SlideShare a Scribd company logo
1 of 11
1
World Food Programme Iraq
PRRO 200035
Cash for Work Programme
Progress Report
Reporting Period: From: 24 September, 2013 To : 28 November, 2013
Name of Cooperating Partner: Qandil, Swedish Humanitarianand Development Org.
Project Location: Baghdad (Mahmudiyah District)
Report prepared by: Alaq Nabeel, Program Officer
Report approved by: Muayad Hadi, Baghdad Field Coordinator
2
Highlights
After accomplishing two phases of Cash For Work (CFW) programme successfully in Baghdad
and other governorates in which the project has met the sought for objectives , Qandil has
launched the third phase of the project for the year 2013 extracting lessons learnt from
previous phases which were taken into consideration that the project was initiated, designed,
and implemented with the goal of improving the living conditions of the target by providing
unemployed labor forces with temporary job opportunities for 40 days period, providing
workers with income so they can meet their essential needs, and achieve some work which is
beneficial to the community and the local economy as well.
The project has been planned to be implemented in Al Mahmudiyah, particularly Al Rasheed
district which is one of nine administrative districts in Baghdad located in southern Baghdad
and it is mostly an agricultural area with a high incidence of irrigation canals that supply plants
with water. As a result of neglect many plants has grown in these canals impeded the water
passage and flow, these plants like (Ceratophyllum) could only be removed by hands, the
district is also characterized by the high percentage of vulnerable, IDP, and returnee families,
in addition to the high unemployment rates, which is often identified as key driver of conflict.
Youth unemployment in particular is seen as a direct motive for all conflict actions, it’s
therefore understandable to see why employment generation is commonly viewed as a key
factor for stability. For the reasons mentioned above Qandil in collaboration with WFP was
keen to create opportunities for the poor and vulnerable to earn an income and to meet their
basic and urgent needs, while rehabilitating basic services in the community. One of Qandil
basic priorities for this project was ensuring a proper communication with the communities
from the beginning of the programme by clarifying that it is a short-term project with defined
objectives implemented by liaising closely with local actors (government as well as NGOs, etc.)
in order to gain a more accurate picture of the project.
Utilizing the same mechanisms, CFW program has been commenced and preceded by
assessment stage, and selection of beneficiaries, locations, and activities which were done in
coordination with WFP and the Local authorities. The preparation activities have been started
with the beginning of June when many joint coordination meetings were conducted attended
by Qandil staff along with representatives from WFP, and local authorities including Ministry
of Water Recourses, Directorate of Irrigation and Drainage, Al Rasheed District Council, in
addition to Mukhtars and tribal leaders of Al Rasheed district. These meetings aimed at
outlining the CFW fundamentals in terms of payment modalities and beneficiaries’ selection
method, and discuss the activities to be implemented in the targeted areas.
The beneficiary selection process was carried out by Beneficiaries’ Selection Committees
which put in consideration the WFP criteria. During the assessment stage, Qandil has
concentrated on the significance of CDG (Community Development Groups) in addition to
women participation and their selection whether from Local Authorities or the host
community. It is worth mentioning as well that during this phase, Smart Cards modality was
used (particularly in Baghdad) for workers’ payments depending on the daily attendance
sheets which were tracking the workers daily presence at the site to determine the wage
entitlement each worker should receive.
3
Activities
During mid July, the laborers registration started to participate in CFW activities, and those
who fall under the WFP standards have been selected to reach (1,100) beneficiaries in two
villages; Sakhrajiyah, and Siyafiya within Al Rasheed district. After persevering efforts to gain
the official approvals and allowance to start the CFW activities in the targeted locations,
Qandil in collaboration with WFP respective staff has eventually obtained the approvals from
the Ministry of Water Recourses on 18 September, 2013. Right after the approvals issuance,
the preparations were proceeded to get started with the activities, as many coordination
meetings were conducted along with the local councils in order to highlight the basics of the
project and identify the LA role. The beneficiaries’ database has also been taken in
cooperation with LAs and WFP and was regularly updated with all detailed information about
each beneficiary based on applications developed by WFP yet modified and filled by Qandil.
The CFW preparation meetings
Registration process for men and women
4
Irrigation canals before CFW interventions
5
The working groups where distributed according to the targeted irrigation canals as (11)
projects of cleaning irrigation canals were implemented in the mentioned areas (5 in
Sakhrajiyah and 6 in Siyafiya). The working groups were distributed into (22) groups, each of
which consist of (50) laborers (49 workers headed by one supervisor) all are directly overseen
and monitored by Qandil Monitors who are basically (5) and responsible for following up all
about field activities and maintaining the attendance sheets on daily basis and other logistic
matters. These groups were intended to work on cleaning the irrigation canals for (40) days in
total, and receive (10) USD per day, while the supervisors are entitled to (13) USD. The
beneficiaries were selected considering that the majorities are displaced, as 70% of them are
IDPs, while the rest are vulnerable families.
On 24 September, 2013 NFI equipments were distributed to the laborers, and immediately the
cleaning activities have actually started, the distributed items included (labor gloves, metal
rakes, wooden brooms, water buckets, wheel barrows, plastic shoes, metal sickles, shovels,
straw hats, paper muzzles, first aid Kits, water pots, and ice bars, etc). The work starts at 6:00
am and ends at 12:00 pm 5 days a week.
Supplied equipments
6
Throughout the project implementation, Qandil field teams has regularly trained the working
groups on fulfilling their tasks as best as possible in addition to instructing them on how to use
the distributed items properly, briefed them about safety precautions and supplied them with
the required equipments to avoid exposing themselves to any possible risk, and ensure the
work quality, they were also briefed about ethical principles. Multiple site visits were paid by
US Embassy representatives in Iraq to the targeted sites in order to oversee the work
mechanism and progress; moreover, representatives of WFP were visiting the sites regularly
accompanying Qandil staff of program officers and monitors to facilitate the project
implementation and monitor the work progress.
Cleaning the irrigation canals in Al Rasheed sidtrict
7
Distribution of working groups and projects for each location:
# Project Title
Name of
communities
Number of Participants
Workers Supervisors
Total
Females
IDPs Female IDPs
Project
(1)
Rehabilitation of the Irrigation
Canals (TH00)
Al-Rasheed / Sakhrija 196 4 40 100 20
Project
(2)
Rehabilitation of the Irrigation
Canals (TH03)
Al-Rasheed / Sakhrija 49 1 5 20 3
Project
(3)
Rehabilitation of the Irrigation
Canals (TH05)
Al-Rasheed / Sakhrija 98 2 10 30 5
Project
(4)
Rehabilitation of the Irrigation
Canals (TH07)
