SlideShare a Scribd company logo
1 of 3
John Paul Hitt
ELECTRICALSUPERINTENDENT
Summary:
John has over 28 years of in Industrial Construction to include Power Generation, Transmission, Pharmaceutical,
Food Process, Textile, and General Manufacturing Plants. Throughout these 28 years John has been driven to
foster a work environment where Quality and Safety are paramount. John has strived to build a safety culture
within his numerous teams that has allowed him to achieve a ZERO recordable rate for his employees. Obtaining
his unlimited electrical licenses has allowed him the opportunity to “do things the right the first time” which in turn
has reduced the risk and improved the quality of each of the projects he has supervised. The following is a
detailed breakdown of some of the major projects.
Professional Experience: While working with Crowder Industrial Construction below is a
list of Projects which most was at Duke Energy Site’s
05/13 – Present Duke Energy – Marshall Steam Station
Project Superintendent (Multiple Sites)
Currently providing management for:
 Coal dust mitigation for replacement of all affected electrical equipment from an
unprotected system to a class 2 div 1 and div 2 location.
 The Dan River de-coupling project, installation of a new PDC building, Motor
Control Center, and Relays.
 Flue Gas Desulphurization drawing and panel label upgrade.
 Marshall Unit 4 Generator outage to replace multiple Motor Control Centers with
Arch Flash Rated Motor Control Centers.
 Marshall Unit 4 GE voltage regulator upgraded with New Basler
 Marshall Unit 4 Generator Relay upgrade. Replaced all mechanical relays with
SEL and BECKWITH. Also installed new digital fault recorder.
 Installation of Activated Carbon Injection system for Unit 4 which consists of
installing 75 foot Silo to include all conveyance piping to duct, Installation of
switch gear and all associated electrical interface including new DCS and MCC
installation.
Duke - Walters Hydro Station
Electrical Superintendent
Review and plan for 2015 upgrade with new Motor Control Centers, Switchgear, PLC
upgrade, and Mechanical Relays to be replaced with new SEL.
11/12 – 05/13 Duke Energy – Marshall Steam Station Unit 3
Electrical Superintendent
 Relocated 575 volt critical loads from MCC-G, MCC-D, MCC-E
 Replaced 575 Motor Control Centers G,D,E
 Replaced Unit 3 voltage regulator with a new BASLER.
 Removed all mechanical relays on Unit 3 gen and upgrade them with SEL and
BECKWITH type relay.
 Installed digital fault recorder on Unit 3
11/10 – 11/12 Duke Energy – Alliance
Electrical Superintendent
Provided management of miscellaneous electrical projects with in the Duke Energy
Carolina’s Fossil and Hydro Fleet. Projects included but not limited to Coal Tunnel
Reclassification Upgrade, Substation Transformer Change Outs, 13.8 Switchgear
Change Out, Excitation Systems, Flue Gas Detection, Cliffside plant electrical systems
verification, along with ongoing maintenance, outages and instrument tech support.
04/10 – 11/10 Duke Energy - Marshall Steam Station - 230KV
Electrical Superintendent
Installation of a duct bank, grounding system, setting 4 each 242kv breakers, reworking
the overhead distribution lines and 5” 230kv bus systems, ground disconnect switches,
lock out relays, 125 volt DC system. The installation was completed systematically in an
energized 230kv switchyard.
12/09 – 04/10 Duke Energy - Cliffside Steam Station - Unit 5 Control Room Upgrade
