SlideShare a Scribd company logo
1 of 15
TERM ASSIGNMENT-2
Ground Improvement Techniques
2CLDE57
BY
19BCL105 PUSHKAL PAREEK
20BCL509 AKSHAT.A.MEHTA
LEANING
TOWER OF
PISA
SOIL INVESTIGATIONS FOR PHYSICAL AND
MECHANICAL PROPERTIES OF SOIL
 The variety of rocks ranges from Paleozoic to tertiary in Pisa city. Due to
tectonic activities, the city’s strata have undergone severe deformation.
Moreover, there is a fault passing through the bedrock beneath the town of
Pisa.
 The town of Pisa is located on the alluvial sediments and the mean sea level is
only 3-4 m.
 Soil profile below the tower consists of three horizons.
 Horizon-A consists mainly of estuarine deposits. This stratum is laid under
tidal conditions. Therefore, the amount of sandy and clayey silts varies under
the strata. The thickness of horizon-A is 10 m.
 Horizon-B consists of marine clay and sandy
soil. Sandy soil is sandwiched between the
layers of clayey soil. The upper clay layer is
very sensitive, whereas the lower clay layer
is stiff and less sensitive. The thickness of
horizon-B is 40 m.
 Horizon-C consists of dense sand. The
thickness of horizon-C extends to a
considerable depth.
 The amount of silt and clay is more on the
south side of the tower. Also, the sand layer
is much thinner than on the north side of the
tower. This is one of the reasons that led to
the tilting of the tower towards the south
side.
 The natural groundwater level is 1-2 m
below the ground surface area. However, in
the past, water extraction from the lower
sand has led to downward seepage from the
horizon-A layer. As a result, the pore
pressure distribution is slightly below
hydrostatic pressure.
CAUSES OF TILTING OF TOWER
 The rapid increase in the leaning process of any building or tower towards the end of
the construction process is known as leaning instability. Leaning instability of a tall,
narrow structure occurs at a critical height when the overturning moment generated
by a small increase in inclination is equal to, or larger than the
corresponding resisting moment generated by the foundations.
 Leaning instability is not due to lack of strength of the ground but due to insufficient
stiffness. It is apparent that the combination of the very soft ground and the
geometry has actually resulted in the tower of Pisa reaching its critical height.
 The factors that have contributed towards the leaning of the Pisa tower are:
1. Change in the groundwater table causing subsidence in the alluvial sand.
2. Heavy rainstorms.
3. Temperature variation in the summers caused the change in the leaning stability of
the tower.
4. Stabilization process of the tower.
STABILIZATION PROCESS
TEMPORARY STABALIZATION
The following points describe the temporary stabilization measures taken to improve
the stability of the tower:
 Marble cladding around the outer wall of the tower started showing signs of cracking.
Therefore, to reduce the failure of marble cladding, temporary lightly pre-stressed
plastic-covered steel tendons were installed at a suitable interval up to the second
story in the year 1992.
 The tower's northern side was gradually rising as well as the southern side, which was
tilting with time. Therefore, the experts recommended placing emphasis on the
masonry foundation's northern side. As a result, it would stop the tower's constant
tilting and perhaps even lessen it somewhat.
 A temporary pre-cast concrete ring was built around the plinth level of the tower for
the aforementioned reason. Lead ingots were positioned on the pre-cast concrete
ring for loading at regular intervals.
• Between July 1994 and January 1995,
there were three lead ingot
placements total. The tower began to
tilt towards the north one month
after the application of loads.
• The tower eventually settled at a
distance of around 2.5 mm from the
surrounding ground level,
nevertheless, as a result of the
application of loads.
• In order to monitor the tower's response, the weight on the northern side
was applied in four stages.
Permanent Stabilization
The committee tested a number of techniques in an effort to find a long-
term solution for rotating the tower back toward the north. These
techniques included loading the earth surrounding the north foundation
using a pressing slab loaded by ground anchors, consolidation below the
north foundation using electro-osmosis, and draining below the north
foundation using wells. None of these approaches, however, turned out to
be successful.
• The installation of several soil extraction tubes directly beneath the
north side of the foundation is done using this technique.
• On the trial footing that was set up close to the tower location, this
approach was tested out initially. It was successful to rotate the trial
footing by 0.25°.
The committee decided to adopt the induced subsidence method on the
northern side of the tower. The following points describe the induced
subsidence method to rotate the tower back in the northern side:
• On the tower's northern base, the true
permanent stabilizing work began in
August 1998. The northern side of the
foundation initially had a little amount of
earth removed from it, creating a hollow.
The overburden pressure caused the cavity
to begin closing automatically, which led to
a modest amount of surface sinking.
• The whole northern side of the foundation
was built using the aforementioned
procedure.
• After the fully induced subsidence, the
tower significantly rotated towards the
northern side.
Additional Foundation
Stabilization Measures
In addition to the above measures, two more permanent solutions
were adopted for reducing the inclination of the tower.
Firstly, At the foot of the tower, a 0.8 m
thick cement-conglomerate ring was
constructed and attached to the
tower's foundation using steel
reinforcement. The ring was also
reinforced using the post-tensioning
technique. As a result, the foundation's
useful area expanded, increasing both
safety and resistance to leaning
instability.
CEMENT-CONGLOMERATE RING
Secondly, to reduce the groundwater
level fluctuation during the rainy
season, a drainage system was
installed. This system consists of three
wells. These wells were constructed
with radial sub-horizontal drains
running beneath the north side of the
foundation. The water level in the
outlet pipes control the water level in
the wells. The installation of this
drainage system induced a further
northward rotation of the tower.
THREE-WELL DRAINAGE SYSTEM
THANK YOU

