IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. III (Mar - Apr. 2015), PP 88-91
www.iosrjournals.org
DOI: 10.9790/1684-12238891 www.iosrjournals.org 88 | Page
Review Paper on Construction Defects
Miss. Neha.V.Bagdiya1
, Prof. Shruti Wadalkar2
1,2, (
Department of Civil Engineering, Pad. D.Y.P.I.E.T, Pune, India)
Abstract: Construction defects are very common and frequently arising in construction project, especially in
the project which has poor workmanship, poor project management in the construction site. Construction defect
can be known as major problem in the construction industry that could cause the value of building decreases. As
the defect impact on time and cost overrun, identification of defect at early stage of construction makes easy to
complete project in stipulated timing. This helps to avoid or minimize defect in future work. Numerous
analytical or statistical methods are available for analyzing impacts and selection of proper method depends
upon: statistical data, time limitation of method. This information further helps to fix responsibilities, penalties
on various parties involved in construction. This data is also required for suggesting different selection of
remedial measures for improving useful life of structure. The purpose of this study is to review various
symptoms & causes of construction defects occurring in construction project.
Keyword: Building Defects, Construction defects.
I. Introduction
Construction defects are always the key concern of the construction industry. Different constructed
facilities generate different types of defects and demands different levels and types of quality depending on the
function, system, types and material used. Various systems have been designed to eliminate defects during
construction operation.
Defect cost is defined as the value of resource expenditure for rework. Various factors are measured
like rework time, materials and equipments to correct the defects. Time is lost in waiting as a consequence of
defects. Defective building construction not only contributes to the final cost of the product but also to the cost
of maintenance which can be considerable. The cost is calculated irrespective of who is going to pay. Defective
construction may lead to complete failure of structure. The construction industry all around the world is getting
modern, advance and growing day by day with the help of information technology age. Defects can affect
success of construction project significantly. More specifically, it has major impact on construction cost,
construction time, and productivity and sustainability aspects also on customer satisfaction
1.1 Defects:
Following are the consequences of defects;
 Dissatisfied Customer
 Extra cost borne by company
 Delay in completion
 Reduced Productivity.
This paper aims to contribute to knowledge of the defect profile of residential buildings regarding the
defect number, type, location, severity and responsible trades. It also identifies various factors causing
construction defects and hence to find justifying measures to reduce defects. Therefore, eliminating defects and
maintaining good quality have an important cost benefit for the society. Although it may be predictable that
defects in a building occur through general wear and tear, defects due to human errors in the construction of a
home should be minimized.
The topic for paper work was selected with an intention that the findings from the literature review,
questionnaire survey and case studies will provide a better solution for problems relating to defects in
construction projects that established in the construction industry. Study was carried out through structured
questionnaire focusing major parties i.e. technical persons, Labours, contractors, customer who buys constructed
products etc.
1.2 Types of Defects
Structural defect:
Structural defect means any defect in a structural element of a building that is attributable to defective
design, defective or faulty workmanship or defective material and sometimes any combination of these.
Building structure includes earth retaining walls, columns, beams and flat slabs.
Review Paper on Construction Defects.
DOI: 10.9790/1684-12238891 www.iosrjournals.org 89 | Page
Structural defect can be categorized as cracks in foundations (Substructure), cracks in floor or slabs
(superstructure), and cracks in walls (superstructure). These defects can be caused by improper soil analysis,
inappropriate site selection, and the use of defective materials. Most of the structural problem can be avoided by
implying the exact and detail of the design and planning. Structural defects in a building can occur over time
due to deterioration, wear and tear, overloading, and poor maintenance. They must be repaired to maintain the
building‟s structure and to prevent any further failures. Regular inspection is the key to protecting the „health‟ of
a building‟s structure. Structural defect that always occurs are steel corrosion, cracks, and deflection.
Non-structural defect:
A non-structural defect in a residential building is described as a defect in a non-structural element of
the building as a result of defective residential building work. Non-structural defect includes defect occurs in the
non-structural components of building, services like in brick work, dampness in old structures, and defects in
plaster works.
II. Literature Review
N. Ahzahar, N.A.Karim(2011) etc discussed Failures and defects are general phenomena in
construction industry. Negative impacts may occur towards cost, duration and resources of project. Failures and
defects can cause needless expenditure and delays. The aim was to identify contribution factors to building
defect and failures, which frequently take place in construction project especially in Penang area in order to
minimize time and cost involved. The data is collectively from questionnaire from various players in
construction industry. This study is succeeds in identifying the common contribution factors of structural defects
and failures in construction project
