PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 1 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
Dibuat Oleh :
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
PT ANSI MEGA INSTRUMENINDO
Graha Makmur , Jln. Jengki Utama No. 1 Cipinang Asem
Kebon Pala , Makasar- Jakarta 13650
Phone : +62 21 8087 2920 Fax : +62 21 80872921
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 2 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
DAFTAR ISI
1. GAMBARAN UMUM PENGGANTIAN METER TUBE PKT 3 FUEL.............................................................4
1.1 LATAR BELAKANG.....................................................................................................................................4
2. LINGKUP PEKERJAAN PENGGANTIAN METER TUBE PKT 3 FUEL .............................................................4
3. PERSIAPAN DAN PELAKSANAAN PEMBUATAN DOKUMEN ADMINISTRASI PROYEK . ............................6
3.1 PEMBUATAN DOKUMEN PROYEK PENGGANTIAN METER TUBE PKT 3 FUEL:.......................................6
4. PEKERJAAN METER TUBE PKT 3 FUEL DALAM MANAJEMEN PROYEK................................................15
5. PROJECT MANAGEMENT.................................................................................................................18
6. QA / QC TEAM................................................................................................................................26
7. PROJECT PLANNING AND CONTROL ................................................................................................28
8. PROJECT ADMINISTRATION AND INFORMATION MANAGEMENT.....................................................29
9. PROJECT CONTROL ESTIMATING .....................................................................................................31
10. ENGINEERING DESIGN....................................................................................................................33
11. CONTRACT MANAGEMENT PROJECT...............................................................................................36
12. PROCUREMENT..............................................................................................................................36
12.1 MATERIAL MANAGEMENT PLAN............................................................................................................36
12.2 PURCHASING ENGINEERING...................................................................................................................36
12.3 EXPEDITING PLAN ...................................................................................................................................37
12.4 MATERIAL INSPECTION...........................................................................................................................37
13. LOGISTICS MANAGEMENT......................................................................................................................37
14. CONSTRUCTION & INSTALLATION .........................................................................................................37
14.1 PROGRAM DOKUMEN LELANG...............................................................................................................37
14.2 TEMPORARY FACILITY PLAN ...................................................................................................................37
14.3 CONSTRUCTION /INSTALLATION EXECUTION PLAN...............................................................................37
14.4 CONSTRUCTION ADMINISTRATION........................................................................................................38
14.5 FIELD ENGINEERING................................................................................................................................38
14.6 FIELD MATERIAL CONTROL .....................................................................................................................39
15. MECHANICAL COMPLETION / PRE-COMMISSIONING............................................................................39
15.1 LANGKAH KEGIATAN MECHANICAL COMPLETION.................................................................................39
15.2 PIPING COMPLETION & INSPECTION......................................................................................................39
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 3 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
15.3 INSTRUMENTATION COMPLETION & TEST.............................................................................................40
15.4 PRE-COMMISSIONING ............................................................................................................................40
16. OPERATION.............................................................................................................................................40
17. CHANGE MANAGEMENT BASIS ..............................................................................................................41
18. RISK MANAGEMENT ...............................................................................................................................41
18.1 PROJECT RISK INDENTIFICATION ............................................................................................................41
19. QUALITY MANAGEMENT ........................................................................................................................42
19.1 AUDIT PLAN.............................................................................................................................................42
19.2 PROGRAM AUDIT....................................................................................................................................42
19.3 CORRECTION ACTION / PREVENTIVE ACTION PROGRAM......................................................................43
20. HEALTH SAFETY & ENFVIROMENTAL......................................................................................................43
20.1 HSE PHYLOSOPHY ...................................................................................................................................43
20.2 DESIGN HSE.............................................................................................................................................43
20.3 EVALUASI KEBIJAKAN HSE ......................................................................................................................43
20.4 SITE HSE...................................................................................................................................................43
20.5 KARYAWAN DAN PEKERJA......................................................................................................................44
21. PROJECT CLOSE UP – HAND OVER SERTIFICATE PACKAGE (HOP) ..........................................................45
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 4 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
1. GAMBARAN UMUM PENGGANTIAN METER TUBE PKT 3 FUEL.
1.1 Latar Belakang
PT Pertamina Gas Kalimantan Area berperan dalam menyalurkan Gas Bumi di Stasiun Kompresor
Gas (SKG) Bontang Kalimantan Area kepada PT Pupuk Kalimantan Timur (PKT), khususnya untuk
(PKT 3) dengan Sistem Meter Gas Orifis, 2 Stream Line peruntukan untuk Fuel Gas.
Pengukuran dan Perhitungan jumlah volume Gas Bumi dengan Sistem Meter Gas Orifis sebagai
dasar transaksi jual-beli gas dan penagihan Toll Fee biaya penyaluran Gas Bumi.
Kondisi saat ini existing Sistem Meter Gas Orifis sudah absolute dan akan dilakukan penggantian
Meter Tube Sistem Mete Gas Orifis untuk menjamin keandalan dan akurasi, atas sumber
pemasukan dari hasil supply gas ke ke PT Pupuk Kaltim 3.
PT Pertamina Gas Kalimantan Area akan melakukan penggantian Meter Tube PKT 3 Fuel dengan
tujuan untuk mengoptimalisasi pengoperasian, pengukuran dan perhitungan serta menghasilkan
tingkat keandalan, akurasi sesuai data hasil pengukuran secara online, sehingga penyaluran gas
lebih terjamin kebenarannya.
1.2 Lokasi Pekerjaan Penggantian Meter Tube PKT 3 Stasiun Kompressor Gas (SKG) Bontang
PT Pertamina Gas Kalimantan Area di Kawasan Industri PT Pupuk Kaltim , Bontang Utara -
Kalimantan Timur (Kaltim).
2. LINGKUP PEKERJAAN PENGGANTIAN METER TUBE PKT 3 FUEL.
2.1 PT Ansi Mega Instrumenindo selaku perusahaan perakit perekayasa Sistem Alat Ukur Serah
Terimna Gas Bumi sesuai SKT Migas ikut berpartisipasi dalam Proyek Penggantian Meter
Meter Tube PKT 3 Fuel di PT Pertamina Gas kalimantan Area meliputi:
2.1.1. Pekerjaan Administrasi Perizinan untuk Pekerjaan Penggantian Meter Tube PKT 3 Fuel, PT
Ansi Mega Instrumenindo akan melaksanakan:
a. Pengurusan dokumen teknis dan persetuan untuk pelaksanaan pekerjaan.
b. Melaksanakan koordinasi perizinan untuk pelaksanaan pekerjaan penggantian meter
tube PKT 3 Fuel termasuk pengurusan ke Perusahaan Inspeksi (PI), Direktorat Metrologi,
Direktorat Jenderal Migas pada Kementerian ESDM.
c. Menyiapkan dokumen untuk melaksanakan pekerjaan sesuai RKS pada pokok pekerjaan
penggantian Meter Tube PKT 3 untuk Fuel PT Pertamina Gas Kalimantan Area.
d. Menyiapkan dokumen nstrument alat ukur dan perlengkapannya serta peralatan
pendukung sesuai RKS.
e. Menyiapkan Standar Operasional Prosedur (SOP) untuk pelaksanaan pekerjaan.
f. Menyerahkan material sisa ex pekerjaan penggantian Meter Tube PKT 3 ke PT Pertamina
Gas Kalimantan Area.
2.1.2. Persiapan Sumber Daya, Tenaga , Material dan Peralatan.
PT Ansi Mega Instrumenindo akan menyiapkan:
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 5 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
a. Tenaga enjinering sebagai ahli teknik dan teknisi instrumen yang sesuai kompetensi
yang diperlukan.
b. Menyiapkan material, peralatan, instrument alat ukur dan perlengkapannya yang
diperlukan pada Gas Metering Skid PKT 3 Fuel Gas.
c. Menyiapkan peralatan kerja dan kelengkapannya sesuai kebutuhan
d. Menyiapkan Alat Pelindung Diri (APD) dan peralatan safety sebagai pendukung
keselamatan kerja, sesuai potensi bahaya yang mungkin ada di tempat kerja .
e. Menyiapkan meterial sesuai dengan spesifikasi teknis dan jumlah yang diperlukan sesuai
design engineering.
f. Menyiapkan sarana dan prasarana angkutan mobilisasi untuk material dan tenaga kerja
sebagai pendukung pelaksanaan pekerjaan penggantian meter tube PKT 3 Fuel Gas.
2.1.3. Penyiapan Pelaksanaan pekerjaan:
a. Mengacu Peraturan Keselamatan Kerja sesuai dengan Undang-undang dan peraturan
tentang HSE serta berdasarkan Contractor Safety Management System (CSMS) dari PT
Pertamina Gas Kalimantan Area.
b. Peraturan dan ketentuan yang terkait dengan metode keselamatan kerja aman dengan
menyesuaikan kondisi pekerjaan keteknikan yang akan dilaksanakan.
2.2 Pekerjaan Pokok yang harus dipenuhi sesuai Collective Number : S18PB0003A, RFQ NUMBER
: 6600043166 / 09.02.2018 dan RKS.
PT Ansi Mega Instrumenindo melaksanakan pekerjaan :
a. Pembuatan dan persiapan serta penyelesaian dokumen Administrasi Proyek.
b. Persiapan pelaksanaan pekerjaan , termasuk mobilisasi orang dan material serta
peralatan kerja.
c. Membuat design dan Perencanaan Teknik dan Engineering
d. Pengadaan material dan peralatan sesuai dalam dokumen kontrak kerja.
e. Melaksanakan Expedisi , Inspeksi dan Pengujian terhadap kontrusksi dan peralatan
teknik yang terkait dengan instrumen.
f. Membuat Progress Report terhadap kemajuan progress pekerjaan yang sedang berjalan
dan rencana kerja.
g. Mobilisasi dan Demobilisasi tenaga kerja , material dan peralatan yang dibutuhkan.
h. Melaksanakan pekerjaan Fabrikasi terhadap pipespool, skid metering dan pekerjaan
pipa dan tubing untuk instalasi metering.
i. Pekerjaan fiskal metering untuk kalibrasi metyering sistem dan sertifikasi dari Dit
Metrologi dan MIGAS.
j. Melaksanakan pekerjaan Pre-Commissioning dan Commissioning untuk peralatan
metering sistem PKT 3 fuel , sesuai dengan urutan dokumen Pre-Commissioning dan
Commissioning yang harus disetujui oleh Pertamina Gas .
k. Operational Acceptance terhadap kontinyuitas operasional sistem metering PKT 3 fuel
terhadap operasional serah terima gas ke PT Pupuk Kalimantan Timur 3.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 6 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
l. Melaksanakan Inhouse Training terhadap Supervisor dan Operator untuk pengenalan
program Operation and Maintenance terhadap metering sistem yang telah dilaksanakan
pemasangannya oleh PT ANSI MEGA INSTRUMENINDO , agar supaya dalam pelaksanaan
di lapangan bisa dilakukan perawatannya.
m.Membuat berita acara serah terima proyek penggantian meter tube PKT 3 Fuel kepada
PT Pertamina Gas , termasuk dokumen teknik , P&ID, Manual Book, Parts Catalog, MDR,
Dokumen Pengelasan, serta sertikasi dari Instansi dan institusi sesuai ketentuan yang
berlaku.
2.2.1 PT Ansi Mega Instrumenindo akan menyelesaikan serah terima pekerjaan proyek
penggantian meter tube PKT 3 Fuel sesuai spesifikasi RKS dan data teknik engineering
dengan standar, serta membuat berita acara serah terima yang akan dituangkan dalam
Berita Acara Pemeriksaan Pekerjaan selesai 100% dan di tandatangani oleh pihak PT
Pertamina Gas.
2.2.2 Membuat laporan dokumen teknis dan dokumen administrasi sesuai dengan kebutuhan
proyek.
3. PERSIAPAN DAN PELAKSANAAN PEMBUATAN DOKUMEN ADMINISTRASI PROYEK .
3.1 PEMBUATAN DOKUMEN PROYEK PENGGANTIAN METER TUBE PKT 3 FUEL:
3.1.1 PT Ansi Mega Instrumenindo secara Mandatori akan membuat Dokumen Proyek sesuai RKS yang
terkait dengan dokummen Engineering dan dokumen administrasi asli meliputi :
a. Design Basis , Calculation ( Orifice calculation , piping calculation detail
b. Bill Of Material, MDR ( Data Sheet, Shop test, data mill test , vendor inspection report dab
sertifikasi material )
c. P & I Diagram, PFD , Isometric Drawing, System Arsitektur, General Arrangement Drawing
d. Wiring & Loop drawing , Shop Drawing, Hook up drawing, Presentasi persetujuan meter ke DitJen
Migas.
e. S-curve & Time Table, Work procedure (civil, electrical, hydrotest, painting, NDE,FAT, SAT dan lain
nya .
f. Laporan fabrikasi & Instalasi (harian, mingguan, bulanan), WPS, PQR
g. Sertifikat kualifikasi personel (welder,NDT), NDT & visual inspection report.
h. Lesk Test dan Hydrotest Valve & Meter System
i. FAT di COO (Country Of Origin) , FAT Meter System, Fat & SAT report.
j. Sertifikat Metrologi & Migas. BA kalibrasi Meter System, Inspection & test plan.
k. Modul Training & troubleshoting, Manual operasi dan pemeliharaan, HSE Plan.
3.1.2 PT Ansi Mega Instrumenindo secara mandatori akan mengirim semua dokumen teknik dan dokumen
administrasi kepada Pertamina Gas Kalimantan Area.
3.1.3 Dokumen tersebut akan didiskusikan dan dibuat persetujuan dengan Pertamina Gas, sebelum
dilakukan penjilidan kedalam odner.
3.1.4 Dokumen asli setelah disetujui akan dilakukan penjilidan dan dan diserahkan kepada Pertamina Gas
dengan rincian 1(satu) jilid asli dan softcopy didalam hard disk.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 7 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
3.1.5 Pt ANSI MEGA INSTRUMENINDO akan menyerahkan Bukti / Berita Acara Penyerahan Dokumen
Proyek kepada Pertamina Gas (asli) yang akan dilampirkan dalam invoice tagihan PT Ansi Mega
Instrumenindo.
3.2 PERSIAPAN PEKERJAAN PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS.
3.2.1 PT ANSI MEGA INSTRUMENINDO akan melaksanakan survey pendahuluan ke lokasi kerja agar bisa
mendapatkan data yang akurat, sehingga pada saat pelaksanaan pekerjaan tidak ada kendala.
3.2.2 PT ANSI MEGA INSTRUMENINDO , akan mengajuklan permohonan untuk pengurusan surat izin
masuk, permit dan simper , simlok, kepada Pertamina Gas Kalimantan Area PKT 3 antara lain:
a. Mengurus Badge Pertamina Gas dan PKT
b. Mengurus SIMPER Pertamina Gas dan PKT
c. Mengurus perijinan masuk , kendaraan alat angkut dan material kepada Pertamina Gas PKT 3.
d. Mengurus Mandatori MCU personil yang bekerja ( Surat Keterangan Sehat untuk Pekerja)
e. Surat Izin Kerja Panas/Dingin dari HSE Pertamina Gas.
3.2.3 PT Ansi Mega Instrumenindo, akan menyerahkan kepada Pertamina Gas Kalimantan Area:
a. Copy SPB (Surat Perjanjian Borongan)
b. 2(dua) buah Map Filling System empat lubang.
c. 1(satu) buah Log Book ditempatkan di lokasi pekerjaan untuk mencatata seluruh aktifitas
kegiatan harian selama dikerjakan.
3.2.4 PT Ansi Mega Instrumenindo, akan mengikuti hasil dan melaksanakan Kick Off Meeting dengan
Pertamina Gas setelah diterbitkan dan diterima PO/SPB untuk membahas:
a. Izin Masuk Kendaraan , Material dan Tenaga Kerja ke Site Plant Pupuk Kaltim Bontang
b. Mengurus Surat Izin Kerja / Permit To Work di PT Pertamina Gas Area Kalimantan
c. JHSEA (Job Health Safety Analysis)
d. SOP (Standard Operating Procedure)
e. Rencana Jadwal Pelaksanaan (S- Curve)
f. Teknis Pelaksanaan Pekerjaan
g. Audit Pre-Job Activity (CSMS)
3.2.5 PT Ansi Mega Instrumenindo Akan mematuhi dan melakukan kalkulasi data detail engineering
design sesuai dengan spesifikasi yang di tetapkan Pertamina Gas, peraturan perundang undangan
yang berlaku dan standard teknik . Hasil kalkulasi engineering akan diserahkan kepada pengawas
pekerjaan, yaitu:
a. Inspection & Test Plan
b. Design basis
c. Detail Drawing
d. Bill Of Material
e. P & I Diagram
f. System Architecture
g. General Arrangement drawing
h. S- curve & time table
i. Jadwal rencana kerja (Bar chart)
j. Prosedur kerja
k. Calculation (Orifice Calculation & piping calculation).
l. Dokumen lainnya terkait dengan pekerjaan sesuai RKS.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 8 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
3.3 Design Dan Perencanaan Teknik Instrumen
3.3.1 PT Ansi Mega Instrumenindo, membuat Detail Design piping dan mekanikal, elektrikal serta
instrument sesuai dengan engineering standard sesuai dengan standard keteknikan Migas
dan Pertamina untuk menentukan spesifikasi peralatan dan material.
3.3.2 PT Ansi Mega Instrumenindo, membuat Detail Design piping dan mekanikal, elektrikal serta
instrument sesuai dengan engineering standard sesuai dengan standard keteknikan Migas
dan Pertamina untuk menentukan spesifikasi peralatan dan material.
3.3.3 Detail Design piping, mekanikal, elektrical dan instrument mengikuti standar Migas dan Pertamina
dan selanjutnya diajukan untuk mendapat persetujuan sesuai dengan spesifikasi peralatan dan
material yang dibutuhkan
3.3.4 Membuat design development detail dari mekanikal , piping, elektrikal, instrumen dan
fabrikasi yang disesuaikan dengan persiapan pekerjan instalasi ulang field transmitter ,
dan flow recorder mengikuti permintaan Pertamina Gas.
3.3.5 Menyiapkan dan membuat gambar detail tentang sipil, mekanikal, & piping, elektrikal,
instrumen termasuk dalam P&ID, sistem arsitektur, general arrangement , isometric
drawing , wiring line diagram, lay out area, shop drawing, hook up memakai software
AutoCad.
3.3.6 PT Ansi Mega Instrumenindo, akan membuata design dan gambar detail teknik , sesuai
dengan spesifikasi teknik dan diajukan kepada Pertamina Gas untuk mendapat
persetujuan.
3.3.7 Membuat detail data spesifikasi kebutuhan material (BOQ - Bill Of Quality), termasuk
kelengkapan Manufacturer Data Report (MDR) dan Certificate of Compliance.
3.3.8 Melaksanakan koordinasi dengan Perusahaan Inspeksi (PI), untuk review design ,
persetujuan design , untuk mengajukan permohonan Persetujuan dan Penggunaan
menjadi Persetujuan Layak Operasi dari Dirjen MIGAS.
3.4 Pengadaan Material
3.4.1 Material dan kelengkapannya:
PT Ansi Mega Instrumenindo, akanmelaksanakan kebutuhan materuial dan peralatan untuk proyek
Penggantian Meter Tube PKT 3 Fuel PT Pertamina Gas Kalimantan Area, sesuai dengan spesifikasi
pengadaan material yang telah disejui oleh Pertamina Gas dan MIGAS.
3.4.1.1 PT Ansi Mega Instrumenindo, akan melengkapi tanggung jawabnya untuk melengkapi semua
pengadaan dan pembelian material untuk peralatan Penggantian Meter Tube PKT 3 Fuel sesuai
dengan dokumen RKS.
3.4.1.2 Barang import PT Ansi Mega Instrumenindo, akan mengikuti semua prosedur negara untuk bea
masuk dan cukai, dan jasa pelabuhan serta pengapalan serti biaya untuk pengiriman ke lokasi
kerja.
3.4.1.3 Material untuk proyek Penggantian Meter Tube PKT 3 Fuel Pertamina Gas, semua dalam kondisi
baru , sesuai dengan dokumen yang dapat dipertanggung jawabkan, dan supply material akan
menjaga jadwal pekerjaan di lapangan .
3.4.1.4 Semua material yang dibeli oleh PT Ansi Mega Instrumenindo sepenuhnya dilindungi Jaminan
Pabrikan ( manufacturing waranty )
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 9 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
3.4.2 Engineering Equipment.
3.4.2.1 Untuk Engineering Equipment PT Ansi Mega Instrumenindo, akan mematuhi aturan pertamina gas
termasuk Approved Manufacture List / Vendor List Pertamina Gas.
a. PT Ansi Mega Instrumenindo, akan mengajukan terlebih dahulu untuk menyertakan
Pertamina Gas dalam paket pembelian material termasuk data, spesifikasi, kalkulasi, data
sheet, engineering drawing, yang direkomendasi oleh vendor untuk start up dan operasi.
b. PT Ansi Mega Instrumenindo, mengajukan review paket ini kepada Pertamina Gas untuk
meyakinkan bahwa peralatan yang diajukan sesuai dengan standar dan spesifikasi proyek
untuk disetujui dan dilakukan pelaksanan pembelian .
3.4.2.2 PT Ansi Mega Instrumenindo, akan menyerahkan dokumen engineering equipment dilengkapi
dengan bukti yang menyatakan bahwa barang bukti sesuai dengan spesifikasi kepada Pertamina
Gas termasuk:
a. Shop Drawing dan Fabrication Drawing detail by detail.
b. Prosedur rinci pengelasan, hot forming, cold forming dan sop lain terkait fabrikasi.
3.5 EXPEDISI, INSPEKSI DAN PENGUJIAN.
3.5.1 PT Ansi Mega Instrumenindo, akan menyerahkan jadwal kegiatan pengiriman expedisi barang
untuk pelaksanaan Penggantian Meter Tube PKT 3 Fuel.
3.5.2 PT Ansi Mega Instrumenindo, akan mengajukan pormohonan Inspection Test Plan (ITP) untuk
dilakukan persetujuan oleh Pertamina Gas .
3.5.3 PT Ansi Mega Instrumenindo, akan menyerahkan jadwal kerja untuk point point penting inspeksi
pada enineering equipment untuk bersama vendor mengatur hold point., sampai semua
persyaratan terpenuhi.
3.5.4 PT Ansi Mega Instrumenindo, akan melaksanakan sesuai hasil inspeksi dari Pertamina Gas dan
pihak lain yang terkait, termasuk peralatan , dan akan bersama sama melakukan pengujian di
Workshop / Fabrikator untuk Metering Skid.
3.5.5 Pelaksanaan pengetesan di pabrikasi untuk FAT (Factory Aceptance Test) oriffice fitting , segala
akomodasi akan disediakan.
3.6 MOBILISASI DAN DEMOBILISASI
3.6.1 Melaksanakan mobilisasi dan demobilisasi peralatan kerja, tenaga kerja dan material kerja untuk
pekerjaan Penggantian Meter Tube PKT 3 Fuel di lokasi SKG Bontang Kalimantan Area.
3.6.2 Melaksanakan pekerjaan paking material dan material pelindung untuk Meter Tube dan peralatan
instrumen yang akan di mobilisasi ke SKG Bontang, agar supaya Meter Tube tidak rusak, cacat
fisik, deformasi dan cacat painting.
3.6.3 Inventarisasi alat ukur dan perlengkapannya (Sistem Meter Gas Orifis)
a. Melaksanakan sesuai dengan daftar peralatan (Check List).
b. Menyiapkan dan melengkapi surat jalan serta dokumen teknis lainnya.
c. Menyiapkan transportasi darat dan laut dari Jasa Angkutan.
3.6.4 Persiapan Kedatangan Barang di Lapangan.
Persiapan Permit To Work
a. Melaksanakan koordinasi dengan Petamina Gas dan PKT3 di lapangan
b. Melaksanakan pekerjan lifting plan sesuai SOP.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 10 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
c. Penyiapan alat bantu, Crane yang sesuai Tonage
d. Penyiapan Lokasi tempat penurunan material
e. Mengamankan dan sterilisasi terhadap lokasi kerja
f. Membuat Dokumentasi sesuai dengan kegiatan.
g. Membuat Berita Acara sesuai kegiatan.
3.7 Pembongkaran Metering Sistem PKT 3 Fuel Existing.
3.7.1 Persiapan Permit To Work
a. Melaksanakan koordinasi dengan Pertamina Gas dan PKT 3 Fuel.
b. Melaksanakan pekerjaan pembongkaran sesuai SOP.
c. Menyiapkan tenaga kerja , ahli teknik dan teknisi
d. Menyiapkan perengkapan kerja , safety plan dan alat bantu kerja aman .
e. Mensterilkan tempat kerja dan rambu rambu keselamatan kerja.
3.7.2 Pelaksanaan Pembongkaran Meter Tube PKT 3 Fuel Existing
a. Pembongkaran platform tangga diatas tube meter existing.
b. Pembongkaran valve SOV dan meter tube existing (2x8” dan 4”)
c. Memindahkan meter tube existing ke stockyard Pertamina Gas.
d. Melaksanakan disconnect transmitter dan chart recorder existing.
3.7.3 Fabrikasi dan Kontruksi Meter Tube
Pelaksanaan Fabrikasi dan Kontruksi
a. Menyiapkan material kebutuhan material sesuai dengan spesifikasi dan kebutuhan, termasuk
plat orifis sesuai dengan spesifikasi teknis perhitungannya .
b. Melakukan pemasangan instalasi sesuai dengan kebutuhan PKT 3 Fuel menjadi 2 Stream (2 x
8”) sesuai dengan spesifikasi Pertamina Gas.
c. Memastikan untuk kedua stream memiliki Flow Profiller, Isolation valve, Remote Operating
Valve (ROV), Daniel Senior Orifice Fitting (Dual Chamber),
d. Melaksanakan pekerjaan pemotongan dan bavel pipa 8” (PKT 3 Fuel) sesuai dengan RKS .
e. Pengelasan pipa spool dan sambungan fitting menggunakan line up clamp 8” dengan posisi
sejajar.
f. Pekerja Las bersertifikasi Migas Klasifikasi 6G sesuai dengan RKS termasuk pengelasannya.
g. Pekerjaan Honing pada meter tube sesuai dengan syarat dan standard AGA
h. Melaksanakan re-fabrikasi frame transmitter & recorder
i. Pengujian radiograph dan penetran pada setiap joint pengelasan.
j. Melaksanakan pekerjaan stand blasting dan painting setelah semua join las lulus radiography
dan hydrostastis test.
k. Melaksanakan hydrotest sistem meter yang telah di fabrikasi sebelum dikirim ke lokasi kerja.
3.7.4 Melaksanakan pekerjaan mekanikal , piping , elektrikal dan instrumen sesuai dengan detail desain
yang telah disetujui oleh Pertamina Gas dengan data :
a. Box transmitter & recorder , cable tray, pipa air instrument, junction box, recorder .
b. Ecer pipa , cutting, beveling , fit up & welding spool pipa dan kelengkapannya.
c. Memasang spool pipa air instrument dengan tie in sesuai dengan drawing.
d. Pemasangan kabel junction box dan kabel sinyal sesuai drawing.
e. Pasang cabel tray dengan struktur / support pipa sesuai dengan drawing.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 11 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
f. Membuat galian , dan pasang kabel bonding kabel grounding eksisting (D003), ke arah
support pipa , tiang lampu dan skid metering standard BS-7430 resistansi max 5 ohm.
g. Melaksanakan pekerjaan instalasi proses control buka tutup ROV di control room (Panel
Eksisting)
h. Re Programing dan integrasi ke Gas Flowcom eksisting dan pengecatan sesuai permintaan
Pertamina Gas.
i. Pemasangan tagging dan penomoran dari stainless steel untuk Junction box, transmitter,
pressure dan temperature indicator.
j. Proses Pekerjaan Pengecatan :
 Pekerjaan Pembersihan material dan Metal Finish & Primer coating.
 Melaksanakan pekerjaan pembersihan permukaan pipa , dari minyak debu dan
karat, dengan sand blasting sampai permukaan sesuai standard.
 Permukaan dibersihan dengan bahan kimia , dilapis permukaan dan di
dikeringkan.
 Melaksanakan pelapisan primer coating dengan campuran thiner (20%), solod
min 82%dan ketebalan 150-200 micron.
 Pekerjaan Intermediate Coating.
 Membersihkan permukaan pipa setelah primer coating dari minyak , kotoran dan
debu.
 Melaksanakan pelapisan intermediate coating dengan campuran thiner (20%),
solod min 82%dan ketebalan 150-200 micron.
 Pekercaan Top Coating
 Menyiapkan finish paint /coating polyurethane dan thiner (20%) minimul solid
50%
 Spray Pertama :
Menspray permukaan pipa dengan cat warna kuning sampai rata , dan ditunggu
sampai kering.
 Spray Kedua :
Menspray semua permukaan pipa dengan cat warna kuning sampai rata dengan
ketebalan 50 – 60 micron
3.7.5 Memasang instalasi meter tube dabn kelengkapannya :
a. Melaksanakan pemasangan meter tube , flow recorder (chart recorder), dan kelengkapan
peralatan tambahan.
b. Pasang valve 4” dan blind flange dan packing serta baut pengikat di setiap ujung valve.
c. Membongkar dan memasang field transmitter tube PKT 3 Fuel , yang terdisi dari :
 Pressure Transmitter, Differential Pressure Transmitter, Temperature Transmitter.
 Pressure Gauge, Temperature Indicator
 Tubing ,Connector, fitting
d. Tagging Instrumentasi dan tanda panah arah jalur gas mengalir pada pipa dan spool.
e. Pasang kabel transmitter dan field transmitter ke junction box, pasang cable gland , cable
shroud, tray kabel,.
f. Instal dan pasang integrasi sistem baru dengan sistem eksisting sesuai standard Migas.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 12 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
g. Melaksanakan pekerjaan purging gas N2 pada seluruh sistem baru sebelum gas in
h. Inspeksi dan kontrol seluruh komponen sambungan sistem pipa dan sistem meter
terpasang dengan sempurna.
i. Menyiapkan checklist dan mengajukan kepada Pertamina Gas untuk persetujuan .
j. Bersama Pertamina Gas melakukan witness SAT di Stasiun Kompresor Bontang
k. Melaksaanakan pembersihan limbah bekas pekerjaan di area kerja PKT 3 Fuel, menyipakan
peralatan tempat limbah/ sampah.
3.8 PEKERJAAN KALIBRASI DAN SERTIFIKASI METER TUBE PKT 3 FUEL.
a. Melaksanakan pekerjaan FAT , SAT/SIT Service Installation dengan petugas PI , MIGAS &
Metrologi dan Pertamina Gas.
b. Mengurus Surat Ijin Penggunaan Sistem Alat Ukur Meter Gas Orifice dari MIGAS da
melengkapi dokumen lainnya yang terkait dengan surat ijin MIGAS.
c. Melaksanakan kalibrasi sistem Meter Gas ( Transmitter, Flow Recorder (Chart recorder),
flow comp dan kelengkapan instrumen lainnya disaksikan oleh petugas PI , Dit Metrologi ,
Dit.Migas, dan Pertamina Gas.
d. Melaksanakan pengaturan dan akomodasi Ditjen Migas , Ditjen Metrologi dalam hal ikut
menyaksikan kalibrasi sistem Meter Gas.
e. Semua perlatan kalibrasi telah bersertifikat yang masih berlaku, untuk melaksanakan
kalibrasi Meter Gas.
f. Pelaksanaan kalibrasi disaksikan oleh.
 Petugas PI
 Petugas Dir. Metrologi
 Petugas Dit. Migas
 Pertamina Gas
 Shipper
 Konsumen
g. Membuat Berita Acara pelaksanaan kalibrasi , yang disaksikan oleh semua petugas yang
terkadung dalam ayat 3.8 point f.
h. Menyerahkan sertifikat izin penggunaan Meter Gas paling lambat 1 (satu) bulan setelah
pelaksanaan kalibrasi.
3.9 PENGUJIAN
3.9.1 Pengajukan prosedur radiography kepada pengawas Pertamina Gas, dan pelaksanaan NDT
pengelasan pipa adalah Radiography Test 100% , disaksikan oleh petugas Pertamina Gas. Bila ada
cacat pengelasan dilakukan perbaikan disaksikan oleh QC & HSE Pertamina Gas dan pihak ketiga
yang direkomendasi oleh Dit Jen Migas serta ada persetujuanb dari Pertamina Gas.
3.9.2 Hidrotest.
a. Menyerahkan SOP Hydrostatis test
b. Melaksanakan pengujian hydrostatis test pada valve dan meter tube.
c. Melaksanakan flushing pipa sebelum dilaksanakan hydrostatis test.
d. Menyiapkan air yang bersih dari kotoran dan kimia, minyak dan mengajukan bukti sertikat
uji air bersih dari Laboratorium bersertifikat KAN.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 13 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
e. Pelaksanaan test secara bertahan denga pressure test + 1,5 x Max Allowable Operating
Pressure (MAOP).
f. Hasil hydrotest dibuatkan berita acara yang telah disetujui oleh Pertamian Gas, dengan
melampiri chart barton
g. Menyiapkan peralatan hydrotest :
 Pompa pengisian
 Pompa Tekan
 Pressure Gauge
 Pressure recorder / chart barton yang masih berlaku masa umur sertifikatnya.
 Peralatan pendukung , dan alat bantu kerja aman , line baricade.
 Mengajukan pemeriksaan peralatan hidrostatik sebelum dipergunakan kepa QC - HSE
Pertamina Gas.
 Melaksanakan cleaning sisa air yang masih tertinggal , dan pipa dipastikan bersih dan
kering.
 Melaksanakan commissioning / start up untuk memastikan sistem pipa dan peralatan
bekerja dengan baik di dampingi oleh Pertamina Gas
3.9.3 Purging.
Melaksanakan pekerjaan purging pada pipa , baru kemudian dapat dalakukan pengisisn gas secara
bertahap sambil membuang nitrogen , agar pipa siap dialiri gas.
3.9.4 Melaksanakan inspeksi secara menyeluruh terhadap fungsi dan saran penunjang pada peralatan
meter.
