SlideShare a Scribd company logo
1 of 15
Micro-
 Generation
Installations
 YOUR Way

                                       Rocky View County
                 Joe Peters, Manager Service Development
            Allison Thomas, Stakeholder Relations Manager
                                       November 30, 2011

                                               1/13/2012   1
Electrical System Overview




Footer Text                          1/13/2012   2
Wires Service Provider

• Deliver safe and reliable
  electricity
• Manage outages
• Connect new customers
• Manage metering data
• Rates regulated by the
  Alberta Utilities Commission
  (AUC)
• Micro-generation
  coordination


                                              1/13/2012   3
Micro-Generation Regulation

• Issued by the Alberta
  Government in 2008

• The AUC oversaw
  implementation and
  developed processes to
  simplify approvals




                                        1/13/2012   4
Connecting YOUR Project


• 128 generators have
  signed interconnection
  agreements with
  FortisAlberta since
  2009.




 Micro-generation                        1/13/2012   5
Micro-Generation

To qualify as a micro-generator
the generating unit must…
• Use renewable or alternative
   energy technologies or
   higher efficiency fossil fuels

• Have a generating capacity
  smaller than one megawatt

• Produce electricity primarily
  for the customer’s own use        2-4 kW
                                    600 kWh per month



                                                   1/13/2012   6
Installations

• Mini MG Inverter-based
    o 10 kW and smaller
• Small MG
    o 0 kW to 150 kW (excludes
      Mini MG)
• Large MG
    o Greater than 150 kW and
      less than 1 MW




 Footer Text                                     1/13/2012   7
Mini Micro-Generator

• Capacity < 10 kW

• Equipped with a grid-tie
  inverter
   o Changes DC to AC
   o AC compatible with
     distribution system
   o Provides safety features




                                                1/13/2012   8
Steps to get your project started!

                                    Step 5 – Submit application to
                                    FortisAlberta

                           Step 4 - Prepare a site plan and electric
                           single-line diagram


                 Step 3 - Get municipal permits


        Step 2 - Consult with an electrical contractor


Step 1 (optional) - Inform FortisAlberta of your plan to install a micro-
generator




                                                                  1/13/2012   9
Application & Guidelines




Footer Text                         1/13/2012   10
Supporting Documents


• Electrical single-line
  diagram

• Site plan - where the
  MG will be located

• Electrical permit




                                         1/13/2012   11
FortisAlberta’s Role

• Process and approve
  application

• Interconnection
  agreement

• Install bi-directional
  meter

• Meter info to Retailer




                                                  1/13/2012   12
Only YOU have the power
to monitor and control the
energy you use.


FortisAlberta wants to help
Save Energy! Save Money!


• Public library power
  monitor program

• Community education
  programs

• Energy efficiency
  resources

• Alberta OnFarm program
  http://www.onfarmenergy.ca/
Visit us online at
www.fortisalberta.com


Phone us 403-310-WIRE or email
micro-gen@fortisalberta.com



Phone us 403-310-WIRE or email
energyyourway@fortisalberta.com



                                  1/13/2012   15

More Related Content

What's hot

Mme presentation customs
Mme presentation customsMme presentation customs
Mme presentation customs
mme
 
Welcome to Net Energy Metering Training
Welcome to Net Energy Metering TrainingWelcome to Net Energy Metering Training
Welcome to Net Energy Metering Training
Angela Robinson
 
Get Your Power From The Sun
Get Your Power From The SunGet Your Power From The Sun
Get Your Power From The Sun
mandika
 

What's hot (19)

Mme presentation customs
Mme presentation customsMme presentation customs
Mme presentation customs
 
Community Economic Development/Revitalization, Utilizing Electrical Micro Gri...
Community Economic Development/Revitalization, Utilizing Electrical Micro Gri...Community Economic Development/Revitalization, Utilizing Electrical Micro Gri...
Community Economic Development/Revitalization, Utilizing Electrical Micro Gri...
 
