SlideShare a Scribd company logo
1 of 22
Download to read offline
Shell Weight reduction in 
BH521 6 Cavity 
Duration Sept‐2007 to Nov‐2007 
Project Leader – Abdullah Ansari
2 
Project Start date : 01/09/07 
Target Completion date : 15/11/07 
Date of proj presentation : 20/11/07 
Throughput Project Open days : 75 
Sponsors reviewed proj : Yes 
No of team meetings : 06 
Savings : Current FY Rs. 2 L 
Annualized Rs. 6 L 
Phase completed : D M A I C 
Belts % time on project : 40% 
Project review status : ( R / Y / G ) 
Sponsors MBB 
Define 
Measure 
Analysis 
Improve 
Control 
GGGGG 
GGGGG
Define project objective, expected benefits to the organization, team 
members, project schedule. 
DEFINE 
3
4 
Objective: 
Benefits: 
Project 
Team: 
To increase number of BH521(6 Cavity) shells per MT of resin coated sand by 
reducing shell weight from 27 Kgs to 25 Kgs at molding while maintaining the 
minimum possible defectives due to shell making. 
S J Chougule (Prod Engg) 
Savings: 52.5 K Rs per Month 
Improved process cycle time 
Reduced operator fatigue 
Effective utilization of raw material 
A T Ansari 
Ashok Khanna S S Kulkarni (Prod Engg) 
R K Choudhary Mahesh (Proc Engg) 
S N Soddy (Quality) 
R K Jena (Melting) 
Schedule: Measurement: 20/09/07 Analyze: 10/10/07 
Improvement: 10/11/07 Control: 15/11/07 
Revision 1 
Shell Weight reduction in BH521 6 Cavity
Base Current Shell Weight – 26 to 27 Kgs Current 
Current Cycle Time – 257 Seconds per shell (14 shells per hour) 
Investment time – 85 Seconds 
MEASURE 
5
6 
50,000 ft Process Map 
Shell Weight reduction in BH521 6 Cavity 
Inputs (Xs) Outputs (Ys) 
C/U/S 
Resin Coated sand C No. of Shell per hour 
Cycle Time C Shell weight 
Heated pattern U 
C = Controllable 
U = Uncontrollable 
S = SOP 
Shell Making
7 
C & E Matrix 
Rating of 
Importance to 
Customer 
8 8 
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 
Process Step Process Inputs 
No. of Shell 
per hour 
Shell weight 
Total 
1 Shell Making Investment time 6 6 96 
2 Shell Making Resin coated sand 0 6 48 
3 Shell Making Preheat time 2 2 32 
4 Shell Making Preheat temp 0 2 16 
5 Shell Making Baking time 2 0 16
8 
‘I’ Chart for Shell Weight before improvement 
I Chart of Shell Weight 
1 7 13 19 25 31 37 43 49 55 
28.5 
28.0 
27.5 
27.0 
26.5 
26.0 
25.5 
Observation 
Individual Value 
UCL=28.247 
_ 
X=26.882 
LCL=25.517 
1
Which factor affecting on shell weight? 
ANALYZE 
9
10 
Histogram of Shell Wt. 
25.8 26.4 27.0 27.6 28.2 
20 
15 
10 
5 
0 
Shell Wt 
Frequency 
Mean 26.88 
StDev 0.4979 
N 60 
Histogram of Shell Wt 
Normal
11 
Regression Analysis 
Shell Weight S 0.494345 
155 160 165 170 175 180 
28.5 
28.0 
27.5 
27.0 
26.5 
26.0 
Pattern Temp 
R-Sq 3.1% 
R-Sq(adj) 1.4% 
Fitted Line Plot 
Shell Weight = 24.35 + 0.01501 Pattern Temp 
Pattern temperature is not the major factor resulting in increase or decrease of shell weight. 
Take trials by varying temperature and investment time and redo regression analysis.
12 
Regression analysis – Fitted line plot for Inv time 
65 70 75 80 85 
27.5 
27.0 
26.5 
26.0 
25.5 
25.0 
Investment time 
Shell weight 
S 0.195085 
R-Sq 96.5% 
R-Sq(adj) 95.6% 
Fitted Line Plot 
