A greater proportion of larger companies are in one way or another looking for ways to utilize the organizations in more effective but mostly common efficient way. Some companies have already started and work in a scaled agile environment for some time, while others are thinking of adopting some of the benefits they have seen in small teams using lean and agile as development methodology. Even if this sounds like the industry has come a long way when it comes to applying lean and agile thoughts into the organizations, this is often not the case when you take a closer look at it. This is why we see three different main ways of scaling:
Real agile – this is what agile from the beginning actually was all about, taking full responsibility from idea to payment
Scaling development pipelines – this is to scale different products or services that doesn’t have any dependencies between the products or services
Scaling structure frameworks – this is the scenario when there are lots of dependencies between products, services or smaller organizations
5. What is your Current state?
• Your business/offerings
• SW products to market
• SW + HW, Internet of things,..
• Cloud - SaaS
• IT to support business
• Business critical
• ….
• Size/co-location
• Architecture/infrastructure
• Agile ”maturity”
• Budget
• ….
5
6. Cost
Business Drivers – top-3 for you?
6
Value Effectiveness Efficiency
Innovation Predictability
Quality
8. Value stream =
”Real Agile”
ValueEffectiveness Innovation
Definition/Description:
• Continuous delivery of value
• End-to-end value stream
collaboration
• Minimum viable product
(MVP)
Homebase:
• Small (and medium) sized
• Co-located
• Product leadership
8
9. Value stream =
”Real Agile”
ValueEffectiveness Innovation
(some typical) Challenges:
- Continuous Delivery
- Get Business/POs in the
flow
- Get instant feedback from
Customer/Market
9
32. Progam Board
32
Sprint 0.1 Sprint 0.2
Sprint0.3
(IP)
Milestones/
Events
Unicorns
Dolphins
Bears
Iguanas
Blue = Features
Red String = A dependency requiring
stories or other dependencies to be
completed before the feature can be
completed
= Significant
Dependency
Antelope
Tarantulas
Eagles
Needs UX
Help
Needs Sys
Arch Help
Orang
e
=
Milestone
/ Event
PI 2 >>>
Red/
Pink
Program Deliverables
Hint:
A pink sticky is an ‘ask’. A
blue sticky fulfils it.
Only put up a blue sticky
in agreement with
whoever will deliver it.