SlideShare a Scribd company logo
1 of 30
Benefit/Cost Analysis
LO4a
EGN 3203 Engineering Economics
LO3 – a
LEARNING OUTCOMES
9-2
1. Explain difference in public vs. private sector projects
2. Calculate B/C ratio for single project
3. Select better of two alternatives using B/C method
Introduction
• Evaluation methods of previous LO are usually applied to alternatives
in the private sector.
• This LO introduces economic consideration for the public sector.
• In the case of public projects, the owners and users (beneficiaries)
are the citizens and residents of a government unit—city, county,
state, province or nation.
• Government units provide the mechanisms to raise capital and
operating funds.
• This chapter also introduces service sector projects and discusses
how their economic evaluation is different from that for other
projects
9-3
• A public sector project is a product, service, or system used,
financed, and owned by the citizens of any government level. The
primary purpose is to provide service to the citizenry for the public
good at no profit. Areas such as public health, criminal justice, safety,
transportation, welfare, and utilities are all publically owned and
require economic evaluation.
Some public sector examples:
• Hospitals and clinics
• Parks and recreation
• Utilities: water, electricity, gas, sewer, sanitation
• Schools: primary, secondary, community
• colleges, universities
9-4
Introduction
9-5
Life Longer (30 – 50+ years) Shorter (2 – 25 years)
Annual CF No profit Profit-driven
Funding Taxes, fees, bonds, etc. Stocks, bonds, loans, etc.
Interest rate Lower Higher
Selection criteria Multiple criteria Primarily ROR
Environment of evaluation Politically inclined Economic
Characteristic Public Private
Size of Investment Large Small, medium, large
9-6
Contractors does not share project risk
 Fixed price - lump-sum payment
 Cost reimbursable - Cost plus, as negotiated
Contractor shares in project risk
 Public-private partnerships (PPP), such as:
 Design-build projects - Contractor responsible from
design stage to operations stage
 Design-build-operate-maintain-finance (DBOMF)
projects - Turnkey project with contractor managing
financing (manage cash flow); government obtains
funding for project
• To perform a benefit/cost economic analysis of public
alternatives, the costs (initial and annual), the benefits, and the
dis-benefits, if considered, must be estimated as accurately as
possible in monetary units.
• Costs—estimated expenditures to the government entity for
construction, operation, and maintenance of the project, less any
expected salvage value.
• Benefits—advantages to be experienced by the owners, the
public.
• Dis-benefits—expected undesirable or negative consequences to
the owners if the alternative is implemented. Dis-benefits may be
indirect economic disadvantages of the alternative.
9-7
Benefit/Cost Analysis
Benefit/Cost Analysis
• The benefit/cost ratio is relied upon as a fundamental analysis method
for public sector projects.
• All cost and benefit estimates must be converted to a common
equivalent monetary unit (PW, AW, or FW) at the discount rate (interest
rate). The B/C ratio is then calculated using one of these relations:
• Present worth and annual worth equivalencies are preferred to future
worth values.
• The sign convention for B/C analysis is positive signs; costs are preceded
by a + sign.
• Salvage values and additional revenues to the government, when they
are estimated, are subtracted from costs in the denominator.
• Dis-benefits are considered in different ways depending upon the model
used.
9-8
• The conventional B/C ratio, probably the most widely used,
• Dis-benefits are subtracted from benefits, not added to costs.
9-9
Benefit/Cost Analysis
• The modified B/C ratio includes all the estimates associated with the
project such as maintenance and operation. (M&O) costs are placed
in the numerator and treated as dis-benefits. The denominator