3.9.5 Melaksanakan function test bersama Pertamina Gas untuk semua peralatan dan aksesories sistem
metering gas.
3.9.6 Memastikan bahwa function test peralatan metering gas berjalan dengan baik dan dapat
digunakan untuk mengukur gas yang mengalir .
3.9.7 Menyerahkan prosedur commissioning dan mengajukan persetujuan kepada Pertamina Gas.
3.9.8 Menyerahkan semua dokumen yang terkait dengan para pihak Dit Metrologi, Dit. Migas untuk
menyetujui dokumen dan berita acra penggunaan meter gas sebagai meter custody.
3.10 PRECOMMISSIONING DAN COMMISSIONING.
3.10.1 Precommissioning
Melaksanakan precommissioning dengan melengkapi persyaratan :
a. Pekerjaan Engineering.
 Menyiapkan As- Build Drawing .
 Menyiapkan Dokumen Engineering
b. Pekerjaan Piping
 Telah melaksanakan pemasangan seluruh system perpipaan sesuai dengan P&ID.
 Telah selesai melaksanakan hydrotest dan flusing , Purging N2
 Telah menyelesaikan pekerjaan pengecatan / coating , marking pipa.
 Menutup dan merapihkan semua galian pipa .
c. Pekerjaan Mekanikal.
 Telah menyerahkan sertifikat dari manufacture untuk Bal Valve dan peralatan lainnya.
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 14 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
 Bal Valve dan peralatan lainnya sudah terpasang sesuai dengan P&ID.
 Menyerahkan sertifikat pengujian untuk Material dan peralatan (Ball Valve, dll).
 Telah melaksanakan hydrotest
 Telah menyelesaikan pekerjaan painting / coating.
 Telah menyiapkan suku cadang untuk commissioning apa bila diperlukan .
 Menyiapkan peralatan house keeping untuk area cleaning.
d. Pekerjaan Elektrikal.
 Menyerahkan pekerjaan listrik yang sudah diuji oleh QC-HSE Pertamina Gas, sesuai
dengan spesifikasi yang telah ditentukan oleh Pertamina Gas.
 Menyerahkan copy berita acara hasil uji pekerjaan listrik yang telah disetujui oleh
Pertamina Gas.
e. Pekerjaan Instrument.
 Menyerahkan hasil pemasangan system instrumen dan kontrol yang sudah dikalibrasi,
di uji dan diterima oleh Pertamina Gas,
 Sudah melaksanakan pemeriksaan loop dan fungsi dari peralatan instrumen, dan hasil
uji yang telah diterima oleh Pertamina Gas.
f. Pekerjan Sistem Meter Gas Orifice.
 Menyerahkan hasil pekerjaan Sistem metering sesuai dengan P&ID dan Drawing , dan
telah dilakukan pengujian kalibrasi meter oleh Dir Metrologi dan Dit Migas , termasuk
hydrotest dan leak test
3.10.2 Commissioning
a. Menyerahkan Prosedure pelaksanaan commissioning yang telah disetujui oleh Pertamina
Gas
b. Memastikan untuk semua jalur pipa dari tie-in sampai metering sudah terisi gas.
c. Melaksanakan inspeksi semua keselamatan system safety berfungsi dengan baik dan
benar.
d. Menyiapkan ahli teknik dan teknisi untuk pelaksanaan commissioning
e. Pelaksanaan commissioning dengan mengopearsikan packaging metering selama 3 (tiga)
hari tanpa kegagalan operasi dan akurasi meter terjaga max error 1%.
f. Setelah dinyatakan lulus commissioning Pertamina Gas akan menerbitkan Certificate Of
Commissioning.
3.11 OPERATIONAL ACCEPTANCE .
Pelaksanaan kegiatan perawatan fasilitas siap dioperasikan oleh Pertamina Gas selama 90 (sembilan
Puluh) hari kalender secara kontinyu dan tidak ada pengerjan yang salah.
3.12 TRAINING SUPERVISOR DAN OPERATOR
3.12.1 Training Operasi Peralatan Meter
3.12.2 Menyiapkan jadwal pelaksanaan training, sylabus training , modul training.
Mengajukan rencana kerja pelaksanaan training operasi kepada Pertamina Gas untuk dilakukan
persetujuan, untuk mengajukan permohonan akan dilakukan satu minggu sebelum pelaksanaan
training operasi.
3.12.3 Materi Training Operasi Meluiputi :
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 15 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
a. Menyiapkan materi training hard copy dan soft copy.
b. Menyiapkan materi dan modul training untuk semua peserta termasuk konsumsi training
sesuai kebutuhan.
c. Fasilitas peralatan training Gedung dan Ruang training akan dipersiapkan oleh Pertamina
Gas.
d. Pelaksanaan training dilaksanakan dalam waktu satu hari serta onhand training mlihat
langsung peralatan meter gas yang baru terpasang untuk Meter Tube PKT 3 Fuel.
e. Melatih stimulasi peralatan intrumentasi meter tube PKT 3 Fuel.
3.12.4 Materi Training Pemeliharaan dan troubleshooting pada GFC.
a. Membuat Checklist peralatan yang kemungkinannya bisa trouble.
b. Latihan Animasi trouble shooting meter tube PKT 3 Fuel.
c. Melatih tanya jawanb dari daftar list Frequently Asked Question , dari contoh beberapa
masalah yang pernah terjadi .
d. Menyiapkan hardcopy dan konsumsi sesuai dengan kebutuhannya.
e. Meminjam Ruang training dari Pertamina Gas termasuk peralatan training.
3.13 GARANSI MASA PEMELIHARAAN METER TUBE PKT 3 FUEL .
a. Masa garansi dari PT Ansi Mega Instrumenindo terhadap semua peralatan selama tiga
bulan setelah Certificate of Commissioning diterima dari Pertamina Gas.
b. Melaksanakan perawatan dan pemeliharaan selama tiga bulan.
4. PEKERJAAN METER TUBE PKT 3 FUEL DALAM MANAJEMEN PROYEK
PT ANSI MEGA INSTRUMENINDO akan melengkapi kegiatan Penggantian Meter Tube PKT 3 Fuel dengan
melibatkan organisasi dan manajemen proyek untuk mensukseskan pekerjaan di SKG Bontang Pertamina
Gas Kalimantan Area , agar pelaksanaan kontrak kerja dalam bidang Engineering , Procurement, Fabrication
, Installation , Pre-Commissioning, Commissioning, Certification,Calibration, Testing, Start-Up dan Hand
Over pekerjaan penggantian meter tube PKT 3 Fuel serta kelengkapannya , dengan lingkup kerja adalah :
1. Manajemen Proyek
2. Engineering
3. Material Procurement and Supply
4. Construction & Installation Work
5. Transportasi Material
6. Fabrikasi Pipa Spoll dan kelengkapannya
7. Hook-Up, Installation and Integration
8. Pre-Commissioning, Commissioning dan Start-Up
9. Sertifikasi ( Migas , Metrologi dan kelengkapan sertifikasi peralatan)
10. Training dan Pelatihan
11. Dokumentasi dan As-Build Drawing
4.1 MISI DAN VISI DALAM PROJECT PENGGANTIAN METER TUBE PKT 3 FUEL
PT. Pertamina Gas Kalimantan Area melaksanakan kegiatan untuk penggantian meter tube PKT 3 Fuel
untuk menyalurkan gas PT Pupuk Kalimantan Timur (“PKT3”), penyaluran gas ke PKT 3 dihitung
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 16 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
dengan Sistem Meter yang terdiri dari 2 line yaitu line PKT 3 Proses dan PKT 3 Fuel. Kondisi eksisting
Metering PKT 3 sudah abnormal sehingga kesulitan melakukan perawatan.
Oleh karenanya PT Ansi Mega Instrumenindo sebagai perakit perekayasa dalam bidang instrument
Migas , ikut berpartisipasi dalam pekerjaan penggantian Meter Tube PKT 3 Fuel di PT Pertamina Gas
Kalimantan Area. Kesempatan ini membuktikan bahwa kami siap untuk melaksanakan pekerjaan ini
dan akan mengikuti segala peraturan yang terkandung dalam dokumen tender Rencana Kerja dan
Syarat-Syarat (RKS) Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018.
4.1.1 Tujuan pekerjaan Pekerjaan Penggantian Meter Tube PKT 3 Fuel
a. Menjamin bahwa pekerjaan tersebut dari mulai start sampai dengan project hand over
memenuhi klasifikasi penjabaran dari dokumen lelang dari mulai pekerjaan persiapan , design
engineering , fabrikasi dan installasi memenuhi standar yang berlaku yang diharapkan dalam
dokumen lelang Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 dan
hasil pekerjaan bisa di aplikasikan sesuai dengan spesifikai teknis
b. Menjamin bahwa semua material/bahan, tenaga kerja, peralatan dan metode pelaksanaan
pekerjaan intalasi sesuai dengan standard/code, Peraturan Pemerintah. (Metrologi & MIGAS)
c. Menjamin bahwa pekerjaan Penggantian Meter Tube PKT 3 Fuel ini sesuai dengan spesifikasi
Teknis.
d. Menjamin bahwa rencana kerja Engineering , Dokumen , Purchasing Material , Installation,
Fabrikasi , sesuai dengan rencana kerja.
4.1.2 Dokumen Teknis dan Sertifikasi
a. Menjamin bahwa seluruh Dokumen Engineering telah memenuhi Standard/Code yang berlaku,
memenuhi ketentuan/peraturan pemerintah (Metrologi & MIGAS), memenuhi stan-
dard/spesifikasi yang diharapkan Pertamina Gas dapat diaplikasikan sesuai spesifikasi teknis
b. Menjamin bahwa semua material/bahan , tenaga kerja, peralatan dan metode pelaksanaan
pekerjaann instalasi sesuai dengan standard / code dokumen
c. Menjamin bahwa rencana kerja Engineering , Dokumen , Purchasing Material , Installation,
Fabrikasi , sesuai dengan rencana kerja dan berkualitas
d. Ahli Teknik yang akan mengerjakan sesuai dengan kompetensi bersertifikat yang dimiliki di bidang
Instrumentasi, baik bidang Mechanical , Electrical
e. Kelengkapan data yang tersusun dan terprogram dalam folder dokumen Penggantian Meter Tube
PKT 3 Fuel , meliputi semua Dokumen Teknis dan Administratip terkait dengan Engineering,
Purchasing , Electrical , Instrument , Mechanical dan Data Vendor List serta Lampiran dokumen
Engineering
f. Calculations,As Build Drawing,Design Approval Document,Inspection & Test Plan
g. Material Sertificate, Catalog, Operation & Maintenance Manual,Installation Manual
h. WPS & PQR/ Welding Performance Qualification,Welding Log Book, Welder Sertificates
i. Welding Test Report, NDT Report, Painting Procedure and Report, Visual Inspection Report,
j. Functional Test Report ( Hydrotest/Pneumatic Leak Report,FAT Report)
k. Dimensional Check Report, Calibration Certificate, Migas / Metrologi Certificate
l. Waranty Statement Letter ( Masa Pemeliharaan)
m. Technical Compliance Letter
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 17 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
n. Mechanical Test Data and Certificate
o. Electrical Test Data
p. Hydrotest Data Certificates
q. Performance Test Data Certificate ( SAT, SIT,FAT )
4.2 Strategi dan Pelaksanaan Pekerjaan
Untuk mensukseskan strategi prlaksanaan pekerjaan ada beberapa tahapan yang akan dilaksanakan
untuk Penggantian Meter Tube PKT 3 Fuel termasuk interfacing sistem alat kontrol dengan tahapan
sebagai berikut yaitu :
a. Klarifikasi Dokumen teknis dan engineering pekerjaan sesuai dokumen RKS Collective Number :
S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018.
b. Design Engineering & P&ID Drawing Instrument
c. Project Planning & Scheduling pelaksanaan rencana kegiatan
d. Reporting , Daily , Weekly, materi dokumen untuk meeting rutin
e. Membuat Penawaran harga sesuai BQ
f. Negoisasi harga penawaran
g. Pemeriksaan HSE dan evaluasi perusahaan
h. Evaluasi kesiapan ahli teknik , teknisi dan staf pendukung proyek administrasi
i. Pemahami dokumen Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018
j. Membuat Schedule pelaksanaan kerja sesuai kontrak kerja
4.3 Mempersiapkan dan menangani sesuai bidang Engineering
a. Engineering , Pre-Fabrication, Pengujian dan instalasi skid sistem alat ukur, Control valve, valve ,
dan kelengkapannya
b. Melengkapi alat ukur , sensor , transmitter tekanan dan temperature dari sistem alat ukur
c. Pasang instalasi flow computerdan setting integrasi dengan PCS dan ESD
d. Sertifikasi Kalibrasi Sistem Alat Ukur Semi Custody dan Master Meter (Migas /Metrologi)
Pekerjaan Pipa dan Mekanikal :
a. Memasang instalasi kebutuhan setting untuk kelengkapan peralatan instrumen
b. Memasang Instalasi kebutuhan Tie-in, pembongkaran dan relokasi fasilitas dengan aman dan
tidak ada gangguan shutdown
Pekerjaan Listrik
a. Supply material kelistrikan untuk instalasi Penggantian Meter Tube PKT 3 Fuel.
b. Pasang instalasi tie-in dan fasilitas UPS , Power distribusi tanpa ada gangguan.
Pekerjaan Instalasi Meter
a. Pasang struktur instalasi untuk Penggantian Meter Tube PKT 3 Fuel.
b. Bongkar pasang instalasi eksisting peralatan meter gas
Pekerjaan Kontrol Meter
a. Pasang instalasi transmisi data dari Flow Computer dan sistem DCS
b. Pekerjaan HMI untuk akomodasi sistem Control Meter Gas
c. Pasang material untuk kebutuhan sistem meter gas
4.4 Biaya Proyek dan Rencana Kerja
Untuk mendukung investasi untuk proyek ini , akan dilakukan langkah penghematan dana melalui
, dan analisa kebutuhan budget dan rencana kerja yang akan dilaksanakan:
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 18 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
a. Project Master Schedule untuk proyek ini diperkirakan sampai 200 hari kerja , untuk procurement
material dibutuhkan skitar 160 hari kerja , paralel dengan menunggu material , pekerjaan
pipespool work bisa sambil dikerjakan,
b. Works Break Down Structure ( WBS) , harus dibreakdown lebih rinci , agar supaya detail, step
pekerjaan bisa llebih jelas baik secara budget dan rencana kerja
c. Antisipasi terhadap procurement procudure , harus bertahap , sehingga tidak salah serial number
, tidak salah spesifikasi , dan rencana kedatangan material jelas 160 hari
d. Membuat breakdown biaya proyek , perkiraan biaya dan membuat estimasi biaya yang akurat
Baseline proyek schedule harus paralel dengan monitoring rencana dan pelaksanaan kerja
a. Bertanggung jawab terhadap perhitungan , Cost Variant(CV), Schedule Variant(SV), Cost
Performance Index (CPI), Schedule Performance Index (SPI)
b. Membuat kalkukasi dasar estimasi , Estimate At Completion (EAC) dan Estimate To Completion
(ETC), sehingga analisa biaya lebih tajam.
5. PROJECT MANAGEMENT
Struktur Organisai :
Lihat Lampiran No1
5.1 Tugas Dan Tanggung Jawab Project Manager
a Bertanggung jawab terhadap manajemen proyek Penggantian Meter Tube PKT 3 Fuel Meter
, pada project Pertamina Gas Kalimantan Area, baik dari segi, Teknis, administrasi,
konsolidasi dan meting dengan PT Pertamina Gas .
b Melaksanakan koordinasi dengan All staf dan pekerjan internal dan external dalam rangka
keselamatan , pelaksanaan pekerjan Penggantian Meter Tube PKT 3 Fuel di Pertamina Gas.
c Membuat distribusi tugas dan pengawasan kepada masing masing pekerja serta membuat
strategi yang tepat untuk rencana kerja, anggaran , serta fokus pada bidang pekerjaan
Instrumentasi yang dipertanggung jawabkan
d Analisa aspek kontruksi dan pekerjaan lapangan sesuai rencana kerja serta memecah-kan
problem solving yang dihadapi, untuk menjaga kualitas pekerjaan, termasuk melaporkan
hasil rutin progres pencapaian progres dan kualitas kerja kontruksi & instrumentasi
5.2 Tugas Dan Tanggung Jawab Engineering Lead
a. Melaksanakan kerja team dengan berbagai engineer
b. Membuat dan mengkontrol Design Architecture Instrument
c. Memuat Design Engineering Instrument dan persiapan termasuk code /standard
d. Control of Quality terhadap instrument dan document kelengkapannya termasuk
engineering documents PML & AML , Spesifikasi Document :
 General Arrangement Document
 QA / QC Document
 Mechanical & Piping Document
 Electrical Document
 Instrumentation Document
 Construction Document
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 19 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
 General Arrangement Report
 Vendor Correspondency
 Process Engineering
 Instrument Engineering
 Electrical Engineering
 Piping Engineering
 Calculation
 Drawing
 Electrical
 Report Calculation
 Drawing List Cable
 Lampiran Tambahan
5.3 Tugas Dan Tanggung Jawab Construction Lead
a. Pengawasi proyek konstruksi langsung dari konsepsi teknis management sampai PHO
b. Mereview perjalanan proyek by detail untuk menjadwalkan material dan tenaga kerjaserta
memperkirakan biaya
c. Mengawasi kontruksi dan memantau keselamatan kontruksi dan keselamatan pelaksanaan
kerja di lapangan
d. Mengkoordinasikan dan mengarahkan pekerja konstruksi dan subkontraktor sesuai dengan
detail pekerjaannya
e. Menggunakan peralatan , bahan dan peralatan dan layak dipakai.
f. Memenuhi spesifikasi kontrak kerja sesuai dengan dokumen Collective Number :
S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018
g. Progress Report harian , mingguan dan bulanan dimonitor
h. Menyiapkan laporan kontruksi internal dan eksternal yang berkaitan dengan status
pekerjaan
i. Merencanakan pekerjaan untuk mencegah kesalahan kontruksi dan menyelesaikan
masalah timbul dilapangan
j. Menganalisis, mengelola dan mengurangi risiko akibat kerja Penggantian Meter Tube PKT
3 Fuel
k. Melaksanakan standar konstruksi sesuai kualitas dan management teknik konstruksi
5.4 Tugas Dan Tanggung Jawab HSE Lead
a. Melaksanakan keselamatan proses untuk pekerjaan Penggantian Meter Tube PKT 3 Fuel.
b. Mengamankan Potensi bahaya dengan kegiatan :
 Risk assessment facilitation
 Hazard and Operability Study (HAZOP)
 Safety Case / Quantitative Risk Assessment (QRA)
c. Tinjauan keselamatan proyek seperti klasifikasi terhadap bahaya listrik, gambar zona
bahaya kebakaran, penghitungan keselamatan , studi penentuan lokasi fasilitas aman.
5.5 Instrumentation And Control Engineer
a. Bertanggung Jawab pada instrumentasi termasuk P&ID, Perhitungan, pengadaan, design
kabel untuk Installasi Metering System Skid, pra-commissioning, commissioning dan start-
up , training dan perawatan
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 20 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
b. Bertanggung jawab pada system control , termasuk , valves, flow,level, temperature,
pressure, safety
c. Bertanggung jawab pada pengujian , FAT, SAT, SIT, Pra-Commissioning, Commissioning dan
Start-up
d. Mampu mengoperasikan peralatan Fieldbus, Profibus, Modbus, untuk data metering
system , dan mampu mengendalikan serta meng install HMI
e. Bertanggung jawab pada keselamatan kerja termasuk , HAZOP, HAZID, serta peraturan
keselamatan kerja
f. Membuat Desing Engineering Electrical & Instrumentation
g.
h. Membuat Front End Engineering Design
i. Membuat General Arrangement
j. Membuat Hazardous Operation Analysis
k. Issued for Constuction,Issued for Design, Issued for Quotation,Issued for Review
l. Membuat Isometric Diagram
m. Membuat Line Design Temperature
n. Membuat Material Selection Diagram
o. Membuat analisa Material Take Off
p. Merencanakan Non Destructive Examination/Test
q. Membuat Design Proses & Instrumentation Diagram
r. Merencanakan Process Flow Diagram
s. Membuat Safety , Integrity level diagram, termasuk HASOP/HAZID
5.6 Mechanical And Piping Engineer
a. Melaksanakan pekerjaan mekanikal instalasi Penggantian Meter Tube PKT 3 Fuel ,pipe
spool skid, dan pekerjaan yang berkaitandengan pekerjaan mechanical termasuk pipa ,
tubing, bracket dan baja
b. Melaksanakan monitoring terhadap pekerjaan mekanikal dan aktifitas kontruksi di
lapangan
c. Bekerjasama dengan HSE untuk pengawasan safety pekerjaan mekanikal dan pipe spool ,
membuat laporan dan prosedur pelaksanaan mechanical dan pipe spool
d. Melaksankan pekerjaan sesuai dengan ketentuan dan persyaratan, dalam prosedur dan
spesifikasi dalam kegiatan mekanikal dan pipe spool
e. Membuat Laporan kegiatan mekanikal untuk , harian , mingguan , bulanan , dan membuat
prosedure pekerjaan mekanikal
f. Menyelesaikan setiap masalah yang terkait dengan mekanikal dan membuat laporan yang
jelas terinci, terurai , lengkap pada setiap pekerjaan Penggantian Meter Tube PKT 3 Fuel.
5.7 Safety Engineer
Safety engineer bertanggung jawab terhadap pelaksanaan Kesehatandan Keselamatan Kerja
Lingkungan (K3L) di lingkungan proyek seperti alat-alatperlengkapan dasar dapat berfungsi
sebagaimana yang dibutuhkan ketika ada benda-benda terjatuh Untuk mengatur kegiatan dan
kebijakan K3L ini, project manager menunjuk safety manager yang memiliki tugas,tanggung jawab
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 21 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
melaksanakan tugas dalam hal keselamatan kerja dan lingkungan kerja sesuai dengan garis besar tugas
di lapangan terjalin keselamatn kerja dan nyaman untuk bekerja.
Dalam hal ini detail pekerjaan dan kegiatan keselamatn kerja dan keselamatan lingkungan sesuai
dengan peraturan HSE .
5.7.1 Tugas Safety Engineer
a. Mempersiapkan barikade, Alat Pemadam Api Ringan (APAR), Alat Perlindungan Diri
(APD),rambu, poster, dan spanduk K3L yangdiperlukan pada tempatnya
b. Mempersiapkan lingkungan kerja yang aman
c. Merencanakan kegiatan safety seperti inspeksi safety,meeting safety,laporansafety, dan
penilaian K3Lsubkontraktor
d. Memberikan briefing kepada pembantu pelaksana, mandor, dan subkontraktor
5.7.2 Tanggung Jawab Safety Engineer.
a. Menjamin kesuksesan implementasi dan terus terjaganya kualitas sistem pengaturan keamanan
b. Bertanggung jawab mengontrol kualitas sistem pengaturan keamanan untuk
memastikankebijakan dan prosedur yang telah dibuat diaplikasikandengan benar
5.8 Structure Engineer
a. Melakukan perencanaan dan perhitungan struktur proyek Penggantian Meter Tube PKT 3 ,
yang ditunjuk/dijadwalkan kepadanya sesuai dengan standar/peraturan dokumen Collective
Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018.
b. Perencanaan struktur yang dihasilkan harus merupakan perencanaan yang ekonomis, mudah
dilaksanakan, memenuhi syarat kekuatan dan kekakuan struktur
c. Bersama-sama dengan Project Engineer/PE lainnya dalam membuat gambar sketsa/detail-detail
konstruksi/sistem struktur untuk keperluan penggambaran di studio
d. Membantu Project Coordinator/PC dalam tahap konstruksi, terutama koordinasi/revisi gambar
yang disesuaikan dengan keadaan lapangan
e. Atas sepengetahuan/persetujuan Project Coordinator/PC mewakili perusahaan dalam rapat-
rapat lapangan yang berhubungan dengan Kunjungan Berkala
f. Bersama-sama dengan Project Engineer/PE lainnya memeriksa gambar dari segi-segi kebenaran
ukuran, dimensi, penulangan, kesesuaian dengan anggapan-anggapan dasar dalam perhitungan,
kesesuaian antara gambar Struktur yang satu dengan yang lainnya maupun gambar-gambar
Struktur dengan gambar-gambar Arsitek, M/E dan lain-lain
g. Bertanggung jawab langsung kepada Project Coordinator/PC atas kualitas/keamanan
perhitungan struktur dan ketepatan jadwal kerja suatu proyek
h. Membantu Project Coordinator/PC dalam Perencanaan Struktur
5.9 Commissioning Engineering
a. Memeriksa prosedur commissioning dan memastikan semua prosedur proyek instalasi sesuai
dengan spesifikasi teknik.
b. Pastikan semua prosedur keselamatan instalasi dan kontruksi sesuai prosedur commissioning
c. Bekerja sama dengan team teknis di fabrikasi dan workshop.
d. Kominikasi dengan tim menganalisa masalah yang timbul dilapangan agar cepat ditangani
perbaikannya, tidak menggangu schedule commisioning.
e. Memeriksa dan melakukan cek Valve Alignment Activities serta peralatan tambahan
f. Memeriksa peralatan mekanis yang terpasang dalam skid metering
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 22 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
g. Bekerja sama dengan I & C dan Electrical Disiplin Memimpin
h. Memastikan bahwa peralatan bekerja sesuai spesifikasi teknis
i. Investigasi masalah dan analisa serta perbaikan peralatan yang sedang terpasang.
j. Membuat laporan dokumentasi pra commissioning dan commissioning / start-up.
5.10 Instrument Commissioning Engineer
1. Cable Diagrams/Schedules list
2. Develop the Instrument Loop folders to cover
3. Cable schedule
4. Tag list
5. I/O list
6. Inst Index
7. J/B schedule
8. Inst Data Sheets
9. Trip and Alarm s register
10. Loop sheets
11. C&E
12. Calibration sheets
13. Manage Point to Point testing
14. Instrument Calibration
15. Loop testing
16. Function Testing
17. C&E testing
18. Assist vendor to commission Vendor
19. P&ID Walk downs
20. Develop Instrument commissioning M/S, philosophy, procedures and Check sheets
21. Monitor Completion system (ATLAS) for Instrument M/C through to H/O
22. Instrument Punch Listing
23. SAT
5.11 Electrical Commissioning Engineer
1. Assist vendor with transformer test
2. Assist vendor with switc panel tests
3. Commission distribution boards
4. Commission L&SP
5. Lux tests
6. Point to point cable check
7. Inter locks
8. Trips and interface to power management
9. Witness earth tests
10. No load and load runs of meter equipment
11. SAT
12. Electrical punch list
13. Validate hazardous area certs
14. Interface with vendors
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 23 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
5.12 Piping Commissioning Engineer
1. Track delivery and approve Vendor Manuals and Documentation
2. Systemize P&ID
3. Develop System Description and Process Commissioning Procedures
4. Preparation of Method Statements / Procedure for Pre-commissioning of System
5. Preparation for pipe cleaning ( Flushing, Leak checking, )
6. Manage Preservation during pre com / com phase
7. Commissioning parts list
8. Review & Identify the training Requirements
9. Develop performance tests
10. Develop Hand Over procedures
11. Custodian of the O&M
12. P&ID Walk downs
13. First Fills
14. Manage Change
5.13 Project Control Engineer
a. Bertanggung jawab dalam hal pengawasan perhitugan biaya proyek, biaya peperencanaan
,pelaksanaan engineering review, waktu pelaksanaan kontruksi,kordinasi pengendalian dan
kontrol proyek secara keseluruhan
b. Bertanggung jawab pada pengawasan administrasi,dan teknis atas biaya dan penjadwalan
tenaga ahli teknik dan teknisi serta pekerja indirect yang bertugas secara khusus
c. Bertanggung Jawab pada pengawasan dan monitoring biaya proyek sesuai dengan BQ dan
rencana kerja instalasi Penggantian Meter Tube PKT 3 Fuel., termasuk persiapan materi rapat
dan diskusi rutin
d. Membuat laporan , harian , minguuan , bulanan, secara tepat benar dan betul, untuk seluruh
kegiatan pekerjaan , serta membuat laporan adanya penyimpangan yang akan mengganggu
biaya dan waktu pelaksanaan
e. Bertanggung jawab untuk pengawasan perencanaan biaya dengan menggunakan metode
teknis Manajen Proyek,dan melakukan review atas biaya pengadaan material dan waktu
pengiriman dari fabrikasi ke Proyek Site
5.14 Project Procurement Team
Bertanggung jawab pada teknik pengadaan material, yang terkait Perencanaan,
Pengorganisasian & Pengendalian arus bahan, mulai dari pembelian awal hingga tujuan
Kebutuhan material dan peralatan akan dipenuhi oleh kontraktor sesuai dengan spesifikasidata
teknis Perusahaan , dan Kontraktor akan melengkapi Prefered Manufacturers List (PML),dan
Approval Manufacture List (AML)
Pelaksanaan procurement termasuk kegiatan logistics untuk pengangkutan peralatan dan
material dari kantor Jakarta seperti :
a. Klarifikasi Engineering
b. Material Management Plan
c. Material Receiving & Shipping Schedule ter update
d. Purchase Order (PO), jelas terinci dan terurai spesifikasi barang dan serial numbernya
e. Material Take Off
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 24 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
f. Data Engineering
g. Schedule Kedatangan Material
h. Schedule Pengiriman dan delivery material
5.15 Procurement Status Report
Membuat data tampilan dengan Format exel , tentang kronologis tatus pengadaan dan
pergerakan material , mulai dari pembuatan PO sampai penyimpanan materian dan inspeksi
material serta rencana dan actual pengiram material sampai onsite .
5.15.1 Bulks Material
a. Procurement MTO (Piping / Mechanical / Electrical / Instrument)
b. Storage & Distribution - Material Control
c. Material Status Report
d. Requirement on-site Dates
e. Material Order & Timing
f. Receiving Material Procedure & Inspections
5.15.2 Procurement Coordinator
a. Melaksanakan prosedur pengadaan yang ditetapkan untuk proyek Semi Custody Meter,
Master Meter .
b. Koordinasi dan berinisiatif perencanaan strategis untuk semua masalah terkait
pengadaan.
c. Melaksanakan kegiatan pengadaan dan pengelolaan budget, peninjauan dan
interpretasi prosedur kontrak.
d. Memberikan pengawasan dalam proses pemilihan dan sumber pemasok utama,
termasuk permintaan penawaran, evaluasi penawaran dan persetujuan budget
penawaran dan pesanan pembelian.
e. Memastikan kepatuhan terhadap kontrak penawaran harga dengan persyaratan
perusahaan, hukum, etika, peraturan, jaminan penawaran, jaminan pelaksanaan, pajak,
dan persyaratan HSE , kick off meeting mengenai masalah terkait pengadaan barang
dan jasa.
f. Menampung semua permasalahan pengadaan barang dan jasa.
g. Membantu analisa kemungkinan yang terkait dengan memberi masukan kepada project
management .
h. Menyediakan dukungan pengadaan dalam mengembangkan dan memberikan
pengawasan fungsional kepada spesialis pengadaan barang dan jasa.
5.15.3 Logistics Officer
Mengembangkan dan melaksanakan alat dan metodologi kerja untuk memungkinkan
pelaksanaan rencana logistik yang efektif cepat dan tepat untuk proyek Semi Custody Meter,
Master Meter.
a. Merancang dan mengembangkan metode operasi standar untuk mengelola operasi
logistik secara efisien
b. Memastikan pelepasan kiriman penjaga perdamaian yang bertanggung jawab, tepat
waktu dan hemat biaya bersamaan dengan personil
c. Pastikan semua anggota staf yang diawasi dilatih dan dilatih secara melelahkan
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 25 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
d. Identifikasi persyaratan pelatihan logistik tambahan untuk mencapai standar kerja yang
tinggi
e. Mengkoordinasikan dan menyajikan dukungan logistik untuk operasi darat, udara,
kereta api dan sungai yang sedang berlangsung
5.15.4 Procurement Officer
a. Responsible of full Procurement and Supply Cycle, including but not limited to;
generating procurement bid/tender packages and receipt of bids/tenders, RFQ’s, bid
evaluations and awards, negotiate terms and commercial bids, creating and issuing
Purchase Orders (PO) and Service Orders (SO)
b. Ensures procurement activities conducted in accordance with company policies
c. Ensures orders adhere to supplier agreements and contracts; reports non-conformances
and propose contract disputes solution
d. Coordinating and conducting on-site job visits; acting as the primary contact and
ensuring that all technical questions submitted by the bidders are answered thoroughly
and distributed accordingly
e. Verify and submit invoices to accounts as well as coordinates with finance in resolving
invoice discrepancies with purchase order/contract terms referred
f. Providing continuous insight into contractors' and suppliers' progress towards meeting
purchase order requirements, including completion and delivery schedules; gathering
available data with respect to supplier and contractor production schedule; monitoring
and reporting progress to Project Management
g. May travel to suppliers' locations and fabrication shops to verify progress, as well as to
our construction and operational sites to ensure deliveries are occurring as required
h. Other Supply Chain duties, as needed
5.15.5 Commissioning Lead
Memimpin dan mempersiapkan Team Engineering dalam pekerjaan melaksanakan kegiatan
Pre-Commissioning / Commissioning & Start-up Berikan informasi teknis yang diperlukan untuk
disiplin lain selama proyek berlangsung Mengkoordinasikan pekerjaan dalam jam kerja dan
jadwal proyek yang dianggarkan
Tugas Utama
1 Melaksanakan penilaian dan evaluasi sampai terinci pekerjaan komisioning dan
melibatkan tim engineer serta mengevaluasi sumber daya yang ada menyelesaikan
problem solving yang ada.
2 Review dokumen teknis dan sop dan indentifikasi spesifikasi batasan dan stanfard untuk
menghilangkan resiko yang akan timbul dalam proyek.
3 Memberikan masukan data yang diperlukan untuk proposal teknis pada tahap
penawaran, melakukan inspeksi dan memastikan kegiatan fabrikasi selesai untuk evaluasi
persiapan data commissioning dan prosedur keselamatan instalasi . memastikan semua
prosedure dengan aman saat komisioning’
4 Pembahasan teknis dalam tim komisioning sampai final dan mengajukan persetujuan Pre-
Commissioning , Commissioning , dan Start Up kepada PHE .
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 26 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
5 Memimpin Tim Engineer untuk pelaksanaan kegiatan Pre-Commissioning /
commissioning , bersama sama dengan tim mekanikal dan QA/QC untuk melaksanakan
jadwal pelaksanaan pra-komisioning dan komisioning.
6 Menganalisa dan memperkecil resiko pelaksanaan pra-commissioning , commissing serta
mengeavuasi dengan teliti peralatan pendukungnya.
7 Melaksanakan dan me-review rutin terhadap penilaian risiko dengan melakukan
pertemuan / assesmment rutin dengan topik bahasan mengenai isu-isu HSE.
a. Evaluasi design dan kesalahan teknis agar bisa mengendalikan biaya , terutama
kesalahan akibat design akan mengeluarkan biaya tambahan harus dihindarkan, dan
ini bisa menjadikan schedule pekerjaan mundur.
b. Melaksanakan kontrol langsung ke lapangan dengan koordinasi QA/QC untuk
menjamin kualitas dan kemajuan progress pekerjaan.
