SlideShare a Scribd company logo
1 of 14
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Paper Reference
New Generation Secondary Systems Design for
Ausgrid North Sydney Zone Substation Including
IEC61850 With Multivendor RTU and IEDs
68_AU_Haines
1
Author Company Email Presenter
Ben Haines Ausgrid bhaines@ausgrid.com.au 
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Why is Ausgrid using
IEC61850?
• Reduce dependence on a single SCADA
supplier
• Make future expansion easier
• Reduce hard wiring
• Improve electrical isolation between panels
• Collect additional information to help inform
operational decisions e.g. trip targets
• Open standard to define customer interfaces
2
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
North Sydney Zone
3
• 2 x 132kV feeders, 45 x 11kv feeders,
3 x 132kV/11kV 50MVA transformers
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Key Design Requirements
• Isolation between A and B.
• Provable with reasonable outages.
• Avoid vendor-specific features.
• Support the different work groups which must
live with the result (PE, Tele, Op)
• Do not introduce common points of
vulnerability.
• Logical design rules applied consistently.
4
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Separation of ‘A’ and ‘B’
• Do not wire ‘A’ relays into ‘B’ relays!
o Prefer two independent protection schemes, rather
than one highly redundant system
• Separate ‘A’ and ‘B’ ethernet networks.
• Future development to implement Sub
Transmission feeder reclosing on bay
controllers with GOOSE subscription from
protection relays
5
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Network structure
6
Control Switch 1A
‘A’ Protection Switch 1 ‘B’ Protection Switch 1
Control Switch 1B
Control Switch 2B
‘A’ Protection Switch 2
‘A’ Protection Switch 3
‘B’ Protection Switch 2
‘B’ Protection Switch 3
‘A’ Protection
Router and firewall
‘B’ Protection
Router and firewall
HMI A
SMU A
(RTU)
HMI B
SMU B
(RTU)
‘A’ Protn
Relay 1
‘A’ Protn
Relay 2
‘A’ Protn
Relay 3
‘A’ Protn
Relay 4
‘B’ Protn
Relay 1
‘B’ Protn
Relay 2
‘B’ Protn
Relay 3
‘B’ Protn
Relay 4
SDR-MA SDR-MBSDR-MC
SDR 2
SDR 3
SDR 1
SDR-A SDR-B
A Protection (10.1.x.x) B Protection (10.2.x.x)
Control (10.3.x.x)
Miscellaneous signals
Master controls
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Sub Transmission Bays
• Relays which talk IEC61850 report signals and
targets directly.
• “Main” relay on each panel collects all sub
signals for that panel.
• Dedicated Bay Control IEDs
o Sub Trans switchgear has many alarms & controls
o Protection is on freestanding panels away from the
switchgear
o Several different relay combinations to deal with
o Can justify more per bay than 11 kV feeders
7
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
11 kV Feeder Relays Provide
SCADA functionality
• Simple fixed pattern switchgear.
• Sufficient I/O on relays.
• Very little panel space.
• Cost sensitive due to number of panels.
• Many identical panels.
• Relays physically close to switchgear.
• Optical arc flash detection implemented for safety
• Backup OC provided on all feeders to meet NERs –
S5.1.9(C) “a Network Service Provider must provide sufficient
primary protection systems and back-up protection systems to
ensure that a fault of any fault type anywhere on its
transmission system or distribution system is automatically
disconnected”
8
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
How would you replace the
SMU in a live substation?
• Separate ‘0c’ positive for all controls which act
via output contacts.
• Status of ‘0c’ broadcast to all relays via GOOSE
message.
• If the broadcast GOOSE indicates that ‘0c’ is
de-energised, relays will report or flag but not
act on software controls.
9
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Under Frequency Load Shedding &
Scheme Testing
• No single IED should be able to trip the whole
substation
• Each transformer has separate ‘check’ and ‘trip’ IED
• 11 kV feeder relays only respond when both ‘check’
and ‘trip’ GOOSE messages are present
• Test mode is not used because it alters the IED logic
10
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
61850 Specific Tree Logical
Nodes vs GGIO
• Desired relay behaviour:
o Standard list of targets and signals for each protection type.
o All IEDs programmed to behave the same way regardless of supplier.
o Relay LED alarms match site HMI and control room screens.
• Presently not possible in supplier defined LNs
• Presently only possible with internal relay logic and GGIOs
• Highly desirable that end user can configure the behaviour of LNs.
11
Relay 1 Relay 2 Relay 3
Zone 1&1B has 2 PDIS
LNs, 6 operation flags, one
per fault loop
6 PDIS LNs in total,
3xP-P, 3xP-N
Zones 1,2,3,4,P
modelled as 5 PDIS LNs
Zones 2,3,4,5,6 as single
PDIS LNs only has a single
operation flag for the zone.
One fault operation
flag per zone.
Each PDIS has
operation flags for 3
phases and neutral.
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Analogue Reports and
Deadbands12
• Philosophy:
o Small deadbands lead to higher network traffic.
o To minimise network traffic dead bands set to trigger on
solid switching events.
o Integrity polling shows small measurement changes.
• Different IED suppliers had different implementations.
o % deadband change of present value,
o % deadband of user defined maximum and minimum.
o Deadband change in primary value.
• Benefit of dead band setting complexity Vs
straight integrity polling?
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
IED Undocumented Features
• Relay denied repeat TCP/IP connections. Ethernet card firmware.
• LNs distance to fault in kms not implemented, used % and scale km in
SMU.
• XCBR tangled up with reclosing logic didn’t allow separate use.
• SBO control sequences had to be redefined in SMU.
• IRIG-B time sync failure not available in relay logic but was in LNs.
• buffered reports missed events. Ethernet card firmware.
• Protection quality variables and or drop out timers had to be used to
capture events in IEC61850 reports.
• Phase flagging in relay logic only available through front panel LEDs.
• Phase flagging reset too quickly for relays own internal logic.
• MODBUS switch port alarms didn’t work with specific settings.
• MMS fault record retrieval was not supported by every IED, so had to
implement telnet file transfer for some. Improved in later firmware.
13
© CIGRÉ Australia
AP B5
SEAPAC 2015
Slide
Hold that thought for question time at the end of this session ….
Thank You
14

