Ahmed Abdul halim sedik
National Technical Concrete Industry Subcommittee (NT-CIS)
Civil Engineer
Quality & Conformity Department . M.O.E
QNCC 26th , 27th October 2014 , DOHA - QATAR
QCS 2014
Concrete Plant Inspection
2
List Contents.
Introduction ……………………………….………….....… 3
The Benefit Of New Amendment……………………….....4
Scope of Inspection ……………………..……………....…5
Check list contents ………………………….….………...6,7
Factory Requirements……………...............................8,9,10
Row Materials Requirements…………...…………....…11,12
Water and admixture Requirements………….………....13
Batching Plan Requirements……………..………………14
Laboratory Requirements………………………...………15
Questions …………………………………………………..16
3
Introduction.
QCS new and previous versions focuses on the concrete plant quality ,
the new version QCS 2014 part no. 7 in section no.5 has been amended
with a check list for concrete plants inspection , the chapter title also has
been changed to "Concrete Plants" instead of “ Batching Plant ", the new
title will be inclusive to all matters related to concrete plant .
The new amendment has been establish of trust and transparency among
governmental parties and manufacturers , and also to encourage
manufacturers to conduct self-audit their factories to improve quality,
through checking all the quality required points in the provided check list.
4
The benefit of new amendment.
 New to QCS.
 Focused on concrete plants.
 Transparency among manufacturers and governmental parties.
 Speed up the completion of inspection stage.
 Minimum requirements of quality specifications for concrete plants.
5
Scope of inspection for concrete plants
at QCS 2014.
Inspection is the most important step to get the
conformity certificate or any certificate of concrete
plant .
The inspectors team mission is to visit the factory to
make sure that the following points are complying with
QCS 2014.
 Factory.
 Materials storage.
 Production lines .
 Laboratory .
 Product storage.
The National Committee has approved a list of
inspection steps, to improve the quality .
6
Inspection Check List
7
Check list.
1- Factory condition.
2-Material storage and handling.
3- Water & Admixture supply.
4- Batching plant requirements.
5- Laboratory.
6- Delivery ticket requirements.
Inspection Steps :
8
1- Factory condition.
1-1 Concrete floor under mixer & silos.
1-2 Concrete floor with slope under
materials.
1-3 Hard and stable floor on axis .
1-4 Floor clean .
1-5 Drainage system .
1-6 Separated place of waste
materials.
1-7 Separated place of wash tank .
9
1-1- Concrete floor under mixer & silos.
1-2- Concrete floor with slope under materials.
1-3- Hard and stable floor on axis .
1-4- Floor clean .
10
1-5- Drainage System . 1-6-Separated Place of Waste Materials.
1-7-Separated Place Of WashTank.
11
2- Row materials
requirements.
F- Effective method for checking
level of materials in bins .
A- Aggregate shading .
B- Aggregate separations.
C- Aggregate scale calibration.
D- Conveyer belts cover .
2-2 Aggregate
E- Board clarify the aggregate type
A
B
A
D
E
12
2- Row materials
requirements.
A- Cleaning of C&C silos.
B - Cement scale calibration.
C - Reflective color for silo.
D - Board clarify the type .
2-3 Cement & cementations
materials
F- All cementations materials excess of
use protected under shed.
A- Water pipe protect.
3-1 Water requirements .
B – Chiller machine .
C – Ice plant or nitrogen cooling
system .
D –Water and ice plant
calibrations.
3- Water and admixture requirements.
A- Additive storage silos .
3-2 Admixture requirements
B – Additive gage calibration .
C – All admixture excess of use
protected under shad.
D –Agitation system for all tanks
or silos more than 5000 liter .
13
14
B- Computer controlled .
4- Batching plant requirements.
C- Plant type .
D- Computer print out .
E- Calibration validity .
F- Cleaning of mixer blades.
A- Certificate validity .
A – Equipment calibration
validity.
5- Laboratory requirements.
D – Temperature for curing
tank.
B – Records of test results .
C – Method and result of slump
and temp for concrete at plant .
15
16
Thank you
Eng . Ahmed Abdul Halim

