SlideShare a Scribd company logo
1 of 64
The Construction Project
Manager’s Modern Toolbelt
How Technology & Creativity
Enable Successful Project Delivery
Webinar Series
Private and Public Partnerships
Move Mainstream
Greg Fitch
August 16, 2016
Private and Public Partnerships
Move Mainstream
Greg Fitch
August 16, 2016
WPI Department of Civil Engineering ‘98
Columbia University Department of Civil
Engineering – PhD Candidate
Greg Fitch
August 16, 2016
Project Controls Lead Analyst
Construction & Procurement in New York City
Private and Public Partnerships
Move Mainstream
PUBLIC-PRIVATE-PARTNERSHIPS (PPP OR P3)
1. Characteristics of PPPs
2. Overview of P3 Project Finance Structures
3. Common Aspects P3 Project Agreements
4. Project Risks & Project Procurement Process
5. PPP Financial Markets, Structure & Model
Traditional and Alternative
Procurement Methods Defined
Design-Build – Owner uses a competitive proposal process to contract with a
private entity to design and build a project.
Design-Build-Operate – Owner uses a competitive proposal process to
contract with a private entity to design and build a project but also adds
operations to the DB Foundation.
Design-Bid-Build – Traditional method in which the agency or owner
contracts with separate entities for the design and construction of a project.
CHARACTERISTICS OF PPPS
DBFO or Public-Private-Partnership
Procurement Method Defined
Design-Build-Finance-Operate or Public-Private-Partnerships (PPP or
P3):
Owner uses a competitive proposal process to contract with a private
consortium to finance, design, construct, maintain and operate a
facility and / or build a project.
Congressional Budget Office (2012)
Variety of alternative arrangements for Projects that transfer more of the risk associated with
control of the project to the private sector.
Dr. Michael J. Garvin (May – June 2011 edition of TR News)
Long-term contractual arrangements between public and private partners for the creation and
enhancement of assets, bundled together with the provision of services and capital financing
through a private entity.
FHWA – Office of Innovative Project Delivery
Contractual agreements between a public agency and a private entity that allow for greater
private participation in the delivery of transportation projects. Participation involves the
private sector taking on additional project risks, such as design, finance, long-term operation,
and traffic revenue.
Why Public-Private Projects Relevant?
• ALTERNATIVE PROJECT DELIVERY METHODS
─ Solution to Resolve Investment Deficits in Infrastructure
• CENTRAL GOAL OF P3 PROJECTS
─ Alleviate Government Budgets with Funding Provided by External
Financiers. (Algarni et al. 2007)
• P3 PROJECTS INCLUDE EQUITY SPONSORS
─ Most Capable of Managing Financial Risk & Owner-like Responsibility
w/out Actually Transferring Ownership. (Culp 2011)
PPP VS. TRADITIONAL DELIVERY
• Private Perspective • Public Perspective
• Service-Oriented Delivery
Model
• Large Scope & Long-term
Contracts
• High Priority Projects
• Optimize vs. Maximum Risk
Allocation
• Opportunities for Stable
Investment
• Public Need & Benefits
─ Local, Regional & State
─ Reliable & Safe Infrastructure
Procurement
─ Traffic Congestion Relief
─ Electrical Power Demands
─ Other Public Use Needs
• Financial Feasibility
─ Alleviate Government
Budgets
─ Better Value for Money
─ Market Demand for Projects
CHARACTERISTICS OF PPPs
• PROJECT SPECIFIC CONTRACT INCLUDES:
─ Significant New Capital Expenditures [large EPC or DB contracts]
─ Long-term O&M Responsibilities
─ Private Financing Allows Public Funds To Be Used On Other Projects
─ Project Specific Revenue Source
• PUBLIC PERCEPTION OF “PRIVATIZATION”:
─ Convey Ownership of Public Assets Transferred to Private Sector
─ Rely on Private Sector to Provide Services Formerly Provided by
Public Owner or Agency
─ Project May Not Require or Support Private Financing Based on
Generated Revenues
• Three Main Models for Project Agreements:
• Offtake Contract (i.e. Process-plant Project):
─ The Project Company produces a product and sells it to an Offtaker.
• Concession Agreement (i.e. Toll Road Project):
─ The Project Company provides a public service, and collects User
Charges.
• Availability-based Contract (i.e. PFI Model):
─ Contracting Authority pays a Project Company for making a project
available for use.
OVERVIEW OF P3 PROJECT FINANCE STRUCTURES
Project-Finance Structures
• Process-Plant Projects:
─ Projects where there is an input at one end of the project, which goes
through a process within the project, and emerges as an output.
• Concession Projects:
─ Construction or refurbishment of public infrastructure with revenues
derived from tolls, fairs, or similar payments from by users.
• Private Finance Initiative Model:
─ Construction / Refurbishment of Public Buildings or other public
infrastructure with revenue derived from payments by a Contracting
Authority (CA).
Example of Project-Finance Structures
Process-plant Project
Investors
16 CE590 – P3 Project Financing
Finance
Lenders
Project-Finance DebtEquity
Government Electricity Distributor
Power Purchase AgreementOperating License
Project Company
Example of Project-Finance Structures
Process-plant Project - Subcontracts
17 CE590 – P3 Project Financing
Project Company
EPC Contract Fuel Supply
Contract
Operation &
Maintenance Contract
Construction
Contractor
Fuel
Supplier
O&M
Contractor
Process-Plant Project
• SOLAR PLANT PROJECT - Roserock (Project Company) will sell
the energy, capacity and green attributes to the City of Austin
based on the terms of the Power Purchase Agreement signed May
1, 2014.
KEY TERMS VALUES
Effective Date 5/01/2014
Delivery Term 20 years
Expected Capacity (which may not be modified by
RE Roserock to change by +/- five percent)
150 MW
Maximum AC Output 150 MW
Minimum Capacity 140 MW
Contract Price ($/MWh)
$44.95 (no
escalation)
Process Plant Project
Holdings
Company “A”
Short Term
Credit
Agreement
Longer Term
Credit Agreement
“Project
Company”
Project
Sponsors
Holdings
Company “B”
Project
Completion
Engineering &
Construction
Operations &
Maintenance
Funding
Funding
Purchase
Shares
Purchase & Sale Agreement Equity Related Contracts
Financial Lender
& Debt Related
Contracts
Initial Investors Other Investors
Other Investors
100%
Example of Project-Finance Structures
Toll-Road ConcessionInvestors
20 CE590 – P3 Project Financing
Finance
Lenders
Project-Finance DebtEquity
Contracting
Authority
Road Users
TollsConcession
Agreement
Project Company
Example of Project-Finance Structures
Toll-Road Concession - Subcontracts
21 CE590 – P3 Project Financing
Project Agreement
Design &
Build Contract
Toll Operation
Contract
Maintenance
Contract
Design & Build
Contractor
Toll
Operator
Maintenance
Contractor
Concession Project
• I-595 CORRIDOR ROADWAY IMPROVEMENTS
─ Located in Broward County Florida.
─ Opened to Traffic in 1989 – With Accelerated Traffic
─ Roadway Improvements includes Reconstruction and Widening of I-595
with various improvements to ramps, interchanges etc.
─ Private concessionaire designed, built, financed and will operate and
maintain project for 35 years.
─ $1.8 Billion (present value in 2009 dollars; a 5% discount Rate)
Example of Project-Finance Structures
Private Finance Initiative (PFI) Model
Investors
23 CE590 – P3 Project Financing
Finance
Lenders
Project-Finance DebtEquity
Project Company
Contracting
Authority
Project
Agreement