More Related Content

What's hot

Highavailability designs-for-juniper-netscreen-firewalls3740
Highavailability designs-for-juniper-netscreen-firewalls3740Highavailability designs-for-juniper-netscreen-firewalls3740
Highavailability designs-for-juniper-netscreen-firewalls3740Saurav Aich
 
"Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N...
"Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N..."Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N...
"Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N...Yandex
 
Pocket Toner® NX2 Cable Kit
Pocket Toner® NX2 Cable KitPocket Toner® NX2 Cable Kit
Pocket Toner® NX2 Cable KitFluke Networks
 
Lika Electronic September 2014 Newsletter in English
Lika Electronic September 2014 Newsletter in EnglishLika Electronic September 2014 Newsletter in English
Lika Electronic September 2014 Newsletter in EnglishLika Electronic
 
LayerZero Series 70: eRPP-FS Front/Side Access Remote Power Panel
LayerZero Series 70: eRPP-FS Front/Side Access Remote Power PanelLayerZero Series 70: eRPP-FS Front/Side Access Remote Power Panel
LayerZero Series 70: eRPP-FS Front/Side Access Remote Power PanelLayerZero Power Systems, Inc.
 
icd_lrs_may2_00_ATE_Hyb.
icd_lrs_may2_00_ATE_Hyb.icd_lrs_may2_00_ATE_Hyb.
icd_lrs_may2_00_ATE_Hyb.Laird Snowden
 
A Better Connected World - IDC Product Catalogue 2018
A Better Connected World - IDC Product Catalogue 2018A Better Connected World - IDC Product Catalogue 2018
A Better Connected World - IDC Product Catalogue 2018Jiunn-Jer Sun
 
RUGGEDCOM RSG2100 / RSG2100P
RUGGEDCOM RSG2100 / RSG2100PRUGGEDCOM RSG2100 / RSG2100P
RUGGEDCOM RSG2100 / RSG2100Pashwini reliserv
 
