SlideShare a Scribd company logo
1 of 34
Earned Value Analysis Training
GPA – Confidential
2
Earned Value Analysis Training
Contents
Context
What is EVA
Why Use It?
How will we use it
EVA examples
EVA and MSP
What next?
Who to contact
GPA – Confidential
3
Earned Value Analysis Training
Context
GPA – Confidential
4
Earned Value Analysis Training
GPA – Confidential
PM
Technique
• Earned Value Analysis (EVA) is a
project management technique for
monitoring the cost and schedule
performance of projects
5
Earned Value Analysis Training
GPA – Confidential
PM
Technique
✔ PMI
• Earned Value Analysis (EVA) is a
project management technique for
monitoring the cost and schedule
performance of projects
• Used within PMI but not exclusive to it
6
Earned Value Analysis Training
GPA – Confidential
PM
Technique
✔ PMI
• Earned Value Analysis (EVA) is a
project management technique for
monitoring the cost and schedule
performance of projects
• Used within PMI but not exclusive to it
• Compares actual and budgeted
resources
7
Earned Value Analysis Training
GPA – Confidential
PM
Technique
Cost Schedule
Cost Status
Schedule Status
✔ PMI
• Earned Value Analysis (EVA) is a
project management technique for
monitoring the cost and schedule
performance of projects
• Used within PMI but not exclusive to it
• Compares actual and budgeted
resources
• Works by comparing project actuals
and budgeted resources expenditures
to show variance from original project
plan in terms of cost and schedule.
8
Earned Value Analysis Training
GPA – Confidential
PM
Technique
Cost Schedule
Monitor
PerformanceCost Status
Schedule Status
✔ PMI
• Earned Value Analysis (EVA) is a
project management technique for
monitoring the cost and schedule
performance of projects
• Used within PMI but not exclusive to it
• Compares actual and budgeted
resources
• Works by comparing project actuals
and budgeted resources expenditures
to show variance from original project
plan in terms of cost and schedule.
• MSP supports EVA but the technique
can be applied without software
9
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it has a budget of £10
10
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
11
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
•This level of expenditure wasn’t forecast until September
12
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
•This level of expenditure was not forecast until September
•20% of the budget to last the remaining two thirds of the project!
13
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
•This level of expenditure was not forecast until September
•20% of the budget to last the remaining two thirds of the project!
?
14
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
•This level of expenditure was not forecast until September
•20% of the budget to last the remaining two thirds of the project!
?
Is this a problem?
15
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
•This level of expenditure was not forecast until September
•20% of the budget to last the remaining two thirds of the project!
?
Is this a problem?
Two possible scenarios
Scenario 1 – Over Budget. Planned amount of work, Greater costs
Scenario 2 – Ahead of Schedule. Planned costs, Faster completion
16
Earned Value Analysis Training
GPA – Confidential
Why Use EVA?
Consider the following project
•In April it had a budget of £10
•By June 80% of the budget has been spent.
•This level of expenditure was not forecast until September
•20% of the budget to last the remaining two thirds of the project!
?
Is this a problem?
Two possible scenarios
Scenario 1 – Over Budget. Planned amount of work, Greater costs
Scenario 2 – Ahead of Schedule. Planned costs, Faster completion
EVA gives the Project manager the technique to see which Scenario is valid
17
Earned Value Analysis Training
EVA lets the Project Manager know if the project is
•On budget using Cost Variance
•On schedule using Schedule Variance
EVA Establishes
GPA – Confidential
Cost Variance (CV)Cost Variance (CV) The difference between what you planned to spend and what you actually
spent based on having lost or saved money
The difference between what you planned to spend and what you actually
spent based on having lost or saved money
18
Earned Value Analysis Training
EVA lets the Project Manager know if the project is
•On budget using Cost Variance
•On schedule using Schedule Variance
EVA Establishes
GPA – Confidential
Cost Variance (CV)Cost Variance (CV)
Schedule Variance
(SV)
Schedule Variance
(SV)
The difference between what you planned to spend and what you actually
spent based on having lost or saved money
The difference between what you planned to spend and what you actually
spent based on having lost or saved money
The difference between what you planned to spend and what you actually
spent based on being ahead of or behind schedule
The difference between what you planned to spend and what you actually
