SlideShare a Scribd company logo
1 of 11
Download to read offline
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 5 Ver. III (Sep. - Oct. 2015), PP 64-74
www.iosrjournals.org
DOI: 10.9790/1684-12536474 www.iosrjournals.org 64 | Page
Automated Monitoring and Measuring Improvement of
Production System Performance
*Maha M. A. Lashin, **Abou Bakr M.Elhady, & ***Rehab E. El Badway
* Mechanical Engineering Department, Shoubra faculty of Engineering, Banha University, ** Lead Scientist,
Egyptian Space Program, *** Lead Scientist, Egyptian Space Program.
Abstract: Overall equipment effectiveness OEE represents a set of key characteristics that allows monitoring
the efficiency and productivity of the manufacturing processes. The main purpose of any OEE initiative is to
become the most efficient, most effective manufacturer within a market, minimizing the main losses. Overall line
effectiveness OLE is another OEE related to measure productivity of production line. It is a powerful metric of
manufacturing performance incorporating measures of the availability, performance efficiency, and quality of a
given processes along the manufacturing line. There are many methods exist by which productivity could be
analyzed and improved, such simulation software that allows users to monitor and identify the problems faced
for improving the productivity of the company.
In the present paper a simulation program (OLE analyzer program) developed to monitor production system
and identify the line based on OLE. The methodology depends on developing the OLE metrics to be more
accurate and suitable for implementing on a production line that all involving number of machine arranged in
series and parallel. It deals with each machine in the production line with its actual performance. The proposed
methodology was applied to a case study where the OLE metric were 46.84% related to the six big losses
(breakdown, setup, idle time, reduced speed, time loss, reject on startup, and production reject), and low
development of losses improvement were assessed.
The study suggested the area of weakness suffer from lack of learning orientation that is ought to be improved
and at the same time, a variety of specific recommendations are provided. After implement the computer
software methodology, the improvements plan the OLE value increased to 68.94%.
Keywords: Overall equipment effectiveness – overall line effectiveness – OLE analyzer program.
I. Introduction
Markets competitions challenges are facing companies to implement various productivity improvement
efforts to meet the needs of ever changing market demands. The total productive maintenance paradigm,
launched by Nakajima [1], has provided a quantitative metric for measuring productivity of an individual
production component. The purpose of Overall Equipment Effectiveness OEE was firstly defined. OEE utilized
to evaluate the progress of the Total Productive Maintenance TPM philosophy through the measure of
individual equipment. Nakajima recognized and categorized the main losses related to availability, performance,
and quality. He established the “six big losses” as follows:
1- Start up and yield losses at the early stage of production,
2- Setup and adjustment for product mix change,
3- Production losses when temporary malfunctions occur,
4- Differences in equipment design speed and actual operating speed,
5- Defects caused by malfunctioning equipment, and
6- Poor productivity and lost yield due to poor quality.
However, due to it is widely spreading in industrial use and effectiveness as a performance
measurement for individual equipment. Further research has attempted to expand the application scope of OEE
to entire processes, workshops, factories and production planets. In addition, its evaluating scope has also been
expanded through the inclusion of more detailed elements of performance than just availability, performance
and quality. Sherwin [2] proposed overall process effectiveness to measure the performance of whole production
processes. Nachiappan and Anantharam [3] introduce a definition of Overall Line Effectiveness, to evaluate the
effectiveness of a continuous product line manufacturing system. They used a systematic methodology based on
overall equipment effectiveness OEE metrics to model the productivity of a line manufacturing system in terms
of OLE. Computer simulation was carried out for the evaluation of the OLE, identifying the bottle-neck
machines and the effect of specific contributing parameter for improvement. Braglia et al. [4] presented overall
equipment effectiveness of a manufacturing line to assess the performance of a production line. Oechsneret al.
[5] proposed overall FAB effectiveness to measure the performance of an entire factory. On the other
hand, Garza-Reyes [6] developed Overall Resource Effectiveness, which also considers material efficiency and
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 65 | Page
variations in material and process cost as part of the evaluation of overall effectiveness, see also Garza-Reyes et
al. [7]. Although OEE was mainly designed to monitor and control performance, Dal [8] suggests that the role of
OEE goes far beyond the task of just monitoring and controlling. This is because OEE takes into account
process improvement in iterative, prevents the sub-optimization of individual machines or production lines,
provides a systematic method for establishing production targets, and incorporates practical management tools
and techniques in order to achieve balanced view of process availability, performance and quality. Moreover,
OEE can be used as an indicator of process improvement and as an approach to achieve it. Dal et al. [9] used it
to measure the improvement of a process within a manufacturing environment. Bamberet al. [10] remark that
OEE is often used as a driver for improving the performance of a business by concentrating on quality,
productivity and machine utilization issues and hence aimed at reducing non-valued adding activities often
inherent in manufacturing processes. In the case study by Dal et al. [9], it was reported that OEE not only helped
to measure the improvement in the area in which it was implemented but also that it enabled new levels of
performance measurement to be introduced.
There are software package [13-14-15] can be used to calculate OEE automated like CMMS, ShopVue
OEE, and GainSeeker. This software’s can determine the OEE value and plot the charts of its quality,
availability, and performance.
In the present study a computer software package is created to calculate OEE, OLE values through
calculate the losses in time for process of the productivity line and give a percentage chart for this losses times.
Also the charts of availability, performance, and quality values can be draw before and after improvement
processes to make the comparison for this process losses time easy. The report for productivity line for each
shift can be get daily, weekly, and monthly. Finally the software can draw a chart value for each losses times
during the productivity process.
