CE 592 - Estimation Planning & Control Term Project
1. BLACKBOX CONSTRUCTION, LLC.
CE 592
CONSTRUCTION ESTIMATING, PLANNING,
AND CONTROL
FALL 2016
PORTERS NECK ELEMENTARY SCHOOL
Abhishek Singh
Parth Malhotra
Rakeshkumar ‘Ron’ Patel
Sai Ruthvik Pabolu
Varun Kumar Sampath
2. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Table of Contents
BID FORMS..............................................................................................................i
SECTION 1 PROJECT DATA......................................................................................1
1.1Project Details
1.2Proposed Construction Team..........................................................................2
1.2.1 Meet Our President .................................................................................3
1.2.2 Estimator .................................................................................................3
1.2.3 Project Manager ......................................................................................3
1.2.4 Project Superintendent............................................................................3
1.2.5 Project Engineer.......................................................................................3
SECTION 2 EXECUTIVE SUMMARY........................................................................10
2.1 Project Description.......................................................................................10
2.2 Project Description.......................................................................................11
2.3 Summary of Main Findings...........................................................................12
2.4 Closing Statement........................................................................................13
2.5 Required Bid Documents .............................................................................13
SECTION 2 ESTIMATE............................................................................................14
3.1 Rough Order Magnitude Estimate................................................................14
3.2 Summary of Bid............................................................................................17
3.3 Detailed Bid.................................................................................................18
3.4 Company Overhead.....................................................................................20
3.5 Sales History................................................................................................22
3.6 Labor Burden...............................................................................................23
3.7 General Conditions......................................................................................41
SECTION 4 SCHEDULE ...........................................................................................42
4.1 Work Breakdown Structure..........................................................................42
4.2 Schedule ......................................................................................................44
3. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 5 PROJECT CONTROLS ...........................................................................46
5.1 Schedule of Values.......................................................................................46
5.2 Cash Flow Analysis .......................................................................................49
5.3 Value Engineering ........................................................................................52
SECTION 6 Appendix ............................................................................................54
6.1 Adjusted Sub-contractor Bid Values.............................................................54
6.2 Detailed Estimates .......................................................................................65
6.2.1 Detailed Estimate for Concrete ......................................................................65
6.2.2 Detailed Estimate for Masonry.......................................................................66
6.2.3 Detailed Estimate for Paving..........................................................................67
6.2.4 Summary of Site Work.................................................................................68
6.2.5 Detailed Estimate for Wood Shelving ...............................................................81
6.2.6 Detailed Estimate for Fire Sprinklers ................................................................82
6.2.7 Detailed Estimate for Painting........................................................................83
6.2.8 Detailed Estimate for PVC Roofing ..................................................................84
6.2.9 Detailed Estimate for Stage Flooring ................................................................85
6.2.10 Detailed Estimate for ACM Panel...................................................................86
6.2.11 Detailed Estimate for Operable Partition .........................................................87
6.2.12 Detailed Estimate for Basket Ball Goals ...........................................................88
6.2.13 Detailed Estimate for Lockers.......................................................................89
6.2.14 Detailed Estimate for HVAC .........................................................................90
6.2.15 Detailed Estimate for Safety Padding............................................................109
6.2.16 Detailed Estimate for Traffic Coatings...........................................................111
6.2.17 Detailed Estimate for Acoustic Ceiling...........................................................112
6.2.18 Detailed Estimate for Acoustic Wall Units ......................................................113
4. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
6.2.19 Detailed Estimate for Landscaping and Irrigation .............................................114
6.2.20 Detailed Estimate for Final Electricity ...........................................................115
6.2.21 Detailed Estimate for Spray Fireproofing .......................................................115
6.2.22 Detailed Estimate for Structural steel ...........................................................116
6.2.23 Detailed Estimate for Aluminum Canopies .....................................................117
6.2.24 Detailed Estimate for Flagpoles ..................................................................118
6.2.25 Detailed Estimate for Ceramic Tiles..............................................................119
6.2.26 Detailed Estimate for Misc Firestopping ........................................................120
6.2.27 Detailed Estimate for Display Cases..............................................................121
6.2.28 Detailed Estimate for Louvers ....................................................................122
6.2.29 Detailed Estimate for Spray Foam Beam Infill..................................................123
6.2.30 Detailed Estimate for Foam Insulation ..........................................................125
6.2.31 Detailed Estimate for Dry Wall- Wall ............................................................127
6.2.32 Detailed Estimate for Dry Wall-Ceilings .........................................................128
6.2.33 Detailed Estimate for Framing ....................................................................131
6.2.34 Detailed Estimate for Inwall Blocking............................................................132
6.2.35 Detailed Estimate for Fiber Cement .............................................................133
6.2.36 Detailed Estimate for Security ....................................................................134
6.2.37 Detailed Estimate for Communication ..........................................................135
6.2.38 Detailed Estimate for Fire Alarm .................................................................136
5. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 1 – PROJECT DATA
1.1 Project Details:
Project Name:
Porters Neck Elementary School
Owner:
New Hanover County Schools
General Contractor:
Black Box Construction, LLC.
Architect:
LS3P Associates Ltd.
Civil:
Paramounte Engineering, Inc.
Structural:
Woods Engineering, PA
Fire Protection:
Robert E. Porterfield
Plumbing/Mechanical:
Cheatham and Associates, PA
Electrical:
Cheatham and Associates, PA
6. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2 Proposed Construction Team
1.2.1 Meet our President:
Rakeshkumar ‘Ron’ Patel
Company President
Ron started his career 26 years ago, as a project engineer. He worked for two construction
companies in capacities of a project engineer and eventually project manager before starting Black
Box Construction in 1997. Under the leadership of Ron, the company has established itself as an
esteemed general contractor in the residential, commercial, and institutional sectors.
Ron has an MS degree in Structural Engineering from North Carolina State University and he is
currently pursuing his doctorate degree (PhD) from North Carolina State University.
Ron can be reached at ronpatel@blackbox.net
7. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.2 Project Manager:
Parth Malhotra
Project Manager
After completing his MS in Construction Engineering from North Carolina State University, Parth
joined the company in 2001 and has been working with the company ever since. Out of his total
experience of 16 years, Parth has worked in the capacity of a project engineer for 3 years, as a
Assistant Project Manager for 4 years and for the past 7 years, he has been working as the Project
Manager for the company. In addition to his responsibilities as a Project Manager, he also oversees
the development of our safety program.
Parth can be reached at pmalhotra@blackbox.net
8. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.3 Estimator:
Abhishek Singh
Chief Estimator
Abhishek has worked in the construction industry since he was 16 years old. His father had a
construction business his home country of India and Abhishek used to work for him since he was
in high school. After graduating with a Bachelor’s degree in Civil Engineering from National
Institute of Technology – India, he worked as a Project Engineer for three years on an airport
project before moving to US for his master’s degree in Construction Engineering from NCSU.
After completing his masters’ degree, Abhishek worked in Turner for 3 years as a Estimator and
as a Senior Estimator for 4 years at Bechtel.
Abhishek joined the Black Box team in 2007 as a Chief Estimator. His vast experience in the
construction industry and his expertise in project management are one of the biggest assets of our
company. He is also currently developing a pull based workflow system to introduce lean
construction principles in our company.