includes only the initial investment.
• all amounts are expressed in PW, AW, or FW terms, the modified B/C
ratio is calculated as
Two types of analyses:
• It is possible to develop a direct formula connection between the B/C
of a public sector and B/C of a private sector project that is a revenue
alternative ; both revenues and costs are estimated.
• the PW for project cash flows is
PW of project = PW of revenue - PW of costs
• This relation can be slightly rewritten to form the profitability index
(PI), which can be used to evaluate revenue projects in the public or
private sector.
9-10
Benefit/Cost Analysis
B/C Relations : summary
cost
Benefit (B) -- Advantages to the public
Disbenefit (D) -- Disadvantages to the public
Cost (C) -- Expenditures by the government
Note: Savings to government are subtracted from costs
Conventional B/C ratio = (B–D) / C
Modified B/C ratio = [(B–D) – C] / Initial Investment
Profitability Index = NCF / Initial Investment
Note 1 : All terms must be expressed in same units, i.e., PW, AW, or FW
Note 2 : Do not use minus sign ahead of costs
9-11
Must identify each cash flow as either benefit, dis-benefit, or cost
9-12
Benefit/cost analysis
If B/C ≥ 1.0, project is economically justified at
discount rate applied
If B/C < 1.0, project is not economically acceptable
Profitability index analysis of
revenue projects
If PI ≥ 1.0, project is economically justified at
discount rate applied
If PI < 1.0, project is not economically acceptable
9-13
Conventional B/C ratio =
B - D
C
Modified B/C ratio = B – D – M&O
C
If B/C ≥ 1.0,
accept project;
otherwise, reject
PI =
PW of initial investment
If PI ≥ 1.0,
accept project;
otherwise, reject
PW of NCFt
Denominator is
initial investment
A flood control project will have a first cost of $1.4 million with an annual
maintenance cost of $40,000 and a 10 year life. Reduced flood damage is
expected to amount to $175,000 per year. Lost income to farmers is estimated
to be $25,000 per year.At an interest rate of 6% per year, should the
project be undertaken?
Solution: Express all values inAW terms and find B/C ratio
B = $175,000
D = $25,000
C = 1,400,000(A/P,10,%6)+40,000$ = 230,218$
B/C= (175,000 – 25,000) / 230,218
= 0.65 < 1.0
Do not build project
9-14
Example: B/C Analysis – Single Project
Annual – use AW
9-15
Example: B/C Analysis – Single Project
Example Conventional & Modified B/C
B
D
A
P
9-16
Example: B/C Analysis – Single Project
Conventional B/C
Modified B/C
Example Conventional & Modified B/C
The cost of grading and spreading gravel on a short rural road is
expected to be $300,000. The road will have to be maintained at a
cost of $25,000 per year. Even though the new road is not very
smooth, it allows access to an area that previously could only be
reached with off-road vehicles. The improved accessibility has led to
a 150% increase in the property values along the road. If the previous
market value of a property was $900,000, calculate the B/C ratio
using an interest rate of 6% per year and a 20-year study period.
Solution
9-17
Example: B/C Analysis – Single Project
Example Conventional B/C
The cost of grading and spreading gravel on a short rural road is
expected to be $300,000. The road will have to be maintained at a
cost of $25,000 per year. Even though the new road is not very
smooth, it allows access to an area that previously could only be
reached with off-road vehicles. The improved accessibility has led to
a 150% increase in the property values along the road. If the previous
market value of a property was $900,000, calculate the B/C ratio
using an interest rate of 6% per year and a 20-year study period.
Solution
B = 900,000(1.5) – 900,000 = $450,000
C = 300,000 + 25,000(P/A,6%,20)
= 300,000 + 25,000(11.4699)
= $586,748
B/C = 450,000/586,748 = 0.77
9-18
Example: B/C Analysis – Single Project
Example Conventional B/C
9-19
Example: B/C Analysis – Single Project
Example profitability index (PI),
9-20
Example: B/C Analysis – Single Project
