SlideShare a Scribd company logo
1 of 15
Download to read offline
GCCSI Financial Model
Case Study
September 03, 2012




Presented by




© 2012 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.
                                                                1
Contents
Model Features
   •   Expected Users
   •   Commercial Relation Model
   •   Model Logic & Features



Project Case Study : IGCC + CCS Project
   •   Case Study (Assumption of a fictional project)
   •   Base Case Results (Model Outputs)
   •   Sensitivity Analysis (Model Outputs)
   •   Value & Request




                                                        2
Model Features/Expected Users
The Model was developed to evaluate CCS Projects at a screening stage

The Expected Users are:
   •   Plant Owners (Utility company etc.)
   •   Project Developers
   •   Investors
   •   Lenders
   •   Policy Makers (Subsidies)
   •   Consultant/Think Tank
   •   EPC Contractor
   •   OEMs

   This presentation is prepared by MHI as Project Developer/EPC Contractor/OEM
   of Gasifier, Gas Turbine, Steam Turbine, CO2 Compressor.




                                                                              3
Model Features/Commercial Relation




                                     Various type of
                                     “Government Subsidies”
                                     can be simulated




                                        Payment to CO2
                                        Transport & Storage
                                        Provider is added to
                                        Cost of Generation &
                                        Capture Plant




                                                          4
Model Features/Model Logic & Features

The model is set up to evaluate an integrated CCS Project including:
    •   Upto three (3) Power Generation and CO2 Capture Projects
    •   A Single CO2 Transport Project
    •   A Single CO2 Storage Project


The Model’s worksheets have been structured around four (4) categories as follows:
    •   Inputs : General Assumptions, Price Assumptions, Scenario Manager
    •   Calculations: WACC (Weighted Average Cost of Capital), Timing, Operating Cash Flow,
                     Capex, Depreciation, Transport & Storage Charges,
                     LCOE (Levelised Cost of Electricity), Government Subsidies
    •   Outputs
          • Financial Statements: P/L Statement, Cashflow Statement, Balance Sheet,
            Discounted Cashflow Valuation
          • Summary: LCOE, Commercial Gaps, NPVs, Government Subsidies
          • Charts: EBITDA, Source & Use of Funds, LCOE constrains, NPV Constituents
            Commercial Gaps
    •   Others: Cover Sheet, Table of Contents, Information, Project Scheme, Macros etc.




                                                                                              5
Model Features/Model Logic & Features
  The Model can run a different scenario of User’s choice using “Scenario Manager”

  The Model contains Sensitivity inputs for the following categories
      • Capex
      • Capex Subsidies
      • O&M Costs
      • Fuel Costs
      • CO2 Cost
      • CO2 Transportation Costs
      • CO2 Storage Costs
      • PPA Revenue
      • Other Revenue (such as EOR Revenue
      • Operating Subsidies
      • WACC (Weighted Average Cost of Capital)

  The Model can run the following Goal Seeking Macros:
      • Goal Seeking Transport & Storage Charges (optimization to NPV = Zero)
      • Goal Seeking Government Capex Subsidies (optimizing to NPV=Zero)
      • Updating Sensitivities

                                                                                     6
Case Study : Project Assumption
  (Base Case)
General Assumption                          CCS Assumption
    Project Scope: IGCC + CCS                   CO2 Transport CAPEX, OPEX
    Commercial Operation starts in 2020         CO2 Storage CAPEX, OPEX
    Business Model : SPC Scheme                 Etc. to calculate CO2 Transport & Storage Fee
         w/ Equity 40%: Debt 60%                (Sample of Input Sheet)
    Revenue: Electricity Tariff @$ 50/MWh
                  No CO2 Revenue               GCCSI CCS Model                    OK
                                               Input - General
                                               Assumptions
Power Generation & Capture Assumption          SHEET CHECK OK
                                              1General Assumptions                Unit
    Gross Generation Capacity: 1017MW
                                                      Timing
    Plant Auxiliary Power: 218MW               1.1 
                                                      Model start date            Year     2012
                                                      Model periods               Years
    Fuel Consumption : 10.2 GJ/MWh                    Model end date              Year
                                                                                             70
                                                                                           2,082

    Fuel Cost: @$2.61/GJ                                                                  30-Jun-
                                                      Valuation date
                                                                                  date       11
    CO2 Capture: 0.8 CO2- ton/Net MWh                 Mid-period cashflows
                                                      assumed
    CO2 Cost: $30/CO2-ton Emission per Yr
                                                      Escalation
    CAPEX: $ 3.0 Billion                       1.2 
                                                      Inflation Rate (CPI)         %       2.5%
    OPEX(Fixed): $ 3.9 Million /Yr                    Base Year of real revenue
                                                      inputs                      Year
                                                                                           2012

    OPEX (Variable): $ 6.1/MWh per Year               Base Year of real cost
                                                      inputs                      Year
                                                                                           2012
                                                      Price Escalation -
                                                                                          100.0%
                                                      Percentage of CPI            %
                                                      Cost Escalation -
                                                                                          100.0%
                                                      Percentage of CPI            %