Training course for Artlink_20140722
Training course for Artlink_20140722Training course for Artlink_20140722
Training course for Artlink_20140722ChiaYang Tsai
 
Timothy J Cash Career Portfolio
Timothy J Cash Career PortfolioTimothy J Cash Career Portfolio
Timothy J Cash Career PortfolioTimothy Cash
 
10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...
10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...
10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...Renesas Electronics Corporation
 
10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit
10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit
10 Reasons to use the Renesas multi-protocol OFDM powerline solution kitRenesas Electronics Corporation
 
Catalyst Backbone and Instant Access Technologies
Catalyst Backbone and Instant Access TechnologiesCatalyst Backbone and Instant Access Technologies
Catalyst Backbone and Instant Access TechnologiesCisco Russia
 
Duotech's F-16 Briefing During the 2015 F-16 TCG WWR
Duotech's F-16 Briefing During the 2015 F-16 TCG WWRDuotech's F-16 Briefing During the 2015 F-16 TCG WWR
Duotech's F-16 Briefing During the 2015 F-16 TCG WWRLee Cloer
 

What's hot (20)

Highavailability designs-for-juniper-netscreen-firewalls3740
Highavailability designs-for-juniper-netscreen-firewalls3740Highavailability designs-for-juniper-netscreen-firewalls3740
Highavailability designs-for-juniper-netscreen-firewalls3740
 
10 Reasons to Use detector and sensor Solution Kits
10 Reasons to Use detector and sensor Solution Kits10 Reasons to Use detector and sensor Solution Kits
10 Reasons to Use detector and sensor Solution Kits
 
NGR Monitor
NGR MonitorNGR Monitor
NGR Monitor
 
"Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N...
"Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N..."Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N...
"Morphology of Modern Data Center Networks: Overview". Dinesh Dutt, Cumulus N...
 
Pocket Toner® NX2 Cable Kit
Pocket Toner® NX2 Cable KitPocket Toner® NX2 Cable Kit
Pocket Toner® NX2 Cable Kit
 
Ingress/egress/LTE
Ingress/egress/LTEIngress/egress/LTE
Ingress/egress/LTE
 
Lika Electronic September 2014 Newsletter in English
Lika Electronic September 2014 Newsletter in EnglishLika Electronic September 2014 Newsletter in English
Lika Electronic September 2014 Newsletter in English
 
LayerZero Series 70: eRPP-FS Front/Side Access Remote Power Panel
LayerZero Series 70: eRPP-FS Front/Side Access Remote Power PanelLayerZero Series 70: eRPP-FS Front/Side Access Remote Power Panel
LayerZero Series 70: eRPP-FS Front/Side Access Remote Power Panel
 
Single phase pole mounted circuit recloser catalog
Single phase pole mounted circuit recloser catalogSingle phase pole mounted circuit recloser catalog
Single phase pole mounted circuit recloser catalog
 
icd_lrs_may2_00_ATE_Hyb.
icd_lrs_may2_00_ATE_Hyb.icd_lrs_may2_00_ATE_Hyb.
icd_lrs_may2_00_ATE_Hyb.
 
LayerZero Series 70: eRDP Remote Distribution Panel
LayerZero Series 70: eRDP Remote Distribution PanelLayerZero Series 70: eRDP Remote Distribution Panel
LayerZero Series 70: eRDP Remote Distribution Panel
 
A Better Connected World - IDC Product Catalogue 2018
A Better Connected World - IDC Product Catalogue 2018A Better Connected World - IDC Product Catalogue 2018
A Better Connected World - IDC Product Catalogue 2018
 
RUGGEDCOM RSG2100 / RSG2100P
RUGGEDCOM RSG2100 / RSG2100PRUGGEDCOM RSG2100 / RSG2100P
RUGGEDCOM RSG2100 / RSG2100P
 
Training course for Artlink_20140722
Training course for Artlink_20140722Training course for Artlink_20140722
Training course for Artlink_20140722
 
Timothy J Cash Career Portfolio
Timothy J Cash Career PortfolioTimothy J Cash Career Portfolio
Timothy J Cash Career Portfolio
 
Renesas RX23T Inverter Kit - Deep dive
Renesas RX23T Inverter Kit - Deep diveRenesas RX23T Inverter Kit - Deep dive
Renesas RX23T Inverter Kit - Deep dive
 
10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...
10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...
10 Reasons to use the Renesas R-IN multi-protocol industrial ethernet solutio...
 