Example profitability index (PI),
Defender, Challenger and Do NothingAlternatives
When selecting from two or more ME alternatives, there is a:
 Defender – in-place system or currently selected alternative
 Challenger – Alternative challenging the defender
 Do-nothing option – Status quo system
General approach for incremental B/C analysis of two ME alternatives:
 Lower total cost alternative is first compared to Do-nothing (DN)
 If B/C for the lower cost alternative is < 1.0, the DN option is compared to
∆B/C of the higher-cost alternative
 If both alternatives lose out to DN option, DN prevails, unless
overriding needs requires selection of one of the alternatives
9-21
9-22
Procedure similar to ROR analysis for multiple alternatives
(1) Determine equivalent total cost for each alternative
(2) Order alternatives by increasing total cost
(3) Identify B and D for each alternative, if given, or go to step 5
(4) Calculate B/C for each alternative and eliminate all with B/C < 1.0
(5) Determine incremental costs and benefits for first two alternatives
(6) Calculate ∆B/C; if >1.0, higher cost alternative becomes defender
(7) Repeat steps 5 and 6 until only one alternative remains
Select higher
cost alternative
B/C Analysis of Independent Projects
 Independent projects comparison does not
require incremental analysis
 Compare each alternative’s overall B/C with DN option
+ No budget limit: Accept all alternatives with B/C ≥ 1.0
+ Budget limit specified: capital budgeting problem; selection
follows different procedure (discussed in chapter 12)
9-23© 2012 by McGraw-Hill All Rights Reserved
Example: Incremental B/C Analysis
Compare two alternatives using i = 10% and B/C ratio
Eliminate X
Eliminate DNY vs. DN: (150,000 – 45,000) / 98,428 = 1.07
9-24© 2012 by McGraw-Hill All Rights Reserved
Solution: First, calculate equivalent total cost
AW of costsX = 320,000(A/P,10%,10) + 45,000 = $97,080
AW of costsY = 540,000(A/P,10%,20) + 35,000 = $98,428
Order of analysis is X, then Y
X vs. DN: (B-D)/C = (110,000 – 20,000) / 97,080 = 0.93
Alternative X Y
First cost, $ 320,000 540,000
M&O costs, $/year 45,000 35,000
Benefits, $/year 110,000 150,000
Disbenefits, $/year 20,000 45,000
Life, years 10 20
9-25
Example: ∆B/C Analysis;
9-26
Example: ∆B/C Analysis;
9-27
Example: ∆B/C Analysis;
Solution
East vs. DN: (B-D)East = 990,000 – 120,000 = $870,000 per year
CEast = 11,000,000(0.06) + 100,000 = $760,000 per year
(B-D)/C = 870,000/760,000
= 1.14
Eliminate DN
West vs. East: Δ(B-D) = (2,400,000 – 100,000) – (990,000 – 120,000) = $1,430,000
ΔC = [27,000,000(0.06) + 90,000] – 760,000 = $950,000
ΔB/C = 1,430,000/950,000
= 1.51
Select West location
9.31 The estimates shown are for a bridge under consideration for a river
crossing in Wheeling, West Virginia. Use the B/C ratio method at an
interest rate of 6% per year to determine which bridge, if either, should be
built.
9-28
Example: ∆B/C Analysis; Selection Required
Must select one of two alternatives using i = 10% and ∆B/C ratio
Alternative X Y
Solution: Must select X or Y; DN not an option, compare Y to X
AW of costsX = $97,080 AW of costsY = $98,428
Incremental values: ∆B = 150,000 – 110,000 = $40,000
Y vs. X: (∆B - ∆D) / ∆C = (40,000 – 25,000) / 1,348 = 11.1 Eliminate X
9-29© 2012 by McGraw-Hill All Rights Reserved
∆D = 45,000 – 20,000 = $25,000
∆C = 98,428 – 97,080 = $1,348
First cost, $ 320,000 540,000
M&O costs, $/year 45,000 35,000
Benefits, $/year 110,000 150,000
Disbenefits, $/year 20,000 45,000
Life, years 10 20
Ethical Considerations
Engineers are routinely involved in two areas
where ethics may be compromised:
Public policy making – Development of strategy, e.g.,
water system management (supply/demand strategy;
ground vs. surface sources)
Public planning - Development of projects, e.g., water
operations (distribution, rates, sales to outlying areas)
Engineers must maintain integrity and impartiality and
always adhere to Code of Ethics
9-30