Abhishek can be reached at asingh@blackbox.net
9. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.4 Project Superintendent:
Varun Kumar Sampath
Project Superintendent
Varun has been with Black Box Construction since its inception in 1997 and has been instrumental
in the success of some of our most prestigious projects. Varun began his career at Samet to support
himself while concurrently pursuing his master’s degree at North Carolina State University with
full time course load. Upon graduating, Varun continued to work with Samet for 12 years before
joining Black Box in 2012. Varun is a thorough team player and has exceptional communication
skills. He has diverse problem solving and analytical skills which enable him to maintain the
schedule on the most complex and challenging projects.
Varun can be reached at vsampath@blackbox.net
10. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.2.5 Project Engineer:
Sai Ruthvik Pabolu
Project Engineer
Ruthvik joined the Black Box family in the Summer of 2012 as an intern while he was pursuing
his construction engineering degree at North Carolina State University. Upon graduation, Ruthvik
began working full time as a project engineer with Black Box Construction. Ruthvik has worked
on estimating, CAD drawings, submittals, change order, safety orientations, task co-ordination and
personnel management. Ruthvik has been also involved in labor productivity studies and he has
also been doing research on ways to reduce construction wastage and improve labor productivity
while concurrently working towards his P.E. certification.
Ruthvik can be reached at rpabolu@blackbox.net
11. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.3 About our Company
In July ,1997 Mr. Rakeshkumar ‘Ron’ Patel, with a loan of $25,000 from his father established the
company in his garage. The company initially began as a masonry sub-contractor and quickly
proliferated in to a general contracting company. Over the years, the company has grown from a
residential contractor in to a diversified company with experience in building commercial,
institutional, and public buildings.
Black Box Construction specializes in construction of high end residential homes, shopping malls,
schools, libraries, museums, theaters, and courthouses.
Since, 2012 the company has grown about twice in size and we expect it to grow with the same
pace in future with the vision to be North Carolina’s premier construction organization by
achieving extraordinary results for our customers, building satisfying careers for our people, and
earning a fair return on the value we deliver.
Our mission and core values are a starting point that help clearly define who we are and what we
stand for as a company. They underlie the passion that drives us to be better and different; they
allow us the freedoms of our entrepreneurial organization, where people can make a difference
with their ideas and hard work
Mission:
To be the preeminent provider of superior construction services by consistently improving the
quality of our services; to add value for clients through innovation, foresight, integrity, and to serve
with character and purpose.
Core Values:
Ethics
We are uncompromising in our integrity, honesty, and fairness.
Safety & Health
We are relentless in keeping people safe from harm, and we provide a healthy work environment.
Quality
We are passionate about excellence and doing our work right the first time. Our reputation depends
on our delivered value in the eyes of every customer and community.
People
We inspire each other with important work full of purpose, challenging development opportunities,
and rewarding careers. We aspire to be the employer of choice in our industry.
Relationships
We build positive, long-term relationships with our customers, joint-venture partners,
subcontractors, suppliers, and colleagues that are built on trust, respect, and collaboration.
12. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
1.3.1 Past Projects:
Davidson Middle School
Value: $14.1 million
Location: Thomasville, NC
Brunswick County Court House
Value: $10.4 million
Location: Bolivia, NC
Hodgson Residence
Value: $8 million
Location: Wilmington, NC
13. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Fairfield Inn and Suite, Merrett
Value: $13.27 million
Myrtle Beach, SC
Status: Under Construction.
Completion date: April 20,2017.
Status on November 2,2016 4:35:02pm
Product at Completion
14. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 2 – EXECUTIVE SUMMARY
2.1 Project Description
Black Box Construction was presented with the opportunity to develop a bid proposal for
providing construction services for the Porters Neck Elementary School to be built in Wilmington,
NC. The project is a two storey 81,201 SF school.
The project delivery method for the project is Design-Bid-Build with a Single Prime Bid contract.
This report contains information on the project estimation, schedule, building system, cost
summaries, client information, project delivery system, and staffing organization.
The following items are required to be provided to the owner before commencement of
construction:
1. A bid for furnishing general contracting services that includes all labor, equipment,
materials, and subcontracting work for the complete scope of work as per the construction
documents provided.
2. A work breakdown structure of all the activities required to complete the project.
3. A list of activities with the quantities, productivity and estimated duration needed for the
completion of each activity required to complete the project.
4. A verifiable Activity on Node (AON) diagram that details the logic sequence of the entire
construction process.
5. A CPM schedule for the project to identify the critical path for the project.
6. A schedule of values, schedule of estimated payments and a cash flow that details the flow
of money throughout the duration of project.
7. Value engineering suggestions that could be beneficial for the owner.
15. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
2.2 Project Description:
One most important aspects of a construction project are to form an effective project team to
manage the construction project effectively. The decisions made by the project team towards the
management of the project ultimately impact the construction of the project. Effective management
ensures on-schedule and on-budget completion of the project which is crucial for any project.
At Black Box Construction, our team recognizes the importance of the Porters Neck Elementary
School project. The school is significant for the nearby community since will impact the
development of children of the community.
The team at Black Box Construction adopted the following process for the completion of the scope
of work of the project:
1. A detailed study of the construction documents and specification was carried out to
effectively plan the scope of work.
2. The team developed pricing for various items included in the scope of work by performing
detailed quantity take-offs for the self-performed work and by obtaining prices from sub-
contractors for the sub-contracted work.
3. A bid was prepared by incorporating the required company overhead, profit, and
contingency to the direct costs. A schedule of values was also concurrently developed.
4. The sub-contractor bids received had the sub-contractor general conditions listed as a
separate item. The general conditions were proportionally distributed among the activities
and the cost was adjusted for January 2017 (Refer to Appendix, )
5. Upon finalizing the cost estimate, the team started the development of a construction
schedule. A work breakdown structure was developed from which the activities were
logically laid out to obtain a construction schedule and the critical path for the project was
identified. The schedule was developed using Primavera P6.
6. After the schedule was developed, the team focused on developing the project cash flow.
The project cash flow is a representation of the expected inflow-outflow of money during
the execution of the project.
7. In the final stages of the process, value engineering alternatives were discussed and the
most beneficial suggestions were incorporated in the project manual subjected to the
approval of the owner/architect.
16. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
2.3 Summary of Main Findings:
Black Box Construction is pleased to provide a Single Prime Bid of $ 14,263,759 for the
construction of Porters Neck Elementary School at 416 Edgewater Club Road, Wilmington, NC
28411. Please refer to Section 3, Page 14 for Bid Summary details.
The project consists of the construction of a new 80,349 sf elementary school including complete
site development, roadway improvements, utilities, structural concrete, masonry and steel
construction, roofing, exterior and interior finishes, equipment, fixtures, furnishing, and complete
fire sprinkler, plumbing, HVAC, and electrical systems.
The Single Prime Bid provided is based on documents developed by LS3P Associates Ltd., dated
August 10, 2015. The bid also incorporates adjustments in the scope of work as per Addendum 1,
Addendum 2 and Addendum 3, dated August 21, 2015; August 28, 2015 and September 4, 2015
respectively.