Electrical Superintendent
Control room was upgraded from the existing PLC system to updated DCS.
Modifications included relocating 4000 wire terminations which had to be individually
tracked down and identified due to the condition of the existing drawings. This project
required extensive coordination between engineering, the client, and the construction
team. The majority of the research and tracing of conductors was completed pre-outage.
12/09 – 04/10 Duke Energy - Cliffside Steam Station - Unit 5 BFP
Electrical Superintendent
Installation of a new lube oil pressure system from an HPU, self-shut down systems with
oil pressure system failure and emergency pump system as a backup.
10/09 – 11/09 Duke Energy - Buck Steam Station
Electrical Superintendent
Upgrade Soot/Bottom Ash Controls, removed PLC program system and replaced with
new DCS system. Two week plant outage. This was coordinated with the owner to
maximize pre outage work.
06/08 – 09/09 Duke Energy - Allen Steam Station - Dry Ash Conversion
Electrical Superintendent
Electrical Superintendent for installing a new Dry Ash self-conveying system that would
move ash from the hoppers through feeders then out to the 2 silo’s about 1000ft away,
which was then remotely dumped into awaiting trucks for transport. This work included
installing new Electrical Equipment: 13.8kv transformer, 4.160kv switchgear, 4.160kv air
compressor PDC building, and a 480v Motor Control Center. Installation of over 153,955
feet of cable, 33,200 feet of conduit/cable tray installed, and over 12,000 terminations.
03/09 – 08/09 Duke Energy - Allen Steam Station - Ash Landfill
Electrical Superintendent
Electrical Superintendent for which is monitoring the run off of water thru filter traps from
the Ash pile. Installed two auto control center, with auto transfer switches, pump control
panels, 112kv transformers, and new 600volt buckets in MCC, 44, 045 feet of wire
installed, 4360 feet of duck bank.
05/09 – 07/09 Fence Grounding - Belmont, NC
Electrical Superintendent
Electrical Superintendent for installing over 10,000 feet of bare copper wire making
connection every 50ft of liner fence, installing isolators where fence crossed under 100kv-
230kv distribution lines. Installed 9,500 feet of new fencing.
10/08 – 02/09 Duke Energy - Steam Station - UPS Building
Electrical Superintendent
Electrical Superintendent for the installation of new ups system that is for the 125vdc
power for the 13.8 switchgear which is the main power supply from the dry ash system
and the FGD system.
05/08 – 10/08 Iverster - Piedmont, SC
Electrical Superintendent
Electrical Superintendent for the Spartanburg Waste Water Treatment Plant
2004 – 2007 Fountain Electric - Forest City, NC
Electrical Superintendent
Electrical Superintendent for the Berea High school and Hubbell Lighting Building
1993 – 2004 Huntington & Guerry- Greenville, SC
Electrical Superintendent
Electrical Superintendent for numerous projects, to include: Cotton Mills all over the
southeast, BMW Plant in Greer SC, Naval Air Station in Cherry Point, NC,
Pharmaceutical Plant in Greenwood SC, and Food Processing Plant in SC.
Education / Training / Certifications:
1986 – 1993 United States of America Navy Sea Bee
Electrician
Electrician for overhead distribution systems.
Electrical Class “A” Certification
Electronics Certification
Generator training
Licenses:
NC Unlimited Electrical
VA Unlimited Electrical