More Related Content

What's hot

7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysisMohsin Siddique
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisionsBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Comparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and ManagementComparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and ManagementNzar Braim
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternativesBich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Annuities and gradient
Annuities and gradientAnnuities and gradient
Annuities and gradientReyman Solas
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy Sebghatullah Karimi
 
3. eng. cost and estimation
3. eng. cost and estimation3. eng. cost and estimation
3. eng. cost and estimationMohsin Siddique
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
4 interest and equivalence
4 interest and equivalence4 interest and equivalence
4 interest and equivalenceMohsin Siddique
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternativesNafis Ahmad
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Project evalaution techniques
Project evalaution techniquesProject evalaution techniques
Project evalaution techniquesMohd Arif
 
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...Dayana Mastura FCCA CA
 
Payback period by harikrishnanan
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnananHari krishna
 
Design of machine elements - Helical gears
Design of machine elements - Helical gearsDesign of machine elements - Helical gears
Design of machine elements - Helical gearsAkram Hossain
 

What's hot (20)

7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysis
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Comparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and ManagementComparing alternatives in Engineering Economics and Management
Comparing alternatives in Engineering Economics and Management
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Annuities and gradient
Annuities and gradientAnnuities and gradient
Annuities and gradient
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy
 
3. eng. cost and estimation
3. eng. cost and estimation3. eng. cost and estimation
3. eng. cost and estimation
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
4 interest and equivalence
4 interest and equivalence4 interest and equivalence
4 interest and equivalence
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternatives
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Project evalaution techniques
Project evalaution techniquesProject evalaution techniques
Project evalaution techniques
 
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
 
Payback period by harikrishnanan
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnanan
 
Design of machine elements - Helical gears
Design of machine elements - Helical gearsDesign of machine elements - Helical gears
Design of machine elements - Helical gears
 

Viewers also liked

Cost-benefit analysis
Cost-benefit analysisCost-benefit analysis
Cost-benefit analysisSoniya Balan
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solutionHaris Hassan
 
Cost Benifit Analysis
Cost Benifit AnalysisCost Benifit Analysis
Cost Benifit AnalysisTareq Zarouni
 
Cost-Benefit Analysis
Cost-Benefit AnalysisCost-Benefit Analysis
Cost-Benefit AnalysisSakshi Sharma
 
Cost benefit analysis
Cost benefit analysis Cost benefit analysis
Cost benefit analysis lekshmik
 
Cost benefit analysis in policy making ta 181113
Cost benefit analysis in policy making ta 181113Cost benefit analysis in policy making ta 181113
Cost benefit analysis in policy making ta 181113bisgovuk
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GMohan Kumar G
 
Cost benefit and cost effective analysis
Cost benefit and cost effective analysis Cost benefit and cost effective analysis
Cost benefit and cost effective analysis Mohamed Sheikh Omar
 
Career options in commerce
Career options in commerceCareer options in commerce
Career options in commerceAnant Agarwal
 
Introduction To Economics
Introduction To EconomicsIntroduction To Economics
Introduction To Economicsdheva B
 
Free Download Powerpoint Slides
Free Download Powerpoint SlidesFree Download Powerpoint Slides
Free Download Powerpoint SlidesGeorge
 

Viewers also liked (15)

Cost-benefit analysis
Cost-benefit analysisCost-benefit analysis
Cost-benefit analysis
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solution
 
Cost Benifit Analysis
Cost Benifit AnalysisCost Benifit Analysis
Cost Benifit Analysis
 
Cost-Benefit Analysis
Cost-Benefit AnalysisCost-Benefit Analysis
Cost-Benefit Analysis
 
Cost benefit analysis
Cost benefit analysis Cost benefit analysis
Cost benefit analysis
 
Kuliah minggu 7 bca
Kuliah minggu 7  bcaKuliah minggu 7  bca
Kuliah minggu 7 bca
 
Cost benefit analysis in policy making ta 181113
Cost benefit analysis in policy making ta 181113Cost benefit analysis in policy making ta 181113
Cost benefit analysis in policy making ta 181113
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
 
Economic Development Strategic Planning
Economic Development Strategic PlanningEconomic Development Strategic Planning
Economic Development Strategic Planning
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
 
Spm unit2
Spm unit2Spm unit2
Spm unit2
 
Cost benefit and cost effective analysis
Cost benefit and cost effective analysis Cost benefit and cost effective analysis
Cost benefit and cost effective analysis
 
Career options in commerce
Career options in commerceCareer options in commerce
Career options in commerce
 
Introduction To Economics
Introduction To EconomicsIntroduction To Economics
Introduction To Economics
 
Free Download Powerpoint Slides
Free Download Powerpoint SlidesFree Download Powerpoint Slides
Free Download Powerpoint Slides
 

Similar to B/C Analysis for Public Sector Projects

Ch9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).pptCh9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).ppt4723bilal
 
3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf18010YeashRahman
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Landry De Chabe
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio methodAli Juma Albahrani
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Neil Mathew
 
Project evaluation and cost benefit analysis
Project evaluation and cost benefit analysisProject evaluation and cost benefit analysis
Project evaluation and cost benefit analysisMAHONDO JAMES
 
appraisal of Forestry projects
appraisal of Forestry projects appraisal of Forestry projects
appraisal of Forestry projects Dronak Sahu
 
Lecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfLecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfssuser5feb82
 
Chapter-9-BC-ratio.pdf
Chapter-9-BC-ratio.pdfChapter-9-BC-ratio.pdf
Chapter-9-BC-ratio.pdfMaheshBika
 
COST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.pptCOST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.pptNamanyaBetrum1
 
NAP Training Viet Nam - Session 7 Appraising Adaptation Options
NAP Training Viet Nam - Session 7 Appraising Adaptation OptionsNAP Training Viet Nam - Session 7 Appraising Adaptation Options
NAP Training Viet Nam - Session 7 Appraising Adaptation OptionsUNDP Climate
 