spent based on being ahead of or behind schedule
19
Earned Value Analysis Training
EVA lets the Project Manager know if the project is
•On budget using Cost Variance
•On schedule using Schedule Variance
•The estimatedcost to complete the project
EVA Establishes
GPA – Confidential
Cost Variance (CV)Cost Variance (CV)
Schedule Variance
(SV)
Schedule Variance
(SV)
The difference between what you planned to spend and what you actually
spent based on having lost or saved money
The difference between what you planned to spend and what you actually
spent based on having lost or saved money
The difference between what you planned to spend and what you actually
spent based on being ahead of or behind schedule
The difference between what you planned to spend and what you actually
spent based on being ahead of or behind schedule
Estimate at
Completion (EAC)
Estimate at
Completion (EAC)
How much it will cost in total to complete the task if current spending
patterns are maintained
How much it will cost in total to complete the task if current spending
patterns are maintained
20
Earned Value Analysis Training
To carry out EVA the following information is needed
GPA – Confidential
Planned Value (PV)Planned Value (PV)
Actual Cost (AC)Actual Cost (AC)
Total budget for a specific Work Breakdown StructureTotal budget for a specific Work Breakdown Structure
Amount it actually cost to complete a specific WBS item during a specific
period
Amount it actually cost to complete a specific WBS item during a specific
period
Earned Value (EV)Earned Value (EV) Approved budget for actual work on a given WBS item during a specific
period
Approved budget for actual work on a given WBS item during a specific
period
BCWSBCWS Budgeted cost of work scheduledBudgeted cost of work scheduled
ACWPACWP Actual cost of work performedActual cost of work performed
21
Earned Value Analysis Training
GPA – Confidential
Cost Variance (CV)Cost Variance (CV) The difference between what you planned to spend and what you actually
spent based on having lost or saved money
The difference between what you planned to spend and what you actually
spent based on having lost or saved money
Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)
Cost Variance (CV) is a measure of project performance and indicates how much over or under budget a project is.
A positive figure means the project is under budget
No difference means the project is on budget
A negative figure means the project is over budget
Cost Variance can also be articulated as the following convenient indicators
Cost Variance Percentage (CV%) = Cost Variance (CV) / Earned Value (EV) * 100
Cost Variance % indicates how much over or under budget the project is in terms of percentage
Cost Performance Indicator (CPI) = Earned Value (EV) / Actual Cost (AC)
Cost Performance Indicator is an index showing the efficiency of utilisation of the resource on the project
22
Earned Value Analysis Training
GPA – Confidential
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)
Schedule Variance (SV) is a measure of project performance and indicates how much ahead of or behind schedule a project is.
A positive figure means the project is ahead of schedule
No difference means the project is on schedule
A negative figure means the project is behind schedule
Schedule Variance can also be articulated as the following convenient indicators
Schedule Variance Percentage (SV%) = Schedule Variance (SV) / Planned Value (PV) *
100
Schedule Variance % indicates how much ahead or behind schedule a project is in terms of percentage
Schedule Performance Indicator (SPI) = Earned Value (EV) / Planned Value (PV)
Schedule Performance Indicator is an index showing the efficiency of time utilised on the project
Schedule Variance
(SV)
Schedule Variance
(SV)
The difference between what you planned to spend and what you actually
spent based on being ahead of or behind schedule
The difference between what you planned to spend and what you actually
spent based on being ahead of or behind schedule
23
Earned Value Analysis Training
GPA – Confidential
Estimate At Completion = Actual Cost (AC) / Earned Value (EV) * Total Budget
Estimate At Completion (EAC) is the estimated cost of the project at the end of the project
Estimate at
Completion (EAC)
Estimate at
Completion (EAC)
How much it will cost in total to complete the task if current spending
patterns are maintained
How much it will cost in total to complete the task if current spending
patterns are maintained
24
Earned Value Analysis Training
GPA – Confidential
A Practical Example
The Lord of the Manor requires 20 family portraits be painted and ready for the next Ball.
The Lord of the Manor has commissioned a painter to paint the portraits and will pay him £150
a day.
The painter estimates that each portrait will take 20 working days to complete.
Today it is the 30th April 2013.