Example of Project-Finance Structures
PFI Model - Subcontracts
24 CE590 – P3 Project Financing
Project Agreement
Design &
Build Contract
Maintenance
Contract
‘Soft’ Services
Contract(s)
Design & Build
Contractor
Service
Provider(s)
Maintenance
Contractor
Project Finance Initiative Model Project
Fargo Moorhead Flood Diversion Channel
Red River Basin surrounding Fargo, ND & Moorhead, MN
─ Red River Basin & Diversion Authority (includes counties in ND and MN)
─ Increased Frequency and Severity of Floods
─ 30 mile wide Diversion Channel in ND w/ 150,000 acre-feet of
Upstream Staging
─ Federally Authorized in February 2016
─ USACE as a Demonstration Split Project Delivery Model
Fargo Moorehead Flood Diversion Channel
• FINANCIAL OVERVIEW & SPLIT PROJECT DELIVERY MODEL
1. USACE will deliver Southern Embankment and Related projects with
Multiple Design-Bid-Build Projects.
2. Diversion Authority will Deliver Channel & Associated Infrastructure
with Locally-led P3 delivery includes a combination of public and
private financing, leveraging state and local funding sources
• FARGO MOORHEAD FLOOD DIVERSION P3 FINANCIAL
OVERVIEW FOR DIVERSION CHANNEL
─ Project Delivery Method
• Design-Build-Finance-Operate-Maintain
─ Construction Funding
• Private financing (debt & equity) secured by P3 Consortium
• Diversion Authority will make Milestone Payments to P3 Consortium
─ Payment Structure for O&M Scope (30 -50 year term)
• Multiple Funding Sources to Meet Debt Service and O&M Payments include
State Appropriations, Sales Tax, Asses.
COMMON ASPECTS P3 PROJECT AGREEMENTS
Common Aspects of Project Agreements
• Contract Term
─ Useful Life of the Project
─ Term of Debt
─ Equity Return
• Payment Mechanism
─ Payment on Project Completion
─ Level Payments
─ Inflation Indexation
• Contract Monitoring by the Offtaker / Contracting Authority
─ Design, Construction and Operation
─ Subcontracts
─ Financing
Common Aspects of Project Agreements
• Performance Bonding and Other Guarantees
─ Offtaker / CA Requires a Performance Bond
─ Duplicates Lenders’ Requirements of Project Company
─ Project Company Incentive is to Generate Revenue
• Compensation Events – “Time & Money”
─ Project Company Receives Reimbursement from Offtaker/CA
─ Breach of Obligation (e.g. provide access to site)
─ Delays in Construction / Contract Variations by Offtaker/CA
• Excusing Causes
─ Protects Project Company against penalties or deductions
─ Temporary Closure of Project by Agreement with Offtaker/CA
─ Implementation of a Contract Variation or Change of Law
Common Aspects of Project Agreements
• Relief Events “Time No Money”
─ Force Majeure - No fault & Cannot be Controlled by Any Party
─ Examples include Nat. Disasters, Embargos, Labor Strikes etc.
• Step-in by the Offtaker / Contracting Authority
─ Offtaker / CA may have the right to operate the project itself
─ Contract Payment to Financial Lenders Continue
─ Investors & Lenders Uneasy about Terms when Step-in is Permitted
• Termination
─ Default by Project Company or Offtaker / CA
─ Force Majeure Events – Impossible to Complete or Continue
─ Complicated Terms and Numerous Scenarios
Common Aspects of Project Agreements
• Change of Ownership
─ Offtaker /CA May Restrict the Sale of Sponsor’s Share
─ Restriction is generally Limited to Construction Phase
─ Project Technology Dependent on Project Sponsor
• Dispute Resolution
─ Preferable Dispute Resolution by Arbitration
─ Avoid Disputes Related to Poor and Ambiguous Language
─ Standard Construction Contracts not Suitable for P3 Projects
PROJECT RISKS &
PROJECT PROCUREMENT PROCESS
Risks & Selection of Project Delivery Method
CASE STUDY
─ Pima County Regional Wastewater Reclamation Department
(PCRWRD)
─ Wastewater treatment facilities & conveyance systems in
Eastern Pima County, Arizona
─ Lower Effluent Limits from Roger Road Wastewater Treatment
Facility into the Santa Cruz River Required Construction of a
New Wastewater Treatment Facility
─ Considered DBB for Conceptual Timeframe & Cost Estimates for
Design & Construction
─ Recommended Alternative Procurement methods be considered
including: DB, DBO, DBFO
(Regional Optimization Master Plan – Alternative Delivery Methods Final Report 2008
ASCE Journal of Eng. Construction Management - Fitch et. al. Jan. 2015)
Risks & Selection of Project Delivery Method
• OPTIMUM PROJECT DELIVERY METHOD
─ Effective Allocation of Risks Between Project Participants Best Able to
Manage Particular Risks
─ Costs Associated with Each Risk & Total Project Cost are Lessened
• MODEL FOR SELECTING PROCUREMENT METHOD
─ Optimize Risk Allocation
─ Perform and Compare a Risk Adjusted PV Analysis For Each Delivery
Method Under Consideration (DB vs. DBO vs. DBFO)
Risks & Selection of Project Delivery Method
• RISK ADJUSTED PV ANALYSIS:
𝑃𝑉 𝑖𝑁 = 𝐶𝐶0 +
𝑡=1
𝑇
𝑁𝐶𝐹𝑡
(1 + 𝑖) 𝑡
─ CC0 = Capital Costs for Design and Engineering in year 0;
─ NCFt = Net Cash Flow in Year t; and
─ i = Discounted Rate for Both Interest and Inflation
Risks & Selection of Project Delivery Method
PCRWRD LIFECYCLE COSTS USED FOR PV ANALYSIS
New WRC Project DB DBO DBFO
Capital Costs (Design,
Construction)
$212,000,000 $206,000,000 $206,000,000
Yearly Operation &
Maintenance Costs
$7,000,000 $5,000,000 $5,000,000
Risks & Selection of Project Delivery Method
PCRWRD ECONOMIC VARIABLES USED FOR TO SIMULATE THE
RISK ADJUSTED PV ANALYSIS
Interest Rates Rate & Term (yr)
Tax Exempt 5.0%
Muni Bond Term 20
Private Rates 6.0%
Private Bond Term 30
Inflation Rates Rate
Capital Inflation Rates 5.0%
O&M Inflation Rates 2.5%
Energy Inflation Rate 3.0%
Discount Rate 6.0%
COMPARISON BETWEEN THE RANGE OF PVs FOR THE NEW
WRC USING DB VS. DBO USING CRYSTALBALL SOFTWARE:
COMPARISON BETWEEN THE RANGE OF PVs FOR THE NEW
WRC USING DBO VS. DBFO USING CRYSTALBALL SOFTWARE :
Risks & Selection of Project Delivery Method
PCRWRD RISK ADJUSTED PV ANALYSIS RESULTS:
Procurement
Process
Baseline PV
Risk Adjusted
Mean PV 90% Certainty PV
Standard
Deviation
DBO $312,000,000 $350,000,000 $370,000,000 $12,000,000
DB $330,000,000 $369,000,000 $391,000,000 $13,000,000
DBFO $332,000,000 $373,000,000 $394,000,000 $12,000,000
DBFO Risk Adjusted NPV Impacted by 6% Interest Rate and 30 Year Term
Risks & Selection of Project Delivery Method
• PIMA COUNTY CONCLUSIONS:
─ Compared Project Delivery Methods (DB v DBO v DBFO)
─ Risk Adjusted NPV for DBFO Higher than DB and DBO
─ For PCRWRD
 Longer Term with Higher Interest Rate (Economic Risk)
 IRS Rev. Proc. 97-13 (Commercial and Regulatory Risk)
• TYPES OF RISKS:
─ Commercial
─ Macro-Economic
─ Regulatory and Political
PPP Risks – Commercial
• Commercial Viability:
─ Does the Project Make Overall Commercial Sense for All Parties
• Construction Risk:
─ Can the Project Be Built On Time and On Budget
• Revenue Risk:
─ Will its Operating Revenues be as Projected
• Operating Risk:
─ Is the Project able to Operate at the Anticipated Level and Cost
• Input Supply Risk:
─ Can Materials or Other Inputs be Obtained at the Estimated Cost
• Uninsured Risk:
─ Are there Significant Risks Not Covered by Insurance
PPP Risks – Commercial
• Environmental Risks:
─ What effect will the project have on the Environment
• Residual-Value Risk:
─ What happens to the project at the end of the Agreement
• Contract Mismatch:
─ Do the Project Contracts Fit Together Properly
• Sponsor Support:
─ Is there Proper Amount of Recourse to the Sponsors
• Other Reasons for Failure:
─ Does the Project Display Any Common Reasons For Failure
PPP Risks – Macro-Economic
• Macro-Economic Risks:
─ External Macro-Economic Risks aka Financial Risks include changes in:
• Interest rates
• Inflation
• Currency Exchange–Rates
─ Are not project specific but relate to the Economic Environment in
which it Operates.
PPP Risks – Macro-Economic
• TIME VALUE OF MONEY
─ Analysis of Risks Discounted Cash Flow to Calculate the Net Present
Value (NPV) of the P3 Project
─ Internal Rate of Return (IRR) – The Discount Rate Results in NPV = 0.
─ IRR is Used For Calculating:
• Overall Return on a Project
• Investors’ Return on Investment in the Project
• Compensation Sums under the Project Agreement
• Early Termination Payments Under the Project Agreement
• Benefits of Refinancing
𝑃𝑉 𝑖𝑁 = 𝐶𝐶0 +
𝑡=1
𝑇
𝑁𝐶𝐹𝑡
(1 + 𝑖) 𝑡
PPP Risks – Macro-Economic
• Interest Rate Risks
─ Construction-Phase
• During Construction the accrued interest is normally capitalized (i.e. added to
the loan amount) or paid by making a new drawing on the loan.
• Interest Rate is part of the Project’s Capital Budget and a Higher Interest
Rate Than Originally Planned During Construction can Result in a
Construction Cost Overruns.
─ Operating-Phase
• During Operation a Higher Interest Rate means Lower Project Cash Flow and
Reduction in Lenders’ Cover Ratio and Lower Returns for Investors.
PPP Risks – Macro-Economic
• Inflation
─ Construction Cost Overruns Related to Higher Inflation Rates
─ Higher Operating Costs Reduces the Return for Investors
─ Mitigating Strategy Includes Indexation of Contract Payments
• Foreign-Exchange Risks
─ Risks Resulting from movements in the Exchange Rate between Once
Currency and Another.
• Refinancing Risks
─ Short-term Construction Loans can be Refinanced by Long-term Loans
after Project Completion
─ Long-term Interest Rates may Be Higher than Originally
Planned.
PPP Risks – Political & Regulatory
• Change In Law
─ Legislation Allows for Private Ownership or Control of the Project and
Protects Private Investment
─ Clear Legal and Regulatory Framework for the Project’s Operation
─ Consistency of Legal and Regulatory Policies
─ Ability for Lenders to Take and Enforce Security
• Investment Risks
─ Currency Convertibility and Transfer
─ Expropriation of the Project by the State
─ Political Violence
• Wider Political Risks
─ Contract Repudiation – Deliberate Failure by a Public-sector
─ Creeping Expropriation – Cumulative Effect of Numerous Actions
FINANCIAL MARKETS STRUCTURE & MODEL
Project-Finance Markets & Lenders
• Private-Sector Project-Finance Debt Provide by:
─ Commercial Banks
─ Bondholders
• Commercial Banks
─ Largest Providers of Project Finance
─ 90% of Private–Sector Finance Debt in 2012
─ Over $18 Billion in Loan Commitments in the U.S. in 2012
• Bonds
─ Bondholders: Life-Insurance Companies and Pension Funds
─ Aimed at the Non-Banking Markets
─ Tradable Debt Instrument
Financial Structuring in P3 Projects
• Investors’ Analysis and Equity Structure
─ Minimum Equity IRR used by Sponsors and Other Investors to
Determine whether the Project is a Viable Investment.
─ Hurdle Rates for Equity IRR above which an Investment is Acceptable:
• Investor’s Own Weighted Cost of Capital
• Additional Return Over Cost of Capital Required for Particular Risks
• Market Competition
• Project Viability
𝑃𝑉 𝑖𝑁 = 𝐶𝐶0 +
𝑡=1
𝑇
𝑁𝐶𝐹𝑡
(1 + 𝑖) 𝑡
Financial Structuring in P3 Projects
• Main Elements For Project-Finance Structure:
1.Debt Cover Ratios
2.Debt:Equity Ratio
3.Debt Service Profile
4.Interest Rate and Fees
Financial Structuring in P3 Projects
• Debt Cover Ratio
─ Level of Debt for a Project is based on Ability to Pay Interest &
Principal with a Margin of Safety.
─ To Assess the Margin of Safety Lenders Calculate Debt Cover Ratios:
• Annual Debt Service Cover Ratio (ADSCR)
• Loan-Life Cover Ratio (LLCR)
• Averages of ADSCR and LLCR
• Project-life Cover Ratio
Financial Structuring in P3 Projects
• Debt:Equity Ratio (Ratio of Debt to Equity)
─ Based on Cover-Ratio Calculations and Reflect Project Risks
─ Greater Safety Margin Required by Lenders = Higher Debt Cover Ratio
─ Projects With Greater Risk have Lower Debt:Equity Ratios:
• 90:10 for and Accommodation-based Contract
• 85:15 for a Process –plant project with an Offtake Contract
• 80:20 for a Transport Concession
• 70:30 for a Power Plant Project with no Offtake Contract
• 50:50 for a Natural Resource Project
Financial Structuring in P3 Projects
• Debt Service Profile
─ Loan Interest Payments and Principal Repayment
─ Investors Look For Dividends Sooner than Later
─ Lenders Look to be Repaid as Rapidly as Possible
─ Debt Repayment Schedule Based:
• Term of Financing – Project-Finance Debt is much longer in term (repayment
period)
• Average Life (or Maximum Average Life) – How Rapid Risk Reduces Over the
Term
• Repayment Schedule – Start Date and Frequency of Repayment
• Flexibility in Repayment – “Target and Minimum” Repayment Structure
Financial Structuring in P3 Projects
• Interest Rate and Fees
─ International Project-Finance Floating Loan Rates Typically 2 – 3.5 %
over LIBOR
(LIBOR stands for Intercontinental Exchange London Interbank Offered Rate)
─ Fees Include:
• Arranging and Underwriting Fees
• Commitment Fees Paid on the Available But Undrawn Portion of Bank Debt
During Construction
• Agency Fees Payable to the Agent Bank or Security Trustee
The P3 Financial Model
• Input or Main Building Blocks include:
─ Macro-economic Assumptions
─ Project Costs and Funding
─ Operating Revenues and Costs
─ Accounting and Taxation Assumptions
• Outputs:
─ Determine Viability of the Project from Investors’ Point of View
─ Determine Viability of the Project from Offtaker’s / CA’s Point of View
─ Sensitivity and Risk Analysis for Lenders
The P3 Financial Model
• Functions of the Financial Model
─ Pre-Financial Close / Development Phase
• Evaluation & Reevaluation of Projects Financial Aspects and Sponsor’s
Economic Return
• Structuring the Finance and Reviewing the Sponsors’ Benefits under Different
Financial Terms
• Formulating Financial Provisions of the Project Contracts including LD Calc.’s
• Part of the Lenders Due Diligence Process
• Quantifying Critical Finance Issues
• Offtaker / CA Confirm Financial Viability
• Compare Proposals Submitted by Sponsors
The P3 Financial Model
• Functions of the Financial Model
─ Post-Financial Close
• Budgeting Tool
• Enables Lenders to Review Long-term Changes
• Enables Investors to Calculate the Value of their Investment
• Used by Investors to Calculate Compensation Event Payments
• Offtaker / CA Calculate Refinancing Gain
• Offtaker / CA Calculate Termination Sum
Private and Public Partnerships
Move Mainstream
Conclusions and Summary:
1. Infrastructure Overhaul in the U.S.
2. Increased Number of Projects procured using Alternative Project Delivery
Methods
3. Greater Frequency of P3 Procurement
4. Increased Participation For Civil Engineers
5. Greater Knowledge & Involvement with Project Finance
6. More Infrastructure Projects + Expanded Roles for Civil Engineers =
Greater and More Value
Private and Public Partnerships
Move Mainstream
Acknowledgements:
Principles of Project Finance
By E.R. Yescombe
Published by ElSevier Publishing
WPI will offer this Fall 2016
On-Line &
Monday Evenings 6:00 – 8:50 p.m.
CE590 - Capital Facility Planning and Financing in
Private and Public Partnerships
Email: gjfitch@wpi.edu
64
CE590 – P3 Project Financing
QUESTIONS?