Al-Rasheed / Sakhrija 49 1 5 0 0
Project
(5)
Rehabilitation of the Irrigation
Canals (TH0502)
Al-Rasheed / Sakhrija 98 2 15 20 5
Project
(6)
Rehabilitation of the Irrigation
Canals (TY00)
Al-Rasheed / Sayafiya 196 4 30 80 10
Project
(7)
Rehabilitation of the Irrigation
Canals (TY00/BC1)
Al-Rasheed / Sayafiya 98 2 15 23 6
Project
(8)
Rehabilitation of the Irrigation
Canals (TY00/DC1)
Al-Rasheed / Sayafiya 49 1 8 15 3
Project
(9)
Rehabilitation of the Irrigation
Canals (TY00/DC2)
Al-Rasheed / Sayafiya 98 2 20 22 12
Project
(10)
Rehabilitation of the Irrigation
Canals (TY00/DC8)
Al-Rasheed / Sayafiya 49 1 10 18 3
Project
(11)
Rehabilitation of the Irrigation
Canals (TY00/DC10)
Al-Rasheed / Sayafiya 98 2 10 35 5
Sub Total 1078 22 168 363 72
Total Number of participants 1100
Community Development Groups
It was indispensable to form community-based groups ‘Community Development Groups
(CDGs)’ for the CFW projects, who consist of local leaders and community members who are
mainly; IDPs and Returnees. CDGs were formed in each of the targeted areas and for each
project in order to enhance the skills, abilities, and commitment of community members and
they helped in accomplishing a large proportion of the work and contributed to social
cohesion in a positive and sustainable manner through collaboration, communication and
cooperation. Despite the limited presence of women in such activities, women have also
participated but couldn’t occupy leadership roles due to community traditions and
conventions, in short 11 females have participated in CDGs, inasmuch as 1 women in each
development group which consist of 3 members with the percentage of 25%.
8
Progress and current status of activities
In order to assess the effectiveness of the project in achieving the stated required objectives
and to examine the extent to which the projects' inputs have been converted into outputs and
results, in addition to extracting lessons learnt which can be taken into consideration in design
of future similar projects, we must have a clear view on the resulted achievements and impact
of the project. The project interventions will make an effective contribution to achieve project
goals and objectives by offering greater potential for increasing people’s access to essential
living items and protecting livelihoods in immediate term and it’s appeared to have a very
positive impact on direct beneficiaries and community members through enhancing the
personnel skills of workers.
With respect to the achieved work on ground, it reaches to 80% of planned (counting the
actual working days and allocated wages accordingly). The targets haven’t fully achieved due
to many work suspension factors including the security situation, and weather factor, as well
as the many religious ceremonies which prohibited the laborers from attendance assiduously.
The file below illustrates the actual project timeline:
Actual Project
Days.xlsx
Payment Modality
According the agreement with the WFP and in cooperation with the International Smart Card
(Qi), Smart Cards method have been adopted in order to deliver immediate cash assistance to
CFW laborers in Baghdad. This new, exemplary method could make the CFW programme
extremely successful, safe and transparent. Each beneficiary got a smart card, thus the total
number of issued cards are 1100, knowing that the smart card staff are distributed on two
stations, with a rate of issuing 60-70 card per day. Supervisors are entitled to receive 13.00 $
per day, while workers are paid 10.00$ per day. The smart cards will still in the beneficiaries
possession even after the completion of the project. Nevertheless, 700 cards have been issues
so far, while the rest are still in progress and more likely to be accomplished within the
upcoming couple of days. It’s also worth mentioning that Qandil has provided the Smart Card
staff with an office to facilitate their work, the office is in the Directorate of Irrigation and
Drainage projects. In order to help beneficiaries get their smart cards, and as already agreed,
Qandil has provided each beneficiary with an identification “Beneficiary Card” contains their
names, type of project, and number of household members. Etc.
9
Sample of
Beneficiary Cards
The International Smart Card staff working on issuing the cards to the beneficiaries
10
Success Story
Bahar Muhammed is one of the
inspiring cases Qandil team has met
in Al Rasheed district, he is 70 years
old, supporting a family of four
daughters and a wife. Bahar or Abu
Hanna (as he’s commonly known),
doesn’t have any steady source of
income like a pension, and no one of
his family has the ability to assist
him, he used to look for random
works just to help him get his daily
bread. During the beneficiaries’ selection stage, the selection committee
was wandering the area and interviewing the participants, while he
volunteered and was very excited to get such opportunity. We’ve
nominated him due to his good physical ability and dire need for work.
Bahar has worked with the groups, and was keen to get to be present at
the site every day with a great
enthusiasm. The project has already
completed, Bahar has done his tasks,
and finally got his smart card from
the company through which he will
get his payment. Bahar has
expressed his joy and gratitude to
work for the CAW programme and
wished that such interventions
continue for longer terms and
include more areas and
communities.
11
Constraints and actual or proposed solutions:
There were numerous difficulties and challenges came across the program execution, but they
all were managed with ample awareness of the challenges and planning for solutions on time,
that now we have the full capacity to cope and reverse the difficulties into advantages and the
biggest challenge is to tackle such obstacles with determination...
The project was supposed to begin earlier than it has actually, but the implementation was
delayed due to the elections of local Government Council which caused deterioration in the
security situation and led to imposing curfew by the LA, in another hand recruiting the CFW
staff has also affected the project timeline somehow.
In order to fulfill the targeted objectives Qandil is committed to make every effort to
accomplish the intended work despite any binding constrains might be faced. The challenges
faced during the reported period could generally be summarized in the security, weather, and
large number of holidays, religious anniversaries.
As for the security situation, the overall conditions in Baghdad got gradually worsened. The
rates of security violation were increased, many explosions, assassinations, and civilian
targeting has occurred, which affected the project progress through street blocks, long lines of
cars next to each check point, and the traffic jams everywhere in Baghdad which is in its turn
affected Qandil visibility in a certain way. The district was exposed to the terror groups who
hindered the project activities, and threatened the inhabitants, especially in Siyafiya where 5
individuals were killed which brought fear into the area and affected the laborers attendance
somehow, in addition to the presence of security forces that restricted the movement of
workers and staff, and break up any gatherings in the area.
The other challenge that faced the project was the climate variability, as during November,
Baghdad witnessed heavy rainfalls which flooded most of Baghdad areas. This rain storm
crippled Baghdad’s activities especially in certain regions as the inhabitants of many quarters
were forced to remain at home when the rain surprised them and hindered their ability to
commute.
The religious ceremonies (Ashura) also affected the work progress and most of the workers
skipped the work days to attend these ceremonies for more than three days.