                                                                                                    7
Base Case Result (Outputs)

•LCOE= Levelised Cost of Electricity = NPV of Project Costs/NPV of Total Generation= @$103.6/MWh
→ Project is not feasible with Market PPA Tariff (@$50/MWh)

•   Commercial Gap = “LCOE” - “Levelised Electricity Price”           =   @$53.6/MWh

•   Sample of “Built-in” chart for Model Outputs is shown below




        CAPEX is the largest constituent $53.61/MWh
                                                                                       $103.6/MWh
       Fuel Cost
       $28.51/MWh is
                                                                                                     $50.0/MWh
       relatively low due
       to low Coal Cost
                                                                                                       Not
                                                                                                    Considered


                                                                                              $53.6/MWh




                            The Model calculates Transportation Cost ($1.55/MWh)”
                            & Storage Cost ($7.24/MWh)


                                                                                                             8
Sensitivity Analysis (Outputs)
                           2Sensitivity Summary                   Unit



                                                                                        IGCC



                                   LCOE changes
                            2.4 
                                   Base Case                     $ / MWh     109.63             109.63
                                   Capex (+/- 10%)               $ / MWh      5.62              (5.62)
                                   O&M costs (+/- 10%)           $ / MWh      0.65              (0.65)
                                   Fuel costs (+/- 10%)          $ / MWh      2.85              (2.85)
                                   CO2 costs (+/- 10%)           $ / MWh      0.29              (0.29)
                                   WACC (high / low)             $ / MWh     18.67             (15.91)


                                   NPV changes
                            2.5 
                                   Base Case                     $ 000's   (373,203.79)   (373,203.79)
                                   Capex (+/- 10%)               $ 000's    (230,049)          230,049
                                   Capex Subsidies (+/- 10%)     $ 000's    (211,652)          211,652
                                   O&M costs (+/- 10%)           $ 000's     (36,308)           36,308
                                   Fuel costs (+/- 10%)          $ 000's    (158,453)          158,453
                                   CO2 costs (+/- 10%)           $ 000's     (15,984)           15,984
                                   Transport costs (+/-10%)      $ 000's      (8,624)           8,624
                                   Storage costs (+/-10%)        $ 000's     (40,088)           40,088
                                   Other revenue (+/-10%)        $ 000's         ‐                 ‐
                                   Operating subsidy (+/-10%)    $ 000's         ‐                 ‐
                                   EOR revenue (+/-10%)          $ 000's         ‐                 ‐
                                   Gov PPA revenue (+/-10%)      $ 000's         ‐                 ‐
                                   Market PPA revenue (+/-10%)   $ 000's    (277,856)          277,856




                                                                                                         9
WACC Assumption /Calculation
      •      The Model provides “Pre-Financing” Cashfow only.
      •      However, it provides “WACC” ( Weighted Average of Capital Cost) simulation.
      •      The following are the Assumption and Calculation of the Case Study Project.
                                                                                           WACC calculation                                     IGCC
WACC Inputs                                              Transport   Storage Hub   IGCC
                                                                                               2.1  Cost of commercial equity
                                                                                                    Risk free rate                              5.00%
   10.1  Funding structure                                                                          Beta - ungeared                               0.75
         Commercial equity                                 35.0%        20.0%      25.0%            Debt / Equity                              150.00%
         Concessional equity                               0.0%         40.0%      15.0%            Regearing factor                              2.05
         Commercial debt                                   65.0%        20.0%      25.0%            Beta - geared                                 1.54
         Concessional debt                                 0.0%         10.0%      20.0%            Market risk premium                         6.00%
         Government debt                                   0.0%         10.0%      15.0%          Alpha                                          2.00%
         Check                                              OK           OK         OK            Cost of commercial equity                     16.23%

   10.2  General valuation parameters                                                          2.2  Commercial debt
         Risk-free rate                                   5.00%        5.00%                        Risk free rate                              5.00%
         Market risk premium                              6.00%        6.00%                      Margin above risk-free rate                   3.50%
         Liability Reserve -Interest Rate                               5.0%                      Swap Margin                                   0.50%
                                                                                                  Cost of commercial debt                       9.00%
   10.3  Commercial equity valuation parameters
         Beta - ungeared                                   0.45         1.05       0.75        2.3  WACC
         Alpha                                             0.0%         2.0%       2.0%             WACC Nominal Post Tax - Calculated          8.80%
                                                                                                    Sensitivity applied to base case            0.00%
   10.4  Concessional equity valuation parameters                                                   WACC Nominal Post Tax                       8.80%
         Concessional equity rate (all in rate)            8.0%         10.0%      12.0%
                                                                                                  Inflation Rate (CPI)                           2.50%
   10.5  Commercial debt valuation parameters                                                     WACC Real Post Tax                            6.14%
         Debt margin above swap                            2.0%         3.0%       3.5%
         Swap Margin                                       0.5%         0.5%       0.5%           WACC Real Pre Tax - Applied                   8.78%