To implement automated monitoring a real world industrial case is studied. A case study (Ideal
Standard Egypt- Company of bathtubs version Florida) used to applied the software in each productivity process
to decrease the time losses during this process to increase the productivity range.
II. Case Study Specifications
The company included 6 departments (Heating, Forming, Coating, Drying, Trimming, Finishing, and
Testing & Packing) as show in Figure1 working 24 hours daily in 3 shifts at 5 separated product lines and the
production rate for each line is 80 bathtub/shift.
Figure 1: Schematic Layout of the Manufacturing Departments
There are big time losses related to;
 Startup rejects (acrylic sheet defect, heated acrylic sheets rejects, bathtub defects, bathtub reject, visual
bathtub inspection, and final test for bathtub reject).
 Idle time (waiting for material, forklift, heated sheet, mould, bathtub, grease the machine, and operator
unavailable).
 Setup and adjustment (setup preparation, cleaning sheet, adjustment sheet, changing tools, balance
adjustment, cleaning, mix the chemical material for coating, visual inspection for acrylic sheet,
bathtub, wooden frame, jigsaw, and product inspection).
 Production rejects (scrap, and rework).
 Speed loss (low temperature, slow evacuations, speed of fan, blinder, moving belt, saw machine,
drilling machine, emery machine, and stretching machine).
 Breakdown (failure of oven, fan, forming machine, dry cabinet, moving belt, drilling machine, saw
machine, emery machine, spray gun, air pump, and stretching machine).
This losses cause a lost time in the all departments within 24-146 hr/week as show in Table1.
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 66 | Page
Table 1: Time Losses during a Working Week for the Manufacturing Department
Manufacturing Big Time Losses (hr/w
eek)
Total Time Run Time for each
department
Department Startup
Rejects
Idle
Tim
e
Setup and
Adjustmen
t
Productio
n Rejects
Speed
Loss
Brea
kdow
n
Loss for each
Departmen
(hr/week)
(hr/week)
Heating - 13 18 2 4 10 47 120
Forming - 31 95 6 4 10 146 120
Coating 3 39 22 4 2 48 118 120
Drying
Cabinet
4 7 8 1 2 2 24 120
Trimming 2 8 12 2 1 6 31 120
Finishing,
Testing, and
Packing
3 8 11 8 0.5 4 34.5 120
Sum of Big
Loss Time
(hr/week)
12 106 166 23 13.5 80 400.5 720
Compared with the actually run the time loss found within range 1.7% (related to startup reject) and
23.2% (related to setup and adjustment). Six big time losses for the manufacturing departments through one
week working time show in Figure2.
Figure 2: Big Six Time Losses for Manufacturing Departments through One Week
Table 2: Quantity Losses during a Working Week for the Manufacturing Department
Manufacturing Big Losses Quantity Products Losses for
each Department
Department Startup Rejects Production Rejects (piece/week)
Heating 19 10 29
Forming 11 25 36
Coating 15 44 59
Drying Cabinet - 22 22
Trimming 10 34 44
Finishing, Testing, and
Packing
13 54 67
Figure3: Quantity Losses for each Department Weekly
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 67 | Page
As show in Table 2 during working week the quantity pieces lost were within 22-67 piece/department.
The biggest losses in quantity were found in finishing department and the lower value was found in drying
cabinet department as Figure 3 explained.
The created software package is developed by Visual basic program; it's helpful for any industry which
is willing to implement the overall equipment effectiveness (OEE) concept. This software depends on
implement automated monitoring and collects continuous measurements manually to improve the productivity
of the industry company.
III. Theoretical Equations Used In the Program
The OEE, and OLE values can be calculating theoretically using David’s equations [16].
OEE = A × P × Q (1)
Where;
A = Availability
P = Performance efficiency
Q = Quality rate
𝐀𝐯𝐚𝐢𝐥𝐚𝐛𝐢𝐥𝐢𝐭𝐲 % =
Loading time −breakdown −setup
Loading time
× 100 (2)
Where;
Loading time = planned production time - breaks - planned maintenance time
Loading time: is the time that the machinery planned to be in operation.
Planned downtime: refers to the amount of downtime officially scheduled in the production plan.
Breaks: is the lunch time or rest time.
Breakdown: equipment downtime involves equipment stoppages losses resulting from failures.
Setup: setup and adjustment procedures or the exchange of dies.
𝐏𝐞𝐫𝐟𝐨𝐫𝐦𝐚𝐧𝐜𝐞 % =
Run time −Minor stoppages −Reduced speed
Run time
× 100 (3)
Where;
Run time: it refers to the time during which the equipment is actually operating.
𝐐𝐮𝐚𝐥𝐢𝐭𝐲 % =
amount of produced units −amount of defect units −amount of reprocessed units
amount of produced units
× 100 (4)
OLE = A line × P line × Q line (5)
Where;
A line = Line Availability
P line = Line Performance Efficiency
Q line = Line Quality Rate
𝐀 𝒍𝒊𝒏𝒆 = 1 − [
T𝑏𝑖 − T𝑠𝑖𝑛
𝑖=1
𝑛
𝑖=1
SL 𝑖 + B𝑖 − PD 𝑖𝑛
𝑖=1
𝑛
𝑖=1
𝑛
𝑖=1
] × 100 (6)
Where;
n: number of equipment per line
Tbi: breakdown time of machine number i
Tsi: setup time of machine number i
PDi : Planned down time for machine i
SLi: scheduled time of operation for machine i
Bi: scheduled time of breaks for machine i
𝑷𝒍𝒊𝒏𝒆 = 1 − [
T𝑟𝑑𝑖 − T𝑟𝑠𝑖 − T𝑟𝑝𝑖𝑛
𝑖=1
𝑛
𝑖=1
𝑛
𝑖=1
T𝑜𝑛
𝑖=1 𝑖
] × 100 (7)
Where;
Toi: Operating time of machine number i
Trdi: Idle time of machine number i
Trsi: Reduced speed time of machine number i
Trpi: Time loss for repair product produced from machine number i
𝑸𝒍𝒊𝒏𝒆 = 1 − [
P𝑟𝑗𝑖𝑛
𝑖=1
P𝑝𝑖𝑛
𝑖=1
] × 100 (8)
Where;
Ppi: Total pieces of machine number i
Prji: Reject pieces of machine number i
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 68 | Page
Overall Line Effectiveness Value before improvement can get from equation (5) as follow;
OLE = A line × P line × Q line
Availability (Aline) = 64.17%
Performance (Pline) = 77.73%
Quality (Qline) = 93.9%
OLE = 0.6417 x 0.7773 x 0.939 = 0.4684 = 46.84%
IV. Oee Analysis Program
Implementation a monitoring process on a production line and measuring time loss during production
processes to be collected into OEE analysis computer program. This program used for reporting the measured
and collected data to help in detecting the value of losses during production processes, calculate OEE and
factors value. The program also shows results in a main report, shift losses report, and result report. These
results used for higher production line effectiveness and for higher productivity. OEE analysis program’s flow
chart shown in Figure4.
S t a rt
N e wS e a rc h
O E E C a lc u la t io n R e p o r t
S h if t d a ta
S a v e
T rim m in g
s ta g e
D ry in g
S t a g e
C o a tin g
S t a g e
F o r m in g
S ta g e
H e a tin g
S ta g e
P a c k in g
S t a g e
E n d
S ix B ig L o s s e s O E E & F a c to rs
S ys t e m B lo ck D ia g ra m
A % P % Q % O E E %
R ep o rtD ia g r a m
R e s u lt
R e p o rt
S h if t L o s s e s
R e p o r t
M ain
R e p o r t
id le t im e
(m in )
S e t - u p
(m in )
B re a kd o w n
( m in )
S p e e d L o s s
( m in )
S t a rt u p R e je ct s
(m in & p ie c e s )
E f f e ct iv e n e s s O p s er v a tio n
R e w o rk
(m in & p ie c e s )