Josephson and Hammerlund‟s 1999 study of seven buildings through observation‟s and surveys
showed that 32% of all defect costs originated from client and design. 45% from sit management and
approximately 20% from materials and machines. Personal in the best position or prevent defects were directly
contributing to the defects. Most of the defects due to human factors were caused solely by “Forgetfulness and
carelessness”.29% by lack of knowledge, and a very small percentage were intentional. Regarding design
defects, 44% of defect costs were due to lack of knowledge and 50% to lack of motivation. As for workmanship
defects, lack of motivation dominated the costs, but the presence of risks directly increases the chance of
defects.58% of defects resulted from faulty design, 35% from operational and installation, 12% from poor
materials, and systems, and 11% from unexpected users requirement.
Atkinson 2003 found that managerial errors accounted for more than 82% of all building defects and
that these errors have hidden or latent characteristics, suggesting that such errors were not visible at the
construction stage.
Anandet al. 2003 examined the resistance of newly developed masonry work to dampness and leakage
and found that better design helped to prevent defects because it could eliminate workmanship defects.
Sunyoto and Minato 2003 identified inadequate information, unawareness, wrong assumptions, and
lack of knowledge, along – side other organizational and motivational factor as contributory factors to defects at
the design stage.
Wai-Kiong Chong,M.ASCE and Sui-Pheng Low discussed the differences among the defects that
occurred during construction and 2 to 6 years after initial occupancy and finds that the defects at both periods
were very different. Defects found during the occupancy stage are commonly known as latent defects, most of
which were hardly ever found during the construction stage and are thus infrequently accounted for by the
designers and building developers. The paper confirms the need to look at defects in another way and to
establish more effective methods to reduce latent defects.
Seung Heon Han(2008) discussed many researchers and project managers have attempted to improve
project performance by applying new philosophies such as lean principle, just-in-time, pull scheduling, and last
planner. This research explores practical solutions for construction performance improvement by applying the
six sigma principle. This theory provides the metrics required to establish performance improvement goals and a
methodology for measuring and evaluating improvement.. Author focused on the development of the general
methodology to apply the six sigma principles on construction operations relatively than construction materials
in terms of the barometers to measure, evaluate, and improve construction performance.
A.S.Ali and K.H.Wen aimed to investigate workmanship quality performance of construction projects
referring to number of defects take place for new completed building. The research objectives are the factors
contribute to poor workmanship and probable measures to minimize the problem, and also the relationship
between measures identified with the factors. Based on a combination of literature review and questionnaire
surveys, this paper explores the factors contribute to poor workmanship and possible measures to minimize the
problem, and also the relationship between measures identified with the factors. This paper concludes that
construction projects suffered from low quality of workmanship created by the contractors. The most significant
Review Paper on Construction Defects.
DOI: 10.9790/1684-12238891 www.iosrjournals.org 90 | Page
factor contributing to poor workmanship is lack of experience and experience of labours. Correlation test result
shows that the significant factor can be solved by providing training and education to the labours, well
manpower management and proper design. To find out the factors contributing to poor workmanship and
possible measures that can be implemented by contractors. This would help the contractors improve quality
performance on their construction projects.
H.Aljassmi,J.Perera and S.Han studied on understanding defect causalities is indispensableto its
prevention. This paper aims to identify the correlations and inter-causalities amongst the root causes of
construction defects, so as to obtain insights about the complex mechanics of defect causation and help in
developing effective defect prevention strategies. Data was collected through a questionnaire survey of 106
professionals in the construction industry. Correlations and inter-causalities analysis showed that time pressure,
financial constraints and organizational culture were the most influential root causes. This paper aims to take out
the major causes resulting in defects from extensive literature review; and subsequently conduct a survey with
industry practitioners to confirm and revise the causes and then analyze their correlations and inter-causalities.
Nuria Forcada studied a total of 2,351 post-handover defects resulting from four Spanish builders and
seven residential developments are classified according to their location, subcontract, and element. The research
reveals that the most common defects identified by customers at handover were incomplete tile grouting and
incorrect fixtures and fittings in toilets. In addition, failure to apply second coats of paint to walls was deemed a
problematic issue. Typical surface/appearance defects were found to include floor or wall unevenness, stains,
mess, and small cracks and marks, primarily caused by lack of protection. In areas where fixtures, fittings, and
finishes were of a similar nature, such as the kitchen and bathroom, defect types also arose. Determining the
location, subcontract, and element where defects occur in residential buildings can provide very useful
knowledge about areas where builders are likely to make errors or mistakes or take deliberate shortcuts during
construction.
III. Conclusion
