SlideShare a Scribd company logo
1 of 32
Download to read offline
SOLAR POWER PLANT PROJECT
3MW SOLAR POWER PLANT
VEDHAAH POWER PLANT - DINDIGUL
CONTRACT : LARSEN & TOUBRO – POWER TRANSMISSION AND
DISTRIBUTION
SUB CONTRACT : RP STRUCTURAL SOLUTIONS
PRODUCED BY
A.WAJID SHARIEFF – FRONTLINE ENGINEER 1
EXECUTIVE SUMMARY
2
PROJECT DETAILS
ENGINEERS 05
LABOURS 46
TOTAL PILES 1158 (2MW) & 570 (1MW)
INVESTMENT Inr 50,00,000
PROJECT DURATION 07 months
TOTAL PANELS 7720 (2MW) & 3800 (1MW)
Layout Drawing Of 2MW
3
EXISTING PLANT EXISTING PLANT
Layout Drawing Of 1MW
4
Type Of Solar Panel Used
5
Types Of Solar Cell Efficiency Selection criteria
Monocrystalline 20% Expensive
Polycrystalline 15% Lower price
Thin-Film: Amorphous 10% Shorter life span
Concentrated PV 41% Cooling needed to reach high efficency
Selected
Specification Of TSM-315PC14
6
Specification Of Solar Panel
MAXIMUM POWER ( Pmax) 315W
MAXIMUM POWER VOLTAGE
(Vmp)
37.1V
MAXIMUM POWER CURRENT
(Imp)
8.51A
OPEN CIRCUIT VOLTAGE (Voc) 45.6V
SORT CIRCUIT CURRENT(Isc) 9.00A
MAXMIMUM SYSTEM VOLTAGE DC 1000V
MAXIMUM SERIES FUSE 15A
MODULE APPLICATION CLASS A
EFFICIENCY 16-20%
SIZE 1.94 x 1.94 metres
Life Span Of Polycrystalline Solar Cell
7
Type Of Transformer Used
8
Specification Of Transformer
TYPE OF TRANSFORMER Regulating Transformer
MAXIMUM CURRENT 25MVa
MAXIMUM VOLTAGE 33kV
PURPOSE Regulation
PHASE USED Three phase
Type Of Inverter Used - ABB central inverters CORE-500.0/1000.0-TL 500 to
1000 kW
9
Specification Of Inverter
TYPE OF INVETRER Indoor inverter
MAXIMUM POWER 500 – 1000 kW
OPEN CIRCUIT VOLTAGE
VOLTAGE
1000Voc
PURPOSE
For solar, operation in any
weather and environment
PHASE USED Three phase
DC INPUTS 12 pairs of inputs
ADVANTAGE Compact size and weight
SUPPLY CONNECTION 3 – phase
EFFICIENCY 98.7%
Layout Of A Solar Power Plant
10
Solar Panels
String
Monitoring Box
69120 panels
40 panels = 1 Table
1728 Tables
26 Boxes
10 tables connected to 1 SMB
INVERTER
3 inverters
TRANSFORMER
2 transformers
POWER
DISTRIBUTION
Design Calculation Of A Solar Power Plant
Total power needed = 3MWp / hour
• Maximum power obtained from each panel = 315W
Since 6 piles are connected to form a table, 40 panels are placed in a table.
So, power obtained per table = 315*40
= 12600W / hour
power obtained for 193 tables = 12600*193
= 2.431MW (DC) / hour
Power needed for 95 tables = 12600*95
= 1.197MW (DC) / hour
So as per the requirement the power obtained is 2.4318+1.197 = 3.6288(DC) / hour
Upon conversion from DC through inverter to AC some power is lost which is then
boosted by a transformer.
11
Work Content In Constructing A Solar Plant
• Civil department
• Mechanical department
• Electrical department
12
The above departments are interconnected to each other. First comes civil, then mechanical and
finally electrical.
Work Content Of A Civil Department
• The civil department consists of surveying, pile casting and inverter room
construction. The pile marking is done by a surveyor and pile alignment is done.
• The pile alignment is done as depth of 1200 millimetres and diameter of 300
millimetres as per drawing by L&T.
• A single table consists of 6 piles and the distance of each pile is 3500mm and
6500mm horizontally.
