Feasibility
Tasks: Establish technical possibilities and
involve other specialists.
People
directly
involved: Client representatives, architects,
engineers and quantity surveyors.
4. ‘Azizan Supardi, 2018
Outline
proposals
Tasks: Analyze the brief and consider alternative
approaches.
People
directly
involved: Client, architects, engineers, quantity
surveyors and specialist as required.
5. ‘Azizan Supardi, 2018
Scheme
design
Tasks: Present spatial arrangement and materials
to be used.
People
directly
involved: Client, architects, engineers, quantity
surveyors and specialist and all statutory
and other approving authorities.
6. ‘Azizan Supardi, 2018
Detail design
Tasks: Develop design into detailed drawings
and specifications.
People
directly
involved: Architects, engineers, quantity surveyors
and specialist, contractor (if appointed).
8. ‘Azizan Supardi, 2018
Tender
document
Tasks: Provide information for quantity
surveyors to produce bills and answer
querries.
People
directly
involved: Architects, quantity surveyors and
contractor (if appointed).
9. ‘Azizan Supardi, 2018
Tender
action
Tasks: Finalise tender documents, suggest
tenderers and help client select.
People
directly
involved: Architects, quantity surveyors, engineers,
contractor and client.
11. ‘Azizan Supardi, 2018
Operations
on site
Tasks: Attend site meetings and supervise the
work and payments.
People
directly
involved: Architects, quantity surveyors, engineers,
contractor, subcontractor and client.
12. ‘Azizan Supardi, 2018
Completion
Tasks: Acceptance of the completed building and
procures for any defects.
People
directly
involved: Architects, quantity surveyors, engineers,
contractor and client.
13. ‘Azizan Supardi, 2018
Feed-back
Tasks: Legal responsibility for any failure and
opportunity for experience.
People
directly
involved: Architects, quantity surveyors, engineers,
contractor and client.
15. ‘Azizan Supardi, 2018
WORKING DRAWING
FeasibilityInception
Outline
proposals
Scheme
design
Detail design
Production
information
Tender
document
Tender
action
Project
planning
Operations
on site
Completion
Feed-back
BRIEFING