Renewable energy.pptx my presentation
Renewable energy.pptx my presentationRenewable energy.pptx my presentation
Renewable energy.pptx my presentation
 
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
 
Net metering seminar
Net metering seminarNet metering seminar
Net metering seminar
 
Mini grid and Solar home system
Mini grid and Solar home systemMini grid and Solar home system
Mini grid and Solar home system
 
The What and Why of Microgrids 4
The What and Why of Microgrids 4The What and Why of Microgrids 4
The What and Why of Microgrids 4
 
Net Metering - Why is TEP paying me less?
Net Metering - Why is TEP paying me less?Net Metering - Why is TEP paying me less?
Net Metering - Why is TEP paying me less?
 
Presentation1
Presentation1Presentation1
Presentation1
 
Hybrid distributed generation
Hybrid distributed generationHybrid distributed generation
Hybrid distributed generation
 
SolarEdge Company Presentation
SolarEdge Company PresentationSolarEdge Company Presentation
SolarEdge Company Presentation
 
Welcome to Net Energy Metering Training
Welcome to Net Energy Metering TrainingWelcome to Net Energy Metering Training
Welcome to Net Energy Metering Training
 
Connection of converters to a low and medium power dc network using an induct...
Connection of converters to a low and medium power dc network using an induct...Connection of converters to a low and medium power dc network using an induct...
Connection of converters to a low and medium power dc network using an induct...
 
A residential roof top solar system
A residential roof top solar systemA residential roof top solar system
A residential roof top solar system
 
Solar rooftop projects primotech
Solar rooftop projects primotechSolar rooftop projects primotech
Solar rooftop projects primotech
 
Microgrid Solar
Microgrid SolarMicrogrid Solar
Microgrid Solar
 
Micro-Grid Site Summaries
Micro-Grid Site SummariesMicro-Grid Site Summaries
Micro-Grid Site Summaries
 
Get Your Power From The Sun
Get Your Power From The SunGet Your Power From The Sun
Get Your Power From The Sun
 
Hybrid Mirco Grid Solutions
Hybrid Mirco Grid SolutionsHybrid Mirco Grid Solutions
Hybrid Mirco Grid Solutions
 

Viewers also liked

Small Scale Solar Energy
Small Scale Solar EnergySmall Scale Solar Energy
Small Scale Solar Energy
RockyViewCounty
 
Els amics sempre s'ajuden
Els amics sempre s'ajudenEls amics sempre s'ajuden
Els amics sempre s'ajuden
carmeo
 
ความขัดแย้งและความร่วมมือระหว่างประเทศ
ความขัดแย้งและความร่วมมือระหว่างประเทศความขัดแย้งและความร่วมมือระหว่างประเทศ
ความขัดแย้งและความร่วมมือระหว่างประเทศ
Pattaratida Luangsupa
 
claire5Mcivilization
claire5Mcivilizationclaire5Mcivilization
claire5Mcivilization
gsbSS
 
Entypo ekpaidefsis kai katartisis
Entypo ekpaidefsis kai katartisisEntypo ekpaidefsis kai katartisis
Entypo ekpaidefsis kai katartisis
Eleni Papadopoulou
 
Fisadelucru modurile nepersonale
Fisadelucru modurile nepersonaleFisadelucru modurile nepersonale
Fisadelucru modurile nepersonale
Anne Marie
 
Biblia hebraica stuttgartensia
Biblia hebraica stuttgartensiaBiblia hebraica stuttgartensia
Biblia hebraica stuttgartensia
gpelayomentor90
 
texto xulingo
texto xulingotexto xulingo
texto xulingo
Vieirarai
 
Els amics sempre s'ajuden
Els amics sempre s'ajudenEls amics sempre s'ajuden
Els amics sempre s'ajuden
carmeo
 
5M Anja Civilization
5M Anja Civilization5M Anja Civilization
5M Anja Civilization
gsbSS
 
Oceanspray &quot;Straight from the Bog&quot; Campaign analysis
Oceanspray &quot;Straight from the Bog&quot; Campaign analysisOceanspray &quot;Straight from the Bog&quot; Campaign analysis
Oceanspray &quot;Straight from the Bog&quot; Campaign analysis
nichoe10
 