c. Penanggung Jawab commissioning & pra-commissioning dan melaksanakan tugas
pengawasan proyek bekerja sama dengan engineering lainnya.
d. Menyelesaikan dan men-data daftar punch list items terhadap pekerjaan di
lapangan.
8 Secara teratur komunikasi dan rapat rutin dengan engineer dan supervisor untuk
memecahkan masalah terkait pelaksanaan proyek dengan aman .
9 Selalu berkomunikasi dan rapat rutin dengan engineer dan supervisor
10 Kerjasama Tim & kordinasi dengan engineer yang akan melaksanakan komisioning dan
berikan dukungan teknis dan pedoman instruksi teknis terkait commissioning
11 Mendistribusikan tugas teknis dan tanggung jawab terkait dengan pekerjaan
commissioning teruta ma tugas yang dibebankan kepada Supervisor.
6. QA / QC Team
6.1 QA/QC
a. Instrumentation
b. Electrical
c. Mechanical
6.1.1 QA / QC Lead
1. Supervise construction and co-ordinate work at site to maximize the effectiveness of
construction delivery to time, budget and quality objectives
2. Monitor and review the implementation of the EPC Contractors site quality management
system
3. Prepare project quality audit schedules and conduct project quality audits
4. Establish, document and maintain a quality control system for PMC site activities, liaise
with the EPC Contractor as directed, and ensure assigned work is managed and delivered
to site plant
5. Monitor and review site inspection and testing
6. Support other quality personnel in monitoring Contractors work execution during the
construction phase
7. Enhance and demonstrate commitment to raising HSE standards and proposing new
initiatives or improvements
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 27 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
8. Maintain and monitor all quality control activities
9. Participate in meetings as required
6.1.2 QA / QC Engineer
Melaksanakan Pemeriksaan dan inspeksi visual terhadap hasil pengelasan pipe spool,
a Membuat laporan harian pengelasan pipe spool ,Melaksanakan Joint Inspection NDT
terhadap Pipe spool ,Melaksanakan inspeksi dan pengukuran Penetration Test
b Melaksanakan dan inspeksi Hydrotest , untuk memastikan kebocoran pada pipe spool
c Membuat Tag Code pada Pipe spool , untuk antisipasi indentifikasi pada uji Hydrotest,
Menganalisa hasif Foto X Ray NDT
d Bertanggung Jawan pada pemeriksaan pipe spool , dari fit-up ke dimensi pipa, dan data
spesifikasi pemotongan pipa
e Bertanggung Jawab pada inspeksi kualitas, prosedur pengelasan pipe spool sesuai dengan
WPS
f Bertanggung jawab pada perbaikan dilakukan dengan benar dan akurat untuk meme-nuhi
Spesifikasi dan kualitas STD perbaikan mutu pengelasan pipe spool
g Bertanggung Jawab untuk Pengendalian Mutu pada Rencana Pemeriksaan dan Uji,
ITP (Surveillance, Witness, Hold Point dan Record Review)
h Bertanggung jawab pada Pemeriksaan dan Verifikasi ,Aktual Sesuai gambar Isometrik
yang –disetujui
i Ikut bertanggung jawab pada Keselamatan Pengelasan, Pengujian dan Aktivitas Terka-
kait sedang dilaksanakan, termasuk ,monitoring data punch list QC, untuk perbaikan
welding pipe spool
6.2 Instrument & Electrical QC Inspector
a Witness continuity testing / meggering of cable immediately prior to installation
b Witness installation / testing of grounding / earthing system
c Perform Surveillance Inspection of conduit and cable tray installation
d Perform Surveillance Inspection of conduit seal pouring
e Perform Surveillance Inspection of cable terminations
f Assist with Receipt Inspection of transformers and MCCs (if purged, perform Surveillance
Inspection periodically to ensure positive pressure is maintained)
g Witness installation of MCCs and switchgear
h Witness installation of transformers
i Assist with Receipt Inspection of heat trace cables and related materials
j Perform Surveillance Inspection of in-process installation to ensure that heat tracing is
installed per specifications
k Witness post-installation testing of heat tracing for acceptance inspection
l Assist with Receipt Inspection of instruments
m Perform Surveillance Inspection of instrument calibration
n Perform Surveillance Inspection of in-process instrument installation
o Verify instrument tubing is properly supported per specifications
p Verify all the instrument electrical installation inspections and megger tests have been
completed and are acceptablePerform Surveillance Inspection of Instrument Loop Checking
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 28 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
q Verify all installation inspections, pressure testing and continuity checks have been
completed and documented by the Contractor
r Verify the loop has been checked and is operating properly
6.3 Mechanical & Piping QC Inspector
1. Reviewing of documents related to Project Quality Control requirements, method
Statements and Inspection Test Plan (ITP)
2. Inspection all activity are spread over various stages of manufacture, including welding of
CRA weld overlay, disbonding for the CRA weld overlay cladding using incolloy 825 an 625
using SMAW/GTAW/GMAW
3. Monitoring activity of auto ect for wall thickness continuity check, manual UT for lamination
check for the CS pipe and disbanding for the weld overlay
4. Reviewing of test packages Semi Custody Meter, Master Meter.
5. Line checking inspection together with sub-contractor and main contractor QC Inspector
6. Generating punch list by category for the items need to install before hydro test after hydro
test and after commissioning
7. Witness hydro test, Pneumatic / Leak Testing and In-service testing
8. Performing line reinstatement
9. Commissioning of system such as for commissioning of instrument, flushing, calibration of
the valve, load test
7. Project Planning and Control
Project Planning
Bertanggung jawab pada langkah prosedural mulai awal persiapan proyek dan menata dalam
manajemen proyek, di mana dokumentasi yang diperlukan dibuat untuk memastikan
penyelesaian proyek yang sukses Dokumentasi mencakup semua tindakan yang diperlukan
untuk mendefinisikan, menyiapkan, mengintegrasikan dan meng-koordinasikan rencana
tambahan Rencana proyek jelas mendefinisikan bagaimana proyek dijalankan, dipantau,
dikendalikan, serta membuat perencanaan proyek membutuhkan analisis mendalam dan
penataan kegiatan berikut:
a Menetapkan tujuan proyek
b Mengidentifikasi deliverable proyek
c Membuat jadwal proyek
d Membuat rencana pengadaan material dan tenaga kerja serta peralatan
Tahap perencanaan proyek memerlukan beberapa masukan, termasuk proposal konseptual,
jadwal proyek, kebutuhan sumber daya / keterbatasan dan metrik ke- berhasilan Project
Planning (Perencanaan Proyek) dimulai dengan menetapkan lingkup proyek dan akhirnya
bekerja melalui setiap tingkat bergantung tindakan, tugas, analia , pelaporan kegiatan dan
rencana kerja serta tenaga kerja
7.1 Project Baseline
Bertanggung jawab pada penyusunan rencana kerja dengan baseline memakai Program MS
Project 2013, baseline proyek diletakkan di bawah kontrol perubahan untuk membantu ,
mengevaluasi perubahan dan dampaknya terhadap proyek
Kontrol kendali akan di analisa terhadap :
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 29 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
a. Data Cost Report (Cash Flow, Cost Overun,Task Cost Overview, Earnet , Resource Cost
Overview)
b. In-Progres Report (Critical Task, Late Task, Milestone Report, Slipping Task)
c. Resources Report (Overview Recources, Overallocated Overview)
d. Dashboard (Cost Overview, Project Overview, Work Overview, Upcoming Task)
e. Planning / Scheduling
f. Overall Project CPM, Engineering CPM, Procurement CPM, Fabrication CPM
g. Offshore Installation CPM
h. Hook-Up CPM
8. PROJECT ADMINISTRATION AND INFORMATION MANAGEMENT
8.1 Project Comunication
Project Communication Management bertangung jawab pada proses yang diperlukan untuk
memastikan bahwa informasi dalam proyek Penggantian Meter Tube PKT 3 Fuel, Collective Number :
S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 bisa dibuat dengan tepat dan cepat, baik dalam
segi pengumpulan, diseminasi, penyimpanan, dan disposisi Hal ini menciptakan hubungan yang penting
antara orang-orang, ide, dan informasi yang diperlukan supaya proyek berakhir dengan kesuksesan
Setiap orang yang terlibat dalam proyek ini harus siap untuk mengirim dan menerima komunikasi, dan
harus memahami bagaimana komunikasi dilakukan di mana mereka terlibat sebagai individu dan
bagaimana komunikasi dapat mempengaruhi proyek secara keseluruhan termasuk :
a. Perencanaan Komunikasi (Communication Planning,Distribusi Informasi, Pelaporan
Kinerja)
b. Membuat sistem administrasi termasuk komunikasi antara kantor pusat dan site opertion
di Fabrikasi atau di Site Plant
c. Safety Communication Plan
 Safety Performance Feedback Plan
 Safety Actifity Information
 Plant Emergency
 Communication interface
8.2 Project Plan dan Procedure :
Standar dan prosedur proyek biasanya didokumentasikan dalam Manual Prosedur dan Prosedur Proyek
Manual ini terdiri dari bagian pendahuluan yang diikuti oleh bagian terpisah untuk setiap aspek kegiatan
proyek, seperti:
a. Standar dan Prosedur untuk Kinerja Tim, termasuk praktik proyek umum seperti kode etik
dan terminologi proyek standar, rapat, prosedur pengendalian perubahan (termasuk
penggunaan Permintaan Perubahan dan Permintaan Keputusan), dan manajemen risiko
b. Standar dan Prosedur untuk Manajemen Biaya / Jadwal, termasuk mengatur pekerjaan,
pemantauan proyek, akuntansi proyek, dan analisis biaya / jadwal
c. Standar dan Prosedur Pengelolaan Data, termasuk perpustakaan proyek, identifikasi
dokumen, struktur dokumen dan gaya, dan persiapan dokumen
d. Standar dan Prosedur untuk Manajemen Konfigurasi, termasuk mengidentifikasi,
mengendalikan, memelihara, dan melaporkan item konfigurasi
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 30 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
e. Standar dan Prosedur untuk Manajemen Mutu, termasuk hal-hal seperti: walk-through,
review, audit dan inspeksi, penanganan dan penyimpanan, pengemasan dan pengiriman,
dan prosedur untuk menghilangkan penyebab masalah.
Standar dan prosedur memberikan instruksi khusus proyek mengenai prosedur, konvensi
penamaan/tag, alat pendukung, peralatan, standar dan metrik yang akan diterapkan oleh
tim proyek Penggantian Meter Tube PKT 3 Fuel ,Collective Number : S18PB0003A, RFQ
NUMBER : 6600043166 / 09.02.2018untuk mencapai sasaran mutu dan target waktu
penyelesaian pekerjaan
Semua anggota tim di Proyek , termasuk personil Perusahaan dan Personalia saat mengerjakan proyek
, diharapkan mematuhi standar yang diuraikan dalam dokumen yang beredar dan sirkulasinya harus
dimonitor, untuk memastikan bahwa informasi yang diserah terimakan di pahami dan dimengerti untuk
dilaksanakan.
8.3 Standar dan prosedur didasarkan pada prinsip-prinsip berikut
a. Standar dan prosedur akan disepakati terlebih dahulu untuk semua kegiatan proyek di
mana sejumlah besar orang harus bekerja sama dalam satu Tim di “ Provision Of Semi
Custody Meter And Installation Service (Tender No TS1/FEI-002/17/JAN)” Semi Custody
Meter, Master Meter.
b. Tim akan dilibatkan dalam pengembangan atau adopsi mereka untuk memastikan bahwa
standar dimiliki oleh Project Team , kemudian akan mendisiplinkan diri mereka untuk
mematuhi standar kualitas
c. Setiap usaha akan dilakukan untuk memastikan bahwa kualitas standar dan prosedur
terbukti dan tidak memaksakan standar yang tidak perlu atau prosedur yang terlalu rumit
d. Setelah diadopsi, standar akan didokumentasikan secara formal, mudah diakses dan mudah
dimengerti
e. Pemimpin Tim akan melakukan:
 Menekanan manfaat saat berhadapan dengan anggota tim,
 Berikan umpan balik awal kepada anggota tim mengenai pekerjaan dengan standar,
 Konsisten dalam menerapkan standar dan prosedur
 Kepatuhan terhadap standar akan disertakan sebagai item untuk ditinjau dalam walk-
through dan inspeksi lapangan
8.4 Project Meeting Report
a. Melaksanakan rapat/meeting untuk membuat laporan dan pertemuan yang dilaksanakan bisa,harian ,
mingguan dan bulanan dengan topik bahasan , problem solving dan progress kemajuan proyek yang
sedang dikerjakan, dengan menyiapakan materi meeting dan materi presentasi power point.
b. Pembahasan dalam proyek meeting , tidak hanya masalah teknik saja , termasuk masalah , Schecule
Proyek, Logistics Proyek ,Material Control , HSE, dan kesehatan lingkungan kerja Laporan tentang
Progress Pekerjaan yang sedang berjalan juga harus jelas terinci dan terurai , dilampiri foto kegiatan nya
8.5 Network Requirement
Untuk mendukung Project diperlukan jaringan internet yang bisa mengirim dan menerima
dokumen dari dan ke PT ANSI MEGA INSTRUMENINDO, jaringan komputer, bisa
mengakses file yang kita miliki sekaligus yang telah diseberluaskan melalui jaringan
internet Selain itu, pekerja di lapangan juga dapat mengirim teks, laporan harian, gambar,
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 31 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
audio, maupun video secara real time dengan bantuan jaringan komputer Informasi
dengan sangat mudah melalui internet
Untuk komunikasi Project Penggantian Meter Tube PKT 3 Fuel , Collective Number :
S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 diperlukan jaringan internet , agar
semua informasi dan dokumen bisa dengan segera , dikirim atau diterima untuk
komunikasi antara Kantor Pusat dan Project Manager dilapangan , serta ahli teknik dan
teknisi yang sedang mengerjakan proyek
8.6 Knowledge Management
Dalam strategi untuk mensukseskan Proyek “Penggantian Meter Tube PKT 3 Fuel,
Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018. Knowledge
Management diperlukan dalam membuat strategi, sistem dan teknik yang digunakan
oleh individu, dan Tim dilapangan akan mengikuti alur pola pikir dan tindakan yang harus
dilakukan untuk mengatasi problem solving dan , rencana tindak lanjut untuk progress
pekerjaan, dengan mengikuti teknik terbaru dalam rangka analisa problem solving ,
termasuk apllikasi komputer dimanfatkan
9. PROJECT CONTROL ESTIMATING
9.1 ESTIMATING
a. Bertugas melakukan estimasi pengendalian biaya proyek , penjadwalan, dokumentasi
perubahan dan pengendalian biaya sambil melaporkan tingkat program dalam
pengendalian proyek
b. Kritis terhadap Penjadwalan Waktu , Estimasi Biaya , Teknik Biaya dan Monitoring nya,
untuk bisa menyelesaikan pekerjaan penggantian meter tube PKT 3 Fuel 360 (tiga ratus
enam puluh) hari kalender, dan masa pemeliharaan 3 (tiga) bulan.
c. Mengarahkan dan set up /review status kontrol proyek (biaya, kontrak, WBS, jadwal,
sumber daya, dll)
d. Kontrol yang ketat terhadap , Logistics dan Material yang akan terpasang
e. Menggunakan perkiraan untuk penjadwalan dan pengendalian biaya
f. Mengontrol biaya dan jadwal di akhir proyek, menganalisa data komponen audit proyek
g. Membuat analisa perhitungan estimasi budget untuk perhitungan variable Budget Control
dan Cost Control
9.2 SCHEDULING & SCHEDULING COST CONTROL
a. Penjadwalan jaringan pekerjaan dan mempertajam WBS/CPM/PERT dan detail pekerjaan
b. Memvalidasi jadwal, dan evaluasi detail jadwal yang sedang berjalan dan yg akan jalan
c. Mempertajam Block Diagram dan diagram perencanaan , serta progres pencapaiannya
d. Penjadwalan dasar dan perhitungan jaringan distribusi kegiatan
e. Menganalisa jalure pekerjaan kritis untuk pengamanan pekerjaan alternativ yg bisa
f. Kendala alternatif, dan mencari jalan keluar agar pekerjaan tetap jalan
g. Gantt charts dan milestone , tetap ditahan agar tidak mundur dari schedule
h. Menahan baselines Schedule tidak stagnasi, Memahami garis baseline
i. Menghitung dan menganalisa biaya atas cost secara bertahap , agar posisi keuangan kuat
j. Membuat Detail Kurva “S” kumulatif costing dan analisa tagihan sesuai progress dari kerja
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 32 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
k. Me-review ulang kegiatan yang terkait dengan scheduling dan membuat persetujuan
dengan Project Manager (PM), agar supaya project costing bertahan dan balance
l. Overall Project CPM, Engineering CPM, Procurement CPM, Fabrication CPM
m. Offshore Installation CPM
n. Hook-Up CPM
o. Progres Report harian , mingguan , bulanan.
9.3 COST CONTROL
Project Cost Control menjadi prioritas PT ANSI MEGA INSTRUMENINDO,untuk menjalankan
sistem penjadwalan, dan jadwal berfungsi untuk pengendalian biaya dan factor yang dominan
dalam project cost plan adalah sebagai berikut :
a. Project Cost Plan
b. Cost Plan
c. Cost Baseline
d. Cash Flow
e. Baseline Budget Cost
f. Budget Project Plan
g. Cost Baseline (CB)
h. Budgeted Cost of Work Scheduled (BCWS)
i. Planned Value (PV)
j. Actual Cost Work Performed (ACWP)
k. Actual Cost (AC)
l. Resource Cost
m. Material Cost
n. Transportation Cost
9.4 Progres Measurement
PT ANSI MEGA INSTRUMENINDO akan menetapkan metode pengukuran /progress
measurement terhadap kemajuan pekerjaan engineering, pengadaan dan konstruksi untuk
project Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER :
6600043166 / 09.02.2018 . Prosedur ini mendefinisikan metode pengukuran kemajuan dan
perhitungan kemajuan fisik untuk proyek yang sedang berjaln dilapangan dengan tambahan
sbb :
a. Rencana Kemajuan Manajemen Proyek unntuk progress daily report dan kurva “S”
termasuk lampiran fota dan detail pekerjaan yg dilaksanakan menjadi prioritas utama
karena berkaitan dengan kondisi aktual dilapangan.
b. Progress Pekerjaan Engineering akan disiapkan sesuai dengan spesifikasi engineering Titik
berat dari progress kemajuan pekerjaan teknik dilapangan akan di evaluasi termasuk jam
kerja orang (Man Hour & Man Power) sebagai dasar efisiensi untuk aktifitas dan setting
budget plan perbandingan jam kerja dan jumlah tenaga kerja yang berttugas di Site Plant.
c. Progress Procurement Plan, terhadap pengadaan peralatan dan material yang akan dibeli
oleh PT ANSI MEGA INSTRUMENINDO Selalu diikuti proses pengadaan material yang akan
dipakai di Site Plan dan Fabrikasi, dan dimonitoring setiap hari sehingga status dari material
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 33 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
termasuk pembelian, penerimaan bahan baku utama dan bahan baku penunjang, FOB dan
kedatangan barang.
d. Persentase dari bobot kedatangan material disesuaikan dengan komitmen fix schedule
kedatangan barang.
e. Contruction & Installation Plan, Rencana Kemajuan Konstruksi ,disiapkan sesuai dengan
rencana kerja pelaksanaan kontruksi / instalasi , fabrikasi dan termasuk mobilisasi,
demobilisasi, pengelolaan, fasilitas sementara dan konstruksi termasuk kemajuan pra-
commissioning / commissioning dan start-up Progress bobot kemajuan untuk instalasi dan
pra-commissioning, termasuk data sesuai data yang tercatat dalam Bills of Quantities (B /
Q) yang akan dialokasikan ke paket pekerjaan Nilai Bobot kontruksi didasarkan pada harga
kontrak , sampai commissioning dan start-up, berdasarkan rencana kerja
f. Persentase dari bobot kedatangan material disesuaikan dengan komitmen fix schedule
kedatangan barang.
g. Contruction & Installation Plan, Rencana Kemajuan Konstruksi ,disiapkan sesuai dengan
rencana kerja pelaksanaan kontruksi / instalasi , fabrikasi dan termasuk mobilisasi,
demobilisasi, pengelolaan, fasilitas sementara dan konstruksi termasuk kemajuan pra-
commissioning / commissioning dan start-up Progress bobot kemajuan untuk instalasi dan
pra-commissioning, termasuk data sesuai data yang tercatat dalam Bills of Quantities (B /
Q) yang akan dialokasikan ke paket pekerjaan Nilai Bobot kontruksi didasarkan pada harga
kontrak , sampai commissioning dan start-up, berdasarkan rencana kerja
9.5 Review And Approved
a. Document Review and Approval adalah proses inspeksi dokumen manajemen mutu dan
dokumen proyek yang memastikan bahwa ada tinjauan atau persetujuan yang memadai
atas deliverable proyek yang berhasil diselesaikan sebelum memulai pekerjaan selanjutnya
b. Review adalah kegiatan untuk mempertimbangkan sesuatu lagi agar tercipta cara yang
sesuai, memadai, efektif, dan efisien untuk mencapai tujuan yang telah ditetapkan
c. Dokumen Review dan Approval Category ditentukan oleh pentingnya dokumen dan
informasi yaitu untuk informasi, untuk tinjauan ulang, untuk persetujuan, dan untuk
catatan Ada: IFR (Issued for Review), IFD (Issued for Approval) , IFD (Issued for Design), FCR
(Issued for Client Review), FCA (Issued for Client Approval), AFD (Approved for Design), and
IFC (Issued for Construction) or AFC (Approved for Construction) sesuai dengan dengan
proses kerja yang telah selesai.
d. Approval dan Persetujuan adalah suatu Dokumen yang harus dilakukan tindakan sebagai
berikut :
 Tindakan untuk mendukung atau menambahkan otorisasi pejabat yang berwenang
untuk , penerimaan atau persetujuan, atau izin resmi untuk suatu dokumen
 Kesepakatan yang tertuang dalam dokumen sebagai persyaratan kontrak oleh pihak
yang mengajukan prosedur proyek dalam Project Execution Plan (PEP) / Metedologi
Kerja.
10. ENGINEERING DESIGN
10.1 Proses Design Basis
a. Dokumen Perhitungan & Stimulasi
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 34 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
b. Simulasi Proses
c. Analisa Alur Minyak Mentah
d. Line Sizing
e. Equipment Sizing
10.2 Simulasi Proses
a. Dokumen Perhitungan & Stimulasi
b. Simulasi Proses
c. Analisa Alur Minyak Mentah
d. Line Sizing
e. Equipment Sizin
10.3 Dokumen Spesifikasi & Data Sheet
a. Dokumen Spesifikasi
b. Process Data Sheet
10.4 Dokumen Gambar
a. Dokumen Spesifikasi
b. Process Data Sheet
10.5Dokumen Gambar Process Flow Diagram
a. Utility Flow Diagram
b. Piping & Instrument Diagram
10.6Piping, Mechanical, Electrical , Instrumentation
10.6.1 Piping Design Basis
a. Piping Arrangement
b. Piping Isometric
c. Piping Layout
10.6.2 Dokumen Spesifikasi & Data sheet
a. Dokumen Perhitungan (Calculation)
b. Dokumen Spesifikasi & Data sheet
c. Maximum Allowable Working Pressure
d. Pipe Wall Thickness
10.6.3 Stress Analysis
a. Equipment Sizing
b. Participate in scope definition during bid / project execution / work sharing stages
c. Responsible for manpower planning based on resource loading per schedule
requirement
d. Responsible for establishing base documents / project procedures / standards /
specifications to be used for the project and to make team aware of the requirements
e. Responsible for identifying resources, mobilization and demobilization planning
f. Responsible for providing correct information to project team in terms of physical
progress and areas of concerns, identify risks and take corrective steps for any
deviations on schedule, budget or quality issues
g. Responsible for establishing action / needs list to resolve project related items
h. Review and approve critical documents produced by the discipline engineer(s)
i. Participate in estimation of man-hours / MTO during bid stage
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 35 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
j. Participate in development of work instructions and procedures for the discipline
k. Perform all assigned work to agreed standards for safety, health environment and
demonstrate a commitment to attaining high levels of HSE (Health, Safety &
Environment) performance
l. Participate in and advice on all design activities and initiatives, including provision of
training, inductions and documentation review
m. Verify that all designs are to required standards and that the objectives of the project.
n. Verify that the works is completed to the agreed schedule
10.6.4 Dokumen Prosedur
a. Metering Skid Intallation Procedure
b. Welding Procedure
c. Equipment Handling Proscedure
d. Pre-Commissioning & Commissioning Procedure
10.6.5 Electrical Design Basis
a. Control & Instrumentation Design Basis
b. Dokumen Spesikasi & Datasheet
c. Hazardous Area Clasification Specification
d. Hazardous Area Clasification Specification
10.6.6 Electrical Cable
a. Earthing Grounding
b. Control Panel
c. Valve & Control Valve
d. Flow , Pressure & Temperature Measurement
e. Management Information System
f. Material Take Off
10.6.7 Dokumen Perhitungan ( Calculation)
a. Electrical Load Study
b. Power System Study
c. Equipment Sizing
d. Valve & Control Valve Sizing
10.6.8 Dokumen Drawing
a. One Line Diagram
b. Cause & Effect Diagram
c. 1/0 Diagram
d. Loop Diagram , Termination
e. Instrument Hook Up
f. Lay Out Diagram
10.6.9 Dokumen Prosedur
a. Electrical Installation Procedure
b. Instrument Installation Procedure
c. Instrument Site Acceptance Test (SAT) Procedure
d. Instrument Calibration Procedure
e. Pre-Commissioning Procedure & Commissioning Procedure
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 36 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
f. Painting Procedure
11. CONTRACT MANAGEMENT PROJECT
11.1 Project Sub-Contracting Plan
Bertanggung jawab , pada rencana yang mencakup seluruh periode kontrak pekerjaan pipe spool, untuk
kontrak dengan waktu tertentu, dan memiliki tujuan yang didasarkan pada subkontrak yang
direncanakan oleh PT ANSI MEGA INSTRUMENINDO untuk mendukung kontrak pekerjaan Penggantian
Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018.
11.2Zero Deffect Program
Sub kontraktor bertanggung jawab pada produk yang berkualitas sesuai dengan standard
engineering yang diminta untuk pembuatan pipe spool, dengan produksi tanpa cacat
diharapkan tidak ada biaya ulang dan schedule pelaksanaan tepat waktu, produksi tepat waktu
dan hasil yang berkualitas sangat membantu kecepatan untuk proses berikut nya Kualitas disini
diukur secara finansial, dinilai sesuai zero defects, yaitu produksi tanpa cacat
12. PROCUREMENT
12.1Material Management Plan
Material Management adalah teknik pengadaan material, yang terkait Perencanaan,
Pengorganisasian & Pengendalian arus bahan, mulai dari pembelian awal hingga tujuan Adapun
untuk pengadaan material perlu persiapan dan langkah sebagai berikut :
a. Material Requsition List ter up-date
b. Material Receiving & Shipping Schedule ter update
c. Purchase Order (PO), jelas terinci dan terurai spesifikasi barang dan serial numbernya
12.2Purchasing Engineering
a Mengikuti dan mendaftar menjadi peserta lelang
b Membuat dan melaksanakan Purchase Order Pro-Forma barang / material
b Mengikuti dan membuat Kontrak Pro-Forma barang / material
c Mengadakan Transportasi dan Logistik Barang / Material
d Mengikuti persetujuandan komitmen Spesifikasi Engineering yang diminta
e Mengikuti dan komitmen pada Persyaratan Quality Engineering
f Mengajukan Meminta / Mengevaluasi Tawaran dan negosiasi harga
g Menyetujui kesekapatan dokumen kontrak yang dipersyaratkan (PO)
h Melaksanakan Inspeksi Kualitas , SIT , SAT , Quality Standard
i Memastikan barang yang akan diterima dan akan diserahkan sesuai Serial Numbernya
j Berusaha Mempercepat per tanggal delivery barang/ material
k Melaksanakan Delivery Pengiriman barang/ material
l Melaksanakan penyimpanan barang di gudang
m Mempertahankan qualitas barang dan mengamankan dari bahaya karat
n Melanjutkan pengiriman barang /material ke konstruksi / instalasi
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 37 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
12.3EXPEDITING PLAN
a. Merencanakan dan men follow up pengiriman barang dengan aman dan berkualitas
b. Membuat Packing terhadap barang yang akan dikirim agar tahan terhadap karat
c. Loading Material dan pengikatannya dalam container kuat dan tidak membuat cacat
12.4MATERIAL INSPECTION
a. Melaksanakan Unpacking dan , inspeksi material / barang yang datang
b. Mencocokan serial number dan no part , Quality dan Quantity Barang
c. Membuat laporan barang yang cacat , salah kirim dan barang yg tidak berkualitas
d. Membuat Laporan Claim Insurance terhadap barang yang cacat, salah kirim
13. LOGISTICS MANAGEMENT
Membuat Shipping Schedule pipe spool dari Fabrication yang akan dikirim PHE WMO dan PEP
Merencanakan, menerapkan, dan mengendalikan arus efisien, efektif , dalam penyimpanan
barang, layanan, dan terkait untuk memenuhi kebutuhan material Construction & Logistics
sebagai bagian penting dari konstruksi yang akan dipakai dalam project pekerjaan Penggantian
Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 /
09.02.2018 ,termasuk kosolidasi dalam manajemen rantai pasokan dan logistik (Chain
Management Logistics)
14. CONSTRUCTION & INSTALLATION
14.1Program Dokumen Lelang
Kontraktor diminta untuk menghadiri Rapat Review Program dengan Engineering dan Manajer
Proyek Project Manager dan Project Planner diminta untuk memberikan presentasi tentang
filosofi Program Tender yang penjelaskan data klarifikasi Engineering, rapat ini bisa berlangsung
ber-kali2 untuk komunikasi setelah proses lelang dilewati.
Program Lelang Pekerjaan disamping menyipak dokumen perusahaan ditambah :
 Organization Chart Tenaga Kerja
 Metode Pelaksanaan Kerja / Project Execution Plan
 Cash Flow Perusahaan dan Bank
 Schedule Rencana Kerja
 Penawaran Harga BQ
14.2Temporary Facility Plan
Rencana Fasilitas Sementara disiapkan sebelum dimulainya pekerjaan di lokasi Pertamina Gas,
mengembangkan rencana lokasi yang menunjukkan lokasi dan dimensi fasilitas sementara
(termasuk tata letak dan rincian, area penyimpanan peralatan dan material (tempat dan di luar
lokasi), dan rute pengangkutan dan pengangkutan , Jalan masuk / jalan masuk ke area berpagar
dan rincian instalasi pagar Identifikasi area mana pun yang mungkin harus dikeruk untuk
mencegah pelacakan lumpur Menunjukkan apakah penggunaan area tambahan atau area
pementasan lainnya diinginkan Agar keselamatan dan konstruksi, trailer situs, pintu masuk
konstruksi, tempat pembuangan sampah, fasilitas sanitasi sementara
14.3Construction /Installation Execution Plan
PROJECT EXECUTION PLAN / METODOLOGI KERJA
PENGGANTIAN METER TUBE PKT 3 FUEL
PT PERTAMINA GAS KALIMANTAN AREA
DOC No :
Revisi : 0
Page : 38 of 46
PARAF
PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS
Construction/Installation Execution Plan dirancang untuk mendukung pengembangan rencana
commissioning dan instalasi untuk pelaksanaan proyek Penggantian Meter Tube PKT 3 Fuel,
Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 .
Bila proyek tidak termasuk konstruksi, PEP mendukung pengembangan rencana berbasis
deliverable Persiapan CEP menjadi bagian dari kegiatan pengembangan tim proyek, termasuk
HSE Plan, agar supaya pekerjaan bisa berjalan dengan aman, dan berkualitas, sesuai dengan
schedule dan budget
Ada beberapa persyaratan yang harus bisa diatasi yaitu :
a Ringkasan Proyek & Back Gound
b Target , Visi dan Misi
c Ruang Lingkup Pekerjaan
d Lokasi dan Lay Out Project
e Kontrak Pengadaan Barang dan Jasa
f Jadwal Rencana Kerja
g Budget & Cash Flow
h Organisasi Proyek
i Strategi Pengadaan Bahan dan Material
j Metode Jalur Kritis
k Manajemen Resiko
l Tindak Lanjut Pekerjaan
m Persyaratan Dokumen Teknis
14.4Construction Administration
Kontraktor bertanggung jawab untuk pekerjaan Penggantian Meter Tube PKT 3 Fuel, Collective
Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 bisa sesuai dengan rencana
dan memenuhi spesifikasi teknik, tim engineering akan memastikan bahwa pembangunan
fasilitas ini mematuhi dan sesuai dengan keselamatan kerja dan keselamatan lingkungan PT
ANSI MEGA INSTRUMENINDO bertanggung jawab untuk melaksanakan pekerjaan dengan
metodologi kerja serta rencana kerja & jadwal pekerjaan instalasi sesuai dengan kontrak
kerjaProsedur administrasi konstruksi kami meliputi:
a Berpartisipasi dengan mitra kontraktor
b Mempersiapkan laporan instalasi site report
c Menerbitkan modifikasi dokumen kontrak ,bila ada
d Meninjau modifikasi yang diminta oleh kontraktor
e Memantau kemajuan konstruksi
f Mengembangkan punch lists
g Menentukan penyelesaian substansial
h Mengkoordinasikan kegiatan penyelesaian proyek
i Mengkoordinasikan modifikasi yang diminta
14.5Field Engineering
Bertanggung jawab untuk memberikan dukungan teknik untuk mengatasi masalah teknis di
lapangan Dan berpartisipasi dalam rapat koordinasi teknis masalah yang terjadi di lapangan
didukung dari kantor pusat Mengidentifikasi dan mencatat penyimpangan data perbaikan
peralatan dan membuat berita acara setelah tindakan perbaikan peralatan selesai
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube
Metodologi Kerja Project  Penggantian Meter Tube

