SlideShare a Scribd company logo
1 of 79
Download to read offline
Heavy Duty GT
Maintenance
2 /
GE /
February 11, 2010
• Maintenance costs and equipment’s availability are two of the most
important parameters for the productivity and profit of a production Plant.
• Gas turbine influence on the above parameters is very signifìcant, and
therefore it is necessary to issue a maintenance program based on the
following milestones :
1. - Frequency and type of scheduied inspections
2. - Spare parts planning
3. - Control of gas turbine operation and lite affecting factors
PRODUCTION PLANT SPECIFIC CHARACTERISTICS
AND PRIORITIES AVERAGE PERSONNEL TRADE
SKILL RECOMMENDATIONS FROM GAS TURBINE
OEM, BASED ON THE FOLLOWING RULES:
Maintenance Considerations
3 /
GE /
February 11, 2010
Maintenance Planning
The major scope of maintenance planning is to reduce the Plant out of production
time to the minimum. To reach good results, the following factors should be taken in
to consideration :
• PECULIAR CHARACTERISTICS OF THE PRODUCTION PLANT
• AMBIENT CONDITIONS
• TYPE OF SERVICE (CONTINUOUS, INTERMITTENT, PEAK LOAD, ETC.)
• TYPE OF FUEL
• LOSS OF PRODUCTION COSTS DUE TO THE TURBINE SHUT-DOWN
TIME FOR INSPECTION/OVERHAULING
• MAN POWER LOCAL CAPABILITIES
• OEM MAINTENANCE RECOMMENDATIONS
4 /
GE /
February 11, 2010
Construction Features and Maintenance Flexibility
To facilitate turbine maintenance practices, the following major construction
features are designed into the majority of the heavy duty gas turbine engines :
• HORIZONTALLY SPLIT CASINGS FOR EASY ACCESS TO THE INTERNAL PARTS
• STATOR BLADES CAN BE SLID ON THE CASING GROOVE WITHOUT ROTOR
REMOVAL.
• ALL TURBINE ROTOR BLADES ARE NORMALLY MOMENT-WEIGHED AND
DISTRIBUTED CIRCUMFERENTIALLY ON THE TURBINE WHEEL BY COMPUTER
CHARTING PROGRAM, SO THAT NO SITE BALANCE IS GENERALLY REQUIRED IN
CASE OF BLADE SUBSTITUTION.
• ALL BEARING HOUSING AND LINERS ARE SPLIT ON THE HORIZONTAL CENTERLINE
SO THAT THEY MAY BE INSPECTED AND REPLACED, WHEN NECESSARY.
• BORESCOPE INSPECTION CAPABILITY.
5 /
GE /
February 11, 2010
Boroscope inspection ports
6 /
GE /
February 11, 2010
Boroscope inspection programming
The borescope inspection can be performed during a combustion inspection,
or during a planned or unplanned shutdown.
A planned borescope inspection program results in opening a turbine unit only
when necessary to repair or replace parts. It should be recognized that
inspection intervals are based on average unit operating modes. Adjustment of
these intervals may be made based on experience and the individual unit
mode of operation and the fuels used.
The borescope inspection program should include :
•Baseline inspection and recording of conditions, both written and
photographically, at the time of start-up.
•Periodic inspection and recording of the results.
The application of a monitoring program, utilizing the borescope, will allow
scheduling outage and pre-planning of parts requirements, resulting in lower
maintenance costs, higher availability and reliability of the gas turbine.
7 /
GE /
February 11, 2010
Boroscope Typycal Equipment
8 /
GE /
February 11, 2010
•Define a reference optimum gas turbine operating conditions, for which the life
of hot gas path components is maximum.
•The following are the most common “standard” operating configuration
considered and applied by the majority of them.
Maintenance and parts life affetting Factors
Under the above condition, the parts life is theoretically 100% of the design and
the recommended intervals between maintenance inspection are maximum.
For different operating conditions, higher maintenance factors must be applied.
Which correspond to reduced intervals between inspections and overhauling.
NATURAL GAS FUEL
CONTINUOUS OPERATION AT BASE LOAD
NO STEAM / WATER INJECTION
9 /
GE /
February 11, 2010
Standard Maintenance Schedule
10 /
GE /
February 11, 2010
Operating factors affecting maintenaince intervals
Continuous duty Cyclic duty
Rupture Thermal/mechanical fatigue
Creep LCF (Low Cycle Fatigue)
HCF (High Cycle Fatigue) Wear
Corrosion FOD( foreign objetcs damage)
Oxidation
Erosion
Wear/rubs
FOD
Causes of potential failures of gas path parts
11 /
GE /
February 11, 2010
Hour’s factors
• Fuel
• Steam injection
• Water injection
• Operating load
12 /
GE /
February 11, 2010
Fuel
13 /
GE /
February 11, 2010
Operating load
14 /
GE /
February 11, 2010
Water and Steam injection
The maintenance factor may be calculated with the following procedure:
M.F. = K + M x I
Where:
I = Percent steam injection referenced to the inlet air flow
M = 0 K = 1 for dry control and I < 2,2%
M = 0,18 K = 0,6 for dry control and I > 2,2%
15 /
GE /
February 11, 2010
• Start up with liquid fuel
• Start up sequence
• Sudden load changes
• Emergency shut downs
Start factors
16 /
GE /
February 11, 2010
Start up with liquid fuel normally causes higher thermal effects if
compared to natural gas fuel.
•Affected components: combustion and hot gas path parts.
•Maintenance factor for start up with No2 distillate = 1.5
Liquid fuel
17 /
GE /
February 11, 2010
Start up sequence
…fast loading start-up where unit is brought from standstill to
full speed no load with the normal sequence and then
submitted to fast load.
…emergency start-up the unit is brought from standstill to
full load with a sequence faster than the standard.
Where…
• Maintenance Factor for emergency start up = 20
• Maintenance Factor for fast-loading start up = 2
18 /
GE /
February 11, 2010
Sudden load changes
19 /
GE /
February 11, 2010
Sudden load changes
20 /
GE /
February 11, 2010
Emergency shut downs
21 /
GE /
February 11, 2010
Maintenance Interval Equation
22 /
GE /
February 11, 2010
Maintenance Interval Equation
23 /
GE /
February 11, 2010
An MS7001 user has accumulated operating data since the last hot gas path inspection and would like to
estimate when the next one should be scheduled. The user is aware from GE publications that the normal
HGP interval is 24,000 hours if operating on natural gas, with no water or steam injection, and at base load.
It is also understood that the nominal starts interval is 1200, based on normal startups, no trips, no
emergency starts. The actual operation of the unit since the last hot gas path inspection is much different
from the GE “baseline case.”
Annual hours on natural gas, base load
G = 3200 hr/yr
Annual hours on light distillate
D = 350 hr/yr
Annual hours on peak load
P = 120 hr/yr
Steam injection rate
I = 2.4%
Also, since the last hot gas path inspection,
140 Normal start-stop cycles:
40 Part load
100 Base load
0 Peak load
In addition,
E = 2 Emergency Starts with ramp to base load
F = 5 Fast loads ending in a normal shut down
from base load
T = 20 Starts with trips from base load
Example – HGP Maintenance Interval Calculation
24 /
GE /
February 11, 2010
For this particular unit, the second and third-stage nozzles are FSX-414 material. The unit operates on “dry
control curve.”
At a steam injection rate of 2.4%, the value of “M” is 0.18, and “K” is 0.6.
From the hours-based criteria, the maintenance factor is determined from Figure 43.
The hours-based adjusted inspection interval is therefore,
H = 24,000/1.25