More Related Content

What's hot

Moore_S_25.10.13
Moore_S_25.10.13Moore_S_25.10.13
Moore_S_25.10.13Moore Sarah
 
Larry Hebert Resume
Larry Hebert ResumeLarry Hebert Resume
Larry Hebert ResumeLarry Hebert
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...McKenney's Inc
 
Promotional Sheet - Grand Mound
Promotional Sheet - Grand MoundPromotional Sheet - Grand Mound
Promotional Sheet - Grand MoundLinda Burman
 
Power+Generation+Project+-+Melbourne
Power+Generation+Project+-+MelbournePower+Generation+Project+-+Melbourne
Power+Generation+Project+-+MelbourneJohn Rimac
 
Centralized Management, Controlled Savings
Centralized Management, Controlled SavingsCentralized Management, Controlled Savings
Centralized Management, Controlled SavingsDon Talend
 
Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...
Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...
Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...Murray Edington
 
Michael Dunlap Resume - 2016
Michael Dunlap Resume - 2016Michael Dunlap Resume - 2016
Michael Dunlap Resume - 2016Michael Dunlap
 
Delivering Turnkey Energy Savings
Delivering Turnkey Energy SavingsDelivering Turnkey Energy Savings
Delivering Turnkey Energy SavingsMcKenney's Inc
 
Gas Turbine Generators Control System Philippines
Gas Turbine Generators Control System PhilippinesGas Turbine Generators Control System Philippines
Gas Turbine Generators Control System PhilippinesUmar Muhammad
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017Dex Bugariu
 
ASSET Project Engineer
ASSET Project EngineerASSET Project Engineer
ASSET Project EngineerMike Yost
 
CEP-SwitchgearRetrofill Upgrade SellSheet
CEP-SwitchgearRetrofill Upgrade SellSheetCEP-SwitchgearRetrofill Upgrade SellSheet
CEP-SwitchgearRetrofill Upgrade SellSheetBrian V. Wilson
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...AMI GE International
 
Special AKOTRACE® Electrical Heat Tracing Solution for Gemasolar Solar Power...
Special AKOTRACE®  Electrical Heat Tracing Solution for Gemasolar Solar Power...Special AKOTRACE®  Electrical Heat Tracing Solution for Gemasolar Solar Power...
Special AKOTRACE® Electrical Heat Tracing Solution for Gemasolar Solar Power...ako_corporate
 
Derek Smith CV. 02.09.16
Derek Smith CV. 02.09.16Derek Smith CV. 02.09.16
Derek Smith CV. 02.09.16Derek Smith
 
LEED_NC and LEED_EB
LEED_NC and LEED_EBLEED_NC and LEED_EB
LEED_NC and LEED_EBArn Akbarieh
 
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...IRJET Journal
 

What's hot (19)

Moore_S_25.10.13
Moore_S_25.10.13Moore_S_25.10.13
Moore_S_25.10.13
 
Larry Hebert Resume
Larry Hebert ResumeLarry Hebert Resume
Larry Hebert Resume
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
 
Promotional Sheet - Grand Mound
Promotional Sheet - Grand MoundPromotional Sheet - Grand Mound
Promotional Sheet - Grand Mound
 
Power+Generation+Project+-+Melbourne
Power+Generation+Project+-+MelbournePower+Generation+Project+-+Melbourne
Power+Generation+Project+-+Melbourne
 
Centralized Management, Controlled Savings
Centralized Management, Controlled SavingsCentralized Management, Controlled Savings
Centralized Management, Controlled Savings
 
Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...
Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...
Evaluation and efficiency comparison of front end ac dc plug-in hybrid charge...
 
Michael Dunlap Resume - 2016
Michael Dunlap Resume - 2016Michael Dunlap Resume - 2016
Michael Dunlap Resume - 2016
 
Delivering Turnkey Energy Savings
Delivering Turnkey Energy SavingsDelivering Turnkey Energy Savings
Delivering Turnkey Energy Savings
 
Gas Turbine Generators Control System Philippines
Gas Turbine Generators Control System PhilippinesGas Turbine Generators Control System Philippines
Gas Turbine Generators Control System Philippines
 
Prsn
PrsnPrsn
Prsn
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017
 
ASSET Project Engineer
ASSET Project EngineerASSET Project Engineer
ASSET Project Engineer
 
CEP-SwitchgearRetrofill Upgrade SellSheet
CEP-SwitchgearRetrofill Upgrade SellSheetCEP-SwitchgearRetrofill Upgrade SellSheet
CEP-SwitchgearRetrofill Upgrade SellSheet
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
 
Special AKOTRACE® Electrical Heat Tracing Solution for Gemasolar Solar Power...
Special AKOTRACE®  Electrical Heat Tracing Solution for Gemasolar Solar Power...Special AKOTRACE®  Electrical Heat Tracing Solution for Gemasolar Solar Power...
Special AKOTRACE® Electrical Heat Tracing Solution for Gemasolar Solar Power...
 
