SlideShare a Scribd company logo
1 of 56
Download to read offline
TUNNEL VENTILATION AND
FIRE SAFETY

A case study of Pir Panjal Tunnel
T-80 of USBRL Project

-Hitesh Khanna
Ircon International Limited
PIR PANJAL TUNNEL- AN OVERVIEW
• IRCON INTERNATIONAL LIMITED is the principle
execution agency for DHARAM-QAZIGUNDBARAMULLAH section of USBRL project of
Northern Railway.
• Pir Panjal Tunnel, between Qazigund and
Banihal, is the landmark tunnel of the project,
connecting Kashmir Valley to Jammu Region.
• At 11.215 Kms., it is the LONGEST transportation
tunnel in India.
2
T 80 ON USBRL PROJECT

3
T80 SECTION AND PLAN

4
• Max Over burden 1100
mts.
• B. G. Rly. S/L Track
• 3 mts. Road
• 48.5 m2 X-Sec Area
• Water Proof
5
UIC Codex 779-9 R
Safety In Railway
Tunnels
• To the Extent That
Safety is regulated at
National level, it shall
be defined by National
Authorities.
• General Principles:
1. Prevent Accidents
2. Mitigate the Impact of
accidents
3. Facilitate ESCAPE
4. Facilitate Rescue
6
UIC Codex 779-9 (contd…)
• Tunnels:
– Minimal Avalanche, Landslides, L-Xing accidents.
– Accidents/Train Km is lower, but critical (Fire)

• For General Public, psychologically, Risk
perception is higher for Tunnel Accidents
– (LOW FREQUENCY- HIGH IMPACT compared to Level Xing
accidents- HIGH FREQUENCY- LOW IMPACT)

• As FIRE in Passenger Trains is a Major and
Specific Risk, the Main Focus is on this type
of Accidents.
7
UIC Codex 779-9 (contd…)
• Applies to Electrified / Non-electrified Tunnels,
and High Rock Cover
• For New Planned Tunnels, longer than 1 Km. but
upto 15 Kms.
– General Strategy is to get the train out of Tunnel (with
in 15 min. of fire).
– Disable Emergency Brakes (operating measures)

• If despite measures, train on Fire comes to stand
still inside the tunnel:
– Facilitate self ESCAPE to SAFE PLACE
– Distance between two safe places not more than 1 Km
– Cross passage at not more than 500 mts.
8
Ventilation Requirement
• Normal Operation:
(Depends on Traction Mode and local conditions):
– Maintain Sustainable Air Quality in side the Tunnel
• Pollutant Levels
• Oxygen Levels
• Temperature

• Emergency Rescue Management:
(for both Diesel and Electric Traction- Fire Load
may vary)
– Fire and Smoke Management to Assist Emergency
Evacuation Strategy
– Fire Effect Mitigation
9
VENTILATION SYSTEMS

• Longitudinal
– Air Set in Motion along Tunnel Axis
•
•
•
•

Portal to Portal, Same speed though out the Tunnel Length
No Division into Aerodynamic Segments
Low Cost, Does not need Transverse air Egress Points
Time to Purge Foul Air depends on Air Flow Velocity, Tunnel
10
Length
VENTILATION SYSTEMS (contd.)

• Transverse
– Two Independent Ducts (Fresh Air Inflow and Exhaust
air exit)
• Can create Aero dynamic Sections (In case of Fire)
• May Need Transverse Exit Routes (Low Overburden
Ventilation Shafts, Stations in Metros
• Costlier to Install, and operate (More Aerodynamic Losses)

11
VENTILATION SYSTEMS (contd.)

• Semi-Transverse
– Combination of Longitudinal and Transversal System:
• Separation of Fresh and Exhaust air
• Reversible• Fire Case Fresh Air through Portal, Exhaust through
Ventilation Stack, Permitting Aerodynamic Separation
• Normally, Fresh air Through Ventilation Stacks
• Larger Tunnel X-Section

12
VENTILATION SYSTEMS (contd.)
• Considering the merits and demerits of each
ventilation system and since there is no
station and stop in pir-panjal tunnel;
– longitudinal ventilation system has been
considered fit to apply in this tunnel
– worldwide also, only longitudinal ventilation is
applied to rail/road tunnel or underground
projects.

• Only in underground stations and stops,
transversal and semi transversal might be
applied.
13
Normal Case: Calculation Of Fresh Air Flow
• Para 3.6.2
–
–
–
–

Fresh Air Demand due to Gaseous Emissions
Fresh Air Demand due to Particulate Emissions
Fresh Air Demand oxygen Depletion (Diesel Engine)
Normalization Of Temperature (Below 40 deg. C)
after passage of 5000T train Uphill

• Ventilation Design (Normal Case- Para 4.0)
– Time to restore Safe Conditions Inside the Tunnel
– Waiting Time for Next Train to enter (after exit of
Uphill Loaded Train)
14
LOCO MOTIVE EXHAUST DATA

emission

g/kWh
CO
NOX
Particle

Standards

ORE
3
12
0.5

UN
6.7
12.7
0.8

measured emission data

UIC
3
10
0.25

US EPA
(line haul
locomotive, WDM2/ALCO WDM3A/AL WDM4/ALCO
Tier 0)
2530HP CO 3073HP 4000HP
6.71
0.52
0.72
0.56
10.73
13.56
12.42
7.62
0.30
???
???
0.39
15
STANDARD THRESHOLD POLLUTION LEVEL
(1)
50