More Related Content

What's hot

Nj future redevelopment forum 2014 financing infrastructure mc monagle
Nj future redevelopment forum 2014 financing infrastructure mc monagleNj future redevelopment forum 2014 financing infrastructure mc monagle
Nj future redevelopment forum 2014 financing infrastructure mc monagleNew Jersey Future
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainBob Prieto
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsConstruction in Focus
 
Private Finance Initiative (PFI)
Private Finance Initiative (PFI)Private Finance Initiative (PFI)
Private Finance Initiative (PFI)tutor2u
 
Toll Roads and Risk Assessment
Toll Roads and Risk AssessmentToll Roads and Risk Assessment
Toll Roads and Risk AssessmentVijai Krishnan V
 
Strategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit ProjectsStrategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit ProjectsGannett Fleming, Inc.
 
Saudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projectsSaudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projectsIbrahim Al-Hudhaif
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016teohwooisin
 
Alandur sewerage treatment plant project ppp model
Alandur sewerage treatment plant project   ppp modelAlandur sewerage treatment plant project   ppp model
Alandur sewerage treatment plant project ppp modelAr.Apurva Sinkar
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...Association for Project Management
 
208 - Geopolitics & World Economic Systems unit3
208 - Geopolitics & World Economic Systems unit3208 - Geopolitics & World Economic Systems unit3
208 - Geopolitics & World Economic Systems unit3ASM's IBMR- Chinchwad
 
Dd P3 Wkshp Procurement Schedule Key Issues 0709
Dd P3 Wkshp Procurement Schedule Key Issues 0709Dd P3 Wkshp Procurement Schedule Key Issues 0709
Dd P3 Wkshp Procurement Schedule Key Issues 0709anxora
 
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionDBL Law
 
Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsAssociation for Project Management
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Social equity in infrastructure
Social equity in infrastructureSocial equity in infrastructure
Social equity in infrastructureParth Joshi
 
Public-Private Partnerships in Housing and Urban Development
Public-Private Partnerships in Housing and Urban DevelopmentPublic-Private Partnerships in Housing and Urban Development
Public-Private Partnerships in Housing and Urban DevelopmentOswar Mungkasa
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...Association for Project Management
 

What's hot (20)

Nj future redevelopment forum 2014 financing infrastructure mc monagle
Nj future redevelopment forum 2014 financing infrastructure mc monagleNj future redevelopment forum 2014 financing infrastructure mc monagle
Nj future redevelopment forum 2014 financing infrastructure mc monagle
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery models
 
Private Finance Initiative (PFI)
Private Finance Initiative (PFI)Private Finance Initiative (PFI)
Private Finance Initiative (PFI)
 
Toll Roads and Risk Assessment
Toll Roads and Risk AssessmentToll Roads and Risk Assessment
Toll Roads and Risk Assessment
 
Strategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit ProjectsStrategies for Reducing Risk on Design-Build Public Transit Projects
Strategies for Reducing Risk on Design-Build Public Transit Projects
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Delhi Gurgaon Expressway PPP
Delhi Gurgaon Expressway PPPDelhi Gurgaon Expressway PPP
Delhi Gurgaon Expressway PPP
 
Saudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projectsSaudi mega transport and infrastructure projects
Saudi mega transport and infrastructure projects
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
Alandur sewerage treatment plant project ppp model
Alandur sewerage treatment plant project   ppp modelAlandur sewerage treatment plant project   ppp model
Alandur sewerage treatment plant project ppp model
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
208 - Geopolitics & World Economic Systems unit3
208 - Geopolitics & World Economic Systems unit3208 - Geopolitics & World Economic Systems unit3
208 - Geopolitics & World Economic Systems unit3
 
Dd P3 Wkshp Procurement Schedule Key Issues 0709
Dd P3 Wkshp Procurement Schedule Key Issues 0709Dd P3 Wkshp Procurement Schedule Key Issues 0709
Dd P3 Wkshp Procurement Schedule Key Issues 0709
 
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in Construction
 
Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contracts
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Social equity in infrastructure
Social equity in infrastructureSocial equity in infrastructure
Social equity in infrastructure
 
Public-Private Partnerships in Housing and Urban Development
Public-Private Partnerships in Housing and Urban DevelopmentPublic-Private Partnerships in Housing and Urban Development
Public-Private Partnerships in Housing and Urban Development
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 

Viewers also liked

The Role of Building Information Modeling in Construction Project Management
The Role of Building Information Modeling in Construction Project ManagementThe Role of Building Information Modeling in Construction Project Management
The Role of Building Information Modeling in Construction Project ManagementKerry Carey
 
The venue shannon public presentation 27 may 2015
The venue shannon public presentation 27 may 2015The venue shannon public presentation 27 may 2015
The venue shannon public presentation 27 may 2015The Venue Shannon
 
Constructing Excellence Kent Introduction - “BIM and the Future Workforce”
Constructing Excellence Kent Introduction - “BIM and the Future Workforce” Constructing Excellence Kent Introduction - “BIM and the Future Workforce”
Constructing Excellence Kent Introduction - “BIM and the Future Workforce” Constructing Excellence Kent Branch
 
'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...
'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...
'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...Constructing Excellence Kent Branch
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areasguestfe6ad
 
A Critical Review of Building Information Modelling
A Critical Review of Building Information ModellingA Critical Review of Building Information Modelling
A Critical Review of Building Information ModellingSiddhartha Kamat
 
Construction industry
Construction industryConstruction industry
Construction industryAdvait Bhobe
 
