1. Ashraf Suleiman
+971 55 359 4842 address: UAE-AbuDhabi
Email: ashraf.suleiman@hotmail.com
Date of Birth: 02/11/1983
Gender: male
Marital Status: married
Nationality: Jordanian
OBJECTIVE STATEMENT
Looking to bring a continued and significant contribution to a successful company that
values intelligence, curiosity, and cross-cultural skills combined with a creative and confident
team player attitude; Committed to professional ethics and integrity.
EDUCATION
An-Najah national University
Nablus-Palestine
B.A. Electrical Engineering
2001-2006
EXPERIENCE RECORD
Ghantoot Tpt. & Gen. Cont. Co. Abu Dhabi-UAE
Construction Manager November 2013-Present
Main duties
Create WBS for construction activity as per scope of works.
Plan resources and dispatch to construction sites.
Developing the program of construction work and strategy for making the project happen
as Project Plan.
Studies and analyses of all inputs to reduce risk and maintain construction program as
planed time, quality and budget.
Following up construction activates at site according to the specification and drawing.
Coordination between site office and engineering office for reviewing the Construction
drawings against design drawings
Manage the handing over completed activates to consultant/Client.
Managing material requirement and availability for construction activity.
Follow up with planning department to keep project on track by monitoring & managing
work progress based on planning schedule
Assuring quality, safety & proper survey works as per planed work sequence.
Monitoring for site progress ensuring for the efficiency for equipment’s and manpower to ensures
that the duration of each activity will meet the required time frame in the schedule
Managing Subcontractors including scope, activity, reporting payments …
Maintain required reports and documents of construction in the project.
Communicating with stakeholders; client, subcontractors, management, suppliers, the
public and the workforce.
Projects:
- New ADAC, CUP2 Cable Works . PROJECT No. N-14516.1. The project owned by TRANSCO,
design & consultancy work held by ATKINS. Planned Complition Date: 15 Nov 2017
2. This project attended by TRANSCO for power feeding of Abu Dhabi airport extension (new 132KV
substation) with 127 milion DHs budget for supply, installation, testing and commissioning of HV
(132 KV) cables and accessories including network modification to increase the capacity of
existing substations.
Total planned man power is 256 at peak.
Total planned subcontractors are 5.
- EPC for Rumaitha/Shanayel Facilities-Phase III PROJECT No. P44010. The project owned by
ADCO and main channel is DODSAL.
This project attended by ADCO for new clusters power feeding in Rumaitha/Shanayel in Abu
Dhabi with with 28 milion $ budget for supply, installation, testing and commissioning of MV(33 KV)
OHL, cables and accessories and to improve Electrical Network and increase the capacity.
Total Man power is 385 at peak.
Total subcontractors were 7.
- Improvement of Mafraq to Ghwaifat Border Post-Highway, Section No. 4B. This project
owned by Musanada, Design by Mott MacDonald, consultancy work held by Dorsch
Group and construction by GAHNTOOT.
The project attended to achieve an intersection of the major international Highway
connect KSA to all UAE emirates with a budget of 1.3 Milliard DHs including 170 million
DHs for HV, MV and Street Lighting Networks.
Total Man power is 165 at peak.
Total subcontractors were 3.
- 132kV & 33 kV Cabling Works in Northern Emirates. This project owned by FEWA,
design & consultancy work held by ENERGOPROJEKT and construction by
GAHNTOOT.
It is a project owned by Federal of Water and Electricity Authority (FEWA) for
improvement electrical networks in Northern Emirates with 55 Million DHs budget for
supply, installation, testing and commissioning of MV(33 KV) cables and accessories in
Ajman, RAK, Um AL Qwain and Al Fujairah.
Total Man power is 140 at peak.
Total subcontractors were 5.
Senior Project Engineer, Team Leader June 2011 - until November 2013
Main duties
Develops projectobjectives by reviewing projectproposals and plans;conferring with management
Identify scope, creation of project WBS, determine deliverables and identify stockholder.
Determines projectschedule bystudying project scope and WBS; calculating time requirements;
sequencing projectelements
Identify Resources needed and assign individual responsibility.
Insure the awareness of all project team members of project scope and specifications;
and utilize each to his fullest potential
Managing procurement in coordination with procurement unit to insure the delivery of
material to site on time
Tracks and reports resources hours and expenses on weekly basis for project cost
control
Maintains projectschedule bymonitoring projectprogress;coordinating activities;resolving
problems
Ensure proper documentation of project and document are current and complete
3. Facilitate team and clients meeting effectively in regular basis
Review deliverables before passing to customers (Client/Consultant)
Provides the technical guidance for project team
Maintains proper communication with customer and project team
Reports on regular basis for project customers and project management
Maintains product and company reputation by complying with federal and state regulations
Projects:
- Maintenance contract with ADM. This project owned by ADM, consultancy WSP and
construction by WBG main contractor / GAHNTOOT electrical Subcontractor.
It is a short period scope for emergency works to open new Mina Link Road. The scope
includes Supply, installation and protection of HV, MV, LV & street lighting cables and
equipment.