75

400

NO

25

37.5

35

NO2

2)
3)

(3)

CO

1)

(2)

5

5

5

American Conference of Governmental and Industrial Hygienists
and Continuous Limit for working environment. (Ref. DPR)
Long Term Sustainable Threshold Values for Industrial Working
Environment (8 hours working)
Non-Continuous Exposure, with intermittent Air Exchange
Limits up-to 15 minutes exposure
16
ADOPTED THRESHOLD ENVIRONMENT
PARAMETERS
Element

8 Hours
Exposure

15 Min. Exposure

CO

50 ppm

200 ppm

Design
Limit
Pir Panjal
50 ppm

NO

25 ppm

35 ppm

90% of NOx

NO2

4 ppm

5 ppm

10% of NOx

Sum: NOx

29 ppm

40 ppm

25 ppm

CO2

5000 ppm

10000 ppm

5000ppm

SO2

5 ppm

5 ppm

5ppm

Not defined

< 0,012m^-1
(extinction
coefficient)

50°C for a train passing, max.65°C

-

Particulates
Not defined
(PM)
Temperature

40°C

17
Ventilation Requirement with Electric
Traction
►

No ventilation required for regular operation

►

Fire load for electric locomotives < Diesel powered ones

►

According to design procedure and UIC
→ fire load depends on type of train
→ typical criteria *:
* According to Deutsche Bahn AG
● Diesel → Peak 20 MW
● Electric → Peak 12 MW
● Passenger train → Peak 25 MW
● Freight train → Peak 8-52 MW (depending on load)

►

Chosen design criteria → 40 MW

►

Electric traction does not impact ventilation design

Page 18
Thermo Dynamic Data
ITEM

REFERENCE

Geothermal Heat Input
Para 3.2.2
Depending on Parent Rock
Temperature and Temp. Gradient
to Tunnel Rock Surface
Temperature, Pressure and Density
Gradient of Air Inside the Tunnel

Para 3.2.2.1

Portal Meteorological Data

Para 3.2.3

Portal Temperature, Wind Pressure,
Para 3.2.3.1, 3.2.3.2, 3.2.3.3, 3.2.3.4
Natural Buoyancy Pressure and Pressure
Differential between the Portals
19
Aero Dynamic Data
ITEM
Tunnel Characteristics:
Portal Losses, Tunnel Wall Friction,
Wind Velocity at Portals
Air Pressure and Temperature
Air Density

REFERENCE
Para 3.4

Critical Velocity
Critical Froude Number
Temperature Near The Fire Scene

Critical Velocity to prevent Back Layering
Constant Air flow to Blow the Smoke
away from Passengers Exiting in Other
Direction,
Drive HC Vapours Away from Fire Source
to avoid Flash Over

Jet Fan Installation Factor &
Piston Effect Of The Train and
Train Data

Para 3.5 & 3.6
20
THERMODYNAMICS
...buoyancy…
a thermodynamic effect
warm mass of rock

temperature rise leads to lower density of air

heat of train

…. and to longitudinal velocity - chimney effect

21
...wind pressure and
meteorological effects...
wind pressure effect depends on:

Tunnel
- meteorological situation

wind pressure

- tunnel data

22
Ventilation Design Approach
Natural velocity achieved inside tunnel :

23
AERODYNAMICS
...piston effect …
depends on:
for the Pir Panjal tunnel
the piston effect leads to:

Tunnel

- speed of train and aerodynamic drag
• longitudinal velocity of about 5.34 m/s

• fresh air of about 241 m3/s

- ratio between tunnel and train cross section area
- tunnel resistance: length of tunnel, wall friction and others

24
Boundary Condns. (Geometry)

Description

Details

Tunnel length

11.215 m

Length from Banihal Station to South

1450 m

portal
Length

from

North

Portal

to

4774 m

Qazigund Section
Finished cross section
Average elevation above sea level

48.50 m2
1734.75 m

25
Boundary Conditions (Geometric Data)

26
longitudinal velocity
5,00
4,00
3,00
2,00
1,00

[m/s]

longitudinal velocity

TRAIN SIMULATION TO ASSESS
VENTILATION NEED

0,00
-1,00

0

60

120

180

240

300

-2,00
-3,00
-4,00
-5,00
time [min]

For normal operatrion
No artificial ventilation is needed

Train with 40 km/h needs about 17 min to pass tunnel
27
Ventilation For Fire and Smoke
Management
What happens if a tunnel fire occurs ?

the tunnel roof fills with smoke
even in the upstream direction against the
longitudinal velocity!!
28
Ventilation For Fire and Smoke
Management
BACKLAYERING

"

• Avoid
Backlayring
– Critical Velocity
of Airflow to be
Maintained

• Smoke To Be
Directed, to
Permit Escape in
other direction
29
Stratification Of Smoke
• Smoke Rises to Top
– Permits Escape
Underneath in cooler
air
– Flashover Control

