3. INDEX
1- CN 1300 & 1400 - Completion of Faculty Environmental Design…………………. 4
2- CN 6600 - General Materials and Laboratories…………………………………….. 5
3- CN 6601 - Completion of Faculty of Science……………………………………….. 6
4- CN 6300 - Biotechnoly and Laboratories…………………………………………… 7
5- CN 2650 - Car Parking……………………………………………………………...... 8
6- CN 460 - Class Rooms for 3 Buildings ( slemaniyah 1 – slemaneyah 2 – faysaleyah ). 9
7- CN 711 - Completion of Scientific Societies……………………………………….. 10
8- CN 241 - English Language Center ( 2 Building )…………………………………… 11
9- Organization Chart…………………………………………………………………... 12
10- Planned VS Actual…………………………………………………………………… 13
11- Penalty Amount……………………………………………………………………… 14
3
Page
Al Muhaidib Contracting Co.
4. KAU PROJECTS ( CN 1300 & 1400 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start AUG 2010
Finish DEC 2012
Progress 100 %
Project Value 36,554 Million SAR
Earned Value 33,244 Million SAR
Invoiced 3,310 Million SAR Penalty
deducted
Variance Balanced 0 SAR
Manpower 0
Al Muhaidib Contracting Co. 4
Project Scope
Completion of Faculty Environmental
Design
Remaining Work &
Issues
• Paper works on going
Comments Building already occupied by client
Expected Final
Handover
20-OCT-2014
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start AUG 2006
Finish OCT 2010
Progress 100 %
Project Value 87,999 Million SAR
Earned Value 87,999 Million SAR
Net Invoiced 0 SAR
Variance Balanced 0 SAR
Manpower 0
CN 1300
CN 1400
5. KAU PROJECTS ( CN 6600 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start DEC 2008
Finish MAR 2013
Progress 100 %
Project Value 87,999 Million SAR
Earned Value 75,388 Million SAR
Net Invoiced 1,760 Million SAR 2% retention
31/NOV/2013 Submit
21/DEC/2013 Approved
10,851 Million SAR Penalty
Variance Balanced 0 SAR
Manpower 0
Al Muhaidib Contracting Co. 5
Project Scope
General Materials and Laboratories
. The structure includes lower level parking and five levels for the facilities including
the pent house.
. Scope of work includes construction of the structure and the finishing of the first
and the fourth floor including electro-mechanical facilities
Remaining Work & Issues • Completed and paper works on going
Comment Building already occupied by client
Expected Final Handover 20-OCT-2014
6. KAU PROJECTS ( CN 6601 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start OCT 2011
Finish SEP 2013
Progress 100 %
Project Value 47,971 Million SAR
Earned Value 41,890 Million SAR
Net Invoiced 960,117 Thousand SAR 2% retention
5,120 Million SAR Penalty
Variance Balanced 0 SAR
Manpower( Direct ) 0
Manpower( Indirect ) 3 Guard
Al Muhaidib Contracting Co. 6
Project Scope
Completion of Faculty of Science
. Scope of work includes finishing works of second and the third floor including
electro-mechanical facilities
Remaining Work & Issues
• Completed and paper works on going
Comment Building already occupied by client
Expected Final Handover 20-OCT-2014
7. KAU PROJECTS ( CN 6300 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start MAY 2010
Finish JUL 2013
Progress 90 %
Project Value 106,094 Million SAR
Earned Value 105,701Million SAR
Net Invoiced 0 SAR
392,770 Thousand SAR Supervision Fees
Variance Balanced 0 SAR
Manpower ( Direct ) 37
Manpower ( Indirect ) 41
Saudi 22
Al Muhaidib Contracting Co. 7
Project Scope
Biotechnology and Laboratories
. The structure includes lower level parking and four levels for the facilities including the pent house.
. Scope of work includes construction of laboratories, research areas, museums, storage for chemicals
/ gases, office spaces, and conference facilities.
Remaining Work & Issues
• Radiation Room ( Additional Work )
• Fire Fighting ( Only Chemical Flashing )
• White and Turk Board
• Air balance
• B.M.S
Expected Final Handover END OF DEC 2014
8. KAU PROJECTS ( CN 2650 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start APR 2011
Finish SEP 2013
Progress 100 %
Project Value 20,358 Million SAR
Earned Value 17,810 Million SAR
Net Invoiced 407,172 Thousand SAR 2% Retention
2,140 Million SAR Penalty
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 8
Project Scope
Car Parking
. Scope of work includes finishing works in
the car parking under the academic square.
Remaining Work &
Issues
• paper work on going
Expected Final
Handover
20-OCT-2014
9. KAU PROJECTS ( CN 460 )
Client Zuhair Fayez Partnership
Contract Type Re-Measured
Start AUG 2010
Finish AUG 2011
Progress 90 %
Project Value 55,785 Million SAR
Earned Value 54,687Million SAR
1,097 Million SAR Penalty
Net Invoiced 0 SAR
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 9
Project Scope
Class Rooms for 3 Buildings :
1. Boys
2. Girls
3. Faysaliyah
Remaining Work &
Issues
• Cladding ( Under Inspection )
• AHU ( by end of OCT )
Comment • Building already occupied by client
Expected Final
Handover
Pending Complete
10. KAU PROJECTS ( CN 711 )
Client Zuhair Fayez
Partnership
Contract Type Re-Measured
Start DEC 2011
Finish JUL 2012
Progress 100 %
Project Value 14,856 Million SAR
Earned Value 14,113 Million SAR
Net Invoiced 742,838 Thousand SAR 2% Retention
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 10
Project Scope
Completion of Scientific Societies
. Scope of work includes finishing of conference facilities, office spaces, seminar
lounges and auditorium along with the site development which involves, asphalt
road, interlocking pavements and landscape.
Remaining Work & Issues • Paper work on going
Expected Final Handover 20-OCT-2014
11. KAU PROJECTS ( CN 241 )
Client Zuhair Fayez Partnership
Contract Type Re-Measured
Start JAN 2012
Finish DEC 2014
Progress 67.37 %
Project Value 141 Million SAR
Earned Value 77,694 Million SAR
Net Invoiced 2,150 Million SAR 25-AUG-2014
Variance Balanced 63,306 Million SAR
2,848 Million SAR Invoice
submitted not
approved from
Consultant
Manpower ( Direct ) 273
Manpower ( Indirect ) 76
Saudi 40
Al Muhaidib Contracting Co. 11
Project Scope
English Language Center ( 2 Building )
The structure includes four levels for the
facilities including the pent house.
Remaining Work &
Issues
• Elevator ( In Progress )
• BMS
Expected Primary
Handover
• 30-DEC-2014
Part A
Part B
CN 241 - Part A
Project Scope
English Language Center ( 2 Building )
The structure includes four levels for the
facilities including the pent house.
Remaining Work &
Issues
• ( In Progress )
Expected Primary
Handover
• 30-DEC-2014
CN 241 - Part B