More Related Content

Similar to Leaning Tower of Pisa.pptx

Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
John Chakamba
 

Similar to Leaning Tower of Pisa.pptx (20)

Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
case study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failurecase study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failure
 
Pisa
PisaPisa
Pisa
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Pisa Tower
Pisa TowerPisa Tower
Pisa Tower
 
1115
11151115
1115
 
Soil properties and its importance in construction
Soil properties and its importance in constructionSoil properties and its importance in construction
Soil properties and its importance in construction
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Geotech Problems.ppt
Geotech Problems.pptGeotech Problems.ppt
Geotech Problems.ppt
 
Longwall_top_coal_caving.pptx
Longwall_top_coal_caving.pptxLongwall_top_coal_caving.pptx
Longwall_top_coal_caving.pptx
 
pile foundation of burj khalifa
pile foundation of burj khalifapile foundation of burj khalifa
pile foundation of burj khalifa
 
Micropile
MicropileMicropile
Micropile
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Soil nailing
Soil nailing Soil nailing
Soil nailing
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 

Recently uploaded

Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 

Recently uploaded (20)

Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 

Leaning Tower of Pisa.pptx

  • 1. TERM ASSIGNMENT-2 Ground Improvement Techniques 2CLDE57 BY 19BCL105 PUSHKAL PAREEK 20BCL509 AKSHAT.A.MEHTA
  • 3. SOIL INVESTIGATIONS FOR PHYSICAL AND MECHANICAL PROPERTIES OF SOIL  The variety of rocks ranges from Paleozoic to tertiary in Pisa city. Due to tectonic activities, the city’s strata have undergone severe deformation. Moreover, there is a fault passing through the bedrock beneath the town of Pisa.  The town of Pisa is located on the alluvial sediments and the mean sea level is only 3-4 m.  Soil profile below the tower consists of three horizons.  Horizon-A consists mainly of estuarine deposits. This stratum is laid under tidal conditions. Therefore, the amount of sandy and clayey silts varies under the strata. The thickness of horizon-A is 10 m.
  • 4.  Horizon-B consists of marine clay and sandy soil. Sandy soil is sandwiched between the layers of clayey soil. The upper clay layer is very sensitive, whereas the lower clay layer is stiff and less sensitive. The thickness of horizon-B is 40 m.  Horizon-C consists of dense sand. The thickness of horizon-C extends to a considerable depth.  The amount of silt and clay is more on the south side of the tower. Also, the sand layer is much thinner than on the north side of the tower. This is one of the reasons that led to the tilting of the tower towards the south side.  The natural groundwater level is 1-2 m below the ground surface area. However, in the past, water extraction from the lower sand has led to downward seepage from the horizon-A layer. As a result, the pore pressure distribution is slightly below hydrostatic pressure.
  • 5. CAUSES OF TILTING OF TOWER  The rapid increase in the leaning process of any building or tower towards the end of the construction process is known as leaning instability. Leaning instability of a tall, narrow structure occurs at a critical height when the overturning moment generated by a small increase in inclination is equal to, or larger than the corresponding resisting moment generated by the foundations.  Leaning instability is not due to lack of strength of the ground but due to insufficient stiffness. It is apparent that the combination of the very soft ground and the geometry has actually resulted in the tower of Pisa reaching its critical height.  The factors that have contributed towards the leaning of the Pisa tower are: 1. Change in the groundwater table causing subsidence in the alluvial sand. 2. Heavy rainstorms. 3. Temperature variation in the summers caused the change in the leaning stability of the tower. 4. Stabilization process of the tower.