   10.6  Concessional debt valuation parameters
         Concessional debt interest rate (all in rate)     6.0%         6.0%       6.0%
                                                                                              IRR of the Project is 8.80%p.a.
   10.7  Government debt valuation parameters
                                                                                              (after Government Capital Cost Subsidy Macoro runs)
         Government debt interest rate (all in rate)       5.0%         5.0%       5.0%



                  © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved.                                                                    10
“Value” and “Request”
  •   The Model is easy to operate and to simulate not only variation of essential
      “Project Values” (CAPEX, OPEX, Revenue, Schedule, Plant Performance etc.)
      but also various form of “Government Subsidies” (Feed-in-Tariff, Capital Cost
      Subsidies, Operating Cost Subsidies and Tax Credit). This is a unique value of
      GCCSI Financial Model.

  •   The Model is also useful to understand and evaluate the relation between
      “Power Generation” and “CCS” in one cashflow model.


  Request for Further Improvement
       1.“Built-in Scenario of EOR (Enhanced Oil Recovery)”
        The current model has EOR Revenue Selection Input but requires manual adjustment
        for CCS related cost inputs. It would be ideal if the Model has a built-in function of
        “CCS: EOR Ratio” (i.e.100%= No CCS but all the captured CO2 goes to EOR)
        2. “Funding Cashflows”
        The current Model is set for “Pre-Financing Cashflow” only. The built-in Option for
        cashflow with various inputs of Debt terms (interest rate, repayment period), Debt
        amortization and Equity distribution. Then, adding “ROE=Return of Equity” in Outputs
        and Sensitivity sheets will be very much appreciated, especially, by Investors.



                                                                                                 11
© 2012 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved.
© 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved.   12
Hand-out Material for Panel Discussion




© 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved.   13
Feed-in-Tariff for Clean Coal Power Generation (1 of 2)

•     In many countries, the Feed-in-Tariff (FIT) has been adopted as an incentive for
      constructing Renewable Energy Plant
•     If the main purpose of FIT is to reduce CO2 Emission, Why not “FIT for Clean Coal
      Power Generation” ?
•     In the Country X where the majority of Power is generated from Coal, “FIT for
      Renewable” is established as follows:
    Technology            Power Tariff          CO2 Emission         Capacity      (A) Annual       (B) Annual   (C) Incentive
                                                Rate                 Utilization   Reduction of     Total        per CO2
                                                (CO2ton/MWh)         Factor        CO2 by 1000MW    Incentive    Reduction
                                                                                   Capacity Plant   ($/Year)     per Year
                                                                                   (CO2 ton/Year)                ($/Ton)

    Conventional          @$55.30/MWh           0.99                 90%           Base             Base         Base
    Coal Power            (Market Tariff)       (Base)
    Generation
    Renewable             @$84.60/MWh           zero                 24%           (2,081,376)      61.6 M$      $29.6/ton
    (Wind)                (FIT)
    Renewable             @$192.80/MWh          zero                 18%           (1,561,032)      216.8 M$     $138.9/ton
    (Solar-PV)            (FIT)
    Renewable             @$258.20/MWh          zero                 23%           (1,994,652)      408.8 M$     $204.9/ton
    (Solar-CSP)           (FIT)


    (A) = CO2 Emission Rate x 1000MW x 24h x 365day x Capacity Utilization Factor
    (B) = (FIT – Market Tariff) x 1000MW x 24h x 365day x Capacity Utilization Factor
    (C) = (B) / (A)



         © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved.                                                          14
Feed-in-Tariff for Clean Coal Power Generation (2 of 2)
The same calculation for IGCC+CCS (90%) shows as follows:
 Technology          Power Tariff           CO2 Emission          Capacity        (A) Annual        (B) Annual        (C) Incentive per
                                            Rate                  Utilization     Reduction of      Total             Annual CO2
                                            (CO2ton/MWh)          Factor          CO2 by            Incentive for     Reduction for
                                                                                  1000MW Plant      1000MW            1000MW Plant
                                                                                  (CO2 ton/Year)    Plant ($/Year)    ($/Ton)
 Conventional        @$55.30/MWh            0.99                  90%             Base              Base              Base
 Coal Power          (Market Tariff)        (Base)
 Generation
 IGCC + CCS                   X             0.089                 90%             (7,103,484)              Y                  Z
 Power Plant

With LCOE of “IGCC+90%CCS” = @$116.0/MWh by GCCSI Financial Model, X~Z can be evaluated as follows:
 Technology                            X: Power Tariff          Y: Annual Total Incentive for      Z: Incentive per Annual CO2
                                                                1000MW Plant ($/Year)              Reduction for 1000MW Plant ($/Ton)
 Conventional Coal Power                 @$55.30/MWh                            Base                                 Base
 Generation                              (Market Tariff)
 IGCC + CCS                            @$116.0/MWh                      478.6 M$/Yr                            $67.4/Ton/Yr
 Power Plant
          If “Wind” FIT is applied       @$84.60/MWh                        61.6 M$                              $29.6/ton


