SlideShare a Scribd company logo
1 of 3
Download to read offline
5 June 2020
Procurement in Focus
It’s all in the delivery – project delivery models for major infrastructure projects
The Basics
The project delivery model is the guiding aspect which
governs the relationship between the principal and the
contractor (and often, other stakeholders). Choosing
the correct delivery model for your infrastructure
project is vital to ensuring contractual obligations are
allocated appropriately, performance is guaranteed,
and a project runs smoothly and in accordance with
requirements.
Key Considerations
Before commencing any major infrastructure project, a
project team should identify the key factors and risks
which may arise during the course of the project and
which party is best placed to manage and deal with
those risks. Some factors to be considered are
detailed in the figure below.
Figure 1: Key considerations when choosing a
project delivery model
Types of Delivery Models
Linear models
These include more traditional construct only and
design and construct delivery models, where the
principal contracts with a contractor, who then
contracts with various subcontractors to deliver
different parts of the project.
Figure 2: Basic linear delivery model
A more complex type of linear model which is often
effective for large infrastructure projects is the design,
build, operate and maintain model (DBOM). As the
name suggests, in a DBOM model, the principal
engages a contractor to not only design and build the
infrastructure, but to operate and maintain it for a set
period of time – often between 5 and 30 years. The
Project objectives
 What are the ultimate project objectives and
outcomes?
 How is the project to be managed and handed over
on completion?
 Are there additional continuing obligations on a
party after completion, such as operating and
maintaining the project works or services?
Complexity
 How complex is the project?
 Are there significant or novel design elements?
 How will these risks be managed?
Performance requirements
 If the infrastructure is required to produce a certain
output (eg. energy), how is that output measured?
 How is that performance contractually guaranteed?
 What are the consequences for under or over-
performance?
Time and cost
 What pricing model is the contractor for the project
being engaged under (e.g. lump sum, schedule of
rates or guaranteed maximum price)?
 Is there a cost regime in place to incentivise the
contractor to achieve critical dates for completion
or for exceeding performance standards?
Experience
 Does the contractor regularly perform the required
project works?
 Has your organisation engaged them before?
 Familiarity with the contractor and their operations
may inform a different contracting approach.
Paul Muscat Craig Tanzer Lachlan Bongers Aaron Williams BJ Doyle Tayla Kamura
PARTNER SENIOR ASSOCIATE ASSOCIATE SENIOR PARALEGAL GRADUATE LAW CLERK
T: +61 7 5553 9485 T: +61 7 5553 9481 T: +61 7 5553 9535 T: +61 7 5553 9546 T: +61 7 5553 9544 T: +61 7 5553 9400
paul.muscat@minterellison.com craig.tanzer@minterellison.com Lachlan.bongers@minterellison.com aaron.williams@minterellison.com bj.doyle@minterellison.com tayla.kamura@minterellison.com
*Disclaimer: The information contained in this update is intended as a guide only. Professional advice should be sought before applying any of the information to particular circumstances. While every reasonable care has been taken in the preparation
of this update, MinterEllison does not accept liability for any errors it may contain.
principal finances the development and owns the
infrastructure, while paying set fees to the contractor
for the operation and maintenance. Alternatively, for
infrastructure which generates operational income like
toll roads, the contractor may provide the operation and
maintenance in exchange for a portion of that
operational income, which further incentivizes the
contractor to operate and maintain the infrastructure
optimally in order to maximise the operational income.
Linear model contracts for project delivery are direct,
commonly used, and effective for projects where the
scope and requirements of the project are known at the
time of contracting. They don’t provide as much room
for collaboration or innovation as some of the delivery
models discussed later in this article, but their relative
simplicity can allow for cheaper procurement processes
and efficient contract administration, especially for less
complex projects.
Construction Management
In a construction management model, the principal
engages a construction manager to manage the
construction works on the principal’s behalf. The
principal engages any required design consultants
directly, and also engages the trade contractors directly
(with the construction manager acting as the principal’s
agent in these transactions).
Figure 3: Construction management delivery model
This model is particularly useful when the principal
needs to maintain direct control over the project while it
is being undertaken, for example, when a state
government is upgrading a hospital which must remain
operational during the upgrade works.
Otherwise though, this model can be complicated from
a contract administration perspective, and the principal
takes on added risk because they’ll need to claim
against each of the trade contractors directly (instead
of just claiming against one head contractor who
contracted with many subcontractors) if something
goes wrong. Likewise, the principal bears the risk of
cost overrun from all contractors, instead of relying on
a fixed price head contract and having the head
contractor bear the risk of subcontractor cost overrun,
as in the linear model. The principal also takes on the
added cost of the construction manager.
Public Private Partnerships (PPPs)
As the name suggests, the PPP model involves a more
collaborative approach between the public and private
sectors. This can make it particularly useful for more
complex and innovative projects. Typically, the
government entity commissioning the project (the
principal) will provide an output-based rather than
completely prescriptive specification for private
contractors (often private consortiums) to tender for.
The principal then engages the chosen contractor to
deliver the services over a long period of time –
typically 25 to 30 years or more – and the contractor
finances, designs, constructs, operates and/or
