SlideShare a Scribd company logo
1 of 20
ENVIRONMENTAL
SAFEGUARD FOR
ROAD PROJECTS
Dr Deepak Kumar Tripathi
researchenviro@gmail.com
9755104410
Environment Expert- IDC Bhopal
SAFEGUARD DEFINITION
 A measure taken to protect someone or
something or to prevent something which is
undesirable.
 Something that provides protection against
possible loss, damage, etc.
 Protect from harm or damage with an
2
SOCIAL
Public participation
(Male, Female, Senior citizen,
students)
Environment
Physical, Social, Biological
Safety and mobility
Workers and Public
Engineering Design
Socially acceptable
Environmentally sound and
Economically sustainable
Safeguard
ENVIRONMENTAL PROJECT CATEGORY
Proposed projects are screened according to type, location, scale, and sensitivity
and
the magnitude of their potential environmental impacts, including direct, indirect,
induced, and cumulative impacts. Projects are classified into the following four
categories:
 Category A. A proposed project is likely to have significant adverse
environmental impacts that are irreversible, diverse, or unprecedented. These
impacts may affect an area larger than the sites or facilities subject to physical
works. An environmental impact assessment (EIA), including an environmental
management plan (EMP), is required.
 Category B. The proposed project’s potential adverse environmental impacts
are site-specific, few if any of them are irreversible, and in most cases mitigation
measures can be designed more readily than for category A projects. An initial
environmental examination (IEE), including an EMP, is required.
 Category C. A proposed project is likely to have minimal or no adverse
environmental impacts. An EIA or IEE is not required, although environmental
implications need to be reviewed.
OFFICIAL SETUP IN PMU-WB
WB – AIIB
•MPRCP-CMGSY
•Upgradation of 10000km (Gravel to BT)
•New connectivity 510km (Earthen road to BT)
Safeguard Cell
•PMU-MPRRDA-CGM,GM,AM
•PIU-District- GM,FNO,AM
•Contractor & SQC team safeguard expert and
engineers
•PMC- IDC, Safeguard Expert team
•PIC- ORG, Safeguard Expert team
GUIDELINE DOCUMENTS- AVAILABLE WITH WB
WB-AIIB
ESMF (Environmental Social Management Framework)
A.SMF Social Management Framework (CPF)
B.VF (Venerable Framework)
C.EMF (Environment Management Framework)
D. ECoP (Environment Codes of Practice)
PAD: Project Appraisal Document
ESHS Parameters Particulars Responses/Compliance
Compliance: Compliance status for conditions of all relevant consents/permits,
for the Work, including quarries, etc.): statement of compliance or
listing of issues and actions taken (or to be taken) to reach
compliance
Compliance status of ESMP/ESIP requirements: statement of
compliance or listing of issues and actions taken (or to be taken)
to reach compliance
Other unresolved issues from previous months related to
environmental and social: continued violations, continued failure
of equipment, continued lack of vehicle covers, spills not dealt
with, continued compensation or blasting issues, etc. Cross-
reference other sections as needed.
Compliance report will be
submit as required
(Signature of Contractor)
Format for Contractor Reporting (ES
ROLE OF PIU FOR SAFEGUARD
 To assure DPR should have IEE checklist
 To assure the IEE findings are reflects in the
DPR technical part as environmental
management cost.
 Put effort to avoid tree cutting and focus the
tree plantation.
 Ensure the Labours are using PPEs while