More Related Content

What's hot

Trò chơi dân gian
Trò chơi dân gianTrò chơi dân gian
Trò chơi dân gianviconyeu
 
Command Area Development with Micro Irrigation
Command Area Development with Micro IrrigationCommand Area Development with Micro Irrigation
Command Area Development with Micro IrrigationOswar Mungkasa
 
Soil quality attributes for a Sustainable Agriculture: A Review
Soil quality attributes for a Sustainable Agriculture: A Review  Soil quality attributes for a Sustainable Agriculture: A Review
Soil quality attributes for a Sustainable Agriculture: A Review 12WEL
 
How to do integrated watershed management in the world
How to do integrated watershed management in the worldHow to do integrated watershed management in the world
How to do integrated watershed management in the worldSai Bhaskar Reddy Nakka
 
Project Implementation
Project ImplementationProject Implementation
Project ImplementationPradeep Panda
 
Soil health card format MS Word
Soil health card format MS WordSoil health card format MS Word
Soil health card format MS WordDr R P Sharma
 
Soil Organic Matter.pptx
Soil Organic Matter.pptxSoil Organic Matter.pptx
Soil Organic Matter.pptxRavitaSaini3
 
Ground water recharge & water logging
Ground water recharge & water loggingGround water recharge & water logging
Ground water recharge & water loggingNIKHIL PAKWANNE
 
Cẩm nang luyện thi TOPIK I
Cẩm nang luyện thi TOPIK ICẩm nang luyện thi TOPIK I
Cẩm nang luyện thi TOPIK IHuyen Phan
 
Ebook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.Vn
Ebook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.VnEbook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.Vn
Ebook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.VnHọc Tiếng Hàn Quốc Sumun.Edu.Vn
 
Methane emission from paddy field.pptx
Methane emission from paddy field.pptxMethane emission from paddy field.pptx
Methane emission from paddy field.pptxSupun Madushanka
 
Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2
Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2
Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2Học Tiếng Hàn Quốc Sumun.Edu.Vn
 
Training for rural development final
Training for rural development  finalTraining for rural development  final
Training for rural development finalAmandeep Kaur
 
Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...
Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...
Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...European Sustainable Phosphorus Platform
 
