SlideShare a Scribd company logo
1 of 17
Integration Management
2
3Integration Management
Project Integration Management includes the processes and activities to identify, define, combine, unify, and
coordinate the various processes and project management activities within the Project Management Process
Groups.
Key Concepts
ļƒ˜ Project Charter to initiate
Projects
ļƒ˜ Project Management Plan to
plan, execute, monitor &
control, and close Projects
ļƒ˜ Change Requests to update
Projects
4
4.1 Develop Project Charterā€”The process of developing a document
that formally authorizes the existence of a project and provides the
project manager with the authority to apply organizational resources to
project activities.
4.2 Develop Project Management Planā€”The process of defining,
preparing, and coordinating all subsidiary plans and integrating them into
a comprehensive project management plan. The projectā€™s integrated
baselines and subsidiary plans may be included within the project
management plan.
4.3 Direct and Manage Project Workā€”The process of leading and
performing the work defined in the project management plan and
implementing approved changes to achieve the projectā€™s objectives.
4.4 Monitor and Control Project Workā€”The process of tracking,
reviewing, and reporting project progress against the performance
objectives defined in the project management plan.
4.5 Perform Integrated Change Controlā€”The process of reviewing all
change requests; approving changes and managing changes to
deliverables, organizational process assets, project documents,
and the project management plan; and communicating their disposition.
4.6 Close Project or Phaseā€”The process of finalizing all activities
across all of the Project Management Process Groups to formally
complete the phase or project.
Integration Management
5
4.1 Develop Project Charter
6Project Charter
The Project Charter is a document that formally
authorizes the existence of a project and
provides the project manager the authority to
apply organizational resources to project
activities. The key benefit of this document is it
creates a formal record of the project and a
direct way for senior management to formally
accept and commit to the project.
7
4.2 Develop Project Management Plan
8Project Management Plan
The Project Management Plan (PMP) is a formal, approved
document used to manage project execution. The PMP documents
the actions necessary to define, prepare, integrate and coordinate
the various planning activities. The PMP defines how the project is
executed, monitored and controlled, and closed. It is progressively
elaborated by updates throughout the course of the project. The
PMP is also a communication vehicle for ensuring key stakeholders
share an understanding of the project. The PMP is NOT a project
schedule. A project schedule lists planned dates for performing
tasks and activities to meet milestones identified in the project plan.
9
4.3 Direct & Manage Project Work
10Project Management Information System
The Project Management Information System (PMIS) provides
access to tools such as scheduling tool, work authorization
system, configuration management system, information collection
and distribution system and other automated systems.
Automated gathering and reporting on key performance
indicators (KPI) can be part of the PMIS.
11
4.4 Monitor & Control Project Work
12
4.5 Perform Integrated Change Control
13Change Request
A Change Request is a formal proposal to modify any document,
deliverable or baseline. When issues are found while project work
is being performed, change requests are submitted which may
modify project policies or procedures, project scope, project
budget, project schedule or project quality. Change requests may
include:
ā€¢ Corrective Action
ā€¢ Preventive Action
ā€¢ Defect Repair
ā€¢ Updates
14
4.6 Close Project/Phase
15Closure Documents
Project or phase closure documents, consisting of
formal documentation that indicates completion of the
project or phase and the transfer of the completed
deliverables to others.
During project closure, the project manager reviews prior
phase documentation, customer acceptance
documentation and exit criteria to ensure that all project
requirements are completed prior to finalizing the closure
of the project. It is then followed by handing over the
completed project or phase for business as usual (BAU)
activities.
16Lessons Learned
Lessons Learned information are transferred to the lessons learned
knowledge base for use by future projects or phases. This can
include information on issues and risks as well as techniques that
worked well applying to future projects.
17

