SlideShare a Scribd company logo
1 of 33
Under guidance-
Prof. V. K. Gupta
HOD CIVIL DEPT.
2/13/2015 1
• Nondestructive testing in the broad sense
refers to methods whereby internal
characteristics of solid structures can be
examined without permanently affecting the
structure. Thus, parts that prove to be
satisfactory under specified test conditions are
not degraded by the test procedures
2/13/2015 2
Nondestructive testing (NDT) is the process of
inspecting, testing, or evaluating materials,
components or assemblies for discontinuities, or
differences in characteristics without destroying the
serviceability of the part or system. In other words,
when the inspection or test is completed the part
can still be used
2/13/2015 3
1)-Assessment of Existing Structures in the
Absence of Drawings.
2)-Quick assessment of the structure.
2/13/2015 4
1. Access to hidden items – “see through walls”
2. Better investigations with NDT
3. Rapid accumulation of data
4. Generally less expensive than destructive
testing.
2/13/2015 5
1. More than one test method may be required
2. Environmental conditions may effect or
distort results
3. Construction details & building components
may effect results
4. Some conditions cannot be determined with
a reasonable degree of accuracy without
destructive testing
2/13/2015 6
1-Rebound Hammer
2-Ultrasonic Pulse Velocity Meter
3-Pull Out
4.Core cutter
5-Covermeter
6- X ray computed tomography
7. Electric resistivity test
2/13/2015 7
• The rebound hammer can provide a fairly
accurate estimate of concrete compressive
strength.
• The concrete should be 14 to 56 days old.
• Surface Condition:
• The surface of the concrete at the point tested
must be smooth, dry, and free of honeycombing.
Otherwise, rebound readings will be low
Indicating a weaker concrete than is actually the
case. The rubbing stone provided can be used to
grind the surface smooth, if necessary.
2/13/2015 8
The concrete to be tested must be at least four
inches thick: It is also recommended that
readings be taken only where the concrete has
been in contact with the form. These conditions
are most easily satisfied if the readings are taken
along the edge of the tank on the sides and ends
where the adjoining concrete face (i.e., wall,
top, or bottom) can support the point of
contact.
2/13/2015 9
2/13/2015 10
• A). Remove hammer from case and press the
plunger end against a hard surface to release the
plunger from the locked position. (Do not press
lock button while doing this.)
• B). Position hammer horizontally with plunger
end against wall at a point.
• C). Slowly apply pressure until hammer fires. This
will occur when only approximately 1/2 inch of
the plunger is still visible. Do not press the lock
button during this step.
2/13/2015 11
• With the hammer still pressed against the
wall, read the rebound number off the scale
provided on the hammer. If it is necessary to
move the hammer before reading, press the
lock button. The rebound number should be
read to two significant figures.
• Repeat the above procedure at different
points around the wall until a total of ten
readings has been taken
2/13/2015 12
2/13/2015 13
• This is based on the principle that the velocity of an
ultrasonic pulse through any material depends
upon the density. Comparatively higher velocity is
obtained when concrete quality is good in terms of
density, uniformity etc.
• Pulse Velocity measurements can be used to assess
the presence of cracks, voids etc., quality of
concrete relative to standards requirements.
2/13/2015 14
There are three possible ways of measuring
pulse velocity.
i) Direct transmission
ii) Semi direct transmission
iii) Indirect transmission (surface probing)
Out of the three methods, the direct
transmission method is considered to be the best.
2/13/2015 15
2/13/2015 16
condition of concrete based on pulse
velocity are given below:
S.No. Pulse Velocity Condition of concrete
I in(Km/Sec.)
• 1. Above 4.5 Excellent
• 2. 3.5 to 4.5 Good
• 3. 3.0 to 3.5 Medium
• 4. Below 3.0 Poor
2/13/2015 17
• The fundamental principle behind pull out testing
with LOK-test and CAPO test is that the test
equipment designed to a specific geometry will
produce results (pull-out forces) that closely
correlate to the compressive strength of concrete.
The first method ,using the cast steel disc is called LOK
test. The second method shown in fig.2 using
expandable ring is called CAPO test (i.e. Cut and Pull
out Test). The diameter of both the disc and ring is
25mm. the distance to the concrete surface is also
25mm. the inner diameter of the counter-pressure is
55mm.2/13/2015 18
2/13/2015 19
The relationship between the pullout
force Fu in kN and compressive
strength Fc in MPa is given in fig
2/13/2015 20
• Determine in-situ compressive strength of the
concrete
• Ascertain the strength of concrete for carrying
out post tensioning operations.
• Determine the time of removal of forms and
shores based on actual in-situ strength of the
structure.
• Terminate curing based on in-situ strength of
the structure.
2/13/2015 21
The test should be taken at points where
minimum strength and maximum stress are likely to
coincide. But, at the same time, the core cutting
causes some damage to the member and may impair
the future performance of the member. Therefore, in
slender members, the core should be taken away
from the critical section. For compression testing, the
diameter of the core should be at least three times
the nominal maximum aggregate size.
2/13/2015 22
Core Cutter is used to cut the core from the
existing concrete structure for testing the
physical properties of the concrete like
compressive strength, density, water absorption,
crack depth and chemical test like depth of
carbonation and chloride content etc. It can also
be used to inspect the interior region of the
structural members.
2/13/2015 23
2/13/2015 24
Cover meters are electromagnetic in operation.
Electric currents in a coil winding in the search
head generate a magnetic field which
propagates through the concrete and will
interact with any buried metal present, such as
reinforcing steel.It is the generic term for
equipment used to locate steel reinforcing bar in
concrete and to estimate the thickness of the
concrete cover over the reinforcement.
2/13/2015 26
Tomography means imaging an object by taking
measurements from “slices” of its cross-section.
2/13/2015 27
In computed tomography, the image of an
object is reconstructed from projections of the
object.
• Most commonly the projections are obtained
by using penetrating x-rays, although other
modalities for measuring projection data are
also available.
2/13/2015 28
2/13/2015 29
2/13/2015 30
This test is carried out to assess the quality / uniformity
of concrete at various depths. The instrument consists of
a four probe device. Electrical current is passed through
the outer probes & the potential drop is measured by the
inner probes. From the current & voltage drop
measurements, the resistivity of concrete can be
measured.
Electrical resistivity = 2(pi)aE/i (in kilo-ohm cm)
where a = distance between probes
= 5 cm in the 1st set of readings
= 10 cm in the 2nd set of readings
E = potential difference between inner two probes in mV
Most useful test in tunnel structure.
2/13/2015 31
2/13/2015 32
2/13/2015 33