3. salt affcted soil.pptx
3. salt affcted soil.pptx3. salt affcted soil.pptx
3. salt affcted soil.pptxfabmovieKhatri
 

What's hot (20)

Trò chơi dân gian
Trò chơi dân gianTrò chơi dân gian
Trò chơi dân gian
 
Internship Report Faculty Of Foreign Languages Đại Học Đại Nam.docx
Internship Report Faculty Of Foreign Languages Đại Học Đại Nam.docxInternship Report Faculty Of Foreign Languages Đại Học Đại Nam.docx
Internship Report Faculty Of Foreign Languages Đại Học Đại Nam.docx
 
Command Area Development with Micro Irrigation
Command Area Development with Micro IrrigationCommand Area Development with Micro Irrigation
Command Area Development with Micro Irrigation
 
Bai 23
Bai 23Bai 23
Bai 23
 
Ec bot. ppt
Ec bot. pptEc bot. ppt
Ec bot. ppt
 
BÀI MẪU luận văn thạc sĩ trường đại học lâm nghiệp, 9 ĐIỂM
BÀI MẪU luận văn thạc sĩ trường đại học lâm nghiệp, 9 ĐIỂMBÀI MẪU luận văn thạc sĩ trường đại học lâm nghiệp, 9 ĐIỂM
BÀI MẪU luận văn thạc sĩ trường đại học lâm nghiệp, 9 ĐIỂM
 
Soil quality attributes for a Sustainable Agriculture: A Review
Soil quality attributes for a Sustainable Agriculture: A Review  Soil quality attributes for a Sustainable Agriculture: A Review
Soil quality attributes for a Sustainable Agriculture: A Review
 
How to do integrated watershed management in the world
How to do integrated watershed management in the worldHow to do integrated watershed management in the world
How to do integrated watershed management in the world
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Soil health card format MS Word
Soil health card format MS WordSoil health card format MS Word
Soil health card format MS Word
 
Soil Organic Matter.pptx
Soil Organic Matter.pptxSoil Organic Matter.pptx
Soil Organic Matter.pptx
 
Ground water recharge & water logging
Ground water recharge & water loggingGround water recharge & water logging
Ground water recharge & water logging
 
Cẩm nang luyện thi TOPIK I
Cẩm nang luyện thi TOPIK ICẩm nang luyện thi TOPIK I
Cẩm nang luyện thi TOPIK I
 
Ebook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.Vn
Ebook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.VnEbook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.Vn
Ebook Tiếng Hàn Tổng Hợp Dành Cho Người Việt Sơ Cấp 1 - Sumun.Edu.Vn
 
Methane emission from paddy field.pptx
Methane emission from paddy field.pptxMethane emission from paddy field.pptx
Methane emission from paddy field.pptx
 
Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2
Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2
Ebook Giáo Trình Tiếng Hàn Tổng Hợp Dành Cho Người Việt sơ cấp 2
 
Training for rural development final
Training for rural development  finalTraining for rural development  final
Training for rural development final
 
Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...
Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...
Willem Schipper – Willem Schipper Consulting - Phosphorus in industry and soc...
 
3. salt affcted soil.pptx
3. salt affcted soil.pptx3. salt affcted soil.pptx
3. salt affcted soil.pptx
 
Sustainable Livelihood SR
Sustainable Livelihood SRSustainable Livelihood SR
Sustainable Livelihood SR
 

Viewers also liked

Influenza general intro. (symptoms and prevention )
Influenza general intro.  (symptoms and prevention )  Influenza general intro.  (symptoms and prevention )
Influenza general intro. (symptoms and prevention ) Reema Choudhary
 
Στο τσιμεντένιο δάσος (2014) Β΄1
Στο τσιμεντένιο δάσος (2014) Β΄1Στο τσιμεντένιο δάσος (2014) Β΄1
Στο τσιμεντένιο δάσος (2014) Β΄1mara_petridou
 
The beast the dragon and the woman
The beast the dragon and the womanThe beast the dragon and the woman
The beast the dragon and the womanjb1955
 
Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled Presentationtristen14
 
Informational interview
Informational interviewInformational interview
Informational interviewJake Sarosi
 
Christian.lopez. muestras de trabajo del candidato a maestro.2015
Christian.lopez. muestras de trabajo del candidato a maestro.2015Christian.lopez. muestras de trabajo del candidato a maestro.2015
Christian.lopez. muestras de trabajo del candidato a maestro.2015Chris Lopez
 
Drummer boy of shiloh
Drummer boy of shilohDrummer boy of shiloh
Drummer boy of shilohtravelntchr
 
Gsk influenza virus vaccine
Gsk influenza virus vaccineGsk influenza virus vaccine
Gsk influenza virus vaccineMahek Dhoot
 
Vendor Consolidation Checklist
Vendor Consolidation ChecklistVendor Consolidation Checklist
Vendor Consolidation ChecklistDemand Metric
 
Principios contratación pública
Principios contratación públicaPrincipios contratación pública
Principios contratación públicaMarjorie Crespo
 
Spain in the middle ages
Spain in the middle agesSpain in the middle ages
Spain in the middle agesRous Han
 
