SlideShare a Scribd company logo
1 of 39
Download to read offline
by Fernand Jacques Guillou,
Judicial Expert @ Appeal Court of Lyon
Revision May 2020
Explosion Fatalities @ Total Petrochemicals
Carling site Moselle ,France , july 2009
Olefins Cracker furnace
Process Safety & Assets Integrity Report
A Case Study
Explosion and Fire @ Total Carling , Moselle 15 juillet
2009 of a dry steam super heater furnace
HSEQIMPS Integrity report
The two Total Carling
Olefins crackers
# 570Kt /y Ethylène
C2H4 ) in 1990
to convert a light naphtha
into lighter molecules such
as ethylene, propylene and
methane, which are then
used to make polyethylene
polystyrene and
polypropylene.
The
Permanent
Duality of
Risk
Explosion Furnace Carling july 2009
• 15 july 2009 at 3pm, during a (re) start up after a big storm
• 2 fatalities , 6 injuries
• Pénal Court , TGI of Sarreguemines Alsace in march 2016 ,
Judgment without Appeal of june 2016
• Civil prosecution in progress
Judgment :
• 200,000 € fine for Total Petrochemicals SA
• 1 year in jail et 20,000€ fine for the site manager
The Explosion Conditions
The Process in Cause
• 2 steam super heaters from T°380c to 525c @ 110 bars eff
supplied dry steam to the gas cracked compressor steam turbine
from the 6 cracker furnaces ( naphta et steam feed stock )
• A Mov gate valve is balancing the steam flowrate from each super
heater to the dowstream compressor inlet
• The Mov valve unreliability (see infra) induced an increase of
furnace outlet steam temperature Tc by lack of flowrate with safety
interlock actions : Tsh 542°, Tshh 545°, Tshhh 600°, by
sequential shut down of the seven burners , but immediate shut
down for Tshhh , followed by the down stream gas cracked compressor
by lack of flow rate
• Total production of gas cracked is then sent to the emergency flare
system ( loss of production during hours or days …)
• The manual (re) start/ light up of a furnace is a dangerous opération
Pid of the superheater furnace concerned by the explosion
Zoom on the dry steam outlet 525°c , 110bars
The unreliable gate valve concerned is noted MV 6101
Safety high tempÊrature Tsh 542°, Tshh 545°
PID Zoom on fuel gas inlet of each furnace
Nota bene : no safety valve exists for burners n° 4 et 7.
in consequence a start up sequence must be implemented .
• 2 steam superheaters in parallel and common to the 6 (six) cracking
furnaces for each olefins crackers , 7 flat burners for each super
heater , dry steam from Tc 380 à 525°c @110 bars tofeedthe HPturbine
of thegas cracked compressor ( hottrain C1aC8+)
• The BSL burner safety low , the safety device which forbid the gas feed
of the burner without any pilot flame was not working. the pilot flame
presence dĂŠtection of all burners are by passed ( shunt officially from
1995 ) because of unreliability , too close from the trap steam of
decoking pyrolysis tubes
• Among the four superhaters availables for both olefins crackers, it was
the only one non equipped with a lighting automate prom ( again
steam of decoking trap too close) which reduced the presence of
operators around the superheater during the startup.
The furnace explosion conditions
• Total, actually, had to review the starting sequences to include all these
safety paths. hazard non evaluated in the PHA with only
compensating mean : ÂŤ increased visual inspection Âť
• Both the MOV flow rate balancing gate valves had not been
overhauled during the last turnaround in 2008 , one year before
• Several interlocks @ TSH 542°, had already occured due to the gate
valve deficience , since the last turnaround 2008
• Injuries and medical center visits were registered and 5 minor back
draft explosions occured during the last 36 hours before the accident
The furnace explosion conditions
300,00
350,00
400,00
450,00
500,00
550,00
600,00
14:16:48 14:24:00 14:31:12 14:38:24 14:45:36 14:52:48 15:00:00
TempÊrature(°C)vapeur110b
15 juillet (heures IMAC)
SteamTempĂŠrature 110 b outlet super heater BF 601A
T vapeur 110 b BF601A
1TSH6101
1TSHH6101
1TSH6184R
1TSHH6184R
1TSHH6184R
1TSH6184R
542°C
545°C
Graph N°12/2 (15/7)
13
Interlock shut down of gas cracked turbo compressor @ Tc < 400°
here around 14h 50
Temporisation of linked tempĂŠratures to alarms TSH6101/TSHH6101, TSH6182/TSHH6182 and
TSH6183/TSHH6183
Example : Olefins cracker
emergency flaring of gas
cracked following a shut
down of the steam turbo
compressor @ P < 100 b or T<
400°c
Exemple of Gas cracked compressor (olefins cracker)
in green the steam turbine 110 bars @ T=525°c, 15 MW
Gas cracked compressor of
olefins cracker
During a 6 years Turnaround
maintenance
• Interlock shutdown by Tshh , one more time
• Burners stop in sequence but not for the pilots flames