Viewers also liked (20)

Small Scale Solar Energy
Small Scale Solar EnergySmall Scale Solar Energy
Small Scale Solar Energy
 
Problemas que trata la macroeconomia
Problemas que trata la macroeconomiaProblemas que trata la macroeconomia
Problemas que trata la macroeconomia
 
Els amics sempre s'ajuden
Els amics sempre s'ajudenEls amics sempre s'ajuden
Els amics sempre s'ajuden
 
Six Fundamentals of a Well-Built Venture
Six Fundamentals of a Well-Built VentureSix Fundamentals of a Well-Built Venture
Six Fundamentals of a Well-Built Venture
 
ศาสนาสากล
ศาสนาสากลศาสนาสากล
ศาสนาสากล
 
ความขัดแย้งและความร่วมมือระหว่างประเทศ
ความขัดแย้งและความร่วมมือระหว่างประเทศความขัดแย้งและความร่วมมือระหว่างประเทศ
ความขัดแย้งและความร่วมมือระหว่างประเทศ
 
claire5Mcivilization
claire5Mcivilizationclaire5Mcivilization
claire5Mcivilization
 
Klim Design Presentation
Klim Design PresentationKlim Design Presentation
Klim Design Presentation
 
Presentation 2
Presentation 2Presentation 2
Presentation 2
 
J av a bmi
J av a bmiJ av a bmi
J av a bmi
 
Entypo ekpaidefsis kai katartisis
Entypo ekpaidefsis kai katartisisEntypo ekpaidefsis kai katartisis
Entypo ekpaidefsis kai katartisis
 
Fisadelucru modurile nepersonale
Fisadelucru modurile nepersonaleFisadelucru modurile nepersonale
Fisadelucru modurile nepersonale
 
CiaoAmoreCiao
CiaoAmoreCiaoCiaoAmoreCiao
CiaoAmoreCiao
 
Biblia hebraica stuttgartensia
Biblia hebraica stuttgartensiaBiblia hebraica stuttgartensia
Biblia hebraica stuttgartensia
 
texto xulingo
texto xulingotexto xulingo
texto xulingo
 
Els amics sempre s'ajuden
Els amics sempre s'ajudenEls amics sempre s'ajuden
Els amics sempre s'ajuden
 
Web Entrepreneurship Plan
Web Entrepreneurship PlanWeb Entrepreneurship Plan
Web Entrepreneurship Plan
 
5M Anja Civilization
5M Anja Civilization5M Anja Civilization
5M Anja Civilization
 
Oceanspray &quot;Straight from the Bog&quot; Campaign analysis
Oceanspray &quot;Straight from the Bog&quot; Campaign analysisOceanspray &quot;Straight from the Bog&quot; Campaign analysis
Oceanspray &quot;Straight from the Bog&quot; Campaign analysis
 
Is My LLC Interest A Security?
Is My LLC Interest A Security?Is My LLC Interest A Security?
Is My LLC Interest A Security?
 

Similar to Micro-Generation Installations Your Way

Smart power grid
Smart power gridSmart power grid
Smart power grid
k shiva
 
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
iQHub
 
Summer Study EE 120318
Summer Study EE 120318Summer Study EE 120318
Summer Study EE 120318
Terry Daly
 
pptWhitepaper 03-smart grid-the future of the electric power system
pptWhitepaper 03-smart grid-the future of the electric power systempptWhitepaper 03-smart grid-the future of the electric power system
pptWhitepaper 03-smart grid-the future of the electric power system
avvariharish
 
REDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGE
REDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGEREDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGE
REDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGE
iQHub
 
Powi investor presentation may 2014
Powi investor presentation may 2014Powi investor presentation may 2014
Powi investor presentation may 2014
Irpowerintegrations
 

Similar to Micro-Generation Installations Your Way (20)

Smart power grid
Smart power gridSmart power grid
Smart power grid
 
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
 
Summer Study EE 120318
Summer Study EE 120318Summer Study EE 120318
Summer Study EE 120318
 