they work at site like Helmet, jackets, boots
Gloves etc.
The roles and responsibilities of the Safeguards Cell at MPRRDA shall
include:
1. Coordination of planning and implementation of environmental and social
management aspects of MPRCP.
2. Obtain clearances through concerned PIUs from the line departments,
especially MoEF&CC, Forest Department, SPCB (as applicable).
3. Monitor MPRCP rural roads for fulfillment of ESMF provisions in co-
ordination with the PMC, Panel of Retired Senior Engineers of Road
Sector and PIUs.
4. Organize training program with the help of PMC for PIUs, Panel of
Retired Senior Engineers of Road Sector and Contractors for capacity
building for implementation of EMF and ECoPs
5. Mobilize community and ensure their participation in addressing
ESMF/ECoPs provisions.
6. Inspection, monitoring and report progress, highlighting environmental
and social issues not addressed, to provide for further course of
correction.
ROLE OF SAFEGUARD CELLAT MPRRDA (PMU)
BULLET CONTENT OF DPR
 Technical part
 DPR Template Annexure to ITB- Modified
DPR Templates (Available in MPRRDA
website)
 Safeguard Part
 Social format
 Environmental Format (IEE)
 Environmental Management Plan (EMaP)
 Annexure as required by format
GENERIC ENVIRONMENT
MANAGEMENT PLAN (EMaP)
 Environment Management Plan (EMaP) is a
document which shows the mitigation measures
of the particular environmental loss of the
project area. It follows the rules of ECoPs and
other state prevailing environmental laws. The
EMaPs covers the short term and long term
effects of the project and how it will affect our
environment as well as how we can manage
with taken effective measures.
COMMON DPR SAFEGUARD COMMENTS
 For safeguard (Social and Environment) the experts are not giving their efficient
input.
 Social safeguard and Environment safeguard file not attached and if attached
they are not filled in proper manner.
 Many format attachments are missing.
 Tree list, utilities and community structure list not properly recorded.
 Tree cutting list information not given and what will be the plantation scheme
proposed.
 CPF file have not signed by the PIU and Sarpanch wherever is required.
 CPF not given questionnaire according answer/response but its filled very
casually like below
 Question: Are community giving any suggestion?
 Answer: Yes, the suggestion given by the community is incorporated
(but
not mentions the type of suggestion they gave).
 Transect walk findings not gave detail information as required.
 Community consultation photographs not attached.
 Consultant used villagers services for their own work like holding chainage slate
 Their environmental and social experts not had gone through
the safeguard report not even field.
 No APs and VAPs found in earthen road is also a big
question of transect walk survey.
 Women participation ratio is very less or negligible in DPR
transect walk.
 Many data are not matched with the actual site condition as
attached photographs.
 Sequences of the pages are missing. Papers are attached in
any where find space.
 Photo plate’s captions are the same repetitive manner
instead of particular.
 Very low participation of the community. CPF Report is made
technically sound instead of socially sound.
Safeguard
s
WORK PIPELINE
PIU/PMC/PIC
ROAD
DPR
consulta
nt
DPR
Tende
r
Contract
or
Review
DPR
GAPS
 DPR consultant
 DPR preparation
 PIU level
WORK FOR OUR
FUTURE GENERATION
WORK FOR HEALTHY
ENVIRONMENT