maintains the infrastructure, depending on the contract
and type of PPP required.
Figure 4: Example PPP delivery model
The ownership of the infrastructure varies depending
on what type of PPP is being implemented for the
project. Two common types are outlined below.
Build, own, operate and transfer (BOOT) – the
contractor finances and builds the infrastructure, often
with some funding provided by the government
principal. The contractor owns and operates the
infrastructure for a set period of time, during which the
principal pays fees to use the infrastructure, and at the
end of the set period the ownership of the infrastructure
is transferred to the government principal, either freely
or for a fee set in the initial contract.
Design, build, finance and operate (DBFO) – the
contractor designs, builds, finances and operates the
infrastructure development, leasing it to the
government principal for an agreed period of time at
agreed rates depending on whether agreed KPI’s are
met. At the end of the set period the ownership of the
infrastructure remains with the contractor.
There are many other variations to each party’s
requirements under the contract, but generally
Paul Muscat Craig Tanzer Lachlan Bongers Aaron Williams BJ Doyle Tayla Kamura
PARTNER SENIOR ASSOCIATE ASSOCIATE SENIOR PARALEGAL GRADUATE LAW CLERK
T: +61 7 5553 9485 T: +61 7 5553 9481 T: +61 7 5553 9535 T: +61 7 5553 9546 T: +61 7 5553 9544 T: +61 7 5553 9400
paul.muscat@minterellison.com craig.tanzer@minterellison.com Lachlan.bongers@minterellison.com aaron.williams@minterellison.com bj.doyle@minterellison.com tayla.kamura@minterellison.com
*Disclaimer: The information contained in this update is intended as a guide only. Professional advice should be sought before applying any of the information to particular circumstances. While every reasonable care has been taken in the preparation
of this update, MinterEllison does not accept liability for any errors it may contain.
speaking under a PPP model, the government principal
pays the contractor over the term of the contract based
on what services the contractor is providing and how
those services are being delivered against various
contractual KPIs. The contractor is the one who bears
the cost risks over the life of the contract because the
fees to be paid by the principal are set ahead of time to
increase or decrease according to those contractual
KPI’s. In this way, efficiency and quality are
encouraged in the design, construction and operation
of the infrastructure, which is why the PPP model lends
itself well to large scale projects where the principal
seeks innovative solutions from providers. The better
the solution provided by the contractor, the more they
will reap the benefits.
From a cashflow standpoint, the long term of the
contract also allows for the contractor to benefit from
steady incoming payments, and allows principals to
benefit from known outgoing costs of the operation of
the infrastructure (within the range calculated in
accordance with KPIs), for an extended period of time.
Some important points to note though, are that the
success of the project relies heavily on well-defined
specifications and performance agreed by the principal
and the contractor. The upfront costs of this model can
therefore be higher than others because the tendering
and contract negotiation processes are complicated.
The principal also generally needs to have a higher
degree of technical skills to be able to assess effective
tenders and negotiate the technical aspects of the
contract with the provider. If these upfront cost hurdles
can be met though, this model can be very successful
over the lifespan of a major infrastructure project.
Alliance models
Alliance models involve a government principal
collaborating with one or more other parties (for
example, a design contractor and construction
contractor, or a materials supplier and a construction
contractor) to deliver infrastructure which the principal
will eventually take ownership of. The parties share
both the risks and rewards of the project on a ‘no-fault,
no-blame’ basis, and decisions usually need to be
unanimous.
Figure 5: Alliance delivery model
Usually the non-owner parties are guaranteed to be
reimbursed their direct project costs and overheads,
but past that the return from the project is based on its
effectiveness. If the actual delivery of the project
exceeds agreed targets the reward is shared between
the parties according to an agreed ‘gain-share’ formula,
but likewise if the project delivery does not meet
agreed targets an agreed ‘pain-share’ formula will
apply.
The mutual interests of all the parties involved can
often lead to better solutions than more adversarial
contracting models, but also means that maintaining
relationships between parties in the alliance is vital.
These relationships can be costly to establish and
maintain at times, and the principal will bear the major
brunt of any catastrophic failure of the project, because
the other parties are guaranteed to be paid at least
their base costs and overheads.
For this reason, this model often works best when the
contractors have worked well with the principal
previously. Even if this is the case, alliance models
should generally only be considered for the delivery of
complex infrastructure projects where significant
innovation is required, where risks are unpredictable
and can best be managed collectively, and when the
government principal can be closely involved with the
project and add value through their own contributions.
Conclusion
Consideration of which delivery model to use for a
given infrastructure project is vital to ensuring the
efficient and effective delivery of the project. Each of
the available models offers its own pros and cons
which make them suitable for different situations. The
decision as to which delivery model to implement can
be a complicated one, but with deliberate consideration
of the requirements of the project, the optimal solution
can always be found for any given infrastructure
project.
If you would like any advice or for further information
about any of the above project delivery models, please
contact Paul Muscat (details below).
*All delivery model flowcharts sourced from the
Australian Government, Department of Infrastructure
and Regional Development, National Public Private
Partnership Guidelines, Volume 1: Procurement
Options Analysis (December 2008).