Restructuring Roundtable 10 28 11 Final
Restructuring Roundtable 10 28 11 FinalRestructuring Roundtable 10 28 11 Final
Restructuring Roundtable 10 28 11 Final
 
GIRES
GIRESGIRES
GIRES
 
Basic presentation
Basic presentationBasic presentation
Basic presentation
 
Smart Grid Technology
Smart Grid TechnologySmart Grid Technology
Smart Grid Technology
 
Standards for Autonomous and Secure Microgrids
Standards for Autonomous and Secure Microgrids 	Standards for Autonomous and Secure Microgrids
Standards for Autonomous and Secure Microgrids
 
Sgcp12 simon-farmpower
Sgcp12 simon-farmpowerSgcp12 simon-farmpower
Sgcp12 simon-farmpower
 
Baby Smart Grid 11/09
Baby Smart Grid 11/09Baby Smart Grid 11/09
Baby Smart Grid 11/09
 
5.13.15 board meeting grid modernization
5.13.15 board meeting   grid modernization5.13.15 board meeting   grid modernization
5.13.15 board meeting grid modernization
 
pptWhitepaper 03-smart grid-the future of the electric power system
pptWhitepaper 03-smart grid-the future of the electric power systempptWhitepaper 03-smart grid-the future of the electric power system
pptWhitepaper 03-smart grid-the future of the electric power system
 
Smart Grids from the perspective of the consumers
Smart Grids from the perspective of the consumers Smart Grids from the perspective of the consumers
Smart Grids from the perspective of the consumers
 
Ontario’s renewable energy, smart grid and EV policy
Ontario’s renewable energy, smart grid and EV policyOntario’s renewable energy, smart grid and EV policy
Ontario’s renewable energy, smart grid and EV policy
 
Megarevo PPT.pptx
Megarevo PPT.pptxMegarevo PPT.pptx
Megarevo PPT.pptx
 
The Benefits of Smart Grid Technology for Buildings, Cities, and Sustainability
The Benefits of Smart Grid Technology for Buildings, Cities, and SustainabilityThe Benefits of Smart Grid Technology for Buildings, Cities, and Sustainability
The Benefits of Smart Grid Technology for Buildings, Cities, and Sustainability
 
RECENT TRENDS IN MICRO GRIDS
     RECENT TRENDS IN MICRO GRIDS     RECENT TRENDS IN MICRO GRIDS
RECENT TRENDS IN MICRO GRIDS
 
New Uses For Electric Meters as We Continue to Leverage AMI Technology
New Uses For Electric Meters as We Continue to Leverage AMI TechnologyNew Uses For Electric Meters as We Continue to Leverage AMI Technology
New Uses For Electric Meters as We Continue to Leverage AMI Technology
 
REDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGE
REDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGEREDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGE
REDUCE PEAK DEMAND AT EV CHARGING WITH LOCAL BATTERY STORAGE
 
Powi investor presentation may 2014
Powi investor presentation may 2014Powi investor presentation may 2014
Powi investor presentation may 2014
 

Recently uploaded

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 

Recently uploaded (20)