10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit
10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit
10 Reasons to use the Renesas multi-protocol OFDM powerline solution kit
 
Catalyst Backbone and Instant Access Technologies
Catalyst Backbone and Instant Access TechnologiesCatalyst Backbone and Instant Access Technologies
Catalyst Backbone and Instant Access Technologies
 
Duotech's F-16 Briefing During the 2015 F-16 TCG WWR
Duotech's F-16 Briefing During the 2015 F-16 TCG WWRDuotech's F-16 Briefing During the 2015 F-16 TCG WWR
Duotech's F-16 Briefing During the 2015 F-16 TCG WWR
 

Viewers also liked

CLASS 2016 - Palestra Paulo Antunes de Souza Jr.
CLASS 2016 - Palestra Paulo Antunes de Souza Jr.CLASS 2016 - Palestra Paulo Antunes de Souza Jr.
CLASS 2016 - Palestra Paulo Antunes de Souza Jr.TI Safe
 
iControl: Substation SCADA
iControl: Substation SCADAiControl: Substation SCADA
iControl: Substation SCADAiGrid T&D
 
IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)
IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)
IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)iGrid T&D
 
Advancements in the Real-Time Simulation of Large Active Distribution Systems...
Advancements in the Real-Time Simulation of Large Active Distribution Systems...Advancements in the Real-Time Simulation of Large Active Distribution Systems...
Advancements in the Real-Time Simulation of Large Active Distribution Systems...OPAL-RT TECHNOLOGIES
 
Invitation to WG 10 Meeting in Moscow in 2010
Invitation to WG 10 Meeting in Moscow in 2010Invitation to WG 10 Meeting in Moscow in 2010
Invitation to WG 10 Meeting in Moscow in 2010Alexey Anoshin
 
132kv Substation demo
132kv Substation demo132kv Substation demo
132kv Substation demoPravesh Kafle
 
Invensys upstream scada technology awareness
Invensys upstream scada technology awarenessInvensys upstream scada technology awareness
Invensys upstream scada technology awarenesschrisjsmith
 
PRESENTATION THESIS
PRESENTATION THESISPRESENTATION THESIS
PRESENTATION THESISUmair Abbasi
 
Overview Of I E C61850 Presentation..... W S M
Overview Of  I E C61850  Presentation..... W S MOverview Of  I E C61850  Presentation..... W S M
Overview Of I E C61850 Presentation..... W S Mginquesada
 
IEC 61850 Lessons Learned 2016 04-11
IEC 61850 Lessons Learned 2016 04-11IEC 61850 Lessons Learned 2016 04-11
IEC 61850 Lessons Learned 2016 04-11Kevin Mahoney
 
Jassim al hamad open substation automation system for oil & gas industry
Jassim al hamad  open substation automation system for oil & gas industryJassim al hamad  open substation automation system for oil & gas industry
Jassim al hamad open substation automation system for oil & gas industrysarah7887
 
Distributech 2015 taking interoperability to the next level
Distributech 2015   taking interoperability to the next levelDistributech 2015   taking interoperability to the next level
Distributech 2015 taking interoperability to the next levelSchneider Electric
 
Challenges in testing iec61850 ver 3
Challenges in testing  iec61850 ver 3Challenges in testing  iec61850 ver 3
Challenges in testing iec61850 ver 3Jay Gosalia
 
Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...
Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...
Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...Schneider Electric
 
Numerical distance presentation
Numerical distance presentationNumerical distance presentation
Numerical distance presentationMohan Sawarkar
 

Viewers also liked (19)

CLASS 2016 - Palestra Paulo Antunes de Souza Jr.
CLASS 2016 - Palestra Paulo Antunes de Souza Jr.CLASS 2016 - Palestra Paulo Antunes de Souza Jr.
CLASS 2016 - Palestra Paulo Antunes de Souza Jr.
 
iControl: Substation SCADA
iControl: Substation SCADAiControl: Substation SCADA
iControl: Substation SCADA
 
IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)
IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)
IEC61850: Use of IEC61850 to telecontrol MV grids (Presentation)
 
Advancements in the Real-Time Simulation of Large Active Distribution Systems...
Advancements in the Real-Time Simulation of Large Active Distribution Systems...Advancements in the Real-Time Simulation of Large Active Distribution Systems...
Advancements in the Real-Time Simulation of Large Active Distribution Systems...
 