Shell weight = 18.58 + 0.1025 Investment time
To decide optimum process parameters to achieve required 
shell weight. 
IMPROVE 
13
14 
DOE 
RUN Pattern Temp x Investment T ime Plan / Status Actual Avg Temp 
Actual Avg Shell 
Weight 
Run 1 220 x 65 04.10.2007 220.8 25.14 
Run 2 220 x 75 04.10.2007 220.9 26.21 
Run 3 220 x 85 04.10.2007 220.9 27.08 
Run 4 240 x 65 07.10.2007 240.8 25.04 
Run 5 240 x 75 07.10.2007 240.2 26.13 
Run 6 240 x 85 07.10.2007 238.8 26.63 
Run 7 260 x 65 08.10.2007 260.1 25.36 
Run 8 260 x 75 08.10.2007 262.6 27.09 
Run 9 260 x 85 08.10.2007 261.4 28.04
Contour Plot of Shell weight vs Pattern Temprature, Investment time 
Shell weight 
< 25.0 
– 
25.0 25.5 
25.5 – 
26.0 
26.0 – 
26.5 
26.5 – 
27.0 
27.0 – 
27.5 
27.5 – 
28.0 
15 
A 
B 
AB 
DOE Results 
0 5 10 15 20 
Term 
Standardized Effect 
1.99 
Factor Name 
A Inv estment time 
B Pattern Temprature 
Pareto Chart of the Standardized Effects 
(response is Shell weight, Alpha = .05) 
Investment time 
Pattern Temprature 
260 
250 
240 
230 
220 
210 
65 70 75 80 85 
> 
28.0 
Investment time = 69.9450 
Pattern Temprature = 220.231 
Shell weight = 25.5168 
Investment time = 65.0255 
Pattern Temprature = 240.176 
Shell weight = 25.2558
16 
Optimized Process controls for further full heat trials 
• Investment time = 65 to 70 Seconds 
– Target 67/68 Seconds 
• Pattern Temperature = 230 to 250 0C 
– Target 240 0C
17 
Results of full heat trials with new process parameters 
1 5 9 13 17 21 25 29 33 
26.4 
26.2 
26.0 
25.8 
25.6 
25.4 
25.2 
25.0 
Observation 
Individual Value 
UCL=26.362 
_ 
X=25.651 
LCL=24.940 
I Chart of Shell Wt 
23.6 24.0 24.4 24.8 25.2 25.6 26.0 
30 
25 
20 
15 
10 
5 
0 
Shell Wt 
Frequency 
Mean 25.00 
StDev 0.5079 
N 172 
Histogram of Shell Wt 
Normal 
Data of 1st 
Trial 
Data of shell weight 172 
shells ~ 5 heats
18 
Any effect on Casting Rejection…? 
• Before 
• Casting rejection 6% 
• Casting rejection due 
to swelling and shell 
crack – 1.5% 
• After 
• Casting rejection in 
full heat trials 5% 
• Casting rejection due 
to swelling and shell 
crack – 1% 
No Negative Effect
19 
Improvement Summary 
• Earlier shell weight 26.9Kgs (based on data collected on 18/09/2007), Now 
25.5Kgs 
• Saving of 1.4 Kg resin coated sand per shell 
• Earlier investment time 85/90 Seconds, Now 67 Seconds 
• Cycle time reduction by 18/23 Seconds per shell. 
• Forecasted saving 
– Due to saving in resin coated sand 
• Rs 49000 per month 
• Rs 5.88 Lacs per annum 
– Productivity improvement 
• 20 seconds x 14(shells per hour) = 280 Seconds ~ 1 shell per hour 
• Capacity enhancement of 3744nos of castings per month
Introduce Controls to sustain the improvement 
CONTROL 
20
21 
Control Plan 
• Resin coated sand 
– Sand properties should be strictly within specifications at receiving 
inspection. 
– Build up should be 49% to 52% 
• Investment time 
– Should be 65 to 70 Seconds. 67 is ideal. To be ensured while setup 
approval. 
• Pattern Temperature 
– Target for 2400C – Measure by infrared gun while setup approval 
– Maintain temperature by keeping burners on/off for every 2 alternate 
shells, as temperature on machine can not be controlled 
automatically.
Thank You