Understanding Building construction
Understanding Building construction Understanding Building construction
Understanding Building construction Llyod cassidy
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentationryanabarton
 
Marketing Presentation on Coca Cola
Marketing Presentation on Coca Cola Marketing Presentation on Coca Cola
Marketing Presentation on Coca Cola Siddhartha Kamat
 

Viewers also liked (16)

The Role of Building Information Modeling in Construction Project Management
The Role of Building Information Modeling in Construction Project ManagementThe Role of Building Information Modeling in Construction Project Management
The Role of Building Information Modeling in Construction Project Management
 
The venue shannon public presentation 27 may 2015
The venue shannon public presentation 27 may 2015The venue shannon public presentation 27 may 2015
The venue shannon public presentation 27 may 2015
 
BIM Al Fouzan
BIM Al FouzanBIM Al Fouzan
BIM Al Fouzan
 
Constructing Excellence Kent Introduction - “BIM and the Future Workforce”
Constructing Excellence Kent Introduction - “BIM and the Future Workforce” Constructing Excellence Kent Introduction - “BIM and the Future Workforce”
Constructing Excellence Kent Introduction - “BIM and the Future Workforce”
 
'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...
'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...
'BIM and the Future Workforce' - Tekla UK, Building with Models, a presentati...
 
Green Construction
Green ConstructionGreen Construction
Green Construction
 
Core Competence of LnT
Core Competence of LnTCore Competence of LnT
Core Competence of LnT
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areas
 
A Critical Review of Building Information Modelling
A Critical Review of Building Information ModellingA Critical Review of Building Information Modelling
A Critical Review of Building Information Modelling
 
Construction industry
Construction industryConstruction industry
Construction industry
 
Understanding Building construction
Understanding Building construction Understanding Building construction
Understanding Building construction
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentation
 
Marketing Presentation on Coca Cola
Marketing Presentation on Coca Cola Marketing Presentation on Coca Cola
Marketing Presentation on Coca Cola
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 

Similar to Private and Public Partnerships Move Mainstream

financing infrastructure projects
financing infrastructure projectsfinancing infrastructure projects
financing infrastructure projectsAmanpreetKaur391966
 
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfSeshukumar53
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)M. Asim U Khan
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnershipAnkit GAJJAR
 
The ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsThe ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsAnatoly Darov, P.E.
 
BOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTSBOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTSaly_ayk
 
Understanding "BOT" projects
Understanding "BOT" projectsUnderstanding "BOT" projects
Understanding "BOT" projectsPrashanth Ravada
 
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInAurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInSteve Richards
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery MethodsMcCarthy Holdings, Inc.
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppChhabiYadav2
 
Credit appraisal and evaluation
Credit appraisal and evaluationCredit appraisal and evaluation
Credit appraisal and evaluationVAIBHAV SINHA
 
UNDERSTANDING_PPPs.pdf
UNDERSTANDING_PPPs.pdfUNDERSTANDING_PPPs.pdf
UNDERSTANDING_PPPs.pdfAlkaPandya5
 
AmericanTransPartners Corporate Background
AmericanTransPartners Corporate BackgroundAmericanTransPartners Corporate Background
AmericanTransPartners Corporate BackgroundKelsee DuBois
 
AmericanTransPartners Corporate Background
AmericanTransPartners Corporate BackgroundAmericanTransPartners Corporate Background
AmericanTransPartners Corporate BackgroundKelsee DuBois
 
financing infrastructure projects
financing infrastructure projectsfinancing infrastructure projects
financing infrastructure projectsDr Naim R Kidwai
 
Procurement & contract.(bot)
Procurement & contract.(bot)Procurement & contract.(bot)
Procurement & contract.(bot)rajlaxmipardeshi
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesLou Milrad
 
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDOECDGlobalRelations
 
Mobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS InfrastructureMobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS InfrastructurePratish Halady
 

Similar to Private and Public Partnerships Move Mainstream (20)

financing infrastructure projects
financing infrastructure projectsfinancing infrastructure projects
financing infrastructure projects
 
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)
 
PPP models.pptx
 PPP models.pptx PPP models.pptx
PPP models.pptx
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
 
The ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and TownsThe ABCs of P3 What it Means for Cities and Towns
The ABCs of P3 What it Means for Cities and Towns
 
BOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTSBOOT, BOT, Management Contracts & Turnkey PROJECTS
BOOT, BOT, Management Contracts & Turnkey PROJECTS
 
Understanding "BOT" projects
Understanding "BOT" projectsUnderstanding "BOT" projects
Understanding "BOT" projects
 
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInAurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in ppp
 
Credit appraisal and evaluation
Credit appraisal and evaluationCredit appraisal and evaluation
Credit appraisal and evaluation
 
UNDERSTANDING_PPPs.pdf
UNDERSTANDING_PPPs.pdfUNDERSTANDING_PPPs.pdf
UNDERSTANDING_PPPs.pdf
 
AmericanTransPartners Corporate Background
AmericanTransPartners Corporate BackgroundAmericanTransPartners Corporate Background
AmericanTransPartners Corporate Background
 
AmericanTransPartners Corporate Background
AmericanTransPartners Corporate BackgroundAmericanTransPartners Corporate Background
AmericanTransPartners Corporate Background
 
financing infrastructure projects
financing infrastructure projectsfinancing infrastructure projects
financing infrastructure projects
 
Procurement & contract.(bot)
Procurement & contract.(bot)Procurement & contract.(bot)
Procurement & contract.(bot)
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal Issues
 
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
 
Mobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS InfrastructureMobilizing Private Sector Investment into GMS Infrastructure
Mobilizing Private Sector Investment into GMS Infrastructure
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 