Capital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptxCapital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptxRachanaSingh78
 

Similar to B/C Analysis for Public Sector Projects (20)

Unit-7.pdf
Unit-7.pdfUnit-7.pdf
Unit-7.pdf
 
Ch9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).pptCh9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).ppt
 
3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
Chapter_13.ppt
Chapter_13.pptChapter_13.ppt
Chapter_13.ppt
 
Lo4a(arif)
Lo4a(arif)Lo4a(arif)
Lo4a(arif)
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)
 
Project evaluation and cost benefit analysis
Project evaluation and cost benefit analysisProject evaluation and cost benefit analysis
Project evaluation and cost benefit analysis
 
appraisal of Forestry projects
appraisal of Forestry projects appraisal of Forestry projects
appraisal of Forestry projects
 
Public projects evaluation cba analysis
Public projects evaluation cba analysisPublic projects evaluation cba analysis
Public projects evaluation cba analysis
 
Bla18632 ch09
Bla18632 ch09Bla18632 ch09
Bla18632 ch09
 
Contruction economics
Contruction economicsContruction economics
Contruction economics
 
Lecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfLecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdf
 
feasibility study
 feasibility study feasibility study
feasibility study
 
Chapter-9-BC-ratio.pdf
Chapter-9-BC-ratio.pdfChapter-9-BC-ratio.pdf
Chapter-9-BC-ratio.pdf
 
COST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.pptCOST-BENEFIT ANALYSIS (2010)-1.ppt
COST-BENEFIT ANALYSIS (2010)-1.ppt
 
NAP Training Viet Nam - Session 7 Appraising Adaptation Options
NAP Training Viet Nam - Session 7 Appraising Adaptation OptionsNAP Training Viet Nam - Session 7 Appraising Adaptation Options
NAP Training Viet Nam - Session 7 Appraising Adaptation Options
 
Capital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptxCapital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptx
 
Vincent 3
Vincent 3Vincent 3
Vincent 3
 

More from Abdulaziz AlSuwaidi

Case study questions Engineering Economics
Case study questions Engineering EconomicsCase study questions Engineering Economics
Case study questions Engineering EconomicsAbdulaziz AlSuwaidi
 
Lo #5 manufacturing technology (jan 2016)
Lo #5 manufacturing technology (jan  2016)Lo #5 manufacturing technology (jan  2016)
Lo #5 manufacturing technology (jan 2016)Abdulaziz AlSuwaidi
 
Lo #4 manufacturing technology (jan 2016)
Lo #4 manufacturing technology (jan  2016)Lo #4 manufacturing technology (jan  2016)
Lo #4 manufacturing technology (jan 2016)Abdulaziz AlSuwaidi
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3bAbdulaziz AlSuwaidi
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Abdulaziz AlSuwaidi
 
Lo #3b (common)manufacturing technology (jan 2016) part 2
Lo #3b (common)manufacturing technology (jan  2016)   part 2Lo #3b (common)manufacturing technology (jan  2016)   part 2
Lo #3b (common)manufacturing technology (jan 2016) part 2Abdulaziz AlSuwaidi
 
Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Abdulaziz AlSuwaidi
 
Lo #2 manufacturing process primary secondary part 1
Lo #2 manufacturing process   primary  secondary part 1 Lo #2 manufacturing process   primary  secondary part 1
Lo #2 manufacturing process primary secondary part 1 Abdulaziz AlSuwaidi
 
Lo #1 design factors in manufacturing processes (sept 2015)
Lo #1 design factors in manufacturing processes (sept  2015)Lo #1 design factors in manufacturing processes (sept  2015)
Lo #1 design factors in manufacturing processes (sept 2015)Abdulaziz AlSuwaidi
 
Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Abdulaziz AlSuwaidi
 

More from Abdulaziz AlSuwaidi (17)

Case study questions Engineering Economics
Case study questions Engineering EconomicsCase study questions Engineering Economics
Case study questions Engineering Economics
 
Lo #5 manufacturing technology (jan 2016)
Lo #5 manufacturing technology (jan  2016)Lo #5 manufacturing technology (jan  2016)
Lo #5 manufacturing technology (jan 2016)
 
Lo4b(arif)
Lo4b(arif)Lo4b(arif)
Lo4b(arif)
 