More Related Content

What's hot

Project management
Project managementProject management
Project managementMoocs Engine
Ā 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areasInsaf Ali Soomro PMP
Ā 
Project management
Project managementProject management
Project managementBiswa Prusty
Ā 
Offshore R&D Project Management
Offshore R&D Project ManagementOffshore R&D Project Management
Offshore R&D Project ManagementN P Singh
Ā 
Project management
Project managementProject management
Project managementIrfan Tahir
Ā 
Project plan or business plan.
Project plan or business plan.Project plan or business plan.
Project plan or business plan.Harinadh Karimikonda
Ā 
Project management
Project managementProject management
Project managementArsh Koul
Ā 
Product and Operation Management
Product and Operation ManagementProduct and Operation Management
Product and Operation ManagementRashed Barakzai
Ā 
Project Management Plan
Project Management Plan Project Management Plan
Project Management Plan Pracas Infosys
Ā 
Building a corporate wide organizational change management discipline
Building a corporate wide organizational change management disciplineBuilding a corporate wide organizational change management discipline
Building a corporate wide organizational change management disciplineCarolyn Reid
Ā 
Project management
Project managementProject management
Project managementPooja Rani
Ā 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Managementafrinaafrose
Ā 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Managementkevinlu
Ā 
Basic project management
Basic project managementBasic project management
Basic project managementKiechelle Degale
Ā 
Change Management - Seven key success factors
Change Management - Seven  key success factorsChange Management - Seven  key success factors
Change Management - Seven key success factorsDr .E. J. Sarma
Ā 
100 Project Management-Success Factor
100 Project Management-Success Factor100 Project Management-Success Factor
100 Project Management-Success FactorDr Fereidoun Dejahang
Ā 
Applied Project Management - P. Garkaviy
Applied Project Management - P. GarkaviyApplied Project Management - P. Garkaviy
Applied Project Management - P. GarkaviyPavel Garkaviy
Ā 

What's hot (20)

Project management
Project managementProject management
Project management
Ā 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
Ā 
Project management
Project managementProject management
Project management
Ā 
Project management
Project managementProject management
Project management
Ā 
Offshore R&D Project Management
Offshore R&D Project ManagementOffshore R&D Project Management
Offshore R&D Project Management
Ā 
Project management
Project managementProject management
Project management
Ā 
Project management
Project managementProject management
Project management
Ā 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Management
Ā 
Project plan or business plan.
Project plan or business plan.Project plan or business plan.
Project plan or business plan.
Ā 
Project management
Project managementProject management
Project management
Ā 
Product and Operation Management
Product and Operation ManagementProduct and Operation Management
Product and Operation Management
Ā 
Project Management Plan
Project Management Plan Project Management Plan
Project Management Plan
Ā 
Building a corporate wide organizational change management discipline
Building a corporate wide organizational change management disciplineBuilding a corporate wide organizational change management discipline
Building a corporate wide organizational change management discipline
Ā 
Project management
Project managementProject management
Project management
Ā 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Management
Ā 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Management
Ā 
Basic project management
Basic project managementBasic project management
Basic project management
Ā 
Change Management - Seven key success factors
Change Management - Seven  key success factorsChange Management - Seven  key success factors
Change Management - Seven key success factors
Ā 
100 Project Management-Success Factor
100 Project Management-Success Factor100 Project Management-Success Factor
100 Project Management-Success Factor
Ā 
Applied Project Management - P. Garkaviy
Applied Project Management - P. GarkaviyApplied Project Management - P. Garkaviy
Applied Project Management - P. Garkaviy
Ā 