(veilleuses) , instead of for Tshhh
• All pilots extinction made by misunderstanding procedure
• Difficulty to rearm (lighting ) pilots (cause supra)
• BSL device was supposed to turn off the gas inlet if no pilot flame
was detected on the burner for 10 seconds and it regularly shut down
the superheater without any reason so it was by passed or shunt.
• Hence, decision to bypass the procedure of flushing/purging the
superheater floor with steam
• No efficient measure of the explosive limit ( % LLE) before lighting
the pilot.
• Décision ( cause furnace still hot ) to light up burners directly ,
to avoid downstream compressor shut down
1 / OpĂŠrations sĂŠquence before explosion
• Shunt or bypass action of central control room to open interlock
XV safety valve ( global furnace BSL or safety by lack of pilot
flame presence )
• Opening of gas manual valve to one burner ( last barrier)
• One opérator is on the first level platform looking inside the
furnace , one is under the floor furnace , a third is outside , the
1er is guiding the second who held a long piĂŠzo electric lighter ,
passing through air inlet fans of one burner
• preventive gaz detection ( in % of gas LLE) was unefficient
• blindness opération because of lack of visibility inside the furnace
through visual inspection holes
• 1ère expérience of furnace start up for the two young operators
2 / OpĂŠrations sĂŠquence before explosion
• Deflagration gas explosion of around 12 kgs (25 pounds eq a
domestic gas bottle ) with internal blast pressure in radiation zone
@ 200 to 300 mbars )
• explosion hatches opened but non sized to eliminate the blast
pressure
• The heavy floor furnace ( pressure force # 50 t) is frangible and got
down onto the opĂŠrator located just below , killed immediatly
(autopsy)
• The explosion killed another : the side opérator is « lighted as a
flare Âť , run away and is killed due to blast and burns effects
(autopsy)
• Debris ( wall bricks réfractory ) rocketed to half a mile
• 6 injuries by hit debris ( with permanent physical damages )
The furnace explosion
Cracker one
the furnace
just after the
explosion
steam from
decoking trap
• Methane gas is heavier than air ; ventilation / air blow up is not
sufficient : all burners air inlet (vantelles and stack butterfly
register ) must be fully opened ,to avoid gas accumulation in
radiation zone ( hence steam purging is necessary )
• Explosion déflagration with internal pressure in radiation zone #
300 mbars , propagation speed V # 300m / sec)
• Static and dynamic Pressures of the blast wave Pd= av²/2g et
Ps=b/V , v propagation speed , V volume of methane gas inside
the furnace before explosion
• σa axial stress ( bottom effect ) and shell hoop stress σt as
σt = 2 σa should have made the shell rupture and not the floor
one
• Safety Barriers of protection : Frangible shell furnace , explosions
hatches /rupture disks, safey relief valves , stack butterfly register
• The bottom floor broke (semi fragile rupture) under dynamic
pressure + its own weight
Elements of explosion mecanism
The explosion effects Carling furnace in 2009
Left bottom floor and right ground 0 furnace , just after explosion
The furnace floor anchors frangible ruptured by
shearing stress under 200 mbars blast pressure
The cause analysis
• Un industrial area in hard recession , olefins cracker with old facilities (40y
) , low competitivity , strategic units shut downed and mothballed before ,
maintenance costs and budgets under pressure , unions on the forefront
• IT computer opérations data informations were unsaved ( 72h before the
explosion (volontary or accident ?) following a magnetic storm with
lightning and heavy rainfalls occured in the control room , 14 july 2009)
• No answers of site mid management to investigation audits questions of
the 4 team judicial experts ( mid management mutism required by top
management ) , idem during contradictory questions to witness hearing
during the trial at Court in march 2016
• Strong traumatism of employees during judicial investigation audits
• No délégation of power from the site manager to the mid management
• The site management tried to report the accident responsability to the
operators by human errors
• Strong shift between engineers and operators making uneasy
investigation to root causes analysis
Environment and Judicial Expertise difficulties
Safety Barriers Analysis and the Tripod beta model
Prevention Barriers , upstream explosion
1. Shunt /By passed volontary and organized of safety BSL 7 burners
2. Unrespect of the furnace operating start up procedure :
a. volontary extinction of all the pilots burners
b. Supervision dĂŠcision to directly light the burners without pilots
flames