The main objective of this research is a preliminary examination of defect with respect to minimize the
cost of construction and improve the quality of construction. Occurrences of defects in buildings lead to
lowering the customer‟s satisfaction level, to stand and progress with increasing reputation in market, customer
oriented construction of buildings needs to be constructed to improve quality and service to end users.. On the
other hand, most important cause is poor workmanship, especially do not compliance with the instruction given
in the specification is also responsible for the occurrence of defects. . Inspection of building is necessary at
specific time interval throughout life of building.. The lack of maintenance or incorrect maintenance can reduce
the effective life of a material, far lower than it should be achieved. This paper concentrated on defects occurs in
construction project after hand over of project. Defect analysis is not so easy task but it is very important
because the building service life and safety is always depends on the strength and durability of building
components and that components are defect free ultimately we get the best service life and safety.
In that paper number of scientist says that the defects are increases the cost of construction and reduces
the life of structure. The reason of defects are very common in everywhere i.e. workmanship, quality of
material, lack of supervision wrong construction method, lack of inspection after construction etc.
IV. Recommendations
A) In the Design Phase
1. Proper Production Management
• During design phase, architect should implement procedures that will subject the design to extensive review
and analysis before it is released to construction.
• Involvement of design team members and subcontractors.
• Proper management of construction documents.
• Complete and well coordinated set of design development documents.
2. Peer Review
• Development of complete, accurate, well-coordinated design and construction documents that are internally
consistent and contain all of the information necessary for the contractor to construct a building without
design defects.
• where a new and/or innovative material and/ or system has been incorporated into the design and
construction documents.
3. Owner Involvement
• The inevitable design changes and coordination that will occur throughout the design phase will be more
effectively accomplished prior to the start of the construction documents phase.
Review Paper on Construction Defects.
DOI: 10.9790/1684-12238891 www.iosrjournals.org 91 | Page
4. Design Schedule
• avoid accelerated and/or shortened design phase.
5. Design and Construction Coordination
• architect and contractor should establish and maintain open lines of communication throughout the project.
6. Construction Manager‟s constructability review of the design and construction documents during the pre-
construction phase of the project will help to minimize potential of design defects.
B) Construction Phase
1. 7eQuality Management implementation, by the contractor, of a comprehensive quality assurance (“QA”) and
quality control (“QC”) program is critical throughout the construction phase of the project.
2. New Building Technology
• Contractor‟s work verification by the manufacturers‟ representative.
• Conduct in-depth inspections of the work by both the architect and the contractor.
• Use experience and trained workers.
• Use the same crew throughout the project.
• Require pre-certification and/or training of the workers by the manufacturer prior to the commencement of
the project.
• Limit overtime and shift work where possible.
References
[1]. Atkinson, G. _1987_. “A century of defects.” Building, 54–55.
[2]. Cheetham, D. _1973_. “Defects in modern buildings.” Building, 225.
[3]. Georgiou, J., Love, P. E. D., and Smith, J. _1999_. “A comparison of defects in houses constructed by owners and registered
builders in the Australian State of Victoria.” Manage. Int. Rev., 17_3_, 160–170.
[4]. Georgiou, J., Smith, J., and Love, P. E. D. _2000_. “A review of builderregistration in the State of Victoria, Australia.” Struct Surv.,
18_1_,38–45.
[5]. Georgiou, J., Smith, J., and Love, P. E. D. _2002a_. “Defects and quality control in the housing industry: Implications for
management and regulatory control.” Proc., 8th Int. Conf. on ISO 9000 & TQM
[6]. (Change Management) _CD-ROM_, Centre for Management Quality Research _CMQR_ at RMIT Univ., RMIT Storey Hall,
Melbourne, Australia.
[7]. Georgiou, J., Smith, J., and Love, P. E. D. _2002b_. “Quality improvement through builder registration.” Proc., 8th Int. Conf. on
ISO 9000 & TQM (Change Management) _CD-ROM_, Centre for Management Quality Research _CMQR_ at RMIT Univ., RMIT
Storey Hall, Melbourne, Australia.
[8]. Hammarlund, Y., and Josephson, P. E. _1991_. “Sources of quality failures in building.” Proc., European Symp. on Management,
Quality and Economics in Housing and Other Building Sectors, Lisbon, Portugal, 671–679.
[9]. Ilozor, B., Okoroh, M. I., and Egbu, C. E. _2004_. “Understanding residentialhouse defects in Australia from the State of Victoria.”
Build. Environ., 39, 327–337.
[10]. Josephson, P.-E., and Hammarlund, Y. _1996_. “The costs of defects in construction.” The organisation and management of
construction: Shaping theory and practice, D. D. Langford and A. Retik, eds., Vol. 2, 519–528.
[11]. Josephson, P.-E., and Hammarlund, Y. _1999_. “The causes and costs of defects in construction. A study of seven building
projects.” Autom. Constr., 8_6_, 681–642.
[12]. Josephson, P.-E., and Larsson, B. _2001_. “The role of early detection of human errors in building projects.” Proc., CIB World
Building Congress-Performance in the Product and Practice _CD-ROM_,Wellington Convention Centre, Wellington, New Zealand.
[13]. Knocke, J. _1992_. Post construction liability and insurance, E & FN Spon, London.
[14]. Love, P. E. D. _2002_. “Influence of project type and procurement method on rework costs in building construction projects.” J.
Constr. Eng. Manage., 128_1_, 18–29.