Influenza epidemiology
Influenza epidemiologyInfluenza epidemiology
Influenza epidemiologyAshraf ElAdawy
 
DevOps: Process, Tool or Mindset?
DevOps: Process, Tool or Mindset?DevOps: Process, Tool or Mindset?
DevOps: Process, Tool or Mindset?Tathagat Varma
 
Chapter 1 introduction to virus
Chapter 1 introduction to virusChapter 1 introduction to virus
Chapter 1 introduction to virusAlia Najiha
 
PRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICA
PRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICAPRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICA
PRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICAWILSON VELASTEGUI
 
Avian influenza virus and transmission
Avian influenza virus and transmissionAvian influenza virus and transmission
Avian influenza virus and transmissionRokshana Parvin
 

Viewers also liked (20)

Influenza general intro. (symptoms and prevention )
Influenza general intro.  (symptoms and prevention )  Influenza general intro.  (symptoms and prevention )
Influenza general intro. (symptoms and prevention )
 
Στο τσιμεντένιο δάσος (2014) Β΄1
Στο τσιμεντένιο δάσος (2014) Β΄1Στο τσιμεντένιο δάσος (2014) Β΄1
Στο τσιμεντένιο δάσος (2014) Β΄1
 
The beast the dragon and the woman
The beast the dragon and the womanThe beast the dragon and the woman
The beast the dragon and the woman
 
Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled Presentation
 
Informational interview
Informational interviewInformational interview
Informational interview
 
influenza
influenzainfluenza
influenza
 
Christian.lopez. muestras de trabajo del candidato a maestro.2015
Christian.lopez. muestras de trabajo del candidato a maestro.2015Christian.lopez. muestras de trabajo del candidato a maestro.2015
Christian.lopez. muestras de trabajo del candidato a maestro.2015
 
MIS chap # 9.....
MIS chap # 9.....MIS chap # 9.....
MIS chap # 9.....
 
Co-factor matrix..
Co-factor matrix..Co-factor matrix..
Co-factor matrix..
 
Drummer boy of shiloh
Drummer boy of shilohDrummer boy of shiloh
Drummer boy of shiloh
 
Gsk influenza virus vaccine
Gsk influenza virus vaccineGsk influenza virus vaccine
Gsk influenza virus vaccine
 
Vendor Consolidation Checklist
Vendor Consolidation ChecklistVendor Consolidation Checklist
Vendor Consolidation Checklist
 
Principios contratación pública
Principios contratación públicaPrincipios contratación pública
Principios contratación pública
 
Spain in the middle ages
Spain in the middle agesSpain in the middle ages
Spain in the middle ages
 
Influenza epidemiology
Influenza epidemiologyInfluenza epidemiology
Influenza epidemiology
 
AbbasMorovvati
AbbasMorovvatiAbbasMorovvati
AbbasMorovvati
 
DevOps: Process, Tool or Mindset?
DevOps: Process, Tool or Mindset?DevOps: Process, Tool or Mindset?
DevOps: Process, Tool or Mindset?
 
Chapter 1 introduction to virus
Chapter 1 introduction to virusChapter 1 introduction to virus
Chapter 1 introduction to virus
 
PRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICA
PRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICAPRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICA
PRESENTACION EXAMEN ESPECIAL A LOS PROCESOS DE CONTRATACIÓN PÚBLICA
 
Avian influenza virus and transmission
Avian influenza virus and transmissionAvian influenza virus and transmission
Avian influenza virus and transmission
 

Similar to CFW Final Report-1

Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP) Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP) miantosef
 
IRSP Annual Review 2013
IRSP Annual Review 2013IRSP Annual Review 2013
IRSP Annual Review 2013IRSP Pakistan
 
IRSP Annual Review 2013
IRSP Annual Review 2013IRSP Annual Review 2013
IRSP Annual Review 2013Shazia Sardar
 
SGP Guyana Report 2013
SGP Guyana Report 2013SGP Guyana Report 2013
SGP Guyana Report 2013Ian Kissoon
 
Waste water treatment plant business plan in Kigali
Waste water treatment plant business plan in KigaliWaste water treatment plant business plan in Kigali
Waste water treatment plant business plan in KigaliAnvit Goyal
 
Rural development planning
Rural development planningRural development planning
Rural development planningM Usama Sehgal
 
How to use GIS for Projects
How to use GIS for ProjectsHow to use GIS for Projects
How to use GIS for ProjectsPaula Richardson
 
1st phase report to TIKA sept to dec 2015
1st phase report to TIKA sept to dec 20151st phase report to TIKA sept to dec 2015
1st phase report to TIKA sept to dec 2015PAKISTAN WATER FORUM
 
IRSP Annual Review 2012
IRSP Annual Review 2012IRSP Annual Review 2012
IRSP Annual Review 2012IRSP Pakistan
 
IRSP Annual Review 2012
IRSP Annual Review 2012IRSP Annual Review 2012
IRSP Annual Review 2012Shazia Sardar
 
Monitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-II
Monitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-IIMonitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-II
Monitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-IIRahman Ali
 

Similar to CFW Final Report-1 (20)

Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP) Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
 
