SlideShare a Scribd company logo
1 of 2
Download to read offline
TECHNICAL INSTALLATION
TECHNICALINSTALLATION
Location
Chachoengsao, Th.
Duration
3 Days
Dimensions (m)
EvaporatorL23.6xW2.6xH2.8
DistillationL16xW1.4xH2.4
SeparatorL9.5xW2.6xH2.9
Pillar Fan L4.3xW3xH3.2
Weight
Evaporator 28 T
Distillation 4 T
Separator 6.5 T
Pillar Fan 8.5 T
Total Tonnage 47 T




SCOPE
CEA Project Logistics completed a potentially
difficult and technical installation for a well-known
drinks manufacturer in Chachoengsao, Thailand.
CEA provided Transportation, Lifting and the
Installation of several parts of distillation columns,
evaporators, separators and fans.
All parts were discharged through the night at Laem Chabang
Port and loaded on to several trailers. Due to its size and weight
the Evaporator Chamber was loaded on to a multi-axle hydraulic
trailer. The parts were transported and unloaded at the factory’s
lay down area. After a site inspection two mobile cranes were
moved into their positions.
The Evaporator Chamber was lifted by both cranes until the
chamber was vertical then the smaller crane was unhooked while
the larger 500 T crane continued the lift into the facility. CEA teams
ensured the safe lowering of the evaporator through the facility.
CASE STUDY		 CS016
Technical Installation 1/2
EVAPORATOR CHAMBER TRANSPORTATION DISTILLATION CHAMBER TRANSPORTATION
TECHNICALINSTALLATION
CEA PROJECT LOGISTICS
41/13 M1 AO-UDOM ROAD
TUNGSUNGKHLA
SRI RACHA
CHONBURI 20230
THAILAND
+66 38 354 019
www.ceaprojects.com
The 16 metre distillation chamber was installed using the same lift
technique as the Evaporator, CEA teams once again were located
on several floors ensuring a safe installation and aligning it to the
previously installed Evaporator. Smaller parts were unloaded and
assembled at the installation site and lifted into the facility. All
aspects of the project were completed in a timely and efficient
manner and within budget.
CASE STUDY		 CS016
Technical Installation 2/2
SEPARATOR LOWERED INTO POSITION
CHAMBER LOWERED THROUGH EACH FLOOR
SEPARATOR BEING READIED FOR LIFT
ALIGNING THE CHAMBER TO ITS BASE
THE W100 28 TONNE EVAPORATOR CHAMBER IS CAREFULLY LOWERED INTO THE FACILITY
CEA ON-SITE TOOLBOX TALK TWO CRANES LIFT THE EVAPORATOR
SMALLER PARTS LOWERED INTO POSITION BOTH MAIN CHAMBERS ALIGNED INSIDE

More Related Content

What's hot

Reverse rotaion of co2 compressor
Reverse rotaion of co2 compressorReverse rotaion of co2 compressor
Reverse rotaion of co2 compressorPrem Baboo
 
Vacumme pump-rotary
Vacumme pump-rotaryVacumme pump-rotary
Vacumme pump-rotaryacmasindia
 
Safe bunkering practices
Safe bunkering practicesSafe bunkering practices
Safe bunkering practicesRaktim Maitra
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
Debris / Junk Catcher Manifold - Worldwide Oilfield Machine
Debris / Junk Catcher Manifold - Worldwide Oilfield MachineDebris / Junk Catcher Manifold - Worldwide Oilfield Machine
Debris / Junk Catcher Manifold - Worldwide Oilfield Machinewomgroup
 
Fresh water generator maintenance
Fresh water generator maintenanceFresh water generator maintenance
Fresh water generator maintenanceViktor Bily
 
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZIHIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZIwina kauzi
 
KNPC Shuaiba Refinery Kuwait - Canada (2)
KNPC Shuaiba Refinery Kuwait - Canada (2)KNPC Shuaiba Refinery Kuwait - Canada (2)
KNPC Shuaiba Refinery Kuwait - Canada (2)Waqas Amjad
 
internship report by usama
internship report by usamainternship report by usama
internship report by usamamuhammad usama
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOCqazi faisal
 
Bayliss Capabilities
Bayliss CapabilitiesBayliss Capabilities
Bayliss CapabilitiesMike Scott
 
Weiler E1250A Remixing Transfer Vehicle
Weiler E1250A Remixing Transfer VehicleWeiler E1250A Remixing Transfer Vehicle
Weiler E1250A Remixing Transfer Vehicleweilersales
 
Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankersjabbar2002pk200
 
Synchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV gridSynchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV gridManohar Tatwawadi
 

