SlideShare a Scribd company logo
1 of 15
Download to read offline
PMP Formulas
PMP Formulas
 No. of Communication Channels
 n (n-1)/2 n = number of members in the
team
 n should include the project manager
 e.g. if the no. of team members increase
from 4 to 5, the increase in
communication channels:
5(5-1)/2 – 4(4-1)/2 = 4
PMP Formulas
 Schedule Performance Index (SPI)
 SPI = EV/PV ; EV = Earned Value
PV = Planned Value
 < 1 behind schedule
= 1 on schedule
> 1 ahead of schedule
PMP Formulas
 Cost Performance Index (CPI)
 CPI = EV/AC ; EV = Earned Value
AC = Actual Cost
 < 1 Over budget
= 1 On budget
> 1 Under budget
sometimes the term ‘cumulative CPI’ would
be shown, which actually is the CPI up to that
moment
PMP Formulas
 Schedule Variance (SV)
 SV = EV – PV ; EV = Earned Value
PV = Planned Value
 < 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule
PMP Formulas
 Cost Variance (CV)
 CV = EV – AC ; EV = Earned Value
AC = Actual Cost
 < 0 Over budget
= 0 On budget
> 0 Within budget
PMP Formulas
 Estimate at Completion (EAC) if original is
flawed
 EAC = AC + New ETC ; AC = Actual Cost
New ETC = New Estimate to Completion
 if the original estimate is based on wrong
data/assumptions or circumstances have
changed
PMP Formulas
 Estimate at Completion (EAC) if BAC
remains the same
 EAC = AC + BAC – EV ; AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
 the variance is caused by a one-time
event and is not likely to happen again
PMP Formulas
 Estimate at Completion (EAC) if CPI
remains the same
 EAC = BAC/CPI ; BAC = Budget at
completion
CPI = Cost performance index
 if the CPI would remain the same till end
of project, i.e. the original estimation is not
accurate
PMP Formulas
 Estimate at Completion (EAC) if substandard
performance continues
 EAC = AC + (BAC -EV)/(CPI*SPI) ; AC = Actual
Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
 use when the question gives all the values
(AC, BAC, EV, CPI and SPI), otherwise, this
formula is not likely to be used
PMP Formulas
 To-Complete Performance Index (TCPI)
 TCPI = (BAC – EV)/(BAC – AC)
 BAC = Budget at completion
EV = Earned value
AC = Actual Cost
 TCPI = Remaining Work/Remaining Funds
 BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
 < 1 Under budget
= 1 On budget
> 1 Over budget
PMP Formulas
 Estimate to Completion
 ETC = EAC -AC
 EAC = Estimate at Completion
 AC = Actual Cost
 Variance at Completion
 VAC = BAC – EAC
 BAC = Budget at completion
EAC = Estimate at Completion
 < 0 Under budget
= 0 On budget
> 0 Over budget
PMP Formulas
 PERT Estimation
 (O + 4M + P)/6
 O= Optimistic estimate
 M= Most Likely estimate
 P= Pessimistic estimate
PMP Formulas
 Standard Deviation
 (P – O)/6
 O= Optimistic estimate
P= Pessimistic estimate
 this is a rough estimate for the standard
deviation
PMP Formulas
 Float/Slack
 LS – ES
 LS = Late start
ES = Early start
 LF – EF
 LF = Late finish
EF = Early finish
 = 0 On critical path
< 0 Behind schedule

More Related Content

What's hot

PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
ejlp12
 

What's hot (20)

CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
PMO-Framework
PMO-FrameworkPMO-Framework
PMO-Framework
 
BIM Portfolio Daniel Almenares
BIM Portfolio Daniel AlmenaresBIM Portfolio Daniel Almenares
BIM Portfolio Daniel Almenares
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
Pmp5
Pmp5Pmp5
Pmp5
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
The PMO journey
The PMO journeyThe PMO journey
The PMO journey
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
 

Viewers also liked

Gestión del tiempo del proyecto
Gestión del tiempo del proyectoGestión del tiempo del proyecto
Gestión del tiempo del proyecto
Catalina Campos
 

Viewers also liked (14)

Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
 
04 gestion del tiempo
04 gestion del tiempo04 gestion del tiempo
04 gestion del tiempo
 
Project management _ cheat sheet _no1
Project management _ cheat sheet _no1Project management _ cheat sheet _no1
Project management _ cheat sheet _no1
 
Pmp sample questions
Pmp sample questionsPmp sample questions
Pmp sample questions
 