Private and Public Partnerships Move Mainstream

  • 1. The Construction Project Manager’s Modern Toolbelt How Technology & Creativity Enable Successful Project Delivery Webinar Series
  • 2. Private and Public Partnerships Move Mainstream Greg Fitch August 16, 2016
  • 3. Private and Public Partnerships Move Mainstream Greg Fitch August 16, 2016 WPI Department of Civil Engineering ‘98 Columbia University Department of Civil Engineering – PhD Candidate
  • 4. Greg Fitch August 16, 2016 Project Controls Lead Analyst Construction & Procurement in New York City Private and Public Partnerships Move Mainstream
  • 5. PUBLIC-PRIVATE-PARTNERSHIPS (PPP OR P3) 1. Characteristics of PPPs 2. Overview of P3 Project Finance Structures 3. Common Aspects P3 Project Agreements 4. Project Risks & Project Procurement Process 5. PPP Financial Markets, Structure & Model
  • 6. Traditional and Alternative Procurement Methods Defined Design-Build – Owner uses a competitive proposal process to contract with a private entity to design and build a project. Design-Build-Operate – Owner uses a competitive proposal process to contract with a private entity to design and build a project but also adds operations to the DB Foundation. Design-Bid-Build – Traditional method in which the agency or owner contracts with separate entities for the design and construction of a project.
  • 8. DBFO or Public-Private-Partnership Procurement Method Defined Design-Build-Finance-Operate or Public-Private-Partnerships (PPP or P3): Owner uses a competitive proposal process to contract with a private consortium to finance, design, construct, maintain and operate a facility and / or build a project.
  • 9. Congressional Budget Office (2012) Variety of alternative arrangements for Projects that transfer more of the risk associated with control of the project to the private sector. Dr. Michael J. Garvin (May – June 2011 edition of TR News) Long-term contractual arrangements between public and private partners for the creation and enhancement of assets, bundled together with the provision of services and capital financing through a private entity. FHWA – Office of Innovative Project Delivery Contractual agreements between a public agency and a private entity that allow for greater private participation in the delivery of transportation projects. Participation involves the private sector taking on additional project risks, such as design, finance, long-term operation, and traffic revenue.
  • 10. Why Public-Private Projects Relevant? • ALTERNATIVE PROJECT DELIVERY METHODS ─ Solution to Resolve Investment Deficits in Infrastructure • CENTRAL GOAL OF P3 PROJECTS ─ Alleviate Government Budgets with Funding Provided by External Financiers. (Algarni et al. 2007) • P3 PROJECTS INCLUDE EQUITY SPONSORS ─ Most Capable of Managing Financial Risk & Owner-like Responsibility w/out Actually Transferring Ownership. (Culp 2011)
  • 11. PPP VS. TRADITIONAL DELIVERY • Private Perspective • Public Perspective • Service-Oriented Delivery Model • Large Scope & Long-term Contracts • High Priority Projects • Optimize vs. Maximum Risk Allocation • Opportunities for Stable Investment • Public Need & Benefits ─ Local, Regional & State ─ Reliable & Safe Infrastructure Procurement ─ Traffic Congestion Relief ─ Electrical Power Demands ─ Other Public Use Needs • Financial Feasibility ─ Alleviate Government Budgets ─ Better Value for Money ─ Market Demand for Projects
  • 12. CHARACTERISTICS OF PPPs • PROJECT SPECIFIC CONTRACT INCLUDES: ─ Significant New Capital Expenditures [large EPC or DB contracts] ─ Long-term O&M Responsibilities ─ Private Financing Allows Public Funds To Be Used On Other Projects ─ Project Specific Revenue Source • PUBLIC PERCEPTION OF “PRIVATIZATION”: ─ Convey Ownership of Public Assets Transferred to Private Sector ─ Rely on Private Sector to Provide Services Formerly Provided by Public Owner or Agency ─ Project May Not Require or Support Private Financing Based on Generated Revenues
  • 13. • Three Main Models for Project Agreements: • Offtake Contract (i.e. Process-plant Project): ─ The Project Company produces a product and sells it to an Offtaker. • Concession Agreement (i.e. Toll Road Project): ─ The Project Company provides a public service, and collects User Charges. • Availability-based Contract (i.e. PFI Model): ─ Contracting Authority pays a Project Company for making a project available for use.
  • 14. OVERVIEW OF P3 PROJECT FINANCE STRUCTURES
  • 15. Project-Finance Structures • Process-Plant Projects: ─ Projects where there is an input at one end of the project, which goes through a process within the project, and emerges as an output. • Concession Projects: ─ Construction or refurbishment of public infrastructure with revenues derived from tolls, fairs, or similar payments from by users. • Private Finance Initiative Model: ─ Construction / Refurbishment of Public Buildings or other public infrastructure with revenue derived from payments by a Contracting Authority (CA).
  • 16. Example of Project-Finance Structures Process-plant Project Investors 16 CE590 – P3 Project Financing Finance Lenders Project-Finance DebtEquity Government Electricity Distributor Power Purchase AgreementOperating License Project Company
  • 17. Example of Project-Finance Structures Process-plant Project - Subcontracts 17 CE590 – P3 Project Financing Project Company EPC Contract Fuel Supply Contract Operation & Maintenance Contract Construction Contractor Fuel Supplier O&M Contractor
  • 18. Process-Plant Project • SOLAR PLANT PROJECT - Roserock (Project Company) will sell the energy, capacity and green attributes to the City of Austin based on the terms of the Power Purchase Agreement signed May 1, 2014. KEY TERMS VALUES Effective Date 5/01/2014 Delivery Term 20 years Expected Capacity (which may not be modified by RE Roserock to change by +/- five percent) 150 MW Maximum AC Output 150 MW Minimum Capacity 140 MW Contract Price ($/MWh) $44.95 (no escalation)
  • 19. Process Plant Project Holdings Company “A” Short Term Credit Agreement Longer Term Credit Agreement “Project Company” Project Sponsors Holdings Company “B” Project Completion Engineering & Construction Operations & Maintenance Funding Funding Purchase Shares Purchase & Sale Agreement Equity Related Contracts Financial Lender & Debt Related Contracts Initial Investors Other Investors Other Investors 100%
  • 20. Example of Project-Finance Structures Toll-Road ConcessionInvestors 20 CE590 – P3 Project Financing Finance Lenders Project-Finance DebtEquity Contracting Authority Road Users TollsConcession Agreement Project Company
  • 21. Example of Project-Finance Structures Toll-Road Concession - Subcontracts 21 CE590 – P3 Project Financing Project Agreement Design & Build Contract Toll Operation Contract Maintenance Contract Design & Build Contractor Toll Operator Maintenance Contractor
  • 22. Concession Project • I-595 CORRIDOR ROADWAY IMPROVEMENTS ─ Located in Broward County Florida. ─ Opened to Traffic in 1989 – With Accelerated Traffic ─ Roadway Improvements includes Reconstruction and Widening of I-595 with various improvements to ramps, interchanges etc. ─ Private concessionaire designed, built, financed and will operate and maintain project for 35 years. ─ $1.8 Billion (present value in 2009 dollars; a 5% discount Rate)
  • 23. Example of Project-Finance Structures Private Finance Initiative (PFI) Model Investors 23 CE590 – P3 Project Financing Finance Lenders Project-Finance DebtEquity Project Company Contracting Authority Project Agreement