  • 7. TEMPORARY STABALIZATION The following points describe the temporary stabilization measures taken to improve the stability of the tower:  Marble cladding around the outer wall of the tower started showing signs of cracking. Therefore, to reduce the failure of marble cladding, temporary lightly pre-stressed plastic-covered steel tendons were installed at a suitable interval up to the second story in the year 1992.  The tower's northern side was gradually rising as well as the southern side, which was tilting with time. Therefore, the experts recommended placing emphasis on the masonry foundation's northern side. As a result, it would stop the tower's constant tilting and perhaps even lessen it somewhat.  A temporary pre-cast concrete ring was built around the plinth level of the tower for the aforementioned reason. Lead ingots were positioned on the pre-cast concrete ring for loading at regular intervals.
  • 8. • Between July 1994 and January 1995, there were three lead ingot placements total. The tower began to tilt towards the north one month after the application of loads. • The tower eventually settled at a distance of around 2.5 mm from the surrounding ground level, nevertheless, as a result of the application of loads. • In order to monitor the tower's response, the weight on the northern side was applied in four stages.
  • 9. Permanent Stabilization The committee tested a number of techniques in an effort to find a long- term solution for rotating the tower back toward the north. These techniques included loading the earth surrounding the north foundation using a pressing slab loaded by ground anchors, consolidation below the north foundation using electro-osmosis, and draining below the north foundation using wells. None of these approaches, however, turned out to be successful.
  • 10. • The installation of several soil extraction tubes directly beneath the north side of the foundation is done using this technique. • On the trial footing that was set up close to the tower location, this approach was tested out initially. It was successful to rotate the trial footing by 0.25°. The committee decided to adopt the induced subsidence method on the northern side of the tower. The following points describe the induced subsidence method to rotate the tower back in the northern side:
  • 11. • On the tower's northern base, the true permanent stabilizing work began in August 1998. The northern side of the foundation initially had a little amount of earth removed from it, creating a hollow. The overburden pressure caused the cavity to begin closing automatically, which led to a modest amount of surface sinking. • The whole northern side of the foundation was built using the aforementioned procedure. • After the fully induced subsidence, the tower significantly rotated towards the northern side.
  • 12. Additional Foundation Stabilization Measures In addition to the above measures, two more permanent solutions were adopted for reducing the inclination of the tower.
  • 13. Firstly, At the foot of the tower, a 0.8 m thick cement-conglomerate ring was constructed and attached to the tower's foundation using steel reinforcement. The ring was also reinforced using the post-tensioning technique. As a result, the foundation's useful area expanded, increasing both safety and resistance to leaning instability. CEMENT-CONGLOMERATE RING
  • 14. Secondly, to reduce the groundwater level fluctuation during the rainy season, a drainage system was installed. This system consists of three wells. These wells were constructed with radial sub-horizontal drains running beneath the north side of the foundation. The water level in the outlet pipes control the water level in the wells. The installation of this drainage system induced a further northward rotation of the tower. THREE-WELL DRAINAGE SYSTEM