More Related Content

What's hot

Designing with Geosynthetics by Koerner 5th edition 2005
Designing with Geosynthetics by Koerner 5th edition 2005Designing with Geosynthetics by Koerner 5th edition 2005
Designing with Geosynthetics by Koerner 5th edition 2005
Agung Noorsamsi
 

What's hot (20)

Effect of rice husk ash on the strenght and durability of concrete by debasree
Effect of rice husk ash on the strenght and durability of concrete  by debasreeEffect of rice husk ash on the strenght and durability of concrete  by debasree
Effect of rice husk ash on the strenght and durability of concrete by debasree
 
Rapport pfe aurelien_rigart_gc5_2009
Rapport pfe aurelien_rigart_gc5_2009Rapport pfe aurelien_rigart_gc5_2009
Rapport pfe aurelien_rigart_gc5_2009
 
New NDT technology for assessment of concrete defects and faults
New NDT technology for assessment of concrete defects and faultsNew NDT technology for assessment of concrete defects and faults
New NDT technology for assessment of concrete defects and faults
 
ASSESSMENT OF SELF COMPACTING CONCRETE IMMERSED IN ACIDIC SOLUTIONS WITH PART...
ASSESSMENT OF SELF COMPACTING CONCRETE IMMERSED IN ACIDIC SOLUTIONS WITH PART...ASSESSMENT OF SELF COMPACTING CONCRETE IMMERSED IN ACIDIC SOLUTIONS WITH PART...
ASSESSMENT OF SELF COMPACTING CONCRETE IMMERSED IN ACIDIC SOLUTIONS WITH PART...
 
Designing with Geosynthetics by Koerner 5th edition 2005
Designing with Geosynthetics by Koerner 5th edition 2005Designing with Geosynthetics by Koerner 5th edition 2005
Designing with Geosynthetics by Koerner 5th edition 2005
 
Phosphogypsum as replacement material for cement
Phosphogypsum as replacement material for cementPhosphogypsum as replacement material for cement
Phosphogypsum as replacement material for cement
 
REACTIVE POWDER CONCRETE
REACTIVE POWDER CONCRETEREACTIVE POWDER CONCRETE
REACTIVE POWDER CONCRETE
 
Section 500
Section 500Section 500
Section 500
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
Methods Of Soil stabilization
Methods Of Soil stabilizationMethods Of Soil stabilization
Methods Of Soil stabilization
 
SOIL STABILIZATION USING LIME AND CEMENT
SOIL STABILIZATION USING LIME AND CEMENTSOIL STABILIZATION USING LIME AND CEMENT
SOIL STABILIZATION USING LIME AND CEMENT
 
Calcul d'un hangar
Calcul d'un hangar Calcul d'un hangar
Calcul d'un hangar
 
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALSCOMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
COMPRESSIVE STRENGTH OF CONCRETE BY USING WASTE MATERIALS
 
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERSANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
 
Presentation on Self Compacting Concrete / SCC
Presentation on Self Compacting Concrete / SCCPresentation on Self Compacting Concrete / SCC
Presentation on Self Compacting Concrete / SCC
 
Overview of Soil Stabilization :Cement / Lime :PPT
Overview of Soil Stabilization :Cement / Lime :PPTOverview of Soil Stabilization :Cement / Lime :PPT
Overview of Soil Stabilization :Cement / Lime :PPT
 
Rpoa
RpoaRpoa
Rpoa
 
SOIL STABILIZATION USING FLY ASH
SOIL STABILIZATION USING FLY ASHSOIL STABILIZATION USING FLY ASH
SOIL STABILIZATION USING FLY ASH
 
Ndt
NdtNdt
Ndt
 
IRJET-Development of Controlled Low Strength Material (CLSM) by Utilising Fly...
IRJET-Development of Controlled Low Strength Material (CLSM) by Utilising Fly...IRJET-Development of Controlled Low Strength Material (CLSM) by Utilising Fly...
IRJET-Development of Controlled Low Strength Material (CLSM) by Utilising Fly...
 