More Related Content

What's hot

Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsAssociation for Project Management
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionDBL Law
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...Association for Project Management
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...Association for Project Management
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
Project Delivery Methods
Project Delivery MethodsProject Delivery Methods
Project Delivery MethodsStacy Abernathy
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 

What's hot (20)

Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contracts
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in Construction
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
Integrated project-delivery
Integrated project-deliveryIntegrated project-delivery
Integrated project-delivery
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 
Design-Build Operate and Finance
Design-Build Operate and FinanceDesign-Build Operate and Finance
Design-Build Operate and Finance
 
Akinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedAkinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 Submitted
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Procurement types
Procurement typesProcurement types
Procurement types
 
Project Delivery Methods
Project Delivery MethodsProject Delivery Methods
Project Delivery Methods
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Practitioner class 3: Contract strategy
Practitioner class 3: Contract strategyPractitioner class 3: Contract strategy
Practitioner class 3: Contract strategy
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 

Similar to Procurement in Focus - the pros and cons of various project delivery models

Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpmKaila Turla
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1reddvise
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt2cd
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure developmentsakariya88
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfTarigTaha3
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project DeliverySHKLaw
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)James Baker
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 

Similar to Procurement in Focus - the pros and cons of various project delivery models (20)

Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpm
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure development
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Bkozlowski wpa
Bkozlowski wpaBkozlowski wpa
Bkozlowski wpa
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project Delivery
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
IPD-Whitepaper_2018-2.pdf
IPD-Whitepaper_2018-2.pdfIPD-Whitepaper_2018-2.pdf
IPD-Whitepaper_2018-2.pdf
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Contract Negotiations
Contract NegotiationsContract Negotiations
Contract Negotiations
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 

More from Construction in Focus

Procurement in Focus - Strategic Contracting.pdf
Procurement in Focus - Strategic Contracting.pdfProcurement in Focus - Strategic Contracting.pdf
Procurement in Focus - Strategic Contracting.pdfConstruction in Focus
 
Construction in Focus - Security of payment during the COVID-19 pandemic
Construction in Focus - Security of payment during the COVID-19 pandemicConstruction in Focus - Security of payment during the COVID-19 pandemic
Construction in Focus - Security of payment during the COVID-19 pandemicConstruction in Focus
 