Elipse energy solutions
Elipse energy solutionsElipse energy solutions
Elipse energy solutions
 
Invitation to WG 10 Meeting in Moscow in 2010
Invitation to WG 10 Meeting in Moscow in 2010Invitation to WG 10 Meeting in Moscow in 2010
Invitation to WG 10 Meeting in Moscow in 2010
 
132kv Substation demo
132kv Substation demo132kv Substation demo
132kv Substation demo
 
Invensys upstream scada technology awareness
Invensys upstream scada technology awarenessInvensys upstream scada technology awareness
Invensys upstream scada technology awareness
 
PRESENTATION THESIS
PRESENTATION THESISPRESENTATION THESIS
PRESENTATION THESIS
 
Iec61850 primer
Iec61850 primerIec61850 primer
Iec61850 primer
 
Overview Of I E C61850 Presentation..... W S M
Overview Of  I E C61850  Presentation..... W S MOverview Of  I E C61850  Presentation..... W S M
Overview Of I E C61850 Presentation..... W S M
 
IEC-61850
IEC-61850IEC-61850
IEC-61850
 
IEC 61850 Lessons Learned 2016 04-11
IEC 61850 Lessons Learned 2016 04-11IEC 61850 Lessons Learned 2016 04-11
IEC 61850 Lessons Learned 2016 04-11
 
Jassim al hamad open substation automation system for oil & gas industry
Jassim al hamad  open substation automation system for oil & gas industryJassim al hamad  open substation automation system for oil & gas industry
Jassim al hamad open substation automation system for oil & gas industry
 
Distributech 2015 taking interoperability to the next level
Distributech 2015   taking interoperability to the next levelDistributech 2015   taking interoperability to the next level
Distributech 2015 taking interoperability to the next level
 
Challenges in testing iec61850 ver 3
Challenges in testing  iec61850 ver 3Challenges in testing  iec61850 ver 3
Challenges in testing iec61850 ver 3
 
Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...
Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...
Redefining IoT with Innovation At Every Level - Prith Banerjee, Chief Technol...
 
Numerical distance presentation
Numerical distance presentationNumerical distance presentation
Numerical distance presentation
 
FEEDER PROTECTION RELAY
FEEDER PROTECTION RELAYFEEDER PROTECTION RELAY
FEEDER PROTECTION RELAY
 

Similar to CIGREAUB5SEAPAC2015PPT68_AU_Haines-revised

MPC of TWT based Transmitter
MPC of TWT based TransmitterMPC of TWT based Transmitter
MPC of TWT based TransmitterAbhishek Sutrave
 
Wireless Gesture Controlled Tank Toy- Transmitter
Wireless Gesture Controlled Tank Toy- TransmitterWireless Gesture Controlled Tank Toy- Transmitter
Wireless Gesture Controlled Tank Toy- TransmitterNeeraj Purohit
 
IRJET- A Review Paper on Development of General Purpose Controller Board
IRJET- A Review Paper on Development of General Purpose Controller BoardIRJET- A Review Paper on Development of General Purpose Controller Board
IRJET- A Review Paper on Development of General Purpose Controller BoardIRJET Journal
 
7SR45 Self Powered Overcurrent Protection Relay
7SR45 Self Powered Overcurrent Protection Relay7SR45 Self Powered Overcurrent Protection Relay
7SR45 Self Powered Overcurrent Protection Relayashwini reliserv
 
CONTROLLING HOME APPLIANCES USING REMOTE(1)
CONTROLLING HOME APPLIANCES USING REMOTE(1)CONTROLLING HOME APPLIANCES USING REMOTE(1)
CONTROLLING HOME APPLIANCES USING REMOTE(1)Ambar Gupta
 
Ricardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMIRicardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMIFrank Warnes
 
Manual osciloscopio GDS-800
Manual osciloscopio GDS-800Manual osciloscopio GDS-800
Manual osciloscopio GDS-800Armando Uribe Jr
 
QuickSilver Controls QCI-DS023 QCI-D2-IGK
QuickSilver Controls QCI-DS023 QCI-D2-IGKQuickSilver Controls QCI-DS023 QCI-D2-IGK
QuickSilver Controls QCI-DS023 QCI-D2-IGKElectromate
 
TRANSFORMER FAULT DETECTION AND MONITORING
TRANSFORMER FAULT DETECTION AND MONITORINGTRANSFORMER FAULT DETECTION AND MONITORING
TRANSFORMER FAULT DETECTION AND MONITORINGIRJET Journal
 
INTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCK
INTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCKINTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCK
INTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCKSantanu Chatterjee
 
IRJET- Explosive Ordinanace Disposal Robot
IRJET- Explosive Ordinanace Disposal RobotIRJET- Explosive Ordinanace Disposal Robot
IRJET- Explosive Ordinanace Disposal RobotIRJET Journal
 
Substation Monitoring and Control Based on Microcontroller Using IoT
Substation Monitoring and Control Based on Microcontroller Using IoTSubstation Monitoring and Control Based on Microcontroller Using IoT
Substation Monitoring and Control Based on Microcontroller Using IoTIRJET Journal
 
QuickSilver Controls QCI-DS032 QCI-N2-MX
QuickSilver Controls QCI-DS032 QCI-N2-MXQuickSilver Controls QCI-DS032 QCI-N2-MX
QuickSilver Controls QCI-DS032 QCI-N2-MXElectromate
 
Electric Control Valve Actuators for Industrial Process Applications
Electric Control Valve Actuators for Industrial Process ApplicationsElectric Control Valve Actuators for Industrial Process Applications
Electric Control Valve Actuators for Industrial Process ApplicationsCTi Controltech
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...IRJET Journal
 
plc_training_manual.pdf
plc_training_manual.pdfplc_training_manual.pdf
plc_training_manual.pdfMarioHaguila
 

Similar to CIGREAUB5SEAPAC2015PPT68_AU_Haines-revised (20)

MPC of TWT based Transmitter
MPC of TWT based TransmitterMPC of TWT based Transmitter
MPC of TWT based Transmitter
 
Wireless Gesture Controlled Tank Toy- Transmitter
Wireless Gesture Controlled Tank Toy- TransmitterWireless Gesture Controlled Tank Toy- Transmitter
Wireless Gesture Controlled Tank Toy- Transmitter
 
IRJET- A Review Paper on Development of General Purpose Controller Board
IRJET- A Review Paper on Development of General Purpose Controller BoardIRJET- A Review Paper on Development of General Purpose Controller Board
IRJET- A Review Paper on Development of General Purpose Controller Board
 
RLW type pole mounted vacuum load break switch
RLW type pole mounted vacuum load break switchRLW type pole mounted vacuum load break switch
RLW type pole mounted vacuum load break switch
 
7SR45 Self Powered Overcurrent Protection Relay
7SR45 Self Powered Overcurrent Protection Relay7SR45 Self Powered Overcurrent Protection Relay
7SR45 Self Powered Overcurrent Protection Relay
 
CONTROLLING HOME APPLIANCES USING REMOTE(1)
CONTROLLING HOME APPLIANCES USING REMOTE(1)CONTROLLING HOME APPLIANCES USING REMOTE(1)
CONTROLLING HOME APPLIANCES USING REMOTE(1)
 
Ricardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMIRicardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMI
 
Manual osciloscopio GDS-800
Manual osciloscopio GDS-800Manual osciloscopio GDS-800
Manual osciloscopio GDS-800
 
QuickSilver Controls QCI-DS023 QCI-D2-IGK
QuickSilver Controls QCI-DS023 QCI-D2-IGKQuickSilver Controls QCI-DS023 QCI-D2-IGK
QuickSilver Controls QCI-DS023 QCI-D2-IGK
 
