SlideShare a Scribd company logo
1 of 19
Download to read offline
1
BASICS OF
EARNED VALUE
MANAGEMENT
2
Why use Earned Value
Management Systems?
“The Bottom Line”
• EVM can focus program management attention on
critical issues and risks during the “project” life
cycle
• How are you doing, and how do you know how you
are doing?
– Early problem identification
• Completion Estimates
– How far along are you? (64%, 50%, >40%)
– What is your productivity/efficiency?
– Work remaining
3
Five Basic Elements
BCWS Budgeted Cost of Work Scheduled
BCWP Budgeted Cost of Work Performed
ACWP Actual Cost of Work Performed
4
5 Basic Performance Data
Questions & Answers
QUESTION ANSWER ACRONYM
How much work should Budgeted Cost for BCWS
be done? Work Scheduled
How much work is done? Budgeted Cost for BCWP
Work Performed
How much did the is done Actual Cost of ACWP
work cost? Work Performed
5
What do we measure progress against?
and Why?
• Performance measurement baseline
– Budget that is spread over . . .
– Time, to accomplish the scope of
– Work, against which progress can be measured
• Earned Value is key concept
– how much progress did I make against my original
plan?
– expressed in dollars or hours
– Why? – early warning
$
time
baseline
earned value
6
Why do we need
Early Warning?
Small course corrections are
easier when made early…
… If you wait until you reach
the Iceberg, its too late!!!
7
Work Budgeted and Earned
• The value of the budgeted work is called:
Budgeted Cost of Work Scheduled
(BCWS)
• The value of work earned is called:
Budgeted Cost of Work Performed
(BCWP)
– BCWP is also called Earned Value (EV)
Budgeted Cost of Work Scheduled
(BCWS)
Total Budget = $5,000
to be spent over 5 months
I plan to lay 1 section
of track each month at an
estimated cost of $1,000.
BCWS each month = $1,000
Total BCWS = $5,000
Month 1
BCWS = $1,000
Month 4
BCWS = $1,000
Month 3
BCWS = $1,000
Month 5
BCWS = $1,000
Month 2
BCWS = $1,000
sum of all BCWS = performance baseline
9
Budgeted Cost of Work Performed
(BCWP)
aka. Earned Value
We’re at the end of
February, Track 1 is
complete and track 2 is ½
done.
BCWS = $1,000
Track 1
Track 2
BCWS = $1,000
50% done
Value of work
performed = $1,500
10
Schedule Variance
BC WS
BC WP
of the work I scheduled to have done,
how much did I budget for it to cost?
of the work I actually performed,
how much did I budget for it to cost?
SCHEDULE VARIANCE is the difference between work scheduled
and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
BUDGET
BASED
example: SV = BCWP - BCWS = $1,500 - $2,000
SV= -$500 (negative = behind schedule)
11
Schedule Variance
$
BCWS
“the baseline”
BCWP
“earned value”
TIME
5,000
sv
12
Actual Cost of Work Performed
(ACWP)
Track 1 Cost = $1,500!
Track 2 Cost = $750 cost to
date
Total Cost to Date = $2,250
13
Cost Variance
BC WP
AC WP
of the work I actually performed,
how much did I budget for it to cost?
of the work I actually performed,
how much did it actually cost?
COST VARIANCE is the difference between budgeted cost
and actual cost
formula: CV $ = BCWP - ACWP
PERFORMANCE
BASED
example: CV = BCWP - ACWP = $1,500 - $2,250
CV= -$750 (negative = cost overrun)
14
Cost Variance
$
TIME
BCWP
“earned value”
ACWP
“actual cost”
5,000
cv
15
Variance Summary
• The difference between the BCWP and the
ACWP is called a cost variance
• The difference between the BCWP and
BCWS is called schedule variance and is
provided in terms of dollars
16
Trend Analysis
Cost Performance Index (CPI) measure of cost efficiency
CPI = Value of Work Completed (BCWP)
Cost of Work Completed (ACWP)
Schedule Performance Index (SPI) measure of schedule efficiency
SPI = Value of Work Completed (BCWP)
Value of Work Planned (BCWS)
Closer to “1” the better
Less than 1 = overrun (CPI); behind schedule (SPI)
Greater than 1 = underrun (CPI); ahead of schedule (SPI)
17
• DO I THINK THE CONTRACTOR WILL COME IN ON BUDGET?
COST PERFORMANCE INDEX:
CPI = cost efficiency for work performed to date
(The value of work accomplished for each dollar spent)
SCHEDULE PERFORMANCE INDEX:
SPI = schedule efficiency with which work has been accomplished
(The rate at which work is being accomplished)
Performance Efficiencies
WORK
= ACCOMPLISHED
ACTUALS
WORK
= ACCOMPLISHED
WORK
SCHEDULED
WORK
BCWP ACCOMPLISHED $1500
= BCWS = WORK = $2000 = .75
SCHEDULED
WORK
BCWP ACCOMPLISHED $1500
= ACWP = ACTUAL = $2250 = .67
COST
18
EXERCISES
• Attendees – Go to your Exercise
Packet
19
Solution
Cost Variance = -10
Schedule Variance = + 20
CPI = .97
SPI = 1.07
• How would you describe this project?
Over budget, ahead of schedule