Viewers also liked

Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)Jeffrey Cheah
Ā 
Time Masterclass
Time MasterclassTime Masterclass
Time MasterclassJeffrey Cheah
Ā 
Day 3-2 - Final Revision (Scope)
Day 3-2 - Final Revision (Scope)Day 3-2 - Final Revision (Scope)
Day 3-2 - Final Revision (Scope)Jeffrey Cheah
Ā 
ISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementPeter Kim
Ā 
Day 1 - 3PM Revision
Day 1 - 3PM RevisionDay 1 - 3PM Revision
Day 1 - 3PM RevisionJeffrey Cheah
Ā 
Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)Jeffrey Cheah
Ā 
Quality Masterclass
Quality MasterclassQuality Masterclass
Quality MasterclassJeffrey Cheah
Ā 
Day 3-1 - Final Revision (Integration)
Day 3-1 - Final Revision (Integration)Day 3-1 - Final Revision (Integration)
Day 3-1 - Final Revision (Integration)Jeffrey Cheah
Ā 
Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)Jeffrey Cheah
Ā 
Tuckman's group development (Norming)
Tuckman's group development (Norming)Tuckman's group development (Norming)
Tuckman's group development (Norming)Jeffrey Cheah
Ā 
Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)Jeffrey Cheah
Ā 
Day 3-8 - Final Revision (Risk)
Day 3-8 - Final Revision (Risk)Day 3-8 - Final Revision (Risk)
Day 3-8 - Final Revision (Risk)Jeffrey Cheah
Ā 
Tuckman's group development (Storming)
Tuckman's group development (Storming)Tuckman's group development (Storming)
Tuckman's group development (Storming)Jeffrey Cheah
Ā 
Day 4 - Group Effectiveness
Day 4 - Group EffectivenessDay 4 - Group Effectiveness
Day 4 - Group EffectivenessJeffrey Cheah
Ā 
Communications Masterclass
Communications MasterclassCommunications Masterclass
Communications MasterclassJeffrey Cheah
Ā 
Day 1 - Revision
Day 1 - RevisionDay 1 - Revision
Day 1 - RevisionJeffrey Cheah
Ā 
Tuckman's group development (Introduction)
Tuckman's group development (Introduction)Tuckman's group development (Introduction)
Tuckman's group development (Introduction)Jeffrey Cheah
Ā 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Jeffrey Cheah
Ā 
Cost Masterclass
Cost MasterclassCost Masterclass
Cost MasterclassJeffrey Cheah
Ā 
Day 3-9 - Final Revision (Procurement)
Day 3-9 - Final Revision (Procurement)Day 3-9 - Final Revision (Procurement)
Day 3-9 - Final Revision (Procurement)Jeffrey Cheah
Ā 

Viewers also liked (20)

Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)Day 3-4 - Final Revision (Cost)
Day 3-4 - Final Revision (Cost)
Ā 
Time Masterclass
Time MasterclassTime Masterclass
Time Masterclass
Ā 
Day 3-2 - Final Revision (Scope)
Day 3-2 - Final Revision (Scope)Day 3-2 - Final Revision (Scope)
Day 3-2 - Final Revision (Scope)
Ā 
ISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project Management
Ā 
Day 1 - 3PM Revision
Day 1 - 3PM RevisionDay 1 - 3PM Revision
Day 1 - 3PM Revision
Ā 
Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)Day 3-7 - Final Revision (Communications)
Day 3-7 - Final Revision (Communications)
Ā 
Quality Masterclass
Quality MasterclassQuality Masterclass
Quality Masterclass
Ā 
Day 3-1 - Final Revision (Integration)
Day 3-1 - Final Revision (Integration)Day 3-1 - Final Revision (Integration)
Day 3-1 - Final Revision (Integration)
Ā 
Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)Day 3-10 - Final Revision (Stakeholder)
Day 3-10 - Final Revision (Stakeholder)
Ā 
Tuckman's group development (Norming)
Tuckman's group development (Norming)Tuckman's group development (Norming)
Tuckman's group development (Norming)
Ā 
Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)Day 3-3 - Final Revision (Time)
Day 3-3 - Final Revision (Time)
Ā 
Day 3-8 - Final Revision (Risk)
Day 3-8 - Final Revision (Risk)Day 3-8 - Final Revision (Risk)
Day 3-8 - Final Revision (Risk)
Ā 
Tuckman's group development (Storming)
Tuckman's group development (Storming)Tuckman's group development (Storming)
Tuckman's group development (Storming)
Ā 
Day 4 - Group Effectiveness
Day 4 - Group EffectivenessDay 4 - Group Effectiveness
Day 4 - Group Effectiveness
Ā 
Communications Masterclass
Communications MasterclassCommunications Masterclass
Communications Masterclass
Ā 
Day 1 - Revision
Day 1 - RevisionDay 1 - Revision
Day 1 - Revision
Ā 
Tuckman's group development (Introduction)
Tuckman's group development (Introduction)Tuckman's group development (Introduction)
Tuckman's group development (Introduction)
Ā 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)
Ā 
Cost Masterclass
Cost MasterclassCost Masterclass
Cost Masterclass
Ā 
Day 3-9 - Final Revision (Procurement)
Day 3-9 - Final Revision (Procurement)Day 3-9 - Final Revision (Procurement)
Day 3-9 - Final Revision (Procurement)
Ā 