More Related Content

What's hot

AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008Vanny Wayongkere
 
modul pelaksanaan proyek
modul pelaksanaan proyekmodul pelaksanaan proyek
modul pelaksanaan proyekMOSES HADUN
 
SOP Pekerjaan Konstruksi
SOP Pekerjaan KonstruksiSOP Pekerjaan Konstruksi
SOP Pekerjaan KonstruksiJocky Nahor
 
Bab ii pgn sicanang
Bab ii pgn sicanangBab ii pgn sicanang
Bab ii pgn sicanangEka Regar
 
Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...
Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...
Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...zaki muliawan
 
METODE PELAKSANAAN, power point rempoa
METODE PELAKSANAAN, power point rempoaMETODE PELAKSANAAN, power point rempoa
METODE PELAKSANAAN, power point rempoaMOSES HADUN
 
Manager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptxManager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptxDatil1906
 
Laporan Study Kelayakan PLTMH
Laporan Study Kelayakan PLTMHLaporan Study Kelayakan PLTMH
Laporan Study Kelayakan PLTMHpandirambo900
 
2007 08-pekerjaan drainase
2007 08-pekerjaan drainase2007 08-pekerjaan drainase
2007 08-pekerjaan drainaseahmad fuadi
 
Metode pelaksanaan konstruksi
Metode pelaksanaan konstruksiMetode pelaksanaan konstruksi
Metode pelaksanaan konstruksiedo dwi guntoro
 
PCM KONTRAK GEDUNG
PCM KONTRAK GEDUNGPCM KONTRAK GEDUNG
PCM KONTRAK GEDUNGRIONOASNAN3
 
Analisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjongAnalisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjongroxzjack
 
Pedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan Pemetaan
Pedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan PemetaanPedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan Pemetaan
Pedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan PemetaanCv. Ainayya
 

What's hot (20)

AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008
 
modul pelaksanaan proyek
modul pelaksanaan proyekmodul pelaksanaan proyek
modul pelaksanaan proyek
 
SOP Pekerjaan Konstruksi
SOP Pekerjaan KonstruksiSOP Pekerjaan Konstruksi
SOP Pekerjaan Konstruksi
 
Desa sukaratu
Desa sukaratuDesa sukaratu
Desa sukaratu
 
Analisa harga satuan
Analisa harga satuanAnalisa harga satuan
Analisa harga satuan
 
Bab ii pgn sicanang
Bab ii pgn sicanangBab ii pgn sicanang
Bab ii pgn sicanang
 
Metode pelaksanaan
Metode pelaksanaanMetode pelaksanaan
Metode pelaksanaan
 
Laporan KP.docx
Laporan KP.docxLaporan KP.docx
Laporan KP.docx
 
Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...
Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...
Manpro.id Software Manajemen Proyek Konstruksi untuk Owner, Kontraktor, Manaj...
 
METODE PELAKSANAAN, power point rempoa
METODE PELAKSANAAN, power point rempoaMETODE PELAKSANAAN, power point rempoa
METODE PELAKSANAAN, power point rempoa
 
Manager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptxManager Pelaksanaan Gedung.pptx
Manager Pelaksanaan Gedung.pptx
 
Company profile PT. Prima Indojaya Mandiri
Company profile PT. Prima Indojaya MandiriCompany profile PT. Prima Indojaya Mandiri
Company profile PT. Prima Indojaya Mandiri
 
Laporan Study Kelayakan PLTMH
Laporan Study Kelayakan PLTMHLaporan Study Kelayakan PLTMH
Laporan Study Kelayakan PLTMH
 
2007 08-pekerjaan drainase
2007 08-pekerjaan drainase2007 08-pekerjaan drainase
2007 08-pekerjaan drainase
 
Metode pelaksanaan konstruksi
Metode pelaksanaan konstruksiMetode pelaksanaan konstruksi
Metode pelaksanaan konstruksi
 
PCM KONTRAK GEDUNG
PCM KONTRAK GEDUNGPCM KONTRAK GEDUNG
PCM KONTRAK GEDUNG
 
RK3K
RK3KRK3K
RK3K
 
Metode pelaksanaan gedung
Metode pelaksanaan gedung Metode pelaksanaan gedung
Metode pelaksanaan gedung
 
Analisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjongAnalisa harga pekerjaan bronjong
Analisa harga pekerjaan bronjong
 
Pedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan Pemetaan
Pedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan PemetaanPedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan Pemetaan
Pedoman Analisa Harga Satuan Pekerjaan Pengukuran Topografi dan Pemetaan
 

Similar to Metodologi Kerja Project Penggantian Meter Tube

Metodologi Kerja SPPP Tempino
Metodologi Kerja SPPP TempinoMetodologi Kerja SPPP Tempino
Metodologi Kerja SPPP TempinoGunawan CNG
 
Menara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic Tower
Menara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic TowerMenara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic Tower
Menara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic Towerenergiputrabangsa
 
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...Andy Sulistio
 
PPT NATUNA (1).pptx
PPT NATUNA (1).pptxPPT NATUNA (1).pptx
PPT NATUNA (1).pptxFadliST
 
power point jalan dan jembatannnnnnnnnnn
power point jalan dan jembatannnnnnnnnnnpower point jalan dan jembatannnnnnnnnnn
power point jalan dan jembatannnnnnnnnnnHeri Susanto
 
Paparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptx
Paparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptxPaparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptx
Paparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptxAMYTHASPMC
 
PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...
PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...
PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...M. Rio Rizky Saputra
 
Fiberglass Specialist | PT Energi Putra Bangsa
Fiberglass Specialist | PT Energi Putra BangsaFiberglass Specialist | PT Energi Putra Bangsa
Fiberglass Specialist | PT Energi Putra Bangsaenergiputrabangsa
 
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air MinumPedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minuminfosanitasi
 
PRESENTASI AFIF PSPPI UNDIP.pdf
PRESENTASI AFIF PSPPI UNDIP.pdfPRESENTASI AFIF PSPPI UNDIP.pdf
PRESENTASI AFIF PSPPI UNDIP.pdfafifsalim12
 
Bab v pgn sicanang
Bab v pgn sicanangBab v pgn sicanang
Bab v pgn sicanangEka Regar
 
Presentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptxPresentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptxMohammadIsaMario1
 
4. audit teknis + aknop danau embung (kab.minahasa)
4. audit teknis + aknop danau embung (kab.minahasa)4. audit teknis + aknop danau embung (kab.minahasa)
4. audit teknis + aknop danau embung (kab.minahasa)QeedzVandemorth
 
Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...
Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...
Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...Agung Noorsamsi
 
Abstrak edit 7
Abstrak  edit 7Abstrak  edit 7
Abstrak edit 7msskunk
 
Analisa biaya dan waktu
Analisa biaya dan waktuAnalisa biaya dan waktu
Analisa biaya dan waktuudin2234
 

Similar to Metodologi Kerja Project Penggantian Meter Tube (20)

Metodologi Kerja SPPP Tempino
Metodologi Kerja SPPP TempinoMetodologi Kerja SPPP Tempino
Metodologi Kerja SPPP Tempino
 
final presentasi ptp3.pptx
final presentasi ptp3.pptxfinal presentasi ptp3.pptx
final presentasi ptp3.pptx
 
LAPORAN PKL Tromol
LAPORAN PKL TromolLAPORAN PKL Tromol
LAPORAN PKL Tromol
 
Menara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic Tower
Menara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic TowerMenara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic Tower
Menara Kamuflase | Tower Kamuflase | Camouflage Tower | Aesthetic Tower
 
Bab 1
Bab 1Bab 1
Bab 1
 
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
Penentuan jadwal-penggantian-optimal-komponen-scraper-plate-pada-mesin-giling...
 