What's hot (20)

drain pit(1)
drain pit(1)drain pit(1)
drain pit(1)
 
Reverse rotaion of co2 compressor
Reverse rotaion of co2 compressorReverse rotaion of co2 compressor
Reverse rotaion of co2 compressor
 
Vacumme pump-rotary
Vacumme pump-rotaryVacumme pump-rotary
Vacumme pump-rotary
 
Safe bunkering practices
Safe bunkering practicesSafe bunkering practices
Safe bunkering practices
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Debris / Junk Catcher Manifold - Worldwide Oilfield Machine
Debris / Junk Catcher Manifold - Worldwide Oilfield MachineDebris / Junk Catcher Manifold - Worldwide Oilfield Machine
Debris / Junk Catcher Manifold - Worldwide Oilfield Machine
 
Fresh water generator maintenance
Fresh water generator maintenanceFresh water generator maintenance
Fresh water generator maintenance
 
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZIHIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
HIGH PRESUURE LEACH PLANT PRESENTATION - W KAUZI
 
KNPC Shuaiba Refinery Kuwait - Canada (2)
KNPC Shuaiba Refinery Kuwait - Canada (2)KNPC Shuaiba Refinery Kuwait - Canada (2)
KNPC Shuaiba Refinery Kuwait - Canada (2)
 
Lpg Bottling Plant
Lpg Bottling PlantLpg Bottling Plant
Lpg Bottling Plant
 
internship report by usama
internship report by usamainternship report by usama
internship report by usama
 
Bfwp
BfwpBfwp
Bfwp
 
Renovation
RenovationRenovation
Renovation
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOC
 
Bayliss Capabilities
Bayliss CapabilitiesBayliss Capabilities
Bayliss Capabilities
 
Weiler E1250A Remixing Transfer Vehicle
Weiler E1250A Remixing Transfer VehicleWeiler E1250A Remixing Transfer Vehicle
Weiler E1250A Remixing Transfer Vehicle
 
Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankers
 
Synchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV gridSynchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV grid
 
Project Final
Project FinalProject Final
Project Final
 

Viewers also liked

Viewers also liked (14)

CEA SURELIFT Brochure 2015
CEA SURELIFT Brochure 2015CEA SURELIFT Brochure 2015
CEA SURELIFT Brochure 2015
 
The Dynamic Workspace: An Emaar story
The Dynamic Workspace: An Emaar storyThe Dynamic Workspace: An Emaar story
The Dynamic Workspace: An Emaar story
 
Fleet & Equipment
Fleet & EquipmentFleet & Equipment
Fleet & Equipment
 
Fuso Trucks - Fv54 prime mover_tsh55_a
Fuso Trucks - Fv54 prime mover_tsh55_aFuso Trucks - Fv54 prime mover_tsh55_a
Fuso Trucks - Fv54 prime mover_tsh55_a
 
ایمنی ریگری و علامت ده جرثقیل
ایمنی ریگری و علامت ده جرثقیلایمنی ریگری و علامت ده جرثقیل
ایمنی ریگری و علامت ده جرثقیل
 
Operating Conditions for Prime Mover & Trailers
Operating Conditions for Prime Mover & TrailersOperating Conditions for Prime Mover & Trailers
Operating Conditions for Prime Mover & Trailers
 
02 3 prime-movers
02 3 prime-movers02 3 prime-movers
02 3 prime-movers
 
Container Handling Equipments
Container Handling EquipmentsContainer Handling Equipments
Container Handling Equipments
 
India :Ports Sector Report_August 2013
India :Ports Sector Report_August 2013India :Ports Sector Report_August 2013
India :Ports Sector Report_August 2013
 
Lifting Sling Safety
Lifting Sling SafetyLifting Sling Safety
Lifting Sling Safety
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
 
Operating practices
Operating practicesOperating practices
Operating practices
 
Port operations & management slideshow
Port operations & management slideshowPort operations & management slideshow
Port operations & management slideshow
 
Hacking the Creative Brain - Web Directions 2015
Hacking the Creative Brain - Web Directions 2015Hacking the Creative Brain - Web Directions 2015
Hacking the Creative Brain - Web Directions 2015
 

Similar to Technical Installation

Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerTheodoros Dragonas
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerTheodoros Dragonas
 
CEA Myanmar - Bottle Washer Relocation
CEA Myanmar - Bottle Washer RelocationCEA Myanmar - Bottle Washer Relocation
CEA Myanmar - Bottle Washer RelocationCEA Project Logistics
 
Indonesia flow station lifted in simultaneous jacking operation - Offshore
Indonesia flow station lifted in simultaneous jacking operation - OffshoreIndonesia flow station lifted in simultaneous jacking operation - Offshore
Indonesia flow station lifted in simultaneous jacking operation - OffshoreNurdin .
 