Lo4b (nabil) breakeven analysis
Lo4b (nabil)   breakeven analysisLo4b (nabil)   breakeven analysis
Lo4b (nabil) breakeven analysis
 
Lo #4 manufacturing technology (jan 2016)
Lo #4 manufacturing technology (jan  2016)Lo #4 manufacturing technology (jan  2016)
Lo #4 manufacturing technology (jan 2016)
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
2. ethical theories part 2 (1)
2.  ethical theories part 2 (1)2.  ethical theories part 2 (1)
2. ethical theories part 2 (1)
 
1. ethical theories part 1
1. ethical theories part 11. ethical theories part 1
1. ethical theories part 1
 
Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3
 
Lo #3b (common)manufacturing technology (jan 2016) part 2
Lo #3b (common)manufacturing technology (jan  2016)   part 2Lo #3b (common)manufacturing technology (jan  2016)   part 2
Lo #3b (common)manufacturing technology (jan 2016) part 2
 
Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1
 
lo 2 handout 1 (2) PART 2
 lo 2 handout 1 (2) PART 2 lo 2 handout 1 (2) PART 2
lo 2 handout 1 (2) PART 2
 
Lo #2 manufacturing process primary secondary part 1
Lo #2 manufacturing process   primary  secondary part 1 Lo #2 manufacturing process   primary  secondary part 1
Lo #2 manufacturing process primary secondary part 1
 
Lo #1 design factors in manufacturing processes (sept 2015)
Lo #1 design factors in manufacturing processes (sept  2015)Lo #1 design factors in manufacturing processes (sept  2015)
Lo #1 design factors in manufacturing processes (sept 2015)
 
Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1
 
Lo 2 a key terminologies
Lo 2 a   key terminologiesLo 2 a   key terminologies
Lo 2 a key terminologies
 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 

