9th Lorton Community Center Steering Committee Meeting 2-11-2019

2,422 views

Published on

Design Development complete. – 35%
Value Engineering - Complete
Start of Construction Document Phase (~40% Complete)
Zoning – Special Exception and 2232 Submitted in October 2018

Published in: Government & Nonprofit
  • Be the first to comment

  • Be the first to like this

9th Lorton Community Center Steering Committee Meeting 2-11-2019

  1. 1. Building Design and Construction Division LORTON COMMUNITY CENTER Steering Committee Meeting February 11, 2019
  2. 2. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 2 Agenda  Current Status  Community Center  Library Renovation & Expansion  Design:  Site Layout  Park Area Plan: Fitness & Playground Areas  Exterior Elevations  Overall Floor Plan  Floor Plan – Community Center  Interior Views  Floor Plan – Library  Interior Views  Schedule and Next Steps  Questions / Comments Building Design and Construction Division
  3. 3. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 3 Current Status  Community Center  Design Development complete. – 35%  Value Engineering - Complete  Start of Construction Document Phase (~40% Complete)  Zoning – Special Exception and 2232 Submitted in October 2018  Library Renovation & Expansion  Schematic Design - Complete  Design Development – Authorized-To-Proceed – December, 2018 Building Design and Construction Division
  4. 4. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE Building Design and Construction Division Design: Site Layout – Community Center and Library Community Center Library Open Field Dry Pond with Vegetation 4
  5. 5. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 5Building Design and Construction Division Design: Site Layout – Alternative Parking Layout
  6. 6. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 6Building Design and Construction Division Open Play Field • Large open field • 3 - Fitness Stations at strategic locations • Enhanced Children’s Playground Area • Park Trail with Picnic Tables & Benches
  7. 7. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 7Building Design and Construction Division Fitness Station Equipment  Proposed Variety of Equipment
  8. 8. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 8Building Design and Construction Division Playground Equipment  Proposed Variety of Play Equipment
  9. 9. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 9Building Design and Construction Division Park Amenities
  10. 10. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 10 Design: Elevation – View of Front from Parking Lot Building Design and Construction Division
  11. 11. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 11 Design: Elevation – View from Parking Lot Building Design and Construction Division
  12. 12. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 12 Design: Elevation -View from Route #1 South Building Design and Construction Division
  13. 13. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 13 Design: Elevation -View from Route #1 North Building Design and Construction Division
  14. 14. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 14 Design: Overall Floor Plan Community Center and Library Building Design and Construction Division • Co-located - shared Lobby • Community Center-29,312 SF • Library Renovation-15,922 SF
  15. 15. Building Design and Construction Division 15 LORTON COMMUNITY LIBRARY COMMUNITY STEERING COMMITTEE Design: Floor Plan – Community Center SENIOR MULTI-PURPOSE YOUTH MULTI-PURPOSE GYMNASIUM LCAC ADMIN NCS ADMIN MULTI-PURPOSEEXERCISE ART MULTI-USE LAB PANTRY STORAGE SHARED LOBBY LIBRARY MTG RM. KITCHEN RECEPTION
  16. 16. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 16 Interior View - Community Center Reception Area Building Design and Construction Division
  17. 17. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 17Building Design and Construction Division Interior Views – Community Center Multi-Purpose Corridor Areas Youth Multi- Purpose Room
  18. 18. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 18Building Design and Construction Division Interior Views – Community Center Corridor Multi-use Spaces Senior Multi-Purpose
  19. 19. Building Design and Construction Division 19 LORTON COMMUNITY LIBRARY COMMUNITY STEERING COMMITTEE Design: Floor Plan - Library SHARED LOBBY MEETING ROOM READING ROOM TEENS QUIET STUDY CHILDREN STAFF LOADING DESK CONF STUDY STUDY STUDY
  20. 20. Building Design and Construction Division 20 LORTON COMMUNITY LIBRARY COMMUNITY STEERING COMMITTEE Design: Interior Rendering - Library Before After
  21. 21. Building Design and Construction Division 21 LORTON COMMUNITY LIBRARY COMMUNITY STEERING COMMITTEE Design: Interior Rendering - Library
  22. 22. Building Design and Construction Division 22 LORTON COMMUNITY LIBRARY COMMUNITY STEERING COMMITTEE Design: Interior Rendering – Library Children’s Area
  23. 23. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 23 Schedule and Next Steps Building Design and Construction Division Design/Zoning/Permits Construction Late 2017 Late 2019 Kick-Off Occupancy Late 2021 Bid Community Center: DPZ Review Process Planning Commission Meeting – May 22, 2019 BOS Meeting – approximately - end of June 2019 Library Renovation: Design Development Submission – February, 2019 Value Engineering Session – End of February, 2019
  24. 24. Building Design and Construction Division LORTON COMMUNITY CENTER COMMUNITY STEERING COMMITTEE 24 Questions/Comments Building Design and Construction Division

×