Q u a n t ity %S c ra p
(m in & p ie c e s )
R e s u lt s
Figure 4: Flow Chart of the OEE Analysis Program
The software forms as shown in Figure 5 contain the access to make the new and search processes.
New process mean run new operation, which is input measured data during production processes per shift into
system block diagram forms. Search process mean run a search for the stored data.
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 69 | Page
Figure 5: Start Form Window
The new process have a several forms to explain the block diagram of the manufacturing processes and
the time losses for each process also as shown in Figures 6, 7. Also the shift time losses and OEE values
calculated in forms shown in Figures 8, 9.
Figure 6: Manufacturing Processes Block Diagram
Figure 7: Losses Time during Heating Process
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 70 | Page
Figure 8: Losses Time during Manufacturing Processes
Figure 9: OEE Calculations
The search process also has form for finding any saving data and a different time of reports, main, shift
losses, and result report as shown in Figure 10.
Figure 10: Search Form
V. Results and Desiccations
By using OEE analyses software the OLE value improved as a results of decreasing the shift losses
time and department quantity losses as Figure 11 (a-b) explained. This improvement takes around 8 months
monitoring the production line after improvement gives a new data.
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 71 | Page
OLE = A line × P line × Q line
Availability (Aline) = 84.03%
Performance (Pline) = 87. 37%
Quality (Qline) = 93.9%
OLE = 0.8403 x 0.8737 x 0.939 = 0.6894 = 68.94%
(a)
(b)
Figure 11: OLE Values (a) Before Improvement (b) After Improvement
The OLE value improves by 1.5% after using the OEE analysis software. The values of time losses also
decreased after used the program. The biggest losses time values were found in set-up& adjustment, breakdown
and idle losses time which also decreased after using the analysis software.
As shown in Figure 12, the set-up & adjustment cause time losses 410 min/shift and after using the
program it decreased to 200 min/shift, it is meaning that the time set up losses time improved by 48.8% after
using the analysis program.
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 72 | Page
(a)
(b)
Figure 12: Set-Up and Adjustment Time Losses (a) Before improvement (b) After Improvement
Also the breakdown losses time improved by 59.3% after using the software, it decreased from
270min/shift to 160min/shift.
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 73 | Page
(a)
(b)
Figure 13: Breakdown Time Losses (a) Before improvement (b) After Improvement
The idle losses time decreased from 460 min/shift to 240 min/shift with decreasing percentage 52.2% after using
OEE analysis software as shown in Figure 14.
(a)
Automated Monitoring and Measuring Improvement of Production System Performance
DOI: 10.9790/1684-12536474 www.iosrjournals.org 74 | Page
(b)
Figure 14: Idle Time Losses (a) Before improvement (b) After Improvement
VI. Conclusion
Overall line effectiveness (OLE) analyzer using easy and popular tools. It is a good index for many
organizations to help themselves to find out where is the root causes for failures and losses. Furthermore, the
value of OLE can help the organizations to recognize the gap from benchmark criteria in the same industry.
Thus the main conclusion of this paper can be summarized in the following points;
- A methodology of the overall line effectiveness calculation has been developed and validated on a case
study.
- Validation shows high efficiency and sensitivity of the applied methodology.
- The OLE calculation on the production line as existed shows very poor effectiveness with value 46.84%.
- The analysis of OLE parameters show big losses in setup and breakdown, improvement procedures has
applied to the production line.
- The running of the new data on the OLE analyzer predicts a respect the change in OLE, its results 68.94%
effectiveness. This means that the developed analysis tool is very efficient in diagnosing the problem and
very sensitive to any changes.
References
[1]. Nakajima, S., “An Introduction to TPM”, Productivity Press, Portland, OR.,1988.
[2]. Sherwin, D. , “A review of overall models for maintenance management”, Journal of Quality in Maintenance Engineering, Vol. 6
No. 3, pp. 137-64, 2000.
[3]. Nachiappan, R.M. and Anantharam, N., “Evaluation of overall line effectiveness (OLE) in a continuous product line manufacturing
system”, Journal of Manufacturing Technology Management, Vol. 17 No. 7, pp. 987-1008, 2006.
[4]. Braglia, M., Frosolini, M. and Zammori, F., “Overall equipment effectiveness of a manufacturing line (OEEML): an integrated
approach to assess systems performance”, Journal of Manufacturing Technology Management, Vol. 20 No. 1, pp. 8-29, 2009.
[5]. Oechsner, R., Pfeffer, M., Pfitzner, L., Binder, H., Muller, E. and Vonderstrass, T.,“From overall equipment efficiency (OEE) to
overall fab effectiveness (OFE)”, Material Science in Semiconductor Processing, Vol. 5 No. 4, pp. 333-9, 2003.
[6]. Garza-Reyes, J.A., “An investigation of OEE and development of the improved measures of performance OEE and ORE for
manufacturing process management”, PhD thesis, Manchester Business School, The University of Manchester, Manchester, 2008.
[7]. Garza-Reyes, J.A., Eldridge, S., Barber, K.D., Archer, E. and Peacock, T., “Overall resource effectiveness (ORE) – an improved
approach for the measure of manufacturing effectiveness and support for decision-making”, Proceedings of the 18th International
Conference on Flexible Automation and Intelligent Manufacturing (FAIM), Sko¨ vde, Sweden, 30 June-2 July, 2008.
[8]. Dal, B.,“Audit and review of manufacturing performance measures at Airbags International Limited”, MSc dissertation, Manchester
School of Management, UMIST, Manchester, 1999.
[9]. Dal, B., Tugwell, P. and Greatbanks, R., “Overall equipment effectiveness as a measure of operational improvement – a practical
analysis”, International Journal of Operations & Production Management, Vol. 20 No. 12, pp. 1488- 502, 2000.
[10]. Bamber, C., Castka, P. Sharp, J. and Motara, Y., “Cross-functional team working for overall equipment effectiveness”, Journal of
Quality in Maintenance Engineering, Vol. 9 No. 3, pp. 223-39, 2003.
[11]. Jonsson, P. and Lesshammar, M., “Evaluation and improvement of manufacturing performance measurement systems – the role of
OEE”, International Journal of Operations & Production Management, Vol. 19 No. 1, pp. 55-78, 1999.
[12]. Law, A. and Kelton, W., Simulation Modeling and Analysis, 2nd ed., McGraw-Hill, New York, NY, 1991.
[13]. “MaintSmart CMMS Software with Overall Equipment Effectiveness (OEE)”, North Bend, Oregon (PRWEB), 2010.
[14]. “GainSeeker® Statistical Process Control software”, 2009.
[15]. “ShopVue - Labor Tracking Software for Shop Floor Control”, 2011.
[16]. David, A.T., “ Japan’s New Advantage: Total Productive Maintenance”, Quality Progress, Vol. 28 No.3, pp.121-3, 1995.