More Related Content

What's hot

Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concreteAyaz khan
 
Ultra sonic pulse velocity tests (Concrete technology)
Ultra sonic pulse velocity tests (Concrete technology)Ultra sonic pulse velocity tests (Concrete technology)
Ultra sonic pulse velocity tests (Concrete technology)Jayshiv Bhimani
 
Non destructive testing in concrete
Non destructive testing in concreteNon destructive testing in concrete
Non destructive testing in concreteHEMANT AVHAD
 
Shrinkage of concrete
Shrinkage of concreteShrinkage of concrete
Shrinkage of concretePramod GK
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitslalitha moorthy
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESbrijlata sharma
 
High performance concrete ppt
High performance concrete pptHigh performance concrete ppt
High performance concrete pptGoogle
 
Epoxy crack injection for concrete (the basics)
Epoxy crack injection for concrete (the basics)Epoxy crack injection for concrete (the basics)
Epoxy crack injection for concrete (the basics)jbors
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concreteRajesh Prasad
 
Distress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesDistress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesZaid Ansari
 
Non Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete StructuresNon Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete StructuresGautam Chaurasia
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concreteKaran Patel
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concreteGaurang Kakadiya
 

What's hot (20)

Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concrete
 
Ultra sonic pulse velocity tests (Concrete technology)
Ultra sonic pulse velocity tests (Concrete technology)Ultra sonic pulse velocity tests (Concrete technology)
Ultra sonic pulse velocity tests (Concrete technology)
 
Non destructive testing in concrete
Non destructive testing in concreteNon destructive testing in concrete
Non destructive testing in concrete
 
Shrinkage of concrete
Shrinkage of concreteShrinkage of concrete
Shrinkage of concrete
 
Compaction of concrete
Compaction of concreteCompaction of concrete
Compaction of concrete
 