  • 24. Example of Project-Finance Structures PFI Model - Subcontracts 24 CE590 – P3 Project Financing Project Agreement Design & Build Contract Maintenance Contract ‘Soft’ Services Contract(s) Design & Build Contractor Service Provider(s) Maintenance Contractor
  • 25. Project Finance Initiative Model Project Fargo Moorhead Flood Diversion Channel Red River Basin surrounding Fargo, ND & Moorhead, MN ─ Red River Basin & Diversion Authority (includes counties in ND and MN) ─ Increased Frequency and Severity of Floods ─ 30 mile wide Diversion Channel in ND w/ 150,000 acre-feet of Upstream Staging ─ Federally Authorized in February 2016 ─ USACE as a Demonstration Split Project Delivery Model
  • 26. Fargo Moorehead Flood Diversion Channel • FINANCIAL OVERVIEW & SPLIT PROJECT DELIVERY MODEL 1. USACE will deliver Southern Embankment and Related projects with Multiple Design-Bid-Build Projects. 2. Diversion Authority will Deliver Channel & Associated Infrastructure with Locally-led P3 delivery includes a combination of public and private financing, leveraging state and local funding sources
  • 27. • FARGO MOORHEAD FLOOD DIVERSION P3 FINANCIAL OVERVIEW FOR DIVERSION CHANNEL ─ Project Delivery Method • Design-Build-Finance-Operate-Maintain ─ Construction Funding • Private financing (debt & equity) secured by P3 Consortium • Diversion Authority will make Milestone Payments to P3 Consortium ─ Payment Structure for O&M Scope (30 -50 year term) • Multiple Funding Sources to Meet Debt Service and O&M Payments include State Appropriations, Sales Tax, Asses.
  • 28. COMMON ASPECTS P3 PROJECT AGREEMENTS
  • 29. Common Aspects of Project Agreements • Contract Term ─ Useful Life of the Project ─ Term of Debt ─ Equity Return • Payment Mechanism ─ Payment on Project Completion ─ Level Payments ─ Inflation Indexation • Contract Monitoring by the Offtaker / Contracting Authority ─ Design, Construction and Operation ─ Subcontracts ─ Financing
  • 30. Common Aspects of Project Agreements • Performance Bonding and Other Guarantees ─ Offtaker / CA Requires a Performance Bond ─ Duplicates Lenders’ Requirements of Project Company ─ Project Company Incentive is to Generate Revenue • Compensation Events – “Time & Money” ─ Project Company Receives Reimbursement from Offtaker/CA ─ Breach of Obligation (e.g. provide access to site) ─ Delays in Construction / Contract Variations by Offtaker/CA • Excusing Causes ─ Protects Project Company against penalties or deductions ─ Temporary Closure of Project by Agreement with Offtaker/CA ─ Implementation of a Contract Variation or Change of Law
  • 31. Common Aspects of Project Agreements • Relief Events “Time No Money” ─ Force Majeure - No fault & Cannot be Controlled by Any Party ─ Examples include Nat. Disasters, Embargos, Labor Strikes etc. • Step-in by the Offtaker / Contracting Authority ─ Offtaker / CA may have the right to operate the project itself ─ Contract Payment to Financial Lenders Continue ─ Investors & Lenders Uneasy about Terms when Step-in is Permitted • Termination ─ Default by Project Company or Offtaker / CA ─ Force Majeure Events – Impossible to Complete or Continue ─ Complicated Terms and Numerous Scenarios
  • 32. Common Aspects of Project Agreements • Change of Ownership ─ Offtaker /CA May Restrict the Sale of Sponsor’s Share ─ Restriction is generally Limited to Construction Phase ─ Project Technology Dependent on Project Sponsor • Dispute Resolution ─ Preferable Dispute Resolution by Arbitration ─ Avoid Disputes Related to Poor and Ambiguous Language ─ Standard Construction Contracts not Suitable for P3 Projects
  • 33. PROJECT RISKS & PROJECT PROCUREMENT PROCESS
  • 34. Risks & Selection of Project Delivery Method CASE STUDY ─ Pima County Regional Wastewater Reclamation Department (PCRWRD) ─ Wastewater treatment facilities & conveyance systems in Eastern Pima County, Arizona ─ Lower Effluent Limits from Roger Road Wastewater Treatment Facility into the Santa Cruz River Required Construction of a New Wastewater Treatment Facility ─ Considered DBB for Conceptual Timeframe & Cost Estimates for Design & Construction ─ Recommended Alternative Procurement methods be considered including: DB, DBO, DBFO (Regional Optimization Master Plan – Alternative Delivery Methods Final Report 2008 ASCE Journal of Eng. Construction Management - Fitch et. al. Jan. 2015)
  • 35. Risks & Selection of Project Delivery Method • OPTIMUM PROJECT DELIVERY METHOD ─ Effective Allocation of Risks Between Project Participants Best Able to Manage Particular Risks ─ Costs Associated with Each Risk & Total Project Cost are Lessened • MODEL FOR SELECTING PROCUREMENT METHOD ─ Optimize Risk Allocation ─ Perform and Compare a Risk Adjusted PV Analysis For Each Delivery Method Under Consideration (DB vs. DBO vs. DBFO)
  • 36. Risks & Selection of Project Delivery Method • RISK ADJUSTED PV ANALYSIS: 𝑃𝑉 𝑖𝑁 = 𝐶𝐶0 + 𝑡=1 𝑇 𝑁𝐶𝐹𝑡 (1 + 𝑖) 𝑡 ─ CC0 = Capital Costs for Design and Engineering in year 0; ─ NCFt = Net Cash Flow in Year t; and ─ i = Discounted Rate for Both Interest and Inflation
  • 37. Risks & Selection of Project Delivery Method PCRWRD LIFECYCLE COSTS USED FOR PV ANALYSIS New WRC Project DB DBO DBFO Capital Costs (Design, Construction) $212,000,000 $206,000,000 $206,000,000 Yearly Operation & Maintenance Costs $7,000,000 $5,000,000 $5,000,000
  • 38. Risks & Selection of Project Delivery Method PCRWRD ECONOMIC VARIABLES USED FOR TO SIMULATE THE RISK ADJUSTED PV ANALYSIS Interest Rates Rate & Term (yr) Tax Exempt 5.0% Muni Bond Term 20 Private Rates 6.0% Private Bond Term 30 Inflation Rates Rate Capital Inflation Rates 5.0% O&M Inflation Rates 2.5% Energy Inflation Rate 3.0% Discount Rate 6.0%
  • 39. COMPARISON BETWEEN THE RANGE OF PVs FOR THE NEW WRC USING DB VS. DBO USING CRYSTALBALL SOFTWARE:
  • 40. COMPARISON BETWEEN THE RANGE OF PVs FOR THE NEW WRC USING DBO VS. DBFO USING CRYSTALBALL SOFTWARE :
  • 41. Risks & Selection of Project Delivery Method PCRWRD RISK ADJUSTED PV ANALYSIS RESULTS: Procurement Process Baseline PV Risk Adjusted Mean PV 90% Certainty PV Standard Deviation DBO $312,000,000 $350,000,000 $370,000,000 $12,000,000 DB $330,000,000 $369,000,000 $391,000,000 $13,000,000 DBFO $332,000,000 $373,000,000 $394,000,000 $12,000,000 DBFO Risk Adjusted NPV Impacted by 6% Interest Rate and 30 Year Term
  • 42. Risks & Selection of Project Delivery Method • PIMA COUNTY CONCLUSIONS: ─ Compared Project Delivery Methods (DB v DBO v DBFO) ─ Risk Adjusted NPV for DBFO Higher than DB and DBO ─ For PCRWRD  Longer Term with Higher Interest Rate (Economic Risk)  IRS Rev. Proc. 97-13 (Commercial and Regulatory Risk) • TYPES OF RISKS: ─ Commercial ─ Macro-Economic ─ Regulatory and Political
  • 43. PPP Risks – Commercial • Commercial Viability: ─ Does the Project Make Overall Commercial Sense for All Parties • Construction Risk: ─ Can the Project Be Built On Time and On Budget • Revenue Risk: ─ Will its Operating Revenues be as Projected • Operating Risk: ─ Is the Project able to Operate at the Anticipated Level and Cost • Input Supply Risk: ─ Can Materials or Other Inputs be Obtained at the Estimated Cost • Uninsured Risk: ─ Are there Significant Risks Not Covered by Insurance
  • 44. PPP Risks – Commercial • Environmental Risks: ─ What effect will the project have on the Environment • Residual-Value Risk: ─ What happens to the project at the end of the Agreement • Contract Mismatch: ─ Do the Project Contracts Fit Together Properly • Sponsor Support: ─ Is there Proper Amount of Recourse to the Sponsors • Other Reasons for Failure: ─ Does the Project Display Any Common Reasons For Failure