More Related Content

What's hot

What's hot (20)

IRJET- Evaluating the Performance of Plant by Overall Equipment Effectiveness...
IRJET- Evaluating the Performance of Plant by Overall Equipment Effectiveness...IRJET- Evaluating the Performance of Plant by Overall Equipment Effectiveness...
IRJET- Evaluating the Performance of Plant by Overall Equipment Effectiveness...
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
 
Malabar cements
Malabar cementsMalabar cements
Malabar cements
 
Maintainance engineering and management
Maintainance engineering and managementMaintainance engineering and management
Maintainance engineering and management
 
E13 1 production planning optimization_final-web
E13 1 production planning  optimization_final-webE13 1 production planning  optimization_final-web
E13 1 production planning optimization_final-web
 
IRJET- Reduction of Breakdown Hours Through Lean Technique in a High Volume L...
IRJET- Reduction of Breakdown Hours Through Lean Technique in a High Volume L...IRJET- Reduction of Breakdown Hours Through Lean Technique in a High Volume L...
IRJET- Reduction of Breakdown Hours Through Lean Technique in a High Volume L...
 
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
IRJET-  	  Six Axis Pneumatic Materials Handling Robotic ArmIRJET-  	  Six Axis Pneumatic Materials Handling Robotic Arm
IRJET- Six Axis Pneumatic Materials Handling Robotic Arm
 
Executive Summary El
Executive Summary ElExecutive Summary El
Executive Summary El
 
E12 1 value-stream-mapping-final-web
E12 1 value-stream-mapping-final-webE12 1 value-stream-mapping-final-web
E12 1 value-stream-mapping-final-web
 
Overview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its ImplementationOverview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its Implementation
 
Implementation of just in time production through kanban system
Implementation of just in time production through kanban systemImplementation of just in time production through kanban system
Implementation of just in time production through kanban system
 
Jy2417091713
Jy2417091713Jy2417091713
Jy2417091713
 
Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
 
A Review on Implementation of TPM in Manufacturing Industry
A Review on Implementation of TPM in Manufacturing IndustryA Review on Implementation of TPM in Manufacturing Industry
A Review on Implementation of TPM in Manufacturing Industry
 
A036501014
A036501014A036501014
A036501014
 
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
 
Improving overall equipment effectiveness by Implementing Total Productive Ma...
Improving overall equipment effectiveness by Implementing Total Productive Ma...Improving overall equipment effectiveness by Implementing Total Productive Ma...
Improving overall equipment effectiveness by Implementing Total Productive Ma...
 
J0371055062
J0371055062J0371055062
J0371055062
 

Viewers also liked

Atrai o meu coração-Filhos do Homem
Atrai o meu coração-Filhos do HomemAtrai o meu coração-Filhos do Homem
Atrai o meu coração-Filhos do Homem
Dhone da Hora
 
First Presbyterian Power Point
First Presbyterian Power PointFirst Presbyterian Power Point
First Presbyterian Power Point
Michelle Hill
 
An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...
An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...
An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...
IOSR Journals
 

Viewers also liked (14)

Modeling the Effect of Variation of Recruitment Rate on the Transmission Dyna...
Modeling the Effect of Variation of Recruitment Rate on the Transmission Dyna...Modeling the Effect of Variation of Recruitment Rate on the Transmission Dyna...
Modeling the Effect of Variation of Recruitment Rate on the Transmission Dyna...
 