H = 19,200 hours
[Note, since total annual operating hours is 3670, the estimated time to reach
19,200 hours is 5.24 years (19,200/3670).]
[K + M(I)] x [G + 1.5(D) + Af(H) + 6(P)]
(G + D + H + P)
MF =
[0.6 + 0.18(2.4)] x [3200 + 1.5(350) + 0 + 6(120)]
(3200 + 350 + 0 + 120)
MF = = 1.25
Example – HGP Maintenance Interval Calculation
25 /
GE /
February 11, 2010
From the starts-based criteria, the maintenance factor is determined as:
The total number of part load starts/stop is NA = 40/yr
The total number of base load starts/stop is NB = 100 + 2 + 5 + 20 = 127/yr
The total number of peak load starts/stop is NP = 0/yr
The adjusted inspection interval based on starts is
S = 1200/2.0
S = 600 starts
[Note, since the total annual number of starts is 167, the estimated time to reach
600 starts is 600/167 = 3.6 years.]
In this case, the starts-based maintenance factor is greater than the hours maintenance factor and
therefore the inspection interval is set by starts. The hot gas path inspection interval is 600
starts (or 3.6 years).
0.5 (NA)+(NB)+1.3(NP)+20(E)+2(F) +  (an-1)T
NA + NB + NP
MF =
0.5(40)+(127)+1.3(0)+20(2)+2(5)+(8–1)20
40+127+0
= 2
MF =
Example – HGP Maintenance Interval Calculation
26 /
GE /
February 11, 2010
Gas Turbine Maintenance
Maintenance Inspections
STAND-BY INSPECTIONS
RUNNING INSPECTIONS
DISMANTLING INSPECTIONS
27 /
GE /
February 11, 2010
STAND-BY INSPECTIONS
They are required when the engine is not in operation. During this period of time, the following
items should be checked :
LUBE OIL SYSTEM COMPONENTS
FUEL SYSTEM COMPONENTS
INTAKE SYSTEM AND FILTERS
INSTRUMENTATION SETTINGS AND REPAIRS/SUBSTITUTIONS
EMERGENCY BATTERIES STATUS
FLUIDS LEVELS (OILS, WATER, ETC.)
OTHER AUXILIARIES IN GENERAL
BORESCOPE INSPECTION FOR ALL THE INTERNAL PARTS
28 /
GE /
February 11, 2010
RUNNING INSPECTIONS
They are required when the engine is
in operation.
During this period of time, the records
of the most important functional
parameters must be done by the
operation personnel, every one or two
hours, in order to have a good
operation trend of the system.
This will help find the root causes of
gas turbine troubles.
TYPICAL PARAMETERS
29 /
GE /
February 11, 2010
DISMANTLING INSPECTIONS
Combustion System inspection
Hot Gas Path inspection
Major inspection
30 /
GE /
February 11, 2010
Gas Turbine Maintenance
Combustion system inspections
31 /
GE /
February 11, 2010
Combustion inspection – Key elements
32 /
GE /
February 11, 2010
Combustion inspection
33 /
GE /
February 11, 2010
Combustion inspection precedure
1. Prepare turbine compartment roof for removal
2. Remove turbine compartment roof and side
panels.
3. Remove liquid fuel lines (if applicable).
4. Remove atomizing air lines (if applicable).
5. Remove gas fuel lines (if applicable).
6. Remove steam injection lines (if applicable).
7. Remove water injection lines (if applicable).
8. Remove liquid fuel check valves.
9. Remove false start drain tubing.
10. Remove fuel nozzles.
34 /
GE /
February 11, 2010
11 Remove flame detectors and spark plugs.
12 Remove 11th stage cooling and sealing air
lines.
13 Unbolt and open up combustion outer casing
covers.
14 Remove crossfire tube retainers, combustion
liners, crossfire tubes and forward flow
sleeves.
15 Remove access port blank flange from upper
half turbine casing or the upper section of the
atomizing air extraction manifold.
16 Remove outer combustion casings and aft
flow sleeves.
17 Remove transition pieces.
Combustion inspection precedure
35 /
GE /
February 11, 2010
• Fuel nozzle (o burners)
• Combustion chamber components ( liner, cap, flow sleeve)
• Transition piece
• Cross-fire tubes
• Spark plug
• Flame detectors
GT Combustion inspection
During this inspection the status of following components should be verified and all necessary
repair/substitution is carried out:
Note:
For the lifting of main components see drawing
“ Gravity centres and weights”
36 /
GE /
February 11, 2010
The inspection of fuel nozzle is
necessary to clean up them from
internal combustion residual
carbon deposits and repair cracks,
as well as for the combustion
chamber.
Fuel nozzle (o burners)
37 /
GE /
February 11, 2010
Normally, cracks inspections carried out using dye penetrating fluids sprayed on
the components surface.
Fuel nozzle (o burners)
38 /
GE /
February 11, 2010
C. C. components ( liner, cap, flow sleeve)
39 /
GE /
February 11, 2010
INSPECTION CRITERIA
C. C. components ( liner, cap, flow sleeve)
40 /
GE /
February 11, 2010
C. C. components ( liner, cap, flow sleeve)
41 /
GE /
February 11, 2010
Crossfire Tube
42 /
GE /
February 11, 2010
Transition piece
43 /
GE /
February 11, 2010
Transition piece
44 /
GE /
February 11, 2010
SPARK PLUG ASSEMBLY
Spark plug
45 /
GE /
February 11, 2010
Flame Detector
Flame detector are checked for eventual electrical damage and carbon deposits on
the optical surface.
46 /
GE /
February 11, 2010
Flame Detector
47 /
GE /
February 11, 2010
Flame Detector
48 /
GE /
February 11, 2010
Gas Turbine Maintenance
Hot gas path parts inspections
49 /
GE /
February 11, 2010
GT Hot Gas path inspection – Key elements
50 /
GE /
February 11, 2010
GT Hot Gas path inspection
To carry out an inspection on the hot gas path, it is necessary to remove the upper half casing of
the turbine. Before proceding with disassembly, put jacks under the lower half casing, in order to
help the upper half casing slide upward when beign opened avoiding subjecting the remaing
parts of turbine casing to bending stress.
51 /
GE /
February 11, 2010
The disassembling procedure to access and remove the parts to be inspected is carried
out in the following sequence:
GT Hot Gas path inspection: Disassembly
1. Remove turbine compartment side panels. (If applicable).
2. Remove roof attachments. (If applicable)
3. Lift off turbine compartment roof. (If applicable).
4. Remove upper half cooling and sealing air piping.
5. Remove turbine casing wheel-space thermocouple wiring and
conduit.
6. Perform combustion inspection disassembly Operations.
7. Establish solid foundation and place mechanical screw jacks
under unit casings.
8. Remove upper half turbine casing.
9. Remove upper half first-stage nozzle.
10. Take turbine clearance checks.
11. Remove lower half first-stage nozzle.
12. ……
13. ……
52 /
GE /
February 11, 2010
• Combustion system .
• 1st stage Nozzle.
• 1st stage shrouds.
• 2ndstage Nozzle.
• 2ndstage shrouds.
• 1st and 2nd stage turbine buckets.
• Compressor Blade (Boroscope)
GT Hot Gas path inspection
During this inspection the status of the following gas turbine section components should
be verified and all necessary repair/substitution is carried out in case of natural gas or light
distillate fuel operation:
53 /
GE /
February 11, 2010
Opening Compressor and Turbine Rotor Position Checks
54 /
GE /
February 11, 2010
1. Inspect first, second and third stage turbine buckets.
2. Inspect first, second and third stage bucket cover-plates.
3. Inspect the Shroud Blocks.
4. Inspect second and third stage diaphragm segments.
5. Inspection the first stage nozzles ellipticity checks.
6. Inspect combustion system components
GT Hot Gas path inspection
55 /
GE /