Gestión del tiempo del proyecto
Gestión del tiempo del proyectoGestión del tiempo del proyecto
Gestión del tiempo del proyecto
 
PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4
 
Gestión del Tiempo
Gestión del TiempoGestión del Tiempo
Gestión del Tiempo
 
Program Management Processes Flow in English - 3rd Edition
Program Management Processes Flow in English - 3rd EditionProgram Management Processes Flow in English - 3rd Edition
Program Management Processes Flow in English - 3rd Edition
 
Pmp brain-dump
Pmp brain-dumpPmp brain-dump
Pmp brain-dump
 
PMP Study Group example
PMP Study Group examplePMP Study Group example
PMP Study Group example
 
Taller Gestión del Tiempo - Oct 09
Taller Gestión del Tiempo - Oct 09Taller Gestión del Tiempo - Oct 09
Taller Gestión del Tiempo - Oct 09
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 

Similar to Pmp formulas

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 

Similar to Pmp formulas (20)

Pmp formulas pmbok5
Pmp formulas pmbok5Pmp formulas pmbok5
Pmp formulas pmbok5
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Earned value management
Earned value managementEarned value management
Earned value management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
 

Recently uploaded

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 

Recently uploaded (20)

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 

Pmp formulas

  • 2. PMP Formulas  No. of Communication Channels  n (n-1)/2 n = number of members in the team  n should include the project manager  e.g. if the no. of team members increase from 4 to 5, the increase in communication channels: 5(5-1)/2 – 4(4-1)/2 = 4
  • 3. PMP Formulas  Schedule Performance Index (SPI)  SPI = EV/PV ; EV = Earned Value PV = Planned Value  < 1 behind schedule = 1 on schedule > 1 ahead of schedule
  • 4. PMP Formulas  Cost Performance Index (CPI)  CPI = EV/AC ; EV = Earned Value AC = Actual Cost  < 1 Over budget = 1 On budget > 1 Under budget sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment
  • 5. PMP Formulas  Schedule Variance (SV)  SV = EV – PV ; EV = Earned Value PV = Planned Value  < 0 Behind schedule = 0 On schedule > 0 Ahead of schedule
  • 6. PMP Formulas  Cost Variance (CV)  CV = EV – AC ; EV = Earned Value AC = Actual Cost  < 0 Over budget = 0 On budget > 0 Within budget
  • 7. PMP Formulas  Estimate at Completion (EAC) if original is flawed  EAC = AC + New ETC ; AC = Actual Cost New ETC = New Estimate to Completion  if the original estimate is based on wrong data/assumptions or circumstances have changed
  • 8. PMP Formulas  Estimate at Completion (EAC) if BAC remains the same  EAC = AC + BAC – EV ; AC = Actual Cost BAC = Budget at completion EV = Earned Value  the variance is caused by a one-time event and is not likely to happen again
  • 9. PMP Formulas  Estimate at Completion (EAC) if CPI remains the same  EAC = BAC/CPI ; BAC = Budget at completion CPI = Cost performance index  if the CPI would remain the same till end of project, i.e. the original estimation is not accurate
  • 10. PMP Formulas  Estimate at Completion (EAC) if substandard performance continues  EAC = AC + (BAC -EV)/(CPI*SPI) ; AC = Actual Cost BAC = Budget at completion EV = Earned Value CPI = Cost Performance Index SPI = Schedule Performance Index  use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used
  • 11. PMP Formulas  To-Complete Performance Index (TCPI)  TCPI = (BAC – EV)/(BAC – AC)  BAC = Budget at completion EV = Earned value AC = Actual Cost  TCPI = Remaining Work/Remaining Funds  BAC = Budget at completion EV = Earned value CPI = Cost performance index  < 1 Under budget = 1 On budget > 1 Over budget
  • 12. PMP Formulas  Estimate to Completion  ETC = EAC -AC  EAC = Estimate at Completion  AC = Actual Cost  Variance at Completion  VAC = BAC – EAC  BAC = Budget at completion EAC = Estimate at Completion  < 0 Under budget = 0 On budget > 0 Over budget
  • 13. PMP Formulas  PERT Estimation  (O + 4M + P)/6  O= Optimistic estimate  M= Most Likely estimate  P= Pessimistic estimate
  • 14. PMP Formulas  Standard Deviation  (P – O)/6  O= Optimistic estimate P= Pessimistic estimate  this is a rough estimate for the standard deviation
  • 15. PMP Formulas  Float/Slack  LS – ES  LS = Late start ES = Early start  LF – EF  LF = Late finish EF = Early finish  = 0 On critical path < 0 Behind schedule