More Related Content

What's hot

A new approach to estimate damage in concrete beams using non linearity
A new approach to estimate damage in concrete beams using non linearityA new approach to estimate damage in concrete beams using non linearity
A new approach to estimate damage in concrete beams using non linearityUniversity of Malaya
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET Journal
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...eSAT Journals
 
IRJET-Understanding the Structural Audit
IRJET-Understanding the Structural AuditIRJET-Understanding the Structural Audit
IRJET-Understanding the Structural AuditIRJET Journal
 
Determining Costs of Construction Errors, Based on Fuzzy Logic Systems
Determining Costs of Construction Errors, Based on Fuzzy Logic SystemsDetermining Costs of Construction Errors, Based on Fuzzy Logic Systems
Determining Costs of Construction Errors, Based on Fuzzy Logic SystemsMohammad Lemar ZALMAİ
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
B0363010015
B0363010015B0363010015
B0363010015theijes
 
Site Safety Management and planning for Building Construction
Site Safety Management and planning for Building ConstructionSite Safety Management and planning for Building Construction
Site Safety Management and planning for Building ConstructionAbu Yousuf Jamil
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projectsijtsrd
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
Reducing i.t. project management failures adib chehade
Reducing i.t. project management failures  adib chehadeReducing i.t. project management failures  adib chehade
Reducing i.t. project management failures adib chehadeAdib Chehade
 
Ballard et al. 2016 - Filmmaking and Construction_ Two Project Production Sy...
Ballard et al.  2016 - Filmmaking and Construction_ Two Project Production Sy...Ballard et al.  2016 - Filmmaking and Construction_ Two Project Production Sy...
Ballard et al. 2016 - Filmmaking and Construction_ Two Project Production Sy...Christin Egebjerg
 
The effectiveness of test-driven development approach on software projects: A...
The effectiveness of test-driven development approach on software projects: A...The effectiveness of test-driven development approach on software projects: A...
The effectiveness of test-driven development approach on software projects: A...journalBEEI
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
what makes a great software engineer?
what makes a great software engineer?what makes a great software engineer?
what makes a great software engineer?mustafa sarac
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 

What's hot (20)

Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
A new approach to estimate damage in concrete beams using non linearity
A new approach to estimate damage in concrete beams using non linearityA new approach to estimate damage in concrete beams using non linearity
A new approach to estimate damage in concrete beams using non linearity
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
 
IRJET-Understanding the Structural Audit
IRJET-Understanding the Structural AuditIRJET-Understanding the Structural Audit
IRJET-Understanding the Structural Audit
 
Determining Costs of Construction Errors, Based on Fuzzy Logic Systems
Determining Costs of Construction Errors, Based on Fuzzy Logic SystemsDetermining Costs of Construction Errors, Based on Fuzzy Logic Systems
Determining Costs of Construction Errors, Based on Fuzzy Logic Systems
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
B0363010015
B0363010015B0363010015
B0363010015
 
Site Safety Management and planning for Building Construction
Site Safety Management and planning for Building ConstructionSite Safety Management and planning for Building Construction
Site Safety Management and planning for Building Construction
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
Reducing i.t. project management failures adib chehade
Reducing i.t. project management failures  adib chehadeReducing i.t. project management failures  adib chehade
Reducing i.t. project management failures adib chehade
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
Ballard et al. 2016 - Filmmaking and Construction_ Two Project Production Sy...
Ballard et al.  2016 - Filmmaking and Construction_ Two Project Production Sy...Ballard et al.  2016 - Filmmaking and Construction_ Two Project Production Sy...
Ballard et al. 2016 - Filmmaking and Construction_ Two Project Production Sy...
 
The effectiveness of test-driven development approach on software projects: A...
The effectiveness of test-driven development approach on software projects: A...The effectiveness of test-driven development approach on software projects: A...
The effectiveness of test-driven development approach on software projects: A...
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
what makes a great software engineer?
what makes a great software engineer?what makes a great software engineer?
what makes a great software engineer?
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
Ijmet 10 01_190
Ijmet 10 01_190Ijmet 10 01_190
Ijmet 10 01_190
 

Viewers also liked

Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...
Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...
Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...IOSR Journals
 
Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...
Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...
Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...IOSR Journals
 
Premium Customer Authentication by Using Third Generation Packet Network
Premium Customer Authentication by Using Third Generation Packet NetworkPremium Customer Authentication by Using Third Generation Packet Network
Premium Customer Authentication by Using Third Generation Packet NetworkIOSR Journals
 
Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...
Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...
Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...IOSR Journals
 
A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...
A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...
A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...IOSR Journals
 
Parallel Hardware Implementation of Convolution using Vedic Mathematics
Parallel Hardware Implementation of Convolution using Vedic MathematicsParallel Hardware Implementation of Convolution using Vedic Mathematics
Parallel Hardware Implementation of Convolution using Vedic MathematicsIOSR Journals
 
Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...
Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...
Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...IOSR Journals
 
Cash Flow Valuation Mode Lin Discrete Time
Cash Flow Valuation Mode Lin Discrete TimeCash Flow Valuation Mode Lin Discrete Time
Cash Flow Valuation Mode Lin Discrete TimeIOSR Journals
 
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...IOSR Journals
 
Orientation of Radar Antenna
Orientation of Radar AntennaOrientation of Radar Antenna
Orientation of Radar AntennaIOSR Journals
 