      If “Solar-PV” FIT is applied       @$192.80/MWh                      216.8 M$                              $138.9/ton


     If “Solar-CSP” FIT is applied       @$258.20/MWh                      408.8 M$                              $204.9/ton

 Conclusion: In Country X,
 1. FIT for “IGCC+CCS” is a valid option for “CO2 Reduction” Incentive.
 2. FIT for IGCC + CCS should be higher than “Wind” but lower than “Solar”

      © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved.                                                                      15

More Related Content

What's hot

Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
seenyeeyong
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
Association for Project Management
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
ubk1411
 

What's hot (20)

Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
COMUNICADO A LA OPINIÓN PÚBLICA
COMUNICADO A LA OPINIÓN PÚBLICACOMUNICADO A LA OPINIÓN PÚBLICA
COMUNICADO A LA OPINIÓN PÚBLICA
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSFINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
 
INFORME TÉCNICO DE ACTUALIZACION DE PRECIOS.pdf
INFORME TÉCNICO DE ACTUALIZACION DE PRECIOS.pdfINFORME TÉCNICO DE ACTUALIZACION DE PRECIOS.pdf
INFORME TÉCNICO DE ACTUALIZACION DE PRECIOS.pdf
 
Plant Performance Monitoring
Plant Performance Monitoring Plant Performance Monitoring
Plant Performance Monitoring
 
OPERATION AND TROUBLE SHOOTING IN UREA SYNTHESI SSECTION.pdf
OPERATION AND TROUBLE SHOOTING IN UREA SYNTHESI SSECTION.pdfOPERATION AND TROUBLE SHOOTING IN UREA SYNTHESI SSECTION.pdf
OPERATION AND TROUBLE SHOOTING IN UREA SYNTHESI SSECTION.pdf
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Informe de ampliacion de plazo final
Informe de ampliacion de plazo finalInforme de ampliacion de plazo final
Informe de ampliacion de plazo final
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
INFORME-Nº-001-Solicito Asig presupuestal.docx
INFORME-Nº-001-Solicito Asig presupuestal.docxINFORME-Nº-001-Solicito Asig presupuestal.docx
INFORME-Nº-001-Solicito Asig presupuestal.docx
 
Mott MacDonald - Intro to NEC PSSC for APM - 1 hour - 2022.07.11.pdf
Mott MacDonald - Intro to NEC PSSC for APM  - 1 hour - 2022.07.11.pdfMott MacDonald - Intro to NEC PSSC for APM  - 1 hour - 2022.07.11.pdf
Mott MacDonald - Intro to NEC PSSC for APM - 1 hour - 2022.07.11.pdf
 
Guidelines for storage Handling and Dispensing of CNG.pptx
Guidelines for storage Handling and Dispensing of CNG.pptxGuidelines for storage Handling and Dispensing of CNG.pptx
Guidelines for storage Handling and Dispensing of CNG.pptx
 
Price adjustment and escalation
Price adjustment and escalationPrice adjustment and escalation
Price adjustment and escalation
 
PPQ Template
PPQ TemplatePPQ Template
PPQ Template
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Prequalification document(1)
Prequalification document(1)Prequalification document(1)
Prequalification document(1)
 
64593743 valorizaciones-y-liquidaciones-de-obra-con-herramientas-de-excel-1
64593743 valorizaciones-y-liquidaciones-de-obra-con-herramientas-de-excel-164593743 valorizaciones-y-liquidaciones-de-obra-con-herramientas-de-excel-1
64593743 valorizaciones-y-liquidaciones-de-obra-con-herramientas-de-excel-1
 

Viewers also liked

HTC Vive Marketing Plan
HTC Vive Marketing PlanHTC Vive Marketing Plan
HTC Vive Marketing Plan
Gregory Haeger
 

Viewers also liked (10)

CA Case Study
CA Case StudyCA Case Study
CA Case Study
 
Twitter Contest Case Study
Twitter Contest Case StudyTwitter Contest Case Study
Twitter Contest Case Study
 
Case Study: Danish Museums on Twitter
Case Study: Danish Museums on TwitterCase Study: Danish Museums on Twitter
Case Study: Danish Museums on Twitter
 
Walmart: How Social Analytics Works at Walmart
Walmart: How Social Analytics Works at WalmartWalmart: How Social Analytics Works at Walmart
Walmart: How Social Analytics Works at Walmart
 
Twitter Case Study by Mitesh M Motwani
Twitter Case Study by Mitesh M MotwaniTwitter Case Study by Mitesh M Motwani
Twitter Case Study by Mitesh M Motwani
 
HTC Vive Marketing Plan
HTC Vive Marketing PlanHTC Vive Marketing Plan
HTC Vive Marketing Plan
 