As per the construction schedule developed for the project based on the scope of work, the
estimated duration for the project is 554 Calendar Days (19 Months). Refer to Section 4, for the
CPM Schedule
The project cash flow based on the 19-month project duration can be found in Section 5.2
For Value Engineering suggestions, refer to Section 5.4
For additional references, such as back-up documentation and detailed quantity take-offs, refer to
Section 6, Appendix
17. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
2.4 Closing Statement:
Black Box Construction is pleased to submit the bid proposal for general contracting services for
the Porters Neck Elementary School. Our team recognizes the objectives and significance of the
project and its impact on the future of the community.
Porters Neck Elementary School is a critical project for the development of the community and
the future of the children of the community. A project of such significance requires a contractor
who has prior experience in delivering similar projects and who is recognized for the quality of its
work. Black Box Construction has worked throughout North Carolina on a wide variety of
projects. More importantly, our team has prior experience of constructing public and institutional
buildings such as courthouses, libraries, and schools. Our previous school project, Davidson
Middle School located in Thomasville, NC was very similar in scope with the proposed project
and we believe that our experience from the project would be tremendously beneficial in the
successful delivery of the proposed project.
Our stellar past performance coupled with an extremely talented and dedicated core team makes
us one of the frontrunners for this project. At Black Box Construction, we always put our customers
first. Customer Satisfaction and Relationships has always been the priority for the company.
We hope that our bid proposal meets your expectations and we look forward to the opportunity to
present our work and highlight our project management approach for the project
18. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
SECTION 3 - ESTIMATE
3.1 Rough Order of Magnitude Estimate
A rough order of magnitude estimate is used to provide an approximate value of final construction.
It is much easier and faster to arrive upon when compared to detailed estimates and is typically
used in the conceptual phase, to determine project feasibility. Its accuracy is around ±20% as
compared to detailed estimate.
The RS Means Building Construction Cost database provides us with data to calculate ROM for
typical building construction in the United States of America. It correlated 4 different factors with
the built-up space and does not include the cost of land, A/E fee and other supplemental. These
factors essentially include quality of construction, size of built up area, project location and time
of construction. It is important to include all these factors to arrive upon the ROM to customize
the costs for our project. RS Means costs are based on a typical size project on an average city in
the US.
The following process with direct us through determining ROM for our project
The following parameters have been identified from the bid documents and will enable us to
arrive upon the ROM.
Parameter Constraint
Construction Size 81,201 sq. ft.
Quality High (Includes Site Work & Equipment)
Location Wilmington, NC
Time of Construction January 2017
Quality Factor
Size Factor
Location Factor
Time Factor
ROM Value
19. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Using RS Means data,
Per sq. ft. cost of construction:
Per sq. ft. cost for “high” quality construction for Elementary School from RS Means is $172
Size modifier:
Typical size of an elementary school from RS Means is 41,000 sq. ft.
The proposed building area is 80,201 sq. ft.
Size factor = Proposed building area / Typical Size
Size factor = 81,201 sq. ft. / 41,000 sq. ft.
Size factor = 1.98
The size modifier (cost multiplier) for the size factor of 1.98 as per the cost modifier curve
is 0.95
Location modifier
Wilmington City Cost Index = 81.0
Location modifier, Wilmington = (City Cost Index Wilmington)/ (Average city USA cost index)
= 81.0 / 100
= 0.81
The location modifier for Wilmington, NC is equal to 0.81
Time modifier
Using data from ENR over RS Means for higher accuracy, the time modifier for January 2017
has been derived as follows:
May 2016 = 5,637
June 2016 = 5,636;
July 2016 = 5,660;
Aug 2016 = 5,670;
∆ Average = 11
January 2017 = July 2016 + 6 * 11
January 2017 = 5726
∆ = -1
∆ = 24
∆ = 10
20. BLACK BOX CONSTRUCTION, LLC.
3320, INDEPENDENCE DRIVE
RALEIGH, NC – 27606
Time modifier = January 2017 Index / January 2015 Index
Time modifier = 5726/5497
Time modifier = 1.04
The time modifier to adjust cost for October 2016 is equal to 1.04
ROM = Size of the building (sq. ft.) * Per square feet cost * location modifier * Size modifier *
Time modifier
ROM = 81,201 sq. ft. * $172 * 0.81 * 0.95 * 1.04
ROM = $ 11, 177, 168
Rough Order Magnitude Estimate
1 Square footage of building (sq. ft.) 81,201
2 Per sq ft. cost ($/sq ft) $172
3 Location Modifier 0.81
4 Size Modifier 0.95
5 Time Modifier 1.04
Total ROM $11,177,168
From the above calculations, the rough order magnitude estimate for the proposed school
building is $11,177,168.
21. BLACK BOX CONSTRUCTION, LLC.
DIV Description Material ($) Labor ($) Equipment ($) Subcontractors ($) Sub-Total($)
1 General Conditions $17,806.25 $593,719.63 $56,133.73 $256,279.02 $923,938.63
2 Site Work $635,979.72 $350,787.98 $282,351.74 $0.00 $1,269,119.44
3 Concrete $253,516.49 $161,570.86 $4,938.51 $0.00 $420,025.86
4 Masonry $359,985.57 $423,520.56 $0.00 $0.00 $783,506.13
5 Metals $990,402.42 $990,402.42
6 Wood, Plastics and Composites $216,290.00 $216,290.00
7 Thermal and Moisture Protection $444,863.24 $444,863.24
8 Openings $379,003.57 $379,003.57
9 Finishes $1,391,528.89 $1,391,528.89
10 Specialities $632,261.56 $632,261.56
11 Equipment $259,075.18 $259,075.18
12 Furnishings $75,178.28 $75,178.28
14 Conveying Equipment $251,217.60 $251,217.60
21 Fire Supression $1,054,680.98 $1,054,680.98
22 Plumbing $629,995.43 $629,995.43
23 HVAC $1,470,781.29 $1,470,781.29
27 Communications $383,335.93 $383,335.93
28 Electronic Safety and Security $59,013.86 $59,013.86
32 Exterior Improvements $266,385.12 $266,385.12
33 Utilities $397,860.98 $397,860.98
Total Direct Cost $12,298,464.40
Company Overhead (CoOH) (7.98% of Direct Cost) $981,417.46
Profit (4% of Direct Cost) $491,938.58
Contingency (4% of Direct Cost) $491,938.58
Total Mark-Up (15.98% of Direct Cost) $1,965,294.61
$14,263,759
For General Conditions, Refer to Page 41
For Company Overhead Calculation, Refer to Page 20
Total Project Cost (BID VALUE)