More Related Content

What's hot

EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projectsAnchal Garg
 
Environmental Management Plan
Environmental Management PlanEnvironmental Management Plan
Environmental Management PlanShehab Sajeeb
 
Environment Social and road safety safeguard
Environment Social and road safety safeguardEnvironment Social and road safety safeguard
Environment Social and road safety safeguardDr Deepak Kumar Tripathi
 
Project Cycle and the World Bank Environmental and Social Framework (ESF)
Project Cycle and the World Bank Environmental and Social Framework (ESF)Project Cycle and the World Bank Environmental and Social Framework (ESF)
Project Cycle and the World Bank Environmental and Social Framework (ESF)MamoudBelloAbubakar
 
Environmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environmentEnvironmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environmentDr. Felicia Chinwe Mogo
 
Environmental and social due diligence
Environmental and social due diligenceEnvironmental and social due diligence
Environmental and social due diligenceJini Rajendran
 
Environmental impact assessment in nepal
Environmental impact assessment in nepalEnvironmental impact assessment in nepal
Environmental impact assessment in nepalBhim Upadhyaya
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction managementsrinivas2036
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)SANDEEP PATRE
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentBimal Antony
 
Chapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptChapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptssuserb4074f
 
Introduction to Carbon Footprint Calculation and the Importance
Introduction to Carbon Footprint Calculation and the Importance Introduction to Carbon Footprint Calculation and the Importance
Introduction to Carbon Footprint Calculation and the Importance Janathakshan Gte Ltd
 
EIA report presentation
EIA report presentationEIA report presentation
EIA report presentationsujit roy
 
Environmental impact assessment 2020
Environmental impact assessment 2020Environmental impact assessment 2020
Environmental impact assessment 2020Chandrakant Singh
 
EIA Report on Ring road lahore
EIA Report on Ring road lahoreEIA Report on Ring road lahore
EIA Report on Ring road lahoreAyesha Akhtar
 
EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009Jenson Samraj
 
Environmental management
Environmental  management Environmental  management
Environmental management Omer Shaikh
 

What's hot (20)

EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projects
 
IEE,EMaP plan for Road projects
IEE,EMaP plan for Road projectsIEE,EMaP plan for Road projects
IEE,EMaP plan for Road projects
 
Environmental Management Plan
Environmental Management PlanEnvironmental Management Plan
Environmental Management Plan
 
Environment Social and road safety safeguard
Environment Social and road safety safeguardEnvironment Social and road safety safeguard
Environment Social and road safety safeguard
 
Project Cycle and the World Bank Environmental and Social Framework (ESF)
Project Cycle and the World Bank Environmental and Social Framework (ESF)Project Cycle and the World Bank Environmental and Social Framework (ESF)
Project Cycle and the World Bank Environmental and Social Framework (ESF)
 
Environmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environmentEnvironmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environment
 
Environmental and social due diligence
Environmental and social due diligenceEnvironmental and social due diligence
Environmental and social due diligence
 
Eia eis fonsi
Eia eis fonsiEia eis fonsi
Eia eis fonsi
 
Environmental impact assessment in nepal
Environmental impact assessment in nepalEnvironmental impact assessment in nepal
Environmental impact assessment in nepal
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction management
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Chapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptChapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.ppt
 
Introduction to Carbon Footprint Calculation and the Importance
Introduction to Carbon Footprint Calculation and the Importance Introduction to Carbon Footprint Calculation and the Importance
Introduction to Carbon Footprint Calculation and the Importance
 
EIA report presentation
EIA report presentationEIA report presentation
EIA report presentation
 
Environmental Impact Assessment in Water Resources Projects
Environmental Impact Assessment in Water Resources ProjectsEnvironmental Impact Assessment in Water Resources Projects
Environmental Impact Assessment in Water Resources Projects
 
Environmental impact assessment 2020
Environmental impact assessment 2020Environmental impact assessment 2020
Environmental impact assessment 2020
 
EIA Report on Ring road lahore
EIA Report on Ring road lahoreEIA Report on Ring road lahore
EIA Report on Ring road lahore
 
EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009
 
Environmental management
Environmental  management Environmental  management
Environmental management
 

Similar to Environment safeguard for Road projects

Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentArunAngadi5
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5Bibhabasu Mohanty
 
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the PhilippinesEIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the PhilippinesMakrisMontejoMalinam
 
IRJET- Health, Safety and Environment Management Plan in Construction
IRJET- Health, Safety and Environment Management Plan in ConstructionIRJET- Health, Safety and Environment Management Plan in Construction
IRJET- Health, Safety and Environment Management Plan in ConstructionIRJET Journal
 
5 social accountability (english)
5 social accountability (english)5 social accountability (english)
5 social accountability (english)Article33
 
Planning And Development Department Strategic Operational Plan
Planning And Development Department Strategic Operational PlanPlanning And Development Department Strategic Operational Plan
Planning And Development Department Strategic Operational PlanFrank Miles
 
Phil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSISPhil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSISABEGAILBENCALO1
 