Derek Smith CV. 02.09.16
Derek Smith CV. 02.09.16Derek Smith CV. 02.09.16
Derek Smith CV. 02.09.16
 
LEED_NC and LEED_EB
LEED_NC and LEED_EBLEED_NC and LEED_EB
LEED_NC and LEED_EB
 
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
Changing Role of Coal-Fired Power Plants: From Base Load Operation to Flexibl...
 

Viewers also liked

Condiciones dignas de trabajo
Condiciones dignas de trabajoCondiciones dignas de trabajo
Condiciones dignas de trabajoEveAlvarez12
 
crear y armacenar datos en la nubes
crear y armacenar datos en la nubescrear y armacenar datos en la nubes
crear y armacenar datos en la nubestelcida
 
So sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiên
So sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiênSo sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiên
So sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiênjin1020
 
abaout Designer Karim Rashid
abaout Designer Karim Rashidabaout Designer Karim Rashid
abaout Designer Karim Rashid규용 이
 
Anatomi dan morfologi tumbuhan
Anatomi dan morfologi tumbuhanAnatomi dan morfologi tumbuhan
Anatomi dan morfologi tumbuhanJuna Edi
 

Viewers also liked (9)

Condiciones dignas de trabajo
Condiciones dignas de trabajoCondiciones dignas de trabajo
Condiciones dignas de trabajo
 
Power of Choice
Power of ChoicePower of Choice
Power of Choice
 
Presentación1
Presentación1Presentación1
Presentación1
 
crear y armacenar datos en la nubes
crear y armacenar datos en la nubescrear y armacenar datos en la nubes
crear y armacenar datos en la nubes
 
Jueces de paz
Jueces de pazJueces de paz
Jueces de paz
 
So sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiên
So sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiênSo sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiên
So sánh cương lĩnh chính trị đầu tiên và luận cương chính trị đầu tiên
 
abaout Designer Karim Rashid
abaout Designer Karim Rashidabaout Designer Karim Rashid
abaout Designer Karim Rashid
 
Publications
PublicationsPublications
Publications
 
Anatomi dan morfologi tumbuhan
Anatomi dan morfologi tumbuhanAnatomi dan morfologi tumbuhan
Anatomi dan morfologi tumbuhan
 

Similar to John Paul Hitt 10-20-2015

Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1Holland Kendall
 
JOE FAIN RESUME 8-8-15
JOE FAIN RESUME 8-8-15JOE FAIN RESUME 8-8-15
JOE FAIN RESUME 8-8-15Joe Fain
 
Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016Sher Chuhan
 
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks
 
TERRY A EVANS RESUME Inspection 07-22-2016
TERRY A EVANS RESUME Inspection 07-22-2016TERRY A EVANS RESUME Inspection 07-22-2016
TERRY A EVANS RESUME Inspection 07-22-2016Terry Evans
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Dennis Kehoe
 
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017Dex Bugariu
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017Dex Bugariu
 
John Hopwood Resume
John Hopwood ResumeJohn Hopwood Resume
John Hopwood ResumeJohn Hopwood
 
JAMES MICHAEL STULTS_RESUME
JAMES MICHAEL STULTS_RESUMEJAMES MICHAEL STULTS_RESUME
JAMES MICHAEL STULTS_RESUMEJames Stults
 
JaxSmith Resume
JaxSmith  ResumeJaxSmith  Resume
JaxSmith ResumeJack Smith
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futurejames hamilton
 
Livewire Automation Daandine Expansion Project
Livewire Automation Daandine Expansion ProjectLivewire Automation Daandine Expansion Project
Livewire Automation Daandine Expansion ProjectPeter Walsh
 

Similar to John Paul Hitt 10-20-2015 (20)

Resume Y
Resume YResume Y
Resume Y
 
Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1
 
JOE FAIN RESUME 8-8-15
JOE FAIN RESUME 8-8-15JOE FAIN RESUME 8-8-15
JOE FAIN RESUME 8-8-15
 
Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
 
C.v. p maidens
C.v. p maidensC.v. p maidens
C.v. p maidens
 
TERRY A EVANS RESUME Inspection 07-22-2016
TERRY A EVANS RESUME Inspection 07-22-2016TERRY A EVANS RESUME Inspection 07-22-2016
TERRY A EVANS RESUME Inspection 07-22-2016
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015
 