Similar to presentation QCS 2014 concrete plant part 7 - final

Resume Muhammad Asfar(1)
Resume Muhammad Asfar(1)Resume Muhammad Asfar(1)
Resume Muhammad Asfar(1)
MUHAMMAD ASFAR
 
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
Rajeev Kumar
 
Painting new construction and maintenance
Painting  new construction and maintenancePainting  new construction and maintenance
Painting new construction and maintenance
Arpit Agrawal
 

Similar to presentation QCS 2014 concrete plant part 7 - final (20)

RoadstaB - Alternative to Expensive Road.
RoadstaB - Alternative to Expensive Road. RoadstaB - Alternative to Expensive Road.
RoadstaB - Alternative to Expensive Road.
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
 
HCS Custom Process Equipment
HCS Custom Process EquipmentHCS Custom Process Equipment
HCS Custom Process Equipment
 
cv_resume_
cv_resume_cv_resume_
cv_resume_
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
Resume Muhammad Asfar(1)
Resume Muhammad Asfar(1)Resume Muhammad Asfar(1)
Resume Muhammad Asfar(1)
 
RoadstaB august 2013
RoadstaB august 2013RoadstaB august 2013
RoadstaB august 2013
 
construction equpment Chapter 2.pdf
construction equpment Chapter 2.pdfconstruction equpment Chapter 2.pdf
construction equpment Chapter 2.pdf
 
2 appendix ii technical conditions, requirements and ma (1)
2 appendix ii   technical conditions, requirements and ma (1)2 appendix ii   technical conditions, requirements and ma (1)
2 appendix ii technical conditions, requirements and ma (1)
 
Quality inspection in Manufacturing Of TRANSMISSION Towers.
Quality inspection in Manufacturing Of TRANSMISSION Towers.Quality inspection in Manufacturing Of TRANSMISSION Towers.
Quality inspection in Manufacturing Of TRANSMISSION Towers.
 
Batch plant maintenance
Batch plant maintenanceBatch plant maintenance
Batch plant maintenance
 
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
2016 Resume of Rajeev Kumar, Inspection Engineer (Surveyor-1)
 
Michael CV.
Michael CV.Michael CV.
Michael CV.
 
FOUNDRY AND FORGING LABORATORY.pdf
FOUNDRY AND FORGING LABORATORY.pdfFOUNDRY AND FORGING LABORATORY.pdf
FOUNDRY AND FORGING LABORATORY.pdf
 
abc
abcabc
abc
 
MCEM-S23-JT-EX03-GD (1).pptx
MCEM-S23-JT-EX03-GD (1).pptxMCEM-S23-JT-EX03-GD (1).pptx
MCEM-S23-JT-EX03-GD (1).pptx
 
Painting new construction and maintenance
Painting  new construction and maintenancePainting  new construction and maintenance
Painting new construction and maintenance
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Concrete Mix Design Report
Concrete Mix Design ReportConcrete Mix Design Report
Concrete Mix Design Report
 
