Design Development complete. – 35%
Value Engineering - Complete
Start of Construction Document Phase (~40% Complete)
Zoning – Special Exception and 2232 Submitted in October 2018
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
9th Lorton Community Center Steering Committee Meeting 2-11-2019
1. Building Design and Construction Division
LORTON COMMUNITY CENTER
Steering Committee Meeting
February 11, 2019
2. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
2
Agenda
Current Status
Community Center
Library Renovation & Expansion
Design:
Site Layout
Park Area Plan: Fitness & Playground Areas
Exterior Elevations
Overall Floor Plan
Floor Plan – Community Center
Interior Views
Floor Plan – Library
Interior Views
Schedule and Next Steps
Questions / Comments
Building Design and Construction Division
3. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
3
Current Status
Community Center
Design Development complete. – 35%
Value Engineering - Complete
Start of Construction Document Phase (~40% Complete)
Zoning – Special Exception and 2232 Submitted in October 2018
Library Renovation & Expansion
Schematic Design - Complete
Design Development – Authorized-To-Proceed – December, 2018
Building Design and Construction Division
4. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
Building Design and Construction Division
Design: Site Layout – Community Center and Library
Community Center Library
Open Field
Dry Pond with
Vegetation
4
5. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
5Building Design and Construction Division
Design: Site Layout – Alternative Parking Layout
6. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
6Building Design and Construction Division
Open Play Field
• Large open field
• 3 - Fitness Stations at strategic locations
• Enhanced Children’s Playground Area
• Park Trail with Picnic Tables & Benches
7. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
7Building Design and Construction Division
Fitness Station Equipment
Proposed Variety of Equipment
8. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
8Building Design and Construction Division
Playground Equipment
Proposed Variety of Play Equipment
9. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
9Building Design and Construction Division
Park Amenities
10. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
10
Design: Elevation – View of Front from Parking Lot
Building Design and Construction Division
11. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
11
Design: Elevation – View from Parking Lot
Building Design and Construction Division
12. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
12
Design: Elevation -View from Route #1 South
Building Design and Construction Division
13. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
13
Design: Elevation -View from Route #1 North
Building Design and Construction Division
14. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
14
Design: Overall Floor Plan Community Center and Library
Building Design and Construction Division
• Co-located - shared Lobby
• Community Center-29,312 SF
• Library Renovation-15,922 SF
15. Building Design and Construction Division 15
LORTON COMMUNITY LIBRARY
COMMUNITY STEERING COMMITTEE
Design: Floor Plan – Community Center
SENIOR
MULTI-PURPOSE
YOUTH
MULTI-PURPOSE GYMNASIUM LCAC
ADMIN
NCS
ADMIN
MULTI-PURPOSEEXERCISE
ART
MULTI-USE
LAB
PANTRY
STORAGE
SHARED
LOBBY
LIBRARY
MTG RM.
KITCHEN
RECEPTION
16. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
16
Interior View - Community Center Reception Area
Building Design and Construction Division
17. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
17Building Design and Construction Division
Interior Views – Community Center
Multi-Purpose
Corridor Areas
Youth Multi-
Purpose Room
18. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
18Building Design and Construction Division
Interior Views – Community Center
Corridor
Multi-use Spaces
Senior
Multi-Purpose
19. Building Design and Construction Division 19
LORTON COMMUNITY LIBRARY
COMMUNITY STEERING COMMITTEE
Design: Floor Plan - Library
SHARED
LOBBY
MEETING
ROOM
READING
ROOM
TEENS QUIET
STUDY
CHILDREN
STAFF
LOADING
DESK
CONF
STUDY
STUDY
STUDY
20. Building Design and Construction Division 20
LORTON COMMUNITY LIBRARY
COMMUNITY STEERING COMMITTEE
Design: Interior Rendering - Library
Before After
21. Building Design and Construction Division 21
LORTON COMMUNITY LIBRARY
COMMUNITY STEERING COMMITTEE
Design: Interior Rendering - Library
22. Building Design and Construction Division 22
LORTON COMMUNITY LIBRARY
COMMUNITY STEERING COMMITTEE
Design: Interior Rendering – Library
Children’s Area
23. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
23
Schedule and Next Steps
Building Design and Construction Division
Design/Zoning/Permits Construction
Late 2017 Late 2019
Kick-Off Occupancy
Late 2021
Bid
Community Center:
DPZ Review Process
Planning Commission Meeting – May 22, 2019
BOS Meeting – approximately - end of June 2019
Library Renovation:
Design Development Submission – February, 2019
Value Engineering Session – End of February, 2019
24. Building Design and Construction Division
LORTON COMMUNITY CENTER
COMMUNITY STEERING COMMITTEE
24
Questions/Comments
Building Design and Construction Division