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
 
resume
resumeresume
resume
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017
 
BugariuDex Resume _ 2017
BugariuDex Resume _ 2017BugariuDex Resume _ 2017
BugariuDex Resume _ 2017
 
John Hopwood Resume
John Hopwood ResumeJohn Hopwood Resume
John Hopwood Resume
 
Rich Mathias CV 2016
Rich Mathias CV 2016Rich Mathias CV 2016
Rich Mathias CV 2016
 
JAMES MICHAEL STULTS_RESUME
JAMES MICHAEL STULTS_RESUMEJAMES MICHAEL STULTS_RESUME
JAMES MICHAEL STULTS_RESUME
 
JaxSmith Resume
JaxSmith  ResumeJaxSmith  Resume
JaxSmith Resume
 
gamal ghazy svc
gamal ghazy svcgamal ghazy svc
gamal ghazy svc
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-future
 
Livewire Automation Daandine Expansion Project
Livewire Automation Daandine Expansion ProjectLivewire Automation Daandine Expansion Project
Livewire Automation Daandine Expansion Project
 

John Paul Hitt 10-20-2015

  • 1. John Paul Hitt ELECTRICALSUPERINTENDENT Summary: John has over 28 years of in Industrial Construction to include Power Generation, Transmission, Pharmaceutical, Food Process, Textile, and General Manufacturing Plants. Throughout these 28 years John has been driven to foster a work environment where Quality and Safety are paramount. John has strived to build a safety culture within his numerous teams that has allowed him to achieve a ZERO recordable rate for his employees. Obtaining his unlimited electrical licenses has allowed him the opportunity to “do things the right the first time” which in turn has reduced the risk and improved the quality of each of the projects he has supervised. The following is a detailed breakdown of some of the major projects. Professional Experience: While working with Crowder Industrial Construction below is a list of Projects which most was at Duke Energy Site’s 05/13 – Present Duke Energy – Marshall Steam Station Project Superintendent (Multiple Sites) Currently providing management for:  Coal dust mitigation for replacement of all affected electrical equipment from an unprotected system to a class 2 div 1 and div 2 location.  The Dan River de-coupling project, installation of a new PDC building, Motor Control Center, and Relays.  Flue Gas Desulphurization drawing and panel label upgrade.  Marshall Unit 4 Generator outage to replace multiple Motor Control Centers with Arch Flash Rated Motor Control Centers.  Marshall Unit 4 GE voltage regulator upgraded with New Basler  Marshall Unit 4 Generator Relay upgrade. Replaced all mechanical relays with SEL and BECKWITH. Also installed new digital fault recorder.  Installation of Activated Carbon Injection system for Unit 4 which consists of installing 75 foot Silo to include all conveyance piping to duct, Installation of switch gear and all associated electrical interface including new DCS and MCC installation. Duke - Walters Hydro Station Electrical Superintendent Review and plan for 2015 upgrade with new Motor Control Centers, Switchgear, PLC upgrade, and Mechanical Relays to be replaced with new SEL. 11/12 – 05/13 Duke Energy – Marshall Steam Station Unit 3 Electrical Superintendent  Relocated 575 volt critical loads from MCC-G, MCC-D, MCC-E  Replaced 575 Motor Control Centers G,D,E  Replaced Unit 3 voltage regulator with a new BASLER.  Removed all mechanical relays on Unit 3 gen and upgrade them with SEL and BECKWITH type relay.  Installed digital fault recorder on Unit 3 11/10 – 11/12 Duke Energy – Alliance Electrical Superintendent Provided management of miscellaneous electrical projects with in the Duke Energy Carolina’s Fossil and Hydro Fleet. Projects included but not limited to Coal Tunnel Reclassification Upgrade, Substation Transformer Change Outs, 13.8 Switchgear