  • 45. PPP Risks – Macro-Economic • Macro-Economic Risks: ─ External Macro-Economic Risks aka Financial Risks include changes in: • Interest rates • Inflation • Currency Exchange–Rates ─ Are not project specific but relate to the Economic Environment in which it Operates.
  • 46. PPP Risks – Macro-Economic • TIME VALUE OF MONEY ─ Analysis of Risks Discounted Cash Flow to Calculate the Net Present Value (NPV) of the P3 Project ─ Internal Rate of Return (IRR) – The Discount Rate Results in NPV = 0. ─ IRR is Used For Calculating: • Overall Return on a Project • Investors’ Return on Investment in the Project • Compensation Sums under the Project Agreement • Early Termination Payments Under the Project Agreement • Benefits of Refinancing 𝑃𝑉 𝑖𝑁 = 𝐶𝐶0 + 𝑡=1 𝑇 𝑁𝐶𝐹𝑡 (1 + 𝑖) 𝑡
  • 47. PPP Risks – Macro-Economic • Interest Rate Risks ─ Construction-Phase • During Construction the accrued interest is normally capitalized (i.e. added to the loan amount) or paid by making a new drawing on the loan. • Interest Rate is part of the Project’s Capital Budget and a Higher Interest Rate Than Originally Planned During Construction can Result in a Construction Cost Overruns. ─ Operating-Phase • During Operation a Higher Interest Rate means Lower Project Cash Flow and Reduction in Lenders’ Cover Ratio and Lower Returns for Investors.
  • 48. PPP Risks – Macro-Economic • Inflation ─ Construction Cost Overruns Related to Higher Inflation Rates ─ Higher Operating Costs Reduces the Return for Investors ─ Mitigating Strategy Includes Indexation of Contract Payments • Foreign-Exchange Risks ─ Risks Resulting from movements in the Exchange Rate between Once Currency and Another. • Refinancing Risks ─ Short-term Construction Loans can be Refinanced by Long-term Loans after Project Completion ─ Long-term Interest Rates may Be Higher than Originally Planned.
  • 49. PPP Risks – Political & Regulatory • Change In Law ─ Legislation Allows for Private Ownership or Control of the Project and Protects Private Investment ─ Clear Legal and Regulatory Framework for the Project’s Operation ─ Consistency of Legal and Regulatory Policies ─ Ability for Lenders to Take and Enforce Security • Investment Risks ─ Currency Convertibility and Transfer ─ Expropriation of the Project by the State ─ Political Violence • Wider Political Risks ─ Contract Repudiation – Deliberate Failure by a Public-sector ─ Creeping Expropriation – Cumulative Effect of Numerous Actions
  • 51. Project-Finance Markets & Lenders • Private-Sector Project-Finance Debt Provide by: ─ Commercial Banks ─ Bondholders • Commercial Banks ─ Largest Providers of Project Finance ─ 90% of Private–Sector Finance Debt in 2012 ─ Over $18 Billion in Loan Commitments in the U.S. in 2012 • Bonds ─ Bondholders: Life-Insurance Companies and Pension Funds ─ Aimed at the Non-Banking Markets ─ Tradable Debt Instrument
  • 52. Financial Structuring in P3 Projects • Investors’ Analysis and Equity Structure ─ Minimum Equity IRR used by Sponsors and Other Investors to Determine whether the Project is a Viable Investment. ─ Hurdle Rates for Equity IRR above which an Investment is Acceptable: • Investor’s Own Weighted Cost of Capital • Additional Return Over Cost of Capital Required for Particular Risks • Market Competition • Project Viability 𝑃𝑉 𝑖𝑁 = 𝐶𝐶0 + 𝑡=1 𝑇 𝑁𝐶𝐹𝑡 (1 + 𝑖) 𝑡
  • 53. Financial Structuring in P3 Projects • Main Elements For Project-Finance Structure: 1.Debt Cover Ratios 2.Debt:Equity Ratio 3.Debt Service Profile 4.Interest Rate and Fees
  • 54. Financial Structuring in P3 Projects • Debt Cover Ratio ─ Level of Debt for a Project is based on Ability to Pay Interest & Principal with a Margin of Safety. ─ To Assess the Margin of Safety Lenders Calculate Debt Cover Ratios: • Annual Debt Service Cover Ratio (ADSCR) • Loan-Life Cover Ratio (LLCR) • Averages of ADSCR and LLCR • Project-life Cover Ratio
  • 55. Financial Structuring in P3 Projects • Debt:Equity Ratio (Ratio of Debt to Equity) ─ Based on Cover-Ratio Calculations and Reflect Project Risks ─ Greater Safety Margin Required by Lenders = Higher Debt Cover Ratio ─ Projects With Greater Risk have Lower Debt:Equity Ratios: • 90:10 for and Accommodation-based Contract • 85:15 for a Process –plant project with an Offtake Contract • 80:20 for a Transport Concession • 70:30 for a Power Plant Project with no Offtake Contract • 50:50 for a Natural Resource Project
  • 56. Financial Structuring in P3 Projects • Debt Service Profile ─ Loan Interest Payments and Principal Repayment ─ Investors Look For Dividends Sooner than Later ─ Lenders Look to be Repaid as Rapidly as Possible ─ Debt Repayment Schedule Based: • Term of Financing – Project-Finance Debt is much longer in term (repayment period) • Average Life (or Maximum Average Life) – How Rapid Risk Reduces Over the Term • Repayment Schedule – Start Date and Frequency of Repayment • Flexibility in Repayment – “Target and Minimum” Repayment Structure
  • 57. Financial Structuring in P3 Projects • Interest Rate and Fees ─ International Project-Finance Floating Loan Rates Typically 2 – 3.5 % over LIBOR (LIBOR stands for Intercontinental Exchange London Interbank Offered Rate) ─ Fees Include: • Arranging and Underwriting Fees • Commitment Fees Paid on the Available But Undrawn Portion of Bank Debt During Construction • Agency Fees Payable to the Agent Bank or Security Trustee
  • 58. The P3 Financial Model • Input or Main Building Blocks include: ─ Macro-economic Assumptions ─ Project Costs and Funding ─ Operating Revenues and Costs ─ Accounting and Taxation Assumptions • Outputs: ─ Determine Viability of the Project from Investors’ Point of View ─ Determine Viability of the Project from Offtaker’s / CA’s Point of View ─ Sensitivity and Risk Analysis for Lenders
  • 59. The P3 Financial Model • Functions of the Financial Model ─ Pre-Financial Close / Development Phase • Evaluation & Reevaluation of Projects Financial Aspects and Sponsor’s Economic Return • Structuring the Finance and Reviewing the Sponsors’ Benefits under Different Financial Terms • Formulating Financial Provisions of the Project Contracts including LD Calc.’s • Part of the Lenders Due Diligence Process • Quantifying Critical Finance Issues • Offtaker / CA Confirm Financial Viability • Compare Proposals Submitted by Sponsors
  • 60. The P3 Financial Model • Functions of the Financial Model ─ Post-Financial Close • Budgeting Tool • Enables Lenders to Review Long-term Changes • Enables Investors to Calculate the Value of their Investment • Used by Investors to Calculate Compensation Event Payments • Offtaker / CA Calculate Refinancing Gain • Offtaker / CA Calculate Termination Sum
  • 61. Private and Public Partnerships Move Mainstream Conclusions and Summary: 1. Infrastructure Overhaul in the U.S. 2. Increased Number of Projects procured using Alternative Project Delivery Methods 3. Greater Frequency of P3 Procurement 4. Increased Participation For Civil Engineers 5. Greater Knowledge & Involvement with Project Finance 6. More Infrastructure Projects + Expanded Roles for Civil Engineers = Greater and More Value
  • 62. Private and Public Partnerships Move Mainstream Acknowledgements: Principles of Project Finance By E.R. Yescombe Published by ElSevier Publishing
  • 63. WPI will offer this Fall 2016 On-Line & Monday Evenings 6:00 – 8:50 p.m. CE590 - Capital Facility Planning and Financing in Private and Public Partnerships Email: gjfitch@wpi.edu
  • 64. 64 CE590 – P3 Project Financing QUESTIONS?