February 11, 2010
First Stage Nozzle Inspection
56 /
GE /
February 11, 2010
Turbine clearance checks
57 /
GE /
February 11, 2010
Turbine Buckets Inspection
58 /
GE /
February 11, 2010
Turbine Buckets Inspection
59 /
GE /
February 11, 2010
Gas Turbine Maintenance
Major inspection/overhaul
60 /
GE /
February 11, 2010
GT Major inspection – Key elements
61 /
GE /
February 11, 2010
Major inspection/overhaul
The aim of a major inspection is to examine all rotor and stator
inner parts, from the filter chamber inlet throughthe exaust
system, including also the load gear and the driven machine.
A major inspection must be scheduled and organized in
accordance with the recommendations in the maintenaince
manual supplied along with the turbine, and with the results of
the combustion and hot gas path inspections carried out
beforehand.
In order to carry out a major inspection, all upper half casing
must be removed,so as to beable to remove the rotors. Before
proceeding with disassembly, jacks must be placed under the
bottom half casings, so as to ease the upper half casing to be
moved upward without subjecting the remain casings to
bending stress.
Maintenance forms must be used for record clearances all
rotor and stator parts.
Typical maintenaince forms
GT Major inspection
62 /
GE /
February 11, 2010
The disassembling procedure to access and remove the parts
to be inspected is done in the following sequence:
1. Remove accessory and load coupling guard.
2. Remove accessory and load coupling.
3. Check alignment rotor accessory side and load side and
record on maintenaince form.
4. Check the rotor positioning after disassembly upper-half
casing and record on maintenaince form.
5. Same sequence described for combustion and hot gas
path inspection.
6. Remove the Inlet duct Elbow, Exhaust Duct section,
Exhaust Insulation pannel, Upper half of Inlet plenum.
7. Fit additional jacks.
8. Disassamble the remaining upper half casingsand cover
from bearing blocks.
9. Record clearance between all rotor and statoric parts.
10. Extract rotors.
11. Open the guard on the accessory and load gears.
12. Open casings on the driven machine.
GT Major inspection: Disassembly
63 /
GE /
February 11, 2010
GT Major inspection
64 /
GE /
February 11, 2010
Tubine Bearing Inspection
65 /
GE /
February 11, 2010
Tubine Bearing Inspection
66 /
GE /
February 11, 2010
1. Inspect No. 1, 2 journal bearings and seals.
2. Inspect No. 1 thrust bearings and seals.
3. Clean, inspect compressor rotor, stator blade, inlet guide vanes and
compressor and turbine casings.
4. Inspect first, second and third-stage turbine buckets and wheel
dovetails.
5. Inspect first, second and third-stage shrouds and diaphragm seals.
6. Perform Hot Gas Path Inspection
GT Major inspection: Inspection
67 /
GE /
February 11, 2010
Components acceptability criteria
More example components acceptability criteria
68 /
GE /
February 11, 2010
Load gear site
alignment fixture
Turbine site
Attach the alignment fixture and dial indicators to the
turbine shaft and check the turbine to load gear alignment.
Refer to the Instructions and Data Alignment-Field, in the
Reference Drawings Section of the service manual for
alignment specifications.
Gas Turbine on-site Alignment
69 /
GE /
February 11, 2010
CHECKS TO BE DONE BEFORE
RESTARTING THE TURBINE
WARNING
TAKE CARE THAT NO FOREIGN
OBJECTS (TOOLS OR OTHER
HARDWARE) ARE FORGOTTEN
INSIDE TURBINE.
OTHER CHECKS ARE LISTED IN THE
SERVICE MANUAL SECT. 2
Gas Turbine Maintenance
70 /
GE /
February 11, 2010
The determination of the manpower and the relevant times required to carry
out the three levels of inspections depend on the following assumptions :
• Intervention with or without the assistance of the OEM
supervision
• Critical spares availability at the plant site
• Repair times in parallel to the substitution activities
• All the necessary standard and OEM’s recommended special
tooling available
• Skill of personnel
• Scheduled inspection
Manpower planning and type
71 /
GE /
February 11, 2010
To obtain successful maintenance planning and operating economical
results it is very important to consider the gas turbine system tear-
down time required to accomplish all the maintenance actions.
Due to the above, a good spare parts planning will reduce the waiting
time from disassembly to reassembly sequence period, during which
the plant is out of operation.
Spare Parts planning
72 /
GE /
February 11, 2010
SPARE PARTS
RECOMMEND
ED FOR
INSPECTIONS
Spare Parts planning
73 /
GE /
February 11, 2010
SPARE PARTS AVAILABILITY CAN BE OBTAINED IN TWO WAYS
By ordering the critical parts together to the main equipment purchase order
By issuing a mutual Customer -to- OEM After Sales Assistance contract which includes
spare parts availability in the OEM’s warehouse at any time during the turbine operating
life. This type of contracts are variable case by case and have different levels of costs, in
function of the required level of service.
THE CHOICE OF THE MOST CONVENIENT SOLUTION DEPENDS ON THE PLANT
PROFITABILITY CALCULATION RESULTS, WHICH SHOULD INCLUDE THE FOLLOWING
PARAMETERS :
• Daily loss of profit in case of turbounit out of operation
• Similar plants feedback experience
• Overall operating hours of the same gas turbine model club
• OEM’s availability and reliability percent average data for the gas turbine model
installed
Spare Parts Availability Criteria
74 /
GE /
February 11, 2010
Type of inspection Ref. turbine
rating (MW)
Average
crew size
8 hour
shifts
2 2 2
5 2 2
Combustion inspection 10 2 2
20 4 5
40 5 10
>100 6 13
2 2 7
5 2 7
Hot gas path parts 10 2 7
20 6 10
40 9 15
>100 10 30
2 4 10
5 4 14
Major inspection 10 4 15
20 8 20
40 10 35
>100 11 50
NOTE
Average values. For specific job values refer to the operating and maintenance manuals.
MI Man-Hour Assumptions
75 /
GE /
February 11, 2010
Availability and reliability data are very important for both gas turbine model
selection and maintenance.
These two factors are used to quantify the ratio between not scheduled gas
turbine “out of service” times and the potential operating time/year of the
gas turbine.
There are many different (but similar) formulas to calculate the above percent
values
Availability and Reliability Concepts
76 /
GE /
February 11, 2010
Availability is defined as “the probability of being available, independent of whether or not
the unit is needed”.
Reliability = 100 x [ PH - FOH] / PH [ % ]
Reliability is defined as “the probability of not being forced out of service when the unit is
needed”.
PH = Sum of the annual operating hours, standby (ready to start) hours, not
operating hours due to external causes.
FOH = Forced Outage Hours. Period of time during which the maintenance team
is actually working during forced outage.
POH = Planned Outage Hours. Period of time during which the maintenance team
is actually working during planned outage.
Availability = 100 x [ PH - (FOH+POH)] / PH [ % ]
Availability and Reliability Concepts
77 /
GE /
February 11, 2010
Estimated repair and replacement cycles
78 /
GE /
February 11, 2010
Estimated repair and replacement cycles
79 /
GE /
February 11, 2010
Estimated repair and replacement cycles