3.2 SUMMARY OF BID
17
23. BLACK BOX CONSTRUCTION, LLC.
DIV 10 Specialities $632,261.56
Hollow Metal, Wood Dorrs, Toilet Part, Toilet acc,
FEC $271,248.79 $271,248.79
Signage and Marquee $24,850.21 $24,850.21
Basket Ball Goals $6,514.59 $6,514.59
Lockers $1,355.25 $1,355.25
Banners $672.98 $672.98
Operable Partititon $124,399.16 $124,399.16
Aluminum Canopies $190,735.40 $190,735.40
Flagpoles $12,485.18 $12,485.18
DIV 11 Equipment $259,075.18
Food Service Equipment $227,356.00 $227,356.00
Kiln $4,315.74 $4,315.74
Residential Appliances $7,492.69 $7,492.69
Stage Curtains, Folding Stages, Cubicle Curtains $19,910.75 $19,910.75
DIV 12 Furnishings $75,178.28
Wood Shelving $70,340.78 $70,340.78
Display Cases $4,837.50 $4,837.50
DIV 14 Conveying Equipment $251,217.60
Elevators $251,217.60 $251,217.60
DIV 21 Fire Supression $1,054,680.98
Spray Fireproofing $449,541.93 $449,541.93
Misc Firestopping $195,558.75 $195,558.75
Fire Sprinklers $409,580.29 $409,580.29
DIV 22 Plumbing $629,995.43
Plumbing System Sub-Contract $629,995.43 $629,995.43
DIV 23 HVAC $1,470,781.29
HVAC System Sub-Contract $1,470,781.29 $1,470,781.29
DIV 26 Electrical $383,335.93
Electrical System Sub-Contract $383,335.93 $383,335.93
DIV 27 Communications $59,013.86
Communication System $59,013.86 $59,013.86
DIV 28 Electronic Safety and Security $266,385.12
Fire Alarm $146,465.21 $146,465.21
Security $119,919.91 $119,919.91
DIV 32 Exterior Improvements $397,860.98
Fencing $35,284.98 $35,284.98
Landscaping and Irrigation $362,576.00 $362,576.00
19
24. CASH FLOW
Activities SOV Work Type 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
General Conditions 516,978$ Self Performed 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$ 32,311$
Site work 284,695$ Self Performed 284,695$
Grading and Footing Excavation 444,319$ Self Performed 133,296$ 311,023$
Utility Pipelines 199,935$ Self Performed 119,961$ 79,974$
Foundation 166,970$ Self Performed 166,970$
Steel 894,611$ Sub-Contracted 894,611$
Concrete Slab 246,949$ Sub-Contracted 49,390$ 197,559$
Caulking 12,706$ Sub-Contracted 12,706$
Masonary 620,758$ Sub-Contracted 248,303$ 372,455$
H.V.A.C 1,274,271$ Sub-Contracted 127,427$ 318,568$ 318,568$ 318,568$ 191,141$
Plumbing 736,769$ Sub-Contracted 221,031$ 294,708$ 221,031$
Electrical 353,999$ Sub-Contracted 106,200$ 247,799$
Elevator 217,653$ Sub-Contracted 217,653$
Exterior Finishings 1,183,747$ Sub-Contracted 591,874$ 591,874$
Brick Veneer 951,998$ Sub-Contracted 380,799$ 571,199$
Roof 303,662$ Sub-Contracted 242,929$ 60,732$
Partition walls 145,297$ Sub-Contracted 58,119$ 36,324$ 36,324$ 14,530$
Dry Wall 209,668$ Sub-Contracted 146,767$ 62,900$
Speciality Rough-ins 729,034$ Sub-Contracted 218,710$ 291,613$ 218,710$
Interior finishes 1,256,042$ Sub-Contracted 125,604$ 62,802$ 125,604$ 502,417$ 314,010$ 125,604$
Door and Windows 453,716$ Sub-Contracted 45,372$ 90,743$ 45,372$ 272,230$
Paint 147,507$ Sub-Contracted 44,252$ 103,255$
Exterior Landscaping 334,828$ Sub-Contracted 284,604$ 50,224$
Hardware 258,876$ Sub-Contracted 194,157$ 64,719$
Miscellaneous 62,809$ Sub-Contracted 3,140$ 6,281$ 53,387$
Kitchen Appliances 274,652$ Sub-Contracted 274,652$
Cleaning 6,378$ Self Performed 6,378$
Final Punch List 117,650$ Self Performed 117,650$
570,263$ 423,308$ 199,281$ 976,312$ 490,879$ 1,598,469$ 1,860,448$ 840,668$ 681,907$ 697,804$ 799,949$ 877,994$ 700,027$ 581,194$ 836,689$ 271,282$
DC as a % of SOV (85%) (1) 484,723$ 359,812$ 169,389$ 829,865$ 417,248$ 1,358,699$ 1,581,380$ 714,568$ 579,621$ 593,134$ 679,956$ 746,295$ 595,023$ 494,015$ 711,186$ 230,590$
COOH as a % of SOV (10%) (2) 57,026$ 42,331$ 19,928$ 97,631$ 49,088$ 159,847$ 186,045$ 84,067$ 68,191$ 69,780$ 79,995$ 87,799$ 70,003$ 58,119$ 83,669$ 27,128$
P+C as a & of SOV (5%) (3) 28,513$ 21,165$ 9,964$ 48,816$ 24,544$ 79,923$ 93,022$ 42,033$ 34,095$ 34,890$ 39,997$ 43,900$ 35,001$ 29,060$ 41,834$ 13,564$
$ paid or spent by the GC 541,750$ 402,143$ 189,317$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 30,696$ 139,892$
$ paid or spent by subs 896,801$ 435,640$ 1,487,850$ 1,736,730$ 767,939$ 617,116$ 632,219$ 729,256$ 803,398$ 634,330$ 521,439$ 764,159$ 117,826$
$ Billed to the client 570,263$ 423,308$ 199,281$ 976,312$ 490,879$ 1,598,469$ 1,860,448$ 840,668$ 681,907$ 697,804$ 799,949$ 877,994$ 700,027$ 581,194$ 836,689$ 271,282$
% Retained by the client (5%) 57,026$ 42,331$ 19,928$ 97,631$ 49,088$ 159,847$ 186,045$ 84,067$ 68,191$ 69,780$ 79,995$ 87,799$ 70,003$ 58,119$ 83,669$ 27,128$
Money Received from client 513,236$ 380,978$ 179,353$ 878,681$ 441,792$ 1,438,622$ 1,674,403$ 756,601$ 613,716$ 628,024$ 719,954$ 790,194$ 630,024$ 523,075$ 753,020$ 244,154$
$ Billed by subs to GC 896,801$ 435,640$ 1,487,850$ 1,736,730$ 767,939$ 617,116$ 632,219$ 729,256$ 803,398$ 634,330$ 521,439$ 764,159$ 117,826$
% Retained by GC on Sub (5%) 89,680$ 43,564$ 148,785$ 173,673$ 76,794$ 61,712$ 63,222$ 72,926$ 80,340$ 63,433$ 52,144$ 76,416$ 11,783$
Total amount of money paid to sub by GC 807,121$ 392,076$ 1,339,065$ 1,563,057$ 691,145$ 555,405$ 568,997$ 656,330$ 723,059$ 570,897$ 469,295$ 687,743$ 106,044$
Net Paid or spent by GC -$ 541,750 $ 111,093 $ 191,660 $ 148,658 $ 40,864 $ 19,020 $ 68,862 $ 80,651 $ 34,761 $ 27,616 $ 28,332 $ 32,928 $ 36,440 $ 28,432 $ 23,084 -$ 74,615 $ 364,287
Cumulative of net paid by GC -$ 541,750 -$ 430,656 -$ 238,996 -$ 90,338 -$ 49,474 -$ 30,454 $ 38,408 $ 119,058 $ 153,819 $ 181,435 $ 209,767 $ 242,695 $ 279,135 $ 307,567 $ 330,651 $ 256,036 $ 620,324
GC is going to submit the bills at end of every month and GC will get paid after one month of the billing.
