1. A G 2 0 0 0
C e n t e r P i v o t
I n s t a l l a t i o n
2. Measure the vertical riser on the pivot.
Ensure there is sufficient straight pipe to meet the
requirements of the meter (see note).
AG2000-400 22" min.
AG2000-800 30" min.
AG2000-600 38" min.
AG2000-1000 48" min.
Tape
Measure
3. Cut out a section of straight pipe, insuring there are at
least two pipe diameters of straight pipe on the inlet side of
the meter, and one pipe diameter of straight pipe on the
outlet side of the meter.
Tape
Measure
Welding
Tools
4. Cut out a section of straight pipe, ensuring there are at
least two pipe diameters of straight pipe upstream of the
meter, and one pipe diameter of straight pipe downstream
of the meter.
Tape
Measure
Welding
Tools
5. Weld the appropriate ANSI flanges on each open end of
pipe, ensuring the flanges are parallel, and the flange bolt
holes are aligned.
Allow the welds to cool to ambient temperature.
Tape
Measure
Welding
Tools
Level
6. Weld the appropriate ANSI flanges on each open end of
pipe, ensuring the flanges are parallel, and the flange bolt
holes are aligned.
Allow the welds to cool to ambient temperature.
WARNING:
DO NOT USE THE METER AS
A WELDING FORM.
THE HEAT AND/OR ELECTRICAL
CURRENTS FROM THE WELDER
WILL DAMAGE THE METER
AND VOID THE WARRANTY.
Tape
Measure
Welding
Tools
Level
7. Install the meter, with the direction arrow on the side of the
meter pointed "up", and the Power/Output cable pointing
"down".
Cable Down
Flow Arrow
Up
Wrench
8. Install the equalization wires and tabs from the lug to the
top and bottom pipe flanges for proper electrical
grounding.
Wrench
Wire Cutters
Screw Driver
Tab on pipe flange
Not
meter flange
Tab on pipe flange
Not
meter flange
9. Use a cable tie to secure the Power/Output cable to the
pivot, ensuring there is a small loop at the meter strain
relief. This will help prevent water running down the cable,
and into the meter.
Cable Ties
Wire Cutters
10. Install the Weather Guard protective cap over the meter
head. This is a force-fit, so measurable pressure will be
required for a correct fit.
Hands
11. Route the Power/Output cable to the appropriate pivot
manufacturers panel.
Consult the Seametrics Instructions "Connections, AG2000" for
specific electrical connections.
Connections,
AG2000
is available on our
website!
Click the link below
to see it now
(document may open
behind presentation).
Computer
12. Your meter is installed!
Refer to the Seametrics AG2000 Instruction Manual for
additional information and instructions.
Congratulations!
Your properly
installed AG2000
will provide years
of low maintenance
operation.