Ndt
NdtNdt
Ndt
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
 
Hardened concrete
Hardened concreteHardened concrete
Hardened concrete
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURES
 
Epoxy injection crack repair
Epoxy injection crack repairEpoxy injection crack repair
Epoxy injection crack repair
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
 
Hardened Concrete
Hardened ConcreteHardened Concrete
Hardened Concrete
 
Rebound hammer test
Rebound hammer testRebound hammer test
Rebound hammer test
 
High performance concrete ppt
High performance concrete pptHigh performance concrete ppt
High performance concrete ppt
 
Epoxy crack injection for concrete (the basics)
Epoxy crack injection for concrete (the basics)Epoxy crack injection for concrete (the basics)
Epoxy crack injection for concrete (the basics)
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
 
Distress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesDistress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniques
 
Non Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete StructuresNon Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete Structures
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 

Similar to NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL

Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteAvinash Kumar Gupta
 
Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction SAURABH GUPTA
 
Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )AkashBhardwaj103
 
summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...Neha Singh
 
IRJET- Case Study of RCC Structure with the Help of Non Destructive Testing
IRJET-  	  Case Study of RCC Structure with the Help of Non Destructive TestingIRJET-  	  Case Study of RCC Structure with the Help of Non Destructive Testing
IRJET- Case Study of RCC Structure with the Help of Non Destructive TestingIRJET Journal
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxReigerRoyal
 
NON DESTRUCTIVE TESTING
NON DESTRUCTIVE TESTINGNON DESTRUCTIVE TESTING
NON DESTRUCTIVE TESTINGShrafatBalti
 
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMVineeshkumar K V
 
REBOUND Hammer Test
REBOUND Hammer Test REBOUND Hammer Test
REBOUND Hammer Test engomar84
 
Non destructive test in building construction
Non destructive test in building construction Non destructive test in building construction
Non destructive test in building construction Aditya Sanyal
 
Condition survey and nde
Condition survey and ndeCondition survey and nde
Condition survey and ndeJay Bhavsar
 
STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...
STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...
STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...IRJET Journal
 

Similar to NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL (20)

Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concrete
 
Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction
 
Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )
 
K04402070075
K04402070075K04402070075
K04402070075
 
summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...
 
IRJET- Case Study of RCC Structure with the Help of Non Destructive Testing
IRJET-  	  Case Study of RCC Structure with the Help of Non Destructive TestingIRJET-  	  Case Study of RCC Structure with the Help of Non Destructive Testing
IRJET- Case Study of RCC Structure with the Help of Non Destructive Testing
 
in- Situ testing of concrete
in- Situ testing of concretein- Situ testing of concrete
in- Situ testing of concrete
 
Trial mixing concrete .pdf
Trial mixing concrete .pdfTrial mixing concrete .pdf
Trial mixing concrete .pdf
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptx
 
Ndt
NdtNdt
Ndt
 
Non Destructive test
Non Destructive testNon Destructive test
Non Destructive test
 
NON DESTRUCTIVE TESTING
NON DESTRUCTIVE TESTINGNON DESTRUCTIVE TESTING
NON DESTRUCTIVE TESTING
 
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
 
REBOUND Hammer Test
REBOUND Hammer Test REBOUND Hammer Test
REBOUND Hammer Test
 
CHILAKALURIPER NDT REPORT.pdf
CHILAKALURIPER NDT REPORT.pdfCHILAKALURIPER NDT REPORT.pdf
CHILAKALURIPER NDT REPORT.pdf
 
Techshore Inspection Services-Concrete NDT.pdf
Techshore Inspection Services-Concrete NDT.pdfTechshore Inspection Services-Concrete NDT.pdf
Techshore Inspection Services-Concrete NDT.pdf
 
Non destructive test in building construction
Non destructive test in building construction Non destructive test in building construction
Non destructive test in building construction
 
Condition survey and nde
Condition survey and ndeCondition survey and nde
Condition survey and nde
 
Fresh and harden properties of concrete
Fresh and harden properties of concreteFresh and harden properties of concrete
Fresh and harden properties of concrete
 
STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...
STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...
STUDY ON STRUCTURAL COLLAPSE BEHAVIOUR OF REINFORCED CONCRETE BUILDING COLLAP...
 