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014Dylan Olivier
 
Stockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with PrideStockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with PrideThomas Ingrey
 
Design and fabrication of car parking system th esis
Design and fabrication of car parking system th esisDesign and fabrication of car parking system th esis
Design and fabrication of car parking system th esisankit chauhan
 
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementReport on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementSujit Tharakan
 
In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour systemKotesh Bhukya
 
Coffer dams 01
Coffer dams 01Coffer dams 01
Coffer dams 01juwes
 
WorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdownWorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdownMorgan Swanlund
 
ArupConceptElevatingACEPlatformsbrochurecopyrightArup
ArupConceptElevatingACEPlatformsbrochurecopyrightArupArupConceptElevatingACEPlatformsbrochurecopyrightArup
ArupConceptElevatingACEPlatformsbrochurecopyrightArupGlynn Thomas
 

Similar to Technical Installation (20)

Technical Lifting
Technical LiftingTechnical Lifting
Technical Lifting
 
Crane Demobilization
Crane DemobilizationCrane Demobilization
Crane Demobilization
 
Injection Mould Demob & Export
Injection Mould Demob & ExportInjection Mould Demob & Export
Injection Mould Demob & Export
 
Seahawk Helicopter Transportation
Seahawk Helicopter TransportationSeahawk Helicopter Transportation
Seahawk Helicopter Transportation
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
 
CEA Myanmar - Bottle Washer Relocation
CEA Myanmar - Bottle Washer RelocationCEA Myanmar - Bottle Washer Relocation
CEA Myanmar - Bottle Washer Relocation
 
Indonesia flow station lifted in simultaneous jacking operation - Offshore
Indonesia flow station lifted in simultaneous jacking operation - OffshoreIndonesia flow station lifted in simultaneous jacking operation - Offshore
Indonesia flow station lifted in simultaneous jacking operation - Offshore
 
Dual Penetrator Catamaran Launch
Dual Penetrator Catamaran LaunchDual Penetrator Catamaran Launch
Dual Penetrator Catamaran Launch
 
78-83-NovDec12
78-83-NovDec1278-83-NovDec12
78-83-NovDec12
 
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
OFFSHORE CV DYLAN OLIVIER UPDATE Oct 2014
 
Deep Energy Description
Deep Energy DescriptionDeep Energy Description
Deep Energy Description
 
Stockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with PrideStockley Week 22 Airport Lines Possession - Share with Pride
Stockley Week 22 Airport Lines Possession - Share with Pride
 
Bottle Blower Installation
Bottle Blower InstallationBottle Blower Installation
Bottle Blower Installation
 
Design and fabrication of car parking system th esis
Design and fabrication of car parking system th esisDesign and fabrication of car parking system th esis
Design and fabrication of car parking system th esis
 
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementReport on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
 
In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour system
 
Coffer dams 01
Coffer dams 01Coffer dams 01
Coffer dams 01
 
WorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdownWorldPipelines-IsolateorShutdown
WorldPipelines-IsolateorShutdown
 
ArupConceptElevatingACEPlatformsbrochurecopyrightArup
ArupConceptElevatingACEPlatformsbrochurecopyrightArupArupConceptElevatingACEPlatformsbrochurecopyrightArup
ArupConceptElevatingACEPlatformsbrochurecopyrightArup
 

More from CEA Project Logistics

Bottle Manufacturing Plant, Assembly & Installation
Bottle Manufacturing Plant, Assembly & InstallationBottle Manufacturing Plant, Assembly & Installation
Bottle Manufacturing Plant, Assembly & InstallationCEA Project Logistics
 

More from CEA Project Logistics (20)

Catamaran Transport & Export
Catamaran Transport & ExportCatamaran Transport & Export
Catamaran Transport & Export
 
CEA & Fagioli Italy
CEA & Fagioli ItalyCEA & Fagioli Italy
CEA & Fagioli Italy
 
Power Plant Demobilisation
Power Plant DemobilisationPower Plant Demobilisation
Power Plant Demobilisation
 
Drill Rig Transportation
Drill Rig TransportationDrill Rig Transportation
Drill Rig Transportation
 
CEA Project Logistics Brochure 2016
CEA Project Logistics Brochure 2016CEA Project Logistics Brochure 2016
CEA Project Logistics Brochure 2016
 
Bottle Manufacturing Plant, Assembly & Installation
Bottle Manufacturing Plant, Assembly & InstallationBottle Manufacturing Plant, Assembly & Installation
Bottle Manufacturing Plant, Assembly & Installation
 