D013152126
D013152126D013152126
D013152126
 
Cheap flower girl dresses nz,latest flower girl gowns online cmdress.co.nz
Cheap flower girl dresses nz,latest flower girl gowns online   cmdress.co.nzCheap flower girl dresses nz,latest flower girl gowns online   cmdress.co.nz
Cheap flower girl dresses nz,latest flower girl gowns online cmdress.co.nz
 
Atrai o meu coração-Filhos do Homem
Atrai o meu coração-Filhos do HomemAtrai o meu coração-Filhos do Homem
Atrai o meu coração-Filhos do Homem
 
LordJeshuaInheritanceMay2016.7007
LordJeshuaInheritanceMay2016.7007LordJeshuaInheritanceMay2016.7007
LordJeshuaInheritanceMay2016.7007
 
IMPOR [ API ] - BARANG PERBAIKAN
IMPOR [ API ] - BARANG PERBAIKANIMPOR [ API ] - BARANG PERBAIKAN
IMPOR [ API ] - BARANG PERBAIKAN
 
First Presbyterian Power Point
First Presbyterian Power PointFirst Presbyterian Power Point
First Presbyterian Power Point
 
DOKUMEN PERUSAHAAN DI BIDANG KEPABEANAN
DOKUMEN PERUSAHAAN DI BIDANG KEPABEANANDOKUMEN PERUSAHAAN DI BIDANG KEPABEANAN
DOKUMEN PERUSAHAAN DI BIDANG KEPABEANAN
 
URUS SIUP
URUS SIUPURUS SIUP
URUS SIUP
 
Radiation Response of Bacteria Associated with Human Cancellous Bone
Radiation Response of Bacteria Associated with Human Cancellous BoneRadiation Response of Bacteria Associated with Human Cancellous Bone
Radiation Response of Bacteria Associated with Human Cancellous Bone
 
An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...
An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...
An Empirical Study of Seasonal Rainfall Effect in Calabar, Cross River State,...
 
F012644451
F012644451F012644451
F012644451
 
Pembuatan Izin Postel
Pembuatan Izin PostelPembuatan Izin Postel
Pembuatan Izin Postel
 
J012326671
J012326671J012326671
J012326671
 

Similar to I012536474

Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...
Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...
Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...
IJMER
 
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
Journal For Research
 

Similar to I012536474 (20)

IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Design and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEDesign and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEE
 
lean & agile
lean & agilelean & agile
lean & agile
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
OVERALL EQUIPMENT EFFECTIVENESS OF CRITICAL MACHINES IN MANUFACTURING INDUSTR...
 
Overall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction EquipmentsOverall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction Equipments
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)
 
total productive maintenance
total productive maintenancetotal productive maintenance
total productive maintenance
 
Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...
Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...
Evaluation of Total Productive Maintenance Implementation in a Selected Semi-...
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing Productivity
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
 
F04943847
F04943847F04943847
F04943847
 
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
 
30120140502015
3012014050201530120140502015
30120140502015
 
OPTIMIZING TIME WITH INCREASING PRODUCTIVITY USING LEAN MANUFACTURING AND OVE...
OPTIMIZING TIME WITH INCREASING PRODUCTIVITY USING LEAN MANUFACTURING AND OVE...OPTIMIZING TIME WITH INCREASING PRODUCTIVITY USING LEAN MANUFACTURING AND OVE...
OPTIMIZING TIME WITH INCREASING PRODUCTIVITY USING LEAN MANUFACTURING AND OVE...
 

More from IOSR Journals

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Recently uploaded (20)

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
 
Modernizing Legacy Systems Using Ballerina
Modernizing Legacy Systems Using BallerinaModernizing Legacy Systems Using Ballerina
Modernizing Legacy Systems Using Ballerina
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation Computing
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 