IRSP Annual Review 2013
IRSP Annual Review 2013IRSP Annual Review 2013
IRSP Annual Review 2013
 
IRSP Annual Review 2013
IRSP Annual Review 2013IRSP Annual Review 2013
IRSP Annual Review 2013
 
SGP Guyana Report 2013
SGP Guyana Report 2013SGP Guyana Report 2013
SGP Guyana Report 2013
 
Waste water treatment plant business plan in Kigali
Waste water treatment plant business plan in KigaliWaste water treatment plant business plan in Kigali
Waste water treatment plant business plan in Kigali
 
Rural development planning
Rural development planningRural development planning
Rural development planning
 
Water aid in mali plan 2010 2015
Water aid in mali plan 2010 2015Water aid in mali plan 2010 2015
Water aid in mali plan 2010 2015
 
PROPOSAL
PROPOSALPROPOSAL
PROPOSAL
 
Improving Sewerage Services for Baghdad
Improving Sewerage Services for BaghdadImproving Sewerage Services for Baghdad
Improving Sewerage Services for Baghdad
 
Updated CV_Munge 2(1)
Updated CV_Munge 2(1)Updated CV_Munge 2(1)
Updated CV_Munge 2(1)
 
Community development and participatory approach concept (phase 2)
Community development and participatory approach concept (phase 2)Community development and participatory approach concept (phase 2)
Community development and participatory approach concept (phase 2)
 
Community development and participatory approach concept (phase 2)
Community development and participatory approach concept (phase 2)Community development and participatory approach concept (phase 2)
Community development and participatory approach concept (phase 2)
 
How to use GIS for Projects
How to use GIS for ProjectsHow to use GIS for Projects
How to use GIS for Projects
 
University Project Proposal docx
University Project Proposal docxUniversity Project Proposal docx
University Project Proposal docx
 
WOCAT_QA_Summary
WOCAT_QA_SummaryWOCAT_QA_Summary
WOCAT_QA_Summary
 
Water shed.ppt
Water shed.pptWater shed.ppt
Water shed.ppt
 
1st phase report to TIKA sept to dec 2015
1st phase report to TIKA sept to dec 20151st phase report to TIKA sept to dec 2015
1st phase report to TIKA sept to dec 2015
 
IRSP Annual Review 2012
IRSP Annual Review 2012IRSP Annual Review 2012
IRSP Annual Review 2012
 
IRSP Annual Review 2012
IRSP Annual Review 2012IRSP Annual Review 2012
IRSP Annual Review 2012
 
Monitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-II
Monitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-IIMonitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-II
Monitoring Visits Weekly Report June-1-8-2012-SAWERA-ADH-II
 