More from Anshul Shakya

Safety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulSafety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulAnshul Shakya
 
PILE FOUNDATION PROJECT TRAINING ANSHUL
PILE FOUNDATION PROJECT TRAINING ANSHULPILE FOUNDATION PROJECT TRAINING ANSHUL
PILE FOUNDATION PROJECT TRAINING ANSHULAnshul Shakya
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshulAnshul Shakya
 
Multi story building construction anshul
Multi story building construction anshulMulti story building construction anshul
Multi story building construction anshulAnshul Shakya
 
ndt test (non destructive testing) for civil engg. material ANSHUL
 ndt test (non destructive testing) for  civil engg. material ANSHUL ndt test (non destructive testing) for  civil engg. material ANSHUL
ndt test (non destructive testing) for civil engg. material ANSHULAnshul Shakya
 
CEMENT MANUFATURING WASTE
CEMENT MANUFATURING WASTECEMENT MANUFATURING WASTE
CEMENT MANUFATURING WASTEAnshul Shakya
 
Anshul pwd training report
Anshul pwd training reportAnshul pwd training report
Anshul pwd training reportAnshul Shakya
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas Anshul Shakya
 

More from Anshul Shakya (8)

Safety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulSafety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area Anshul
 
PILE FOUNDATION PROJECT TRAINING ANSHUL
PILE FOUNDATION PROJECT TRAINING ANSHULPILE FOUNDATION PROJECT TRAINING ANSHUL
PILE FOUNDATION PROJECT TRAINING ANSHUL
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
Multi story building construction anshul
Multi story building construction anshulMulti story building construction anshul
Multi story building construction anshul
 
ndt test (non destructive testing) for civil engg. material ANSHUL
 ndt test (non destructive testing) for  civil engg. material ANSHUL ndt test (non destructive testing) for  civil engg. material ANSHUL
ndt test (non destructive testing) for civil engg. material ANSHUL
 
CEMENT MANUFATURING WASTE
CEMENT MANUFATURING WASTECEMENT MANUFATURING WASTE
CEMENT MANUFATURING WASTE
 
Anshul pwd training report
Anshul pwd training reportAnshul pwd training report
Anshul pwd training report
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
 