B/C Analysis for Public Sector Projects

  • 1. Benefit/Cost Analysis LO4a EGN 3203 Engineering Economics LO3 – a
  • 2. LEARNING OUTCOMES 9-2 1. Explain difference in public vs. private sector projects 2. Calculate B/C ratio for single project 3. Select better of two alternatives using B/C method
  • 3. Introduction • Evaluation methods of previous LO are usually applied to alternatives in the private sector. • This LO introduces economic consideration for the public sector. • In the case of public projects, the owners and users (beneficiaries) are the citizens and residents of a government unit—city, county, state, province or nation. • Government units provide the mechanisms to raise capital and operating funds. • This chapter also introduces service sector projects and discusses how their economic evaluation is different from that for other projects 9-3
  • 4. • A public sector project is a product, service, or system used, financed, and owned by the citizens of any government level. The primary purpose is to provide service to the citizenry for the public good at no profit. Areas such as public health, criminal justice, safety, transportation, welfare, and utilities are all publically owned and require economic evaluation. Some public sector examples: • Hospitals and clinics • Parks and recreation • Utilities: water, electricity, gas, sewer, sanitation • Schools: primary, secondary, community • colleges, universities 9-4 Introduction
  • 5. 9-5 Life Longer (30 – 50+ years) Shorter (2 – 25 years) Annual CF No profit Profit-driven Funding Taxes, fees, bonds, etc. Stocks, bonds, loans, etc. Interest rate Lower Higher Selection criteria Multiple criteria Primarily ROR Environment of evaluation Politically inclined Economic Characteristic Public Private Size of Investment Large Small, medium, large
  • 6. 9-6 Contractors does not share project risk  Fixed price - lump-sum payment  Cost reimbursable - Cost plus, as negotiated Contractor shares in project risk  Public-private partnerships (PPP), such as:  Design-build projects - Contractor responsible from design stage to operations stage  Design-build-operate-maintain-finance (DBOMF) projects - Turnkey project with contractor managing financing (manage cash flow); government obtains funding for project
  • 7. • To perform a benefit/cost economic analysis of public alternatives, the costs (initial and annual), the benefits, and the dis-benefits, if considered, must be estimated as accurately as possible in monetary units. • Costs—estimated expenditures to the government entity for construction, operation, and maintenance of the project, less any expected salvage value. • Benefits—advantages to be experienced by the owners, the public. • Dis-benefits—expected undesirable or negative consequences to the owners if the alternative is implemented. Dis-benefits may be indirect economic disadvantages of the alternative. 9-7 Benefit/Cost Analysis
  • 8. Benefit/Cost Analysis • The benefit/cost ratio is relied upon as a fundamental analysis method for public sector projects. • All cost and benefit estimates must be converted to a common equivalent monetary unit (PW, AW, or FW) at the discount rate (interest rate). The B/C ratio is then calculated using one of these relations: • Present worth and annual worth equivalencies are preferred to future worth values. • The sign convention for B/C analysis is positive signs; costs are preceded by a + sign. • Salvage values and additional revenues to the government, when they are estimated, are subtracted from costs in the denominator. • Dis-benefits are considered in different ways depending upon the model used. 9-8
  • 9. • The conventional B/C ratio, probably the most widely used, • Dis-benefits are subtracted from benefits, not added to costs. 9-9 Benefit/Cost Analysis • The modified B/C ratio includes all the estimates associated with the project such as maintenance and operation. (M&O) costs are placed in the numerator and treated as dis-benefits. The denominator includes only the initial investment. • all amounts are expressed in PW, AW, or FW terms, the modified B/C ratio is calculated as Two types of analyses:
  • 10. • It is possible to develop a direct formula connection between the B/C of a public sector and B/C of a private sector project that is a revenue alternative ; both revenues and costs are estimated. • the PW for project cash flows is PW of project = PW of revenue - PW of costs • This relation can be slightly rewritten to form the profitability index (PI), which can be used to evaluate revenue projects in the public or private sector. 9-10 Benefit/Cost Analysis
  • 11. B/C Relations : summary cost Benefit (B) -- Advantages to the public Disbenefit (D) -- Disadvantages to the public Cost (C) -- Expenditures by the government Note: Savings to government are subtracted from costs Conventional B/C ratio = (B–D) / C Modified B/C ratio = [(B–D) – C] / Initial Investment Profitability Index = NCF / Initial Investment Note 1 : All terms must be expressed in same units, i.e., PW, AW, or FW Note 2 : Do not use minus sign ahead of costs 9-11 Must identify each cash flow as either benefit, dis-benefit, or cost
  • 12. 9-12 Benefit/cost analysis If B/C ≥ 1.0, project is economically justified at discount rate applied If B/C < 1.0, project is not economically acceptable Profitability index analysis of revenue projects If PI ≥ 1.0, project is economically justified at discount rate applied If PI < 1.0, project is not economically acceptable
  • 13. 9-13 Conventional B/C ratio = B - D C Modified B/C ratio = B – D – M&O C If B/C ≥ 1.0, accept project; otherwise, reject PI = PW of initial investment If PI ≥ 1.0, accept project; otherwise, reject PW of NCFt Denominator is initial investment