More Related Content

What's hot

Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositTurbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositProject Sales Corp
 
Steam Turbine Parts.pdf
Steam Turbine Parts.pdfSteam Turbine Parts.pdf
Steam Turbine Parts.pdfKAhmedRehman
 
GE Frame 9E Gas Turbine Nandipur Power Project
GE  Frame 9E Gas Turbine Nandipur Power ProjectGE  Frame 9E Gas Turbine Nandipur Power Project
GE Frame 9E Gas Turbine Nandipur Power ProjectZohaib Asif
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
 
Steam turbine
Steam turbineSteam turbine
Steam turbinewatbN kh
 
Gas Turbine Operation
Gas Turbine OperationGas Turbine Operation
Gas Turbine OperationMalik M. N.
 
Gas turbine technology
Gas turbine technologyGas turbine technology
Gas turbine technologyAshish kumar
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingTahoor Alam Khan
 
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010Shaun West
 
Ball & tube mill
Ball & tube millBall & tube mill
Ball & tube millStudy Hub
 
Steam turbine
Steam turbineSteam turbine
Steam turbineNathan
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overviewGaurav Kaushik
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 

What's hot (20)

Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositTurbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
 
Steam Turbine Parts.pdf
Steam Turbine Parts.pdfSteam Turbine Parts.pdf
Steam Turbine Parts.pdf
 
GE Frame 9E Gas Turbine Nandipur Power Project
GE  Frame 9E Gas Turbine Nandipur Power ProjectGE  Frame 9E Gas Turbine Nandipur Power Project
GE Frame 9E Gas Turbine Nandipur Power Project
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Gas Turbine Operation
Gas Turbine OperationGas Turbine Operation
Gas Turbine Operation
 
Gas turbine technology
Gas turbine technologyGas turbine technology
Gas turbine technology
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & Working
 
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
 
Ball & tube mill
Ball & tube millBall & tube mill
Ball & tube mill
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Gas turbine
Gas turbineGas turbine
Gas turbine
 
Ci
CiCi
Ci
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 

Similar to Gas Turbine Basics.pdf

Maintenance plan
Maintenance planMaintenance plan
Maintenance planNauman khan
 
Andrew Chant\'s CanWEA O &amp; M Presentation
Andrew Chant\'s CanWEA  O  &amp; M  PresentationAndrew Chant\'s CanWEA  O  &amp; M  Presentation
Andrew Chant\'s CanWEA O &amp; M Presentationmtingle
 
Utilities and oil movement-Final.pdf
Utilities and oil movement-Final.pdfUtilities and oil movement-Final.pdf
Utilities and oil movement-Final.pdfhariskhalil8
 
96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbine96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbinemanojg1990
 
Energy Auditing of Thermal Power plant
Energy Auditing of Thermal Power plantEnergy Auditing of Thermal Power plant
Energy Auditing of Thermal Power plantIRJET Journal
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaUdhayakumar Venkataraman
 
J parmar d gilmartin o&m paper
J parmar d gilmartin o&m paperJ parmar d gilmartin o&m paper
J parmar d gilmartin o&m paperjparmar100
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingeSAT Publishing House
 
IRJET- LPG Tank Burst Pressure Determination using FEM
IRJET- LPG Tank Burst Pressure Determination using FEMIRJET- LPG Tank Burst Pressure Determination using FEM
IRJET- LPG Tank Burst Pressure Determination using FEMIRJET Journal
 
IRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass ValveIRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass ValveIRJET Journal
 
IRJET- Analysis of Emission Data by using Testbed for Euro VI Norms
IRJET- Analysis of Emission Data by using Testbed for Euro VI NormsIRJET- Analysis of Emission Data by using Testbed for Euro VI Norms
IRJET- Analysis of Emission Data by using Testbed for Euro VI NormsIRJET Journal
 
Thermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine bladeThermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine bladeeSAT Publishing House
 
Thermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine bladeThermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine bladeeSAT Journals
 
Performance &amp; emission optimization of single cylinder diesel engine to m...
Performance &amp; emission optimization of single cylinder diesel engine to m...Performance &amp; emission optimization of single cylinder diesel engine to m...
Performance &amp; emission optimization of single cylinder diesel engine to m...eSAT Journals
 
IRJET- Static Structural and Modal Analysis of Secondary Air Flow System
IRJET- Static Structural and Modal Analysis of Secondary Air Flow SystemIRJET- Static Structural and Modal Analysis of Secondary Air Flow System
IRJET- Static Structural and Modal Analysis of Secondary Air Flow SystemIRJET Journal
 
An approach to evaluate the heat exchanger retrofit for installed industrial ...
An approach to evaluate the heat exchanger retrofit for installed industrial ...An approach to evaluate the heat exchanger retrofit for installed industrial ...
An approach to evaluate the heat exchanger retrofit for installed industrial ...eSAT Journals
 

Similar to Gas Turbine Basics.pdf (20)

Maintenance plan
Maintenance planMaintenance plan
Maintenance plan
 
Andrew Chant\'s CanWEA O &amp; M Presentation
Andrew Chant\'s CanWEA  O  &amp; M  PresentationAndrew Chant\'s CanWEA  O  &amp; M  Presentation
Andrew Chant\'s CanWEA O &amp; M Presentation
 
Utilities and oil movement-Final.pdf
Utilities and oil movement-Final.pdfUtilities and oil movement-Final.pdf
Utilities and oil movement-Final.pdf
 
96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbine96924703 performance-monitoring-for-gas-turbine
96924703 performance-monitoring-for-gas-turbine
 
I0354062068
I0354062068I0354062068
I0354062068
 
Energy Auditing of Thermal Power plant
Energy Auditing of Thermal Power plantEnergy Auditing of Thermal Power plant
Energy Auditing of Thermal Power plant
 
Condition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performaCondition monitoring of_steam_turbines_by_performa
Condition monitoring of_steam_turbines_by_performa
 
J parmar d gilmartin o&m paper
J parmar d gilmartin o&m paperJ parmar d gilmartin o&m paper
J parmar d gilmartin o&m paper
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
IRJET- LPG Tank Burst Pressure Determination using FEM
IRJET- LPG Tank Burst Pressure Determination using FEMIRJET- LPG Tank Burst Pressure Determination using FEM
IRJET- LPG Tank Burst Pressure Determination using FEM
 
IRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass ValveIRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass Valve
 
IRJET- Analysis of Emission Data by using Testbed for Euro VI Norms
IRJET- Analysis of Emission Data by using Testbed for Euro VI NormsIRJET- Analysis of Emission Data by using Testbed for Euro VI Norms
IRJET- Analysis of Emission Data by using Testbed for Euro VI Norms
 
144 M Information Notice.pdf
144 M Information Notice.pdf144 M Information Notice.pdf
144 M Information Notice.pdf
 
Thermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine bladeThermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine blade
 
Thermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine bladeThermal analysis of cooling effect on gas turbine blade
Thermal analysis of cooling effect on gas turbine blade
 
Performance &amp; emission optimization of single cylinder diesel engine to m...
Performance &amp; emission optimization of single cylinder diesel engine to m...Performance &amp; emission optimization of single cylinder diesel engine to m...
Performance &amp; emission optimization of single cylinder diesel engine to m...
 
