The project status report from September 2020 provides updates on the construction progress of 17 towers. For towers 7 through 10, painting of external coats is in progress. Towers 11 through 17 are undergoing internal plastering, painting, and other internal work. Foundation work like concrete slabs is complete for tower 6, while towers 1 through 5 are in earlier stages of internal and external plastering and painting.