CFW Final Report-1

  • 1. 1 World Food Programme Iraq PRRO 200035 Cash for Work Programme Progress Report Reporting Period: From: 24 September, 2013 To : 28 November, 2013 Name of Cooperating Partner: Qandil, Swedish Humanitarianand Development Org. Project Location: Baghdad (Mahmudiyah District) Report prepared by: Alaq Nabeel, Program Officer Report approved by: Muayad Hadi, Baghdad Field Coordinator
  • 2. 2 Highlights After accomplishing two phases of Cash For Work (CFW) programme successfully in Baghdad and other governorates in which the project has met the sought for objectives , Qandil has launched the third phase of the project for the year 2013 extracting lessons learnt from previous phases which were taken into consideration that the project was initiated, designed, and implemented with the goal of improving the living conditions of the target by providing unemployed labor forces with temporary job opportunities for 40 days period, providing workers with income so they can meet their essential needs, and achieve some work which is beneficial to the community and the local economy as well. The project has been planned to be implemented in Al Mahmudiyah, particularly Al Rasheed district which is one of nine administrative districts in Baghdad located in southern Baghdad and it is mostly an agricultural area with a high incidence of irrigation canals that supply plants with water. As a result of neglect many plants has grown in these canals impeded the water passage and flow, these plants like (Ceratophyllum) could only be removed by hands, the district is also characterized by the high percentage of vulnerable, IDP, and returnee families, in addition to the high unemployment rates, which is often identified as key driver of conflict. Youth unemployment in particular is seen as a direct motive for all conflict actions, it’s therefore understandable to see why employment generation is commonly viewed as a key factor for stability. For the reasons mentioned above Qandil in collaboration with WFP was keen to create opportunities for the poor and vulnerable to earn an income and to meet their basic and urgent needs, while rehabilitating basic services in the community. One of Qandil basic priorities for this project was ensuring a proper communication with the communities from the beginning of the programme by clarifying that it is a short-term project with defined objectives implemented by liaising closely with local actors (government as well as NGOs, etc.) in order to gain a more accurate picture of the project. Utilizing the same mechanisms, CFW program has been commenced and preceded by assessment stage, and selection of beneficiaries, locations, and activities which were done in coordination with WFP and the Local authorities. The preparation activities have been started with the beginning of June when many joint coordination meetings were conducted attended by Qandil staff along with representatives from WFP, and local authorities including Ministry of Water Recourses, Directorate of Irrigation and Drainage, Al Rasheed District Council, in addition to Mukhtars and tribal leaders of Al Rasheed district. These meetings aimed at outlining the CFW fundamentals in terms of payment modalities and beneficiaries’ selection method, and discuss the activities to be implemented in the targeted areas. The beneficiary selection process was carried out by Beneficiaries’ Selection Committees which put in consideration the WFP criteria. During the assessment stage, Qandil has concentrated on the significance of CDG (Community Development Groups) in addition to women participation and their selection whether from Local Authorities or the host community. It is worth mentioning as well that during this phase, Smart Cards modality was used (particularly in Baghdad) for workers’ payments depending on the daily attendance sheets which were tracking the workers daily presence at the site to determine the wage entitlement each worker should receive.
  • 3. 3 Activities During mid July, the laborers registration started to participate in CFW activities, and those who fall under the WFP standards have been selected to reach (1,100) beneficiaries in two villages; Sakhrajiyah, and Siyafiya within Al Rasheed district. After persevering efforts to gain the official approvals and allowance to start the CFW activities in the targeted locations, Qandil in collaboration with WFP respective staff has eventually obtained the approvals from the Ministry of Water Recourses on 18 September, 2013. Right after the approvals issuance, the preparations were proceeded to get started with the activities, as many coordination meetings were conducted along with the local councils in order to highlight the basics of the project and identify the LA role. The beneficiaries’ database has also been taken in cooperation with LAs and WFP and was regularly updated with all detailed information about each beneficiary based on applications developed by WFP yet modified and filled by Qandil. The CFW preparation meetings Registration process for men and women
  • 4. 4 Irrigation canals before CFW interventions
  • 5. 5 The working groups where distributed according to the targeted irrigation canals as (11) projects of cleaning irrigation canals were implemented in the mentioned areas (5 in Sakhrajiyah and 6 in Siyafiya). The working groups were distributed into (22) groups, each of which consist of (50) laborers (49 workers headed by one supervisor) all are directly overseen and monitored by Qandil Monitors who are basically (5) and responsible for following up all about field activities and maintaining the attendance sheets on daily basis and other logistic matters. These groups were intended to work on cleaning the irrigation canals for (40) days in total, and receive (10) USD per day, while the supervisors are entitled to (13) USD. The beneficiaries were selected considering that the majorities are displaced, as 70% of them are IDPs, while the rest are vulnerable families. On 24 September, 2013 NFI equipments were distributed to the laborers, and immediately the cleaning activities have actually started, the distributed items included (labor gloves, metal rakes, wooden brooms, water buckets, wheel barrows, plastic shoes, metal sickles, shovels, straw hats, paper muzzles, first aid Kits, water pots, and ice bars, etc). The work starts at 6:00 am and ends at 12:00 pm 5 days a week. Supplied equipments
  • 6. 6 Throughout the project implementation, Qandil field teams has regularly trained the working groups on fulfilling their tasks as best as possible in addition to instructing them on how to use the distributed items properly, briefed them about safety precautions and supplied them with the required equipments to avoid exposing themselves to any possible risk, and ensure the work quality, they were also briefed about ethical principles. Multiple site visits were paid by US Embassy representatives in Iraq to the targeted sites in order to oversee the work mechanism and progress; moreover, representatives of WFP were visiting the sites regularly accompanying Qandil staff of program officers and monitors to facilitate the project implementation and monitor the work progress. Cleaning the irrigation canals in Al Rasheed sidtrict