Effect of substrate temperature on the morphological and optical properties o...
Effect of substrate temperature on the morphological and optical properties o...Effect of substrate temperature on the morphological and optical properties o...
Effect of substrate temperature on the morphological and optical properties o...IOSR Journals
 
Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...
Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...
Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...IOSR Journals
 
Video Encryption and Decryption with Authentication using Artificial Neural N...
Video Encryption and Decryption with Authentication using Artificial Neural N...Video Encryption and Decryption with Authentication using Artificial Neural N...
Video Encryption and Decryption with Authentication using Artificial Neural N...IOSR Journals
 
A Study on Fire Detection System using Statistic Color Model
A Study on Fire Detection System using Statistic Color ModelA Study on Fire Detection System using Statistic Color Model
A Study on Fire Detection System using Statistic Color ModelIOSR Journals
 
Implementation of Various Cryptosystem Using Chaos
Implementation of Various Cryptosystem Using ChaosImplementation of Various Cryptosystem Using Chaos
Implementation of Various Cryptosystem Using ChaosIOSR Journals
 
Improvement of Congestion window and Link utilization of High Speed Protocols...
Improvement of Congestion window and Link utilization of High Speed Protocols...Improvement of Congestion window and Link utilization of High Speed Protocols...
Improvement of Congestion window and Link utilization of High Speed Protocols...IOSR Journals
 

Viewers also liked (20)

Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...
Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...
Android Malware: Study and analysis of malware for privacy leak in ad-hoc net...
 
Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...
Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...
Effect of Different Physico-Chemical Parameters on Production ofAmylase by Ba...
 
Premium Customer Authentication by Using Third Generation Packet Network
Premium Customer Authentication by Using Third Generation Packet NetworkPremium Customer Authentication by Using Third Generation Packet Network
Premium Customer Authentication by Using Third Generation Packet Network
 
Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...
Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...
Implementation of Fuzzy Logic for the High-Resolution Remote Sensing Images w...
 
A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...
A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...
A Novel Learning Formulation in a unified Min-Max Framework for Computer Aide...
 
Parallel Hardware Implementation of Convolution using Vedic Mathematics
Parallel Hardware Implementation of Convolution using Vedic MathematicsParallel Hardware Implementation of Convolution using Vedic Mathematics
Parallel Hardware Implementation of Convolution using Vedic Mathematics
 
Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...
Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...
Impact of Hepatitis B Virus (HBV) Vaccination in Childrens Born to HBV Positi...
 
Cash Flow Valuation Mode Lin Discrete Time
Cash Flow Valuation Mode Lin Discrete TimeCash Flow Valuation Mode Lin Discrete Time
Cash Flow Valuation Mode Lin Discrete Time
 
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
 
Orientation of Radar Antenna
Orientation of Radar AntennaOrientation of Radar Antenna
Orientation of Radar Antenna
 
Effect of substrate temperature on the morphological and optical properties o...
Effect of substrate temperature on the morphological and optical properties o...Effect of substrate temperature on the morphological and optical properties o...
Effect of substrate temperature on the morphological and optical properties o...
 
D0512327
D0512327D0512327
D0512327
 
F1303053542
F1303053542F1303053542
F1303053542
 
Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...
Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...
Prevalence of Cleft Lip and Palate in Abuja Nigeria (From December2000 to Dec...
 
M010527678
M010527678M010527678
M010527678
 
Video Encryption and Decryption with Authentication using Artificial Neural N...
Video Encryption and Decryption with Authentication using Artificial Neural N...Video Encryption and Decryption with Authentication using Artificial Neural N...
Video Encryption and Decryption with Authentication using Artificial Neural N...
 
A Study on Fire Detection System using Statistic Color Model
A Study on Fire Detection System using Statistic Color ModelA Study on Fire Detection System using Statistic Color Model
A Study on Fire Detection System using Statistic Color Model
 
Implementation of Various Cryptosystem Using Chaos
Implementation of Various Cryptosystem Using ChaosImplementation of Various Cryptosystem Using Chaos
Implementation of Various Cryptosystem Using Chaos
 
Improvement of Congestion window and Link utilization of High Speed Protocols...
Improvement of Congestion window and Link utilization of High Speed Protocols...Improvement of Congestion window and Link utilization of High Speed Protocols...
Improvement of Congestion window and Link utilization of High Speed Protocols...
 
O01213106111
O01213106111O01213106111
O01213106111
 

Similar to L012238891

IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IRJET- A Study on Low Cost Housing Construction with Delay Management
IRJET- A Study on Low Cost Housing Construction with Delay ManagementIRJET- A Study on Low Cost Housing Construction with Delay Management
IRJET- A Study on Low Cost Housing Construction with Delay ManagementIRJET Journal
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...Alexander Decker
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...Alexander Decker
 
Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...
Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...
Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...IJERA Editor
 
Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Alexander Decker
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...IRJET Journal
 
Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfYohannesBizuneheWeld
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSIAEME Publication
 

Similar to L012238891 (20)

IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- A Study on Low Cost Housing Construction with Delay Management
IRJET- A Study on Low Cost Housing Construction with Delay ManagementIRJET- A Study on Low Cost Housing Construction with Delay Management
IRJET- A Study on Low Cost Housing Construction with Delay Management
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
20320140503023
2032014050302320320140503023
20320140503023
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
E253446
E253446E253446
E253446
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
 
Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...
Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...
Discrete Event Simulation Analysis of the Effect of Labor Absenteeism on the ...
 
Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
 
Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdf
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Hyundai Motor Group
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 

Recently uploaded (20)

SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2Next-generation AAM aircraft unveiled by Supernal, S-A2
Next-generation AAM aircraft unveiled by Supernal, S-A2
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 

L012238891

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. III (Mar - Apr. 2015), PP 88-91 www.iosrjournals.org DOI: 10.9790/1684-12238891 www.iosrjournals.org 88 | Page Review Paper on Construction Defects Miss. Neha.V.Bagdiya1 , Prof. Shruti Wadalkar2 1,2, ( Department of Civil Engineering, Pad. D.Y.P.I.E.T, Pune, India) Abstract: Construction defects are very common and frequently arising in construction project, especially in the project which has poor workmanship, poor project management in the construction site. Construction defect can be known as major problem in the construction industry that could cause the value of building decreases. As the defect impact on time and cost overrun, identification of defect at early stage of construction makes easy to complete project in stipulated timing. This helps to avoid or minimize defect in future work. Numerous analytical or statistical methods are available for analyzing impacts and selection of proper method depends upon: statistical data, time limitation of method. This information further helps to fix responsibilities, penalties on various parties involved in construction. This data is also required for suggesting different selection of remedial measures for improving useful life of structure. The purpose of this study is to review various symptoms & causes of construction defects occurring in construction project. Keyword: Building Defects, Construction defects. I. Introduction Construction defects are always the key concern of the construction industry. Different constructed facilities generate different types of defects and demands different levels and types of quality depending on the function, system, types and material used. Various systems have been designed to eliminate defects during construction operation. Defect cost is defined as the value of resource expenditure for rework. Various factors are measured like rework time, materials and equipments to correct the defects. Time is lost in waiting as a consequence of defects. Defective building construction not only contributes to the final cost of the product but also to the cost of maintenance which can be considerable. The cost is calculated irrespective of who is going to pay. Defective construction may lead to complete failure of structure. The construction industry all around the world is getting modern, advance and growing day by day with the help of information technology age. Defects can affect success of construction project significantly. More specifically, it has major impact on construction cost, construction time, and productivity and sustainability aspects also on customer satisfaction 1.1 Defects: Following are the consequences of defects;  Dissatisfied Customer  Extra cost borne by company  Delay in completion  Reduced Productivity. This paper aims to contribute to knowledge of the defect profile of residential buildings regarding the defect number, type, location, severity and responsible trades. It also identifies various factors causing construction defects and hence to find justifying measures to reduce defects. Therefore, eliminating defects and maintaining good quality have an important cost benefit for the society. Although it may be predictable that defects in a building occur through general wear and tear, defects due to human errors in the construction of a home should be minimized. The topic for paper work was selected with an intention that the findings from the literature review, questionnaire survey and case studies will provide a better solution for problems relating to defects in construction projects that established in the construction industry. Study was carried out through structured questionnaire focusing major parties i.e. technical persons, Labours, contractors, customer who buys constructed products etc. 1.2 Types of Defects Structural defect: Structural defect means any defect in a structural element of a building that is attributable to defective design, defective or faulty workmanship or defective material and sometimes any combination of these. Building structure includes earth retaining walls, columns, beams and flat slabs.
  • 2. Review Paper on Construction Defects. DOI: 10.9790/1684-12238891 www.iosrjournals.org 89 | Page Structural defect can be categorized as cracks in foundations (Substructure), cracks in floor or slabs (superstructure), and cracks in walls (superstructure). These defects can be caused by improper soil analysis, inappropriate site selection, and the use of defective materials. Most of the structural problem can be avoided by implying the exact and detail of the design and planning. Structural defects in a building can occur over time due to deterioration, wear and tear, overloading, and poor maintenance. They must be repaired to maintain the building‟s structure and to prevent any further failures. Regular inspection is the key to protecting the „health‟ of a building‟s structure. Structural defect that always occurs are steel corrosion, cracks, and deflection. Non-structural defect: A non-structural defect in a residential building is described as a defect in a non-structural element of the building as a result of defective residential building work. Non-structural defect includes defect occurs in the non-structural components of building, services like in brick work, dampness in old structures, and defects in plaster works. II. Literature Review N. Ahzahar, N.A.Karim(2011) etc discussed Failures and defects are general phenomena in construction industry. Negative impacts may occur towards cost, duration and resources of project. Failures and defects can cause needless expenditure and delays. The aim was to identify contribution factors to building defect and failures, which frequently take place in construction project especially in Penang area in order to minimize time and cost involved. The data is collectively from questionnaire from various players in construction industry. This study is succeeds in identifying the common contribution factors of structural defects and failures in construction project Josephson and Hammerlund‟s 1999 study of seven buildings through observation‟s and surveys showed that 32% of all defect costs originated from client and design. 