I012536474

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 5 Ver. III (Sep. - Oct. 2015), PP 64-74 www.iosrjournals.org DOI: 10.9790/1684-12536474 www.iosrjournals.org 64 | Page Automated Monitoring and Measuring Improvement of Production System Performance *Maha M. A. Lashin, **Abou Bakr M.Elhady, & ***Rehab E. El Badway * Mechanical Engineering Department, Shoubra faculty of Engineering, Banha University, ** Lead Scientist, Egyptian Space Program, *** Lead Scientist, Egyptian Space Program. Abstract: Overall equipment effectiveness OEE represents a set of key characteristics that allows monitoring the efficiency and productivity of the manufacturing processes. The main purpose of any OEE initiative is to become the most efficient, most effective manufacturer within a market, minimizing the main losses. Overall line effectiveness OLE is another OEE related to measure productivity of production line. It is a powerful metric of manufacturing performance incorporating measures of the availability, performance efficiency, and quality of a given processes along the manufacturing line. There are many methods exist by which productivity could be analyzed and improved, such simulation software that allows users to monitor and identify the problems faced for improving the productivity of the company. In the present paper a simulation program (OLE analyzer program) developed to monitor production system and identify the line based on OLE. The methodology depends on developing the OLE metrics to be more accurate and suitable for implementing on a production line that all involving number of machine arranged in series and parallel. It deals with each machine in the production line with its actual performance. The proposed methodology was applied to a case study where the OLE metric were 46.84% related to the six big losses (breakdown, setup, idle time, reduced speed, time loss, reject on startup, and production reject), and low development of losses improvement were assessed. The study suggested the area of weakness suffer from lack of learning orientation that is ought to be improved and at the same time, a variety of specific recommendations are provided. After implement the computer software methodology, the improvements plan the OLE value increased to 68.94%. Keywords: Overall equipment effectiveness – overall line effectiveness – OLE analyzer program. I. Introduction Markets competitions challenges are facing companies to implement various productivity improvement efforts to meet the needs of ever changing market demands. The total productive maintenance paradigm, launched by Nakajima [1], has provided a quantitative metric for measuring productivity of an individual production component. The purpose of Overall Equipment Effectiveness OEE was firstly defined. OEE utilized to evaluate the progress of the Total Productive Maintenance TPM philosophy through the measure of individual equipment. Nakajima recognized and categorized the main losses related to availability, performance, and quality. He established the “six big losses” as follows: 1- Start up and yield losses at the early stage of production, 2- Setup and adjustment for product mix change, 3- Production losses when temporary malfunctions occur, 4- Differences in equipment design speed and actual operating speed, 5- Defects caused by malfunctioning equipment, and 6- Poor productivity and lost yield due to poor quality. However, due to it is widely spreading in industrial use and effectiveness as a performance measurement for individual equipment. Further research has attempted to expand the application scope of OEE to entire processes, workshops, factories and production planets. In addition, its evaluating scope has also been expanded through the inclusion of more detailed elements of performance than just availability, performance and quality. Sherwin [2] proposed overall process effectiveness to measure the performance of whole production processes. Nachiappan and Anantharam [3] introduce a definition of Overall Line Effectiveness, to evaluate the effectiveness of a continuous product line manufacturing system. They used a systematic methodology based on overall equipment effectiveness OEE metrics to model the productivity of a line manufacturing system in terms of OLE. Computer simulation was carried out for the evaluation of the OLE, identifying the bottle-neck machines and the effect of specific contributing parameter for improvement. Braglia et al. [4] presented overall equipment effectiveness of a manufacturing line to assess the performance of a production line. Oechsneret al. [5] proposed overall FAB effectiveness to measure the performance of an entire factory. On the other hand, Garza-Reyes [6] developed Overall Resource Effectiveness, which also considers material efficiency and
  • 2. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 65 | Page variations in material and process cost as part of the evaluation of overall effectiveness, see also Garza-Reyes et al. [7]. Although OEE was mainly designed to monitor and control performance, Dal [8] suggests that the role of OEE goes far beyond the task of just monitoring and controlling. This is because OEE takes into account process improvement in iterative, prevents the sub-optimization of individual machines or production lines, provides a systematic method for establishing production targets, and incorporates practical management tools and techniques in order to achieve balanced view of process availability, performance and quality. Moreover, OEE can be used as an indicator of process improvement and as an approach to achieve it. Dal et al. [9] used it to measure the improvement of a process within a manufacturing environment. Bamberet al. [10] remark that OEE is often used as a driver for improving the performance of a business by concentrating on quality, productivity and machine utilization issues and hence aimed at reducing non-valued adding activities often inherent in manufacturing processes. In the case study by Dal et al. [9], it was reported that OEE not only helped to measure the improvement in the area in which it was implemented but also that it enabled new levels of performance measurement to be introduced. There are software package [13-14-15] can be used to calculate OEE automated like CMMS, ShopVue OEE, and GainSeeker. This software’s can determine the OEE value and plot the charts of its quality, availability, and performance. In the present study a computer software package is created to calculate OEE, OLE values through calculate the losses in time for process of the productivity line and give a percentage chart for this losses times. Also the charts of availability, performance, and quality values can be draw before and after improvement processes to make the comparison for this process losses time easy. The report for productivity line for each shift can be get daily, weekly, and monthly. Finally the software can draw a chart value for each losses times during the productivity process. To implement automated monitoring a real world industrial case is studied. A case study (Ideal Standard Egypt- Company of bathtubs version Florida) used to applied the software in each productivity process to decrease the time losses during this process to increase the productivity range. II. Case Study Specifications The company included 6 departments (Heating, Forming, Coating, Drying, Trimming, Finishing, and Testing & Packing) as show in Figure1 working 24 hours daily in 3 shifts at 5 separated product lines and the production rate for each line is 80 bathtub/shift. Figure 1: Schematic Layout of the Manufacturing Departments There are big time losses related to;  Startup rejects (acrylic sheet defect, heated acrylic sheets rejects, bathtub defects, bathtub reject, visual bathtub inspection, and final test for bathtub reject).  