Similar to Manage Integration Projects

CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4Muzette Charles, PMP
Ā 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration managementreddvise
Ā 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
Ā 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete NotesKareemBullard1
Ā 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processesAbdullah Ahmed, PMP, RMP
Ā 
Project integration management
Project integration managementProject integration management
Project integration managementEhsan Ullah
Ā 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete NotesKareemBullard1
Ā 
Project management.docx
Project management.docxProject management.docx
Project management.docxHumaRazi1
Ā 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...Arlene Smith
Ā 
integration management
 integration management integration management
integration managementsaiftahlawi1
Ā 
PMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptxPMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptxKareemBullard1
Ā 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18Nawzad Bilal
Ā 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
Ā 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Fida Karim šŸ‡µšŸ‡°
Ā 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
Ā 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
Ā 

Similar to Manage Integration Projects (20)

CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
Ā 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration management
Ā 
CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4
Ā 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
Ā 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
Ā 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
Ā 
Project integration management
Project integration managementProject integration management
Project integration management
Ā 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
Ā 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
Ā 
Project management.docx
Project management.docxProject management.docx
Project management.docx
Ā 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
Ā 
integration management
 integration management integration management
integration management
Ā 
PMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptxPMP - Session 01 Updated.pptx
PMP - Session 01 Updated.pptx
Ā 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
Ā 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
Ā 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Ā 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
Ā 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
Ā 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
Ā 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
Ā 

More from Jeffrey Cheah

Stakeholder Masterclass
Stakeholder MasterclassStakeholder Masterclass
Stakeholder MasterclassJeffrey Cheah
Ā 
Procurement Masterclass
Procurement MasterclassProcurement Masterclass
Procurement MasterclassJeffrey Cheah
Ā 
Risk Masterclass
Risk MasterclassRisk Masterclass
Risk MasterclassJeffrey Cheah
Ā 
Human Resource Masterclass
Human Resource MasterclassHuman Resource Masterclass
Human Resource MasterclassJeffrey Cheah
Ā 
Scope Masterclass
Scope MasterclassScope Masterclass
Scope MasterclassJeffrey Cheah
Ā 
Day 3-5 - Final Revision (Quality)
Day 3-5 - Final Revision (Quality)Day 3-5 - Final Revision (Quality)
Day 3-5 - Final Revision (Quality)Jeffrey Cheah
Ā 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Jeffrey Cheah
Ā 
Project Management Body of Knowledge (Scope)
Project Management Body of Knowledge (Scope)Project Management Body of Knowledge (Scope)
Project Management Body of Knowledge (Scope)Jeffrey Cheah
Ā 
Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Jeffrey Cheah
Ā 

More from Jeffrey Cheah (9)

Stakeholder Masterclass
Stakeholder MasterclassStakeholder Masterclass
Stakeholder Masterclass
Ā 
Procurement Masterclass
Procurement MasterclassProcurement Masterclass
Procurement Masterclass
Ā 
Risk Masterclass
Risk MasterclassRisk Masterclass
Risk Masterclass
Ā 
Human Resource Masterclass
Human Resource MasterclassHuman Resource Masterclass
Human Resource Masterclass
Ā 
Scope Masterclass
Scope MasterclassScope Masterclass
Scope Masterclass
Ā 
Day 3-5 - Final Revision (Quality)
Day 3-5 - Final Revision (Quality)Day 3-5 - Final Revision (Quality)
Day 3-5 - Final Revision (Quality)
Ā 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)
Ā 
Project Management Body of Knowledge (Scope)
Project Management Body of Knowledge (Scope)Project Management Body of Knowledge (Scope)
Project Management Body of Knowledge (Scope)
Ā 
Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)
Ā 