45% from sit management and approximately 20% from materials and machines. Personal in the best position or prevent defects were directly contributing to the defects. Most of the defects due to human factors were caused solely by “Forgetfulness and carelessness”.29% by lack of knowledge, and a very small percentage were intentional. Regarding design defects, 44% of defect costs were due to lack of knowledge and 50% to lack of motivation. As for workmanship defects, lack of motivation dominated the costs, but the presence of risks directly increases the chance of defects.58% of defects resulted from faulty design, 35% from operational and installation, 12% from poor materials, and systems, and 11% from unexpected users requirement. Atkinson 2003 found that managerial errors accounted for more than 82% of all building defects and that these errors have hidden or latent characteristics, suggesting that such errors were not visible at the construction stage. Anandet al. 2003 examined the resistance of newly developed masonry work to dampness and leakage and found that better design helped to prevent defects because it could eliminate workmanship defects. Sunyoto and Minato 2003 identified inadequate information, unawareness, wrong assumptions, and lack of knowledge, along – side other organizational and motivational factor as contributory factors to defects at the design stage. Wai-Kiong Chong,M.ASCE and Sui-Pheng Low discussed the differences among the defects that occurred during construction and 2 to 6 years after initial occupancy and finds that the defects at both periods were very different. Defects found during the occupancy stage are commonly known as latent defects, most of which were hardly ever found during the construction stage and are thus infrequently accounted for by the designers and building developers. The paper confirms the need to look at defects in another way and to establish more effective methods to reduce latent defects. Seung Heon Han(2008) discussed many researchers and project managers have attempted to improve project performance by applying new philosophies such as lean principle, just-in-time, pull scheduling, and last planner. This research explores practical solutions for construction performance improvement by applying the six sigma principle. This theory provides the metrics required to establish performance improvement goals and a methodology for measuring and evaluating improvement.. Author focused on the development of the general methodology to apply the six sigma principles on construction operations relatively than construction materials in terms of the barometers to measure, evaluate, and improve construction performance. A.S.Ali and K.H.Wen aimed to investigate workmanship quality performance of construction projects referring to number of defects take place for new completed building. The research objectives are the factors contribute to poor workmanship and probable measures to minimize the problem, and also the relationship between measures identified with the factors. Based on a combination of literature review and questionnaire surveys, this paper explores the factors contribute to poor workmanship and possible measures to minimize the problem, and also the relationship between measures identified with the factors. This paper concludes that construction projects suffered from low quality of workmanship created by the contractors. The most significant
  • 3. Review Paper on Construction Defects. DOI: 10.9790/1684-12238891 www.iosrjournals.org 90 | Page factor contributing to poor workmanship is lack of experience and experience of labours. Correlation test result shows that the significant factor can be solved by providing training and education to the labours, well manpower management and proper design. To find out the factors contributing to poor workmanship and possible measures that can be implemented by contractors. This would help the contractors improve quality performance on their construction projects. H.Aljassmi,J.Perera and S.Han studied on understanding defect causalities is indispensableto its prevention. This paper aims to identify the correlations and inter-causalities amongst the root causes of construction defects, so as to obtain insights about the complex mechanics of defect causation and help in developing effective defect prevention strategies. Data was collected through a questionnaire survey of 106 professionals in the construction industry. Correlations and inter-causalities analysis showed that time pressure, financial constraints and organizational culture were the most influential root causes. This paper aims to take out the major causes resulting in defects from extensive literature review; and subsequently conduct a survey with industry practitioners to confirm and revise the causes and then analyze their correlations and inter-causalities. Nuria Forcada studied a total of 2,351 post-handover defects resulting from four Spanish builders and seven residential developments are classified according to their location, subcontract, and element. The research reveals that the most common defects identified by customers at handover were incomplete tile grouting and incorrect fixtures and fittings in toilets. In addition, failure to apply second coats of paint to walls was deemed a problematic issue. Typical surface/appearance defects were found to include floor or wall unevenness, stains, mess, and small cracks and marks, primarily caused by lack of protection. In areas where fixtures, fittings, and finishes were of a similar nature, such as the kitchen and bathroom, defect types also arose. Determining the location, subcontract, and element where defects occur in residential buildings can