c. Opening manual valve to one burner without pilot flame
d. No safety steam purge of the floor ( procedure), before lighting
e. Gaz detection test ineffective before and during lighting
f. Blind OpĂŠration (ref risk mitigation mean: visual inspection
improvement )
3. Volontary shunt / bypass of general safety interlock ( in control room )
and of local inhibition to open the XV (gaz inlet interlock valve )
( safety by lack of pilot flame detection/presence )
Protection Barriers , downstream explosion
1. DĂŠficiency of furnace design , explosion relief hatches
2. Frangibility of the bottom floor , instead of radiation shell
10 Safety Barriers in cause : 8 transgressed, 2 failed
Organizationnal Factors
• Process Safety management ( Seveso) unreliable and no updating :
MOC,PHA,HAZID ,HAZOP, HIRARC , etc…Total, actually had to
review all the starting sequences to include all these safety paths.
• Non Respect of operating procedures , check lists and work orders
• Organized and voluntary Shunt/by pass of all the 7 BSL of the furnace
burners ( root cause )
Technical Factors
• Unreliability of safety barriers ( BSL SIL/SIF )
• Design Déficiency of the Furnace , explosion Hatches , etc …
• Floor bottom Frangibility ( not Shell in radiation zone )
• Maintenance degradation of safety équipments
• Lack of gaz detection , Gad , inadequat tests, no automatisms
Humans Factors
• Lack of Skills / expérience / Training of operators and foremen
• Human Errors ( slips/lapses + voluntary and violations )
• Incompatibles Goals ( safety ,costs, production )
• Errors enforcing conditions ( stress ,schedules ,precipitations ,etc..)
• When subject to an increasing pressure ,we must stay and remain
welded to better resist to any test , cold blood ( fjguillou)
Explosion an Fire @Carling en 2009, Latent causes :
Basic Risk Factors
BRF of latent causes
Basic Risk Factors BRF Tripod Beta (1 to 11)
Except house keeping , the others 10 BRF were nominated several times
Several alarms for similar incidents occured just before the accident ( Back
Drafts dĂŠflagrations ) they were not registered and not Pha analized as required
by Seveso Directive SGS ( safety management system ) for classified sites
A strong gap was observed in communications between officers/engineers and
field operators and control room as well
Errors enforcing conditions and incompatibles goals played a premier role on
human behavior factor , before the accident
A safety culture deficient with strong impact on field opĂŠrations although ISRS
and directive SEVESO in place , in other words a table desk safety culture …
Explosion @ Carling in 2009, latent causes :
Some relative accidents in the Usa for major petrochemicals
companies
31
Occurrence Root Causes
Olefins
cracker
Date Start-
up?
Fatality ProcĂŠdures/
training
Bypass shunt ./
Insuff. safety
PHA, lack
,Moc
measure O2 /
CO mètre
Morris 2002 Yes NO ProcĂŠdures Bypass XVs
Canada
Chemicals
2003 NO NO ProcĂŠdures No BSLs PHA
dĂŠficient
no CO/O2
meter
Congrès
ASME
2009 Yes NO Presentation
feed back
Design of
safety
No PHA
Houston Tx 2008 Yes NO Respect
procĂŠdures
Bypass safety
BSLs
Mississipi 2013 Yes 1 training no CO meter
New Jersey 2016 NO NO training No CO, meter
Corpus
Christi
2017 Yes No Respect
procĂŠdures
Bypass safety
XVs
Carling total 2009 Yes 2 ProcĂŠdures
& training
Bypass safety
XVs + BSLs
PHA
dĂŠficient
No steam
purge
- Often during pendant un (re) start up
- Training /procĂŠdures/ personal always in cause
Some solutions , risk prĂŠvention
samples
1- Explosion furnace with shell vertical welds frangible , floor
intact , blast directed , double safety protection barrier
2- Explosion furnace with shell frangibility , floor intact ,
directed blast , few debris
Example of Olefins Cracker 1> Million t/y C2H4,
feed stock upgrading project and Turnaround
Process Safety PHA Fully Implemented ,HIRARC
HAZOP,LOPA, RBI, FMECA, with MOC, etc …
Integrity
HSEQIM/AIPS RM
Assets integrity
process safety risk
management
implemented with
management of
change ,MOC
Copyright fjguillou
Brave far away
from Danger
ÂŤ When we are subject to increasing
pressure , we must know and remain
welded , to better resist to any tests »…
a devise of way of life , stress and risks ,
by analogy to inspection/safety in PĂŠtrochemical
industry , (i.e. pressure directive & NDT ) par
fjguillou
corollary :
ÂŤ over all after being rolled Âť, by ÂŤ serial cost
killers Âť, an inextinguishable race who put
pressure , fiever and stress , on facilities safety … ,
in addition to NDT we need as well safety relief
valve ,rĂŠsilience , stress relieve and cold blood to
resist at all kind of tests …
Explosion at Total Petrochemicals Carling Site in Moselle, France