More Related Content

What's hot

Turbine Spin Gauge Center Locator
Turbine Spin Gauge Center LocatorTurbine Spin Gauge Center Locator
Turbine Spin Gauge Center LocatorPatrick Bier
 
Development of a Gasoline Direct Injector, Nostrum Energy
Development of a Gasoline Direct Injector, Nostrum EnergyDevelopment of a Gasoline Direct Injector, Nostrum Energy
Development of a Gasoline Direct Injector, Nostrum EnergyNostrum Energy, LLC
 
Material Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,PeshawarMaterial Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,PeshawarSyed Qaseem Haider
 
KLC - Process Engineering - Feb 2020
KLC - Process Engineering - Feb 2020KLC - Process Engineering - Feb 2020
KLC - Process Engineering - Feb 2020Pankaj Khandelwal
 
Boiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingBoiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingAll4 Inc.
 
Process engineering of chemical plant
Process engineering of chemical plantProcess engineering of chemical plant
Process engineering of chemical plantPankaj Khandelwal
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumJohn Glenning
 
Drilling economics drilling engineering
Drilling economics drilling engineeringDrilling economics drilling engineering
Drilling economics drilling engineeringSafen D Taha
 
Mat 045 final exam review part ii
Mat 045 final exam review   part iiMat 045 final exam review   part ii
Mat 045 final exam review part iiMae Guerra
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationKBC (A Yokogawa Company)
 
Europe User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practicesEurope User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practicesKBC (A Yokogawa Company)
 

What's hot (19)

Bills
BillsBills
Bills
 
Turbine Spin Gauge Center Locator
Turbine Spin Gauge Center LocatorTurbine Spin Gauge Center Locator
Turbine Spin Gauge Center Locator
 
Plant visit report
Plant visit reportPlant visit report
Plant visit report
 
Development of a Gasoline Direct Injector, Nostrum Energy
Development of a Gasoline Direct Injector, Nostrum EnergyDevelopment of a Gasoline Direct Injector, Nostrum Energy
Development of a Gasoline Direct Injector, Nostrum Energy
 
Material Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,PeshawarMaterial Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,Peshawar
 
Reaction Concepts-2019
Reaction Concepts-2019Reaction Concepts-2019
Reaction Concepts-2019
 
KLC - Process Engineering - Feb 2020
KLC - Process Engineering - Feb 2020KLC - Process Engineering - Feb 2020
KLC - Process Engineering - Feb 2020
 
LINK
LINKLINK
LINK
 
Brunswick motors, inc
Brunswick motors, incBrunswick motors, inc
Brunswick motors, inc
 
Boiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingBoiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air Permitting
 
Process engineering of chemical plant
Process engineering of chemical plantProcess engineering of chemical plant
Process engineering of chemical plant
 
Layout
LayoutLayout
Layout
 
GT-SSR
GT-SSRGT-SSR
GT-SSR
 
Process Flow Diagram
Process Flow DiagramProcess Flow Diagram
Process Flow Diagram
 
Velocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology ForumVelocys ppt140730_Velocys_GTL Technology Forum
Velocys ppt140730_Velocys_GTL Technology Forum
 
Drilling economics drilling engineering
Drilling economics drilling engineeringDrilling economics drilling engineering
Drilling economics drilling engineering
 
Mat 045 final exam review part ii
Mat 045 final exam review   part iiMat 045 final exam review   part ii
Mat 045 final exam review part ii
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluation
 
Europe User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practicesEurope User Conference: Albemarle FCC-SIM calibration best practices
Europe User Conference: Albemarle FCC-SIM calibration best practices
 