• Typically Stratification
lasts for 500-800mts
– 30-40 MW fire
– Tunnel Geomtry, Slope
– Air Flow Conditions
30
VENTILATION DESIGN INPUTS SMOKE
CONTROL
• Input Parameters
– What is the maximum size of any fire, which may
reasonably be expected to occur, given the use of
tunnel
• (Design Fire Curve- Fire/Smoke Vs. Time)

– What Corresponding Ventilation is required to
prevent smoke Backflow
• Critical Velocity to be attained
31
Emergency Ventilation Design Fire
• Select Design Fire Load:
Investigations were
performed by Deutsche
Bahn AG
– Diesel Loco → Peak 20
MW
– Electric Loco → Peak 12
MW
– Passenger train → Peak
25 MW
– Freight train → Peak 852 MW (depending on
load)

• Design Fire Adopted 40
MW (Two Dsl. Loco in
Tandem)
32
Emergency Ventilation Design Approach:
TEMPERATURE /
SMOKE PROGRESSION
ALONG THE LENGTH
HEIGHT
Computation fluid
dynamics (camatt)
– Design Fire
– Tunnel Geometry
– Fan design &
Configuration
– Thermo Dynamics
– Fluid Dynamics

33
Emergency Ventilation Design Approach:
TEMPERATURE / SMOKE
PROGRESSION ALONG THE
LENGTH HEIGHT BY NEAR FIRE
CONDITIONS BY 3DCFD
Objective:– To clarify condition d/s of
fire
– Influence of longitudinal
flow velocity on the
tenability d/s from fire
– Design Fire load 25 MW
– Smoke plum should remain
2.5m above rail level during
self evacuation time
– Use of Deutsche Bahn Fire
curve for smoke release rate
and critical velocity
34
FINAL VENTILATION DESIGN

Jet Fan (Main Tunnel)
Jet Fan (Access Tunnel)

35
Ventilation Actuation:





Visibility detection
Airflow measurement
Automatic operation
Basic ventilation
Visibility data
Airflow direction
Wind speed
 Fire Ventilation
Fire Alarm
Visibility data
Airflow direction
Wind Speed

36
Ventilation System -Installations
Sr.No.

Location

Fixing height

Spacing

25

MVS

3.5 Mtrs.

150Mtrs.

3
21
21

Adit
Each next MN
Each next MN

4.0 Mtrs.
4.0 Mtrs.
4.0 Mtrs.

150 Mtrs
500 Mtrs.
500 Mtrs.

25
3

Each Jet fan
Each Jet fan

150 Mtrs
150 Mtrs

a) Main tunnel

75

Each Jet fan (3)

150 Mtrs

b) Adit Tunnel

9

Each Jet fan (3)

150 Mtrs

Vibration Sensor
a) Main tunnel

25

Each Jet fan

150 Mtrs

b) Adit Tunnel

1

Description of Items

Qty.

3

Each Jet fan

150 Mtrs

2

Adit tunnel

Jet Fan
a) Main tunnel ( Five Groups)

b) Adit Tunnel
2
Air Velocity Measuremnt.
3
CO/Dust Particle
4

Proximity Sensor
a) Main tunnel
b) Adit Tunnel
5
PT 100 Unit (Temp Sensor)

6

7

ADIT Axail Fan

3.0 Mtrs.

37
4.0 Mtrs.
E&M System
Consists of the following
433/250V – 50 Hz Power Supply
Emergency Power Supply
Earthing & Potential Equalisation
System
Tunnel Lighting
Tunnel Fittings
Fire Detection System
Building Power & Lighting Installations
Room Ventilation & Air Conditioning
38
System Compliance

World
Standard

Pir Panjal

UIC

Redundant Power Supply





~

I-67, I-65

CCTV System







I-68

Emergency and Service Phone
System







I-42

Tunnel Radio System







I-66, I-2

Public Address System (Speaker
System)





~

Fire Detection System







Fire Fighting System (Water Line,
Extinguishers)







I-24, I-64

Ventilation System







I-25

Emergency Lighting







I-41

Control Centre





~

Escape Distance to be not more than
1000 mts.



~



Comments

I-43

Page 39
T-80 TUNNEL CONTROL MONITORING
CENTRE

40
MULTI SCRN TUNNEL VIDEO MNTRING
- WITH MOTION SENSOR TRIGGERS

41
CCTV MONITORING
42
VENTILATION FUNCTION

43
ESS FUNCTIONING SCRN

44
LIGHT & EROS MONITORING

45
EVENT LOG
46
VENTILATION CONTROL STRATEGY
REQUIREMENTS TO THE STAFF (NORMAL
OPERATION)
Train staff
►Report about type and direction of train
entering the tunnel
►Break down: Report the location of the break
down
Control center staff
►Know about train type and direction
►Monitor emission levels in the tunnel
►Monitor appropriate operation of ventilation
►Instruct the train driver to shut down engines (if
necessary)

47
Ventilation Control Strategy
Requirements to the staff (emergency operation)
Train staff
►Guide passengers in the right direction
►Communicate and Local Guidance for Passenger
Rescue
Control center staff
►Select and confirm the appropriate mode of
operation
►Monitor the appropriate mode of ventilation
►Support rescue operation (e.g. coordinate the
rescue train)
48
• Detailed Design
Consultants
– M/s GeoconsultRITES JV
– Overall Tunnel Design
and Top level
Supervision,
observations based
On-site design with
NATM approach
– Ventilation, Rescue,
E&M Design
49
• HBI Haerter
– Ventilation
Design
Proof
Check

