Con Edison implemented storm hardening initiatives following Superstorm Sandy to increase the resiliency of its electric system. Immediate hardening was completed by June 2013 and included flood barriers, pumps, and sealing equipment at 9 substations and 3 generating stations. A $1 billion, multi-year storm hardening program was proposed to continue hardening efforts through 2017. This includes raising critical equipment, backup generators, robust walls and doors, and new control systems to protect against flooding up to FEMA's 100-year flood level plus 3 feet. Con Edison collaborated with regulators and stakeholders to review risks and justify storm hardening projects.
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
ย
11LucianoVillani_NICHI_BusinessSummit
1. Storm Hardening Initiatives at
Con Edison
May 7th, 2014
Luciano Villani
Department Manager, Project
Engineering, Con Edison
2. Network Systems Non-Network Systems
Generating Station
(electricity generated at
13.8 to 22.0 kV)
Transmission
Substation
Area Substation
(voltage stepped down to
primary distribution
voltage)
Transformers
(voltage stepped
down to 480, 208,
or 120 V)
Feeders
Con Edison Overview
2
3. Super Storm Sandy Statistics
โข Largest Atlantic storm on
record spanning 1,000 miles
โข Impacted over 8.5 million
customers across 21 states
โข Sustained winds reached
64 mph at LaGuardia Airport
with peak gust of 90 mph
on Staten Island
โข 14.06 foot storm tide
recorded at Battery Park
4. Super Storm Sandy Impact to Con Edison
โข 1.1 million customer outages
โข Lost 4,000 MW of generation
โข 60% of 345 kV feeders lost
โข 5 transmission substations
โ 11 Manhattan networks
โ 3 Staten Island area stations
โข 2 steam stations and 561
steam customers impacted
โข 398 gas services interrupted
4
5. Con Edison Response
โข Service Restoration โ restore service as quickly as possible
โข System Normalization โ repair equipment damage
โข Site Assessments
โ Multidiscipline engineering teams visited all impacted stations
โ Identification of critical impacted equipment and water infiltration
โ Conceptual storm hardening scopes and estimates
โข Immediate Storm Hardening (June 1, 2013)
โข Long-Term Storm Resiliency
5
6. Sandy Aftermath Timeline
Oct 2012 Jan 2013 Apr 2013 July 2013 Oct 2013 Jan 2014
Sandy
Hits
Normalization
Immediate/Phase 1 Storm
Hardening
Phase 2 (thru 2017)
6
June 1, 2013 โ
Construction Complete
9. Immediate Hardening Scope
June 1st, 2013
๏ง New walls/barriers around critical equipment
๏ง New sump pumps
๏ง Sealed conduit penetration points with RTV
๏ง Shrink wrap important control boxes
๏ง Install backup nitrogen pumps
๏ง Raised equipment where feasible and economic
๏ง Valve-off sewer drains
Governing flood control elevation, higher of:
1. SLOSH 2010
2. 2007 FEMA 100-yr flood +2 feet
3. Witnessed Sandy level
Breaker
Disconnect
PotheadStand
Breaker
Relay
House
Control
Room Pumping
Plant
Power line
Control/protection line(s)
Oil line
Terminal box
Insulator To Distribution
From Transmission
Power
Transformer
Flood Control
Elevation
Disconnect
PotheadStand
Sandy Flood
Elevation
Sewer Drain
10. June 1, 2013
Accomplishments
โข Work completed at 9 Substations
and 3 Generating Stations
โ 54 new concrete moats (6100 LF)
โ 210 flood doors and barriers
โ 81 submersible pumps
โ 21 high capacity diesel pumps
โ Approx. 3000 conduit and trough
seals
10
11. Con Edison Rate Case & Collaborative
โข Filed January 2013
โข All 3 commodities (Electric, Steam & Gas)
โข Storm Hardening Program
โ $1 billion Company-wide
โ Projects span 2014 โ 2017
โข Storm Hardening Collaborative
โ Cooperation among all interested rate case parties
โ Risk prioritization and project justification
11
12. Collaborative Activities
โข Collaborative Parties
โ PSC, NYC, Attorney General,
Utility Intervention Unit, EDF,
Columbia Center for Climate
Change, Local 1-2
โข Benchmarking
โ United Illuminating
โ PSE&G
โ Brooklyn Navy Yard
โ NYC MTA
โ Swedish Delegation
โข With Collaborative
โ 8 meetings and 2 field visits
โ 3 detailed presentations
โ 32 technical and economic
questions/information
requests
โ 11 order of magnitude
estimates
โ Established flood control
criteria (FEMA 100yr + 3โ)
โ Ongoing meetings
12
13. Next Steps โ Phase 2 Storm Hardening
โข More robust walls, doors and
barriers
โข Additional pumps with redundant
feeds
โข Backup generators
โข Raise or relocate critical equipment
โข New control room and automation
system
13
2013 Flood
Protection Level
0-8
Feet
New Flood
Protection Level 3-4
Feet
Design Standard: FEMA 100 year flood level + 3 feet
(design level re-examined every five years)
14. Goethals โ Proposed Perimeter Wall
Before & After
14
โข Interlocking metal
sheet pile wall.
โข 25 feet below grade
โข 10 feet above grade
15. New Control Room & Lifting Electrical
Panels
15
Digital HMI and
Automation System
High pressure Rankine units. Truncated combined cycle (gas turbine feeding
345kV transformer with a tertiary winding that went into a flooded breaker.
This is the prototype of the moveable relay panel that is installed in the 13th St. millyard.
This was designed and built in the Van Nest Shop. During normal operations, the panel will be at an accessible level for personnel. During the storm preparation it can be mechanically raised to a safe height out of the water.