More Related Content

Similar to Basics of EVM.pdf

Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 

Similar to Basics of EVM.pdf (20)

Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

Basics of EVM.pdf

  • 2. 2 Why use Earned Value Management Systems? “The Bottom Line” • EVM can focus program management attention on critical issues and risks during the “project” life cycle • How are you doing, and how do you know how you are doing? – Early problem identification • Completion Estimates – How far along are you? (64%, 50%, >40%) – What is your productivity/efficiency? – Work remaining
  • 3. 3 Five Basic Elements BCWS Budgeted Cost of Work Scheduled BCWP Budgeted Cost of Work Performed ACWP Actual Cost of Work Performed
  • 4. 4 5 Basic Performance Data Questions & Answers QUESTION ANSWER ACRONYM How much work should Budgeted Cost for BCWS be done? Work Scheduled How much work is done? Budgeted Cost for BCWP Work Performed How much did the is done Actual Cost of ACWP work cost? Work Performed
  • 5. 5 What do we measure progress against? and Why? • Performance measurement baseline – Budget that is spread over . . . – Time, to accomplish the scope of – Work, against which progress can be measured • Earned Value is key concept – how much progress did I make against my original plan? – expressed in dollars or hours – Why? – early warning $ time baseline earned value
  • 6. 6 Why do we need Early Warning? Small course corrections are easier when made early… … If you wait until you reach the Iceberg, its too late!!!
  • 7. 7 Work Budgeted and Earned • The value of the budgeted work is called: Budgeted Cost of Work Scheduled (BCWS) • The value of work earned is called: Budgeted Cost of Work Performed (BCWP) – BCWP is also called Earned Value (EV)
  • 8. Budgeted Cost of Work Scheduled (BCWS) Total Budget = $5,000 to be spent over 5 months I plan to lay 1 section of track each month at an estimated cost of $1,000. BCWS each month = $1,000 Total BCWS = $5,000 Month 1 BCWS = $1,000 Month 4 BCWS = $1,000 Month 3 BCWS = $1,000 Month 5 BCWS = $1,000 Month 2 BCWS = $1,000 sum of all BCWS = performance baseline
  • 9. 9 Budgeted Cost of Work Performed (BCWP) aka. Earned Value We’re at the end of February, Track 1 is complete and track 2 is ½ done. BCWS = $1,000 Track 1 Track 2 BCWS = $1,000 50% done Value of work performed = $1,500
  • 10. 10 Schedule Variance BC WS BC WP of the work I scheduled to have done, how much did I budget for it to cost? of the work I actually performed, how much did I budget for it to cost? SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars) formula: SV $ = BCWP - BCWS BUDGET BASED example: SV = BCWP - BCWS = $1,500 - $2,000 SV= -$500 (negative = behind schedule)
  • 12. 12 Actual Cost of Work Performed (ACWP) Track 1 Cost = $1,500! Track 2 Cost = $750 cost to date Total Cost to Date = $2,250
  • 13. 13 Cost Variance BC WP AC WP of the work I actually performed, how much did I budget for it to cost? of the work I actually performed, how much did it actually cost? COST VARIANCE is the difference between budgeted cost and actual cost formula: CV $ = BCWP - ACWP PERFORMANCE BASED example: CV = BCWP - ACWP = $1,500 - $2,250 CV= -$750 (negative = cost overrun)
  • 15. 15 Variance Summary • The difference between the BCWP and the ACWP is called a cost variance • The difference between the BCWP and BCWS is called schedule variance and is provided in terms of dollars
  • 16. 16 Trend Analysis Cost Performance Index (CPI) measure of cost efficiency CPI = Value of Work Completed (BCWP) Cost of Work Completed (ACWP) Schedule Performance Index (SPI) measure of schedule efficiency SPI = Value of Work Completed (BCWP) Value of Work Planned (BCWS) Closer to “1” the better Less than 1 = overrun (CPI); behind schedule (SPI) Greater than 1 = underrun (CPI); ahead of schedule (SPI)
  • 17. 17 • DO I THINK THE CONTRACTOR WILL COME IN ON BUDGET? COST PERFORMANCE INDEX: CPI = cost efficiency for work performed to date (The value of work accomplished for each dollar spent) SCHEDULE PERFORMANCE INDEX: SPI = schedule efficiency with which work has been accomplished (The rate at which work is being accomplished) Performance Efficiencies WORK = ACCOMPLISHED ACTUALS WORK = ACCOMPLISHED WORK SCHEDULED WORK BCWP ACCOMPLISHED $1500 = BCWS = WORK = $2000 = .75 SCHEDULED WORK BCWP ACCOMPLISHED $1500 = ACWP = ACTUAL = $2250 = .67 COST
  • 18. 18 EXERCISES • Attendees – Go to your Exercise Packet
  • 19. 19 Solution Cost Variance = -10 Schedule Variance = + 20 CPI = .97 SPI = 1.07 • How would you describe this project? Over budget, ahead of schedule