South africaprojectprojectproposal20151102
South africaprojectprojectproposal20151102South africaprojectprojectproposal20151102
South africaprojectprojectproposal20151102Patrícia Pereira
 
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )sandeepprasad87
 
20220224 turkey oiz_project_governance_framework
20220224 turkey oiz_project_governance_framework20220224 turkey oiz_project_governance_framework
20220224 turkey oiz_project_governance_frameworkElifGzdeDoyuran
 
EIA Report Preparation and its Challenges.pptx
 EIA Report Preparation and its Challenges.pptx EIA Report Preparation and its Challenges.pptx
EIA Report Preparation and its Challenges.pptxAmit Chaudhary
 
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...Semakula Allan Kinene
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSamanth kumar
 
Environmental impact assessment
Environmental impact assessment Environmental impact assessment
Environmental impact assessment BiplobDas38
 
Comprehensive Parking Master Plan Presentation (April 2015)
Comprehensive Parking Master Plan Presentation (April 2015)Comprehensive Parking Master Plan Presentation (April 2015)
Comprehensive Parking Master Plan Presentation (April 2015)larsonn
 
Eia - environmental impact assessment
Eia - environmental impact assessmentEia - environmental impact assessment
Eia - environmental impact assessmentParth Patel
 

Similar to Environment safeguard for Road projects (20)

Chief Minister Gram Sadak Yojana (CMGSY)
Chief Minister Gram Sadak Yojana (CMGSY)Chief Minister Gram Sadak Yojana (CMGSY)
Chief Minister Gram Sadak Yojana (CMGSY)
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessment
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5
 
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the PhilippinesEIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
 
Question
QuestionQuestion
Question
 
IRJET- Health, Safety and Environment Management Plan in Construction
IRJET- Health, Safety and Environment Management Plan in ConstructionIRJET- Health, Safety and Environment Management Plan in Construction
IRJET- Health, Safety and Environment Management Plan in Construction
 
5 social accountability (english)
5 social accountability (english)5 social accountability (english)
5 social accountability (english)
 
Planning And Development Department Strategic Operational Plan
Planning And Development Department Strategic Operational PlanPlanning And Development Department Strategic Operational Plan
Planning And Development Department Strategic Operational Plan
 
Phil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSISPhil-EIA-history_issues, REPORT AND ANALYSIS
Phil-EIA-history_issues, REPORT AND ANALYSIS
 
South africaprojectprojectproposal20151102
South africaprojectprojectproposal20151102South africaprojectprojectproposal20151102
South africaprojectprojectproposal20151102
 
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
 
PEISS
PEISSPEISS
PEISS
 
20220224 turkey oiz_project_governance_framework
20220224 turkey oiz_project_governance_framework20220224 turkey oiz_project_governance_framework
20220224 turkey oiz_project_governance_framework
 
EIA Report Preparation and its Challenges.pptx
 EIA Report Preparation and its Challenges.pptx EIA Report Preparation and its Challenges.pptx
EIA Report Preparation and its Challenges.pptx
 
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Environmental impact assessment
Environmental impact assessment Environmental impact assessment
Environmental impact assessment
 
EIA;- EC
EIA;- ECEIA;- EC
EIA;- EC
 
Comprehensive Parking Master Plan Presentation (April 2015)
Comprehensive Parking Master Plan Presentation (April 2015)Comprehensive Parking Master Plan Presentation (April 2015)
Comprehensive Parking Master Plan Presentation (April 2015)
 
Eia - environmental impact assessment
Eia - environmental impact assessmentEia - environmental impact assessment
Eia - environmental impact assessment
 

Recently uploaded

Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsprasan26
 
办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书zdzoqco
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhidelih Escorts
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdfsrivastavaakshat51
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Open Access Research Paper
 
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书zdzoqco
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...Aqsa Yasmin
 
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesGwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
AI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptxAI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptxNeoV2
 
Group 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfGroup 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfs2015004
 
Soil pollution causes effects remedial measures
Soil pollution causes effects remedial measuresSoil pollution causes effects remedial measures
Soil pollution causes effects remedial measuresvasubhanot1234
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一F dds
 
earthquake drill seminar for schools.pptx
earthquake drill  seminar for schools.pptxearthquake drill  seminar for schools.pptx
earthquake drill seminar for schools.pptxBfpSiniloanFSLaguna
 
Thessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfThessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfTheaMan11
 

Recently uploaded (20)

Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCREscort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnids
 
办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...
 