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Construction in Focus
 
Procurement in Focus - Amendments to electoral provisions in the Local Govern...
Procurement in Focus - Amendments to electoral provisions in the Local Govern...Procurement in Focus - Amendments to electoral provisions in the Local Govern...
Procurement in Focus - Amendments to electoral provisions in the Local Govern...Construction in Focus
 
Procurement in focus: common probity pitfalls and how to avoid them - june 2019
Procurement in focus: common probity pitfalls and how to avoid them - june 2019Procurement in focus: common probity pitfalls and how to avoid them - june 2019
Procurement in focus: common probity pitfalls and how to avoid them - june 2019Construction in Focus
 
Construction in Focus - New cladding regulation sets the construction industr...
Construction in Focus - New cladding regulation sets the construction industr...Construction in Focus - New cladding regulation sets the construction industr...
Construction in Focus - New cladding regulation sets the construction industr...Construction in Focus
 

More from Construction in Focus (7)

Procurement in Focus - Strategic Contracting.pdf
Procurement in Focus - Strategic Contracting.pdfProcurement in Focus - Strategic Contracting.pdf
Procurement in Focus - Strategic Contracting.pdf
 
Construction in Focus - Security of payment during the COVID-19 pandemic
Construction in Focus - Security of payment during the COVID-19 pandemicConstruction in Focus - Security of payment during the COVID-19 pandemic
Construction in Focus - Security of payment during the COVID-19 pandemic
 
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
 
Procurement in Focus - Amendments to electoral provisions in the Local Govern...
Procurement in Focus - Amendments to electoral provisions in the Local Govern...Procurement in Focus - Amendments to electoral provisions in the Local Govern...
Procurement in Focus - Amendments to electoral provisions in the Local Govern...
 
Procurement in focus: common probity pitfalls and how to avoid them - june 2019
Procurement in focus: common probity pitfalls and how to avoid them - june 2019Procurement in focus: common probity pitfalls and how to avoid them - june 2019
Procurement in focus: common probity pitfalls and how to avoid them - june 2019
 
Construction in Focus - New cladding regulation sets the construction industr...
Construction in Focus - New cladding regulation sets the construction industr...Construction in Focus - New cladding regulation sets the construction industr...
Construction in Focus - New cladding regulation sets the construction industr...
 
BIF is coming, are you ready?
BIF is coming, are you ready?BIF is coming, are you ready?
BIF is coming, are you ready?
 

Recently uploaded

国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》o8wvnojp
 
POLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxPOLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxAbhishekchatterjee248859
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementShubhiSharma858417
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书Fir sss
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书Fir sss
 
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书Fs Las
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书Fir L
 
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一st Las
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书Fir sss
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一jr6r07mb
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSDr. Oliver Massmann
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书SD DS
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Dr. Oliver Massmann
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书1k98h0e1
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书SD DS
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
 
POLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptxPOLICE ACT, 1861 the details about police system.pptx
POLICE ACT, 1861 the details about police system.pptx
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreement
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书
 
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
 
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
如何办理(UNK毕业证书)内布拉斯加大学卡尼尔分校毕业证学位证书
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
 