  • 2. Change Out, Excitation Systems, Flue Gas Detection, Cliffside plant electrical systems verification, along with ongoing maintenance, outages and instrument tech support. 04/10 – 11/10 Duke Energy - Marshall Steam Station - 230KV Electrical Superintendent Installation of a duct bank, grounding system, setting 4 each 242kv breakers, reworking the overhead distribution lines and 5” 230kv bus systems, ground disconnect switches, lock out relays, 125 volt DC system. The installation was completed systematically in an energized 230kv switchyard. 12/09 – 04/10 Duke Energy - Cliffside Steam Station - Unit 5 Control Room Upgrade Electrical Superintendent Control room was upgraded from the existing PLC system to updated DCS. Modifications included relocating 4000 wire terminations which had to be individually tracked down and identified due to the condition of the existing drawings. This project required extensive coordination between engineering, the client, and the construction team. The majority of the research and tracing of conductors was completed pre-outage. 12/09 – 04/10 Duke Energy - Cliffside Steam Station - Unit 5 BFP Electrical Superintendent Installation of a new lube oil pressure system from an HPU, self-shut down systems with oil pressure system failure and emergency pump system as a backup. 10/09 – 11/09 Duke Energy - Buck Steam Station Electrical Superintendent Upgrade Soot/Bottom Ash Controls, removed PLC program system and replaced with new DCS system. Two week plant outage. This was coordinated with the owner to maximize pre outage work. 06/08 – 09/09 Duke Energy - Allen Steam Station - Dry Ash Conversion Electrical Superintendent Electrical Superintendent for installing a new Dry Ash self-conveying system that would move ash from the hoppers through feeders then out to the 2 silo’s about 1000ft away, which was then remotely dumped into awaiting trucks for transport. This work included installing new Electrical Equipment: 13.8kv transformer, 4.160kv switchgear, 4.160kv air compressor PDC building, and a 480v Motor Control Center. Installation of over 153,955 feet of cable, 33,200 feet of conduit/cable tray installed, and over 12,000 terminations. 03/09 – 08/09 Duke Energy - Allen Steam Station - Ash Landfill Electrical Superintendent Electrical Superintendent for which is monitoring the run off of water thru filter traps from the Ash pile. Installed two auto control center, with auto transfer switches, pump control panels, 112kv transformers, and new 600volt buckets in MCC, 44, 045 feet of wire installed, 4360 feet of duck bank. 05/09 – 07/09 Fence Grounding - Belmont, NC Electrical Superintendent Electrical Superintendent for installing over 10,000 feet of bare copper wire making connection every 50ft of liner fence, installing isolators where fence crossed under 100kv- 230kv distribution lines. Installed 9,500 feet of new fencing.
  • 3. 10/08 – 02/09 Duke Energy - Steam Station - UPS Building Electrical Superintendent Electrical Superintendent for the installation of new ups system that is for the 125vdc power for the 13.8 switchgear which is the main power supply from the dry ash system and the FGD system. 05/08 – 10/08 Iverster - Piedmont, SC Electrical Superintendent Electrical Superintendent for the Spartanburg Waste Water Treatment Plant 2004 – 2007 Fountain Electric - Forest City, NC Electrical Superintendent Electrical Superintendent for the Berea High school and Hubbell Lighting Building 1993 – 2004 Huntington & Guerry- Greenville, SC Electrical Superintendent Electrical Superintendent for numerous projects, to include: Cotton Mills all over the southeast, BMW Plant in Greer SC, Naval Air Station in Cherry Point, NC, Pharmaceutical Plant in Greenwood SC, and Food Processing Plant in SC. Education / Training / Certifications: 1986 – 1993 United States of America Navy Sea Bee Electrician Electrician for overhead distribution systems. Electrical Class “A” Certification Electronics Certification Generator training Licenses: NC Unlimited Electrical VA Unlimited Electrical