
Grizzle 2012 Resume
 
Joyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CV
 
Joyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CVJoyce Lee_2016_ARCADIS_CV
Joyce Lee_2016_ARCADIS_CV
 
Kathy Karras Resume
Kathy Karras ResumeKathy Karras Resume
Kathy Karras Resume
 
Luke Morrison resume
Luke Morrison resumeLuke Morrison resume
Luke Morrison resume
 
Antonio J Mendes MASc_Resume
Antonio J Mendes MASc_ResumeAntonio J Mendes MASc_Resume
Antonio J Mendes MASc_Resume
 
James Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to OilJames Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
James Nolan experience in Energy, renewables, Waste to Energy and Waste to Oil
 
Hammam Mostafa CV 2015 - Copy
Hammam Mostafa CV 2015 - CopyHammam Mostafa CV 2015 - Copy
Hammam Mostafa CV 2015 - Copy
 

Kieran Pelling BM CV

  • 1. KIERAN PELLING Project Engineer Kieran’s engineering background and practical approach provide the technical foundations required to manage design from concept through to implementation on site in a smooth and targeted manner. His experience has provided him with an appreciation for the different roles within a Design and Construct management team, a set of skills that place him in a pivotal role between the design and contracts team and a construction site. Project Responsibilities As Project Engineer, Kieran is responsible for design and engineering coordination to construct the project to client requirements while meeting quality, time and cost objectives. His responsibilities also include buildability analysis, preparing method statements and client liaison. Career Overview In 2008, Kieran was employed by Brookfield Multiplex on a 3 month work experience rotation as an introduction to the construction industry. Assigned to the Sydney Water Corporate Headquarters, he was exposed to the different facets of a Design and Construct project, completing such tasks as safety, quality and environmental management, site supervision of the basement car park fit out works and defects completion. After returning to his university studies for two semesters to complete his thesis, Kieran recommenced work with Brookfield Multiplex working on the Sydney Water Field Operations Facility, Potts Hill. Here Kieran assisted in design quality management and coordination and defects rectification. Following this, Kieran worked on the 5 Star The Darling hotel, part of The Star casino upgrade works, and for two years he covered a variety of different roles on the project. He gained first hand site experience in managing subcontractors and material handling for the detailed excavation and structure, including the installation and running of different structure systems. He then managed the onsite installation of the facade which included a typical curtain wall and a 12 storey raked edge shop front glazing nose. Kieran’s final role on The Star included the design coordination, procurement, authority approvals and site management of The Darling day spa ($8m); all in all giving him a well-rounded appreciation of a project from start to finish. Following The Star project, Kieran was assigned as a Site Engineer on the Charles Perkins Centre, a project for the University of Sydney in Camperdown. Kieran was involved from the tender stage, including providing information for DA requirements; site set up of an office for 40 people and 500 workers; managed the approval and erection of two tower cranes; planning of the structure build; hoists, lifting penetrations, concrete placing booms, three jump form systems and loading platforms; the scope and letting of the scaffold package; design management of structure and structural steel; and the erection of a 35T structural steel café; as well as managing the design coordination, subcontractor scopes and planning for a 1,000m2 cafe and 14,000m2 of landscaping works. After the completion of The Charles Perkins Centre, Kieran assisted in the delivery of Macquarie Group’s newly refurbished headquarters at 50 Martin Place in Sydney’s CBD. Here he managed the refurbishment of the Commonwealth Bank Banking Chamber, a heritage interior that included extensive marble and bronze works. The Banking Chamber was required to remain fully operational throughout construction with the Bank stipulating low levels of noise and vibration throughout the works. As testament to the success of the Brookfield Multiplex approach to working in operational environments, there were no complaints during this time. Kieran then worked on tenders within the head office New Business team where he developed detailed construction methodologies for potential projects. Following the successful conversion of Mark Moran at Vaucluse, a high end residential aged care project, Kieran joined the site team as Project Engineer. His earlier involvement in the planning for the project provided him with a thorough understanding of the project as he worked with the design team to bring the architectural concept from preliminary stages to a fully coordinated design. He has now guided a relatively inexperienced team through the construction of 40000m2 of concrete structure and led the procurement and installation of 140T of structural steel which included an atrium steel support structure, a spiral stair, and an independent café structure. Qualifications » Bachelor of Engineering, Civil Engineering, University of Sydney Referees Hung Nguyen Taylor Thomson and Whitting T. 0416 160 988 Laurent Stewart Webber Design T. 0433 777 434 Projects » Mark Moran at Vaucluse Aged Care Facility, NSW ($100m) » 50 Martin Place, Sydney ($147m) » Charles Perkins Centre, University of Sydney, Camperdown ($252m) » The Star – Casino Expansion & The Darling Hotel, Pyrmont ($273m) » Sydney Water Field Operations Facility, Potts Hill ($51m) » Sydney Water Corporate Headquarters, Parramatta ($159m)