50
51
52
53
MAIN TUNNEL
CROSS-PASSAGES
ESCAPE TUNNEL

RAILWAY TUNNEL (T-74R) LAYOUT
(AS PER UIC 779)
54
55
56

More Related Content

What's hot

Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenanceMohd Bakhsh
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxBalpreetSingh47890
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)Sukhdarshan Singh
 
Kolkata metro rail via-duct project
Kolkata metro rail via-duct projectKolkata metro rail via-duct project
Kolkata metro rail via-duct projectrajnish singh
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelAbhishek Kansara
 
SUBMERGED FLOATING TUNNELS
SUBMERGED FLOATING TUNNELSSUBMERGED FLOATING TUNNELS
SUBMERGED FLOATING TUNNELSsathish sak
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringLatif Hyder Wadho
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackKHUSHBU SHAH
 
Basics of Metro Railway Signalling system
Basics of Metro Railway Signalling systemBasics of Metro Railway Signalling system
Basics of Metro Railway Signalling systemBhaskar Kumar Dan
 
Sarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training reportSarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training reportGAURAV KUMAR CHAUBEY
 
Summer Training in DMRC
Summer Training in DMRCSummer Training in DMRC
Summer Training in DMRCAsim Ghatak
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling pptSuman Paul
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingssrinivas2036
 

What's hot (20)

Metro presentation
Metro presentationMetro presentation
Metro presentation
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
 
ELEVATOR SYSTEM IN DELHI METRO STATIONS
ELEVATOR SYSTEM IN DELHI METRO STATIONSELEVATOR SYSTEM IN DELHI METRO STATIONS
ELEVATOR SYSTEM IN DELHI METRO STATIONS
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Railway ppt
Railway pptRailway ppt
Railway ppt
 
Kolkata metro rail via-duct project
Kolkata metro rail via-duct projectKolkata metro rail via-duct project
Kolkata metro rail via-duct project
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
 
Tunnel Boring Machines
Tunnel Boring Machines  Tunnel Boring Machines
Tunnel Boring Machines
 
SUBMERGED FLOATING TUNNELS
SUBMERGED FLOATING TUNNELSSUBMERGED FLOATING TUNNELS
SUBMERGED FLOATING TUNNELS
 
Unit 1
Unit 1Unit 1
Unit 1
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway Engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Basics of Metro Railway Signalling system
Basics of Metro Railway Signalling systemBasics of Metro Railway Signalling system
Basics of Metro Railway Signalling system
 
Sarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training reportSarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training report
 
Summer Training in DMRC
Summer Training in DMRCSummer Training in DMRC
Summer Training in DMRC
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
vikanksh
vikankshvikanksh
vikanksh
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 

Viewers also liked

Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
510 tunneling safety 2016
510 tunneling safety 2016510 tunneling safety 2016
510 tunneling safety 2016John Newquist
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpointishict
 
Tunnel Safety
Tunnel SafetyTunnel Safety
Tunnel Safetyroypun
 
Sustainability and Safety in Tunnels
Sustainability and Safety in TunnelsSustainability and Safety in Tunnels
Sustainability and Safety in TunnelsFathi Tarada
 
1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015John Newquist
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machineNaquiakhter
 
St.kitts tunnel - project references
St.kitts tunnel - project referencesSt.kitts tunnel - project references
St.kitts tunnel - project referencesAgata Woźniak
 
Report on study of socail impact due to tunnel construction at sundarijal ou...
Report on study of socail impact due to tunnel construction at sundarijal  ou...Report on study of socail impact due to tunnel construction at sundarijal  ou...
Report on study of socail impact due to tunnel construction at sundarijal ou...shekharkc
 
SMART tunnel report
SMART tunnel reportSMART tunnel report
SMART tunnel reportYap Xin
 
Fire Protection and Safety in Tunnels
Fire Protection and Safety in TunnelsFire Protection and Safety in Tunnels
Fire Protection and Safety in TunnelsArena International
 
Tunnel Safety Technologies
Tunnel Safety Technologies Tunnel Safety Technologies
Tunnel Safety Technologies Luigi Carrarini
 

Viewers also liked (20)

Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
High Tunnel Ventilation, 2015
High Tunnel Ventilation, 2015High Tunnel Ventilation, 2015
High Tunnel Ventilation, 2015
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
510 tunneling safety 2016
510 tunneling safety 2016510 tunneling safety 2016
510 tunneling safety 2016
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpoint
 
Tunnel Safety
Tunnel SafetyTunnel Safety
Tunnel Safety
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Tunnel Project
Tunnel ProjectTunnel Project
Tunnel Project
 
Sustainability and Safety in Tunnels
Sustainability and Safety in TunnelsSustainability and Safety in Tunnels
Sustainability and Safety in Tunnels
 
1926 tunneling safety 2015
1926 tunneling safety 20151926 tunneling safety 2015
1926 tunneling safety 2015
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
floating tunnels
floating tunnelsfloating tunnels
floating tunnels
 
types of bridges
types of bridgestypes of bridges
types of bridges
 
St.kitts tunnel - project references
St.kitts tunnel - project referencesSt.kitts tunnel - project references
St.kitts tunnel - project references
 
Report on study of socail impact due to tunnel construction at sundarijal ou...
Report on study of socail impact due to tunnel construction at sundarijal  ou...Report on study of socail impact due to tunnel construction at sundarijal  ou...
Report on study of socail impact due to tunnel construction at sundarijal ou...
 
