This document provides a summary of Michael Sobhy Fakhry's personal and professional experience. It includes his personal details, education history, technical skills in piping engineering, personal skills, computer skills, courses, training, and work experience with three different companies from 2008 to present. His work experience includes roles as a piping site engineer for large industrial plants in Egypt and Saudi Arabia, and as a mechanical maintenance engineer for a plastics company in Egypt.
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
The Project management plan presented here will describe the project manager’s approach and the general responsibilities of the project team. In addition to the project management plan, several other documents will be developed and used to ensure compliance with project requirements as well regulations and industry specific standards. The specific plans will include processes, flow diagrams, responsibility matrices, organizational charts, and other pertinent information to guide the project staff.
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
The Project management plan presented here will describe the project manager’s approach and the general responsibilities of the project team. In addition to the project management plan, several other documents will be developed and used to ensure compliance with project requirements as well regulations and industry specific standards. The specific plans will include processes, flow diagrams, responsibility matrices, organizational charts, and other pertinent information to guide the project staff.
Senior Supervisor Piping & Mechanical
Piping &Pipe Line Fabrication/Erection&/ Hydro test /Mechanical Completion Pre-Commissioning
I have around17+, years ‘work experience I have done three years diploma inMechanical engineering,
I have worked as a Piping supervisor in Oil, Gas, power plant & Petro-chemical.
1. Michael Sobhy Fakhry
Piping Engineer
PPeerrssoonnaall DDaattaa
• Date of Birth : 27th March 1986
• Nationality : Egyptian
• Mobile Number : +2 01227030325
• Land Line : +2(03)3245346
• E-mail : michaelsobhy@ymail.com
• Marital Status : Married
• Military Status : Exempted
• Address : 24 El Tdamon Eleslamy st branched from Balbaa,
sidi beshr, Alexandria, Egypt.
• Driving License : Valid
• Hobbies : Reading,
Studying for technical objectives,
Fixing old things,
Research for new sciences
EEdduuccaattiioonn
• University Degree: : Bachelor of mechanical Engineering.
• University : Alexandria University.
• Grade : Passed.
• Graduation project : Design for 3D automatic washing machine.
• Project grade : Excellent.
• Graduated Year : 2008.
• Languages : English (Very Good).
Arabic (mother language).
2. TTeecchhnniiccaall SSkkiillllss
Have 7+ Years of Experience in piping Engineering : fabrication, erection,
pressure testing, flushing and blowing activities. Skilled in leading and
supervising piping teams during the
plants erection, commissioning and start-up phases.
Making site evaluation, proposals and contact the technical office for approval.
PPeerrssoonnaall SSkkiillllss
Ability to work under pressure for many hours, interpersonal skills,
communication skills, well organized, Ability to improve my performance.
Ability to deal with different religions, cultures, foods and persons without
problems
CCoommppuutteerr SSkkiillssll :
• AutoCAD.
• Navisworks
• Windows XP.
• Microsoft Power point.
• Internet Explorer.
• Microsoft Word.
• (ICDL): valid.
• Mat lab.
3. CCoouurrsseess
• Vibration analysis. ( for motors –mechanical parts using graphs , charts
,devices like vibrometer )
• Automotive engineering.
• Hydraulic (circuits – design – maintenance –trade marks knowledge )
TTrraaiinniinngg ::
• Mosahmet El Behera for heavy trucks. [caterpillar ,komatsu ]
(Hydraulic system, mechanical maintenance for engines and gear boxes)
• El Seiof power station.
(Boilers, steam and gas turbines, condensers, pumps, compressors and fire
fitting system)
• Ideal Company washing machines department.
(Assembling and disassembling for the mechanical parts and maintenance)
WWoorrkk eexxppeerriieenncceess::
11--DDaanniieellii &&CC EErreeccttiioonn aanndd CCoommmmiissssiioonniinngg IInntteerrnnaattiioonnaall CCoommppaannyy ffoorr
ppllaannttss ::
A- November 2013 – Present:
Company : Danieli & C. SpA.
Job Title : Piping Site Engineer
Location : Ezz Steel-Egypt - New Direct Reduction Plant (DRP).
4. B- December 2012 – November 2013:
Company : Danieli & C. SpA.
Job Title : Piping Site Engineer
Location : Hadeed Steel-Saudi Arabia – Rolling mill and steel making
plant
C- June 2012 – November 2012:
Company : Danieli & C. SpA.
Job Title : Piping Site Engineer
Location : Ezz Steel-Egypt - New Direct Reduction Plant (DRP).