SDI to IP 2110 Transition Part 2
SDI to IP 2110 Transition Part 2SDI to IP 2110 Transition Part 2
SDI to IP 2110 Transition Part 2
 
TRANSFORMER FAULT DETECTION AND MONITORING
TRANSFORMER FAULT DETECTION AND MONITORINGTRANSFORMER FAULT DETECTION AND MONITORING
TRANSFORMER FAULT DETECTION AND MONITORING
 
INTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCK
INTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCKINTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCK
INTERRUPT DRIVEN MULTIPLEXED 7 SEGMENT DIGITAL CLOCK
 
IRJET- Explosive Ordinanace Disposal Robot
IRJET- Explosive Ordinanace Disposal RobotIRJET- Explosive Ordinanace Disposal Robot
IRJET- Explosive Ordinanace Disposal Robot
 
Substation Monitoring and Control Based on Microcontroller Using IoT
Substation Monitoring and Control Based on Microcontroller Using IoTSubstation Monitoring and Control Based on Microcontroller Using IoT
Substation Monitoring and Control Based on Microcontroller Using IoT
 
QuickSilver Controls QCI-DS032 QCI-N2-MX
QuickSilver Controls QCI-DS032 QCI-N2-MXQuickSilver Controls QCI-DS032 QCI-N2-MX
QuickSilver Controls QCI-DS032 QCI-N2-MX
 
5 FINAL PROJECT REPORT
5 FINAL PROJECT REPORT5 FINAL PROJECT REPORT
5 FINAL PROJECT REPORT
 
embedded system
embedded systemembedded system
embedded system
 
Electric Control Valve Actuators for Industrial Process Applications
Electric Control Valve Actuators for Industrial Process ApplicationsElectric Control Valve Actuators for Industrial Process Applications
Electric Control Valve Actuators for Industrial Process Applications
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
 
plc_training_manual.pdf
plc_training_manual.pdfplc_training_manual.pdf
plc_training_manual.pdf
 