More Related Content

What's hot

Cfbc burner startup sequence
Cfbc burner startup sequenceCfbc burner startup sequence
Cfbc burner startup sequenceAshvani Shukla
 
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired HeatersAIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired HeatersAshutosh Garg
 
Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystGerard B. Hawkins
 
Heater operation
Heater operationHeater operation
Heater operationJOMON M.C
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loadingManohar Tatwawadi
 
Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdfManohar Tatwawadi
 
Ten the operation steps of coal fired boiler
Ten the operation steps of coal fired boilerTen the operation steps of coal fired boiler
Ten the operation steps of coal fired boilerzgwendy
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergencymitravanu mishra
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Gas Heated Reforming - An Overview
Gas Heated Reforming - An OverviewGas Heated Reforming - An Overview
Gas Heated Reforming - An OverviewGerard B. Hawkins
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency HandlingAshish Kumar Jain
 
Chemistry ppt fuels
Chemistry ppt fuels Chemistry ppt fuels
Chemistry ppt fuels Arihant Bothra
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignGerard B. Hawkins
 
Burner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-pptBurner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-pptmkpq pasha
 
SMART Explosion Venting
SMART Explosion VentingSMART Explosion Venting
SMART Explosion VentingUBMCanon
 
Thermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on MalfunctionsThermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on MalfunctionsManohar Tatwawadi
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergenciesManohar Tatwawadi
 

What's hot (19)

Cfbc burner startup sequence
Cfbc burner startup sequenceCfbc burner startup sequence
Cfbc burner startup sequence
 
Boiler safety
Boiler safetyBoiler safety
Boiler safety
 
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired HeatersAIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
 
Why use PGT Vaporizers
Why use PGT VaporizersWhy use PGT Vaporizers
Why use PGT Vaporizers
 
Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming Catalyst
 
Heater operation
Heater operationHeater operation
Heater operation
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdf
 
Ten the operation steps of coal fired boiler
Ten the operation steps of coal fired boilerTen the operation steps of coal fired boiler
Ten the operation steps of coal fired boiler
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Gas Heated Reforming - An Overview
Gas Heated Reforming - An OverviewGas Heated Reforming - An Overview
Gas Heated Reforming - An Overview
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Chemistry ppt fuels
Chemistry ppt fuels Chemistry ppt fuels
Chemistry ppt fuels
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
 
Burner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-pptBurner management-systems-a-technical-discussion-ppt
Burner management-systems-a-technical-discussion-ppt
 
SMART Explosion Venting
SMART Explosion VentingSMART Explosion Venting
SMART Explosion Venting
 
Thermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on MalfunctionsThermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on Malfunctions
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 

Similar to Explosion at Total Petrochemicals Carling Site in Moselle, France

Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGBio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGanirbanmaity1992
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptxrajneeshjauhari2
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfMadan Karki
 
hummudity test machine.pptx
hummudity test machine.pptxhummudity test machine.pptx
hummudity test machine.pptxTewodrosAtirsaw
 
Process safety management and business impact analysis
Process safety management and business impact analysisProcess safety management and business impact analysis
Process safety management and business impact analysisEduardo Teixeira Neto
 
Accident Analysis
Accident AnalysisAccident Analysis
Accident Analysisdivyadeepak77
 
4.0 Case studies on Actuators and valves .pptx
4.0 Case  studies on Actuators and valves .pptx4.0 Case  studies on Actuators and valves .pptx
4.0 Case studies on Actuators and valves .pptxManikyalaRao3
 
GEWINN Company Profile
GEWINN Company ProfileGEWINN Company Profile
GEWINN Company ProfileDinesh Kumar
 
Tube Wall Temperature Measurement On Steam Reformers - Best Practices
Tube Wall Temperature Measurement On Steam Reformers - Best PracticesTube Wall Temperature Measurement On Steam Reformers - Best Practices
Tube Wall Temperature Measurement On Steam Reformers - Best PracticesGerard B. Hawkins
 
Maintenance of Wood Chip and Wood Pellet Boilers - Fink Machine
Maintenance of Wood Chip and Wood Pellet Boilers - Fink MachineMaintenance of Wood Chip and Wood Pellet Boilers - Fink Machine
Maintenance of Wood Chip and Wood Pellet Boilers - Fink MachineArcticEnergyAlliance
 
Coke oven life prolongation a multidisciplinary approach
Coke oven life prolongation   a multidisciplinary approachCoke oven life prolongation   a multidisciplinary approach
Coke oven life prolongation a multidisciplinary approachJorge Madias
 
54666070 kiln-operation
54666070 kiln-operation54666070 kiln-operation
54666070 kiln-operationDin Sokreach
 

Similar to Explosion at Total Petrochemicals Carling Site in Moselle, France (20)

Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGBio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdf
 
IOC jaipur
IOC jaipurIOC jaipur
IOC jaipur
 
hummudity test machine.pptx
hummudity test machine.pptxhummudity test machine.pptx
hummudity test machine.pptx
 
Gas disaster in steel industries
Gas disaster in steel industriesGas disaster in steel industries
Gas disaster in steel industries
 