Duties Description :
• Work as piping site engineer for DRP, Rolling mills and steel making plant
with all related Auxiliary and RO plants.
• Preparing material request according to standards specifications.
• Reviewing the drawing supplied and checking P&ID drawing for assuring
its possibility and correctness according to the site condition
• Making site evaluation, proposals and contact the technical office for
approval.
• Prepare scope of work for the contractors explaining the required activities
and the contractor responsibilities and showing the mandatory quality
requirements.
• Calculate and quote price, time period, required manpower and required
tools estimation for the jobs.
• Prepare job method statement for each job (The scope of this document is to
detail how a work task or process is to be completed, highlighting the
hazards involved and including a step by step guide on how to do the job
5. safely and relevant control measures have been introduced to ensure the
safety of anyone who is affected by the task or process).
• Checking the offers/quotations submitted by the contractors, and select the
suitable company to do the job according on the quality, price and work
duration.
• Generating punch list of all the piping issues
• Witness and performing hydro tests, pneumatic tests, flushing and blowing
for the circuits.
• Performing alignment for expansion joints, pumps and compressors piping
tie-in and supervise the fabrication and erection of the modified lines
assuring the matching of the work quality with the quality standards.
• Prepare the required material lists and spools dimensions for pressure test,
flushing and blowing temporary spools and bypasses required.
• Prepare test packages for pressure tests, flushing and blowing activities
showing the test limits, bypasses and temporary spools locations, valves to
be closed/opened and instruments to be isolated/removed.
• Dealed with water lines, gas lines (process gas, natural gas and oxygen
lines), steam lines (high pressure, low pressure) and hydraulic lines.
• Following steam blow out, oxygen lines degreasing and hydraulic lines
pickling activities.
• Work with FRP /GRP pipes and lamination procedure.
• Work with Polyethylene and Polypropylene pipes with fusion welding
procedure.
6. 22-- EESSIISSCCOO ::EEggyyppttiiaann SSppoonnggee IIrroonn aanndd SStteeeell CCoommppaannyy ((BBeesshhaayy sstteeeell
ggrroouupp))
October 2009 – June 2012
Company : Beshay Steel
Job Title : Piping Site Engineer
Location : Sadat City-Egypt – Section mill and steel making plant
Duties Description:
Erection
1. Fabrication and Erection of pipe lines in MELT SHOP: EAF, LF and pipe rack,
CCM (Siemens) for few months.
• Light section mill DANIELI .
2. Supervising a group of pipe fitters, grinders and welders working in
Hydraulic, Oxygen, Natural Gas, Water, AIR , AR and lubrication pipe lines
using mechanical drawings , P&ID and 3D model.
3. Technical office: making isometrics for workshop, engineering details, and
modifications to drawings by using AutoCAD program, request material
according to drawings and international standards.
4. Material control and inspection.
5. Making punch list for pipe lines systems.
Testing
1. Assistance for hydro test.
2. Preparing and following pickling procedure related to international
standards.
3. Assistance for making flushing for hydraulic, grease and lubrication lines.
4. Assistance for making flushing and pasivation for water lines for WTP.
5. Managing for making flushing for all air lines.
6. Using standard documentation like: ASME ,ASTM .
7. Organization for all manpower per area and jobs.
7. Commissioning
1. Following all procedures before and during the commissioning like: purging
the lines with nitrogen, reassembling for the lines with final check by P&IDs
and first filling also organize the manpower for the commissioning people.
2. Check of Instrument data list / Hook up and following the erection related
to P&IDs and drawings.
3. Making detail reports: work progress, problems during erection, missing
materials and manpower distribution.
4. Following all commissioning procedures for the light section mill including
all the problems of that phase.
5. Finishing all the cold test for the plant (furnace ,EWR ,mill stands ,cooling
bed,straightening machine,cold shear and disk saws)
Maintenance
1. Preparing the maintenance schedules.
2. Preparing all the spare parts (hydraulic & pneumatic cylinders, pumps,
bearing, hydraulic &pneumatic valves, and cranes for the factory for the
next 2 years.
3. Following the maintenance works (mechanical and hydraulic).
33-- MMeennaass PPllaasstt CCoommppaannyy ffoorr ppllaassttiicc--EEggyypptt..
October 2008 – October 2009
Company : Menas Plast for plastic
Job Title : Mechanical Maintenance Engineer.
Location : El Amrya City-Egypt
Duties Description:
1. Performing Maintenance works for Hydraulic and pneumatic machines.
2. Preparing Maintenance schedule for all machines.
3. Preparing Material requests for spare parts.
4. Performing modification by the aid of workshop.