provide very useful knowledge about areas where builders are likely to make errors or mistakes or take deliberate shortcuts during construction. III. Conclusion The main objective of this research is a preliminary examination of defect with respect to minimize the cost of construction and improve the quality of construction. Occurrences of defects in buildings lead to lowering the customer‟s satisfaction level, to stand and progress with increasing reputation in market, customer oriented construction of buildings needs to be constructed to improve quality and service to end users.. On the other hand, most important cause is poor workmanship, especially do not compliance with the instruction given in the specification is also responsible for the occurrence of defects. . Inspection of building is necessary at specific time interval throughout life of building.. The lack of maintenance or incorrect maintenance can reduce the effective life of a material, far lower than it should be achieved. This paper concentrated on defects occurs in construction project after hand over of project. Defect analysis is not so easy task but it is very important because the building service life and safety is always depends on the strength and durability of building components and that components are defect free ultimately we get the best service life and safety. In that paper number of scientist says that the defects are increases the cost of construction and reduces the life of structure. The reason of defects are very common in everywhere i.e. workmanship, quality of material, lack of supervision wrong construction method, lack of inspection after construction etc. IV. Recommendations A) In the Design Phase 1. Proper Production Management • During design phase, architect should implement procedures that will subject the design to extensive review and analysis before it is released to construction. • Involvement of design team members and subcontractors. • Proper management of construction documents. • Complete and well coordinated set of design development documents. 2. Peer Review • Development of complete, accurate, well-coordinated design and construction documents that are internally consistent and contain all of the information necessary for the contractor to construct a building without design defects. • where a new and/or innovative material and/ or system has been incorporated into the design and construction documents. 3. Owner Involvement • The inevitable design changes and coordination that will occur throughout the design phase will be more effectively accomplished prior to the start of the construction documents phase.
  • 4. Review Paper on Construction Defects. DOI: 10.9790/1684-12238891 www.iosrjournals.org 91 | Page 4. Design Schedule • avoid accelerated and/or shortened design phase. 5. Design and Construction Coordination • architect and contractor should establish and maintain open lines of communication throughout the project. 6. Construction Manager‟s constructability review of the design and construction documents during the pre- construction phase of the project will help to minimize potential of design defects. B) Construction Phase 1. 7eQuality Management implementation, by the contractor, of a comprehensive quality assurance (“QA”) and quality control (“QC”) program is critical throughout the construction phase of the project. 2. New Building Technology • Contractor‟s work verification by the manufacturers‟ representative. • Conduct in-depth inspections of the work by both the architect and the contractor. • Use experience and trained workers. • Use the same crew throughout the project. • Require pre-certification and/or training of the workers by the manufacturer prior to the commencement of the project. • Limit overtime and shift work where possible. References [1]. Atkinson, G. _1987_. “A century of defects.” Building, 54–55. [2]. Cheetham, D. _1973_. “Defects in modern buildings.” Building, 225. [3]. Georgiou, J., Love, P. E. D., and Smith, J. _1999_. “A comparison of defects in houses constructed by owners and registered builders in the Australian State of Victoria.” Manage. Int. Rev., 17_3_, 160–170. [4]. Georgiou, J., Smith, J., and Love, P. E. D. _2000_. “A review of builderregistration in the State of Victoria, Australia.” Struct Surv., 18_1_,38–45. [5]. Georgiou, J., Smith, J., and Love, P. E. D. _2002a_. “Defects and quality control in the housing industry: Implications for management and regulatory control.” Proc., 8th Int. Conf. on ISO 9000 & TQM [6]. (Change Management) _CD-ROM_, Centre for Management Quality Research _CMQR_ at RMIT Univ., RMIT Storey Hall, Melbourne, Australia. [7]. Georgiou, J., Smith, J., and Love, P. E. D. _2002b_. “Quality improvement through builder registration.” Proc., 8th Int. Conf. on ISO 9000 & TQM (Change Management) _CD-ROM_, Centre for Management Quality Research _CMQR_ at RMIT Univ., RMIT Storey Hall, Melbourne, Australia. [8]. Hammarlund, Y., and Josephson, P. E. _1991_. “Sources of quality failures in building.” Proc., European Symp. on Management, Quality and Economics in Housing and Other Building Sectors, Lisbon, Portugal, 671–679. [9]. Ilozor, B., Okoroh, M. I., and Egbu, C. E. _2004_. “Understanding residentialhouse defects in Australia from the State of Victoria.” Build. Environ., 39, 327–337. [10]. Josephson, P.-E., and Hammarlund, Y. _1996_. “The costs of defects in construction.” The organisation and management of construction: Shaping theory and practice, D. D. Langford and A. Retik, eds., Vol. 2, 519–528. [11]. Josephson, P.-E., and Hammarlund, Y. _1999_. “The causes and costs of defects in construction. A study of seven building projects.” Autom. Constr., 8_6_, 681–642. [12]. Josephson, P.-E., and Larsson, B. _2001_. “The role of early detection of human errors in building projects.” Proc., CIB World Building Congress-Performance in the Product and Practice _CD-ROM_,Wellington Convention Centre, Wellington, New Zealand. [13]. Knocke, J. _1992_. Post construction liability and insurance, E & FN Spon, London. [14]. Love, P. E. D. _2002_. “Influence of project type and procurement method on rework costs in building construction projects.” J. Constr. Eng. Manage., 128_1_, 18–29.