Steam Blow out
Steam Blow outSteam Blow out
Steam Blow out
 
automation
automationautomation
automation
 
Jaipur Fire
Jaipur FireJaipur Fire
Jaipur Fire
 
Process safety management and business impact analysis
Process safety management and business impact analysisProcess safety management and business impact analysis
Process safety management and business impact analysis
 
Accident Analysis
Accident AnalysisAccident Analysis
Accident Analysis
 
4.0 Case studies on Actuators and valves .pptx
4.0 Case  studies on Actuators and valves .pptx4.0 Case  studies on Actuators and valves .pptx
4.0 Case studies on Actuators and valves .pptx
 
GEWINN Company Profile
GEWINN Company ProfileGEWINN Company Profile
GEWINN Company Profile
 
Boiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singaporeBoiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singapore
 
Tube Wall Temperature Measurement On Steam Reformers - Best Practices
Tube Wall Temperature Measurement On Steam Reformers - Best PracticesTube Wall Temperature Measurement On Steam Reformers - Best Practices
Tube Wall Temperature Measurement On Steam Reformers - Best Practices
 
Maintenance of Wood Chip and Wood Pellet Boilers - Fink Machine
Maintenance of Wood Chip and Wood Pellet Boilers - Fink MachineMaintenance of Wood Chip and Wood Pellet Boilers - Fink Machine
Maintenance of Wood Chip and Wood Pellet Boilers - Fink Machine
 
Coke oven life prolongation a multidisciplinary approach
Coke oven life prolongation   a multidisciplinary approachCoke oven life prolongation   a multidisciplinary approach
Coke oven life prolongation a multidisciplinary approach
 
54666070 kiln-operation
54666070 kiln-operation54666070 kiln-operation
54666070 kiln-operation
 
Agnee engineering
Agnee engineeringAgnee engineering
Agnee engineering
 
Agnee Engineering
Agnee EngineeringAgnee Engineering
Agnee Engineering
 

More from Fernand-Jacques GUILLOU

Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020Fernand-Jacques GUILLOU
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020Fernand-Jacques GUILLOU
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020Fernand-Jacques GUILLOU
 
Explosion mortelle @carling 2009 synthese judiciaire
Explosion mortelle @carling 2009 synthese judiciaire Explosion mortelle @carling 2009 synthese judiciaire
Explosion mortelle @carling 2009 synthese judiciaire Fernand-Jacques GUILLOU
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020Fernand-Jacques GUILLOU
 
Facteurs humains en securite industrielle
Facteurs humains en securite industrielle Facteurs humains en securite industrielle
Facteurs humains en securite industrielle Fernand-Jacques GUILLOU
 
Non destructive testing for engineers
Non destructive testing  for engineers Non destructive testing  for engineers
Non destructive testing for engineers Fernand-Jacques GUILLOU
 
Non destructive testing cnd judicial experts
Non destructive testing cnd  judicial experts Non destructive testing cnd  judicial experts
Non destructive testing cnd judicial experts Fernand-Jacques GUILLOU
 

More from Fernand-Jacques GUILLOU (15)

Projetindustrie lrev3
Projetindustrie lrev3Projetindustrie lrev3
Projetindustrie lrev3
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020
 
Explosion mortelle @carling 2009 synthese judiciaire
Explosion mortelle @carling 2009 synthese judiciaire Explosion mortelle @carling 2009 synthese judiciaire
Explosion mortelle @carling 2009 synthese judiciaire
 
ASSETS INTEGRITY& PROCESS SAFETY
ASSETS  INTEGRITY& PROCESS SAFETY ASSETS  INTEGRITY& PROCESS SAFETY
ASSETS INTEGRITY& PROCESS SAFETY
 
Sapiens nihil affirmat quod non probet 2020
Sapiens  nihil affirmat quod non probet 2020Sapiens  nihil affirmat quod non probet 2020
Sapiens nihil affirmat quod non probet 2020
 
Cnd industriels
Cnd industriels Cnd industriels
Cnd industriels
 
HUMAN ERRORS MANAGEMENT
HUMAN ERRORS MANAGEMENT HUMAN ERRORS MANAGEMENT
HUMAN ERRORS MANAGEMENT
 
HUMAN and ORGANIZATION FACTORS
HUMAN and ORGANIZATION FACTORSHUMAN and ORGANIZATION FACTORS
HUMAN and ORGANIZATION FACTORS
 
Facteurs humains en securite industrielle
Facteurs humains en securite industrielle Facteurs humains en securite industrielle
Facteurs humains en securite industrielle
 
RISK MANAGEMENT and ASSESSMENT
RISK MANAGEMENT and ASSESSMENTRISK MANAGEMENT and ASSESSMENT
RISK MANAGEMENT and ASSESSMENT
 