Similar to Productivity improvement & waste reduction

Monisha Alam_1412059
Monisha Alam_1412059Monisha Alam_1412059
Monisha Alam_1412059Monisha Alam
 
CatFT(r) Fischer-Tropsch Process presentation
CatFT(r) Fischer-Tropsch Process presentationCatFT(r) Fischer-Tropsch Process presentation
CatFT(r) Fischer-Tropsch Process presentationThomas Holcombe
 
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_ceaCea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_ceaProbodh Mallick
 
KSB Energy Saving_FPG (Send out)
KSB Energy Saving_FPG (Send out)KSB Energy Saving_FPG (Send out)
KSB Energy Saving_FPG (Send out)Zach Huang
 
A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...Parag Patil
 
8. DMAIC Control Phase Gate - Spool Installation
8. DMAIC Control Phase Gate - Spool Installation8. DMAIC Control Phase Gate - Spool Installation
8. DMAIC Control Phase Gate - Spool InstallationMichael Job
 
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand ReclamationIRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand ReclamationIRJET Journal
 
Design and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnDesign and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnHariKirant29
 
Technical and organizational optimization of the product freezing in a meat p...
Technical and organizational optimization of the product freezing in a meat p...Technical and organizational optimization of the product freezing in a meat p...
Technical and organizational optimization of the product freezing in a meat p...Enrique Cabrera Cano
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaDr. Bikram Jit Singh
 
Design improvements and costing analysis
Design improvements and costing analysisDesign improvements and costing analysis
Design improvements and costing analysisASHISH MENKUDALE
 
Introducing Process Group
Introducing Process GroupIntroducing Process Group
Introducing Process Groupprocess group
 
Prefeseability study of petroleum field
Prefeseability study of petroleum fieldPrefeseability study of petroleum field
Prefeseability study of petroleum fieldSafwen Sakhraoui
 
Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfBlentBulut5
 
Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014John Glenning
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Global CCS Institute
 

Similar to Productivity improvement & waste reduction (20)

Monisha Alam_1412059
Monisha Alam_1412059Monisha Alam_1412059
Monisha Alam_1412059
 
CatFT(r) Fischer-Tropsch Process presentation
CatFT(r) Fischer-Tropsch Process presentationCatFT(r) Fischer-Tropsch Process presentation
CatFT(r) Fischer-Tropsch Process presentation
 
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_ceaCea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
 
KSB Energy Saving_FPG (Send out)
KSB Energy Saving_FPG (Send out)KSB Energy Saving_FPG (Send out)
KSB Energy Saving_FPG (Send out)
 
A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...A report on Economic Feasibility for a chemical Process.(For details on Appen...
A report on Economic Feasibility for a chemical Process.(For details on Appen...
 
8. DMAIC Control Phase Gate - Spool Installation
8. DMAIC Control Phase Gate - Spool Installation8. DMAIC Control Phase Gate - Spool Installation
8. DMAIC Control Phase Gate - Spool Installation
 
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand ReclamationIRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
 
Design and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnDesign and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the Column
 
Technical and organizational optimization of the product freezing in a meat p...
Technical and organizational optimization of the product freezing in a meat p...Technical and organizational optimization of the product freezing in a meat p...
Technical and organizational optimization of the product freezing in a meat p...
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in india
 
Design improvements and costing analysis
Design improvements and costing analysisDesign improvements and costing analysis
Design improvements and costing analysis
 
Introducing Process Group
Introducing Process GroupIntroducing Process Group
Introducing Process Group
 
Prefeseability study of petroleum field
Prefeseability study of petroleum fieldPrefeseability study of petroleum field
Prefeseability study of petroleum field
 
Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdf
 
Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014
 
21myceit
21myceit21myceit
21myceit
 
21myceit
21myceit21myceit
21myceit
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
 
Vikram ie
Vikram ieVikram ie
Vikram ie
 

More from Abdullah Ansari

Effects of HDG (tZn) on high tensile fasteners & other alternatives
Effects of HDG (tZn) on high tensile fasteners & other alternativesEffects of HDG (tZn) on high tensile fasteners & other alternatives
Effects of HDG (tZn) on high tensile fasteners & other alternativesAbdullah Ansari
 