Subcontractor will submit their bill at end of each month and will get paid by GC after one month of billing.
Retainage will be 5% for the GC and Subcontractor.
-$ 600,000
-$ 400,000
-$ 200,000
$ 0
$ 200,000
$ 400,000
$ 600,000
$ 800,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Series1
25. BLACK BOX CONSTRUCTION, LLC.
Q1 Q3 Q4
P1 P2 P3 P4 P5
Sales $12,200,000 $1,275,000 $2,335,000 $4,010,000 $1,130,000 $20,950,000
PoOH $1,464,000 $153,000 $280,200 $481,200 $135,600 $2,514,000
Labor $3,721,000 $318,750 $553,750 $1,223,050 $344,650 $6,161,200
Materials $3,660,000 $372,500 $700,500 $1,203,000 $339,000 $6,275,000
Equipment $1,586,000 $165,750 $303,550 $521,300 $126,900 $2,703,500
Subcontractors - $63,519 $190,000 - - $253,519
Direct Cost (DC) $10,431,000 $1,073,519 $2,028,000 $3,428,550 $946,150 $17,907,219
CoOH $771,894 $62,420 $162,292 $271,285 $71,495 $1,339,386
Profit $997,106 $139,061 $144,708 $310,165 $112,355 $1,703,395
$17,907,219
$1,339,386
$1,703,395
7.48
3.5 Sales History - 2015
Black Box Construction, LLC., Sales History - 2015
Description
Q2
Total
The increase of 0.5% is to take into consideration a 5% salary increase (An increase of $ 60,960) that is proposed for the
employees and also the increase in the CoOH to account for increase in the cost of utilities such as Electricity, Internet,
Legal Services, Maintenance costs, Insurance costs etc.
Total Direct Cost for 2015
Company Overhead for 2015
Profit
CooH as a percentage of Direct Costs
For, the school project we propose a CoOH of 7.98%
22
26. BLACK BOX CONSTRUCTION, LLC.
Employee Base Salary Rate Burdened Salary Burden
President $150,000 1.32 $197,714 $47,714
CFO $120,000 1.34 $161,219 $41,219
Sr .Estimator $85,000 1.42 $121,073 $36,073
Estimator $75,000 1.37 $103,093 $28,093
Sr. Scheduler $75,000 1.46 $109,740 $34,740
Scheduler 65,000$ 1.41 $91,361 $26,361
Safety Manager (60%) $34,800 1.80 $62,766 $27,966
Office Manager $50,000 1.37 $68,316 $18,316
Bid Co-ordinator $50,000 1.37 $68,316 $18,316
Acountant $50,000 1.37 $68,316 $18,316
Administrator $45,000 1.28 $57,412 $12,412
HR $45,000 1.28 $57,412 $12,412
Receptionist $37,440 1.40 $52,467 $15,027
Total $882,240 $1,219,205 $336,965
Employee Base Salary Rate Burdened Salary Burden
Project Manager $75,000 1.56 $116,693 $41,693
Field Superintendent $60,000 1.60 $96,011 $36,011
Project Engineer $55,000 1.62 $88,834 $33,834
General Superintendent (40% of Time)$26,000 1.59 $41,276 $15,276
Safety Manager (40%) $23,200 1.80 $41,844 $18,644
Total $239,200 $384,659 $145,459
General Superintendent - 40% on this project, 60% on other projects
3.6 Labor Burden
*Refer to Labor Burden Sheets for Calculations
Labor Burden (Part of PoOH)
Labor Burden (Part of CoOH)
Safety Manager - Base Salary - $58,000 is split 60% in Office and 40% in Field
23
27. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 150,000.00$ per year
Equivalent "Base" Wage Per Hour 72.12$
"Base" Hourly Wage 72.12$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 72.12$
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 1 days 4 hours/day 4 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1876 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 108.18$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.92$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 1.92$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 74.04$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 74.04$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.94$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.59$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 4.59$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 1.07$ per hour
Cost of Government Required Insurance and Taxes 7.60$ per/hr
Hourly Rate c): Inclusive of Portion 2 81.64$ per/hr
Vacation 80 hours 81.64$ per hour 6,531.3$ 3.48$ per/hr
Holidays 80 hours 81.64$ per hour 6,531.3$ 3.48$ per/hr
Sick Leave 40 hours 81.64$ per hour 3,265.7$ 1.74$ per/hr
Company Wide Meetings/Training 4 hours 81.64$ per hour 326.6$ 0.17$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 81.64$ per hour -$ -$ per/hr
Morning Meetings 0 hours 81.64$ per hour -$ -$ per/hr
Rest Breaks 0 hours 81.64$ per hour -$ -$ per/hr
16,654.86$ 8.88$ per/hr
Hourly Wage d): Inclusive of Portion 3 90.52$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Company Provided Car 500.00$ per month 6,000.0$ per year 3.20$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour
Cost of Non-Taxable, Company Paid, Fringes 4.54$ per/hr
Hourly Wage e): Inclusive of Portion 4 95.06$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 72.12$ "Base" Rate Compared To: 95.06$ 1.32
Labor Burden -President
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
24
28. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 120,000.00$ per year
Equivalent "Base" Wage Per Hour 57.69$
"Base" Hourly Wage 57.69$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 57.69$
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 1 days 4 hours/day 4 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1876 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 86.54$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.92$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 1.92$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 59.61$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 59.61$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.76$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.48$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 3.70$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.86$ per hour
Cost of Government Required Insurance and Taxes 6.20$ per/hr
Hourly Rate c): Inclusive of Portion 2 65.81$ per/hr
Vacation 80 hours 65.81$ per hour 5,264.7$ 2.81$ per/hr
Holidays 80 hours 65.81$ per hour 5,264.7$ 2.81$ per/hr
Sick Leave 40 hours 65.81$ per hour 2,632.3$ 1.40$ per/hr
Company Wide Meetings/Training 4 hours 65.81$ per hour 263.2$ 0.14$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 65.81$ per hour -$ -$ per/hr
Morning Meetings 0 hours 65.81$ per hour -$ -$ per/hr
Rest Breaks 0 hours 65.81$ per hour -$ -$ per/hr
per year 13,424.86$ 7.16$ per/hr
Hourly Wage d): Inclusive of Portion 3 72.96$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Company Provided Car 500.00$ per month 6,000.0$ per year 3.20$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour
Cost of Non-Taxable, Company Paid, Fringes 4.54$ per/hr
Hourly Wage e): Inclusive of Portion 4 77.51$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 57.69$ "Base" Rate Compared To: 77.51$ 1.34
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Labor Burden -Chief Financial Officer (CFO)
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
25
29. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 85,000.00$ per year
Equivalent "Base" Wage Per Hour 40.87$
"Base" Hourly Wage 40.87$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 40.87$
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 61.31$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $250 per month per year 3,000.0$ 1.60$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 3.51$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 44.38$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 44.38$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.57$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.36$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.75$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.64$ per hour
Cost of Government Required Insurance and Taxes 4.72$ per/hr
Hourly Rate c): Inclusive of Portion 2 49.10$ per/hr
Vacation 80 hours 49.10$ per hour 3,927.8$ 2.09$ per/hr
Holidays 80 hours 49.10$ per hour 3,927.8$ 2.09$ per/hr
Sick Leave 40 hours 49.10$ per hour 1,963.9$ 1.04$ per/hr
Company Wide Meetings/Training 0 hours 49.10$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 49.10$ per hour -$ -$ per/hr
Morning Meetings 0 hours 49.10$ per hour -$ -$ per/hr
Rest Breaks 0 hours 49.10$ per hour -$ -$ per/hr
per year 9,819.60$ 5.22$ per/hr
Hourly Wage d): Inclusive of Portion 3 54.32$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Company Provided Car 400.00$ per month 4,800.0$ per year 2.55$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour
Cost of Non-Taxable, Company Paid, Fringes 3.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 58.21$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 40.87$ "Base" Rate Compared To: 58.21$ 1.42
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Labor Burden - Senior Estimator
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
26
30. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 75,000.00$ per year
Equivalent "Base" Wage Per Hour 36.06$
"Base" Hourly Wage 36.06$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 36.06$
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 54.09$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $250 per month per year 3,000.0$ 1.60$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 3.51$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 39.57$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 39.57$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.50$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.32$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.45$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.57$ per hour
Cost of Government Required Insurance and Taxes 4.25$ per/hr
Hourly Rate c): Inclusive of Portion 2 43.82$ per/hr
Vacation 80 hours 43.82$ per hour 3,505.6$ 1.86$ per/hr
Holidays 80 hours 43.82$ per hour 3,505.6$ 1.86$ per/hr
Sick Leave 40 hours 43.82$ per hour 1,752.8$ 0.93$ per/hr
Company Wide Meetings/Training 0 hours 43.82$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 43.82$ per hour -$ -$ per/hr
Morning Meetings 0 hours 43.82$ per hour -$ -$ per/hr
Rest Breaks 0 hours 43.82$ per hour -$ -$ per/hr
per year 8,764.04$ 4.66$ per/hr
Hourly Wage d): Inclusive of Portion 3 48.48$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Company Provided Cell Phone 30.00$ per month 360.0$ per year 0.19$ per hour
Cost of Non-Taxable, Company Paid, Fringes 1.09$ per/hr
Hourly Wage e): Inclusive of Portion 4 49.57$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 36.06$ "Base" Rate Compared To: 49.57$ 1.37
Labor Burden - Estimator
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
27
31. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 75,000.00$ per year
Equivalent "Base" Wage Per Hour 36.06$
"Base" Hourly Wage 36.06$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 36.06$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 54.09$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 3.83$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 39.89$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 39.89$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.51$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.32$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.47$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.58$ per hour
Cost of Government Required Insurance and Taxes 4.28$ per/hr
Hourly Rate c): Inclusive of Portion 2 44.17$ per/hr
Vacation 80 hours 44.17$ per hour 3,533.6$ 1.88$ per/hr
Holidays 80 hours 44.17$ per hour 3,533.6$ 1.88$ per/hr
Sick Leave 40 hours 44.17$ per hour 1,766.8$ 0.94$ per/hr
Company Wide Meetings/Training 0 hours 44.17$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 44.17$ per hour -$ -$ per/hr
Morning Meetings 0 hours 44.17$ per hour -$ -$ per/hr
Rest Breaks 0 hours 44.17$ per hour -$ -$ per/hr
per year 8,834.08$ 4.70$ per/hr
Hourly Wage d): Inclusive of Portion 3 48.87$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Company Provided Car 400.00$ per month 4,800.0$ per year 2.55$ per hour
Company Provided Cell Phone 70.00$ per month 840.0$ per year 0.45$ per hour
Cost of Non-Taxable, Company Paid, Fringes 3.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 52.76$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 36.06$ "Base" Rate Compared To: 52.76$ 1.46
Labor Burden - Senior Scheduler
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
28
32. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 65,000$ per year
Equivalent "Base" Wage Per Hour 31.25$
"Base" Hourly Wage 31.25$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 31.25$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 46.88$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 3.83$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 35.08$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 35.08$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.45$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.28$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.17$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.51$ per hour
Cost of Government Required Insurance and Taxes 3.81$ per/hr
Hourly Rate c): Inclusive of Portion 2 38.89$ per/hr
Vacation 80 hours 38.89$ per hour 3,111.4$ 1.66$ per/hr
Holidays 80 hours 38.89$ per hour 3,111.4$ 1.66$ per/hr
Sick Leave 40 hours 38.89$ per hour 1,555.7$ 0.83$ per/hr
Company Wide Meetings/Training 0 hours 38.89$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 38.89$ per hour -$ -$ per/hr
Morning Meetings 0 hours 38.89$ per hour -$ -$ per/hr
Rest Breaks 0 hours 38.89$ per hour -$ -$ per/hr
7,778.53$ 4.14$ per/hr
Hourly Wage d): Inclusive of Portion 3 43.03$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 43.92$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 31.25$ "Base" Rate Compared To: 43.92$ 1.41
Labor Burden - Scheduler
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
29
33. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 50,000.00$ per year
Equivalent "Base" Wage Per Hour 24.04$
"Base" Hourly Wage 24.04$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 24.04$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 36.06$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 1.91$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 25.95$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 25.95$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.33$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.21$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.61$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.38$ per hour
Cost of Government Required Insurance and Taxes 2.93$ per/hr
Hourly Rate c): Inclusive of Portion 2 28.88$ per/hr
Vacation 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Holidays 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Sick Leave 40 hours 28.88$ per hour 1,155.2$ 0.61$ per/hr
Company Wide Meetings/Training 0 hours 28.88$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 28.88$ per hour -$ -$ per/hr
Morning Meetings 0 hours 28.88$ per hour -$ -$ per/hr
Rest Breaks 0 hours 28.88$ per hour -$ -$ per/hr
5,776.07$ 3.07$ per/hr
Hourly Wage d): Inclusive of Portion 3 31.95$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 32.85$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 24.04$ "Base" Rate Compared To: 32.85$ 1.37
Labor Burden - Office Manager
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
30
34. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 50,000.00$ per year
Equivalent "Base" Wage Per Hour 24.04$
"Base" Hourly Wage 24.04$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 24.04$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 36.06$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 1.91$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 25.95$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 25.95$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.33$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.21$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.61$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.38$ per hour
Cost of Government Required Insurance and Taxes 2.93$ per/hr
Hourly Rate c): Inclusive of Portion 2 28.88$ per/hr
Vacation 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Holidays 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Sick Leave 40 hours 28.88$ per hour 1,155.2$ 0.61$ per/hr
Company Wide Meetings/Training 0 hours 28.88$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 28.88$ per hour -$ -$ per/hr
Morning Meetings 0 hours 28.88$ per hour -$ -$ per/hr
Rest Breaks 0 hours 28.88$ per hour -$ -$ per/hr
5,776.07$ 3.07$ per/hr