The Ball takes place on the 8th
November 2014.
25
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
• The project starts on the 30th April
• The Lord of the Manor asks for a status update on the 1st September
• By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a
day. Equating to a cost of £3,000 per portrait
26
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
• The project starts on the 30th April
• The Lord of the Manor asks for a status update on the 1st September
• By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a
day. Equating to a cost of £3,000 per portrait
The Planned Value is calculated as follows.
Planned Value (PV) = £3,000 * 4 portraits = £12,000
27
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
• The project starts on the 30th April
• The Lord of the Manor asks for a status update on the 1st September
• By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a
day. Equating to a cost of £3,000 per portrait
The Planned Value is calculated as follows
Planned Value (PV) = £3,000 * 4 portraits = £12,000
However, the painter has only completed 3 portraits.
The Earned Value is calculated as follows
Earned Value (EV) = £3,000 * 3 portraits = £9,000
28
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
• The project starts on the 30th April
• The Lord of the Manor asks for a status update on the 1st September
• By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a
day. Equating to a cost of £3,000 per portrait
The Planned Value is calculated as follows
Planned Value (PV) = £3,000 * 4 portraits = £12,000
However, the painter has only completed 3 portraits.
The Earned Value is calculated as follows
Earned Value (EV) = £3,000 * 3 portraits = £9,000
The painter only completed 2 portraits as two of the portraits took 30 days to finish and not 20 days as originally planned. Representing a 50% increase on
the original estimate of £3,000 per portrait
The Actual Cost is calculated as follows
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
29
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
Planned Value (PV) = £3,000 * 4 portraits = £12,000
Earned Value (EV) = £3,000 * 3 portraits = £9,000
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
From this the Cost Variance (CV), Cost Variance % (CV%) and Cost Variance Indicator (CVI) can be calculated
30
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
Planned Value (PV) = £3,000 * 4 portraits = £12,000
Earned Value (EV) = £3,000 * 3 portraits = £9,000
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
From this the Cost Variance (CV), Cost Variance % (CV%) and Cost Variance Indicator (CVI) can be calculated
Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000
31
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
Planned Value (PV) = £3,000 * 4 portraits = £12,000
Earned Value (EV) = £3,000 * 3 portraits = £9,000
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
From this the Cost Variance (CV), Cost Variance Percentage (CV%) and Cost Variance Indicator (CVI) can be calculated
Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000
Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33%
32
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
Planned Value (PV) = £3,000 * 4 portraits = £12,000
Earned Value (EV) = £3,000 * 3 portraits = £9,000
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
From this the Cost Variance (CV), Cost Variance Percentage (CV%) can be calculated
Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000
Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33%
In real terms this means the project to date has cost £3,000 more than the Lord of the Manor planned to pay and is 33% over budget
33
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
Planned Value (PV) = £3,000 * 4 portraits = £12,000
Earned Value (EV) = £3,000 * 3 portraits = £9,000
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000
Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33%
The Schedule Variance (SV) and Schedule Variance Percentage (SV%) can now be derived
Schedule Variance (SV) = EV £9,000 – PV £12,000 = -£3,000
Schedule Variance Percentage (SV%) = SV £9,000 – PV £12,000 * 100 = 25%
34
Earned Value Analysis Training
GPA – Confidential
Start 30th
April
Start 30th
April
End 8th
Nov
End 8th
Nov
Update
1st
Sept
Update
1st
Sept
Planned Value (PV) = £3,000 * 4 portraits = £12,000
Earned Value (EV) = £3,000 * 3 portraits = £9,000
Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000
Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33%
The Schedule Variance (SV) and Schedule Variance Percentage (SV%) can now be derived
Schedule Variance (SV) = EV £9,000 – PV £12,000 = -£3,000
Schedule Variance Percentage (SV%) = SV £9,000 – PV £12,000 * 100 = 25%
The painter has done £3,000 less worth of work than the Lord of the Manor had expected at this point and is 25% behind schedule.