SMART tunnel report
SMART tunnel reportSMART tunnel report
SMART tunnel report
 
Fire Protection and Safety in Tunnels
Fire Protection and Safety in TunnelsFire Protection and Safety in Tunnels
Fire Protection and Safety in Tunnels
 
Tunnel Safety Technologies
Tunnel Safety Technologies Tunnel Safety Technologies
Tunnel Safety Technologies
 

Similar to Tunnel Ventilation and Fire Safety: A Case Study of Pir Panjal Tunnel T-80

Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel designhaziq42
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel designkhan510459
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentationLee Chun Yee
 
final presentation edit.pptx
final presentation edit.pptxfinal presentation edit.pptx
final presentation edit.pptxssuser0ee912
 
1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal Handling1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal HandlingNani Thirupathi
 
Gas turbine lecture by kpm
Gas turbine lecture by kpmGas turbine lecture by kpm
Gas turbine lecture by kpmKrunal Mudafale
 
ashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdf
ashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdfashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdf
ashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdfMarcGajudo
 
Post-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsPost-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsHamid Abroshan
 
coal mining training report
coal mining training report coal mining training report
coal mining training report VIKRAMSINGH1231
 
UPDATED-GTM Presentation v3 email
UPDATED-GTM Presentation v3 emailUPDATED-GTM Presentation v3 email
UPDATED-GTM Presentation v3 emailKen Kelley
 
CPD Presentation: Car Park Ventilation
CPD Presentation: Car Park VentilationCPD Presentation: Car Park Ventilation
CPD Presentation: Car Park VentilationColt UK
 
Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2ROSHAN SAH
 
Metro tunnel ventilaiton .pptx
Metro tunnel ventilaiton .pptxMetro tunnel ventilaiton .pptx
Metro tunnel ventilaiton .pptxssuser983518
 
Forced cooling of a supercritical steam turbine after shut down of power plant
Forced cooling of a supercritical steam turbine after shut down of power plantForced cooling of a supercritical steam turbine after shut down of power plant
Forced cooling of a supercritical steam turbine after shut down of power plantSrikar Yadav
 
Compact Remote High Altitude Balloon Launcher
Compact Remote High Altitude Balloon Launcher�Compact Remote High Altitude Balloon Launcher�
Compact Remote High Altitude Balloon LauncherReetam Singh
 
Closed Loop Electric Arc
Closed Loop Electric ArcClosed Loop Electric Arc
Closed Loop Electric ArcMarcel van W
 

Similar to Tunnel Ventilation and Fire Safety: A Case Study of Pir Panjal Tunnel T-80 (20)

Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel design
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel design
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentation
 
Aircooling underground coal mine
 Aircooling underground coal mine Aircooling underground coal mine
Aircooling underground coal mine
 
final presentation edit.pptx
final presentation edit.pptxfinal presentation edit.pptx
final presentation edit.pptx
 
1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal Handling1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal Handling
 
Gas turbine lecture by kpm
Gas turbine lecture by kpmGas turbine lecture by kpm
Gas turbine lecture by kpm
 
ashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdf
ashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdfashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdf
ashraeqatar_16.04.09_s_p_introduction_to_car_park_jetfan_ventilation_1.pdf
 
Post-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsPost-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plants
 
Tunnels firefighting
Tunnels firefightingTunnels firefighting
Tunnels firefighting
 
coal mining training report
coal mining training report coal mining training report
coal mining training report
 
UPDATED-GTM Presentation v3 email
UPDATED-GTM Presentation v3 emailUPDATED-GTM Presentation v3 email
UPDATED-GTM Presentation v3 email
 
CPD Presentation: Car Park Ventilation
CPD Presentation: Car Park VentilationCPD Presentation: Car Park Ventilation
CPD Presentation: Car Park Ventilation
 
BMRCL.ppt
 BMRCL.ppt BMRCL.ppt
BMRCL.ppt
 
Design HVAC System for Hospital
Design HVAC System for Hospital Design HVAC System for Hospital
Design HVAC System for Hospital
 
Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2
 
Metro tunnel ventilaiton .pptx
Metro tunnel ventilaiton .pptxMetro tunnel ventilaiton .pptx
Metro tunnel ventilaiton .pptx
 
Forced cooling of a supercritical steam turbine after shut down of power plant
Forced cooling of a supercritical steam turbine after shut down of power plantForced cooling of a supercritical steam turbine after shut down of power plant
Forced cooling of a supercritical steam turbine after shut down of power plant
 
Compact Remote High Altitude Balloon Launcher
Compact Remote High Altitude Balloon Launcher�Compact Remote High Altitude Balloon Launcher�
Compact Remote High Altitude Balloon Launcher
 
Closed Loop Electric Arc
Closed Loop Electric ArcClosed Loop Electric Arc
Closed Loop Electric Arc
 