Advanced Diploma in AutoCAD
Advanced Diploma in AutoCADAdvanced Diploma in AutoCAD
Advanced Diploma in AutoCADAbdullah Ansari
 
Certified Internal Auditor QS9000
Certified Internal Auditor QS9000Certified Internal Auditor QS9000
Certified Internal Auditor QS9000Abdullah Ansari
 
Cetified Internal Auditor ISO/TS16949
Cetified Internal Auditor ISO/TS16949Cetified Internal Auditor ISO/TS16949
Cetified Internal Auditor ISO/TS16949Abdullah Ansari
 
Cold forging Process and Product Development - Case study
Cold forging Process and Product Development - Case studyCold forging Process and Product Development - Case study
Cold forging Process and Product Development - Case studyAbdullah Ansari
 
Carburization & Decarburization in Fasteners
Carburization & Decarburization in FastenersCarburization & Decarburization in Fasteners
Carburization & Decarburization in FastenersAbdullah Ansari
 
ASQ CSSBB letter and Certificate
ASQ CSSBB letter and CertificateASQ CSSBB letter and Certificate
ASQ CSSBB letter and CertificateAbdullah Ansari
 
Overview of Bolted Connections
Overview of Bolted ConnectionsOverview of Bolted Connections
Overview of Bolted ConnectionsAbdullah Ansari
 
Assessment of for Suitability of Ductile Iron Castings for cold climates
Assessment of for Suitability of Ductile Iron Castings for cold climatesAssessment of for Suitability of Ductile Iron Castings for cold climates
Assessment of for Suitability of Ductile Iron Castings for cold climatesAbdullah Ansari
 
Casting manufacturing process improvement
Casting manufacturing process improvementCasting manufacturing process improvement
Casting manufacturing process improvementAbdullah Ansari
 
General Foundry Guidelines
General Foundry GuidelinesGeneral Foundry Guidelines
General Foundry GuidelinesAbdullah Ansari
 

More from Abdullah Ansari (14)

Effects of HDG (tZn) on high tensile fasteners & other alternatives
Effects of HDG (tZn) on high tensile fasteners & other alternativesEffects of HDG (tZn) on high tensile fasteners & other alternatives
Effects of HDG (tZn) on high tensile fasteners & other alternatives
 
Corrosion protection
Corrosion protectionCorrosion protection
Corrosion protection
 
Cert 14001
Cert 14001Cert 14001
Cert 14001
 
Advanced Diploma in AutoCAD
Advanced Diploma in AutoCADAdvanced Diploma in AutoCAD
Advanced Diploma in AutoCAD
 
Advanced diploma in TQM
Advanced diploma in TQMAdvanced diploma in TQM
Advanced diploma in TQM
 
Certified Internal Auditor QS9000
Certified Internal Auditor QS9000Certified Internal Auditor QS9000
Certified Internal Auditor QS9000
 
Cetified Internal Auditor ISO/TS16949
Cetified Internal Auditor ISO/TS16949Cetified Internal Auditor ISO/TS16949
Cetified Internal Auditor ISO/TS16949
 
Cold forging Process and Product Development - Case study
Cold forging Process and Product Development - Case studyCold forging Process and Product Development - Case study
Cold forging Process and Product Development - Case study
 
Carburization & Decarburization in Fasteners
Carburization & Decarburization in FastenersCarburization & Decarburization in Fasteners
Carburization & Decarburization in Fasteners
 
ASQ CSSBB letter and Certificate
ASQ CSSBB letter and CertificateASQ CSSBB letter and Certificate
ASQ CSSBB letter and Certificate
 
Overview of Bolted Connections
Overview of Bolted ConnectionsOverview of Bolted Connections
Overview of Bolted Connections
 