Procurement in Focus - the pros and cons of various project delivery models

  • 1. 5 June 2020 Procurement in Focus It’s all in the delivery – project delivery models for major infrastructure projects The Basics The project delivery model is the guiding aspect which governs the relationship between the principal and the contractor (and often, other stakeholders). Choosing the correct delivery model for your infrastructure project is vital to ensuring contractual obligations are allocated appropriately, performance is guaranteed, and a project runs smoothly and in accordance with requirements. Key Considerations Before commencing any major infrastructure project, a project team should identify the key factors and risks which may arise during the course of the project and which party is best placed to manage and deal with those risks. Some factors to be considered are detailed in the figure below. Figure 1: Key considerations when choosing a project delivery model Types of Delivery Models Linear models These include more traditional construct only and design and construct delivery models, where the principal contracts with a contractor, who then contracts with various subcontractors to deliver different parts of the project. Figure 2: Basic linear delivery model A more complex type of linear model which is often effective for large infrastructure projects is the design, build, operate and maintain model (DBOM). As the name suggests, in a DBOM model, the principal engages a contractor to not only design and build the infrastructure, but to operate and maintain it for a set period of time – often between 5 and 30 years. The Project objectives  What are the ultimate project objectives and outcomes?  How is the project to be managed and handed over on completion?  Are there additional continuing obligations on a party after completion, such as operating and maintaining the project works or services? Complexity  How complex is the project?  Are there significant or novel design elements?  How will these risks be managed? Performance requirements  If the infrastructure is required to produce a certain output (eg. energy), how is that output measured?  How is that performance contractually guaranteed?  What are the consequences for under or over- performance? Time and cost  What pricing model is the contractor for the project being engaged under (e.g. lump sum, schedule of rates or guaranteed maximum price)?  Is there a cost regime in place to incentivise the contractor to achieve critical dates for completion or for exceeding performance standards? Experience  Does the contractor regularly perform the required project works?  Has your organisation engaged them before?  Familiarity with the contractor and their operations may inform a different contracting approach.
  • 2. Paul Muscat Craig Tanzer Lachlan Bongers Aaron Williams BJ Doyle Tayla Kamura PARTNER SENIOR ASSOCIATE ASSOCIATE SENIOR PARALEGAL GRADUATE LAW CLERK T: +61 7 5553 9485 T: +61 7 5553 9481 T: +61 7 5553 9535 T: +61 7 5553 9546 T: +61 7 5553 9544 T: +61 7 5553 9400 paul.muscat@minterellison.com craig.tanzer@minterellison.com Lachlan.bongers@minterellison.com aaron.williams@minterellison.com bj.doyle@minterellison.com tayla.kamura@minterellison.com *Disclaimer: The information contained in this update is intended as a guide only. Professional advice should be sought before applying any of the information to particular circumstances. While every reasonable care has been taken in the preparation of this update, MinterEllison does not accept liability for any errors it may contain. principal finances the development and owns the infrastructure, while paying set fees to the contractor for the operation and maintenance. Alternatively, for infrastructure which generates operational income like toll roads, the contractor may provide the operation and maintenance in exchange for a portion of that operational income, which further incentivizes the contractor to operate and maintain the infrastructure optimally in order to maximise the operational income. Linear model contracts for project delivery are direct, commonly used, and effective for projects where the scope and requirements of the project are known at the time of contracting. They don’t provide as much room for collaboration or innovation as some of the delivery models discussed later in this article, but their relative simplicity can allow for cheaper procurement processes and efficient contract administration, especially for less complex projects. Construction Management In a construction management model, the principal engages a construction manager to manage the construction works on the principal’s behalf. The principal engages any required design consultants directly, and also engages the trade contractors directly (with the construction manager acting as the principal’s agent in these transactions). Figure 3: Construction management delivery model This model is particularly useful when the principal needs to maintain direct control over the project while it is being undertaken, for example, when a state government is upgrading a hospital which must remain operational during the upgrade works. Otherwise though, this model can be complicated from a contract administration perspective, and the principal takes on added risk because they’ll need to claim against each of the trade contractors directly (instead of just claiming against one head contractor who contracted with many subcontractors) if something goes wrong. Likewise, the principal bears the risk of cost overrun from all contractors, instead of relying on a fixed price head contract and having the head contractor bear the risk of subcontractor cost overrun, as in the linear model. The principal also takes on the added cost of the construction manager. Public Private Partnerships (PPPs) As the name suggests, the PPP model involves a more collaborative approach between the public and private sectors. This can make it particularly useful for more complex and innovative projects. Typically, the government entity commissioning the project (the principal) will provide an output-based rather than completely prescriptive specification for private contractors (often private consortiums) to tender for. The principal then engages the chosen contractor to deliver the services over a long period of time – typically 25 to 30 years or more – and the contractor finances, designs, constructs, operates