Hourly Wage d): Inclusive of Portion 3 31.95$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 32.85$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 24.04$ "Base" Rate Compared To: 32.85$ 1.37
Labor Burden - Bid Co-ordinator
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
31
35. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 50,000.00$ per year
Equivalent "Base" Wage Per Hour 24.04$
"Base" Hourly Wage 24.04$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 24.04$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 36.06$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 1.91$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 1.91$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 25.95$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 25.95$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.33$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.21$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.61$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.38$ per hour
Cost of Government Required Insurance and Taxes 2.93$ per/hr
Hourly Rate c): Inclusive of Portion 2 28.88$ per/hr
Vacation 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Holidays 80 hours 28.88$ per hour 2,310.4$ 1.23$ per/hr
Sick Leave 40 hours 28.88$ per hour 1,155.2$ 0.61$ per/hr
Company Wide Meetings/Training 0 hours 28.88$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 28.88$ per hour -$ -$ per/hr
Morning Meetings 0 hours 28.88$ per hour -$ -$ per/hr
Rest Breaks 0 hours 28.88$ per hour -$ -$ per/hr
per year 5,776.07$ 3.07$ per/hr
Hourly Wage d): Inclusive of Portion 3 31.95$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 32.85$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 24.04$ "Base" Rate Compared To: 32.85$ 1.37
Labor Burden - Accountant
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
32
36. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 45,000.00$ per year
Equivalent "Base" Wage Per Hour 21.63$
"Base" Hourly Wage 21.63$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 21.63$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 32.45$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $0 per month per year -$ -$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents -$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 21.63$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 21.63$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.28$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.17$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.34$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.31$ per hour
Cost of Government Required Insurance and Taxes 2.50$ per/hr
Hourly Rate c): Inclusive of Portion 2 24.13$ per/hr
Vacation 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hr
Holidays 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hr
Sick Leave 40 hours 24.13$ per hour 965.4$ 0.51$ per/hr
Company Wide Meetings/Training 0 hours 24.13$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 24.13$ per hour -$ -$ per/hr
Morning Meetings 0 hours 24.13$ per hour -$ -$ per/hr
Rest Breaks 0 hours 24.13$ per hour -$ -$ per/hr
per year 4,826.97$ 2.57$ per/hr
Hourly Wage d): Inclusive of Portion 3 26.70$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 27.60$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 21.63$ "Base" Rate Compared To: 27.60$ 1.28
Labor Burden - Administrator
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
33
37. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 45,000.00$ per year
Equivalent "Base" Wage Per Hour 21.63$
"Base" Hourly Wage 21.63$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 21.63$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1880 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 32.45$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $0 per month per year -$ -$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents -$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 21.63$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 21.63$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.28$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.17$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.34$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.31$ per hour
Cost of Government Required Insurance and Taxes 2.50$ per/hr
Hourly Rate c): Inclusive of Portion 2 24.13$ per/hr
Vacation 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hr
Holidays 80 hours 24.13$ per hour 1,930.8$ 1.03$ per/hr
Sick Leave 40 hours 24.13$ per hour 965.4$ 0.51$ per/hr
Company Wide Meetings/Training 0 hours 24.13$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 24.13$ per hour -$ -$ per/hr
Morning Meetings 0 hours 24.13$ per hour -$ -$ per/hr
Rest Breaks 0 hours 24.13$ per hour -$ -$ per/hr
per year 4,826.97$ 2.57$ per/hr
Hourly Wage d): Inclusive of Portion 3 26.70$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.64$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.89$ per/hr
Hourly Wage e): Inclusive of Portion 4 27.60$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 21.63$ "Base" Rate Compared To: 27.60$ 1.28
Labor Burden - HR
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
34
38. BLACK BOX CONSTRUCTION, LLC.
Equivalent Yearly Wage 37,440.00$ per year
Equivalent "Base" Wage Per Hour 18.00$
"Base" Hourly Wage 18.00$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 18.00$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 5 days 4 hours/day 20 hours per year
Morning Meetings 235 days 0 hours/day 0 hours per year
Rest Breaks 235 days 0 hours/day 0 hours per year
Effective Work Hours = Contracted - Unbillable 1860 hours per year
Company Paid Overtime Work Time (If Any) 100.0 hours/year overtime rate 27.00$ per hour
Company Paid Overtime 100 hours/year per year 2,700.0$ 1.45$ per/hr
Company Paid Allowance for Use of Personal Car per month per year -$ -$ per/hr
Company Paid Health Care Allowance* per month per year -$ -$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 1.45$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 19.45$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 19.45$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 1.50 1.275 % of Hourly Rate a) 0.25$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.16$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.39$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.21$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.28$ per hour
Cost of Government Required Insurance and Taxes 2.30$ per/hr
Hourly Rate c): Inclusive of Portion 2 21.75$ per/hr
Vacation 80 hours 21.75$ per hour 1,739.9$ 0.94$ per/hr
Holidays 80 hours 21.75$ per hour 1,739.9$ 0.94$ per/hr
Sick Leave 40 hours 21.75$ per hour 870.0$ 0.47$ per/hr
Company Wide Meetings/Training 0 hours 21.75$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 20 hours 21.75$ per hour 435.0$ 0.23$ per/hr
Morning Meetings 0 hours 21.75$ per hour -$ -$ per/hr
Rest Breaks 0 hours 21.75$ per hour -$ -$ per/hr
per year 4,784.76$ 2.57$ per/hr
Hourly Wage d): Inclusive of Portion 3 24.32$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.65$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.06$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.06$ per hour
401K 20.00$ per month 240.0$ per year 0.13$ per hour
Cost of Non-Taxable, Company Paid, Fringes 0.90$ per/hr
Hourly Wage e): Inclusive of Portion 4 25.22$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 18.00$ "Base" Rate Compared To: 25.22$ 1.40
Labor Burden - Receptionist
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
35
39. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 58,000.00$ per year
Equivalent "Base" Wage Per Hour 27.88$
"Base" Hourly Wage 27.88$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 27.88$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per year
Effective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 41.82$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 4.38$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 32.26$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 32.26$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 4.00 3.4 % of Hourly Rate a) 1.10$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.26$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.00$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.47$ per hour