Drill Pipe Storage & Transportation
Drill Pipe Storage & TransportationDrill Pipe Storage & Transportation
Drill Pipe Storage & Transportation
 
CEA Ao-Udom Facility
CEA Ao-Udom FacilityCEA Ao-Udom Facility
CEA Ao-Udom Facility
 
Steel Handling & Consolidation
Steel Handling & ConsolidationSteel Handling & Consolidation
Steel Handling & Consolidation
 
CEA Project Logistics News Articles
CEA Project Logistics News ArticlesCEA Project Logistics News Articles
CEA Project Logistics News Articles
 
Warehousing & Storage
Warehousing & StorageWarehousing & Storage
Warehousing & Storage
 
Specialized Lifting
Specialized LiftingSpecialized Lifting
Specialized Lifting
 
Break Bulk Consolidation
Break Bulk ConsolidationBreak Bulk Consolidation
Break Bulk Consolidation
 
DAFF/AQIS Quarantine Project
DAFF/AQIS Quarantine ProjectDAFF/AQIS Quarantine Project
DAFF/AQIS Quarantine Project
 
CEA Project Logistics Myanmar
CEA Project Logistics MyanmarCEA Project Logistics Myanmar
CEA Project Logistics Myanmar
 
VpCI Cortec Preservation
VpCI Cortec PreservationVpCI Cortec Preservation
VpCI Cortec Preservation
 
Heliotrope 65 Catamaran Launch
Heliotrope 65 Catamaran LaunchHeliotrope 65 Catamaran Launch
Heliotrope 65 Catamaran Launch
 
Cleaning & Quarantine
Cleaning & QuarantineCleaning & Quarantine
Cleaning & Quarantine
 
The Asian Marshalling Yard
The Asian Marshalling YardThe Asian Marshalling Yard
The Asian Marshalling Yard
 
CEA Quarantine Management
CEA Quarantine ManagementCEA Quarantine Management
CEA Quarantine Management
 

Recently uploaded

Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

Technical Installation

  • 1. TECHNICAL INSTALLATION TECHNICALINSTALLATION Location Chachoengsao, Th. Duration 3 Days Dimensions (m) EvaporatorL23.6xW2.6xH2.8 DistillationL16xW1.4xH2.4 SeparatorL9.5xW2.6xH2.9 Pillar Fan L4.3xW3xH3.2 Weight Evaporator 28 T Distillation 4 T Separator 6.5 T Pillar Fan 8.5 T Total Tonnage 47 T SCOPE CEA Project Logistics completed a potentially difficult and technical installation for a well-known drinks manufacturer in Chachoengsao, Thailand. CEA provided Transportation, Lifting and the Installation of several parts of distillation columns, evaporators, separators and fans. All parts were discharged through the night at Laem Chabang Port and loaded on to several trailers. Due to its size and weight the Evaporator Chamber was loaded on to a multi-axle hydraulic trailer. The parts were transported and unloaded at the factory’s lay down area. After a site inspection two mobile cranes were moved into their positions. The Evaporator Chamber was lifted by both cranes until the chamber was vertical then the smaller crane was unhooked while the larger 500 T crane continued the lift into the facility. CEA teams ensured the safe lowering of the evaporator through the facility. CASE STUDY CS016 Technical Installation 1/2 EVAPORATOR CHAMBER TRANSPORTATION DISTILLATION CHAMBER TRANSPORTATION
  • 2. TECHNICALINSTALLATION CEA PROJECT LOGISTICS 41/13 M1 AO-UDOM ROAD TUNGSUNGKHLA SRI RACHA CHONBURI 20230 THAILAND +66 38 354 019 www.ceaprojects.com The 16 metre distillation chamber was installed using the same lift technique as the Evaporator, CEA teams once again were located on several floors ensuring a safe installation and aligning it to the previously installed Evaporator. Smaller parts were unloaded and assembled at the installation site and lifted into the facility. All aspects of the project were completed in a timely and efficient manner and within budget. CASE STUDY CS016 Technical Installation 2/2 SEPARATOR LOWERED INTO POSITION CHAMBER LOWERED THROUGH EACH FLOOR SEPARATOR BEING READIED FOR LIFT ALIGNING THE CHAMBER TO ITS BASE THE W100 28 TONNE EVAPORATOR CHAMBER IS CAREFULLY LOWERED INTO THE FACILITY CEA ON-SITE TOOLBOX TALK TWO CRANES LIFT THE EVAPORATOR SMALLER PARTS LOWERED INTO POSITION BOTH MAIN CHAMBERS ALIGNED INSIDE