1q05 performancemonitoring
1q05 performancemonitoring1q05 performancemonitoring
1q05 performancemonitoring
 
Warranty
WarrantyWarranty
Warranty
 
IRJET- Static Structural and Modal Analysis of Secondary Air Flow System
IRJET- Static Structural and Modal Analysis of Secondary Air Flow SystemIRJET- Static Structural and Modal Analysis of Secondary Air Flow System
IRJET- Static Structural and Modal Analysis of Secondary Air Flow System
 
An approach to evaluate the heat exchanger retrofit for installed industrial ...
An approach to evaluate the heat exchanger retrofit for installed industrial ...An approach to evaluate the heat exchanger retrofit for installed industrial ...
An approach to evaluate the heat exchanger retrofit for installed industrial ...
 

More from yusuf699644

Session 7 - Firepumps for the Oil .pdf
Session 7 - Firepumps for the Oil .pdfSession 7 - Firepumps for the Oil .pdf
Session 7 - Firepumps for the Oil .pdfyusuf699644
 
Short Course 6- Mechanical Seals and Sealing Systems.pdf
Short Course 6- Mechanical Seals and Sealing Systems.pdfShort Course 6- Mechanical Seals and Sealing Systems.pdf
Short Course 6- Mechanical Seals and Sealing Systems.pdfyusuf699644
 
Centrifugal-compressor-ge.pdf
Centrifugal-compressor-ge.pdfCentrifugal-compressor-ge.pdf
Centrifugal-compressor-ge.pdfyusuf699644
 
Materi-operation-kupang-amp-sumbagut.pdf
Materi-operation-kupang-amp-sumbagut.pdfMateri-operation-kupang-amp-sumbagut.pdf
Materi-operation-kupang-amp-sumbagut.pdfyusuf699644
 
dokumen.tips_api-682-presentation.pdf
dokumen.tips_api-682-presentation.pdfdokumen.tips_api-682-presentation.pdf
dokumen.tips_api-682-presentation.pdfyusuf699644
 
Pemeliharaan-pembangkit-listrik-tenaga-diesel.pdf
Pemeliharaan-pembangkit-listrik-tenaga-diesel.pdfPemeliharaan-pembangkit-listrik-tenaga-diesel.pdf
Pemeliharaan-pembangkit-listrik-tenaga-diesel.pdfyusuf699644
 
Comparison of API610 12th and 11th Editions (1).pdf
Comparison of API610 12th and 11th Editions (1).pdfComparison of API610 12th and 11th Editions (1).pdf
Comparison of API610 12th and 11th Editions (1).pdfyusuf699644
 
Materi-operation-gas-engine-tarakan.pdf
Materi-operation-gas-engine-tarakan.pdfMateri-operation-gas-engine-tarakan.pdf
Materi-operation-gas-engine-tarakan.pdfyusuf699644
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdfyusuf699644
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...yusuf699644
 
CENTRIFUGAL PUMPS TRAINING.pdf
CENTRIFUGAL PUMPS TRAINING.pdfCENTRIFUGAL PUMPS TRAINING.pdf
CENTRIFUGAL PUMPS TRAINING.pdfyusuf699644
 
Introduction to Pumps.pdf
Introduction to Pumps.pdfIntroduction to Pumps.pdf
Introduction to Pumps.pdfyusuf699644
 
Basic Pump Training Material .pdf
Basic Pump Training Material .pdfBasic Pump Training Material .pdf
Basic Pump Training Material .pdfyusuf699644
 
PLANT COMMISSIONING.pdf
PLANT COMMISSIONING.pdfPLANT COMMISSIONING.pdf
PLANT COMMISSIONING.pdfyusuf699644
 

More from yusuf699644 (16)

Session 7 - Firepumps for the Oil .pdf
Session 7 - Firepumps for the Oil .pdfSession 7 - Firepumps for the Oil .pdf
Session 7 - Firepumps for the Oil .pdf
 
Short Course 6- Mechanical Seals and Sealing Systems.pdf
Short Course 6- Mechanical Seals and Sealing Systems.pdfShort Course 6- Mechanical Seals and Sealing Systems.pdf
Short Course 6- Mechanical Seals and Sealing Systems.pdf
 
Centrifugal-compressor-ge.pdf
Centrifugal-compressor-ge.pdfCentrifugal-compressor-ge.pdf
Centrifugal-compressor-ge.pdf
 
Materi-operation-kupang-amp-sumbagut.pdf
Materi-operation-kupang-amp-sumbagut.pdfMateri-operation-kupang-amp-sumbagut.pdf
Materi-operation-kupang-amp-sumbagut.pdf
 
dokumen.tips_api-682-presentation.pdf
dokumen.tips_api-682-presentation.pdfdokumen.tips_api-682-presentation.pdf
dokumen.tips_api-682-presentation.pdf
 
Pemeliharaan-pembangkit-listrik-tenaga-diesel.pdf
Pemeliharaan-pembangkit-listrik-tenaga-diesel.pdfPemeliharaan-pembangkit-listrik-tenaga-diesel.pdf
Pemeliharaan-pembangkit-listrik-tenaga-diesel.pdf
 
Comparison of API610 12th and 11th Editions (1).pdf
Comparison of API610 12th and 11th Editions (1).pdfComparison of API610 12th and 11th Editions (1).pdf
Comparison of API610 12th and 11th Editions (1).pdf
 
Materi-operation-gas-engine-tarakan.pdf
Materi-operation-gas-engine-tarakan.pdfMateri-operation-gas-engine-tarakan.pdf
Materi-operation-gas-engine-tarakan.pdf
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
 
CENTRIFUGAL PUMPS TRAINING.pdf
CENTRIFUGAL PUMPS TRAINING.pdfCENTRIFUGAL PUMPS TRAINING.pdf
CENTRIFUGAL PUMPS TRAINING.pdf
 
API 610.pdf
API 610.pdfAPI 610.pdf
API 610.pdf
 
Introduction to Pumps.pdf
Introduction to Pumps.pdfIntroduction to Pumps.pdf
Introduction to Pumps.pdf
 
Basic Pump Training Material .pdf
Basic Pump Training Material .pdfBasic Pump Training Material .pdf
Basic Pump Training Material .pdf
 
PLANT COMMISSIONING.pdf
PLANT COMMISSIONING.pdfPLANT COMMISSIONING.pdf
PLANT COMMISSIONING.pdf
 
pidslide.ppt
pidslide.pptpidslide.ppt
pidslide.ppt
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 