- Installation of 33/11K KV package unit and cable works in Al Adla of eastern region in
Abu Dhabi. This project owned by ADDC, consultancy AECOM and construction by
GAHNTOOT.
This project attended to increase electrical networks capacity in Al-Adla Area with a
budget of 11 million DHs.
- Replacement of 11KV SWG, SRUP Panels in central and eastern region of Abu Dhabi.
This project owned by ADDC and construction by GAHNTOOT.
Maintenance project to supply and replace old 11KV switchgear for 40 substations in
deferent locations with budget of 16 million DHs.
Project Engineer July 2009 - until June 2011
Main duties
Coordination with project manager and reporting all activities regularly.
Study, review and implement the project plan and schedule.
Following running construction activity and maintain the productivity as per planed time,
quality and client requirement; and reporting to project manager regularly.
Coordination with procurement and staff regarding materials approval, quantities and
delivery.
Handing and validating deliverable to the consultant/client; requesting and approving
work acceptance certificates and measurements.
Review, check and approve shop drawings prior to site implementation.
Following subcontractor’s activities, requirements and approvals.
Preparing monthly progress report detailing progress and cost for project manager.
Ensure the validity of all official document and certificates, and to assure the availability
of required permits and approval from all concerned authority.
Projects:
- Maintenance and Rehabilitation works for Abu Dhabi strategic roads. Zone 1 – Abu Dhabi
Region. This project owned by DOT, consultancy AECOM and construction by
GAHNTOOT.
- Fast Track contract for reinforcement of 11KV and LV network in central region. This
project owned by ADDC, consultancy Dr. Mhmd. Ali. Al-Sai and construction by
GAHNTOOT.
4. - ESKAN AMD Tracking No.: AGS007. Engineering, Procurement and Construction of M41
33/11 kV Primary Substation and other related works at ICAD Residential City. This
project owned by ESCAN, consultancy M/s. DECON and construction by GAHNTOOT.
- Relocation & Protection of existing 132 KV cable circuit at the main inter change Area
located on SAS Nakhl–shahama Highway. This project owned by TRANSCO & ADM,
consultancy HALCRO and construction by Al-JABER & GAHNTOOT.
Site Engineer July 2007 - until July 2009
Main duties
Supervise erection works for electrical network, substations, transformers, and street
lightening.
Installing and terminating for the MV & LV cables.
Dismantling and relocation of Over Head Line.
Installation and protection for HV cables.
Following and Applying all required test for high voltage cables and arranging with
Transco, consultant and main contractor for shutdown and procedures.
All site and document work related to Erecting and assembling substation (11KV
switchgear, LV panels, transformer and commissioning including all electrical
connections required between elements and making solid earth for all substation
elements.
Arranging shutdown work /procedure and coordination with ADDC or TRANSCO
Engineers.
Follow up for permissions and approval from all concerned department and authorities.
Comments and preparing all required document.
Following up daily activities, daily program of work, and site coordination with consultant /
client staff at site.
Prepare progress reports for completed daily and weekly works.
Projects:
- Contract with ADM. Widening of Sheikh Rashid Bin Saed Al-Maktoom Street. Scope
includes protection of HV, MV & LV cables in addition to new 30.5 Meter street lighting
networks.
- Contract with AL-Qudra.; Danet Abu Dhabi Infrastructure Development. Scope include
new 11KV networks with FOC and two substations.
- Contract with TRANSCO. Power Network Development works for (Icad) Emirates Steel
Factory (EISF) And private emirate steel Lot 2A.2- 220KV cable connections.
- Contract with TABREED. Tabreed Cooling Plant Al Dhar- 10 Khalifa City -2. Scope is
supply, install, testing and commissioning 33KV cables and accessories.
- Contract with ADM. New infrastructure works in Khalifa City. Scope include supply and
install new 11KV, LV and street lighting netwrorks.
-
Mays Electrical and Contracting Co. Amman-Jordan
Site Engineer
February 2007 - until July 2007
5. Main duties
Training & Supervision of Infra structure electrical works related for installation and
maintenance of OHL and Street lightings.
MISCELLANEOUS
Projects, trainings and achievements
- PMP, Project management Professional training. Cambridge PMP Training Center.
- Planning electrical installation for Howara hospital –Najah University
- Training in Howara Engineering Office. / 2 moths
- Training in JAWWAL Company (The Palestinian Cellular Phone Company). /2 weeks
- Basic Fire Fighting, Basic First Aid and General Safety Courses in Emirates Technical &
Safety Development Centre
Approvals and certificate
- Approved as Construction Manager with FEWA.
- Cambridge PMP Training Center Certificate.
- Approved as Project Engineer with ADDC.
- Approved as Site Engineer with ADDC.
- ADDC HSE Competency Certificate for.
- TRANSCO HSE Competency Certificate.
- GASCO & DOLPHIN Competency Certificate for civil work.
- First Aid and Fire Fighting Certificate
Computing and Computer Skills
- Programming language: C++ and MatLab.
- AutoCAD
- Microsoft, outlook and internet.
Languages
- Arabic: Mother tongue
- English: Excellent
Memberships
- Jordanian Engineers Association since 2007
REFERENCES
Available upon request (Notice period 1 months)