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
办理英属哥伦比亚大学毕业证成绩单|购买加拿大UBC文凭证书
 
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
 
FULL ENJOY Call Girls In kashmiri gate (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In  kashmiri gate (Delhi) Call Us 9953056974FULL ENJOY Call Girls In  kashmiri gate (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In kashmiri gate (Delhi) Call Us 9953056974
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
 
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesGwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Gwalior Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
AI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptxAI and Ecology - The H4rmony Project.pptx
AI and Ecology - The H4rmony Project.pptx
 
Group 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfGroup 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdf
 
Soil pollution causes effects remedial measures
Soil pollution causes effects remedial measuresSoil pollution causes effects remedial measures
Soil pollution causes effects remedial measures
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
办理学位证(KU证书)堪萨斯大学毕业证成绩单原版一比一
 
earthquake drill seminar for schools.pptx
earthquake drill  seminar for schools.pptxearthquake drill  seminar for schools.pptx
earthquake drill seminar for schools.pptx
 
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi NcrCall Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
Thessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfThessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdf
 

Environment safeguard for Road projects

  • 1. ENVIRONMENTAL SAFEGUARD FOR ROAD PROJECTS Dr Deepak Kumar Tripathi researchenviro@gmail.com 9755104410 Environment Expert- IDC Bhopal
  • 2. SAFEGUARD DEFINITION  A measure taken to protect someone or something or to prevent something which is undesirable.  Something that provides protection against possible loss, damage, etc.  Protect from harm or damage with an 2
  • 3. SOCIAL Public participation (Male, Female, Senior citizen, students) Environment Physical, Social, Biological Safety and mobility Workers and Public Engineering Design Socially acceptable Environmentally sound and Economically sustainable Safeguard
  • 4. ENVIRONMENTAL PROJECT CATEGORY Proposed projects are screened according to type, location, scale, and sensitivity and the magnitude of their potential environmental impacts, including direct, indirect, induced, and cumulative impacts. Projects are classified into the following four categories:  Category A. A proposed project is likely to have significant adverse environmental impacts that are irreversible, diverse, or unprecedented. These impacts may affect an area larger than the sites or facilities subject to physical works. An environmental impact assessment (EIA), including an environmental management plan (EMP), is required.  Category B. The proposed project’s potential adverse environmental impacts are site-specific, few if any of them are irreversible, and in most cases mitigation measures can be designed more readily than for category A projects. An initial environmental examination (IEE), including an EMP, is required.  Category C. A proposed project is likely to have minimal or no adverse environmental impacts. An EIA or IEE is not required, although environmental implications need to be reviewed.
  • 5. OFFICIAL SETUP IN PMU-WB WB – AIIB •MPRCP-CMGSY •Upgradation of 10000km (Gravel to BT) •New connectivity 510km (Earthen road to BT) Safeguard Cell •PMU-MPRRDA-CGM,GM,AM •PIU-District- GM,FNO,AM •Contractor & SQC team safeguard expert and engineers •PMC- IDC, Safeguard Expert team •PIC- ORG, Safeguard Expert team
  • 6. GUIDELINE DOCUMENTS- AVAILABLE WITH WB WB-AIIB ESMF (Environmental Social Management Framework) A.SMF Social Management Framework (CPF) B.VF (Venerable Framework) C.EMF (Environment Management Framework) D. ECoP (Environment Codes of Practice) PAD: Project Appraisal Document
