The document outlines a 4-phase timeline to rehabilitate the property at 712 Raines Drive over 30 to 45 days. Phase 1 involves full roof replacement, siding installation, and pool repairs over 7 to 10 days. Phase 2 removes doors and wallpaper, patches sheetrock, and paints rooms over 3 to 5 days. Phase 3 demolishes debris, installs interior doors, repairs sheetrock, removes fixtures, and paints over 4 to 7 days. Phase 4 installs cabinets, flooring, and fixes concrete over 4 to 7 days, after which marketing will begin.