RISK MANAGEMENT
RISK MANAGEMENTRISK MANAGEMENT
RISK MANAGEMENT
 
Non destructive testing for engineers
Non destructive testing  for engineers Non destructive testing  for engineers
Non destructive testing for engineers
 
Non destructive testing cnd judicial experts
Non destructive testing cnd  judicial experts Non destructive testing cnd  judicial experts
Non destructive testing cnd judicial experts
 

Recently uploaded

LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 

Recently uploaded (17)

LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 

Explosion at Total Petrochemicals Carling Site in Moselle, France

  • 1. by Fernand Jacques Guillou, Judicial Expert @ Appeal Court of Lyon Revision May 2020 Explosion Fatalities @ Total Petrochemicals Carling site Moselle ,France , july 2009 Olefins Cracker furnace Process Safety & Assets Integrity Report A Case Study
  • 2. Explosion and Fire @ Total Carling , Moselle 15 juillet 2009 of a dry steam super heater furnace HSEQIMPS Integrity report
  • 3. The two Total Carling Olefins crackers # 570Kt /y Ethylène C2H4 ) in 1990 to convert a light naphtha into lighter molecules such as ethylene, propylene and methane, which are then used to make polyethylene polystyrene and polypropylene.
  • 5. Explosion Furnace Carling july 2009 • 15 july 2009 at 3pm, during a (re) start up after a big storm • 2 fatalities , 6 injuries • PĂŠnal Court , TGI of Sarreguemines Alsace in march 2016 , Judgment without Appeal of june 2016 • Civil prosecution in progress Judgment : • 200,000 € fine for Total Petrochemicals SA • 1 year in jail et 20,000€ fine for the site manager
  • 7. The Process in Cause • 2 steam super heaters from T°380c to 525c @ 110 bars eff supplied dry steam to the gas cracked compressor steam turbine from the 6 cracker furnaces ( naphta et steam feed stock ) • A Mov gate valve is balancing the steam flowrate from each super heater to the dowstream compressor inlet • The Mov valve unreliability (see infra) induced an increase of furnace outlet steam temperature Tc by lack of flowrate with safety interlock actions : Tsh 542°, Tshh 545°, Tshhh 600°, by sequential shut down of the seven burners , but immediate shut down for Tshhh , followed by the down stream gas cracked compressor by lack of flow rate • Total production of gas cracked is then sent to the emergency flare system ( loss of production during hours or days …) • The manual (re) start/ light up of a furnace is a dangerous opĂŠration
  • 8. Pid of the superheater furnace concerned by the explosion
  • 9. Zoom on the dry steam outlet 525°c , 110bars The unreliable gate valve concerned is noted MV 6101 Safety high tempĂŠrature Tsh 542°, Tshh 545°
  • 10. PID Zoom on fuel gas inlet of each furnace Nota bene : no safety valve exists for burners n° 4 et 7. in consequence a start up sequence must be implemented .
  • 11. • 2 steam superheaters in parallel and common to the 6 (six) cracking furnaces for each olefins crackers , 7 flat burners for each super heater , dry steam from Tc 380 Ă  525°c @110 bars tofeedthe HPturbine of thegas cracked compressor ( hottrain C1aC8+) • The BSL burner safety low , the safety device which forbid the gas feed of the burner without any pilot flame was not working. the pilot flame presence dĂŠtection of all burners are by passed ( shunt officially from 1995 ) because of unreliability , too close from the trap steam of decoking pyrolysis tubes • Among the four superhaters availables for both olefins crackers, it was the only one non equipped with a lighting automate prom ( again steam of decoking trap too close) which reduced the presence of operators around the superheater during the startup. The furnace explosion conditions
  • 12. • Total, actually, had to review the starting sequences to include all these safety paths. hazard non evaluated in the PHA with only compensating mean : ÂŤ increased visual inspection Âť • Both the MOV flow rate balancing gate valves had not been overhauled during the last turnaround in 2008 , one year before • Several interlocks @ TSH 542°, had already occured due to the gate valve deficience , since the last turnaround 2008 • Injuries and medical center visits were registered and 5 minor back draft explosions occured during the last 36 hours before the accident The furnace explosion conditions
  • 13. 300,00 350,00 400,00 450,00 500,00 550,00 600,00 14:16:48 14:24:00 14:31:12 14:38:24 14:45:36 14:52:48 15:00:00 TempĂŠrature(°C)vapeur110b 15 juillet (heures IMAC) SteamTempĂŠrature 110 b outlet super heater BF 601A T vapeur 110 b BF601A 1TSH6101 1TSHH6101 1TSH6184R 1TSHH6184R 1TSHH6184R 1TSH6184R 542°C 545°C Graph N°12/2 (15/7) 13 Interlock shut down of gas cracked turbo compressor @ Tc < 400° here around 14h 50 Temporisation of linked tempĂŠratures to alarms TSH6101/TSHH6101, TSH6182/TSHH6182 and TSH6183/TSHH6183