Gas Turbine Basics.pdf

  • 2. 2 / GE / February 11, 2010 • Maintenance costs and equipment’s availability are two of the most important parameters for the productivity and profit of a production Plant. • Gas turbine influence on the above parameters is very signifìcant, and therefore it is necessary to issue a maintenance program based on the following milestones : 1. - Frequency and type of scheduied inspections 2. - Spare parts planning 3. - Control of gas turbine operation and lite affecting factors PRODUCTION PLANT SPECIFIC CHARACTERISTICS AND PRIORITIES AVERAGE PERSONNEL TRADE SKILL RECOMMENDATIONS FROM GAS TURBINE OEM, BASED ON THE FOLLOWING RULES: Maintenance Considerations
  • 3. 3 / GE / February 11, 2010 Maintenance Planning The major scope of maintenance planning is to reduce the Plant out of production time to the minimum. To reach good results, the following factors should be taken in to consideration : • PECULIAR CHARACTERISTICS OF THE PRODUCTION PLANT • AMBIENT CONDITIONS • TYPE OF SERVICE (CONTINUOUS, INTERMITTENT, PEAK LOAD, ETC.) • TYPE OF FUEL • LOSS OF PRODUCTION COSTS DUE TO THE TURBINE SHUT-DOWN TIME FOR INSPECTION/OVERHAULING • MAN POWER LOCAL CAPABILITIES • OEM MAINTENANCE RECOMMENDATIONS
  • 4. 4 / GE / February 11, 2010 Construction Features and Maintenance Flexibility To facilitate turbine maintenance practices, the following major construction features are designed into the majority of the heavy duty gas turbine engines : • HORIZONTALLY SPLIT CASINGS FOR EASY ACCESS TO THE INTERNAL PARTS • STATOR BLADES CAN BE SLID ON THE CASING GROOVE WITHOUT ROTOR REMOVAL. • ALL TURBINE ROTOR BLADES ARE NORMALLY MOMENT-WEIGHED AND DISTRIBUTED CIRCUMFERENTIALLY ON THE TURBINE WHEEL BY COMPUTER CHARTING PROGRAM, SO THAT NO SITE BALANCE IS GENERALLY REQUIRED IN CASE OF BLADE SUBSTITUTION. • ALL BEARING HOUSING AND LINERS ARE SPLIT ON THE HORIZONTAL CENTERLINE SO THAT THEY MAY BE INSPECTED AND REPLACED, WHEN NECESSARY. • BORESCOPE INSPECTION CAPABILITY.
  • 5. 5 / GE / February 11, 2010 Boroscope inspection ports
  • 6. 6 / GE / February 11, 2010 Boroscope inspection programming The borescope inspection can be performed during a combustion inspection, or during a planned or unplanned shutdown. A planned borescope inspection program results in opening a turbine unit only when necessary to repair or replace parts. It should be recognized that inspection intervals are based on average unit operating modes. Adjustment of these intervals may be made based on experience and the individual unit mode of operation and the fuels used. The borescope inspection program should include : •Baseline inspection and recording of conditions, both written and photographically, at the time of start-up. •Periodic inspection and recording of the results. The application of a monitoring program, utilizing the borescope, will allow scheduling outage and pre-planning of parts requirements, resulting in lower maintenance costs, higher availability and reliability of the gas turbine.
  • 7. 7 / GE / February 11, 2010 Boroscope Typycal Equipment
  • 8. 8 / GE / February 11, 2010 •Define a reference optimum gas turbine operating conditions, for which the life of hot gas path components is maximum. •The following are the most common “standard” operating configuration considered and applied by the majority of them. Maintenance and parts life affetting Factors Under the above condition, the parts life is theoretically 100% of the design and the recommended intervals between maintenance inspection are maximum. For different operating conditions, higher maintenance factors must be applied. Which correspond to reduced intervals between inspections and overhauling. NATURAL GAS FUEL CONTINUOUS OPERATION AT BASE LOAD NO STEAM / WATER INJECTION
  • 9. 9 / GE / February 11, 2010 Standard Maintenance Schedule
  • 10. 10 / GE / February 11, 2010 Operating factors affecting maintenaince intervals Continuous duty Cyclic duty Rupture Thermal/mechanical fatigue Creep LCF (Low Cycle Fatigue) HCF (High Cycle Fatigue) Wear Corrosion FOD( foreign objetcs damage) Oxidation Erosion Wear/rubs FOD Causes of potential failures of gas path parts
  • 11. 11 / GE / February 11, 2010 Hour’s factors • Fuel • Steam injection • Water injection • Operating load
  • 12. 12 / GE / February 11, 2010 Fuel
  • 13. 13 / GE / February 11, 2010 Operating load
  • 14. 14 / GE / February 11, 2010 Water and Steam injection The maintenance factor may be calculated with the following procedure: M.F. = K + M x I Where: I = Percent steam injection referenced to the inlet air flow M = 0 K = 1 for dry control and I < 2,2% M = 0,18 K = 0,6 for dry control and I > 2,2%
  • 15. 15 / GE / February 11, 2010 • Start up with liquid fuel • Start up sequence • Sudden load changes • Emergency shut downs Start factors
  • 16. 16 / GE / February 11, 2010 Start up with liquid fuel normally causes higher thermal effects if compared to natural gas fuel. •Affected components: combustion and hot gas path parts. •Maintenance factor for start up with No2 distillate = 1.5 Liquid fuel
  • 17. 17 / GE / February 11, 2010 Start up sequence …fast loading start-up where unit is brought from standstill to full speed no load with the normal sequence and then submitted to fast load. …emergency start-up the unit is brought from standstill to full load with a sequence faster than the standard. Where… • Maintenance Factor for emergency start up = 20 • Maintenance Factor for fast-loading start up = 2
  • 18. 18 / GE / February 11, 2010 Sudden load changes
  • 19. 19 / GE / February 11, 2010 Sudden load changes
  • 20. 20 / GE / February 11, 2010 Emergency shut downs
  • 21. 21 / GE / February 11, 2010 Maintenance Interval Equation
  • 22. 22 / GE / February 11, 2010 Maintenance Interval Equation
  • 23. 23 / GE / February 11, 2010 An MS7001 user has accumulated operating data since the last hot gas path inspection and would like to estimate when the next one should be scheduled. The user is aware from GE publications that the normal HGP interval is 24,000 hours if operating on natural gas, with no water or steam injection, and at base load. It is also understood that the nominal starts interval is 1200, based on normal startups, no trips, no emergency starts. The actual operation of the unit since the last hot gas path inspection is much different from the GE “baseline case.” Annual hours on natural gas, base load G = 3200 hr/yr Annual hours on light distillate D = 350 hr/yr Annual hours on peak load P = 120 hr/yr Steam injection rate I = 2.4% Also, since the last hot gas path inspection, 140 Normal start-stop cycles: 40 Part load 100 Base load 0 Peak load In addition, E = 2 Emergency Starts with ramp to base load F = 5 Fast loads ending in a normal shut down from base load T = 20 Starts with trips from base load Example – HGP Maintenance Interval Calculation
  • 24. 24 / GE / February 11, 2010 For this particular unit, the second and third-stage nozzles are FSX-414 material. The unit operates on “dry control curve.” At a steam injection rate of 2.4%, the value of “M” is 0.18, and “K” is 0.6. From the hours-based criteria, the maintenance factor is determined from Figure 43. The hours-based adjusted inspection interval is therefore, H = 24,000/1.25 H = 19,200 hours [Note, since total annual operating hours is 3670, the estimated time to reach 19,200 hours is 5.24 years (19,200/3670).] [K + M(I)] x [G + 1.5(D) + Af(H) + 6(P)] (G + D + H + P) MF = [0.6 + 0.18(2.4)] x [3200 + 1.5(350) + 0 + 6(120)] (3200 + 350 + 0 + 120) MF = = 1.25 Example – HGP Maintenance Interval Calculation