Assessment of for Suitability of Ductile Iron Castings for cold climates
Assessment of for Suitability of Ductile Iron Castings for cold climatesAssessment of for Suitability of Ductile Iron Castings for cold climates
Assessment of for Suitability of Ductile Iron Castings for cold climates
 
Casting manufacturing process improvement
Casting manufacturing process improvementCasting manufacturing process improvement
Casting manufacturing process improvement
 
General Foundry Guidelines
General Foundry GuidelinesGeneral Foundry Guidelines
General Foundry Guidelines
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Productivity improvement & waste reduction

  • 1. Shell Weight reduction in BH521 6 Cavity Duration Sept‐2007 to Nov‐2007 Project Leader – Abdullah Ansari
  • 2. 2 Project Start date : 01/09/07 Target Completion date : 15/11/07 Date of proj presentation : 20/11/07 Throughput Project Open days : 75 Sponsors reviewed proj : Yes No of team meetings : 06 Savings : Current FY Rs. 2 L Annualized Rs. 6 L Phase completed : D M A I C Belts % time on project : 40% Project review status : ( R / Y / G ) Sponsors MBB Define Measure Analysis Improve Control GGGGG GGGGG
  • 3. Define project objective, expected benefits to the organization, team members, project schedule. DEFINE 3
  • 4. 4 Objective: Benefits: Project Team: To increase number of BH521(6 Cavity) shells per MT of resin coated sand by reducing shell weight from 27 Kgs to 25 Kgs at molding while maintaining the minimum possible defectives due to shell making. S J Chougule (Prod Engg) Savings: 52.5 K Rs per Month Improved process cycle time Reduced operator fatigue Effective utilization of raw material A T Ansari Ashok Khanna S S Kulkarni (Prod Engg) R K Choudhary Mahesh (Proc Engg) S N Soddy (Quality) R K Jena (Melting) Schedule: Measurement: 20/09/07 Analyze: 10/10/07 Improvement: 10/11/07 Control: 15/11/07 Revision 1 Shell Weight reduction in BH521 6 Cavity
  • 5. Base Current Shell Weight – 26 to 27 Kgs Current Current Cycle Time – 257 Seconds per shell (14 shells per hour) Investment time – 85 Seconds MEASURE 5
  • 6. 6 50,000 ft Process Map Shell Weight reduction in BH521 6 Cavity Inputs (Xs) Outputs (Ys) C/U/S Resin Coated sand C No. of Shell per hour Cycle Time C Shell weight Heated pattern U C = Controllable U = Uncontrollable S = SOP Shell Making
  • 7. 7 C & E Matrix Rating of Importance to Customer 8 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Process Step Process Inputs No. of Shell per hour Shell weight Total 1 Shell Making Investment time 6 6 96 2 Shell Making Resin coated sand 0 6 48 3 Shell Making Preheat time 2 2 32 4 Shell Making Preheat temp 0 2 16 5 Shell Making Baking time 2 0 16
  • 8. 8 ‘I’ Chart for Shell Weight before improvement I Chart of Shell Weight 1 7 13 19 25 31 37 43 49 55 28.5 28.0 27.5 27.0 26.5 26.0 25.5 Observation Individual Value UCL=28.247 _ X=26.882 LCL=25.517 1
  • 9. Which factor affecting on shell weight? ANALYZE 9
  • 10. 10 Histogram of Shell Wt. 25.8 26.4 27.0 27.6 28.2 20 15 10 5 0 Shell Wt Frequency Mean 26.88 StDev 0.4979 N 60 Histogram of Shell Wt Normal
  • 11. 11 Regression Analysis Shell Weight S 0.494345 155 160 165 170 175 180 28.5 28.0 27.5 27.0 26.5 26.0 Pattern Temp R-Sq 3.1% R-Sq(adj) 1.4% Fitted Line Plot Shell Weight = 24.35 + 0.01501 Pattern Temp Pattern temperature is not the major factor resulting in increase or decrease of shell weight. Take trials by varying temperature and investment time and redo regression analysis.