  • 14. Example : Olefins cracker emergency flaring of gas cracked following a shut down of the steam turbo compressor @ P < 100 b or T< 400°c
  • 15. Exemple of Gas cracked compressor (olefins cracker) in green the steam turbine 110 bars @ T=525°c, 15 MW Gas cracked compressor of olefins cracker During a 6 years Turnaround maintenance
  • 16. • Interlock shutdown by Tshh , one more time • Burners stop in sequence but not for the pilots flames (veilleuses) , instead of for Tshhh • All pilots extinction made by misunderstanding procedure • Difficulty to rearm (lighting ) pilots (cause supra) • BSL device was supposed to turn off the gas inlet if no pilot flame was detected on the burner for 10 seconds and it regularly shut down the superheater without any reason so it was by passed or shunt. • Hence, decision to bypass the procedure of flushing/purging the superheater floor with steam • No efficient measure of the explosive limit ( % LLE) before lighting the pilot. • DĂŠcision ( cause furnace still hot ) to light up burners directly , to avoid downstream compressor shut down 1 / OpĂŠrations sĂŠquence before explosion
  • 17. • Shunt or bypass action of central control room to open interlock XV safety valve ( global furnace BSL or safety by lack of pilot flame presence ) • Opening of gas manual valve to one burner ( last barrier) • One opĂŠrator is on the first level platform looking inside the furnace , one is under the floor furnace , a third is outside , the 1er is guiding the second who held a long piĂŠzo electric lighter , passing through air inlet fans of one burner • preventive gaz detection ( in % of gas LLE) was unefficient • blindness opĂŠration because of lack of visibility inside the furnace through visual inspection holes • 1ère expĂŠrience of furnace start up for the two young operators 2 / OpĂŠrations sĂŠquence before explosion
  • 18. • Deflagration gas explosion of around 12 kgs (25 pounds eq a domestic gas bottle ) with internal blast pressure in radiation zone @ 200 to 300 mbars ) • explosion hatches opened but non sized to eliminate the blast pressure • The heavy floor furnace ( pressure force # 50 t) is frangible and got down onto the opĂŠrator located just below , killed immediatly (autopsy) • The explosion killed another : the side opĂŠrator is ÂŤ lighted as a flare Âť , run away and is killed due to blast and burns effects (autopsy) • Debris ( wall bricks rĂŠfractory ) rocketed to half a mile • 6 injuries by hit debris ( with permanent physical damages ) The furnace explosion
  • 19. Cracker one the furnace just after the explosion steam from decoking trap
  • 20. • Methane gas is heavier than air ; ventilation / air blow up is not sufficient : all burners air inlet (vantelles and stack butterfly register ) must be fully opened ,to avoid gas accumulation in radiation zone ( hence steam purging is necessary ) • Explosion dĂŠflagration with internal pressure in radiation zone # 300 mbars , propagation speed V # 300m / sec) • Static and dynamic Pressures of the blast wave Pd= av²/2g et Ps=b/V , v propagation speed , V volume of methane gas inside the furnace before explosion • σa axial stress ( bottom effect ) and shell hoop stress σt as σt = 2 σa should have made the shell rupture and not the floor one • Safety Barriers of protection : Frangible shell furnace , explosions hatches /rupture disks, safey relief valves , stack butterfly register • The bottom floor broke (semi fragile rupture) under dynamic pressure + its own weight Elements of explosion mecanism
  • 21. The explosion effects Carling furnace in 2009 Left bottom floor and right ground 0 furnace , just after explosion
  • 22. The furnace floor anchors frangible ruptured by shearing stress under 200 mbars blast pressure
  • 24. • Un industrial area in hard recession , olefins cracker with old facilities (40y ) , low competitivity , strategic units shut downed and mothballed before , maintenance costs and budgets under pressure , unions on the forefront • IT computer opĂŠrations data informations were unsaved ( 72h before the explosion (volontary or accident ?) following a magnetic storm with lightning and heavy rainfalls occured in the control room , 14 july 2009) • No answers of site mid management to investigation audits questions of the 4 team judicial experts ( mid management mutism required by top management ) , idem during contradictory questions to witness hearing during the trial at Court in march 2016 • Strong traumatism of employees during judicial investigation audits • No dĂŠlĂŠgation of power from the site manager to the mid management • The site management tried to report the accident responsability to the operators by human errors • Strong shift between engineers and operators making uneasy investigation to root causes analysis Environment and Judicial Expertise difficulties
  • 25. Safety Barriers Analysis and the Tripod beta model