Walmart Quick Strategic Analysis / case study, past, present and future
Walmart Quick Strategic Analysis / case study, past, present and futureWalmart Quick Strategic Analysis / case study, past, present and future
Walmart Quick Strategic Analysis / case study, past, present and future
 
Toyota motors and CSR case study
Toyota motors and CSR case studyToyota motors and CSR case study
Toyota motors and CSR case study
 
Case Study: Google 2012
Case Study: Google 2012Case Study: Google 2012
Case Study: Google 2012
 
wal mart case study
wal mart case study wal mart case study
wal mart case study
 

Similar to GCCSI Financial Model Case Study

Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...
Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...
Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...
Global CCS Institute
 
First Solar Inc., July 2009
First Solar Inc., July 2009First Solar Inc., July 2009
First Solar Inc., July 2009
raja_lkc
 
Pathways To Low Carbon Power Generation Abatement Potential Towards 2020
Pathways To Low Carbon Power Generation   Abatement Potential Towards 2020Pathways To Low Carbon Power Generation   Abatement Potential Towards 2020
Pathways To Low Carbon Power Generation Abatement Potential Towards 2020
George Teriakidis
 
Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09
Chris Smith
 
US Methodologies for Assessing Non-Energy Benefits of Efficiency Measures
US Methodologies for Assessing Non-Energy Benefits of Efficiency MeasuresUS Methodologies for Assessing Non-Energy Benefits of Efficiency Measures
US Methodologies for Assessing Non-Energy Benefits of Efficiency Measures
International Energy Agency
 
xcel energy RBC_August_2008
xcel energy  RBC_August_2008xcel energy  RBC_August_2008
xcel energy RBC_August_2008
finance26
 
xcel energy RBC_August_2008
xcel energy  RBC_August_2008xcel energy  RBC_August_2008
xcel energy RBC_August_2008
finance26
 
UNFCCC - RE Project Funding International presentation
UNFCCC - RE Project Funding International presentationUNFCCC - RE Project Funding International presentation
UNFCCC - RE Project Funding International presentation
Howard Barmil
 
xcel energy RBC_July_2008
xcel energy  RBC_July_2008xcel energy  RBC_July_2008
xcel energy RBC_July_2008
finance26
 
xcel energy RBC_July_2008
xcel energy  RBC_July_2008xcel energy  RBC_July_2008
xcel energy RBC_July_2008
finance26
 
Massachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerMassachusetts policies for combined heat & power
Massachusetts policies for combined heat & power
TNenergy
 

Similar to GCCSI Financial Model Case Study (20)

Geo Epc Merrigan
Geo Epc MerriganGeo Epc Merrigan
Geo Epc Merrigan
 
Financing Energy Optimization Projects
Financing Energy Optimization Projects Financing Energy Optimization Projects
Financing Energy Optimization Projects
 
Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...
Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...
Juho Lipponen - CCS incentive policies: lessons and strategies - Presentation...
 
First Solar Inc., July 2009
First Solar Inc., July 2009First Solar Inc., July 2009
First Solar Inc., July 2009
 
Pathways To Low Carbon Power Generation Abatement Potential Towards 2020
Pathways To Low Carbon Power Generation   Abatement Potential Towards 2020Pathways To Low Carbon Power Generation   Abatement Potential Towards 2020
Pathways To Low Carbon Power Generation Abatement Potential Towards 2020
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4Course on Regulation and Sustainable Energy in Developing Countries - Session 4
Course on Regulation and Sustainable Energy in Developing Countries - Session 4
 
Evaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In TariffsEvaluating the Development and Impact of Feed-In Tariffs
Evaluating the Development and Impact of Feed-In Tariffs
 
Patrick Costello Green Guide Presentation Final 032112
Patrick Costello Green Guide Presentation Final 032112Patrick Costello Green Guide Presentation Final 032112
Patrick Costello Green Guide Presentation Final 032112
 
Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09Task Force Pace Phone Confer Q&A 7 29 09
Task Force Pace Phone Confer Q&A 7 29 09
 
US Methodologies for Assessing Non-Energy Benefits of Efficiency Measures
US Methodologies for Assessing Non-Energy Benefits of Efficiency MeasuresUS Methodologies for Assessing Non-Energy Benefits of Efficiency Measures
US Methodologies for Assessing Non-Energy Benefits of Efficiency Measures
 
Prgramme of activities fundamentals
Prgramme of activities  fundamentalsPrgramme of activities  fundamentals
Prgramme of activities fundamentals
 
xcel energy RBC_August_2008
xcel energy  RBC_August_2008xcel energy  RBC_August_2008
xcel energy RBC_August_2008
 
xcel energy RBC_August_2008
xcel energy  RBC_August_2008xcel energy  RBC_August_2008
xcel energy RBC_August_2008
 
UNFCCC - RE Project Funding International presentation
UNFCCC - RE Project Funding International presentationUNFCCC - RE Project Funding International presentation
UNFCCC - RE Project Funding International presentation
 
Profit Potential of Green Airport Strategies
Profit Potential of Green Airport StrategiesProfit Potential of Green Airport Strategies
Profit Potential of Green Airport Strategies
 