More Related Content

What's hot

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
Fahad Ali
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 
Earned value management
Earned value managementEarned value management
Earned value management
Ashif AR
 

What's hot (20)

Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
The Benefits of using Earned Value Management
The Benefits of using Earned Value ManagementThe Benefits of using Earned Value Management
The Benefits of using Earned Value Management
 

Viewers also liked

Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman
 

Viewers also liked (11)

Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 

Similar to Earned value analysis training

L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
AsBali1
 

Similar to Earned value analysis training (20)

Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 

Recently uploaded

Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 

Recently uploaded (20)

Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Rice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna ExportsRice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna Exports
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 

Earned value analysis training

  • 1. Earned Value Analysis Training GPA – Confidential
  • 2. 2 Earned Value Analysis Training Contents Context What is EVA Why Use It? How will we use it EVA examples EVA and MSP What next? Who to contact GPA – Confidential
  • 3. 3 Earned Value Analysis Training Context GPA – Confidential
  • 4. 4 Earned Value Analysis Training GPA – Confidential PM Technique • Earned Value Analysis (EVA) is a project management technique for monitoring the cost and schedule performance of projects
  • 5. 5 Earned Value Analysis Training GPA – Confidential PM Technique ✔ PMI • Earned Value Analysis (EVA) is a project management technique for monitoring the cost and schedule performance of projects • Used within PMI but not exclusive to it
  • 6. 6 Earned Value Analysis Training GPA – Confidential PM Technique ✔ PMI • Earned Value Analysis (EVA) is a project management technique for monitoring the cost and schedule performance of projects • Used within PMI but not exclusive to it • Compares actual and budgeted resources
  • 7. 7 Earned Value Analysis Training GPA – Confidential PM Technique Cost Schedule Cost Status Schedule Status ✔ PMI • Earned Value Analysis (EVA) is a project management technique for monitoring the cost and schedule performance of projects • Used within PMI but not exclusive to it • Compares actual and budgeted resources • Works by comparing project actuals and budgeted resources expenditures to show variance from original project plan in terms of cost and schedule.
  • 8. 8 Earned Value Analysis Training GPA – Confidential PM Technique Cost Schedule Monitor PerformanceCost Status Schedule Status ✔ PMI • Earned Value Analysis (EVA) is a project management technique for monitoring the cost and schedule performance of projects • Used within PMI but not exclusive to it • Compares actual and budgeted resources • Works by comparing project actuals and budgeted resources expenditures to show variance from original project plan in terms of cost and schedule. • MSP supports EVA but the technique can be applied without software
  • 9. 9 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it has a budget of £10
  • 10. 10 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent.
  • 11. 11 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent. •This level of expenditure wasn’t forecast until September
  • 12. 12 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent. •This level of expenditure was not forecast until September •20% of the budget to last the remaining two thirds of the project!
  • 13. 13 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent. •This level of expenditure was not forecast until September •20% of the budget to last the remaining two thirds of the project! ?
  • 14. 14 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent. •This level of expenditure was not forecast until September •20% of the budget to last the remaining two thirds of the project! ? Is this a problem?
  • 15. 15 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent. •This level of expenditure was not forecast until September •20% of the budget to last the remaining two thirds of the project! ? Is this a problem? Two possible scenarios Scenario 1 – Over Budget. Planned amount of work, Greater costs Scenario 2 – Ahead of Schedule. Planned costs, Faster completion
  • 16. 16 Earned Value Analysis Training GPA – Confidential Why Use EVA? Consider the following project •In April it had a budget of £10 •By June 80% of the budget has been spent. •This level of expenditure was not forecast until September •20% of the budget to last the remaining two thirds of the project! ? Is this a problem? Two possible scenarios Scenario 1 – Over Budget. Planned amount of work, Greater costs Scenario 2 – Ahead of Schedule. Planned costs, Faster completion EVA gives the Project manager the technique to see which Scenario is valid
  • 17. 17 Earned Value Analysis Training EVA lets the Project Manager know if the project is •On budget using Cost Variance •On schedule using Schedule Variance EVA Establishes GPA – Confidential Cost Variance (CV)Cost Variance (CV) The difference between what you planned to spend and what you actually spent based on having lost or saved money The difference between what you planned to spend and what you actually spent based on having lost or saved money