Cost of Government Required Insurance and Taxes 4.28$ per/hr
Hourly Rate c): Inclusive of Portion 2 36.54$ per/hr
Vacation 80 hours 36.54$ per hour 2,923.0$ 1.78$ per/hr
Holidays 80 hours 36.54$ per hour 2,923.0$ 1.78$ per/hr
Sick Leave 40 hours 36.54$ per hour 1,461.5$ 0.89$ per/hr
Company Wide Meetings/Training 0 hours 36.54$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 36.54$ per hour -$ -$ per/hr
Morning Meetings 117.5 hours 36.54$ per hour 4,293.2$ 2.61$ per/hr
Rest Breaks 117.5 hours 36.54$ per hour 4,293.2$ 2.61$ per/hr
per year 15,894.03$ 9.66$ per/hr
Hourly Wage d): Inclusive of Portion 3 46.20$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour
Company provided Pick up Truck 400.00$ 4,800.0$ 2.92$
Company provided cell phone 30.00$
401K 20.00$ per month 240.0$ per year 0.15$ per hour
Cost of Non-Taxable, Company Paid, Fringes 4.09$ per/hr
Hourly Wage e): Inclusive of Portion 4 50.29$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 27.88$ "Base" Rate Compared To: 50.29$ 1.80
Labor Burden - Safety Manager (60% Office and 40% Site)
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
36
40. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 75,000.00$ per year
Equivalent "Base" Wage Per Hour 36.06$
"Base" Hourly Wage 36.06$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 36.06$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per year
Effective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 54.09$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 38.25$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 38.25$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 5.00 4.25 % of Hourly Rate a) 1.63$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.31$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.37$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.55$ per hour
Cost of Government Required Insurance and Taxes 5.32$ per/hr
Hourly Rate c): Inclusive of Portion 2 43.56$ per/hr
Vacation 80 hours 43.56$ per hour 3,485.2$ 2.12$ per/hr
Holidays 80 hours 43.56$ per hour 3,485.2$ 2.12$ per/hr
Sick Leave 40 hours 43.56$ per hour 1,742.6$ 1.06$ per/hr
Company Wide Meetings/Training 0 hours 43.56$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 43.56$ per hour -$ -$ per/hr
Morning Meetings 117.5 hours 43.56$ per hour 5,118.8$ 3.11$ per/hr
Rest Breaks 117.5 hours 43.56$ per hour 5,118.8$ 3.11$ per/hr
per year 18,950.63$ 11.52$ per/hr
Hourly Wage d): Inclusive of Portion 3 55.08$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour
Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hr
Hourly Wage e): Inclusive of Portion 4 56.11$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 36.06$ "Base" Rate Compared To: 56.11$ 1.56
Labor Burden - Project Manager
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
37
41. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 65,000.00$ per year
Equivalent "Base" Wage Per Hour 31.25$
"Base" Hourly Wage 31.25$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 31.25$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per year
Effective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 46.88$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 33.44$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 33.44$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 6.00 5.1 % of Hourly Rate a) 1.71$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.27$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 2.07$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.48$ per hour
Cost of Government Required Insurance and Taxes 4.99$ per/hr
Hourly Rate c): Inclusive of Portion 2 38.43$ per/hr
Vacation 80 hours 38.43$ per hour 3,074.2$ 1.87$ per/hr
Holidays 80 hours 38.43$ per hour 3,074.2$ 1.87$ per/hr
Sick Leave 40 hours 38.43$ per hour 1,537.1$ 0.93$ per/hr
Company Wide Meetings/Training 0 hours 38.43$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 38.43$ per hour -$ -$ per/hr
Morning Meetings 117.5 hours 38.43$ per hour 4,515.3$ 2.74$ per/hr
Rest Breaks 117.5 hours 38.43$ per hour 4,515.3$ 2.74$ per/hr
per year 16,716.19$ 10.16$ per/hr
Hourly Wage d): Inclusive of Portion 3 48.59$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour
Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hr
Hourly Wage e): Inclusive of Portion 4 49.61$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 31.25$ "Base" Rate Compared To: 49.61$ 1.59
Labor Burden - General Superintendent
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
38
42. BLACK BOX CONSTRUCTION, LLC.
Base Yearly Salary 60,000.00$ per year
Equivalent "Base" Wage Per Hour 28.85$
"Base" Hourly Wage 28.85$ per hour WORK DAYS:
Contracted Work Hours (CWH) 52 weeks 40 hours/week 2080 hours per year 260
This is the Hourly "Base" Rate Used for Labor Burden Calculation 28.85$
Company Unbillable Paid Time: Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Vacation 10 days 8 hours/day 80 hours per year
Holidays 10 days 8 hours/day 80 hours per year
Sick Leave 5 days 8 hours/day 40 hours per year
Company Wide Meetings/Employer Required Training 0 days 0 hours/day 0 hours per year
Bad Weather Minimum Show-Up Time 0 days 0 hours/day 0 hours per year
Morning Meetings 235 days 0.5 hours/day 117.5 hours per year
Rest Breaks 235 days 0.5 hours/day 117.5 hours per year
Effective Work Hours = Contracted - Unbillable 1645 hours per year
Company Paid Overtime Work Time (If Any) 0.0% as a % of CWH overtime rate 43.28$ per hour
Company Paid Overtime 0 hours/year per year -$ -$ per/hr
Company Paid Allowance for Use of Personal Car $0 per month per year -$ -$ per/hr
Company Paid Health Care Allowance* $300 per month per year 3,600.0$ 2.19$ per/hr
Company Paid Bonus 0 per month per year -$ -$ per/hr
Cost of Taxable, Company Paid, Allowances and Cash Equivalents 2.19$ per/hr
Hourly Rate a): Inclusive of Portion 1 (Used for Wcomp and Building Risk and Pub Liability Insurance Cost Calc) 31.04$ per/hr
PreTax Payments Made By Employee for Insurance -$ per month per year -$ -$ per/hr
Hourly Rate b) Incluse of Portion 1 (Used for SS and Medicare Tax Calc) 31.04$ per/hr
Required Insurance and Taxes Enter EMR 0.85 per hour
Workers Compensation Ins. 6.00 5.1 % of Hourly Rate a) 1.58$ per hour
Builders Risk and Public Liability Ins. 8.00 per 1,000 of Hourly Rate a) 0.25$ per hour
Federal Unemployment Tax 0.25 % 9,000.00$ is Co's Federal Tax Base 0.01$ per hour
State Unemployment Tax 3.00 % 24,400.00$ is Co's State Tax Base 0.44$ per hour
Social Security Tax 6.20 % of Hourly Rate b) 1.92$ per hour
Medicare, Medicaid Tax 1.45 % of Hourly Rate b) 0.45$ per hour
Cost of Government Required Insurance and Taxes 4.66$ per/hr
Hourly Rate c): Inclusive of Portion 2 35.70$ per/hr
Vacation 80 hours 35.70$ per hour 2,856.2$ 1.74$ per/hr
Holidays 80 hours 35.70$ per hour 2,856.2$ 1.74$ per/hr
Sick Leave 40 hours 35.70$ per hour 1,428.1$ 0.87$ per/hr
Company Wide Meetings/Training 0 hours 35.70$ per hour -$ -$ per/hr
Bad Weather Minimum Show-Up Time 0 hours 35.70$ per hour -$ -$ per/hr
Morning Meetings 117.5 hours 35.70$ per hour 4,195.1$ 2.55$ per/hr
Rest Breaks 117.5 hours 35.70$ per hour 4,195.1$ 2.55$ per/hr
per year 15,530.73$ 9.44$ per/hr
Hourly Wage d): Inclusive of Portion 3 45.14$ per/hr
Group Health Insurance (includes Dental)* 100.00$ per month 1,200.0$ per year 0.73$ per hour
Disability Insurance (Short Term) 10.00$ per month 120.0$ per year 0.07$ per hour
Disability Insurance (Long Term) 10.00$ per month 120.0$ per year 0.07$ per hour
401K 20.00$ per month 240.0$ per year 0.15$ per hour
Cost of Non-Taxable, Company Paid, Fringes 1.02$ per/hr
Hourly Wage e): Inclusive of Portion 4 46.17$ per/hr
BURDEN FOR THIS EMPLOYEE IS: 28.85$ "Base" Rate Compared To: 46.17$ 1.60
Labor Burden - Field Superintendent
Portion 1 of Labor Burden: Cost of Taxable, Company Paid, Cash Allowances and Other Taxable Cash Equivalents
Portion 2 of Labor Burden: Cost of Government Required Insurance and Taxes
Portion 3 of Labor Burden: Cost of Unbillable Time as a result of Company Provided BENEFITS and needed for OPERATIONS
Portion 4 of Labor Burden: Cost of Non Taxable, Company Paid, Fringes
39