Dānijas pieredze Energoefektivitātes pienākuma shēmas ieviešanā enerģijas sad...
Dānijas pieredze Energoefektivitātes pienākuma shēmas ieviešanā enerģijas sad...Dānijas pieredze Energoefektivitātes pienākuma shēmas ieviešanā enerģijas sad...
Dānijas pieredze Energoefektivitātes pienākuma shēmas ieviešanā enerģijas sad...
 
xcel energy RBC_July_2008
xcel energy  RBC_July_2008xcel energy  RBC_July_2008
xcel energy RBC_July_2008
 
xcel energy RBC_July_2008
xcel energy  RBC_July_2008xcel energy  RBC_July_2008
xcel energy RBC_July_2008
 
Massachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerMassachusetts policies for combined heat & power
Massachusetts policies for combined heat & power
 
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
 

More from Global CCS Institute

Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Global CCS Institute
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Global CCS Institute
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Global CCS Institute
 
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Global CCS Institute
 
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Global CCS Institute
 
Managing carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsManaging carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basins
Global CCS Institute
 
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Global CCS Institute
 
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Global CCS Institute
 

More from Global CCS Institute (20)

Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project
 
Webinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSWebinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCS
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
 
Global CCS Institute Presentation
Global CCS Institute PresentationGlobal CCS Institute Presentation
Global CCS Institute Presentation
 
ION Engineering Presentation
ION Engineering PresentationION Engineering Presentation
ION Engineering Presentation
 
Membrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationMembrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) Presentation
 
Mission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeMission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation Challenge
 
Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?
 
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
 
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
 
Managing carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsManaging carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basins
 
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
 
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
 
Water use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsWater use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systems
 

Recently uploaded

Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
lizamodels9
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Recently uploaded (20)

Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 

GCCSI Financial Model Case Study

  • 1. GCCSI Financial Model Case Study September 03, 2012 Presented by © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. 1
  • 2. Contents Model Features • Expected Users • Commercial Relation Model • Model Logic & Features Project Case Study : IGCC + CCS Project • Case Study (Assumption of a fictional project) • Base Case Results (Model Outputs) • Sensitivity Analysis (Model Outputs) • Value & Request 2
  • 3. Model Features/Expected Users The Model was developed to evaluate CCS Projects at a screening stage The Expected Users are: • Plant Owners (Utility company etc.) • Project Developers • Investors • Lenders • Policy Makers (Subsidies) • Consultant/Think Tank • EPC Contractor • OEMs This presentation is prepared by MHI as Project Developer/EPC Contractor/OEM of Gasifier, Gas Turbine, Steam Turbine, CO2 Compressor. 3
  • 4. Model Features/Commercial Relation Various type of “Government Subsidies” can be simulated Payment to CO2 Transport & Storage Provider is added to Cost of Generation & Capture Plant 4
  • 5. Model Features/Model Logic & Features The model is set up to evaluate an integrated CCS Project including: • Upto three (3) Power Generation and CO2 Capture Projects • A Single CO2 Transport Project • A Single CO2 Storage Project The Model’s worksheets have been structured around four (4) categories as follows: • Inputs : General Assumptions, Price Assumptions, Scenario Manager • Calculations: WACC (Weighted Average Cost of Capital), Timing, Operating Cash Flow, Capex, Depreciation, Transport & Storage Charges, LCOE (Levelised Cost of Electricity), Government Subsidies • Outputs • Financial Statements: P/L Statement, Cashflow Statement, Balance Sheet, Discounted Cashflow Valuation • Summary: LCOE, Commercial Gaps, NPVs, Government Subsidies • Charts: EBITDA, Source & Use of Funds, LCOE constrains, NPV Constituents Commercial Gaps • Others: Cover Sheet, Table of Contents, Information, Project Scheme, Macros etc. 5
  • 6. Model Features/Model Logic & Features The Model can run a different scenario of User’s choice using “Scenario Manager” The Model contains Sensitivity inputs for the following categories • Capex • Capex Subsidies • O&M Costs • Fuel Costs • CO2 Cost • CO2 Transportation Costs • CO2 Storage Costs • PPA Revenue • Other Revenue (such as EOR Revenue • Operating Subsidies • WACC (Weighted Average Cost of Capital) The Model can run the following Goal Seeking Macros: • Goal Seeking Transport & Storage Charges (optimization to NPV = Zero) • Goal Seeking Government Capex Subsidies (optimizing to NPV=Zero) • Updating Sensitivities 6
  • 7. Case Study : Project Assumption (Base Case) General Assumption CCS Assumption Project Scope: IGCC + CCS CO2 Transport CAPEX, OPEX Commercial Operation starts in 2020 CO2 Storage CAPEX, OPEX Business Model : SPC Scheme Etc. to calculate CO2 Transport & Storage Fee w/ Equity 40%: Debt 60% (Sample of Input Sheet) Revenue: Electricity Tariff @$ 50/MWh No CO2 Revenue GCCSI CCS Model OK Input - General Assumptions Power Generation & Capture Assumption SHEET CHECK OK 1General Assumptions Unit Gross Generation Capacity: 1017MW Timing Plant Auxiliary Power: 218MW 1.1  Model start date Year 2012 Model periods Years Fuel Consumption : 10.2 GJ/MWh Model end date Year 70 2,082 Fuel Cost: @$2.61/GJ 30-Jun- Valuation date date 11 CO2 Capture: 0.8 CO2- ton/Net MWh Mid-period cashflows assumed CO2 Cost: $30/CO2-ton Emission per Yr Escalation CAPEX: $ 3.0 Billion 1.2  Inflation Rate (CPI) % 2.5% OPEX(Fixed): $ 3.9 Million /Yr Base Year of real revenue inputs Year 2012 OPEX (Variable): $ 6.1/MWh per Year Base Year of real cost inputs Year 2012 Price Escalation - 100.0% Percentage of CPI % Cost Escalation - 100.0% Percentage of CPI % 7
  • 8. Base Case Result (Outputs) •LCOE= Levelised Cost of Electricity = NPV of Project Costs/NPV of Total Generation= @$103.6/MWh → Project is not feasible with Market PPA Tariff (@$50/MWh) • Commercial Gap = “LCOE” - “Levelised Electricity Price” = @$53.6/MWh • Sample of “Built-in” chart for Model Outputs is shown below CAPEX is the largest constituent $53.61/MWh $103.6/MWh Fuel Cost $28.51/MWh is $50.0/MWh relatively low due to low Coal Cost Not Considered $53.6/MWh The Model calculates Transportation Cost ($1.55/MWh)” & Storage Cost ($7.24/MWh) 8
  • 9. Sensitivity Analysis (Outputs) 2Sensitivity Summary Unit IGCC LCOE changes 2.4  Base Case $ / MWh 109.63 109.63 Capex (+/- 10%) $ / MWh 5.62 (5.62) O&M costs (+/- 10%) $ / MWh 0.65 (0.65) Fuel costs (+/- 10%) $ / MWh 2.85 (2.85) CO2 costs (+/- 10%) $ / MWh 0.29 (0.29) WACC (high / low) $ / MWh 18.67 (15.91) NPV changes 2.5  Base Case $ 000's (373,203.79) (373,203.79) Capex (+/- 10%) $ 000's (230,049) 230,049 Capex Subsidies (+/- 10%) $ 000's (211,652) 211,652 O&M costs (+/- 10%) $ 000's (36,308) 36,308 Fuel costs (+/- 10%) $ 000's (158,453) 158,453 CO2 costs (+/- 10%) $ 000's (15,984) 15,984 Transport costs (+/-10%) $ 000's (8,624) 8,624 Storage costs (+/-10%) $ 000's (40,088) 40,088 Other revenue (+/-10%) $ 000's ‐ ‐ Operating subsidy (+/-10%) $ 000's ‐ ‐ EOR revenue (+/-10%) $ 000's ‐ ‐ Gov PPA revenue (+/-10%) $ 000's ‐ ‐ Market PPA revenue (+/-10%) $ 000's (277,856) 277,856 9