  • 18. 18 Earned Value Analysis Training EVA lets the Project Manager know if the project is •On budget using Cost Variance •On schedule using Schedule Variance EVA Establishes GPA – Confidential Cost Variance (CV)Cost Variance (CV) Schedule Variance (SV) Schedule Variance (SV) The difference between what you planned to spend and what you actually spent based on having lost or saved money The difference between what you planned to spend and what you actually spent based on having lost or saved money The difference between what you planned to spend and what you actually spent based on being ahead of or behind schedule The difference between what you planned to spend and what you actually spent based on being ahead of or behind schedule
  • 19. 19 Earned Value Analysis Training EVA lets the Project Manager know if the project is •On budget using Cost Variance •On schedule using Schedule Variance •The estimatedcost to complete the project EVA Establishes GPA – Confidential Cost Variance (CV)Cost Variance (CV) Schedule Variance (SV) Schedule Variance (SV) The difference between what you planned to spend and what you actually spent based on having lost or saved money The difference between what you planned to spend and what you actually spent based on having lost or saved money The difference between what you planned to spend and what you actually spent based on being ahead of or behind schedule The difference between what you planned to spend and what you actually spent based on being ahead of or behind schedule Estimate at Completion (EAC) Estimate at Completion (EAC) How much it will cost in total to complete the task if current spending patterns are maintained How much it will cost in total to complete the task if current spending patterns are maintained
  • 20. 20 Earned Value Analysis Training To carry out EVA the following information is needed GPA – Confidential Planned Value (PV)Planned Value (PV) Actual Cost (AC)Actual Cost (AC) Total budget for a specific Work Breakdown StructureTotal budget for a specific Work Breakdown Structure Amount it actually cost to complete a specific WBS item during a specific period Amount it actually cost to complete a specific WBS item during a specific period Earned Value (EV)Earned Value (EV) Approved budget for actual work on a given WBS item during a specific period Approved budget for actual work on a given WBS item during a specific period BCWSBCWS Budgeted cost of work scheduledBudgeted cost of work scheduled ACWPACWP Actual cost of work performedActual cost of work performed
  • 21. 21 Earned Value Analysis Training GPA – Confidential Cost Variance (CV)Cost Variance (CV) The difference between what you planned to spend and what you actually spent based on having lost or saved money The difference between what you planned to spend and what you actually spent based on having lost or saved money Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC) Cost Variance (CV) is a measure of project performance and indicates how much over or under budget a project is. A positive figure means the project is under budget No difference means the project is on budget A negative figure means the project is over budget Cost Variance can also be articulated as the following convenient indicators Cost Variance Percentage (CV%) = Cost Variance (CV) / Earned Value (EV) * 100 Cost Variance % indicates how much over or under budget the project is in terms of percentage Cost Performance Indicator (CPI) = Earned Value (EV) / Actual Cost (AC) Cost Performance Indicator is an index showing the efficiency of utilisation of the resource on the project
  • 22. 22 Earned Value Analysis Training GPA – Confidential Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) Schedule Variance (SV) is a measure of project performance and indicates how much ahead of or behind schedule a project is. A positive figure means the project is ahead of schedule No difference means the project is on schedule A negative figure means the project is behind schedule Schedule Variance can also be articulated as the following convenient indicators Schedule Variance Percentage (SV%) = Schedule Variance (SV) / Planned Value (PV) * 100 Schedule Variance % indicates how much ahead or behind schedule a project is in terms of percentage Schedule Performance Indicator (SPI) = Earned Value (EV) / Planned Value (PV) Schedule Performance Indicator is an index showing the efficiency of time utilised on the project Schedule Variance (SV) Schedule Variance (SV) The difference between what you planned to spend and what you actually spent based on being ahead of or behind schedule The difference between what you planned to spend and what you actually spent based on being ahead of or behind schedule
  • 23. 23 Earned Value Analysis Training GPA – Confidential Estimate At Completion = Actual Cost (AC) / Earned Value (EV) * Total Budget Estimate At Completion (EAC) is the estimated cost of the project at the end of the project Estimate at Completion (EAC) Estimate at Completion (EAC) How much it will cost in total to complete the task if current spending patterns are maintained How much it will cost in total to complete the task if current spending patterns are maintained