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 

Micro-Generation Installations Your Way

  • 1. Micro- Generation Installations YOUR Way Rocky View County Joe Peters, Manager Service Development Allison Thomas, Stakeholder Relations Manager November 30, 2011 1/13/2012 1
  • 3. Wires Service Provider • Deliver safe and reliable electricity • Manage outages • Connect new customers • Manage metering data • Rates regulated by the Alberta Utilities Commission (AUC) • Micro-generation coordination 1/13/2012 3
  • 4. Micro-Generation Regulation • Issued by the Alberta Government in 2008 • The AUC oversaw implementation and developed processes to simplify approvals 1/13/2012 4
  • 5. Connecting YOUR Project • 128 generators have signed interconnection agreements with FortisAlberta since 2009. Micro-generation 1/13/2012 5
  • 6. Micro-Generation To qualify as a micro-generator the generating unit must… • Use renewable or alternative energy technologies or higher efficiency fossil fuels • Have a generating capacity smaller than one megawatt • Produce electricity primarily for the customer’s own use 2-4 kW 600 kWh per month 1/13/2012 6
  • 7. Installations • Mini MG Inverter-based o 10 kW and smaller • Small MG o 0 kW to 150 kW (excludes Mini MG) • Large MG o Greater than 150 kW and less than 1 MW Footer Text 1/13/2012 7
  • 8. Mini Micro-Generator • Capacity < 10 kW • Equipped with a grid-tie inverter o Changes DC to AC o AC compatible with distribution system o Provides safety features 1/13/2012 8
  • 9. Steps to get your project started! Step 5 – Submit application to FortisAlberta Step 4 - Prepare a site plan and electric single-line diagram Step 3 - Get municipal permits Step 2 - Consult with an electrical contractor Step 1 (optional) - Inform FortisAlberta of your plan to install a micro- generator 1/13/2012 9
  • 10. Application & Guidelines Footer Text 1/13/2012 10
  • 11. Supporting Documents • Electrical single-line diagram • Site plan - where the MG will be located • Electrical permit 1/13/2012 11
  • 12. FortisAlberta’s Role • Process and approve application • Interconnection agreement • Install bi-directional meter • Meter info to Retailer 1/13/2012 12
  • 13. Only YOU have the power to monitor and control the energy you use. FortisAlberta wants to help
  • 14. Save Energy! Save Money! • Public library power monitor program • Community education programs • Energy efficiency resources • Alberta OnFarm program http://www.onfarmenergy.ca/
  • 15. Visit us online at www.fortisalberta.com Phone us 403-310-WIRE or email micro-gen@fortisalberta.com Phone us 403-310-WIRE or email energyyourway@fortisalberta.com 1/13/2012 15

Editor's Notes

  1. 1.8 kW array
  2. Typical home-based installations - Mini MG Invert-base-10 kW and smallerOther categories for distributed generation:Small MG 0 kW to 150 kW (excluding Mini MG)Large MG Greater than 150 kW and less than 1 MWThere are three classes of MG but for this presentation I will concentrate on the Mini-MG.This I believe will be the largest number of generators.Usually residential, acreages, farms and small business are Mini-Micro Generation
  3. Step-by step guideProvides information on the construction, safety requirements etc.A place to start familiarizing yourself with micro-generation connection is on the Alberta Utilities Commission web-site and the micro-generator Application GuidelinesAlso on the web-site are the micro-generator Regulation and Rule 024 “Rules respecting micro-generation”Legal land description (SE-15-30-01-W5)Site id (0040 plus 9 additional numbers)LocationRetailerGenerator type (solar, wind, hydro, biomass)Generator to utility interface (inverter, non inverter, induction, synchronous)Electrical loadAnnual usageDoes your generator…Satisfy Anti-Islanding Clause CSA C22.2 No. 107-1?Meet the micro-generator regulation for renewable or alternate energy definition?Require bi-direction interval metering (mini or small MG only)?
  4. An example of the single line diagram is in the Application Guideline. How will the generated be interconnect to the electric distribution system?Site plan is usually for wind turbines, the location of the wind turbine to buildings and FortisAlberta power lines.Normally when application is submitted the electrical permit for the project is not complete and the final permit is not available yet. The final electrical permit triggers the request internally in Fortis to have the meter changed.Applicant’s signature should be the land ownerDate you sent the application.
  5. Reference number is how FortisAlberta tracks the project. If you know the reference number it is useful to use this number when talking to FortisAlberta. The number is issued after the first contact (application) with the customer.Generators larger than 150 kW require an AESO Asset Id. FortisAlberta will arrange for the Asset Id.Who received the application at FortisAlberta.Interconnection line is important to FortisAlberta and AUC to show location of generator on the distribution system.Is the MG approved under the MG Regulations if not then FortisAlberta must inform you and tell you why.If all the information submitted is correct, the interconnection agreement is signed, and the final electrical permit is sent to FortisAlberta, the micro-generator is ready for interconnection to the grid.For each 10 to 12 inquires 1 application is submitted once an application is submitted they usually proceed to interconnection
  6. FortisAlberta is available to answer any questions and help customers through the process.1.2 kW wind