  • 25. 25 / GE / February 11, 2010 From the starts-based criteria, the maintenance factor is determined as: The total number of part load starts/stop is NA = 40/yr The total number of base load starts/stop is NB = 100 + 2 + 5 + 20 = 127/yr The total number of peak load starts/stop is NP = 0/yr The adjusted inspection interval based on starts is S = 1200/2.0 S = 600 starts [Note, since the total annual number of starts is 167, the estimated time to reach 600 starts is 600/167 = 3.6 years.] In this case, the starts-based maintenance factor is greater than the hours maintenance factor and therefore the inspection interval is set by starts. The hot gas path inspection interval is 600 starts (or 3.6 years). 0.5 (NA)+(NB)+1.3(NP)+20(E)+2(F) +  (an-1)T NA + NB + NP MF = 0.5(40)+(127)+1.3(0)+20(2)+2(5)+(8–1)20 40+127+0 = 2 MF = Example – HGP Maintenance Interval Calculation
  • 26. 26 / GE / February 11, 2010 Gas Turbine Maintenance Maintenance Inspections STAND-BY INSPECTIONS RUNNING INSPECTIONS DISMANTLING INSPECTIONS
  • 27. 27 / GE / February 11, 2010 STAND-BY INSPECTIONS They are required when the engine is not in operation. During this period of time, the following items should be checked : LUBE OIL SYSTEM COMPONENTS FUEL SYSTEM COMPONENTS INTAKE SYSTEM AND FILTERS INSTRUMENTATION SETTINGS AND REPAIRS/SUBSTITUTIONS EMERGENCY BATTERIES STATUS FLUIDS LEVELS (OILS, WATER, ETC.) OTHER AUXILIARIES IN GENERAL BORESCOPE INSPECTION FOR ALL THE INTERNAL PARTS
  • 28. 28 / GE / February 11, 2010 RUNNING INSPECTIONS They are required when the engine is in operation. During this period of time, the records of the most important functional parameters must be done by the operation personnel, every one or two hours, in order to have a good operation trend of the system. This will help find the root causes of gas turbine troubles. TYPICAL PARAMETERS
  • 29. 29 / GE / February 11, 2010 DISMANTLING INSPECTIONS Combustion System inspection Hot Gas Path inspection Major inspection
  • 30. 30 / GE / February 11, 2010 Gas Turbine Maintenance Combustion system inspections
  • 31. 31 / GE / February 11, 2010 Combustion inspection – Key elements
  • 32. 32 / GE / February 11, 2010 Combustion inspection
  • 33. 33 / GE / February 11, 2010 Combustion inspection precedure 1. Prepare turbine compartment roof for removal 2. Remove turbine compartment roof and side panels. 3. Remove liquid fuel lines (if applicable). 4. Remove atomizing air lines (if applicable). 5. Remove gas fuel lines (if applicable). 6. Remove steam injection lines (if applicable). 7. Remove water injection lines (if applicable). 8. Remove liquid fuel check valves. 9. Remove false start drain tubing. 10. Remove fuel nozzles.
  • 34. 34 / GE / February 11, 2010 11 Remove flame detectors and spark plugs. 12 Remove 11th stage cooling and sealing air lines. 13 Unbolt and open up combustion outer casing covers. 14 Remove crossfire tube retainers, combustion liners, crossfire tubes and forward flow sleeves. 15 Remove access port blank flange from upper half turbine casing or the upper section of the atomizing air extraction manifold. 16 Remove outer combustion casings and aft flow sleeves. 17 Remove transition pieces. Combustion inspection precedure
  • 35. 35 / GE / February 11, 2010 • Fuel nozzle (o burners) • Combustion chamber components ( liner, cap, flow sleeve) • Transition piece • Cross-fire tubes • Spark plug • Flame detectors GT Combustion inspection During this inspection the status of following components should be verified and all necessary repair/substitution is carried out: Note: For the lifting of main components see drawing “ Gravity centres and weights”
  • 36. 36 / GE / February 11, 2010 The inspection of fuel nozzle is necessary to clean up them from internal combustion residual carbon deposits and repair cracks, as well as for the combustion chamber. Fuel nozzle (o burners)
  • 37. 37 / GE / February 11, 2010 Normally, cracks inspections carried out using dye penetrating fluids sprayed on the components surface. Fuel nozzle (o burners)
  • 38. 38 / GE / February 11, 2010 C. C. components ( liner, cap, flow sleeve)
  • 39. 39 / GE / February 11, 2010 INSPECTION CRITERIA C. C. components ( liner, cap, flow sleeve)
  • 40. 40 / GE / February 11, 2010 C. C. components ( liner, cap, flow sleeve)
  • 41. 41 / GE / February 11, 2010 Crossfire Tube
  • 42. 42 / GE / February 11, 2010 Transition piece
  • 43. 43 / GE / February 11, 2010 Transition piece
  • 44. 44 / GE / February 11, 2010 SPARK PLUG ASSEMBLY Spark plug
  • 45. 45 / GE / February 11, 2010 Flame Detector Flame detector are checked for eventual electrical damage and carbon deposits on the optical surface.
  • 46. 46 / GE / February 11, 2010 Flame Detector
  • 47. 47 / GE / February 11, 2010 Flame Detector
  • 48. 48 / GE / February 11, 2010 Gas Turbine Maintenance Hot gas path parts inspections
  • 49. 49 / GE / February 11, 2010 GT Hot Gas path inspection – Key elements
  • 50. 50 / GE / February 11, 2010 GT Hot Gas path inspection To carry out an inspection on the hot gas path, it is necessary to remove the upper half casing of the turbine. Before proceding with disassembly, put jacks under the lower half casing, in order to help the upper half casing slide upward when beign opened avoiding subjecting the remaing parts of turbine casing to bending stress.
  • 51. 51 / GE / February 11, 2010 The disassembling procedure to access and remove the parts to be inspected is carried out in the following sequence: GT Hot Gas path inspection: Disassembly 1. Remove turbine compartment side panels. (If applicable). 2. Remove roof attachments. (If applicable) 3. Lift off turbine compartment roof. (If applicable). 4. Remove upper half cooling and sealing air piping. 5. Remove turbine casing wheel-space thermocouple wiring and conduit. 6. Perform combustion inspection disassembly Operations. 7. Establish solid foundation and place mechanical screw jacks under unit casings. 8. Remove upper half turbine casing. 9. Remove upper half first-stage nozzle. 10. Take turbine clearance checks. 11. Remove lower half first-stage nozzle. 12. …… 13. ……
  • 52. 52 / GE / February 11, 2010 • Combustion system . • 1st stage Nozzle. • 1st stage shrouds. • 2ndstage Nozzle. • 2ndstage shrouds. • 1st and 2nd stage turbine buckets. • Compressor Blade (Boroscope) GT Hot Gas path inspection During this inspection the status of the following gas turbine section components should be verified and all necessary repair/substitution is carried out in case of natural gas or light distillate fuel operation:
  • 53. 53 / GE / February 11, 2010 Opening Compressor and Turbine Rotor Position Checks
  • 54. 54 / GE / February 11, 2010 1. Inspect first, second and third stage turbine buckets. 2. Inspect first, second and third stage bucket cover-plates. 3. Inspect the Shroud Blocks. 4. Inspect second and third stage diaphragm segments. 5. Inspection the first stage nozzles ellipticity checks. 6. Inspect combustion system components GT Hot Gas path inspection
  • 55. 55 / GE / February 11, 2010 First Stage Nozzle Inspection