  • 10. WACC Assumption /Calculation • The Model provides “Pre-Financing” Cashfow only. • However, it provides “WACC” ( Weighted Average of Capital Cost) simulation. • The following are the Assumption and Calculation of the Case Study Project. WACC calculation IGCC WACC Inputs Transport Storage Hub IGCC 2.1  Cost of commercial equity Risk free rate 5.00% 10.1  Funding structure Beta - ungeared 0.75 Commercial equity 35.0% 20.0% 25.0% Debt / Equity 150.00% Concessional equity 0.0% 40.0% 15.0% Regearing factor 2.05 Commercial debt 65.0% 20.0% 25.0% Beta - geared 1.54 Concessional debt 0.0% 10.0% 20.0% Market risk premium 6.00% Government debt 0.0% 10.0% 15.0% Alpha 2.00% Check OK OK OK Cost of commercial equity 16.23% 10.2  General valuation parameters 2.2  Commercial debt Risk-free rate 5.00% 5.00% Risk free rate 5.00% Market risk premium 6.00% 6.00% Margin above risk-free rate 3.50% Liability Reserve -Interest Rate 5.0% Swap Margin 0.50% Cost of commercial debt 9.00% 10.3  Commercial equity valuation parameters Beta - ungeared 0.45 1.05 0.75 2.3  WACC Alpha 0.0% 2.0% 2.0% WACC Nominal Post Tax - Calculated 8.80% Sensitivity applied to base case 0.00% 10.4  Concessional equity valuation parameters WACC Nominal Post Tax 8.80% Concessional equity rate (all in rate) 8.0% 10.0% 12.0% Inflation Rate (CPI) 2.50% 10.5  Commercial debt valuation parameters WACC Real Post Tax 6.14% Debt margin above swap 2.0% 3.0% 3.5% Swap Margin 0.5% 0.5% 0.5% WACC Real Pre Tax - Applied 8.78% 10.6  Concessional debt valuation parameters Concessional debt interest rate (all in rate) 6.0% 6.0% 6.0% IRR of the Project is 8.80%p.a. 10.7  Government debt valuation parameters (after Government Capital Cost Subsidy Macoro runs) Government debt interest rate (all in rate) 5.0% 5.0% 5.0% © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved. 10
  • 11. “Value” and “Request” • The Model is easy to operate and to simulate not only variation of essential “Project Values” (CAPEX, OPEX, Revenue, Schedule, Plant Performance etc.) but also various form of “Government Subsidies” (Feed-in-Tariff, Capital Cost Subsidies, Operating Cost Subsidies and Tax Credit). This is a unique value of GCCSI Financial Model. • The Model is also useful to understand and evaluate the relation between “Power Generation” and “CCS” in one cashflow model. Request for Further Improvement 1.“Built-in Scenario of EOR (Enhanced Oil Recovery)” The current model has EOR Revenue Selection Input but requires manual adjustment for CCS related cost inputs. It would be ideal if the Model has a built-in function of “CCS: EOR Ratio” (i.e.100%= No CCS but all the captured CO2 goes to EOR) 2. “Funding Cashflows” The current Model is set for “Pre-Financing Cashflow” only. The built-in Option for cashflow with various inputs of Debt terms (interest rate, repayment period), Debt amortization and Equity distribution. Then, adding “ROE=Return of Equity” in Outputs and Sensitivity sheets will be very much appreciated, especially, by Investors. 11
  • 12. © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved. 12
  • 13. Hand-out Material for Panel Discussion © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved. 13
  • 14. Feed-in-Tariff for Clean Coal Power Generation (1 of 2) • In many countries, the Feed-in-Tariff (FIT) has been adopted as an incentive for constructing Renewable Energy Plant • If the main purpose of FIT is to reduce CO2 Emission, Why not “FIT for Clean Coal Power Generation” ? • In the Country X where the majority of Power is generated from Coal, “FIT for Renewable” is established as follows: Technology Power Tariff CO2 Emission Capacity (A) Annual (B) Annual (C) Incentive Rate Utilization Reduction of Total per CO2 (CO2ton/MWh) Factor CO2 by 1000MW Incentive Reduction Capacity Plant ($/Year) per Year (CO2 ton/Year) ($/Ton) Conventional @$55.30/MWh 0.99 90% Base Base Base Coal Power (Market Tariff) (Base) Generation Renewable @$84.60/MWh zero 24% (2,081,376) 61.6 M$ $29.6/ton (Wind) (FIT) Renewable @$192.80/MWh zero 18% (1,561,032) 216.8 M$ $138.9/ton (Solar-PV) (FIT) Renewable @$258.20/MWh zero 23% (1,994,652) 408.8 M$ $204.9/ton (Solar-CSP) (FIT) (A) = CO2 Emission Rate x 1000MW x 24h x 365day x Capacity Utilization Factor (B) = (FIT – Market Tariff) x 1000MW x 24h x 365day x Capacity Utilization Factor (C) = (B) / (A) © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved. 14
  • 15. Feed-in-Tariff for Clean Coal Power Generation (2 of 2) The same calculation for IGCC+CCS (90%) shows as follows: Technology Power Tariff CO2 Emission Capacity (A) Annual (B) Annual (C) Incentive per Rate Utilization Reduction of Total Annual CO2 (CO2ton/MWh) Factor CO2 by Incentive for Reduction for 1000MW Plant 1000MW 1000MW Plant (CO2 ton/Year) Plant ($/Year) ($/Ton) Conventional @$55.30/MWh 0.99 90% Base Base Base Coal Power (Market Tariff) (Base) Generation IGCC + CCS X 0.089 90% (7,103,484) Y Z Power Plant With LCOE of “IGCC+90%CCS” = @$116.0/MWh by GCCSI Financial Model, X~Z can be evaluated as follows: Technology X: Power Tariff Y: Annual Total Incentive for Z: Incentive per Annual CO2 1000MW Plant ($/Year) Reduction for 1000MW Plant ($/Ton) Conventional Coal Power @$55.30/MWh Base Base Generation (Market Tariff) IGCC + CCS @$116.0/MWh 478.6 M$/Yr $67.4/Ton/Yr Power Plant If “Wind” FIT is applied @$84.60/MWh 61.6 M$ $29.6/ton If “Solar-PV” FIT is applied @$192.80/MWh 216.8 M$ $138.9/ton If “Solar-CSP” FIT is applied @$258.20/MWh 408.8 M$ $204.9/ton Conclusion: In Country X, 1. FIT for “IGCC+CCS” is a valid option for “CO2 Reduction” Incentive. 2. FIT for IGCC + CCS should be higher than “Wind” but lower than “Solar” © 2012 MITSUBISHI HEAVY INDUSTRIES, LTD.  All Rights Reserved. 15