Idle time (waiting for material, forklift, heated sheet, mould, bathtub, grease the machine, and operator unavailable).  Setup and adjustment (setup preparation, cleaning sheet, adjustment sheet, changing tools, balance adjustment, cleaning, mix the chemical material for coating, visual inspection for acrylic sheet, bathtub, wooden frame, jigsaw, and product inspection).  Production rejects (scrap, and rework).  Speed loss (low temperature, slow evacuations, speed of fan, blinder, moving belt, saw machine, drilling machine, emery machine, and stretching machine).  Breakdown (failure of oven, fan, forming machine, dry cabinet, moving belt, drilling machine, saw machine, emery machine, spray gun, air pump, and stretching machine). This losses cause a lost time in the all departments within 24-146 hr/week as show in Table1.
  • 3. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 66 | Page Table 1: Time Losses during a Working Week for the Manufacturing Department Manufacturing Big Time Losses (hr/w eek) Total Time Run Time for each department Department Startup Rejects Idle Tim e Setup and Adjustmen t Productio n Rejects Speed Loss Brea kdow n Loss for each Departmen (hr/week) (hr/week) Heating - 13 18 2 4 10 47 120 Forming - 31 95 6 4 10 146 120 Coating 3 39 22 4 2 48 118 120 Drying Cabinet 4 7 8 1 2 2 24 120 Trimming 2 8 12 2 1 6 31 120 Finishing, Testing, and Packing 3 8 11 8 0.5 4 34.5 120 Sum of Big Loss Time (hr/week) 12 106 166 23 13.5 80 400.5 720 Compared with the actually run the time loss found within range 1.7% (related to startup reject) and 23.2% (related to setup and adjustment). Six big time losses for the manufacturing departments through one week working time show in Figure2. Figure 2: Big Six Time Losses for Manufacturing Departments through One Week Table 2: Quantity Losses during a Working Week for the Manufacturing Department Manufacturing Big Losses Quantity Products Losses for each Department Department Startup Rejects Production Rejects (piece/week) Heating 19 10 29 Forming 11 25 36 Coating 15 44 59 Drying Cabinet - 22 22 Trimming 10 34 44 Finishing, Testing, and Packing 13 54 67 Figure3: Quantity Losses for each Department Weekly
  • 4. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 67 | Page As show in Table 2 during working week the quantity pieces lost were within 22-67 piece/department. The biggest losses in quantity were found in finishing department and the lower value was found in drying cabinet department as Figure 3 explained. The created software package is developed by Visual basic program; it's helpful for any industry which is willing to implement the overall equipment effectiveness (OEE) concept. This software depends on implement automated monitoring and collects continuous measurements manually to improve the productivity of the industry company. III. Theoretical Equations Used In the Program The OEE, and OLE values can be calculating theoretically using David’s equations [16]. OEE = A × P × Q (1) Where; A = Availability P = Performance efficiency Q = Quality rate 𝐀𝐯𝐚𝐢𝐥𝐚𝐛𝐢𝐥𝐢𝐭𝐲 % = Loading time −breakdown −setup Loading time × 100 (2) Where; Loading time = planned production time - breaks - planned maintenance time Loading time: is the time that the machinery planned to be in operation. Planned downtime: refers to the amount of downtime officially scheduled in the production plan. Breaks: is the lunch time or rest time. Breakdown: equipment downtime involves equipment stoppages losses resulting from failures. Setup: setup and adjustment procedures or the exchange of dies. 𝐏𝐞𝐫𝐟𝐨𝐫𝐦𝐚𝐧𝐜𝐞 % = Run time −Minor stoppages −Reduced speed Run time × 100 (3) Where; Run time: it refers to the time during which the equipment is actually operating. 𝐐𝐮𝐚𝐥𝐢𝐭𝐲 % = amount of produced units −amount of defect units −amount of reprocessed units amount of produced units × 100 (4) OLE = A line × P line × Q line (5) Where; A line = Line Availability P line = Line Performance Efficiency Q line = Line Quality Rate 𝐀 𝒍𝒊𝒏𝒆 = 1 − [ T𝑏𝑖 − T𝑠𝑖𝑛 𝑖=1 𝑛 𝑖=1 SL 𝑖 + B𝑖 − PD 𝑖𝑛 𝑖=1 𝑛 𝑖=1 𝑛 𝑖=1 ] × 100 (6) Where; n: number of equipment per line Tbi: breakdown time of machine number i Tsi: setup time of machine number i PDi : Planned down time for machine i SLi: scheduled time of operation for machine i Bi: scheduled time of breaks for machine i 𝑷𝒍𝒊𝒏𝒆 = 1 − [ T𝑟𝑑𝑖 − T𝑟𝑠𝑖 − T𝑟𝑝𝑖𝑛 𝑖=1 𝑛 𝑖=1 𝑛 𝑖=1 T𝑜𝑛 𝑖=1 𝑖 ] × 100 (7) Where; Toi: Operating time of machine number i Trdi: Idle time of machine number i Trsi: Reduced speed time of machine number i Trpi: Time loss for repair product produced from machine number i 𝑸𝒍𝒊𝒏𝒆 = 1 − [ P𝑟𝑗𝑖𝑛 𝑖=1 P𝑝𝑖𝑛 𝑖=1 ] × 100 (8) Where; Ppi: Total pieces of machine number i Prji: Reject pieces of machine number i
  • 5. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 68 | Page Overall Line Effectiveness Value before improvement can get from equation (5) as follow; OLE = A line × P line × Q line Availability (Aline) = 64.17% Performance (Pline) = 77.73% Quality (Qline) = 93.9% OLE = 0.6417 x 0.7773 x 0.939 = 0.4684 = 46.84% IV. Oee Analysis Program Implementation a monitoring process on a production line and measuring time loss during production processes to be collected into OEE analysis computer program. This program used for reporting the measured and collected data to help in detecting the value of losses during production processes, calculate OEE and factors value. The program also shows results in a main report, shift losses report, and result report. These results used for higher production line effectiveness and for higher productivity. OEE analysis program’s flow chart shown in Figure4. S t a rt N e wS e a rc h O E E C a lc u la t io n R e p o r t S h if t d a ta S a v e T rim m in g s ta g e D ry in g S t a g e C o a tin g S t a g e F o r m in g S ta g e H e a tin g S ta g e P a c k in g S t a g e E n d S ix B ig L o s s e s O E E & F a c to rs S ys t e m B lo ck D ia g ra m A % P % Q % O E E % R ep o rtD ia g r a m R e s u lt R e p o rt S h if t L o s s e s R e p o r t M ain R e p o r t id le t im e (m in ) S e t - u p (m in ) B re a kd o w n ( m in ) S p e e d L o s s ( m in ) S t a rt u p R e je ct s (m in & p ie c e s ) E f f e ct iv e n e s s O p s er v a tio n R e w o rk (m in & p ie c e s ) Q u a n t ity %S c ra p (m in & p ie c e s ) R e s u lt s Figure 4: Flow Chart of the OEE Analysis Program The software forms as shown in Figure 5 contain the access to make the new and search processes. New process mean run new operation, which is input measured data during production processes per shift into system block diagram forms. Search process mean run a search for the stored data.