  • 56. 56 / GE / February 11, 2010 Turbine clearance checks
  • 57. 57 / GE / February 11, 2010 Turbine Buckets Inspection
  • 58. 58 / GE / February 11, 2010 Turbine Buckets Inspection
  • 59. 59 / GE / February 11, 2010 Gas Turbine Maintenance Major inspection/overhaul
  • 60. 60 / GE / February 11, 2010 GT Major inspection – Key elements
  • 61. 61 / GE / February 11, 2010 Major inspection/overhaul The aim of a major inspection is to examine all rotor and stator inner parts, from the filter chamber inlet throughthe exaust system, including also the load gear and the driven machine. A major inspection must be scheduled and organized in accordance with the recommendations in the maintenaince manual supplied along with the turbine, and with the results of the combustion and hot gas path inspections carried out beforehand. In order to carry out a major inspection, all upper half casing must be removed,so as to beable to remove the rotors. Before proceeding with disassembly, jacks must be placed under the bottom half casings, so as to ease the upper half casing to be moved upward without subjecting the remain casings to bending stress. Maintenance forms must be used for record clearances all rotor and stator parts. Typical maintenaince forms GT Major inspection
  • 62. 62 / GE / February 11, 2010 The disassembling procedure to access and remove the parts to be inspected is done in the following sequence: 1. Remove accessory and load coupling guard. 2. Remove accessory and load coupling. 3. Check alignment rotor accessory side and load side and record on maintenaince form. 4. Check the rotor positioning after disassembly upper-half casing and record on maintenaince form. 5. Same sequence described for combustion and hot gas path inspection. 6. Remove the Inlet duct Elbow, Exhaust Duct section, Exhaust Insulation pannel, Upper half of Inlet plenum. 7. Fit additional jacks. 8. Disassamble the remaining upper half casingsand cover from bearing blocks. 9. Record clearance between all rotor and statoric parts. 10. Extract rotors. 11. Open the guard on the accessory and load gears. 12. Open casings on the driven machine. GT Major inspection: Disassembly
  • 63. 63 / GE / February 11, 2010 GT Major inspection
  • 64. 64 / GE / February 11, 2010 Tubine Bearing Inspection
  • 65. 65 / GE / February 11, 2010 Tubine Bearing Inspection
  • 66. 66 / GE / February 11, 2010 1. Inspect No. 1, 2 journal bearings and seals. 2. Inspect No. 1 thrust bearings and seals. 3. Clean, inspect compressor rotor, stator blade, inlet guide vanes and compressor and turbine casings. 4. Inspect first, second and third-stage turbine buckets and wheel dovetails. 5. Inspect first, second and third-stage shrouds and diaphragm seals. 6. Perform Hot Gas Path Inspection GT Major inspection: Inspection
  • 67. 67 / GE / February 11, 2010 Components acceptability criteria More example components acceptability criteria
  • 68. 68 / GE / February 11, 2010 Load gear site alignment fixture Turbine site Attach the alignment fixture and dial indicators to the turbine shaft and check the turbine to load gear alignment. Refer to the Instructions and Data Alignment-Field, in the Reference Drawings Section of the service manual for alignment specifications. Gas Turbine on-site Alignment
  • 69. 69 / GE / February 11, 2010 CHECKS TO BE DONE BEFORE RESTARTING THE TURBINE WARNING TAKE CARE THAT NO FOREIGN OBJECTS (TOOLS OR OTHER HARDWARE) ARE FORGOTTEN INSIDE TURBINE. OTHER CHECKS ARE LISTED IN THE SERVICE MANUAL SECT. 2 Gas Turbine Maintenance
  • 70. 70 / GE / February 11, 2010 The determination of the manpower and the relevant times required to carry out the three levels of inspections depend on the following assumptions : • Intervention with or without the assistance of the OEM supervision • Critical spares availability at the plant site • Repair times in parallel to the substitution activities • All the necessary standard and OEM’s recommended special tooling available • Skill of personnel • Scheduled inspection Manpower planning and type
  • 71. 71 / GE / February 11, 2010 To obtain successful maintenance planning and operating economical results it is very important to consider the gas turbine system tear- down time required to accomplish all the maintenance actions. Due to the above, a good spare parts planning will reduce the waiting time from disassembly to reassembly sequence period, during which the plant is out of operation. Spare Parts planning
  • 72. 72 / GE / February 11, 2010 SPARE PARTS RECOMMEND ED FOR INSPECTIONS Spare Parts planning
  • 73. 73 / GE / February 11, 2010 SPARE PARTS AVAILABILITY CAN BE OBTAINED IN TWO WAYS By ordering the critical parts together to the main equipment purchase order By issuing a mutual Customer -to- OEM After Sales Assistance contract which includes spare parts availability in the OEM’s warehouse at any time during the turbine operating life. This type of contracts are variable case by case and have different levels of costs, in function of the required level of service. THE CHOICE OF THE MOST CONVENIENT SOLUTION DEPENDS ON THE PLANT PROFITABILITY CALCULATION RESULTS, WHICH SHOULD INCLUDE THE FOLLOWING PARAMETERS : • Daily loss of profit in case of turbounit out of operation • Similar plants feedback experience • Overall operating hours of the same gas turbine model club • OEM’s availability and reliability percent average data for the gas turbine model installed Spare Parts Availability Criteria
  • 74. 74 / GE / February 11, 2010 Type of inspection Ref. turbine rating (MW) Average crew size 8 hour shifts 2 2 2 5 2 2 Combustion inspection 10 2 2 20 4 5 40 5 10 >100 6 13 2 2 7 5 2 7 Hot gas path parts 10 2 7 20 6 10 40 9 15 >100 10 30 2 4 10 5 4 14 Major inspection 10 4 15 20 8 20 40 10 35 >100 11 50 NOTE Average values. For specific job values refer to the operating and maintenance manuals. MI Man-Hour Assumptions
  • 75. 75 / GE / February 11, 2010 Availability and reliability data are very important for both gas turbine model selection and maintenance. These two factors are used to quantify the ratio between not scheduled gas turbine “out of service” times and the potential operating time/year of the gas turbine. There are many different (but similar) formulas to calculate the above percent values Availability and Reliability Concepts
  • 76. 76 / GE / February 11, 2010 Availability is defined as “the probability of being available, independent of whether or not the unit is needed”. Reliability = 100 x [ PH - FOH] / PH [ % ] Reliability is defined as “the probability of not being forced out of service when the unit is needed”. PH = Sum of the annual operating hours, standby (ready to start) hours, not operating hours due to external causes. FOH = Forced Outage Hours. Period of time during which the maintenance team is actually working during forced outage. POH = Planned Outage Hours. Period of time during which the maintenance team is actually working during planned outage. Availability = 100 x [ PH - (FOH+POH)] / PH [ % ] Availability and Reliability Concepts
  • 77. 77 / GE / February 11, 2010 Estimated repair and replacement cycles
  • 78. 78 / GE / February 11, 2010 Estimated repair and replacement cycles
  • 79. 79 / GE / February 11, 2010 Estimated repair and replacement cycles