PPT NATUNA (1).pptx
PPT NATUNA (1).pptxPPT NATUNA (1).pptx
PPT NATUNA (1).pptx
 
power point jalan dan jembatannnnnnnnnnn
power point jalan dan jembatannnnnnnnnnnpower point jalan dan jembatannnnnnnnnnn
power point jalan dan jembatannnnnnnnnnn
 
Paparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptx
Paparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptxPaparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptx
Paparan RAPAT OPSI PERPANJANGAN BBI 1 DES 2021.pptx
 
PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...
PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...
PENGARUH PENGGANTIAN COMBUSTION LINER TERHADAP PERFORMA TURBIN GAS PLTGU UNIT...
 
Fiberglass Specialist | PT Energi Putra Bangsa
Fiberglass Specialist | PT Energi Putra BangsaFiberglass Specialist | PT Energi Putra Bangsa
Fiberglass Specialist | PT Energi Putra Bangsa
 
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air MinumPedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
Pedoman Pelaksanaan Konstruksi Sistem Penyediaan Air Minum
 
PRESENTASI AFIF PSPPI UNDIP.pdf
PRESENTASI AFIF PSPPI UNDIP.pdfPRESENTASI AFIF PSPPI UNDIP.pdf
PRESENTASI AFIF PSPPI UNDIP.pdf
 
Bab v pgn sicanang
Bab v pgn sicanangBab v pgn sicanang
Bab v pgn sicanang
 
Presentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptxPresentasi pertek emisi PT BRM .pptx
Presentasi pertek emisi PT BRM .pptx
 
4. audit teknis + aknop danau embung (kab.minahasa)
4. audit teknis + aknop danau embung (kab.minahasa)4. audit teknis + aknop danau embung (kab.minahasa)
4. audit teknis + aknop danau embung (kab.minahasa)
 
Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...
Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...
Penyusunan Audit Teknis & AKNOP Danau & Embung di Kab. Minahasa & Kab. Minaha...
 
Abstrak edit 7
Abstrak  edit 7Abstrak  edit 7
Abstrak edit 7
 
PGN.pptx
PGN.pptxPGN.pptx
PGN.pptx
 
Analisa biaya dan waktu
Analisa biaya dan waktuAnalisa biaya dan waktu
Analisa biaya dan waktu
 

Recently uploaded

Gambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdf
Gambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdfGambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdf
Gambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdfYoyokSuwiknyo
 
Makalah pptMOTOR LISTRIK DAN MOTOR AC.pptx
Makalah pptMOTOR LISTRIK DAN MOTOR AC.pptxMakalah pptMOTOR LISTRIK DAN MOTOR AC.pptx
Makalah pptMOTOR LISTRIK DAN MOTOR AC.pptxDevaldiferdiansyah
 
Pelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman Madya
Pelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman MadyaPelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman Madya
Pelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman Madyadedekhendro370
 
Jual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan Konsultasi
Jual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan KonsultasiJual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan Konsultasi
Jual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan Konsultasissupi412
 
K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015
K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015
K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015IrfanAdiPratomo1
 
PPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptx
PPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptxPPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptx
PPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptxHeruHadiSaputro
 
Presentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptx
Presentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptxPresentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptx
Presentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptxyoodika046
 
Electrostatic Precipitator handbook manual
Electrostatic Precipitator handbook manualElectrostatic Precipitator handbook manual
Electrostatic Precipitator handbook manualdendranov19
 
Bahan kuliah elemen mesin semester 2 rekayasa manufaktur
Bahan kuliah elemen mesin semester 2 rekayasa manufakturBahan kuliah elemen mesin semester 2 rekayasa manufaktur
Bahan kuliah elemen mesin semester 2 rekayasa manufakturAhmadAffandi36
 
Petunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptx
Petunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptxPetunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptx
Petunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptxpkmcipakudrive
 
ESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptx
ESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptxESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptx
ESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptxadnijayautama
 

Recently uploaded (16)

Gambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdf
Gambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdfGambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdf
Gambar Rencana TOYOMARTO KETINDAN Malang jawa timur.pdf
 
Makalah pptMOTOR LISTRIK DAN MOTOR AC.pptx
Makalah pptMOTOR LISTRIK DAN MOTOR AC.pptxMakalah pptMOTOR LISTRIK DAN MOTOR AC.pptx
Makalah pptMOTOR LISTRIK DAN MOTOR AC.pptx
 
Pelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman Madya
Pelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman MadyaPelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman Madya
Pelaksana Lapangan Pekerjaan Bangun air Limbah Permukiman Madya
 
Jual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan Konsultasi
Jual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan KonsultasiJual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan Konsultasi
Jual Cytotec Di Batam Ori 👙082122229359👙Pusat Peluntur Kandungan Konsultasi
 
K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015
K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015
K3 INSTALASI PENYALUR PETIR PERMEN 31 TH 2015
 
Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...
Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...
Jual Obat Aborsi Batam ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik Jual Ob...
 
PPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptx
PPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptxPPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptx
PPT PELAKSANA LAPANGAN PERPIPAAN MADYA - IWAN SYAHRONI.pptx
 
Obat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai Penuh
Obat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai PenuhObat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai Penuh
Obat Aborsi Sungai Penuh 082223109953 Jual Cytotec Asli Di Sungai Penuh
 
Jual Obat Aborsi Denpasar Bali ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik...
Jual Obat Aborsi Denpasar Bali ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik...Jual Obat Aborsi Denpasar Bali ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik...
Jual Obat Aborsi Denpasar Bali ( Asli Ampuh No.1 ) 082223109953 Tempat Klinik...
 
obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...
obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...
obat aborsi Pangkal pinang Wa 082223109953 Jual obat aborsi Cytotec asli Di P...
 
Presentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptx
Presentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptxPresentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptx
Presentation Bisnis Teknologi Modern Biru & Ungu_20240429_074226_0000.pptx
 
Electrostatic Precipitator handbook manual
Electrostatic Precipitator handbook manualElectrostatic Precipitator handbook manual
Electrostatic Precipitator handbook manual
 
Obat Aborsi jakarta WA 082223109953 Jual Obat Aborsi Cytotec Asli Di jakarta
Obat Aborsi jakarta WA 082223109953  Jual Obat Aborsi Cytotec Asli Di jakartaObat Aborsi jakarta WA 082223109953  Jual Obat Aborsi Cytotec Asli Di jakarta
Obat Aborsi jakarta WA 082223109953 Jual Obat Aborsi Cytotec Asli Di jakarta
 
Bahan kuliah elemen mesin semester 2 rekayasa manufaktur
Bahan kuliah elemen mesin semester 2 rekayasa manufakturBahan kuliah elemen mesin semester 2 rekayasa manufaktur
Bahan kuliah elemen mesin semester 2 rekayasa manufaktur
 
Petunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptx
Petunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptxPetunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptx
Petunjuk teknis Pengisian Usulan Alat Kesehatan SOPHI.pptx
 
ESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptx
ESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptxESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptx
ESTIMASI BIAYA PEMELIHARAAN BANGUNAN BERDASARKAN PEDOMAN PEMELIHARAAN DAN.pptx
 