  • 7. 7 Distribution of working groups and projects for each location: # Project Title Name of communities Number of Participants Workers Supervisors Total Females IDPs Female IDPs Project (1) Rehabilitation of the Irrigation Canals (TH00) Al-Rasheed / Sakhrija 196 4 40 100 20 Project (2) Rehabilitation of the Irrigation Canals (TH03) Al-Rasheed / Sakhrija 49 1 5 20 3 Project (3) Rehabilitation of the Irrigation Canals (TH05) Al-Rasheed / Sakhrija 98 2 10 30 5 Project (4) Rehabilitation of the Irrigation Canals (TH07) Al-Rasheed / Sakhrija 49 1 5 0 0 Project (5) Rehabilitation of the Irrigation Canals (TH0502) Al-Rasheed / Sakhrija 98 2 15 20 5 Project (6) Rehabilitation of the Irrigation Canals (TY00) Al-Rasheed / Sayafiya 196 4 30 80 10 Project (7) Rehabilitation of the Irrigation Canals (TY00/BC1) Al-Rasheed / Sayafiya 98 2 15 23 6 Project (8) Rehabilitation of the Irrigation Canals (TY00/DC1) Al-Rasheed / Sayafiya 49 1 8 15 3 Project (9) Rehabilitation of the Irrigation Canals (TY00/DC2) Al-Rasheed / Sayafiya 98 2 20 22 12 Project (10) Rehabilitation of the Irrigation Canals (TY00/DC8) Al-Rasheed / Sayafiya 49 1 10 18 3 Project (11) Rehabilitation of the Irrigation Canals (TY00/DC10) Al-Rasheed / Sayafiya 98 2 10 35 5 Sub Total 1078 22 168 363 72 Total Number of participants 1100 Community Development Groups It was indispensable to form community-based groups ‘Community Development Groups (CDGs)’ for the CFW projects, who consist of local leaders and community members who are mainly; IDPs and Returnees. CDGs were formed in each of the targeted areas and for each project in order to enhance the skills, abilities, and commitment of community members and they helped in accomplishing a large proportion of the work and contributed to social cohesion in a positive and sustainable manner through collaboration, communication and cooperation. Despite the limited presence of women in such activities, women have also participated but couldn’t occupy leadership roles due to community traditions and conventions, in short 11 females have participated in CDGs, inasmuch as 1 women in each development group which consist of 3 members with the percentage of 25%.
  • 8. 8 Progress and current status of activities In order to assess the effectiveness of the project in achieving the stated required objectives and to examine the extent to which the projects' inputs have been converted into outputs and results, in addition to extracting lessons learnt which can be taken into consideration in design of future similar projects, we must have a clear view on the resulted achievements and impact of the project. The project interventions will make an effective contribution to achieve project goals and objectives by offering greater potential for increasing people’s access to essential living items and protecting livelihoods in immediate term and it’s appeared to have a very positive impact on direct beneficiaries and community members through enhancing the personnel skills of workers. With respect to the achieved work on ground, it reaches to 80% of planned (counting the actual working days and allocated wages accordingly). The targets haven’t fully achieved due to many work suspension factors including the security situation, and weather factor, as well as the many religious ceremonies which prohibited the laborers from attendance assiduously. The file below illustrates the actual project timeline: Actual Project Days.xlsx Payment Modality According the agreement with the WFP and in cooperation with the International Smart Card (Qi), Smart Cards method have been adopted in order to deliver immediate cash assistance to CFW laborers in Baghdad. This new, exemplary method could make the CFW programme extremely successful, safe and transparent. Each beneficiary got a smart card, thus the total number of issued cards are 1100, knowing that the smart card staff are distributed on two stations, with a rate of issuing 60-70 card per day. Supervisors are entitled to receive 13.00 $ per day, while workers are paid 10.00$ per day. The smart cards will still in the beneficiaries possession even after the completion of the project. Nevertheless, 700 cards have been issues so far, while the rest are still in progress and more likely to be accomplished within the upcoming couple of days. It’s also worth mentioning that Qandil has provided the Smart Card staff with an office to facilitate their work, the office is in the Directorate of Irrigation and Drainage projects. In order to help beneficiaries get their smart cards, and as already agreed, Qandil has provided each beneficiary with an identification “Beneficiary Card” contains their names, type of project, and number of household members. Etc.
  • 9. 9 Sample of Beneficiary Cards The International Smart Card staff working on issuing the cards to the beneficiaries
  • 10. 10 Success Story Bahar Muhammed is one of the inspiring cases Qandil team has met in Al Rasheed district, he is 70 years old, supporting a family of four daughters and a wife. Bahar or Abu Hanna (as he’s commonly known), doesn’t have any steady source of income like a pension, and no one of his family has the ability to assist him, he used to look for random works just to help him get his daily bread. During the beneficiaries’ selection stage, the selection committee was wandering the area and interviewing the participants, while he volunteered and was very excited to get such opportunity. We’ve nominated him due to his good physical ability and dire need for work. Bahar has worked with the groups, and was keen to get to be present at the site every day with a great enthusiasm. The project has already completed, Bahar has done his tasks, and finally got his smart card from the company through which he will get his payment. Bahar has expressed his joy and gratitude to work for the CAW programme and wished that such interventions continue for longer terms and include more areas and communities.
  • 11. 11 Constraints and actual or proposed solutions: There were numerous difficulties and challenges came across the program execution, but they all were managed with ample awareness of the challenges and planning for solutions on time, that now we have the full capacity to cope and reverse the difficulties into advantages and the biggest challenge is to tackle such obstacles with determination... The project was supposed to begin earlier than it has actually, but the implementation was delayed due to the elections of local Government Council which caused deterioration in the security situation and led to imposing curfew by the LA, in another hand recruiting the CFW staff has also affected the project timeline somehow. In order to fulfill the targeted objectives Qandil is committed to make every effort to accomplish the intended work despite any binding constrains might be faced. The challenges faced during the reported period could generally be summarized in the security, weather, and large number of holidays, religious anniversaries. As for the security situation, the overall conditions in Baghdad got gradually worsened. The rates of security violation were increased, many explosions, assassinations, and civilian targeting has occurred, which affected the project progress through street blocks, long lines of cars next to each check point, and the traffic jams everywhere in Baghdad which is in its turn affected Qandil visibility in a certain way. The district was exposed to the terror groups who hindered the project activities, and threatened the inhabitants, especially in Siyafiya where 5 individuals were killed which brought fear into the area and affected the laborers attendance somehow, in addition to the presence of security forces that restricted the movement of workers and staff, and break up any gatherings in the area. The other challenge that faced the project was the climate variability, as during November, Baghdad witnessed heavy rainfalls which flooded most of Baghdad areas. This rain storm crippled Baghdad’s activities especially in certain regions as the inhabitants of many quarters were forced to remain at home when the rain surprised them and hindered their ability to commute. The religious ceremonies (Ashura) also affected the work progress and most of the workers skipped the work days to attend these ceremonies for more than three days.