  • 14. A flood control project will have a first cost of $1.4 million with an annual maintenance cost of $40,000 and a 10 year life. Reduced flood damage is expected to amount to $175,000 per year. Lost income to farmers is estimated to be $25,000 per year.At an interest rate of 6% per year, should the project be undertaken? Solution: Express all values inAW terms and find B/C ratio B = $175,000 D = $25,000 C = 1,400,000(A/P,10,%6)+40,000$ = 230,218$ B/C= (175,000 – 25,000) / 230,218 = 0.65 < 1.0 Do not build project 9-14 Example: B/C Analysis – Single Project Annual – use AW
  • 15. 9-15 Example: B/C Analysis – Single Project Example Conventional & Modified B/C B D A P
  • 16. 9-16 Example: B/C Analysis – Single Project Conventional B/C Modified B/C Example Conventional & Modified B/C
  • 17. The cost of grading and spreading gravel on a short rural road is expected to be $300,000. The road will have to be maintained at a cost of $25,000 per year. Even though the new road is not very smooth, it allows access to an area that previously could only be reached with off-road vehicles. The improved accessibility has led to a 150% increase in the property values along the road. If the previous market value of a property was $900,000, calculate the B/C ratio using an interest rate of 6% per year and a 20-year study period. Solution 9-17 Example: B/C Analysis – Single Project Example Conventional B/C
  • 18. The cost of grading and spreading gravel on a short rural road is expected to be $300,000. The road will have to be maintained at a cost of $25,000 per year. Even though the new road is not very smooth, it allows access to an area that previously could only be reached with off-road vehicles. The improved accessibility has led to a 150% increase in the property values along the road. If the previous market value of a property was $900,000, calculate the B/C ratio using an interest rate of 6% per year and a 20-year study period. Solution B = 900,000(1.5) – 900,000 = $450,000 C = 300,000 + 25,000(P/A,6%,20) = 300,000 + 25,000(11.4699) = $586,748 B/C = 450,000/586,748 = 0.77 9-18 Example: B/C Analysis – Single Project Example Conventional B/C
  • 19. 9-19 Example: B/C Analysis – Single Project Example profitability index (PI),
  • 20. 9-20 Example: B/C Analysis – Single Project Example profitability index (PI),
  • 21. Defender, Challenger and Do NothingAlternatives When selecting from two or more ME alternatives, there is a:  Defender – in-place system or currently selected alternative  Challenger – Alternative challenging the defender  Do-nothing option – Status quo system General approach for incremental B/C analysis of two ME alternatives:  Lower total cost alternative is first compared to Do-nothing (DN)  If B/C for the lower cost alternative is < 1.0, the DN option is compared to ∆B/C of the higher-cost alternative  If both alternatives lose out to DN option, DN prevails, unless overriding needs requires selection of one of the alternatives 9-21
  • 22. 9-22 Procedure similar to ROR analysis for multiple alternatives (1) Determine equivalent total cost for each alternative (2) Order alternatives by increasing total cost (3) Identify B and D for each alternative, if given, or go to step 5 (4) Calculate B/C for each alternative and eliminate all with B/C < 1.0 (5) Determine incremental costs and benefits for first two alternatives (6) Calculate ∆B/C; if >1.0, higher cost alternative becomes defender (7) Repeat steps 5 and 6 until only one alternative remains Select higher cost alternative
  • 23. B/C Analysis of Independent Projects  Independent projects comparison does not require incremental analysis  Compare each alternative’s overall B/C with DN option + No budget limit: Accept all alternatives with B/C ≥ 1.0 + Budget limit specified: capital budgeting problem; selection follows different procedure (discussed in chapter 12) 9-23© 2012 by McGraw-Hill All Rights Reserved
  • 24. Example: Incremental B/C Analysis Compare two alternatives using i = 10% and B/C ratio Eliminate X Eliminate DNY vs. DN: (150,000 – 45,000) / 98,428 = 1.07 9-24© 2012 by McGraw-Hill All Rights Reserved Solution: First, calculate equivalent total cost AW of costsX = 320,000(A/P,10%,10) + 45,000 = $97,080 AW of costsY = 540,000(A/P,10%,20) + 35,000 = $98,428 Order of analysis is X, then Y X vs. DN: (B-D)/C = (110,000 – 20,000) / 97,080 = 0.93 Alternative X Y First cost, $ 320,000 540,000 M&O costs, $/year 45,000 35,000 Benefits, $/year 110,000 150,000 Disbenefits, $/year 20,000 45,000 Life, years 10 20
  • 28. Solution East vs. DN: (B-D)East = 990,000 – 120,000 = $870,000 per year CEast = 11,000,000(0.06) + 100,000 = $760,000 per year (B-D)/C = 870,000/760,000 = 1.14 Eliminate DN West vs. East: Δ(B-D) = (2,400,000 – 100,000) – (990,000 – 120,000) = $1,430,000 ΔC = [27,000,000(0.06) + 90,000] – 760,000 = $950,000 ΔB/C = 1,430,000/950,000 = 1.51 Select West location 9.31 The estimates shown are for a bridge under consideration for a river crossing in Wheeling, West Virginia. Use the B/C ratio method at an interest rate of 6% per year to determine which bridge, if either, should be built. 9-28
  • 29. Example: ∆B/C Analysis; Selection Required Must select one of two alternatives using i = 10% and ∆B/C ratio Alternative X Y Solution: Must select X or Y; DN not an option, compare Y to X AW of costsX = $97,080 AW of costsY = $98,428 Incremental values: ∆B = 150,000 – 110,000 = $40,000 Y vs. X: (∆B - ∆D) / ∆C = (40,000 – 25,000) / 1,348 = 11.1 Eliminate X 9-29© 2012 by McGraw-Hill All Rights Reserved ∆D = 45,000 – 20,000 = $25,000 ∆C = 98,428 – 97,080 = $1,348 First cost, $ 320,000 540,000 M&O costs, $/year 45,000 35,000 Benefits, $/year 110,000 150,000 Disbenefits, $/year 20,000 45,000 Life, years 10 20
  • 30. Ethical Considerations Engineers are routinely involved in two areas where ethics may be compromised: Public policy making – Development of strategy, e.g., water system management (supply/demand strategy; ground vs. surface sources) Public planning - Development of projects, e.g., water operations (distribution, rates, sales to outlying areas) Engineers must maintain integrity and impartiality and always adhere to Code of Ethics 9-30