CORE KNOWLEGDE for CIVIL INSPECTORS.pdf
CORE KNOWLEGDE for CIVIL INSPECTORS.pdfCORE KNOWLEGDE for CIVIL INSPECTORS.pdf
CORE KNOWLEGDE for CIVIL INSPECTORS.pdf
 

presentation QCS 2014 concrete plant part 7 - final

  • 1. Ahmed Abdul halim sedik National Technical Concrete Industry Subcommittee (NT-CIS) Civil Engineer Quality & Conformity Department . M.O.E QNCC 26th , 27th October 2014 , DOHA - QATAR QCS 2014 Concrete Plant Inspection
  • 2. 2 List Contents. Introduction ……………………………….………….....… 3 The Benefit Of New Amendment……………………….....4 Scope of Inspection ……………………..……………....…5 Check list contents ………………………….….………...6,7 Factory Requirements……………...............................8,9,10 Row Materials Requirements…………...…………....…11,12 Water and admixture Requirements………….………....13 Batching Plan Requirements……………..………………14 Laboratory Requirements………………………...………15 Questions …………………………………………………..16
  • 3. 3 Introduction. QCS new and previous versions focuses on the concrete plant quality , the new version QCS 2014 part no. 7 in section no.5 has been amended with a check list for concrete plants inspection , the chapter title also has been changed to "Concrete Plants" instead of “ Batching Plant ", the new title will be inclusive to all matters related to concrete plant . The new amendment has been establish of trust and transparency among governmental parties and manufacturers , and also to encourage manufacturers to conduct self-audit their factories to improve quality, through checking all the quality required points in the provided check list.
  • 4. 4 The benefit of new amendment.  New to QCS.  Focused on concrete plants.  Transparency among manufacturers and governmental parties.  Speed up the completion of inspection stage.  Minimum requirements of quality specifications for concrete plants.
  • 5. 5 Scope of inspection for concrete plants at QCS 2014. Inspection is the most important step to get the conformity certificate or any certificate of concrete plant . The inspectors team mission is to visit the factory to make sure that the following points are complying with QCS 2014.  Factory.  Materials storage.  Production lines .  Laboratory .  Product storage. The National Committee has approved a list of inspection steps, to improve the quality .
  • 7. 7 Check list. 1- Factory condition. 2-Material storage and handling. 3- Water & Admixture supply. 4- Batching plant requirements. 5- Laboratory. 6- Delivery ticket requirements. Inspection Steps :
  • 8. 8 1- Factory condition. 1-1 Concrete floor under mixer & silos. 1-2 Concrete floor with slope under materials. 1-3 Hard and stable floor on axis . 1-4 Floor clean . 1-5 Drainage system . 1-6 Separated place of waste materials. 1-7 Separated place of wash tank .
  • 9. 9 1-1- Concrete floor under mixer & silos. 1-2- Concrete floor with slope under materials. 1-3- Hard and stable floor on axis . 1-4- Floor clean .
  • 10. 10 1-5- Drainage System . 1-6-Separated Place of Waste Materials. 1-7-Separated Place Of WashTank.
  • 11. 11 2- Row materials requirements. F- Effective method for checking level of materials in bins . A- Aggregate shading . B- Aggregate separations. C- Aggregate scale calibration. D- Conveyer belts cover . 2-2 Aggregate E- Board clarify the aggregate type A B A D E
  • 12. 12 2- Row materials requirements. A- Cleaning of C&C silos. B - Cement scale calibration. C - Reflective color for silo. D - Board clarify the type . 2-3 Cement & cementations materials F- All cementations materials excess of use protected under shed.
  • 13. A- Water pipe protect. 3-1 Water requirements . B – Chiller machine . C – Ice plant or nitrogen cooling system . D –Water and ice plant calibrations. 3- Water and admixture requirements. A- Additive storage silos . 3-2 Admixture requirements B – Additive gage calibration . C – All admixture excess of use protected under shad. D –Agitation system for all tanks or silos more than 5000 liter . 13
  • 14. 14 B- Computer controlled . 4- Batching plant requirements. C- Plant type . D- Computer print out . E- Calibration validity . F- Cleaning of mixer blades. A- Certificate validity .
  • 15. A – Equipment calibration validity. 5- Laboratory requirements. D – Temperature for curing tank. B – Records of test results . C – Method and result of slump and temp for concrete at plant . 15
  • 16. 16 Thank you Eng . Ahmed Abdul Halim