  • 26. Prevention Barriers , upstream explosion 1. Shunt /By passed volontary and organized of safety BSL 7 burners 2. Unrespect of the furnace operating start up procedure : a. volontary extinction of all the pilots burners b. Supervision dĂŠcision to directly light the burners without pilots flames c. Opening manual valve to one burner without pilot flame d. No safety steam purge of the floor ( procedure), before lighting e. Gaz detection test ineffective before and during lighting f. Blind OpĂŠration (ref risk mitigation mean: visual inspection improvement ) 3. Volontary shunt / bypass of general safety interlock ( in control room ) and of local inhibition to open the XV (gaz inlet interlock valve ) ( safety by lack of pilot flame detection/presence ) Protection Barriers , downstream explosion 1. DĂŠficiency of furnace design , explosion relief hatches 2. Frangibility of the bottom floor , instead of radiation shell 10 Safety Barriers in cause : 8 transgressed, 2 failed
  • 27. Organizationnal Factors • Process Safety management ( Seveso) unreliable and no updating : MOC,PHA,HAZID ,HAZOP, HIRARC , etc…Total, actually had to review all the starting sequences to include all these safety paths. • Non Respect of operating procedures , check lists and work orders • Organized and voluntary Shunt/by pass of all the 7 BSL of the furnace burners ( root cause ) Technical Factors • Unreliability of safety barriers ( BSL SIL/SIF ) • Design DĂŠficiency of the Furnace , explosion Hatches , etc … • Floor bottom Frangibility ( not Shell in radiation zone ) • Maintenance degradation of safety ĂŠquipments • Lack of gaz detection , Gad , inadequat tests, no automatisms Humans Factors • Lack of Skills / expĂŠrience / Training of operators and foremen • Human Errors ( slips/lapses + voluntary and violations ) • Incompatibles Goals ( safety ,costs, production ) • Errors enforcing conditions ( stress ,schedules ,precipitations ,etc..) • When subject to an increasing pressure ,we must stay and remain welded to better resist to any test , cold blood ( fjguillou) Explosion an Fire @Carling en 2009, Latent causes :
  • 29. BRF of latent causes
  • 30. Basic Risk Factors BRF Tripod Beta (1 to 11) Except house keeping , the others 10 BRF were nominated several times Several alarms for similar incidents occured just before the accident ( Back Drafts dĂŠflagrations ) they were not registered and not Pha analized as required by Seveso Directive SGS ( safety management system ) for classified sites A strong gap was observed in communications between officers/engineers and field operators and control room as well Errors enforcing conditions and incompatibles goals played a premier role on human behavior factor , before the accident A safety culture deficient with strong impact on field opĂŠrations although ISRS and directive SEVESO in place , in other words a table desk safety culture … Explosion @ Carling in 2009, latent causes :
  • 31. Some relative accidents in the Usa for major petrochemicals companies 31 Occurrence Root Causes Olefins cracker Date Start- up? Fatality ProcĂŠdures/ training Bypass shunt ./ Insuff. safety PHA, lack ,Moc measure O2 / CO mètre Morris 2002 Yes NO ProcĂŠdures Bypass XVs Canada Chemicals 2003 NO NO ProcĂŠdures No BSLs PHA dĂŠficient no CO/O2 meter Congrès ASME 2009 Yes NO Presentation feed back Design of safety No PHA Houston Tx 2008 Yes NO Respect procĂŠdures Bypass safety BSLs Mississipi 2013 Yes 1 training no CO meter New Jersey 2016 NO NO training No CO, meter Corpus Christi 2017 Yes No Respect procĂŠdures Bypass safety XVs Carling total 2009 Yes 2 ProcĂŠdures & training Bypass safety XVs + BSLs PHA dĂŠficient No steam purge - Often during pendant un (re) start up - Training /procĂŠdures/ personal always in cause
  • 32. Some solutions , risk prĂŠvention samples
  • 33. 1- Explosion furnace with shell vertical welds frangible , floor intact , blast directed , double safety protection barrier
  • 34. 2- Explosion furnace with shell frangibility , floor intact , directed blast , few debris
  • 35. Example of Olefins Cracker 1> Million t/y C2H4, feed stock upgrading project and Turnaround Process Safety PHA Fully Implemented ,HIRARC HAZOP,LOPA, RBI, FMECA, with MOC, etc …
  • 36. Integrity HSEQIM/AIPS RM Assets integrity process safety risk management implemented with management of change ,MOC Copyright fjguillou
  • 38. ÂŤ When we are subject to increasing pressure , we must know and remain welded , to better resist to any tests »… a devise of way of life , stress and risks , by analogy to inspection/safety in PĂŠtrochemical industry , (i.e. pressure directive & NDT ) par fjguillou corollary : ÂŤ over all after being rolled Âť, by ÂŤ serial cost killers Âť, an inextinguishable race who put pressure , fiever and stress , on facilities safety … , in addition to NDT we need as well safety relief valve ,rĂŠsilience , stress relieve and cold blood to resist at all kind of tests …