  • 7. ESHS Parameters Particulars Responses/Compliance Compliance: Compliance status for conditions of all relevant consents/permits, for the Work, including quarries, etc.): statement of compliance or listing of issues and actions taken (or to be taken) to reach compliance Compliance status of ESMP/ESIP requirements: statement of compliance or listing of issues and actions taken (or to be taken) to reach compliance Other unresolved issues from previous months related to environmental and social: continued violations, continued failure of equipment, continued lack of vehicle covers, spills not dealt with, continued compensation or blasting issues, etc. Cross- reference other sections as needed. Compliance report will be submit as required (Signature of Contractor) Format for Contractor Reporting (ES
  • 8. ROLE OF PIU FOR SAFEGUARD  To assure DPR should have IEE checklist  To assure the IEE findings are reflects in the DPR technical part as environmental management cost.  Put effort to avoid tree cutting and focus the tree plantation.  Ensure the Labours are using PPEs while they work at site like Helmet, jackets, boots Gloves etc.
  • 9. The roles and responsibilities of the Safeguards Cell at MPRRDA shall include: 1. Coordination of planning and implementation of environmental and social management aspects of MPRCP. 2. Obtain clearances through concerned PIUs from the line departments, especially MoEF&CC, Forest Department, SPCB (as applicable). 3. Monitor MPRCP rural roads for fulfillment of ESMF provisions in co- ordination with the PMC, Panel of Retired Senior Engineers of Road Sector and PIUs. 4. Organize training program with the help of PMC for PIUs, Panel of Retired Senior Engineers of Road Sector and Contractors for capacity building for implementation of EMF and ECoPs 5. Mobilize community and ensure their participation in addressing ESMF/ECoPs provisions. 6. Inspection, monitoring and report progress, highlighting environmental and social issues not addressed, to provide for further course of correction. ROLE OF SAFEGUARD CELLAT MPRRDA (PMU)
  • 10. BULLET CONTENT OF DPR  Technical part  DPR Template Annexure to ITB- Modified DPR Templates (Available in MPRRDA website)  Safeguard Part  Social format  Environmental Format (IEE)  Environmental Management Plan (EMaP)  Annexure as required by format
  • 11.
  • 12.
  • 13.
  • 14.
  • 15. GENERIC ENVIRONMENT MANAGEMENT PLAN (EMaP)  Environment Management Plan (EMaP) is a document which shows the mitigation measures of the particular environmental loss of the project area. It follows the rules of ECoPs and other state prevailing environmental laws. The EMaPs covers the short term and long term effects of the project and how it will affect our environment as well as how we can manage with taken effective measures.
  • 16. COMMON DPR SAFEGUARD COMMENTS  For safeguard (Social and Environment) the experts are not giving their efficient input.  Social safeguard and Environment safeguard file not attached and if attached they are not filled in proper manner.  Many format attachments are missing.  Tree list, utilities and community structure list not properly recorded.  Tree cutting list information not given and what will be the plantation scheme proposed.  CPF file have not signed by the PIU and Sarpanch wherever is required.  CPF not given questionnaire according answer/response but its filled very casually like below  Question: Are community giving any suggestion?  Answer: Yes, the suggestion given by the community is incorporated (but not mentions the type of suggestion they gave).  Transect walk findings not gave detail information as required.  Community consultation photographs not attached.  Consultant used villagers services for their own work like holding chainage slate
  • 17.  Their environmental and social experts not had gone through the safeguard report not even field.  No APs and VAPs found in earthen road is also a big question of transect walk survey.  Women participation ratio is very less or negligible in DPR transect walk.  Many data are not matched with the actual site condition as attached photographs.  Sequences of the pages are missing. Papers are attached in any where find space.  Photo plate’s captions are the same repetitive manner instead of particular.  Very low participation of the community. CPF Report is made technically sound instead of socially sound.
  • 19. GAPS  DPR consultant  DPR preparation  PIU level
  • 20. WORK FOR OUR FUTURE GENERATION WORK FOR HEALTHY ENVIRONMENT