  • 6. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 69 | Page Figure 5: Start Form Window The new process have a several forms to explain the block diagram of the manufacturing processes and the time losses for each process also as shown in Figures 6, 7. Also the shift time losses and OEE values calculated in forms shown in Figures 8, 9. Figure 6: Manufacturing Processes Block Diagram Figure 7: Losses Time during Heating Process
  • 7. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 70 | Page Figure 8: Losses Time during Manufacturing Processes Figure 9: OEE Calculations The search process also has form for finding any saving data and a different time of reports, main, shift losses, and result report as shown in Figure 10. Figure 10: Search Form V. Results and Desiccations By using OEE analyses software the OLE value improved as a results of decreasing the shift losses time and department quantity losses as Figure 11 (a-b) explained. This improvement takes around 8 months monitoring the production line after improvement gives a new data.
  • 8. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 71 | Page OLE = A line × P line × Q line Availability (Aline) = 84.03% Performance (Pline) = 87. 37% Quality (Qline) = 93.9% OLE = 0.8403 x 0.8737 x 0.939 = 0.6894 = 68.94% (a) (b) Figure 11: OLE Values (a) Before Improvement (b) After Improvement The OLE value improves by 1.5% after using the OEE analysis software. The values of time losses also decreased after used the program. The biggest losses time values were found in set-up& adjustment, breakdown and idle losses time which also decreased after using the analysis software. As shown in Figure 12, the set-up & adjustment cause time losses 410 min/shift and after using the program it decreased to 200 min/shift, it is meaning that the time set up losses time improved by 48.8% after using the analysis program.
  • 9. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 72 | Page (a) (b) Figure 12: Set-Up and Adjustment Time Losses (a) Before improvement (b) After Improvement Also the breakdown losses time improved by 59.3% after using the software, it decreased from 270min/shift to 160min/shift.
  • 10. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 73 | Page (a) (b) Figure 13: Breakdown Time Losses (a) Before improvement (b) After Improvement The idle losses time decreased from 460 min/shift to 240 min/shift with decreasing percentage 52.2% after using OEE analysis software as shown in Figure 14. (a)
  • 11. Automated Monitoring and Measuring Improvement of Production System Performance DOI: 10.9790/1684-12536474 www.iosrjournals.org 74 | Page (b) Figure 14: Idle Time Losses (a) Before improvement (b) After Improvement VI. Conclusion Overall line effectiveness (OLE) analyzer using easy and popular tools. It is a good index for many organizations to help themselves to find out where is the root causes for failures and losses. Furthermore, the value of OLE can help the organizations to recognize the gap from benchmark criteria in the same industry. Thus the main conclusion of this paper can be summarized in the following points; - A methodology of the overall line effectiveness calculation has been developed and validated on a case study. - Validation shows high efficiency and sensitivity of the applied methodology. - The OLE calculation on the production line as existed shows very poor effectiveness with value 46.84%. - The analysis of OLE parameters show big losses in setup and breakdown, improvement procedures has applied to the production line. - The running of the new data on the OLE analyzer predicts a respect the change in OLE, its results 68.94% effectiveness. This means that the developed analysis tool is very efficient in diagnosing the problem and very sensitive to any changes. References [1]. Nakajima, S., “An Introduction to TPM”, Productivity Press, Portland, OR.,1988. [2]. Sherwin, D. , “A review of overall models for maintenance management”, Journal of Quality in Maintenance Engineering, Vol. 6 No. 3, pp. 137-64, 2000. [3]. Nachiappan, R.M. and Anantharam, N., “Evaluation of overall line effectiveness (OLE) in a continuous product line manufacturing system”, Journal of Manufacturing Technology Management, Vol. 17 No. 7, pp. 987-1008, 2006. [4]. Braglia, M., Frosolini, M. and Zammori, F., “Overall equipment effectiveness of a manufacturing line (OEEML): an integrated approach to assess systems performance”, Journal of Manufacturing Technology Management, Vol. 20 No. 1, pp. 8-29, 2009. [5]. Oechsner, R., Pfeffer, M., Pfitzner, L., Binder, H., Muller, E. and Vonderstrass, T.,“From overall equipment efficiency (OEE) to overall fab effectiveness (OFE)”, Material Science in Semiconductor Processing, Vol. 5 No. 4, pp. 333-9, 2003. [6]. Garza-Reyes, J.A., “An investigation of OEE and development of the improved measures of performance OEE and ORE for manufacturing process management”, PhD thesis, Manchester Business School, The University of Manchester, Manchester, 2008. [7]. Garza-Reyes, J.A., Eldridge, S., Barber, K.D., Archer, E. and Peacock, T., “Overall resource effectiveness (ORE) – an improved approach for the measure of manufacturing effectiveness and support for decision-making”, Proceedings of the 18th International Conference on Flexible Automation and Intelligent Manufacturing (FAIM), Sko¨ vde, Sweden, 30 June-2 July, 2008. [8]. Dal, B.,“Audit and review of manufacturing performance measures at Airbags International Limited”, MSc dissertation, Manchester School of Management, UMIST, Manchester, 1999. [9]. Dal, B., Tugwell, P. and Greatbanks, R., “Overall equipment effectiveness as a measure of operational improvement – a practical analysis”, International Journal of Operations & Production Management, Vol. 20 No. 12, pp. 1488- 502, 2000. [10]. Bamber, C., Castka, P. Sharp, J. and Motara, Y., “Cross-functional team working for overall equipment effectiveness”, Journal of Quality in Maintenance Engineering, Vol. 9 No. 3, pp. 223-39, 2003. [11]. Jonsson, P. and Lesshammar, M., “Evaluation and improvement of manufacturing performance measurement systems – the role of OEE”, International Journal of Operations & Production Management, Vol. 19 No. 1, pp. 55-78, 1999. [12]. Law, A. and Kelton, W., Simulation Modeling and Analysis, 2nd ed., McGraw-Hill, New York, NY, 1991. [13]. “MaintSmart CMMS Software with Overall Equipment Effectiveness (OEE)”, North Bend, Oregon (PRWEB), 2010. [14]. “GainSeeker® Statistical Process Control software”, 2009. [15]. “ShopVue - Labor Tracking Software for Shop Floor Control”, 2011. [16]. David, A.T., “ Japan’s New Advantage: Total Productive Maintenance”, Quality Progress, Vol. 28 No.3, pp.121-3, 1995.