Metodologi Kerja Project Penggantian Meter Tube

  • 1. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 1 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS Dibuat Oleh : PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA PT ANSI MEGA INSTRUMENINDO Graha Makmur , Jln. Jengki Utama No. 1 Cipinang Asem Kebon Pala , Makasar- Jakarta 13650 Phone : +62 21 8087 2920 Fax : +62 21 80872921
  • 2. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 2 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS DAFTAR ISI 1. GAMBARAN UMUM PENGGANTIAN METER TUBE PKT 3 FUEL.............................................................4 1.1 LATAR BELAKANG.....................................................................................................................................4 2. LINGKUP PEKERJAAN PENGGANTIAN METER TUBE PKT 3 FUEL .............................................................4 3. PERSIAPAN DAN PELAKSANAAN PEMBUATAN DOKUMEN ADMINISTRASI PROYEK . ............................6 3.1 PEMBUATAN DOKUMEN PROYEK PENGGANTIAN METER TUBE PKT 3 FUEL:.......................................6 4. PEKERJAAN METER TUBE PKT 3 FUEL DALAM MANAJEMEN PROYEK................................................15 5. PROJECT MANAGEMENT.................................................................................................................18 6. QA / QC TEAM................................................................................................................................26 7. PROJECT PLANNING AND CONTROL ................................................................................................28 8. PROJECT ADMINISTRATION AND INFORMATION MANAGEMENT.....................................................29 9. PROJECT CONTROL ESTIMATING .....................................................................................................31 10. ENGINEERING DESIGN....................................................................................................................33 11. CONTRACT MANAGEMENT PROJECT...............................................................................................36 12. PROCUREMENT..............................................................................................................................36 12.1 MATERIAL MANAGEMENT PLAN............................................................................................................36 12.2 PURCHASING ENGINEERING...................................................................................................................36 12.3 EXPEDITING PLAN ...................................................................................................................................37 12.4 MATERIAL INSPECTION...........................................................................................................................37 13. LOGISTICS MANAGEMENT......................................................................................................................37 14. CONSTRUCTION & INSTALLATION .........................................................................................................37 14.1 PROGRAM DOKUMEN LELANG...............................................................................................................37 14.2 TEMPORARY FACILITY PLAN ...................................................................................................................37 14.3 CONSTRUCTION /INSTALLATION EXECUTION PLAN...............................................................................37 14.4 CONSTRUCTION ADMINISTRATION........................................................................................................38 14.5 FIELD ENGINEERING................................................................................................................................38 14.6 FIELD MATERIAL CONTROL .....................................................................................................................39 15. MECHANICAL COMPLETION / PRE-COMMISSIONING............................................................................39 15.1 LANGKAH KEGIATAN MECHANICAL COMPLETION.................................................................................39 15.2 PIPING COMPLETION & INSPECTION......................................................................................................39
  • 3. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 3 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 15.3 INSTRUMENTATION COMPLETION & TEST.............................................................................................40 15.4 PRE-COMMISSIONING ............................................................................................................................40 16. OPERATION.............................................................................................................................................40 17. CHANGE MANAGEMENT BASIS ..............................................................................................................41 18. RISK MANAGEMENT ...............................................................................................................................41 18.1 PROJECT RISK INDENTIFICATION ............................................................................................................41 19. QUALITY MANAGEMENT ........................................................................................................................42 19.1 AUDIT PLAN.............................................................................................................................................42 19.2 PROGRAM AUDIT....................................................................................................................................42 19.3 CORRECTION ACTION / PREVENTIVE ACTION PROGRAM......................................................................43 20. HEALTH SAFETY & ENFVIROMENTAL......................................................................................................43 20.1 HSE PHYLOSOPHY ...................................................................................................................................43 20.2 DESIGN HSE.............................................................................................................................................43 20.3 EVALUASI KEBIJAKAN HSE ......................................................................................................................43 20.4 SITE HSE...................................................................................................................................................43 20.5 KARYAWAN DAN PEKERJA......................................................................................................................44 21. PROJECT CLOSE UP – HAND OVER SERTIFICATE PACKAGE (HOP) ..........................................................45
  • 4. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 4 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 1. GAMBARAN UMUM PENGGANTIAN METER TUBE PKT 3 FUEL. 1.1 Latar Belakang PT Pertamina Gas Kalimantan Area berperan dalam menyalurkan Gas Bumi di Stasiun Kompresor Gas (SKG) Bontang Kalimantan Area kepada PT Pupuk Kalimantan Timur (PKT), khususnya untuk (PKT 3) dengan Sistem Meter Gas Orifis, 2 Stream Line peruntukan untuk Fuel Gas. Pengukuran dan Perhitungan jumlah volume Gas Bumi dengan Sistem Meter Gas Orifis sebagai dasar transaksi jual-beli gas dan penagihan Toll Fee biaya penyaluran Gas Bumi. Kondisi saat ini existing Sistem Meter Gas Orifis sudah absolute dan akan dilakukan penggantian Meter Tube Sistem Mete Gas Orifis untuk menjamin keandalan dan akurasi, atas sumber pemasukan dari hasil supply gas ke ke PT Pupuk Kaltim 3. PT Pertamina Gas Kalimantan Area akan melakukan penggantian Meter Tube PKT 3 Fuel dengan tujuan untuk mengoptimalisasi pengoperasian, pengukuran dan perhitungan serta menghasilkan tingkat keandalan, akurasi sesuai data hasil pengukuran secara online, sehingga penyaluran gas lebih terjamin kebenarannya. 1.2 Lokasi Pekerjaan Penggantian Meter Tube PKT 3 Stasiun Kompressor Gas (SKG) Bontang PT Pertamina Gas Kalimantan Area di Kawasan Industri PT Pupuk Kaltim , Bontang Utara - Kalimantan Timur (Kaltim). 2. LINGKUP PEKERJAAN PENGGANTIAN METER TUBE PKT 3 FUEL. 2.1 PT Ansi Mega Instrumenindo selaku perusahaan perakit perekayasa Sistem Alat Ukur Serah Terimna Gas Bumi sesuai SKT Migas ikut berpartisipasi dalam Proyek Penggantian Meter Meter Tube PKT 3 Fuel di PT Pertamina Gas kalimantan Area meliputi: 2.1.1. Pekerjaan Administrasi Perizinan untuk Pekerjaan Penggantian Meter Tube PKT 3 Fuel, PT Ansi Mega Instrumenindo akan melaksanakan: a. Pengurusan dokumen teknis dan persetuan untuk pelaksanaan pekerjaan. b. Melaksanakan koordinasi perizinan untuk pelaksanaan pekerjaan penggantian meter tube PKT 3 Fuel termasuk pengurusan ke Perusahaan Inspeksi (PI), Direktorat Metrologi, Direktorat Jenderal Migas pada Kementerian ESDM. c. Menyiapkan dokumen untuk melaksanakan pekerjaan sesuai RKS pada pokok pekerjaan penggantian Meter Tube PKT 3 untuk Fuel PT Pertamina Gas Kalimantan Area. d. Menyiapkan dokumen nstrument alat ukur dan perlengkapannya serta peralatan pendukung sesuai RKS. e. Menyiapkan Standar Operasional Prosedur (SOP) untuk pelaksanaan pekerjaan. f. Menyerahkan material sisa ex pekerjaan penggantian Meter Tube PKT 3 ke PT Pertamina Gas Kalimantan Area. 2.1.2. Persiapan Sumber Daya, Tenaga , Material dan Peralatan. PT Ansi Mega Instrumenindo akan menyiapkan:
  • 5. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 5 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS a. Tenaga enjinering sebagai ahli teknik dan teknisi instrumen yang sesuai kompetensi yang diperlukan. b. Menyiapkan material, peralatan, instrument alat ukur dan perlengkapannya yang diperlukan pada Gas Metering Skid PKT 3 Fuel Gas. c. Menyiapkan peralatan kerja dan kelengkapannya sesuai kebutuhan d. Menyiapkan Alat Pelindung Diri (APD) dan peralatan safety sebagai pendukung keselamatan kerja, sesuai potensi bahaya yang mungkin ada di tempat kerja . e. Menyiapkan meterial sesuai dengan spesifikasi teknis dan jumlah yang diperlukan sesuai design engineering. f. Menyiapkan sarana dan prasarana angkutan mobilisasi untuk material dan tenaga kerja sebagai pendukung pelaksanaan pekerjaan penggantian meter tube PKT 3 Fuel Gas. 2.1.3. Penyiapan Pelaksanaan pekerjaan: a. Mengacu Peraturan Keselamatan Kerja sesuai dengan Undang-undang dan peraturan tentang HSE serta berdasarkan Contractor Safety Management System (CSMS) dari PT Pertamina Gas Kalimantan Area. b. Peraturan dan ketentuan yang terkait dengan metode keselamatan kerja aman dengan menyesuaikan kondisi pekerjaan keteknikan yang akan dilaksanakan. 2.2 Pekerjaan Pokok yang harus dipenuhi sesuai Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 dan RKS. PT Ansi Mega Instrumenindo melaksanakan pekerjaan : a. Pembuatan dan persiapan serta penyelesaian dokumen Administrasi Proyek. b. Persiapan pelaksanaan pekerjaan , termasuk mobilisasi orang dan material serta peralatan kerja. c. Membuat design dan Perencanaan Teknik dan Engineering d. Pengadaan material dan peralatan sesuai dalam dokumen kontrak kerja. e. Melaksanakan Expedisi , Inspeksi dan Pengujian terhadap kontrusksi dan peralatan teknik yang terkait dengan instrumen. f. Membuat Progress Report terhadap kemajuan progress pekerjaan yang sedang berjalan dan rencana kerja. g. Mobilisasi dan Demobilisasi tenaga kerja , material dan peralatan yang dibutuhkan. h. Melaksanakan pekerjaan Fabrikasi terhadap pipespool, skid metering dan pekerjaan pipa dan tubing untuk instalasi metering. i. Pekerjaan fiskal metering untuk kalibrasi metyering sistem dan sertifikasi dari Dit Metrologi dan MIGAS. j. Melaksanakan pekerjaan Pre-Commissioning dan Commissioning untuk peralatan metering sistem PKT 3 fuel , sesuai dengan urutan dokumen Pre-Commissioning dan Commissioning yang harus disetujui oleh Pertamina Gas . k. Operational Acceptance terhadap kontinyuitas operasional sistem metering PKT 3 fuel terhadap operasional serah terima gas ke PT Pupuk Kalimantan Timur 3.
  • 6. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 6 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS l. Melaksanakan Inhouse Training terhadap Supervisor dan Operator untuk pengenalan program Operation and Maintenance terhadap metering sistem yang telah dilaksanakan pemasangannya oleh PT ANSI MEGA INSTRUMENINDO , agar supaya dalam pelaksanaan di lapangan bisa dilakukan perawatannya. m.Membuat berita acara serah terima proyek penggantian meter tube PKT 3 Fuel kepada PT Pertamina Gas , termasuk dokumen teknik , P&ID, Manual Book, Parts Catalog, MDR, Dokumen Pengelasan, serta sertikasi dari Instansi dan institusi sesuai ketentuan yang berlaku. 2.2.1 PT Ansi Mega Instrumenindo akan menyelesaikan serah terima pekerjaan proyek penggantian meter tube PKT 3 Fuel sesuai spesifikasi RKS dan data teknik engineering dengan standar, serta membuat berita acara serah terima yang akan dituangkan dalam Berita Acara Pemeriksaan Pekerjaan selesai 100% dan di tandatangani oleh pihak PT Pertamina Gas. 2.2.2 Membuat laporan dokumen teknis dan dokumen administrasi sesuai dengan kebutuhan proyek. 3. PERSIAPAN DAN PELAKSANAAN PEMBUATAN DOKUMEN ADMINISTRASI PROYEK . 3.1 PEMBUATAN DOKUMEN PROYEK PENGGANTIAN METER TUBE PKT 3 FUEL: 3.1.1 PT Ansi Mega Instrumenindo secara Mandatori akan membuat Dokumen Proyek sesuai RKS yang terkait dengan dokummen Engineering dan dokumen administrasi asli meliputi : a. Design Basis , Calculation ( Orifice calculation , piping calculation detail b. Bill Of Material, MDR ( Data Sheet, Shop test, data mill test , vendor inspection report dab sertifikasi material ) c. P & I Diagram, PFD , Isometric Drawing, System Arsitektur, General Arrangement Drawing d. Wiring & Loop drawing , Shop Drawing, Hook up drawing, Presentasi persetujuan meter ke DitJen Migas. e. S-curve & Time Table, Work procedure (civil, electrical, hydrotest, painting, NDE,FAT, SAT dan lain nya . f. Laporan fabrikasi & Instalasi (harian, mingguan, bulanan), WPS, PQR g. Sertifikat kualifikasi personel (welder,NDT), NDT & visual inspection report. h. Lesk Test dan Hydrotest Valve & Meter System i. FAT di COO (Country Of Origin) , FAT Meter System, Fat & SAT report. j. Sertifikat Metrologi & Migas. BA kalibrasi Meter System, Inspection & test plan. k. Modul Training & troubleshoting, Manual operasi dan pemeliharaan, HSE Plan. 3.1.2 PT Ansi Mega Instrumenindo secara mandatori akan mengirim semua dokumen teknik dan dokumen administrasi kepada Pertamina Gas Kalimantan Area. 3.1.3 Dokumen tersebut akan didiskusikan dan dibuat persetujuan dengan Pertamina Gas, sebelum dilakukan penjilidan kedalam odner. 3.1.4 Dokumen asli setelah disetujui akan dilakukan penjilidan dan dan diserahkan kepada Pertamina Gas dengan rincian 1(satu) jilid asli dan softcopy didalam hard disk.
  • 7. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 7 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 3.1.5 Pt ANSI MEGA INSTRUMENINDO akan menyerahkan Bukti / Berita Acara Penyerahan Dokumen Proyek kepada Pertamina Gas (asli) yang akan dilampirkan dalam invoice tagihan PT Ansi Mega Instrumenindo. 3.2 PERSIAPAN PEKERJAAN PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS. 3.2.1 PT ANSI MEGA INSTRUMENINDO akan melaksanakan survey pendahuluan ke lokasi kerja agar bisa mendapatkan data yang akurat, sehingga pada saat pelaksanaan pekerjaan tidak ada kendala. 3.2.2 PT ANSI MEGA INSTRUMENINDO , akan mengajuklan permohonan untuk pengurusan surat izin masuk, permit dan simper , simlok, kepada Pertamina Gas Kalimantan Area PKT 3 antara lain: a. Mengurus Badge Pertamina Gas dan PKT b. Mengurus SIMPER Pertamina Gas dan PKT c. Mengurus perijinan masuk , kendaraan alat angkut dan material kepada Pertamina Gas PKT 3. d. Mengurus Mandatori MCU personil yang bekerja ( Surat Keterangan Sehat untuk Pekerja) e. Surat Izin Kerja Panas/Dingin dari HSE Pertamina Gas. 3.2.3 PT Ansi Mega Instrumenindo, akan menyerahkan kepada Pertamina Gas Kalimantan Area: a. Copy SPB (Surat Perjanjian Borongan) b. 2(dua) buah Map Filling System empat lubang. c. 1(satu) buah Log Book ditempatkan di lokasi pekerjaan untuk mencatata seluruh aktifitas kegiatan harian selama dikerjakan. 3.2.4 PT Ansi Mega Instrumenindo, akan mengikuti hasil dan melaksanakan Kick Off Meeting dengan Pertamina Gas setelah diterbitkan dan diterima PO/SPB untuk membahas: a. Izin Masuk Kendaraan , Material dan Tenaga Kerja ke Site Plant Pupuk Kaltim Bontang b. Mengurus Surat Izin Kerja / Permit To Work di PT Pertamina Gas Area Kalimantan c. JHSEA (Job Health Safety Analysis) d. SOP (Standard Operating Procedure) e. Rencana Jadwal Pelaksanaan (S- Curve) f. Teknis Pelaksanaan Pekerjaan g. Audit Pre-Job Activity (CSMS) 3.2.5 PT Ansi Mega Instrumenindo Akan mematuhi dan melakukan kalkulasi data detail engineering design sesuai dengan spesifikasi yang di tetapkan Pertamina Gas, peraturan perundang undangan yang berlaku dan standard teknik . Hasil kalkulasi engineering akan diserahkan kepada pengawas pekerjaan, yaitu: a. Inspection & Test Plan b. Design basis c. Detail Drawing d. Bill Of Material e. P & I Diagram f. System Architecture g. General Arrangement drawing h. S- curve & time table i. Jadwal rencana kerja (Bar chart) j. Prosedur kerja k. Calculation (Orifice Calculation & piping calculation). l. Dokumen lainnya terkait dengan pekerjaan sesuai RKS.
  • 8. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 8 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 3.3 Design Dan Perencanaan Teknik Instrumen 3.3.1 PT Ansi Mega Instrumenindo, membuat Detail Design piping dan mekanikal, elektrikal serta instrument sesuai dengan engineering standard sesuai dengan standard keteknikan Migas dan Pertamina untuk menentukan spesifikasi peralatan dan material. 3.3.2 PT Ansi Mega Instrumenindo, membuat Detail Design piping dan mekanikal, elektrikal serta instrument sesuai dengan engineering standard sesuai dengan standard keteknikan Migas dan Pertamina untuk menentukan spesifikasi peralatan dan material. 3.3.3 Detail Design piping, mekanikal, elektrical dan instrument mengikuti standar Migas dan Pertamina dan selanjutnya diajukan untuk mendapat persetujuan sesuai dengan spesifikasi peralatan dan material yang dibutuhkan 3.3.4 Membuat design development detail dari mekanikal , piping, elektrikal, instrumen dan fabrikasi yang disesuaikan dengan persiapan pekerjan instalasi ulang field transmitter , dan flow recorder mengikuti permintaan Pertamina Gas. 3.3.5 Menyiapkan dan membuat gambar detail tentang sipil, mekanikal, & piping, elektrikal, instrumen termasuk dalam P&ID, sistem arsitektur, general arrangement , isometric drawing , wiring line diagram, lay out area, shop drawing, hook up memakai software AutoCad. 3.3.6 PT Ansi Mega Instrumenindo, akan membuata design dan gambar detail teknik , sesuai dengan spesifikasi teknik dan diajukan kepada Pertamina Gas untuk mendapat persetujuan. 3.3.7 Membuat detail data spesifikasi kebutuhan material (BOQ - Bill Of Quality), termasuk kelengkapan Manufacturer Data Report (MDR) dan Certificate of Compliance. 3.3.8 Melaksanakan koordinasi dengan Perusahaan Inspeksi (PI), untuk review design , persetujuan design , untuk mengajukan permohonan Persetujuan dan Penggunaan menjadi Persetujuan Layak Operasi dari Dirjen MIGAS. 3.4 Pengadaan Material 3.4.1 Material dan kelengkapannya: PT Ansi Mega Instrumenindo, akanmelaksanakan kebutuhan materuial dan peralatan untuk proyek Penggantian Meter Tube PKT 3 Fuel PT Pertamina Gas Kalimantan Area, sesuai dengan spesifikasi pengadaan material yang telah disejui oleh Pertamina Gas dan MIGAS. 3.4.1.1 PT Ansi Mega Instrumenindo, akan melengkapi tanggung jawabnya untuk melengkapi semua pengadaan dan pembelian material untuk peralatan Penggantian Meter Tube PKT 3 Fuel sesuai dengan dokumen RKS. 3.4.1.2 Barang import PT Ansi Mega Instrumenindo, akan mengikuti semua prosedur negara untuk bea masuk dan cukai, dan jasa pelabuhan serta pengapalan serti biaya untuk pengiriman ke lokasi kerja. 3.4.1.3 Material untuk proyek Penggantian Meter Tube PKT 3 Fuel Pertamina Gas, semua dalam kondisi baru , sesuai dengan dokumen yang dapat dipertanggung jawabkan, dan supply material akan menjaga jadwal pekerjaan di lapangan . 3.4.1.4 Semua material yang dibeli oleh PT Ansi Mega Instrumenindo sepenuhnya dilindungi Jaminan Pabrikan ( manufacturing waranty )
  • 9. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 9 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 3.4.2 Engineering Equipment. 3.4.2.1 Untuk Engineering Equipment PT Ansi Mega Instrumenindo, akan mematuhi aturan pertamina gas termasuk Approved Manufacture List / Vendor List Pertamina Gas. a. PT Ansi Mega Instrumenindo, akan mengajukan terlebih dahulu untuk menyertakan Pertamina Gas dalam paket pembelian material termasuk data, spesifikasi, kalkulasi, data sheet, engineering drawing, yang direkomendasi oleh vendor untuk start up dan operasi. b. PT Ansi Mega Instrumenindo, mengajukan review paket ini kepada Pertamina Gas untuk meyakinkan bahwa peralatan yang diajukan sesuai dengan standar dan spesifikasi proyek untuk disetujui dan dilakukan pelaksanan pembelian . 3.4.2.2 PT Ansi Mega Instrumenindo, akan menyerahkan dokumen engineering equipment dilengkapi dengan bukti yang menyatakan bahwa barang bukti sesuai dengan spesifikasi kepada Pertamina Gas termasuk: a. Shop Drawing dan Fabrication Drawing detail by detail. b. Prosedur rinci pengelasan, hot forming, cold forming dan sop lain terkait fabrikasi. 3.5 EXPEDISI, INSPEKSI DAN PENGUJIAN. 3.5.1 PT Ansi Mega Instrumenindo, akan menyerahkan jadwal kegiatan pengiriman expedisi barang untuk pelaksanaan Penggantian Meter Tube PKT 3 Fuel. 3.5.2 PT Ansi Mega Instrumenindo, akan mengajukan pormohonan Inspection Test Plan (ITP) untuk dilakukan persetujuan oleh Pertamina Gas . 3.5.3 PT Ansi Mega Instrumenindo, akan menyerahkan jadwal kerja untuk point point penting inspeksi pada enineering equipment untuk bersama vendor mengatur hold point., sampai semua persyaratan terpenuhi. 3.5.4 PT Ansi Mega Instrumenindo, akan melaksanakan sesuai hasil inspeksi dari Pertamina Gas dan pihak lain yang terkait, termasuk peralatan , dan akan bersama sama melakukan pengujian di Workshop / Fabrikator untuk Metering Skid. 3.5.5 Pelaksanaan pengetesan di pabrikasi untuk FAT (Factory Aceptance Test) oriffice fitting , segala akomodasi akan disediakan. 3.6 MOBILISASI DAN DEMOBILISASI 3.6.1 Melaksanakan mobilisasi dan demobilisasi peralatan kerja, tenaga kerja dan material kerja untuk pekerjaan Penggantian Meter Tube PKT 3 Fuel di lokasi SKG Bontang Kalimantan Area. 3.6.2 Melaksanakan pekerjaan paking material dan material pelindung untuk Meter Tube dan peralatan instrumen yang akan di mobilisasi ke SKG Bontang, agar supaya Meter Tube tidak rusak, cacat fisik, deformasi dan cacat painting. 3.6.3 Inventarisasi alat ukur dan perlengkapannya (Sistem Meter Gas Orifis) a. Melaksanakan sesuai dengan daftar peralatan (Check List). b. Menyiapkan dan melengkapi surat jalan serta dokumen teknis lainnya. c. Menyiapkan transportasi darat dan laut dari Jasa Angkutan. 3.6.4 Persiapan Kedatangan Barang di Lapangan. Persiapan Permit To Work a. Melaksanakan koordinasi dengan Petamina Gas dan PKT3 di lapangan b. Melaksanakan pekerjan lifting plan sesuai SOP.
  • 10. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 10 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS c. Penyiapan alat bantu, Crane yang sesuai Tonage d. Penyiapan Lokasi tempat penurunan material e. Mengamankan dan sterilisasi terhadap lokasi kerja f. Membuat Dokumentasi sesuai dengan kegiatan. g. Membuat Berita Acara sesuai kegiatan. 3.7 Pembongkaran Metering Sistem PKT 3 Fuel Existing. 3.7.1 Persiapan Permit To Work a. Melaksanakan koordinasi dengan Pertamina Gas dan PKT 3 Fuel. b. Melaksanakan pekerjaan pembongkaran sesuai SOP. c. Menyiapkan tenaga kerja , ahli teknik dan teknisi d. Menyiapkan perengkapan kerja , safety plan dan alat bantu kerja aman . e. Mensterilkan tempat kerja dan rambu rambu keselamatan kerja. 3.7.2 Pelaksanaan Pembongkaran Meter Tube PKT 3 Fuel Existing a. Pembongkaran platform tangga diatas tube meter existing. b. Pembongkaran valve SOV dan meter tube existing (2x8” dan 4”) c. Memindahkan meter tube existing ke stockyard Pertamina Gas. d. Melaksanakan disconnect transmitter dan chart recorder existing. 3.7.3 Fabrikasi dan Kontruksi Meter Tube Pelaksanaan Fabrikasi dan Kontruksi a. Menyiapkan material kebutuhan material sesuai dengan spesifikasi dan kebutuhan, termasuk plat orifis sesuai dengan spesifikasi teknis perhitungannya . b. Melakukan pemasangan instalasi sesuai dengan kebutuhan PKT 3 Fuel menjadi 2 Stream (2 x 8”) sesuai dengan spesifikasi Pertamina Gas. c. Memastikan untuk kedua stream memiliki Flow Profiller, Isolation valve, Remote Operating Valve (ROV), Daniel Senior Orifice Fitting (Dual Chamber), d. Melaksanakan pekerjaan pemotongan dan bavel pipa 8” (PKT 3 Fuel) sesuai dengan RKS . e. Pengelasan pipa spool dan sambungan fitting menggunakan line up clamp 8” dengan posisi sejajar. f. Pekerja Las bersertifikasi Migas Klasifikasi 6G sesuai dengan RKS termasuk pengelasannya. g. Pekerjaan Honing pada meter tube sesuai dengan syarat dan standard AGA h. Melaksanakan re-fabrikasi frame transmitter & recorder i. Pengujian radiograph dan penetran pada setiap joint pengelasan. j. Melaksanakan pekerjaan stand blasting dan painting setelah semua join las lulus radiography dan hydrostastis test. k. Melaksanakan hydrotest sistem meter yang telah di fabrikasi sebelum dikirim ke lokasi kerja. 3.7.4 Melaksanakan pekerjaan mekanikal , piping , elektrikal dan instrumen sesuai dengan detail desain yang telah disetujui oleh Pertamina Gas dengan data : a. Box transmitter & recorder , cable tray, pipa air instrument, junction box, recorder . b. Ecer pipa , cutting, beveling , fit up & welding spool pipa dan kelengkapannya. c. Memasang spool pipa air instrument dengan tie in sesuai dengan drawing. d. Pemasangan kabel junction box dan kabel sinyal sesuai drawing. e. Pasang cabel tray dengan struktur / support pipa sesuai dengan drawing.
  • 11. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 11 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS f. Membuat galian , dan pasang kabel bonding kabel grounding eksisting (D003), ke arah support pipa , tiang lampu dan skid metering standard BS-7430 resistansi max 5 ohm. g. Melaksanakan pekerjaan instalasi proses control buka tutup ROV di control room (Panel Eksisting) h. Re Programing dan integrasi ke Gas Flowcom eksisting dan pengecatan sesuai permintaan Pertamina Gas. i. Pemasangan tagging dan penomoran dari stainless steel untuk Junction box, transmitter, pressure dan temperature indicator. j. Proses Pekerjaan Pengecatan :  Pekerjaan Pembersihan material dan Metal Finish & Primer coating.  Melaksanakan pekerjaan pembersihan permukaan pipa , dari minyak debu dan karat, dengan sand blasting sampai permukaan sesuai standard.  Permukaan dibersihan dengan bahan kimia , dilapis permukaan dan di dikeringkan.  Melaksanakan pelapisan primer coating dengan campuran thiner (20%), solod min 82%dan ketebalan 150-200 micron.  Pekerjaan Intermediate Coating.  Membersihkan permukaan pipa setelah primer coating dari minyak , kotoran dan debu.  Melaksanakan pelapisan intermediate coating dengan campuran thiner (20%), solod min 82%dan ketebalan 150-200 micron.  Pekercaan Top Coating  Menyiapkan finish paint /coating polyurethane dan thiner (20%) minimul solid 50%  Spray Pertama : Menspray permukaan pipa dengan cat warna kuning sampai rata , dan ditunggu sampai kering.  Spray Kedua : Menspray semua permukaan pipa dengan cat warna kuning sampai rata dengan ketebalan 50 – 60 micron 3.7.5 Memasang instalasi meter tube dabn kelengkapannya : a. Melaksanakan pemasangan meter tube , flow recorder (chart recorder), dan kelengkapan peralatan tambahan. b. Pasang valve 4” dan blind flange dan packing serta baut pengikat di setiap ujung valve. c. Membongkar dan memasang field transmitter tube PKT 3 Fuel , yang terdisi dari :  Pressure Transmitter, Differential Pressure Transmitter, Temperature Transmitter.  Pressure Gauge, Temperature Indicator  Tubing ,Connector, fitting d. Tagging Instrumentasi dan tanda panah arah jalur gas mengalir pada pipa dan spool. e. Pasang kabel transmitter dan field transmitter ke junction box, pasang cable gland , cable shroud, tray kabel,. f. Instal dan pasang integrasi sistem baru dengan sistem eksisting sesuai standard Migas.
  • 12. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 12 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS g. Melaksanakan pekerjaan purging gas N2 pada seluruh sistem baru sebelum gas in h. Inspeksi dan kontrol seluruh komponen sambungan sistem pipa dan sistem meter terpasang dengan sempurna. i. Menyiapkan checklist dan mengajukan kepada Pertamina Gas untuk persetujuan . j. Bersama Pertamina Gas melakukan witness SAT di Stasiun Kompresor Bontang k. Melaksaanakan pembersihan limbah bekas pekerjaan di area kerja PKT 3 Fuel, menyipakan peralatan tempat limbah/ sampah. 3.8 PEKERJAAN KALIBRASI DAN SERTIFIKASI METER TUBE PKT 3 FUEL. a. Melaksanakan pekerjaan FAT , SAT/SIT Service Installation dengan petugas PI , MIGAS & Metrologi dan Pertamina Gas. b. Mengurus Surat Ijin Penggunaan Sistem Alat Ukur Meter Gas Orifice dari MIGAS da melengkapi dokumen lainnya yang terkait dengan surat ijin MIGAS. c. Melaksanakan kalibrasi sistem Meter Gas ( Transmitter, Flow Recorder (Chart recorder), flow comp dan kelengkapan instrumen lainnya disaksikan oleh petugas PI , Dit Metrologi , Dit.Migas, dan Pertamina Gas. d. Melaksanakan pengaturan dan akomodasi Ditjen Migas , Ditjen Metrologi dalam hal ikut menyaksikan kalibrasi sistem Meter Gas. e. Semua perlatan kalibrasi telah bersertifikat yang masih berlaku, untuk melaksanakan kalibrasi Meter Gas. f. Pelaksanaan kalibrasi disaksikan oleh.  Petugas PI  Petugas Dir. Metrologi  Petugas Dit. Migas  Pertamina Gas  Shipper  Konsumen g. Membuat Berita Acara pelaksanaan kalibrasi , yang disaksikan oleh semua petugas yang terkadung dalam ayat 3.8 point f. h. Menyerahkan sertifikat izin penggunaan Meter Gas paling lambat 1 (satu) bulan setelah pelaksanaan kalibrasi. 3.9 PENGUJIAN 3.9.1 Pengajukan prosedur radiography kepada pengawas Pertamina Gas, dan pelaksanaan NDT pengelasan pipa adalah Radiography Test 100% , disaksikan oleh petugas Pertamina Gas. Bila ada cacat pengelasan dilakukan perbaikan disaksikan oleh QC & HSE Pertamina Gas dan pihak ketiga yang direkomendasi oleh Dit Jen Migas serta ada persetujuanb dari Pertamina Gas. 3.9.2 Hidrotest. a. Menyerahkan SOP Hydrostatis test b. Melaksanakan pengujian hydrostatis test pada valve dan meter tube. c. Melaksanakan flushing pipa sebelum dilaksanakan hydrostatis test. d. Menyiapkan air yang bersih dari kotoran dan kimia, minyak dan mengajukan bukti sertikat uji air bersih dari Laboratorium bersertifikat KAN.