Recently uploaded

Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 

Recently uploaded (20)

Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 

Tunnel Ventilation and Fire Safety: A Case Study of Pir Panjal Tunnel T-80

  • 1. TUNNEL VENTILATION AND FIRE SAFETY A case study of Pir Panjal Tunnel T-80 of USBRL Project -Hitesh Khanna Ircon International Limited
  • 2. PIR PANJAL TUNNEL- AN OVERVIEW • IRCON INTERNATIONAL LIMITED is the principle execution agency for DHARAM-QAZIGUNDBARAMULLAH section of USBRL project of Northern Railway. • Pir Panjal Tunnel, between Qazigund and Banihal, is the landmark tunnel of the project, connecting Kashmir Valley to Jammu Region. • At 11.215 Kms., it is the LONGEST transportation tunnel in India. 2
  • 3. T 80 ON USBRL PROJECT 3
  • 5. • Max Over burden 1100 mts. • B. G. Rly. S/L Track • 3 mts. Road • 48.5 m2 X-Sec Area • Water Proof 5
  • 6. UIC Codex 779-9 R Safety In Railway Tunnels • To the Extent That Safety is regulated at National level, it shall be defined by National Authorities. • General Principles: 1. Prevent Accidents 2. Mitigate the Impact of accidents 3. Facilitate ESCAPE 4. Facilitate Rescue 6
  • 7. UIC Codex 779-9 (contd…) • Tunnels: – Minimal Avalanche, Landslides, L-Xing accidents. – Accidents/Train Km is lower, but critical (Fire) • For General Public, psychologically, Risk perception is higher for Tunnel Accidents – (LOW FREQUENCY- HIGH IMPACT compared to Level Xing accidents- HIGH FREQUENCY- LOW IMPACT) • As FIRE in Passenger Trains is a Major and Specific Risk, the Main Focus is on this type of Accidents. 7
  • 8. UIC Codex 779-9 (contd…) • Applies to Electrified / Non-electrified Tunnels, and High Rock Cover • For New Planned Tunnels, longer than 1 Km. but upto 15 Kms. – General Strategy is to get the train out of Tunnel (with in 15 min. of fire). – Disable Emergency Brakes (operating measures) • If despite measures, train on Fire comes to stand still inside the tunnel: – Facilitate self ESCAPE to SAFE PLACE – Distance between two safe places not more than 1 Km – Cross passage at not more than 500 mts. 8
  • 9. Ventilation Requirement • Normal Operation: (Depends on Traction Mode and local conditions): – Maintain Sustainable Air Quality in side the Tunnel • Pollutant Levels • Oxygen Levels • Temperature • Emergency Rescue Management: (for both Diesel and Electric Traction- Fire Load may vary) – Fire and Smoke Management to Assist Emergency Evacuation Strategy – Fire Effect Mitigation 9
  • 10. VENTILATION SYSTEMS • Longitudinal – Air Set in Motion along Tunnel Axis • • • • Portal to Portal, Same speed though out the Tunnel Length No Division into Aerodynamic Segments Low Cost, Does not need Transverse air Egress Points Time to Purge Foul Air depends on Air Flow Velocity, Tunnel 10 Length
  • 11. VENTILATION SYSTEMS (contd.) • Transverse – Two Independent Ducts (Fresh Air Inflow and Exhaust air exit) • Can create Aero dynamic Sections (In case of Fire) • May Need Transverse Exit Routes (Low Overburden Ventilation Shafts, Stations in Metros • Costlier to Install, and operate (More Aerodynamic Losses) 11
  • 12. VENTILATION SYSTEMS (contd.) • Semi-Transverse – Combination of Longitudinal and Transversal System: • Separation of Fresh and Exhaust air • Reversible• Fire Case Fresh Air through Portal, Exhaust through Ventilation Stack, Permitting Aerodynamic Separation • Normally, Fresh air Through Ventilation Stacks • Larger Tunnel X-Section 12
  • 13. VENTILATION SYSTEMS (contd.) • Considering the merits and demerits of each ventilation system and since there is no station and stop in pir-panjal tunnel; – longitudinal ventilation system has been considered fit to apply in this tunnel – worldwide also, only longitudinal ventilation is applied to rail/road tunnel or underground projects. • Only in underground stations and stops, transversal and semi transversal might be applied. 13
  • 14. Normal Case: Calculation Of Fresh Air Flow • Para 3.6.2 – – – – Fresh Air Demand due to Gaseous Emissions Fresh Air Demand due to Particulate Emissions Fresh Air Demand oxygen Depletion (Diesel Engine) Normalization Of Temperature (Below 40 deg. C) after passage of 5000T train Uphill • Ventilation Design (Normal Case- Para 4.0) – Time to restore Safe Conditions Inside the Tunnel – Waiting Time for Next Train to enter (after exit of Uphill Loaded Train) 14