  • 24. 24 Earned Value Analysis Training GPA – Confidential A Practical Example The Lord of the Manor requires 20 family portraits be painted and ready for the next Ball. The Lord of the Manor has commissioned a painter to paint the portraits and will pay him £150 a day. The painter estimates that each portrait will take 20 working days to complete. Today it is the 30th April 2013. The Ball takes place on the 8th November 2014.
  • 25. 25 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept • The project starts on the 30th April • The Lord of the Manor asks for a status update on the 1st September • By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a day. Equating to a cost of £3,000 per portrait
  • 26. 26 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept • The project starts on the 30th April • The Lord of the Manor asks for a status update on the 1st September • By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a day. Equating to a cost of £3,000 per portrait The Planned Value is calculated as follows. Planned Value (PV) = £3,000 * 4 portraits = £12,000
  • 27. 27 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept • The project starts on the 30th April • The Lord of the Manor asks for a status update on the 1st September • By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a day. Equating to a cost of £3,000 per portrait The Planned Value is calculated as follows Planned Value (PV) = £3,000 * 4 portraits = £12,000 However, the painter has only completed 3 portraits. The Earned Value is calculated as follows Earned Value (EV) = £3,000 * 3 portraits = £9,000
  • 28. 28 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept • The project starts on the 30th April • The Lord of the Manor asks for a status update on the 1st September • By the 1st of September the original project plan showed that the painter should have completed 4 portraits, each taking 20 days at a cost of £150 a day. Equating to a cost of £3,000 per portrait The Planned Value is calculated as follows Planned Value (PV) = £3,000 * 4 portraits = £12,000 However, the painter has only completed 3 portraits. The Earned Value is calculated as follows Earned Value (EV) = £3,000 * 3 portraits = £9,000 The painter only completed 2 portraits as two of the portraits took 30 days to finish and not 20 days as originally planned. Representing a 50% increase on the original estimate of £3,000 per portrait The Actual Cost is calculated as follows Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000
  • 29. 29 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept Planned Value (PV) = £3,000 * 4 portraits = £12,000 Earned Value (EV) = £3,000 * 3 portraits = £9,000 Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000 From this the Cost Variance (CV), Cost Variance % (CV%) and Cost Variance Indicator (CVI) can be calculated
  • 30. 30 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept Planned Value (PV) = £3,000 * 4 portraits = £12,000 Earned Value (EV) = £3,000 * 3 portraits = £9,000 Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000 From this the Cost Variance (CV), Cost Variance % (CV%) and Cost Variance Indicator (CVI) can be calculated Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000
  • 31. 31 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept Planned Value (PV) = £3,000 * 4 portraits = £12,000 Earned Value (EV) = £3,000 * 3 portraits = £9,000 Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000 From this the Cost Variance (CV), Cost Variance Percentage (CV%) and Cost Variance Indicator (CVI) can be calculated Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000 Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33%
  • 32. 32 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept Planned Value (PV) = £3,000 * 4 portraits = £12,000 Earned Value (EV) = £3,000 * 3 portraits = £9,000 Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000 From this the Cost Variance (CV), Cost Variance Percentage (CV%) can be calculated Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000 Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33% In real terms this means the project to date has cost £3,000 more than the Lord of the Manor planned to pay and is 33% over budget
  • 33. 33 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept Planned Value (PV) = £3,000 * 4 portraits = £12,000 Earned Value (EV) = £3,000 * 3 portraits = £9,000 Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000 Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000 Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33% The Schedule Variance (SV) and Schedule Variance Percentage (SV%) can now be derived Schedule Variance (SV) = EV £9,000 – PV £12,000 = -£3,000 Schedule Variance Percentage (SV%) = SV £9,000 – PV £12,000 * 100 = 25%
  • 34. 34 Earned Value Analysis Training GPA – Confidential Start 30th April Start 30th April End 8th Nov End 8th Nov Update 1st Sept Update 1st Sept Planned Value (PV) = £3,000 * 4 portraits = £12,000 Earned Value (EV) = £3,000 * 3 portraits = £9,000 Actual Cost (AC) = £3,000 * 1 portrait + £4,500 * 2 portraits = £12,000 Cost Variance (CV) = EV £9,000 – AC £12,000 = -£3,000 Cost Variance Percentage (CV%) = CV -£3,000 / EV £9,000 * 100 = -33% The Schedule Variance (SV) and Schedule Variance Percentage (SV%) can now be derived Schedule Variance (SV) = EV £9,000 – PV £12,000 = -£3,000 Schedule Variance Percentage (SV%) = SV £9,000 – PV £12,000 * 100 = 25% The painter has done £3,000 less worth of work than the Lord of the Manor had expected at this point and is 25% behind schedule.