  • 13. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 13 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS e. Pelaksanaan test secara bertahan denga pressure test + 1,5 x Max Allowable Operating Pressure (MAOP). f. Hasil hydrotest dibuatkan berita acara yang telah disetujui oleh Pertamian Gas, dengan melampiri chart barton g. Menyiapkan peralatan hydrotest :  Pompa pengisian  Pompa Tekan  Pressure Gauge  Pressure recorder / chart barton yang masih berlaku masa umur sertifikatnya.  Peralatan pendukung , dan alat bantu kerja aman , line baricade.  Mengajukan pemeriksaan peralatan hidrostatik sebelum dipergunakan kepa QC - HSE Pertamina Gas.  Melaksanakan cleaning sisa air yang masih tertinggal , dan pipa dipastikan bersih dan kering.  Melaksanakan commissioning / start up untuk memastikan sistem pipa dan peralatan bekerja dengan baik di dampingi oleh Pertamina Gas 3.9.3 Purging. Melaksanakan pekerjaan purging pada pipa , baru kemudian dapat dalakukan pengisisn gas secara bertahap sambil membuang nitrogen , agar pipa siap dialiri gas. 3.9.4 Melaksanakan inspeksi secara menyeluruh terhadap fungsi dan saran penunjang pada peralatan meter. 3.9.5 Melaksanakan function test bersama Pertamina Gas untuk semua peralatan dan aksesories sistem metering gas. 3.9.6 Memastikan bahwa function test peralatan metering gas berjalan dengan baik dan dapat digunakan untuk mengukur gas yang mengalir . 3.9.7 Menyerahkan prosedur commissioning dan mengajukan persetujuan kepada Pertamina Gas. 3.9.8 Menyerahkan semua dokumen yang terkait dengan para pihak Dit Metrologi, Dit. Migas untuk menyetujui dokumen dan berita acra penggunaan meter gas sebagai meter custody. 3.10 PRECOMMISSIONING DAN COMMISSIONING. 3.10.1 Precommissioning Melaksanakan precommissioning dengan melengkapi persyaratan : a. Pekerjaan Engineering.  Menyiapkan As- Build Drawing .  Menyiapkan Dokumen Engineering b. Pekerjaan Piping  Telah melaksanakan pemasangan seluruh system perpipaan sesuai dengan P&ID.  Telah selesai melaksanakan hydrotest dan flusing , Purging N2  Telah menyelesaikan pekerjaan pengecatan / coating , marking pipa.  Menutup dan merapihkan semua galian pipa . c. Pekerjaan Mekanikal.  Telah menyerahkan sertifikat dari manufacture untuk Bal Valve dan peralatan lainnya.
  • 14. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 14 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS  Bal Valve dan peralatan lainnya sudah terpasang sesuai dengan P&ID.  Menyerahkan sertifikat pengujian untuk Material dan peralatan (Ball Valve, dll).  Telah melaksanakan hydrotest  Telah menyelesaikan pekerjaan painting / coating.  Telah menyiapkan suku cadang untuk commissioning apa bila diperlukan .  Menyiapkan peralatan house keeping untuk area cleaning. d. Pekerjaan Elektrikal.  Menyerahkan pekerjaan listrik yang sudah diuji oleh QC-HSE Pertamina Gas, sesuai dengan spesifikasi yang telah ditentukan oleh Pertamina Gas.  Menyerahkan copy berita acara hasil uji pekerjaan listrik yang telah disetujui oleh Pertamina Gas. e. Pekerjaan Instrument.  Menyerahkan hasil pemasangan system instrumen dan kontrol yang sudah dikalibrasi, di uji dan diterima oleh Pertamina Gas,  Sudah melaksanakan pemeriksaan loop dan fungsi dari peralatan instrumen, dan hasil uji yang telah diterima oleh Pertamina Gas. f. Pekerjan Sistem Meter Gas Orifice.  Menyerahkan hasil pekerjaan Sistem metering sesuai dengan P&ID dan Drawing , dan telah dilakukan pengujian kalibrasi meter oleh Dir Metrologi dan Dit Migas , termasuk hydrotest dan leak test 3.10.2 Commissioning a. Menyerahkan Prosedure pelaksanaan commissioning yang telah disetujui oleh Pertamina Gas b. Memastikan untuk semua jalur pipa dari tie-in sampai metering sudah terisi gas. c. Melaksanakan inspeksi semua keselamatan system safety berfungsi dengan baik dan benar. d. Menyiapkan ahli teknik dan teknisi untuk pelaksanaan commissioning e. Pelaksanaan commissioning dengan mengopearsikan packaging metering selama 3 (tiga) hari tanpa kegagalan operasi dan akurasi meter terjaga max error 1%. f. Setelah dinyatakan lulus commissioning Pertamina Gas akan menerbitkan Certificate Of Commissioning. 3.11 OPERATIONAL ACCEPTANCE . Pelaksanaan kegiatan perawatan fasilitas siap dioperasikan oleh Pertamina Gas selama 90 (sembilan Puluh) hari kalender secara kontinyu dan tidak ada pengerjan yang salah. 3.12 TRAINING SUPERVISOR DAN OPERATOR 3.12.1 Training Operasi Peralatan Meter 3.12.2 Menyiapkan jadwal pelaksanaan training, sylabus training , modul training. Mengajukan rencana kerja pelaksanaan training operasi kepada Pertamina Gas untuk dilakukan persetujuan, untuk mengajukan permohonan akan dilakukan satu minggu sebelum pelaksanaan training operasi. 3.12.3 Materi Training Operasi Meluiputi :
  • 15. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 15 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS a. Menyiapkan materi training hard copy dan soft copy. b. Menyiapkan materi dan modul training untuk semua peserta termasuk konsumsi training sesuai kebutuhan. c. Fasilitas peralatan training Gedung dan Ruang training akan dipersiapkan oleh Pertamina Gas. d. Pelaksanaan training dilaksanakan dalam waktu satu hari serta onhand training mlihat langsung peralatan meter gas yang baru terpasang untuk Meter Tube PKT 3 Fuel. e. Melatih stimulasi peralatan intrumentasi meter tube PKT 3 Fuel. 3.12.4 Materi Training Pemeliharaan dan troubleshooting pada GFC. a. Membuat Checklist peralatan yang kemungkinannya bisa trouble. b. Latihan Animasi trouble shooting meter tube PKT 3 Fuel. c. Melatih tanya jawanb dari daftar list Frequently Asked Question , dari contoh beberapa masalah yang pernah terjadi . d. Menyiapkan hardcopy dan konsumsi sesuai dengan kebutuhannya. e. Meminjam Ruang training dari Pertamina Gas termasuk peralatan training. 3.13 GARANSI MASA PEMELIHARAAN METER TUBE PKT 3 FUEL . a. Masa garansi dari PT Ansi Mega Instrumenindo terhadap semua peralatan selama tiga bulan setelah Certificate of Commissioning diterima dari Pertamina Gas. b. Melaksanakan perawatan dan pemeliharaan selama tiga bulan. 4. PEKERJAAN METER TUBE PKT 3 FUEL DALAM MANAJEMEN PROYEK PT ANSI MEGA INSTRUMENINDO akan melengkapi kegiatan Penggantian Meter Tube PKT 3 Fuel dengan melibatkan organisasi dan manajemen proyek untuk mensukseskan pekerjaan di SKG Bontang Pertamina Gas Kalimantan Area , agar pelaksanaan kontrak kerja dalam bidang Engineering , Procurement, Fabrication , Installation , Pre-Commissioning, Commissioning, Certification,Calibration, Testing, Start-Up dan Hand Over pekerjaan penggantian meter tube PKT 3 Fuel serta kelengkapannya , dengan lingkup kerja adalah : 1. Manajemen Proyek 2. Engineering 3. Material Procurement and Supply 4. Construction & Installation Work 5. Transportasi Material 6. Fabrikasi Pipa Spoll dan kelengkapannya 7. Hook-Up, Installation and Integration 8. Pre-Commissioning, Commissioning dan Start-Up 9. Sertifikasi ( Migas , Metrologi dan kelengkapan sertifikasi peralatan) 10. Training dan Pelatihan 11. Dokumentasi dan As-Build Drawing 4.1 MISI DAN VISI DALAM PROJECT PENGGANTIAN METER TUBE PKT 3 FUEL PT. Pertamina Gas Kalimantan Area melaksanakan kegiatan untuk penggantian meter tube PKT 3 Fuel untuk menyalurkan gas PT Pupuk Kalimantan Timur (“PKT3”), penyaluran gas ke PKT 3 dihitung
  • 16. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 16 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS dengan Sistem Meter yang terdiri dari 2 line yaitu line PKT 3 Proses dan PKT 3 Fuel. Kondisi eksisting Metering PKT 3 sudah abnormal sehingga kesulitan melakukan perawatan. Oleh karenanya PT Ansi Mega Instrumenindo sebagai perakit perekayasa dalam bidang instrument Migas , ikut berpartisipasi dalam pekerjaan penggantian Meter Tube PKT 3 Fuel di PT Pertamina Gas Kalimantan Area. Kesempatan ini membuktikan bahwa kami siap untuk melaksanakan pekerjaan ini dan akan mengikuti segala peraturan yang terkandung dalam dokumen tender Rencana Kerja dan Syarat-Syarat (RKS) Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018. 4.1.1 Tujuan pekerjaan Pekerjaan Penggantian Meter Tube PKT 3 Fuel a. Menjamin bahwa pekerjaan tersebut dari mulai start sampai dengan project hand over memenuhi klasifikasi penjabaran dari dokumen lelang dari mulai pekerjaan persiapan , design engineering , fabrikasi dan installasi memenuhi standar yang berlaku yang diharapkan dalam dokumen lelang Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 dan hasil pekerjaan bisa di aplikasikan sesuai dengan spesifikai teknis b. Menjamin bahwa semua material/bahan, tenaga kerja, peralatan dan metode pelaksanaan pekerjaan intalasi sesuai dengan standard/code, Peraturan Pemerintah. (Metrologi & MIGAS) c. Menjamin bahwa pekerjaan Penggantian Meter Tube PKT 3 Fuel ini sesuai dengan spesifikasi Teknis. d. Menjamin bahwa rencana kerja Engineering , Dokumen , Purchasing Material , Installation, Fabrikasi , sesuai dengan rencana kerja. 4.1.2 Dokumen Teknis dan Sertifikasi a. Menjamin bahwa seluruh Dokumen Engineering telah memenuhi Standard/Code yang berlaku, memenuhi ketentuan/peraturan pemerintah (Metrologi & MIGAS), memenuhi stan- dard/spesifikasi yang diharapkan Pertamina Gas dapat diaplikasikan sesuai spesifikasi teknis b. Menjamin bahwa semua material/bahan , tenaga kerja, peralatan dan metode pelaksanaan pekerjaann instalasi sesuai dengan standard / code dokumen c. Menjamin bahwa rencana kerja Engineering , Dokumen , Purchasing Material , Installation, Fabrikasi , sesuai dengan rencana kerja dan berkualitas d. Ahli Teknik yang akan mengerjakan sesuai dengan kompetensi bersertifikat yang dimiliki di bidang Instrumentasi, baik bidang Mechanical , Electrical e. Kelengkapan data yang tersusun dan terprogram dalam folder dokumen Penggantian Meter Tube PKT 3 Fuel , meliputi semua Dokumen Teknis dan Administratip terkait dengan Engineering, Purchasing , Electrical , Instrument , Mechanical dan Data Vendor List serta Lampiran dokumen Engineering f. Calculations,As Build Drawing,Design Approval Document,Inspection & Test Plan g. Material Sertificate, Catalog, Operation & Maintenance Manual,Installation Manual h. WPS & PQR/ Welding Performance Qualification,Welding Log Book, Welder Sertificates i. Welding Test Report, NDT Report, Painting Procedure and Report, Visual Inspection Report, j. Functional Test Report ( Hydrotest/Pneumatic Leak Report,FAT Report) k. Dimensional Check Report, Calibration Certificate, Migas / Metrologi Certificate l. Waranty Statement Letter ( Masa Pemeliharaan) m. Technical Compliance Letter
  • 17. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 17 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS n. Mechanical Test Data and Certificate o. Electrical Test Data p. Hydrotest Data Certificates q. Performance Test Data Certificate ( SAT, SIT,FAT ) 4.2 Strategi dan Pelaksanaan Pekerjaan Untuk mensukseskan strategi prlaksanaan pekerjaan ada beberapa tahapan yang akan dilaksanakan untuk Penggantian Meter Tube PKT 3 Fuel termasuk interfacing sistem alat kontrol dengan tahapan sebagai berikut yaitu : a. Klarifikasi Dokumen teknis dan engineering pekerjaan sesuai dokumen RKS Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018. b. Design Engineering & P&ID Drawing Instrument c. Project Planning & Scheduling pelaksanaan rencana kegiatan d. Reporting , Daily , Weekly, materi dokumen untuk meeting rutin e. Membuat Penawaran harga sesuai BQ f. Negoisasi harga penawaran g. Pemeriksaan HSE dan evaluasi perusahaan h. Evaluasi kesiapan ahli teknik , teknisi dan staf pendukung proyek administrasi i. Pemahami dokumen Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 j. Membuat Schedule pelaksanaan kerja sesuai kontrak kerja 4.3 Mempersiapkan dan menangani sesuai bidang Engineering a. Engineering , Pre-Fabrication, Pengujian dan instalasi skid sistem alat ukur, Control valve, valve , dan kelengkapannya b. Melengkapi alat ukur , sensor , transmitter tekanan dan temperature dari sistem alat ukur c. Pasang instalasi flow computerdan setting integrasi dengan PCS dan ESD d. Sertifikasi Kalibrasi Sistem Alat Ukur Semi Custody dan Master Meter (Migas /Metrologi) Pekerjaan Pipa dan Mekanikal : a. Memasang instalasi kebutuhan setting untuk kelengkapan peralatan instrumen b. Memasang Instalasi kebutuhan Tie-in, pembongkaran dan relokasi fasilitas dengan aman dan tidak ada gangguan shutdown Pekerjaan Listrik a. Supply material kelistrikan untuk instalasi Penggantian Meter Tube PKT 3 Fuel. b. Pasang instalasi tie-in dan fasilitas UPS , Power distribusi tanpa ada gangguan. Pekerjaan Instalasi Meter a. Pasang struktur instalasi untuk Penggantian Meter Tube PKT 3 Fuel. b. Bongkar pasang instalasi eksisting peralatan meter gas Pekerjaan Kontrol Meter a. Pasang instalasi transmisi data dari Flow Computer dan sistem DCS b. Pekerjaan HMI untuk akomodasi sistem Control Meter Gas c. Pasang material untuk kebutuhan sistem meter gas 4.4 Biaya Proyek dan Rencana Kerja Untuk mendukung investasi untuk proyek ini , akan dilakukan langkah penghematan dana melalui , dan analisa kebutuhan budget dan rencana kerja yang akan dilaksanakan:
  • 18. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 18 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS a. Project Master Schedule untuk proyek ini diperkirakan sampai 200 hari kerja , untuk procurement material dibutuhkan skitar 160 hari kerja , paralel dengan menunggu material , pekerjaan pipespool work bisa sambil dikerjakan, b. Works Break Down Structure ( WBS) , harus dibreakdown lebih rinci , agar supaya detail, step pekerjaan bisa llebih jelas baik secara budget dan rencana kerja c. Antisipasi terhadap procurement procudure , harus bertahap , sehingga tidak salah serial number , tidak salah spesifikasi , dan rencana kedatangan material jelas 160 hari d. Membuat breakdown biaya proyek , perkiraan biaya dan membuat estimasi biaya yang akurat Baseline proyek schedule harus paralel dengan monitoring rencana dan pelaksanaan kerja a. Bertanggung jawab terhadap perhitungan , Cost Variant(CV), Schedule Variant(SV), Cost Performance Index (CPI), Schedule Performance Index (SPI) b. Membuat kalkukasi dasar estimasi , Estimate At Completion (EAC) dan Estimate To Completion (ETC), sehingga analisa biaya lebih tajam. 5. PROJECT MANAGEMENT Struktur Organisai : Lihat Lampiran No1 5.1 Tugas Dan Tanggung Jawab Project Manager a Bertanggung jawab terhadap manajemen proyek Penggantian Meter Tube PKT 3 Fuel Meter , pada project Pertamina Gas Kalimantan Area, baik dari segi, Teknis, administrasi, konsolidasi dan meting dengan PT Pertamina Gas . b Melaksanakan koordinasi dengan All staf dan pekerjan internal dan external dalam rangka keselamatan , pelaksanaan pekerjan Penggantian Meter Tube PKT 3 Fuel di Pertamina Gas. c Membuat distribusi tugas dan pengawasan kepada masing masing pekerja serta membuat strategi yang tepat untuk rencana kerja, anggaran , serta fokus pada bidang pekerjaan Instrumentasi yang dipertanggung jawabkan d Analisa aspek kontruksi dan pekerjaan lapangan sesuai rencana kerja serta memecah-kan problem solving yang dihadapi, untuk menjaga kualitas pekerjaan, termasuk melaporkan hasil rutin progres pencapaian progres dan kualitas kerja kontruksi & instrumentasi 5.2 Tugas Dan Tanggung Jawab Engineering Lead a. Melaksanakan kerja team dengan berbagai engineer b. Membuat dan mengkontrol Design Architecture Instrument c. Memuat Design Engineering Instrument dan persiapan termasuk code /standard d. Control of Quality terhadap instrument dan document kelengkapannya termasuk engineering documents PML & AML , Spesifikasi Document :  General Arrangement Document  QA / QC Document  Mechanical & Piping Document  Electrical Document  Instrumentation Document  Construction Document
  • 19. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 19 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS  General Arrangement Report  Vendor Correspondency  Process Engineering  Instrument Engineering  Electrical Engineering  Piping Engineering  Calculation  Drawing  Electrical  Report Calculation  Drawing List Cable  Lampiran Tambahan 5.3 Tugas Dan Tanggung Jawab Construction Lead a. Pengawasi proyek konstruksi langsung dari konsepsi teknis management sampai PHO b. Mereview perjalanan proyek by detail untuk menjadwalkan material dan tenaga kerjaserta memperkirakan biaya c. Mengawasi kontruksi dan memantau keselamatan kontruksi dan keselamatan pelaksanaan kerja di lapangan d. Mengkoordinasikan dan mengarahkan pekerja konstruksi dan subkontraktor sesuai dengan detail pekerjaannya e. Menggunakan peralatan , bahan dan peralatan dan layak dipakai. f. Memenuhi spesifikasi kontrak kerja sesuai dengan dokumen Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 g. Progress Report harian , mingguan dan bulanan dimonitor h. Menyiapkan laporan kontruksi internal dan eksternal yang berkaitan dengan status pekerjaan i. Merencanakan pekerjaan untuk mencegah kesalahan kontruksi dan menyelesaikan masalah timbul dilapangan j. Menganalisis, mengelola dan mengurangi risiko akibat kerja Penggantian Meter Tube PKT 3 Fuel k. Melaksanakan standar konstruksi sesuai kualitas dan management teknik konstruksi 5.4 Tugas Dan Tanggung Jawab HSE Lead a. Melaksanakan keselamatan proses untuk pekerjaan Penggantian Meter Tube PKT 3 Fuel. b. Mengamankan Potensi bahaya dengan kegiatan :  Risk assessment facilitation  Hazard and Operability Study (HAZOP)  Safety Case / Quantitative Risk Assessment (QRA) c. Tinjauan keselamatan proyek seperti klasifikasi terhadap bahaya listrik, gambar zona bahaya kebakaran, penghitungan keselamatan , studi penentuan lokasi fasilitas aman. 5.5 Instrumentation And Control Engineer a. Bertanggung Jawab pada instrumentasi termasuk P&ID, Perhitungan, pengadaan, design kabel untuk Installasi Metering System Skid, pra-commissioning, commissioning dan start- up , training dan perawatan
  • 20. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 20 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS b. Bertanggung jawab pada system control , termasuk , valves, flow,level, temperature, pressure, safety c. Bertanggung jawab pada pengujian , FAT, SAT, SIT, Pra-Commissioning, Commissioning dan Start-up d. Mampu mengoperasikan peralatan Fieldbus, Profibus, Modbus, untuk data metering system , dan mampu mengendalikan serta meng install HMI e. Bertanggung jawab pada keselamatan kerja termasuk , HAZOP, HAZID, serta peraturan keselamatan kerja f. Membuat Desing Engineering Electrical & Instrumentation g. h. Membuat Front End Engineering Design i. Membuat General Arrangement j. Membuat Hazardous Operation Analysis k. Issued for Constuction,Issued for Design, Issued for Quotation,Issued for Review l. Membuat Isometric Diagram m. Membuat Line Design Temperature n. Membuat Material Selection Diagram o. Membuat analisa Material Take Off p. Merencanakan Non Destructive Examination/Test q. Membuat Design Proses & Instrumentation Diagram r. Merencanakan Process Flow Diagram s. Membuat Safety , Integrity level diagram, termasuk HASOP/HAZID 5.6 Mechanical And Piping Engineer a. Melaksanakan pekerjaan mekanikal instalasi Penggantian Meter Tube PKT 3 Fuel ,pipe spool skid, dan pekerjaan yang berkaitandengan pekerjaan mechanical termasuk pipa , tubing, bracket dan baja b. Melaksanakan monitoring terhadap pekerjaan mekanikal dan aktifitas kontruksi di lapangan c. Bekerjasama dengan HSE untuk pengawasan safety pekerjaan mekanikal dan pipe spool , membuat laporan dan prosedur pelaksanaan mechanical dan pipe spool d. Melaksankan pekerjaan sesuai dengan ketentuan dan persyaratan, dalam prosedur dan spesifikasi dalam kegiatan mekanikal dan pipe spool e. Membuat Laporan kegiatan mekanikal untuk , harian , mingguan , bulanan , dan membuat prosedure pekerjaan mekanikal f. Menyelesaikan setiap masalah yang terkait dengan mekanikal dan membuat laporan yang jelas terinci, terurai , lengkap pada setiap pekerjaan Penggantian Meter Tube PKT 3 Fuel. 5.7 Safety Engineer Safety engineer bertanggung jawab terhadap pelaksanaan Kesehatandan Keselamatan Kerja Lingkungan (K3L) di lingkungan proyek seperti alat-alatperlengkapan dasar dapat berfungsi sebagaimana yang dibutuhkan ketika ada benda-benda terjatuh Untuk mengatur kegiatan dan kebijakan K3L ini, project manager menunjuk safety manager yang memiliki tugas,tanggung jawab
  • 21. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 21 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS melaksanakan tugas dalam hal keselamatan kerja dan lingkungan kerja sesuai dengan garis besar tugas di lapangan terjalin keselamatn kerja dan nyaman untuk bekerja. Dalam hal ini detail pekerjaan dan kegiatan keselamatn kerja dan keselamatan lingkungan sesuai dengan peraturan HSE . 5.7.1 Tugas Safety Engineer a. Mempersiapkan barikade, Alat Pemadam Api Ringan (APAR), Alat Perlindungan Diri (APD),rambu, poster, dan spanduk K3L yangdiperlukan pada tempatnya b. Mempersiapkan lingkungan kerja yang aman c. Merencanakan kegiatan safety seperti inspeksi safety,meeting safety,laporansafety, dan penilaian K3Lsubkontraktor d. Memberikan briefing kepada pembantu pelaksana, mandor, dan subkontraktor 5.7.2 Tanggung Jawab Safety Engineer. a. Menjamin kesuksesan implementasi dan terus terjaganya kualitas sistem pengaturan keamanan b. Bertanggung jawab mengontrol kualitas sistem pengaturan keamanan untuk memastikankebijakan dan prosedur yang telah dibuat diaplikasikandengan benar 5.8 Structure Engineer a. Melakukan perencanaan dan perhitungan struktur proyek Penggantian Meter Tube PKT 3 , yang ditunjuk/dijadwalkan kepadanya sesuai dengan standar/peraturan dokumen Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018. b. Perencanaan struktur yang dihasilkan harus merupakan perencanaan yang ekonomis, mudah dilaksanakan, memenuhi syarat kekuatan dan kekakuan struktur c. Bersama-sama dengan Project Engineer/PE lainnya dalam membuat gambar sketsa/detail-detail konstruksi/sistem struktur untuk keperluan penggambaran di studio d. Membantu Project Coordinator/PC dalam tahap konstruksi, terutama koordinasi/revisi gambar yang disesuaikan dengan keadaan lapangan e. Atas sepengetahuan/persetujuan Project Coordinator/PC mewakili perusahaan dalam rapat- rapat lapangan yang berhubungan dengan Kunjungan Berkala f. Bersama-sama dengan Project Engineer/PE lainnya memeriksa gambar dari segi-segi kebenaran ukuran, dimensi, penulangan, kesesuaian dengan anggapan-anggapan dasar dalam perhitungan, kesesuaian antara gambar Struktur yang satu dengan yang lainnya maupun gambar-gambar Struktur dengan gambar-gambar Arsitek, M/E dan lain-lain g. Bertanggung jawab langsung kepada Project Coordinator/PC atas kualitas/keamanan perhitungan struktur dan ketepatan jadwal kerja suatu proyek h. Membantu Project Coordinator/PC dalam Perencanaan Struktur 5.9 Commissioning Engineering a. Memeriksa prosedur commissioning dan memastikan semua prosedur proyek instalasi sesuai dengan spesifikasi teknik. b. Pastikan semua prosedur keselamatan instalasi dan kontruksi sesuai prosedur commissioning c. Bekerja sama dengan team teknis di fabrikasi dan workshop. d. Kominikasi dengan tim menganalisa masalah yang timbul dilapangan agar cepat ditangani perbaikannya, tidak menggangu schedule commisioning. e. Memeriksa dan melakukan cek Valve Alignment Activities serta peralatan tambahan f. Memeriksa peralatan mekanis yang terpasang dalam skid metering
  • 22. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 22 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS g. Bekerja sama dengan I & C dan Electrical Disiplin Memimpin h. Memastikan bahwa peralatan bekerja sesuai spesifikasi teknis i. Investigasi masalah dan analisa serta perbaikan peralatan yang sedang terpasang. j. Membuat laporan dokumentasi pra commissioning dan commissioning / start-up. 5.10 Instrument Commissioning Engineer 1. Cable Diagrams/Schedules list 2. Develop the Instrument Loop folders to cover 3. Cable schedule 4. Tag list 5. I/O list 6. Inst Index 7. J/B schedule 8. Inst Data Sheets 9. Trip and Alarm s register 10. Loop sheets 11. C&E 12. Calibration sheets 13. Manage Point to Point testing 14. Instrument Calibration 15. Loop testing 16. Function Testing 17. C&E testing 18. Assist vendor to commission Vendor 19. P&ID Walk downs 20. Develop Instrument commissioning M/S, philosophy, procedures and Check sheets 21. Monitor Completion system (ATLAS) for Instrument M/C through to H/O 22. Instrument Punch Listing 23. SAT 5.11 Electrical Commissioning Engineer 1. Assist vendor with transformer test 2. Assist vendor with switc panel tests 3. Commission distribution boards 4. Commission L&SP 5. Lux tests 6. Point to point cable check 7. Inter locks 8. Trips and interface to power management 9. Witness earth tests 10. No load and load runs of meter equipment 11. SAT 12. Electrical punch list 13. Validate hazardous area certs 14. Interface with vendors
  • 23. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 23 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 5.12 Piping Commissioning Engineer 1. Track delivery and approve Vendor Manuals and Documentation 2. Systemize P&ID 3. Develop System Description and Process Commissioning Procedures 4. Preparation of Method Statements / Procedure for Pre-commissioning of System 5. Preparation for pipe cleaning ( Flushing, Leak checking, ) 6. Manage Preservation during pre com / com phase 7. Commissioning parts list 8. Review & Identify the training Requirements 9. Develop performance tests 10. Develop Hand Over procedures 11. Custodian of the O&M 12. P&ID Walk downs 13. First Fills 14. Manage Change 5.13 Project Control Engineer a. Bertanggung jawab dalam hal pengawasan perhitugan biaya proyek, biaya peperencanaan ,pelaksanaan engineering review, waktu pelaksanaan kontruksi,kordinasi pengendalian dan kontrol proyek secara keseluruhan b. Bertanggung jawab pada pengawasan administrasi,dan teknis atas biaya dan penjadwalan tenaga ahli teknik dan teknisi serta pekerja indirect yang bertugas secara khusus c. Bertanggung Jawab pada pengawasan dan monitoring biaya proyek sesuai dengan BQ dan rencana kerja instalasi Penggantian Meter Tube PKT 3 Fuel., termasuk persiapan materi rapat dan diskusi rutin d. Membuat laporan , harian , minguuan , bulanan, secara tepat benar dan betul, untuk seluruh kegiatan pekerjaan , serta membuat laporan adanya penyimpangan yang akan mengganggu biaya dan waktu pelaksanaan e. Bertanggung jawab untuk pengawasan perencanaan biaya dengan menggunakan metode teknis Manajen Proyek,dan melakukan review atas biaya pengadaan material dan waktu pengiriman dari fabrikasi ke Proyek Site 5.14 Project Procurement Team Bertanggung jawab pada teknik pengadaan material, yang terkait Perencanaan, Pengorganisasian & Pengendalian arus bahan, mulai dari pembelian awal hingga tujuan Kebutuhan material dan peralatan akan dipenuhi oleh kontraktor sesuai dengan spesifikasidata teknis Perusahaan , dan Kontraktor akan melengkapi Prefered Manufacturers List (PML),dan Approval Manufacture List (AML) Pelaksanaan procurement termasuk kegiatan logistics untuk pengangkutan peralatan dan material dari kantor Jakarta seperti : a. Klarifikasi Engineering b. Material Management Plan c. Material Receiving & Shipping Schedule ter update d. Purchase Order (PO), jelas terinci dan terurai spesifikasi barang dan serial numbernya e. Material Take Off
  • 24. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 24 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS f. Data Engineering g. Schedule Kedatangan Material h. Schedule Pengiriman dan delivery material 5.15 Procurement Status Report Membuat data tampilan dengan Format exel , tentang kronologis tatus pengadaan dan pergerakan material , mulai dari pembuatan PO sampai penyimpanan materian dan inspeksi material serta rencana dan actual pengiram material sampai onsite . 5.15.1 Bulks Material a. Procurement MTO (Piping / Mechanical / Electrical / Instrument) b. Storage & Distribution - Material Control c. Material Status Report d. Requirement on-site Dates e. Material Order & Timing f. Receiving Material Procedure & Inspections 5.15.2 Procurement Coordinator a. Melaksanakan prosedur pengadaan yang ditetapkan untuk proyek Semi Custody Meter, Master Meter . b. Koordinasi dan berinisiatif perencanaan strategis untuk semua masalah terkait pengadaan. c. Melaksanakan kegiatan pengadaan dan pengelolaan budget, peninjauan dan interpretasi prosedur kontrak. d. Memberikan pengawasan dalam proses pemilihan dan sumber pemasok utama, termasuk permintaan penawaran, evaluasi penawaran dan persetujuan budget penawaran dan pesanan pembelian. e. Memastikan kepatuhan terhadap kontrak penawaran harga dengan persyaratan perusahaan, hukum, etika, peraturan, jaminan penawaran, jaminan pelaksanaan, pajak, dan persyaratan HSE , kick off meeting mengenai masalah terkait pengadaan barang dan jasa. f. Menampung semua permasalahan pengadaan barang dan jasa. g. Membantu analisa kemungkinan yang terkait dengan memberi masukan kepada project management . h. Menyediakan dukungan pengadaan dalam mengembangkan dan memberikan pengawasan fungsional kepada spesialis pengadaan barang dan jasa. 5.15.3 Logistics Officer Mengembangkan dan melaksanakan alat dan metodologi kerja untuk memungkinkan pelaksanaan rencana logistik yang efektif cepat dan tepat untuk proyek Semi Custody Meter, Master Meter. a. Merancang dan mengembangkan metode operasi standar untuk mengelola operasi logistik secara efisien b. Memastikan pelepasan kiriman penjaga perdamaian yang bertanggung jawab, tepat waktu dan hemat biaya bersamaan dengan personil c. Pastikan semua anggota staf yang diawasi dilatih dan dilatih secara melelahkan
  • 25. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 25 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS d. Identifikasi persyaratan pelatihan logistik tambahan untuk mencapai standar kerja yang tinggi e. Mengkoordinasikan dan menyajikan dukungan logistik untuk operasi darat, udara, kereta api dan sungai yang sedang berlangsung 5.15.4 Procurement Officer a. Responsible of full Procurement and Supply Cycle, including but not limited to; generating procurement bid/tender packages and receipt of bids/tenders, RFQ’s, bid evaluations and awards, negotiate terms and commercial bids, creating and issuing Purchase Orders (PO) and Service Orders (SO) b. Ensures procurement activities conducted in accordance with company policies c. Ensures orders adhere to supplier agreements and contracts; reports non-conformances and propose contract disputes solution d. Coordinating and conducting on-site job visits; acting as the primary contact and ensuring that all technical questions submitted by the bidders are answered thoroughly and distributed accordingly e. Verify and submit invoices to accounts as well as coordinates with finance in resolving invoice discrepancies with purchase order/contract terms referred f. Providing continuous insight into contractors' and suppliers' progress towards meeting purchase order requirements, including completion and delivery schedules; gathering available data with respect to supplier and contractor production schedule; monitoring and reporting progress to Project Management g. May travel to suppliers' locations and fabrication shops to verify progress, as well as to our construction and operational sites to ensure deliveries are occurring as required h. Other Supply Chain duties, as needed 5.15.5 Commissioning Lead Memimpin dan mempersiapkan Team Engineering dalam pekerjaan melaksanakan kegiatan Pre-Commissioning / Commissioning & Start-up Berikan informasi teknis yang diperlukan untuk disiplin lain selama proyek berlangsung Mengkoordinasikan pekerjaan dalam jam kerja dan jadwal proyek yang dianggarkan Tugas Utama 1 Melaksanakan penilaian dan evaluasi sampai terinci pekerjaan komisioning dan melibatkan tim engineer serta mengevaluasi sumber daya yang ada menyelesaikan problem solving yang ada. 2 Review dokumen teknis dan sop dan indentifikasi spesifikasi batasan dan stanfard untuk menghilangkan resiko yang akan timbul dalam proyek. 3 Memberikan masukan data yang diperlukan untuk proposal teknis pada tahap penawaran, melakukan inspeksi dan memastikan kegiatan fabrikasi selesai untuk evaluasi persiapan data commissioning dan prosedur keselamatan instalasi . memastikan semua prosedure dengan aman saat komisioning’ 4 Pembahasan teknis dalam tim komisioning sampai final dan mengajukan persetujuan Pre- Commissioning , Commissioning , dan Start Up kepada PHE .