  • 12. 12 Regression analysis – Fitted line plot for Inv time 65 70 75 80 85 27.5 27.0 26.5 26.0 25.5 25.0 Investment time Shell weight S 0.195085 R-Sq 96.5% R-Sq(adj) 95.6% Fitted Line Plot Shell weight = 18.58 + 0.1025 Investment time
  • 13. To decide optimum process parameters to achieve required shell weight. IMPROVE 13
  • 14. 14 DOE RUN Pattern Temp x Investment T ime Plan / Status Actual Avg Temp Actual Avg Shell Weight Run 1 220 x 65 04.10.2007 220.8 25.14 Run 2 220 x 75 04.10.2007 220.9 26.21 Run 3 220 x 85 04.10.2007 220.9 27.08 Run 4 240 x 65 07.10.2007 240.8 25.04 Run 5 240 x 75 07.10.2007 240.2 26.13 Run 6 240 x 85 07.10.2007 238.8 26.63 Run 7 260 x 65 08.10.2007 260.1 25.36 Run 8 260 x 75 08.10.2007 262.6 27.09 Run 9 260 x 85 08.10.2007 261.4 28.04
  • 15. Contour Plot of Shell weight vs Pattern Temprature, Investment time Shell weight < 25.0 – 25.0 25.5 25.5 – 26.0 26.0 – 26.5 26.5 – 27.0 27.0 – 27.5 27.5 – 28.0 15 A B AB DOE Results 0 5 10 15 20 Term Standardized Effect 1.99 Factor Name A Inv estment time B Pattern Temprature Pareto Chart of the Standardized Effects (response is Shell weight, Alpha = .05) Investment time Pattern Temprature 260 250 240 230 220 210 65 70 75 80 85 > 28.0 Investment time = 69.9450 Pattern Temprature = 220.231 Shell weight = 25.5168 Investment time = 65.0255 Pattern Temprature = 240.176 Shell weight = 25.2558
  • 16. 16 Optimized Process controls for further full heat trials • Investment time = 65 to 70 Seconds – Target 67/68 Seconds • Pattern Temperature = 230 to 250 0C – Target 240 0C
  • 17. 17 Results of full heat trials with new process parameters 1 5 9 13 17 21 25 29 33 26.4 26.2 26.0 25.8 25.6 25.4 25.2 25.0 Observation Individual Value UCL=26.362 _ X=25.651 LCL=24.940 I Chart of Shell Wt 23.6 24.0 24.4 24.8 25.2 25.6 26.0 30 25 20 15 10 5 0 Shell Wt Frequency Mean 25.00 StDev 0.5079 N 172 Histogram of Shell Wt Normal Data of 1st Trial Data of shell weight 172 shells ~ 5 heats
  • 18. 18 Any effect on Casting Rejection…? • Before • Casting rejection 6% • Casting rejection due to swelling and shell crack – 1.5% • After • Casting rejection in full heat trials 5% • Casting rejection due to swelling and shell crack – 1% No Negative Effect
  • 19. 19 Improvement Summary • Earlier shell weight 26.9Kgs (based on data collected on 18/09/2007), Now 25.5Kgs • Saving of 1.4 Kg resin coated sand per shell • Earlier investment time 85/90 Seconds, Now 67 Seconds • Cycle time reduction by 18/23 Seconds per shell. • Forecasted saving – Due to saving in resin coated sand • Rs 49000 per month • Rs 5.88 Lacs per annum – Productivity improvement • 20 seconds x 14(shells per hour) = 280 Seconds ~ 1 shell per hour • Capacity enhancement of 3744nos of castings per month
  • 20. Introduce Controls to sustain the improvement CONTROL 20
  • 21. 21 Control Plan • Resin coated sand – Sand properties should be strictly within specifications at receiving inspection. – Build up should be 49% to 52% • Investment time – Should be 65 to 70 Seconds. 67 is ideal. To be ensured while setup approval. • Pattern Temperature – Target for 2400C – Measure by infrared gun while setup approval – Maintain temperature by keeping burners on/off for every 2 alternate shells, as temperature on machine can not be controlled automatically.