  • 15. LOCO MOTIVE EXHAUST DATA emission g/kWh CO NOX Particle Standards ORE 3 12 0.5 UN 6.7 12.7 0.8 measured emission data UIC 3 10 0.25 US EPA (line haul locomotive, WDM2/ALCO WDM3A/AL WDM4/ALCO Tier 0) 2530HP CO 3073HP 4000HP 6.71 0.52 0.72 0.56 10.73 13.56 12.42 7.62 0.30 ??? ??? 0.39 15
  • 16. STANDARD THRESHOLD POLLUTION LEVEL (1) 50 75 400 NO 25 37.5 35 NO2 2) 3) (3) CO 1) (2) 5 5 5 American Conference of Governmental and Industrial Hygienists and Continuous Limit for working environment. (Ref. DPR) Long Term Sustainable Threshold Values for Industrial Working Environment (8 hours working) Non-Continuous Exposure, with intermittent Air Exchange Limits up-to 15 minutes exposure 16
  • 17. ADOPTED THRESHOLD ENVIRONMENT PARAMETERS Element 8 Hours Exposure 15 Min. Exposure CO 50 ppm 200 ppm Design Limit Pir Panjal 50 ppm NO 25 ppm 35 ppm 90% of NOx NO2 4 ppm 5 ppm 10% of NOx Sum: NOx 29 ppm 40 ppm 25 ppm CO2 5000 ppm 10000 ppm 5000ppm SO2 5 ppm 5 ppm 5ppm Not defined < 0,012m^-1 (extinction coefficient) 50°C for a train passing, max.65°C - Particulates Not defined (PM) Temperature 40°C 17
  • 18. Ventilation Requirement with Electric Traction ► No ventilation required for regular operation ► Fire load for electric locomotives < Diesel powered ones ► According to design procedure and UIC → fire load depends on type of train → typical criteria *: * According to Deutsche Bahn AG ● Diesel → Peak 20 MW ● Electric → Peak 12 MW ● Passenger train → Peak 25 MW ● Freight train → Peak 8-52 MW (depending on load) ► Chosen design criteria → 40 MW ► Electric traction does not impact ventilation design Page 18
  • 19. Thermo Dynamic Data ITEM REFERENCE Geothermal Heat Input Para 3.2.2 Depending on Parent Rock Temperature and Temp. Gradient to Tunnel Rock Surface Temperature, Pressure and Density Gradient of Air Inside the Tunnel Para 3.2.2.1 Portal Meteorological Data Para 3.2.3 Portal Temperature, Wind Pressure, Para 3.2.3.1, 3.2.3.2, 3.2.3.3, 3.2.3.4 Natural Buoyancy Pressure and Pressure Differential between the Portals 19
  • 20. Aero Dynamic Data ITEM Tunnel Characteristics: Portal Losses, Tunnel Wall Friction, Wind Velocity at Portals Air Pressure and Temperature Air Density REFERENCE Para 3.4 Critical Velocity Critical Froude Number Temperature Near The Fire Scene Critical Velocity to prevent Back Layering Constant Air flow to Blow the Smoke away from Passengers Exiting in Other Direction, Drive HC Vapours Away from Fire Source to avoid Flash Over Jet Fan Installation Factor & Piston Effect Of The Train and Train Data Para 3.5 & 3.6 20
  • 21. THERMODYNAMICS ...buoyancy… a thermodynamic effect warm mass of rock temperature rise leads to lower density of air heat of train …. and to longitudinal velocity - chimney effect 21
  • 22. ...wind pressure and meteorological effects... wind pressure effect depends on: Tunnel - meteorological situation wind pressure - tunnel data 22
  • 23. Ventilation Design Approach Natural velocity achieved inside tunnel : 23
  • 24. AERODYNAMICS ...piston effect … depends on: for the Pir Panjal tunnel the piston effect leads to: Tunnel - speed of train and aerodynamic drag • longitudinal velocity of about 5.34 m/s • fresh air of about 241 m3/s - ratio between tunnel and train cross section area - tunnel resistance: length of tunnel, wall friction and others 24
  • 25. Boundary Condns. (Geometry) Description Details Tunnel length 11.215 m Length from Banihal Station to South 1450 m portal Length from North Portal to 4774 m Qazigund Section Finished cross section Average elevation above sea level 48.50 m2 1734.75 m 25
  • 27. longitudinal velocity 5,00 4,00 3,00 2,00 1,00 [m/s] longitudinal velocity TRAIN SIMULATION TO ASSESS VENTILATION NEED 0,00 -1,00 0 60 120 180 240 300 -2,00 -3,00 -4,00 -5,00 time [min] For normal operatrion No artificial ventilation is needed Train with 40 km/h needs about 17 min to pass tunnel 27
  • 28. Ventilation For Fire and Smoke Management What happens if a tunnel fire occurs ? the tunnel roof fills with smoke even in the upstream direction against the longitudinal velocity!! 28
  • 29. Ventilation For Fire and Smoke Management BACKLAYERING " • Avoid Backlayring – Critical Velocity of Airflow to be Maintained • Smoke To Be Directed, to Permit Escape in other direction 29
  • 30. Stratification Of Smoke • Smoke Rises to Top – Permits Escape Underneath in cooler air – Flashover Control • Typically Stratification lasts for 500-800mts – 30-40 MW fire – Tunnel Geomtry, Slope – Air Flow Conditions 30