CIGREAUB5SEAPAC2015PPT68_AU_Haines-revised

  • 1. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Paper Reference New Generation Secondary Systems Design for Ausgrid North Sydney Zone Substation Including IEC61850 With Multivendor RTU and IEDs 68_AU_Haines 1 Author Company Email Presenter Ben Haines Ausgrid bhaines@ausgrid.com.au 
  • 2. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Why is Ausgrid using IEC61850? • Reduce dependence on a single SCADA supplier • Make future expansion easier • Reduce hard wiring • Improve electrical isolation between panels • Collect additional information to help inform operational decisions e.g. trip targets • Open standard to define customer interfaces 2
  • 3. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide North Sydney Zone 3 • 2 x 132kV feeders, 45 x 11kv feeders, 3 x 132kV/11kV 50MVA transformers
  • 4. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Key Design Requirements • Isolation between A and B. • Provable with reasonable outages. • Avoid vendor-specific features. • Support the different work groups which must live with the result (PE, Tele, Op) • Do not introduce common points of vulnerability. • Logical design rules applied consistently. 4
  • 5. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Separation of ‘A’ and ‘B’ • Do not wire ‘A’ relays into ‘B’ relays! o Prefer two independent protection schemes, rather than one highly redundant system • Separate ‘A’ and ‘B’ ethernet networks. • Future development to implement Sub Transmission feeder reclosing on bay controllers with GOOSE subscription from protection relays 5
  • 6. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Network structure 6 Control Switch 1A ‘A’ Protection Switch 1 ‘B’ Protection Switch 1 Control Switch 1B Control Switch 2B ‘A’ Protection Switch 2 ‘A’ Protection Switch 3 ‘B’ Protection Switch 2 ‘B’ Protection Switch 3 ‘A’ Protection Router and firewall ‘B’ Protection Router and firewall HMI A SMU A (RTU) HMI B SMU B (RTU) ‘A’ Protn Relay 1 ‘A’ Protn Relay 2 ‘A’ Protn Relay 3 ‘A’ Protn Relay 4 ‘B’ Protn Relay 1 ‘B’ Protn Relay 2 ‘B’ Protn Relay 3 ‘B’ Protn Relay 4 SDR-MA SDR-MBSDR-MC SDR 2 SDR 3 SDR 1 SDR-A SDR-B A Protection (10.1.x.x) B Protection (10.2.x.x) Control (10.3.x.x) Miscellaneous signals Master controls
  • 7. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Sub Transmission Bays • Relays which talk IEC61850 report signals and targets directly. • “Main” relay on each panel collects all sub signals for that panel. • Dedicated Bay Control IEDs o Sub Trans switchgear has many alarms & controls o Protection is on freestanding panels away from the switchgear o Several different relay combinations to deal with o Can justify more per bay than 11 kV feeders 7
  • 8. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide 11 kV Feeder Relays Provide SCADA functionality • Simple fixed pattern switchgear. • Sufficient I/O on relays. • Very little panel space. • Cost sensitive due to number of panels. • Many identical panels. • Relays physically close to switchgear. • Optical arc flash detection implemented for safety • Backup OC provided on all feeders to meet NERs – S5.1.9(C) “a Network Service Provider must provide sufficient primary protection systems and back-up protection systems to ensure that a fault of any fault type anywhere on its transmission system or distribution system is automatically disconnected” 8
  • 9. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide How would you replace the SMU in a live substation? • Separate ‘0c’ positive for all controls which act via output contacts. • Status of ‘0c’ broadcast to all relays via GOOSE message. • If the broadcast GOOSE indicates that ‘0c’ is de-energised, relays will report or flag but not act on software controls. 9
  • 10. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Under Frequency Load Shedding & Scheme Testing • No single IED should be able to trip the whole substation • Each transformer has separate ‘check’ and ‘trip’ IED • 11 kV feeder relays only respond when both ‘check’ and ‘trip’ GOOSE messages are present • Test mode is not used because it alters the IED logic 10
  • 11. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide 61850 Specific Tree Logical Nodes vs GGIO • Desired relay behaviour: o Standard list of targets and signals for each protection type. o All IEDs programmed to behave the same way regardless of supplier. o Relay LED alarms match site HMI and control room screens. • Presently not possible in supplier defined LNs • Presently only possible with internal relay logic and GGIOs • Highly desirable that end user can configure the behaviour of LNs. 11 Relay 1 Relay 2 Relay 3 Zone 1&1B has 2 PDIS LNs, 6 operation flags, one per fault loop 6 PDIS LNs in total, 3xP-P, 3xP-N Zones 1,2,3,4,P modelled as 5 PDIS LNs Zones 2,3,4,5,6 as single PDIS LNs only has a single operation flag for the zone. One fault operation flag per zone. Each PDIS has operation flags for 3 phases and neutral.
  • 12. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Analogue Reports and Deadbands12 • Philosophy: o Small deadbands lead to higher network traffic. o To minimise network traffic dead bands set to trigger on solid switching events. o Integrity polling shows small measurement changes. • Different IED suppliers had different implementations. o % deadband change of present value, o % deadband of user defined maximum and minimum. o Deadband change in primary value. • Benefit of dead band setting complexity Vs straight integrity polling?
  • 13. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide IED Undocumented Features • Relay denied repeat TCP/IP connections. Ethernet card firmware. • LNs distance to fault in kms not implemented, used % and scale km in SMU. • XCBR tangled up with reclosing logic didn’t allow separate use. • SBO control sequences had to be redefined in SMU. • IRIG-B time sync failure not available in relay logic but was in LNs. • buffered reports missed events. Ethernet card firmware. • Protection quality variables and or drop out timers had to be used to capture events in IEC61850 reports. • Phase flagging in relay logic only available through front panel LEDs. • Phase flagging reset too quickly for relays own internal logic. • MODBUS switch port alarms didn’t work with specific settings. • MMS fault record retrieval was not supported by every IED, so had to implement telnet file transfer for some. Improved in later firmware. 13
  • 14. © CIGRÉ Australia AP B5 SEAPAC 2015 Slide Hold that thought for question time at the end of this session …. Thank You 14