and/or maintains the infrastructure, depending on the contract and type of PPP required. Figure 4: Example PPP delivery model The ownership of the infrastructure varies depending on what type of PPP is being implemented for the project. Two common types are outlined below. Build, own, operate and transfer (BOOT) – the contractor finances and builds the infrastructure, often with some funding provided by the government principal. The contractor owns and operates the infrastructure for a set period of time, during which the principal pays fees to use the infrastructure, and at the end of the set period the ownership of the infrastructure is transferred to the government principal, either freely or for a fee set in the initial contract. Design, build, finance and operate (DBFO) – the contractor designs, builds, finances and operates the infrastructure development, leasing it to the government principal for an agreed period of time at agreed rates depending on whether agreed KPI’s are met. At the end of the set period the ownership of the infrastructure remains with the contractor. There are many other variations to each party’s requirements under the contract, but generally
  • 3. Paul Muscat Craig Tanzer Lachlan Bongers Aaron Williams BJ Doyle Tayla Kamura PARTNER SENIOR ASSOCIATE ASSOCIATE SENIOR PARALEGAL GRADUATE LAW CLERK T: +61 7 5553 9485 T: +61 7 5553 9481 T: +61 7 5553 9535 T: +61 7 5553 9546 T: +61 7 5553 9544 T: +61 7 5553 9400 paul.muscat@minterellison.com craig.tanzer@minterellison.com Lachlan.bongers@minterellison.com aaron.williams@minterellison.com bj.doyle@minterellison.com tayla.kamura@minterellison.com *Disclaimer: The information contained in this update is intended as a guide only. Professional advice should be sought before applying any of the information to particular circumstances. While every reasonable care has been taken in the preparation of this update, MinterEllison does not accept liability for any errors it may contain. speaking under a PPP model, the government principal pays the contractor over the term of the contract based on what services the contractor is providing and how those services are being delivered against various contractual KPIs. The contractor is the one who bears the cost risks over the life of the contract because the fees to be paid by the principal are set ahead of time to increase or decrease according to those contractual KPI’s. In this way, efficiency and quality are encouraged in the design, construction and operation of the infrastructure, which is why the PPP model lends itself well to large scale projects where the principal seeks innovative solutions from providers. The better the solution provided by the contractor, the more they will reap the benefits. From a cashflow standpoint, the long term of the contract also allows for the contractor to benefit from steady incoming payments, and allows principals to benefit from known outgoing costs of the operation of the infrastructure (within the range calculated in accordance with KPIs), for an extended period of time. Some important points to note though, are that the success of the project relies heavily on well-defined specifications and performance agreed by the principal and the contractor. The upfront costs of this model can therefore be higher than others because the tendering and contract negotiation processes are complicated. The principal also generally needs to have a higher degree of technical skills to be able to assess effective tenders and negotiate the technical aspects of the contract with the provider. If these upfront cost hurdles can be met though, this model can be very successful over the lifespan of a major infrastructure project. Alliance models Alliance models involve a government principal collaborating with one or more other parties (for example, a design contractor and construction contractor, or a materials supplier and a construction contractor) to deliver infrastructure which the principal will eventually take ownership of. The parties share both the risks and rewards of the project on a ‘no-fault, no-blame’ basis, and decisions usually need to be unanimous. Figure 5: Alliance delivery model Usually the non-owner parties are guaranteed to be reimbursed their direct project costs and overheads, but past that the return from the project is based on its effectiveness. If the actual delivery of the project exceeds agreed targets the reward is shared between the parties according to an agreed ‘gain-share’ formula, but likewise if the project delivery does not meet agreed targets an agreed ‘pain-share’ formula will apply. The mutual interests of all the parties involved can often lead to better solutions than more adversarial contracting models, but also means that maintaining relationships between parties in the alliance is vital. These relationships can be costly to establish and maintain at times, and the principal will bear the major brunt of any catastrophic failure of the project, because the other parties are guaranteed to be paid at least their base costs and overheads. For this reason, this model often works best when the contractors have worked well with the principal previously. Even if this is the case, alliance models should generally only be considered for the delivery of complex infrastructure projects where significant innovation is required, where risks are unpredictable and can best be managed collectively, and when the government principal can be closely involved with the project and add value through their own contributions. Conclusion Consideration of which delivery model to use for a given infrastructure project is vital to ensuring the efficient and effective delivery of the project. Each of the available models offers its own pros and cons which make them suitable for different situations. The decision as to which delivery model to implement can be a complicated one, but with deliberate consideration of the requirements of the project, the optimal solution can always be found for any given infrastructure project. If you would like any advice or for further information about any of the above project delivery models, please contact Paul Muscat (details below). *All delivery model flowcharts sourced from the Australian Government, Department of Infrastructure and Regional Development, National Public Private Partnership Guidelines, Volume 1: Procurement Options Analysis (December 2008).