  • 31. VENTILATION DESIGN INPUTS SMOKE CONTROL • Input Parameters – What is the maximum size of any fire, which may reasonably be expected to occur, given the use of tunnel • (Design Fire Curve- Fire/Smoke Vs. Time) – What Corresponding Ventilation is required to prevent smoke Backflow • Critical Velocity to be attained 31
  • 32. Emergency Ventilation Design Fire • Select Design Fire Load: Investigations were performed by Deutsche Bahn AG – Diesel Loco → Peak 20 MW – Electric Loco → Peak 12 MW – Passenger train → Peak 25 MW – Freight train → Peak 852 MW (depending on load) • Design Fire Adopted 40 MW (Two Dsl. Loco in Tandem) 32
  • 33. Emergency Ventilation Design Approach: TEMPERATURE / SMOKE PROGRESSION ALONG THE LENGTH HEIGHT Computation fluid dynamics (camatt) – Design Fire – Tunnel Geometry – Fan design & Configuration – Thermo Dynamics – Fluid Dynamics 33
  • 34. Emergency Ventilation Design Approach: TEMPERATURE / SMOKE PROGRESSION ALONG THE LENGTH HEIGHT BY NEAR FIRE CONDITIONS BY 3DCFD Objective:– To clarify condition d/s of fire – Influence of longitudinal flow velocity on the tenability d/s from fire – Design Fire load 25 MW – Smoke plum should remain 2.5m above rail level during self evacuation time – Use of Deutsche Bahn Fire curve for smoke release rate and critical velocity 34
  • 35. FINAL VENTILATION DESIGN Jet Fan (Main Tunnel) Jet Fan (Access Tunnel) 35
  • 36. Ventilation Actuation:     Visibility detection Airflow measurement Automatic operation Basic ventilation Visibility data Airflow direction Wind speed  Fire Ventilation Fire Alarm Visibility data Airflow direction Wind Speed 36
  • 37. Ventilation System -Installations Sr.No. Location Fixing height Spacing 25 MVS 3.5 Mtrs. 150Mtrs. 3 21 21 Adit Each next MN Each next MN 4.0 Mtrs. 4.0 Mtrs. 4.0 Mtrs. 150 Mtrs 500 Mtrs. 500 Mtrs. 25 3 Each Jet fan Each Jet fan 150 Mtrs 150 Mtrs a) Main tunnel 75 Each Jet fan (3) 150 Mtrs b) Adit Tunnel 9 Each Jet fan (3) 150 Mtrs Vibration Sensor a) Main tunnel 25 Each Jet fan 150 Mtrs b) Adit Tunnel 1 Description of Items Qty. 3 Each Jet fan 150 Mtrs 2 Adit tunnel Jet Fan a) Main tunnel ( Five Groups) b) Adit Tunnel 2 Air Velocity Measuremnt. 3 CO/Dust Particle 4 Proximity Sensor a) Main tunnel b) Adit Tunnel 5 PT 100 Unit (Temp Sensor) 6 7 ADIT Axail Fan 3.0 Mtrs. 37 4.0 Mtrs.
  • 38. E&M System Consists of the following 433/250V – 50 Hz Power Supply Emergency Power Supply Earthing & Potential Equalisation System Tunnel Lighting Tunnel Fittings Fire Detection System Building Power & Lighting Installations Room Ventilation & Air Conditioning 38
  • 39. System Compliance World Standard Pir Panjal UIC Redundant Power Supply   ~ I-67, I-65 CCTV System    I-68 Emergency and Service Phone System    I-42 Tunnel Radio System    I-66, I-2 Public Address System (Speaker System)   ~ Fire Detection System    Fire Fighting System (Water Line, Extinguishers)    I-24, I-64 Ventilation System    I-25 Emergency Lighting    I-41 Control Centre   ~ Escape Distance to be not more than 1000 mts.  ~  Comments I-43 Page 39
  • 40. T-80 TUNNEL CONTROL MONITORING CENTRE 40
  • 41. MULTI SCRN TUNNEL VIDEO MNTRING - WITH MOTION SENSOR TRIGGERS 41
  • 45. LIGHT & EROS MONITORING 45
  • 47. VENTILATION CONTROL STRATEGY REQUIREMENTS TO THE STAFF (NORMAL OPERATION) Train staff ►Report about type and direction of train entering the tunnel ►Break down: Report the location of the break down Control center staff ►Know about train type and direction ►Monitor emission levels in the tunnel ►Monitor appropriate operation of ventilation ►Instruct the train driver to shut down engines (if necessary) 47
  • 48. Ventilation Control Strategy Requirements to the staff (emergency operation) Train staff ►Guide passengers in the right direction ►Communicate and Local Guidance for Passenger Rescue Control center staff ►Select and confirm the appropriate mode of operation ►Monitor the appropriate mode of ventilation ►Support rescue operation (e.g. coordinate the rescue train) 48
  • 49. • Detailed Design Consultants – M/s GeoconsultRITES JV – Overall Tunnel Design and Top level Supervision, observations based On-site design with NATM approach – Ventilation, Rescue, E&M Design 49
  • 50. • HBI Haerter – Ventilation Design Proof Check 50
  • 51. 51
  • 52. 52
  • 53. 53
  • 54. MAIN TUNNEL CROSS-PASSAGES ESCAPE TUNNEL RAILWAY TUNNEL (T-74R) LAYOUT (AS PER UIC 779) 54
  • 55. 55
  • 56. 56