Recently uploaded

LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
Ā 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
Ā 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
Ā 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
Ā 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
Ā 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
Ā 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
Ā 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
Ā 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
Ā 
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Roomdivyansh0kumar0
Ā 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
Ā 

Recently uploaded (13)

LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
Ā 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
Ā 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
Ā 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Ā 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Ā 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Ā 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
Ā 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
Ā 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
Ā 
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
Ā 
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Servicesauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
Ā 
Call Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance VVIP šŸŽ SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance  VVIP šŸŽ SERVICECall Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance  VVIP šŸŽ SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance VVIP šŸŽ SERVICE
Ā 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
Ā 

Manage Integration Projects

  • 2. 2
  • 3. 3Integration Management Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. Key Concepts ļƒ˜ Project Charter to initiate Projects ļƒ˜ Project Management Plan to plan, execute, monitor & control, and close Projects ļƒ˜ Change Requests to update Projects
  • 4. 4 4.1 Develop Project Charterā€”The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. 4.2 Develop Project Management Planā€”The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The projectā€™s integrated baselines and subsidiary plans may be included within the project management plan. 4.3 Direct and Manage Project Workā€”The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the projectā€™s objectives. 4.4 Monitor and Control Project Workā€”The process of tracking, reviewing, and reporting project progress against the performance objectives defined in the project management plan. 4.5 Perform Integrated Change Controlā€”The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. 4.6 Close Project or Phaseā€”The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project. Integration Management
  • 6. 6Project Charter The Project Charter is a document that formally authorizes the existence of a project and provides the project manager the authority to apply organizational resources to project activities. The key benefit of this document is it creates a formal record of the project and a direct way for senior management to formally accept and commit to the project.
  • 7. 7 4.2 Develop Project Management Plan
  • 8. 8Project Management Plan The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents the actions necessary to define, prepare, integrate and coordinate the various planning activities. The PMP defines how the project is executed, monitored and controlled, and closed. It is progressively elaborated by updates throughout the course of the project. The PMP is also a communication vehicle for ensuring key stakeholders share an understanding of the project. The PMP is NOT a project schedule. A project schedule lists planned dates for performing tasks and activities to meet milestones identified in the project plan.
  • 9. 9 4.3 Direct & Manage Project Work
  • 10. 10Project Management Information System The Project Management Information System (PMIS) provides access to tools such as scheduling tool, work authorization system, configuration management system, information collection and distribution system and other automated systems. Automated gathering and reporting on key performance indicators (KPI) can be part of the PMIS.
  • 11. 11 4.4 Monitor & Control Project Work
  • 12. 12 4.5 Perform Integrated Change Control
  • 13. 13Change Request A Change Request is a formal proposal to modify any document, deliverable or baseline. When issues are found while project work is being performed, change requests are submitted which may modify project policies or procedures, project scope, project budget, project schedule or project quality. Change requests may include: ā€¢ Corrective Action ā€¢ Preventive Action ā€¢ Defect Repair ā€¢ Updates
  • 15. 15Closure Documents Project or phase closure documents, consisting of formal documentation that indicates completion of the project or phase and the transfer of the completed deliverables to others. During project closure, the project manager reviews prior phase documentation, customer acceptance documentation and exit criteria to ensure that all project requirements are completed prior to finalizing the closure of the project. It is then followed by handing over the completed project or phase for business as usual (BAU) activities.
  • 16. 16Lessons Learned Lessons Learned information are transferred to the lessons learned knowledge base for use by future projects or phases. This can include information on issues and risks as well as techniques that worked well applying to future projects.
  • 17. 17