  • 26. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 26 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 5 Memimpin Tim Engineer untuk pelaksanaan kegiatan Pre-Commissioning / commissioning , bersama sama dengan tim mekanikal dan QA/QC untuk melaksanakan jadwal pelaksanaan pra-komisioning dan komisioning. 6 Menganalisa dan memperkecil resiko pelaksanaan pra-commissioning , commissing serta mengeavuasi dengan teliti peralatan pendukungnya. 7 Melaksanakan dan me-review rutin terhadap penilaian risiko dengan melakukan pertemuan / assesmment rutin dengan topik bahasan mengenai isu-isu HSE. a. Evaluasi design dan kesalahan teknis agar bisa mengendalikan biaya , terutama kesalahan akibat design akan mengeluarkan biaya tambahan harus dihindarkan, dan ini bisa menjadikan schedule pekerjaan mundur. b. Melaksanakan kontrol langsung ke lapangan dengan koordinasi QA/QC untuk menjamin kualitas dan kemajuan progress pekerjaan. c. Penanggung Jawab commissioning & pra-commissioning dan melaksanakan tugas pengawasan proyek bekerja sama dengan engineering lainnya. d. Menyelesaikan dan men-data daftar punch list items terhadap pekerjaan di lapangan. 8 Secara teratur komunikasi dan rapat rutin dengan engineer dan supervisor untuk memecahkan masalah terkait pelaksanaan proyek dengan aman . 9 Selalu berkomunikasi dan rapat rutin dengan engineer dan supervisor 10 Kerjasama Tim & kordinasi dengan engineer yang akan melaksanakan komisioning dan berikan dukungan teknis dan pedoman instruksi teknis terkait commissioning 11 Mendistribusikan tugas teknis dan tanggung jawab terkait dengan pekerjaan commissioning teruta ma tugas yang dibebankan kepada Supervisor. 6. QA / QC Team 6.1 QA/QC a. Instrumentation b. Electrical c. Mechanical 6.1.1 QA / QC Lead 1. Supervise construction and co-ordinate work at site to maximize the effectiveness of construction delivery to time, budget and quality objectives 2. Monitor and review the implementation of the EPC Contractors site quality management system 3. Prepare project quality audit schedules and conduct project quality audits 4. Establish, document and maintain a quality control system for PMC site activities, liaise with the EPC Contractor as directed, and ensure assigned work is managed and delivered to site plant 5. Monitor and review site inspection and testing 6. Support other quality personnel in monitoring Contractors work execution during the construction phase 7. Enhance and demonstrate commitment to raising HSE standards and proposing new initiatives or improvements
  • 27. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 27 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 8. Maintain and monitor all quality control activities 9. Participate in meetings as required 6.1.2 QA / QC Engineer Melaksanakan Pemeriksaan dan inspeksi visual terhadap hasil pengelasan pipe spool, a Membuat laporan harian pengelasan pipe spool ,Melaksanakan Joint Inspection NDT terhadap Pipe spool ,Melaksanakan inspeksi dan pengukuran Penetration Test b Melaksanakan dan inspeksi Hydrotest , untuk memastikan kebocoran pada pipe spool c Membuat Tag Code pada Pipe spool , untuk antisipasi indentifikasi pada uji Hydrotest, Menganalisa hasif Foto X Ray NDT d Bertanggung Jawan pada pemeriksaan pipe spool , dari fit-up ke dimensi pipa, dan data spesifikasi pemotongan pipa e Bertanggung Jawab pada inspeksi kualitas, prosedur pengelasan pipe spool sesuai dengan WPS f Bertanggung jawab pada perbaikan dilakukan dengan benar dan akurat untuk meme-nuhi Spesifikasi dan kualitas STD perbaikan mutu pengelasan pipe spool g Bertanggung Jawab untuk Pengendalian Mutu pada Rencana Pemeriksaan dan Uji, ITP (Surveillance, Witness, Hold Point dan Record Review) h Bertanggung jawab pada Pemeriksaan dan Verifikasi ,Aktual Sesuai gambar Isometrik yang –disetujui i Ikut bertanggung jawab pada Keselamatan Pengelasan, Pengujian dan Aktivitas Terka- kait sedang dilaksanakan, termasuk ,monitoring data punch list QC, untuk perbaikan welding pipe spool 6.2 Instrument & Electrical QC Inspector a Witness continuity testing / meggering of cable immediately prior to installation b Witness installation / testing of grounding / earthing system c Perform Surveillance Inspection of conduit and cable tray installation d Perform Surveillance Inspection of conduit seal pouring e Perform Surveillance Inspection of cable terminations f Assist with Receipt Inspection of transformers and MCCs (if purged, perform Surveillance Inspection periodically to ensure positive pressure is maintained) g Witness installation of MCCs and switchgear h Witness installation of transformers i Assist with Receipt Inspection of heat trace cables and related materials j Perform Surveillance Inspection of in-process installation to ensure that heat tracing is installed per specifications k Witness post-installation testing of heat tracing for acceptance inspection l Assist with Receipt Inspection of instruments m Perform Surveillance Inspection of instrument calibration n Perform Surveillance Inspection of in-process instrument installation o Verify instrument tubing is properly supported per specifications p Verify all the instrument electrical installation inspections and megger tests have been completed and are acceptablePerform Surveillance Inspection of Instrument Loop Checking
  • 28. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 28 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS q Verify all installation inspections, pressure testing and continuity checks have been completed and documented by the Contractor r Verify the loop has been checked and is operating properly 6.3 Mechanical & Piping QC Inspector 1. Reviewing of documents related to Project Quality Control requirements, method Statements and Inspection Test Plan (ITP) 2. Inspection all activity are spread over various stages of manufacture, including welding of CRA weld overlay, disbonding for the CRA weld overlay cladding using incolloy 825 an 625 using SMAW/GTAW/GMAW 3. Monitoring activity of auto ect for wall thickness continuity check, manual UT for lamination check for the CS pipe and disbanding for the weld overlay 4. Reviewing of test packages Semi Custody Meter, Master Meter. 5. Line checking inspection together with sub-contractor and main contractor QC Inspector 6. Generating punch list by category for the items need to install before hydro test after hydro test and after commissioning 7. Witness hydro test, Pneumatic / Leak Testing and In-service testing 8. Performing line reinstatement 9. Commissioning of system such as for commissioning of instrument, flushing, calibration of the valve, load test 7. Project Planning and Control Project Planning Bertanggung jawab pada langkah prosedural mulai awal persiapan proyek dan menata dalam manajemen proyek, di mana dokumentasi yang diperlukan dibuat untuk memastikan penyelesaian proyek yang sukses Dokumentasi mencakup semua tindakan yang diperlukan untuk mendefinisikan, menyiapkan, mengintegrasikan dan meng-koordinasikan rencana tambahan Rencana proyek jelas mendefinisikan bagaimana proyek dijalankan, dipantau, dikendalikan, serta membuat perencanaan proyek membutuhkan analisis mendalam dan penataan kegiatan berikut: a Menetapkan tujuan proyek b Mengidentifikasi deliverable proyek c Membuat jadwal proyek d Membuat rencana pengadaan material dan tenaga kerja serta peralatan Tahap perencanaan proyek memerlukan beberapa masukan, termasuk proposal konseptual, jadwal proyek, kebutuhan sumber daya / keterbatasan dan metrik ke- berhasilan Project Planning (Perencanaan Proyek) dimulai dengan menetapkan lingkup proyek dan akhirnya bekerja melalui setiap tingkat bergantung tindakan, tugas, analia , pelaporan kegiatan dan rencana kerja serta tenaga kerja 7.1 Project Baseline Bertanggung jawab pada penyusunan rencana kerja dengan baseline memakai Program MS Project 2013, baseline proyek diletakkan di bawah kontrol perubahan untuk membantu , mengevaluasi perubahan dan dampaknya terhadap proyek Kontrol kendali akan di analisa terhadap :
  • 29. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 29 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS a. Data Cost Report (Cash Flow, Cost Overun,Task Cost Overview, Earnet , Resource Cost Overview) b. In-Progres Report (Critical Task, Late Task, Milestone Report, Slipping Task) c. Resources Report (Overview Recources, Overallocated Overview) d. Dashboard (Cost Overview, Project Overview, Work Overview, Upcoming Task) e. Planning / Scheduling f. Overall Project CPM, Engineering CPM, Procurement CPM, Fabrication CPM g. Offshore Installation CPM h. Hook-Up CPM 8. PROJECT ADMINISTRATION AND INFORMATION MANAGEMENT 8.1 Project Comunication Project Communication Management bertangung jawab pada proses yang diperlukan untuk memastikan bahwa informasi dalam proyek Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 bisa dibuat dengan tepat dan cepat, baik dalam segi pengumpulan, diseminasi, penyimpanan, dan disposisi Hal ini menciptakan hubungan yang penting antara orang-orang, ide, dan informasi yang diperlukan supaya proyek berakhir dengan kesuksesan Setiap orang yang terlibat dalam proyek ini harus siap untuk mengirim dan menerima komunikasi, dan harus memahami bagaimana komunikasi dilakukan di mana mereka terlibat sebagai individu dan bagaimana komunikasi dapat mempengaruhi proyek secara keseluruhan termasuk : a. Perencanaan Komunikasi (Communication Planning,Distribusi Informasi, Pelaporan Kinerja) b. Membuat sistem administrasi termasuk komunikasi antara kantor pusat dan site opertion di Fabrikasi atau di Site Plant c. Safety Communication Plan  Safety Performance Feedback Plan  Safety Actifity Information  Plant Emergency  Communication interface 8.2 Project Plan dan Procedure : Standar dan prosedur proyek biasanya didokumentasikan dalam Manual Prosedur dan Prosedur Proyek Manual ini terdiri dari bagian pendahuluan yang diikuti oleh bagian terpisah untuk setiap aspek kegiatan proyek, seperti: a. Standar dan Prosedur untuk Kinerja Tim, termasuk praktik proyek umum seperti kode etik dan terminologi proyek standar, rapat, prosedur pengendalian perubahan (termasuk penggunaan Permintaan Perubahan dan Permintaan Keputusan), dan manajemen risiko b. Standar dan Prosedur untuk Manajemen Biaya / Jadwal, termasuk mengatur pekerjaan, pemantauan proyek, akuntansi proyek, dan analisis biaya / jadwal c. Standar dan Prosedur Pengelolaan Data, termasuk perpustakaan proyek, identifikasi dokumen, struktur dokumen dan gaya, dan persiapan dokumen d. Standar dan Prosedur untuk Manajemen Konfigurasi, termasuk mengidentifikasi, mengendalikan, memelihara, dan melaporkan item konfigurasi
  • 30. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 30 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS e. Standar dan Prosedur untuk Manajemen Mutu, termasuk hal-hal seperti: walk-through, review, audit dan inspeksi, penanganan dan penyimpanan, pengemasan dan pengiriman, dan prosedur untuk menghilangkan penyebab masalah. Standar dan prosedur memberikan instruksi khusus proyek mengenai prosedur, konvensi penamaan/tag, alat pendukung, peralatan, standar dan metrik yang akan diterapkan oleh tim proyek Penggantian Meter Tube PKT 3 Fuel ,Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018untuk mencapai sasaran mutu dan target waktu penyelesaian pekerjaan Semua anggota tim di Proyek , termasuk personil Perusahaan dan Personalia saat mengerjakan proyek , diharapkan mematuhi standar yang diuraikan dalam dokumen yang beredar dan sirkulasinya harus dimonitor, untuk memastikan bahwa informasi yang diserah terimakan di pahami dan dimengerti untuk dilaksanakan. 8.3 Standar dan prosedur didasarkan pada prinsip-prinsip berikut a. Standar dan prosedur akan disepakati terlebih dahulu untuk semua kegiatan proyek di mana sejumlah besar orang harus bekerja sama dalam satu Tim di “ Provision Of Semi Custody Meter And Installation Service (Tender No TS1/FEI-002/17/JAN)” Semi Custody Meter, Master Meter. b. Tim akan dilibatkan dalam pengembangan atau adopsi mereka untuk memastikan bahwa standar dimiliki oleh Project Team , kemudian akan mendisiplinkan diri mereka untuk mematuhi standar kualitas c. Setiap usaha akan dilakukan untuk memastikan bahwa kualitas standar dan prosedur terbukti dan tidak memaksakan standar yang tidak perlu atau prosedur yang terlalu rumit d. Setelah diadopsi, standar akan didokumentasikan secara formal, mudah diakses dan mudah dimengerti e. Pemimpin Tim akan melakukan:  Menekanan manfaat saat berhadapan dengan anggota tim,  Berikan umpan balik awal kepada anggota tim mengenai pekerjaan dengan standar,  Konsisten dalam menerapkan standar dan prosedur  Kepatuhan terhadap standar akan disertakan sebagai item untuk ditinjau dalam walk- through dan inspeksi lapangan 8.4 Project Meeting Report a. Melaksanakan rapat/meeting untuk membuat laporan dan pertemuan yang dilaksanakan bisa,harian , mingguan dan bulanan dengan topik bahasan , problem solving dan progress kemajuan proyek yang sedang dikerjakan, dengan menyiapakan materi meeting dan materi presentasi power point. b. Pembahasan dalam proyek meeting , tidak hanya masalah teknik saja , termasuk masalah , Schecule Proyek, Logistics Proyek ,Material Control , HSE, dan kesehatan lingkungan kerja Laporan tentang Progress Pekerjaan yang sedang berjalan juga harus jelas terinci dan terurai , dilampiri foto kegiatan nya 8.5 Network Requirement Untuk mendukung Project diperlukan jaringan internet yang bisa mengirim dan menerima dokumen dari dan ke PT ANSI MEGA INSTRUMENINDO, jaringan komputer, bisa mengakses file yang kita miliki sekaligus yang telah diseberluaskan melalui jaringan internet Selain itu, pekerja di lapangan juga dapat mengirim teks, laporan harian, gambar,
  • 31. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 31 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS audio, maupun video secara real time dengan bantuan jaringan komputer Informasi dengan sangat mudah melalui internet Untuk komunikasi Project Penggantian Meter Tube PKT 3 Fuel , Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 diperlukan jaringan internet , agar semua informasi dan dokumen bisa dengan segera , dikirim atau diterima untuk komunikasi antara Kantor Pusat dan Project Manager dilapangan , serta ahli teknik dan teknisi yang sedang mengerjakan proyek 8.6 Knowledge Management Dalam strategi untuk mensukseskan Proyek “Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018. Knowledge Management diperlukan dalam membuat strategi, sistem dan teknik yang digunakan oleh individu, dan Tim dilapangan akan mengikuti alur pola pikir dan tindakan yang harus dilakukan untuk mengatasi problem solving dan , rencana tindak lanjut untuk progress pekerjaan, dengan mengikuti teknik terbaru dalam rangka analisa problem solving , termasuk apllikasi komputer dimanfatkan 9. PROJECT CONTROL ESTIMATING 9.1 ESTIMATING a. Bertugas melakukan estimasi pengendalian biaya proyek , penjadwalan, dokumentasi perubahan dan pengendalian biaya sambil melaporkan tingkat program dalam pengendalian proyek b. Kritis terhadap Penjadwalan Waktu , Estimasi Biaya , Teknik Biaya dan Monitoring nya, untuk bisa menyelesaikan pekerjaan penggantian meter tube PKT 3 Fuel 360 (tiga ratus enam puluh) hari kalender, dan masa pemeliharaan 3 (tiga) bulan. c. Mengarahkan dan set up /review status kontrol proyek (biaya, kontrak, WBS, jadwal, sumber daya, dll) d. Kontrol yang ketat terhadap , Logistics dan Material yang akan terpasang e. Menggunakan perkiraan untuk penjadwalan dan pengendalian biaya f. Mengontrol biaya dan jadwal di akhir proyek, menganalisa data komponen audit proyek g. Membuat analisa perhitungan estimasi budget untuk perhitungan variable Budget Control dan Cost Control 9.2 SCHEDULING & SCHEDULING COST CONTROL a. Penjadwalan jaringan pekerjaan dan mempertajam WBS/CPM/PERT dan detail pekerjaan b. Memvalidasi jadwal, dan evaluasi detail jadwal yang sedang berjalan dan yg akan jalan c. Mempertajam Block Diagram dan diagram perencanaan , serta progres pencapaiannya d. Penjadwalan dasar dan perhitungan jaringan distribusi kegiatan e. Menganalisa jalure pekerjaan kritis untuk pengamanan pekerjaan alternativ yg bisa f. Kendala alternatif, dan mencari jalan keluar agar pekerjaan tetap jalan g. Gantt charts dan milestone , tetap ditahan agar tidak mundur dari schedule h. Menahan baselines Schedule tidak stagnasi, Memahami garis baseline i. Menghitung dan menganalisa biaya atas cost secara bertahap , agar posisi keuangan kuat j. Membuat Detail Kurva “S” kumulatif costing dan analisa tagihan sesuai progress dari kerja
  • 32. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 32 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS k. Me-review ulang kegiatan yang terkait dengan scheduling dan membuat persetujuan dengan Project Manager (PM), agar supaya project costing bertahan dan balance l. Overall Project CPM, Engineering CPM, Procurement CPM, Fabrication CPM m. Offshore Installation CPM n. Hook-Up CPM o. Progres Report harian , mingguan , bulanan. 9.3 COST CONTROL Project Cost Control menjadi prioritas PT ANSI MEGA INSTRUMENINDO,untuk menjalankan sistem penjadwalan, dan jadwal berfungsi untuk pengendalian biaya dan factor yang dominan dalam project cost plan adalah sebagai berikut : a. Project Cost Plan b. Cost Plan c. Cost Baseline d. Cash Flow e. Baseline Budget Cost f. Budget Project Plan g. Cost Baseline (CB) h. Budgeted Cost of Work Scheduled (BCWS) i. Planned Value (PV) j. Actual Cost Work Performed (ACWP) k. Actual Cost (AC) l. Resource Cost m. Material Cost n. Transportation Cost 9.4 Progres Measurement PT ANSI MEGA INSTRUMENINDO akan menetapkan metode pengukuran /progress measurement terhadap kemajuan pekerjaan engineering, pengadaan dan konstruksi untuk project Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 . Prosedur ini mendefinisikan metode pengukuran kemajuan dan perhitungan kemajuan fisik untuk proyek yang sedang berjaln dilapangan dengan tambahan sbb : a. Rencana Kemajuan Manajemen Proyek unntuk progress daily report dan kurva “S” termasuk lampiran fota dan detail pekerjaan yg dilaksanakan menjadi prioritas utama karena berkaitan dengan kondisi aktual dilapangan. b. Progress Pekerjaan Engineering akan disiapkan sesuai dengan spesifikasi engineering Titik berat dari progress kemajuan pekerjaan teknik dilapangan akan di evaluasi termasuk jam kerja orang (Man Hour & Man Power) sebagai dasar efisiensi untuk aktifitas dan setting budget plan perbandingan jam kerja dan jumlah tenaga kerja yang berttugas di Site Plant. c. Progress Procurement Plan, terhadap pengadaan peralatan dan material yang akan dibeli oleh PT ANSI MEGA INSTRUMENINDO Selalu diikuti proses pengadaan material yang akan dipakai di Site Plan dan Fabrikasi, dan dimonitoring setiap hari sehingga status dari material
  • 33. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 33 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS termasuk pembelian, penerimaan bahan baku utama dan bahan baku penunjang, FOB dan kedatangan barang. d. Persentase dari bobot kedatangan material disesuaikan dengan komitmen fix schedule kedatangan barang. e. Contruction & Installation Plan, Rencana Kemajuan Konstruksi ,disiapkan sesuai dengan rencana kerja pelaksanaan kontruksi / instalasi , fabrikasi dan termasuk mobilisasi, demobilisasi, pengelolaan, fasilitas sementara dan konstruksi termasuk kemajuan pra- commissioning / commissioning dan start-up Progress bobot kemajuan untuk instalasi dan pra-commissioning, termasuk data sesuai data yang tercatat dalam Bills of Quantities (B / Q) yang akan dialokasikan ke paket pekerjaan Nilai Bobot kontruksi didasarkan pada harga kontrak , sampai commissioning dan start-up, berdasarkan rencana kerja f. Persentase dari bobot kedatangan material disesuaikan dengan komitmen fix schedule kedatangan barang. g. Contruction & Installation Plan, Rencana Kemajuan Konstruksi ,disiapkan sesuai dengan rencana kerja pelaksanaan kontruksi / instalasi , fabrikasi dan termasuk mobilisasi, demobilisasi, pengelolaan, fasilitas sementara dan konstruksi termasuk kemajuan pra- commissioning / commissioning dan start-up Progress bobot kemajuan untuk instalasi dan pra-commissioning, termasuk data sesuai data yang tercatat dalam Bills of Quantities (B / Q) yang akan dialokasikan ke paket pekerjaan Nilai Bobot kontruksi didasarkan pada harga kontrak , sampai commissioning dan start-up, berdasarkan rencana kerja 9.5 Review And Approved a. Document Review and Approval adalah proses inspeksi dokumen manajemen mutu dan dokumen proyek yang memastikan bahwa ada tinjauan atau persetujuan yang memadai atas deliverable proyek yang berhasil diselesaikan sebelum memulai pekerjaan selanjutnya b. Review adalah kegiatan untuk mempertimbangkan sesuatu lagi agar tercipta cara yang sesuai, memadai, efektif, dan efisien untuk mencapai tujuan yang telah ditetapkan c. Dokumen Review dan Approval Category ditentukan oleh pentingnya dokumen dan informasi yaitu untuk informasi, untuk tinjauan ulang, untuk persetujuan, dan untuk catatan Ada: IFR (Issued for Review), IFD (Issued for Approval) , IFD (Issued for Design), FCR (Issued for Client Review), FCA (Issued for Client Approval), AFD (Approved for Design), and IFC (Issued for Construction) or AFC (Approved for Construction) sesuai dengan dengan proses kerja yang telah selesai. d. Approval dan Persetujuan adalah suatu Dokumen yang harus dilakukan tindakan sebagai berikut :  Tindakan untuk mendukung atau menambahkan otorisasi pejabat yang berwenang untuk , penerimaan atau persetujuan, atau izin resmi untuk suatu dokumen  Kesepakatan yang tertuang dalam dokumen sebagai persyaratan kontrak oleh pihak yang mengajukan prosedur proyek dalam Project Execution Plan (PEP) / Metedologi Kerja. 10. ENGINEERING DESIGN 10.1 Proses Design Basis a. Dokumen Perhitungan & Stimulasi
  • 34. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 34 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS b. Simulasi Proses c. Analisa Alur Minyak Mentah d. Line Sizing e. Equipment Sizing 10.2 Simulasi Proses a. Dokumen Perhitungan & Stimulasi b. Simulasi Proses c. Analisa Alur Minyak Mentah d. Line Sizing e. Equipment Sizin 10.3 Dokumen Spesifikasi & Data Sheet a. Dokumen Spesifikasi b. Process Data Sheet 10.4 Dokumen Gambar a. Dokumen Spesifikasi b. Process Data Sheet 10.5Dokumen Gambar Process Flow Diagram a. Utility Flow Diagram b. Piping & Instrument Diagram 10.6Piping, Mechanical, Electrical , Instrumentation 10.6.1 Piping Design Basis a. Piping Arrangement b. Piping Isometric c. Piping Layout 10.6.2 Dokumen Spesifikasi & Data sheet a. Dokumen Perhitungan (Calculation) b. Dokumen Spesifikasi & Data sheet c. Maximum Allowable Working Pressure d. Pipe Wall Thickness 10.6.3 Stress Analysis a. Equipment Sizing b. Participate in scope definition during bid / project execution / work sharing stages c. Responsible for manpower planning based on resource loading per schedule requirement d. Responsible for establishing base documents / project procedures / standards / specifications to be used for the project and to make team aware of the requirements e. Responsible for identifying resources, mobilization and demobilization planning f. Responsible for providing correct information to project team in terms of physical progress and areas of concerns, identify risks and take corrective steps for any deviations on schedule, budget or quality issues g. Responsible for establishing action / needs list to resolve project related items h. Review and approve critical documents produced by the discipline engineer(s) i. Participate in estimation of man-hours / MTO during bid stage
  • 35. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 35 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS j. Participate in development of work instructions and procedures for the discipline k. Perform all assigned work to agreed standards for safety, health environment and demonstrate a commitment to attaining high levels of HSE (Health, Safety & Environment) performance l. Participate in and advice on all design activities and initiatives, including provision of training, inductions and documentation review m. Verify that all designs are to required standards and that the objectives of the project. n. Verify that the works is completed to the agreed schedule 10.6.4 Dokumen Prosedur a. Metering Skid Intallation Procedure b. Welding Procedure c. Equipment Handling Proscedure d. Pre-Commissioning & Commissioning Procedure 10.6.5 Electrical Design Basis a. Control & Instrumentation Design Basis b. Dokumen Spesikasi & Datasheet c. Hazardous Area Clasification Specification d. Hazardous Area Clasification Specification 10.6.6 Electrical Cable a. Earthing Grounding b. Control Panel c. Valve & Control Valve d. Flow , Pressure & Temperature Measurement e. Management Information System f. Material Take Off 10.6.7 Dokumen Perhitungan ( Calculation) a. Electrical Load Study b. Power System Study c. Equipment Sizing d. Valve & Control Valve Sizing 10.6.8 Dokumen Drawing a. One Line Diagram b. Cause & Effect Diagram c. 1/0 Diagram d. Loop Diagram , Termination e. Instrument Hook Up f. Lay Out Diagram 10.6.9 Dokumen Prosedur a. Electrical Installation Procedure b. Instrument Installation Procedure c. Instrument Site Acceptance Test (SAT) Procedure d. Instrument Calibration Procedure e. Pre-Commissioning Procedure & Commissioning Procedure
  • 36. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 36 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS f. Painting Procedure 11. CONTRACT MANAGEMENT PROJECT 11.1 Project Sub-Contracting Plan Bertanggung jawab , pada rencana yang mencakup seluruh periode kontrak pekerjaan pipe spool, untuk kontrak dengan waktu tertentu, dan memiliki tujuan yang didasarkan pada subkontrak yang direncanakan oleh PT ANSI MEGA INSTRUMENINDO untuk mendukung kontrak pekerjaan Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018. 11.2Zero Deffect Program Sub kontraktor bertanggung jawab pada produk yang berkualitas sesuai dengan standard engineering yang diminta untuk pembuatan pipe spool, dengan produksi tanpa cacat diharapkan tidak ada biaya ulang dan schedule pelaksanaan tepat waktu, produksi tepat waktu dan hasil yang berkualitas sangat membantu kecepatan untuk proses berikut nya Kualitas disini diukur secara finansial, dinilai sesuai zero defects, yaitu produksi tanpa cacat 12. PROCUREMENT 12.1Material Management Plan Material Management adalah teknik pengadaan material, yang terkait Perencanaan, Pengorganisasian & Pengendalian arus bahan, mulai dari pembelian awal hingga tujuan Adapun untuk pengadaan material perlu persiapan dan langkah sebagai berikut : a. Material Requsition List ter up-date b. Material Receiving & Shipping Schedule ter update c. Purchase Order (PO), jelas terinci dan terurai spesifikasi barang dan serial numbernya 12.2Purchasing Engineering a Mengikuti dan mendaftar menjadi peserta lelang b Membuat dan melaksanakan Purchase Order Pro-Forma barang / material b Mengikuti dan membuat Kontrak Pro-Forma barang / material c Mengadakan Transportasi dan Logistik Barang / Material d Mengikuti persetujuandan komitmen Spesifikasi Engineering yang diminta e Mengikuti dan komitmen pada Persyaratan Quality Engineering f Mengajukan Meminta / Mengevaluasi Tawaran dan negosiasi harga g Menyetujui kesekapatan dokumen kontrak yang dipersyaratkan (PO) h Melaksanakan Inspeksi Kualitas , SIT , SAT , Quality Standard i Memastikan barang yang akan diterima dan akan diserahkan sesuai Serial Numbernya j Berusaha Mempercepat per tanggal delivery barang/ material k Melaksanakan Delivery Pengiriman barang/ material l Melaksanakan penyimpanan barang di gudang m Mempertahankan qualitas barang dan mengamankan dari bahaya karat n Melanjutkan pengiriman barang /material ke konstruksi / instalasi
  • 37. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 37 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS 12.3EXPEDITING PLAN a. Merencanakan dan men follow up pengiriman barang dengan aman dan berkualitas b. Membuat Packing terhadap barang yang akan dikirim agar tahan terhadap karat c. Loading Material dan pengikatannya dalam container kuat dan tidak membuat cacat 12.4MATERIAL INSPECTION a. Melaksanakan Unpacking dan , inspeksi material / barang yang datang b. Mencocokan serial number dan no part , Quality dan Quantity Barang c. Membuat laporan barang yang cacat , salah kirim dan barang yg tidak berkualitas d. Membuat Laporan Claim Insurance terhadap barang yang cacat, salah kirim 13. LOGISTICS MANAGEMENT Membuat Shipping Schedule pipe spool dari Fabrication yang akan dikirim PHE WMO dan PEP Merencanakan, menerapkan, dan mengendalikan arus efisien, efektif , dalam penyimpanan barang, layanan, dan terkait untuk memenuhi kebutuhan material Construction & Logistics sebagai bagian penting dari konstruksi yang akan dipakai dalam project pekerjaan Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 ,termasuk kosolidasi dalam manajemen rantai pasokan dan logistik (Chain Management Logistics) 14. CONSTRUCTION & INSTALLATION 14.1Program Dokumen Lelang Kontraktor diminta untuk menghadiri Rapat Review Program dengan Engineering dan Manajer Proyek Project Manager dan Project Planner diminta untuk memberikan presentasi tentang filosofi Program Tender yang penjelaskan data klarifikasi Engineering, rapat ini bisa berlangsung ber-kali2 untuk komunikasi setelah proses lelang dilewati. Program Lelang Pekerjaan disamping menyipak dokumen perusahaan ditambah :  Organization Chart Tenaga Kerja  Metode Pelaksanaan Kerja / Project Execution Plan  Cash Flow Perusahaan dan Bank  Schedule Rencana Kerja  Penawaran Harga BQ 14.2Temporary Facility Plan Rencana Fasilitas Sementara disiapkan sebelum dimulainya pekerjaan di lokasi Pertamina Gas, mengembangkan rencana lokasi yang menunjukkan lokasi dan dimensi fasilitas sementara (termasuk tata letak dan rincian, area penyimpanan peralatan dan material (tempat dan di luar lokasi), dan rute pengangkutan dan pengangkutan , Jalan masuk / jalan masuk ke area berpagar dan rincian instalasi pagar Identifikasi area mana pun yang mungkin harus dikeruk untuk mencegah pelacakan lumpur Menunjukkan apakah penggunaan area tambahan atau area pementasan lainnya diinginkan Agar keselamatan dan konstruksi, trailer situs, pintu masuk konstruksi, tempat pembuangan sampah, fasilitas sanitasi sementara 14.3Construction /Installation Execution Plan
  • 38. PROJECT EXECUTION PLAN / METODOLOGI KERJA PENGGANTIAN METER TUBE PKT 3 FUEL PT PERTAMINA GAS KALIMANTAN AREA DOC No : Revisi : 0 Page : 38 of 46 PARAF PT ANSI MEGA INSTRUMENINDO PT PERTAMINA GAS Construction/Installation Execution Plan dirancang untuk mendukung pengembangan rencana commissioning dan instalasi untuk pelaksanaan proyek Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 . Bila proyek tidak termasuk konstruksi, PEP mendukung pengembangan rencana berbasis deliverable Persiapan CEP menjadi bagian dari kegiatan pengembangan tim proyek, termasuk HSE Plan, agar supaya pekerjaan bisa berjalan dengan aman, dan berkualitas, sesuai dengan schedule dan budget Ada beberapa persyaratan yang harus bisa diatasi yaitu : a Ringkasan Proyek & Back Gound b Target , Visi dan Misi c Ruang Lingkup Pekerjaan d Lokasi dan Lay Out Project e Kontrak Pengadaan Barang dan Jasa f Jadwal Rencana Kerja g Budget & Cash Flow h Organisasi Proyek i Strategi Pengadaan Bahan dan Material j Metode Jalur Kritis k Manajemen Resiko l Tindak Lanjut Pekerjaan m Persyaratan Dokumen Teknis 14.4Construction Administration Kontraktor bertanggung jawab untuk pekerjaan Penggantian Meter Tube PKT 3 Fuel, Collective Number : S18PB0003A, RFQ NUMBER : 6600043166 / 09.02.2018 bisa sesuai dengan rencana dan memenuhi spesifikasi teknik, tim engineering akan memastikan bahwa pembangunan fasilitas ini mematuhi dan sesuai dengan keselamatan kerja dan keselamatan lingkungan PT ANSI MEGA INSTRUMENINDO bertanggung jawab untuk melaksanakan pekerjaan dengan metodologi kerja serta rencana kerja & jadwal pekerjaan instalasi sesuai dengan kontrak kerjaProsedur administrasi konstruksi kami meliputi: a Berpartisipasi dengan mitra kontraktor b Mempersiapkan laporan instalasi site report c Menerbitkan modifikasi dokumen kontrak ,bila ada d Meninjau modifikasi yang diminta oleh kontraktor e Memantau kemajuan konstruksi f Mengembangkan punch lists g Menentukan penyelesaian substansial h Mengkoordinasikan kegiatan penyelesaian proyek i Mengkoordinasikan modifikasi yang diminta 14.5Field Engineering Bertanggung jawab untuk memberikan dukungan teknik untuk mengatasi masalah teknis di lapangan Dan berpartisipasi dalam rapat koordinasi teknis masalah yang terjadi di lapangan didukung dari kantor pusat Mengidentifikasi dan mencatat penyimpangan data perbaikan peralatan dan membuat berita acara setelah tindakan perbaikan peralatan selesai