Construction Pics Day by Daybefore
1st day   [lower Grade / lower west Sewer Line / expose House Ledger, Foundation]
2nd day   [inspect Footings, install Posts / tamp Ground / lay Foam – 4ft horizontal from Foundation / lay Plastic, Stone]
3rd day   [notch Addition Posts]
4th day   [install Gutter n Curtain Drain / repair Sewer Line west / cover w stone]
5th day   [install boundry Board / install Addition Beams, Joists, SubFloor / final Grade Area]
6th day   [build n raise Addition west Wall, build east Wall]
7th day   [raise Addition east Wall, build n raise north Wall, install Roof Rafters / temporary Tarp Floor]
8th day   [build Ceiling Joists, Roof Extension , north Ceiling Studs / install east Wall OSB, north Wall OSB n Wrap]
9th day   [install Roof OSB, flashing w Flat / install east Wall Wrap]
10th day   [install west Wall Wrap / install new Roof Shingles w Ridge Vent, flash to Flat Roof]
11th day   [install Deck Ledger Boards w Ice Shield, Beams / inspect Framing / Ceiling Fan Mount / east Windows / rough El...
12th day   [Concealed Electric Inspection / install east west Deck Ledger Flashing, Deck Joists / install Sliding Door]
13th day   [install east west Stair Stringers, Deck Posts
14th day   [Trim out east Steps, start west Steps / install steel exterior Door
15th day   [re install Siding no LR, Soffits west Addition, tear down east side old Soffit – vent, frame n cut screens for...
16th day   [install J and Soffett east side, form alum both ends; start Soffets north; install east and north Windows]
17th day (1/2 day) [finish install alum Soffit Boxes; Insulate]
18th day   [shim House n Sliding Doors for Drywall; Inspect INSULATION; start Siding west Addition; start Decking west Deck]
19th day   north face Siding, Soffit, alum Trim / west Deck Planks, install (7) Post Sleeves, Bases, Caps / hang Drywall, ...
20th day finish east Siding, alum Fascia, J-block; texture Ceiling; finish west F Channel, Siding alum Fascia; mud floor gap
21st day mud n tape bottom Walls, cut n route Sill Plates, finish east-west Deck Planking, repl east lawn border, start Ra...
22nd day SD Handle, Screen, west n east Deck Railing, Fascia; alum trim for Sill Plates, relocate Down Spouts, cover Micro...
23rd day PAINT Addition I/S, entry DOOR, Kitchen Door 1 side; add Dirt n Stone to border; install Screens
24th day install tack strip, backer, Carpet
25th day finish Electric
26th day Gutters
Upcoming SlideShare
Loading in …5
×

Construction pics day by day

4,079 views

Published on

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
4,079
On SlideShare
0
From Embeds
0
Number of Embeds
3,540
Actions
Shares
0
Downloads
6
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Construction pics day by day

  1. 1. Construction Pics Day by Daybefore
  2. 2. 1st day [lower Grade / lower west Sewer Line / expose House Ledger, Foundation]
  3. 3. 2nd day [inspect Footings, install Posts / tamp Ground / lay Foam – 4ft horizontal from Foundation / lay Plastic, Stone]
  4. 4. 3rd day [notch Addition Posts]
  5. 5. 4th day [install Gutter n Curtain Drain / repair Sewer Line west / cover w stone]
  6. 6. 5th day [install boundry Board / install Addition Beams, Joists, SubFloor / final Grade Area]
  7. 7. 6th day [build n raise Addition west Wall, build east Wall]
  8. 8. 7th day [raise Addition east Wall, build n raise north Wall, install Roof Rafters / temporary Tarp Floor]
  9. 9. 8th day [build Ceiling Joists, Roof Extension , north Ceiling Studs / install east Wall OSB, north Wall OSB n Wrap]
  10. 10. 9th day [install Roof OSB, flashing w Flat / install east Wall Wrap]
  11. 11. 10th day [install west Wall Wrap / install new Roof Shingles w Ridge Vent, flash to Flat Roof]
  12. 12. 11th day [install Deck Ledger Boards w Ice Shield, Beams / inspect Framing / Ceiling Fan Mount / east Windows / rough Electric]
  13. 13. 12th day [Concealed Electric Inspection / install east west Deck Ledger Flashing, Deck Joists / install Sliding Door]
  14. 14. 13th day [install east west Stair Stringers, Deck Posts
  15. 15. 14th day [Trim out east Steps, start west Steps / install steel exterior Door
  16. 16. 15th day [re install Siding no LR, Soffits west Addition, tear down east side old Soffit – vent, frame n cut screens for new]
  17. 17. 16th day [install J and Soffett east side, form alum both ends; start Soffets north; install east and north Windows]
  18. 18. 17th day (1/2 day) [finish install alum Soffit Boxes; Insulate]
  19. 19. 18th day [shim House n Sliding Doors for Drywall; Inspect INSULATION; start Siding west Addition; start Decking west Deck]
  20. 20. 19th day north face Siding, Soffit, alum Trim / west Deck Planks, install (7) Post Sleeves, Bases, Caps / hang Drywall, metal Edge
  21. 21. 20th day finish east Siding, alum Fascia, J-block; texture Ceiling; finish west F Channel, Siding alum Fascia; mud floor gap
  22. 22. 21st day mud n tape bottom Walls, cut n route Sill Plates, finish east-west Deck Planking, repl east lawn border, start Railing
  23. 23. 22nd day SD Handle, Screen, west n east Deck Railing, Fascia; alum trim for Sill Plates, relocate Down Spouts, cover Microlams
  24. 24. 23rd day PAINT Addition I/S, entry DOOR, Kitchen Door 1 side; add Dirt n Stone to border; install Screens
  25. 25. 24th day install tack strip, backer, Carpet
  26. 26. 25th day finish Electric
  27. 27. 26th day Gutters

×