Recently uploaded

Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 

Recently uploaded (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 

NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL

  • 1. Under guidance- Prof. V. K. Gupta HOD CIVIL DEPT. 2/13/2015 1
  • 2. • Nondestructive testing in the broad sense refers to methods whereby internal characteristics of solid structures can be examined without permanently affecting the structure. Thus, parts that prove to be satisfactory under specified test conditions are not degraded by the test procedures 2/13/2015 2
  • 3. Nondestructive testing (NDT) is the process of inspecting, testing, or evaluating materials, components or assemblies for discontinuities, or differences in characteristics without destroying the serviceability of the part or system. In other words, when the inspection or test is completed the part can still be used 2/13/2015 3
  • 4. 1)-Assessment of Existing Structures in the Absence of Drawings. 2)-Quick assessment of the structure. 2/13/2015 4
  • 5. 1. Access to hidden items – “see through walls” 2. Better investigations with NDT 3. Rapid accumulation of data 4. Generally less expensive than destructive testing. 2/13/2015 5
  • 6. 1. More than one test method may be required 2. Environmental conditions may effect or distort results 3. Construction details & building components may effect results 4. Some conditions cannot be determined with a reasonable degree of accuracy without destructive testing 2/13/2015 6
  • 7. 1-Rebound Hammer 2-Ultrasonic Pulse Velocity Meter 3-Pull Out 4.Core cutter 5-Covermeter 6- X ray computed tomography 7. Electric resistivity test 2/13/2015 7
  • 8. • The rebound hammer can provide a fairly accurate estimate of concrete compressive strength. • The concrete should be 14 to 56 days old. • Surface Condition: • The surface of the concrete at the point tested must be smooth, dry, and free of honeycombing. Otherwise, rebound readings will be low Indicating a weaker concrete than is actually the case. The rubbing stone provided can be used to grind the surface smooth, if necessary. 2/13/2015 8
  • 9. The concrete to be tested must be at least four inches thick: It is also recommended that readings be taken only where the concrete has been in contact with the form. These conditions are most easily satisfied if the readings are taken along the edge of the tank on the sides and ends where the adjoining concrete face (i.e., wall, top, or bottom) can support the point of contact. 2/13/2015 9
  • 11. • A). Remove hammer from case and press the plunger end against a hard surface to release the plunger from the locked position. (Do not press lock button while doing this.) • B). Position hammer horizontally with plunger end against wall at a point. • C). Slowly apply pressure until hammer fires. This will occur when only approximately 1/2 inch of the plunger is still visible. Do not press the lock button during this step. 2/13/2015 11
  • 12. • With the hammer still pressed against the wall, read the rebound number off the scale provided on the hammer. If it is necessary to move the hammer before reading, press the lock button. The rebound number should be read to two significant figures. • Repeat the above procedure at different points around the wall until a total of ten readings has been taken 2/13/2015 12
  • 14. • This is based on the principle that the velocity of an ultrasonic pulse through any material depends upon the density. Comparatively higher velocity is obtained when concrete quality is good in terms of density, uniformity etc. • Pulse Velocity measurements can be used to assess the presence of cracks, voids etc., quality of concrete relative to standards requirements. 2/13/2015 14
  • 15. There are three possible ways of measuring pulse velocity. i) Direct transmission ii) Semi direct transmission iii) Indirect transmission (surface probing) Out of the three methods, the direct transmission method is considered to be the best. 2/13/2015 15
  • 17. condition of concrete based on pulse velocity are given below: S.No. Pulse Velocity Condition of concrete I in(Km/Sec.) • 1. Above 4.5 Excellent • 2. 3.5 to 4.5 Good • 3. 3.0 to 3.5 Medium • 4. Below 3.0 Poor 2/13/2015 17
  • 18. • The fundamental principle behind pull out testing with LOK-test and CAPO test is that the test equipment designed to a specific geometry will produce results (pull-out forces) that closely correlate to the compressive strength of concrete. The first method ,using the cast steel disc is called LOK test. The second method shown in fig.2 using expandable ring is called CAPO test (i.e. Cut and Pull out Test). The diameter of both the disc and ring is 25mm. the distance to the concrete surface is also 25mm. the inner diameter of the counter-pressure is 55mm.2/13/2015 18
  • 20. The relationship between the pullout force Fu in kN and compressive strength Fc in MPa is given in fig 2/13/2015 20
  • 21. • Determine in-situ compressive strength of the concrete • Ascertain the strength of concrete for carrying out post tensioning operations. • Determine the time of removal of forms and shores based on actual in-situ strength of the structure. • Terminate curing based on in-situ strength of the structure. 2/13/2015 21
  • 22. The test should be taken at points where minimum strength and maximum stress are likely to coincide. But, at the same time, the core cutting causes some damage to the member and may impair the future performance of the member. Therefore, in slender members, the core should be taken away from the critical section. For compression testing, the diameter of the core should be at least three times the nominal maximum aggregate size. 2/13/2015 22
  • 23. Core Cutter is used to cut the core from the existing concrete structure for testing the physical properties of the concrete like compressive strength, density, water absorption, crack depth and chemical test like depth of carbonation and chloride content etc. It can also be used to inspect the interior region of the structural members. 2/13/2015 23
  • 25. Cover meters are electromagnetic in operation. Electric currents in a coil winding in the search head generate a magnetic field which propagates through the concrete and will interact with any buried metal present, such as reinforcing steel.It is the generic term for equipment used to locate steel reinforcing bar in concrete and to estimate the thickness of the concrete cover over the reinforcement.
  • 27. Tomography means imaging an object by taking measurements from “slices” of its cross-section. 2/13/2015 27
  • 28. In computed tomography, the image of an object is reconstructed from projections of the object. • Most commonly the projections are obtained by using penetrating x-rays, although other modalities for measuring projection data are also available. 2/13/2015 28
  • 31. This test is carried out to assess the quality / uniformity of concrete at various depths. The instrument consists of a four probe device. Electrical current is passed through the outer probes & the potential drop is measured by the inner probes. From the current & voltage drop measurements, the resistivity of concrete can be measured. Electrical resistivity = 2(pi)aE/i (in kilo-ohm cm) where a = distance between probes = 5 cm in the 1st set of readings = 10 cm in the 2nd set of readings E = potential difference between inner two probes in mV Most useful test in tunnel structure. 2/13/2015 31