• The pile casting is done by filling the hole by concrete in the ratio 1:2:3, that is
cement : sand : blue metal.
• Then coping is done of 75mm height and 150mm diameter ( as per the drawing).
• After the field work, the inverter room is constructed. The inverter room ids
constructed with ventilators and ducts.
• The inverter room is constructed as one inverter for each room. For example
1MW=1 inverter and a transformer.
• Further finishing is done by interior works and painting.
13
Pile Drawing
14
Diagram Of Civil Work Content
15
Pile
Coping
Concrete casting
Schematic Function Of A Civil Department
16
Land clearing Survey marking and pile drilling Pile alignment
Pile castingInverter room construction
Work Content Of A Mechanical Department
• The rafter is to be place at 8 – 9 degrees. The structure is made of galvanised iron
which is iron coated with zinc. This prevents corrosion.
• The purlin, rafter, brazing channel, connecting channel are connected to the stub.
• The grade of the nut bolt and washer used is M8 for a fixed type solar bed. Two
plain washer and one spring washer is used.
• The nut is of M8 * 25mm, the plain washer is of M8 * 2.5mm and spring washer
M8 * 2.5mm.
• The torque value is 58 N – mm for tightening the purlin and rafter with the stub.
• the nut, bolt and washer is made up of GI material.
• The length is of 1027mm and purlin is of 3957mm.
17
Structure Of A Solar Panel Mounting
The following components are used in a fixed type solar plant
• Purlin ( 3Nos.)
• Brazing connecting channel (1Nos.)
• Cleat plate (6Nos.)
• Brazing (2Nos.)
• Rafter (1Nos.)
18
Purlin
Cleat plate
Rafter
Brazing connecting channel
Stub
Concrete
Brazing
Work Content Of A Electrical Department
• The electrical work content consisted of two parts, AC and DC.
• The power from solar panel is DC and the power from inverter to distribution is
AC.
• The DC work starts with digging trench of depth 900mm as per the diagram.
Through these trench the DC cable, string cable and communication cable passes.
• The trench connects all the SMBs. For every 10 tables one SMB is connected.
• The power ( DC cable) from each and every table connects a SMB and from SMB
the communication connects the inverter in the inverter room.
• The SMB is connected by a string cable of 4sq.mm specification and DC cable of
300sq.mm specification.
• From inverter to the distribution line AC passes. The inverter room consists of a
inverter/MW a high tension panel and a transformer.
19
• The type of inverter used is of three phase string inverter from ABB
• The transformer used is of 2.2 MVa.
• The inverter room carries AC cables that are placed on a separate trays called cable trays.
• There are two types of trays used one is ladder trays and another, perforated trays.
• Perforated trays contain communication cables and ladder trays contain other AC cables
that are to be connected to the inverter to transformer.
• The size of those cables is 1core 300sq.mm.
• The inverter room consists of pulling pits having two holes through which the cables from
the field enters the room.
• The use of a string monitoring box is to collect all the information from the panels and
send it for monitoring. A SCADA software is used to monitor the exact power production
from the field.
• Then the power production is distributed to the destiny.
• The trench diagram is shown in the next slide. The blue line indicates the trench across
the field.
20
Layout Drawing Of 2MW
Sub Trench Main trench
1 Table consisting of 40 panels
EXISTING PLANT EXISTING PLANT
Inverter room
Layout Drawing Of 1MW
22
Sub trench Main trenchFencing Inverter room
DC Cables Laying Task
• The DC cable is laid across the trench. Main trench and the sub trench has to laid
with different type of cables.
• The sub trench is to be laid with a conduit pipe of radius 500mm and length
1000mts along with 1core 4 sq. mm of length varying from 1000-2000mts. The
conduit pipe connects the SMB.
• From SMB the 1core 300 sq. mm connects the inverter.
• There are four layers in a trench, first will be the rammed sand of 75mm and next
will be the conduit pipe (in case of a sub trench) or other DC cables ( in case of a
main trench), and then will be dry sand and one layer of brick of 75 mm height.
• Then the communication cable of type (RS485) and then warning tape is laid.
• Then the sand is filled. And a warning tape is provided as a caution. The whole
height of the trench is 900m.
• There are three steps in cable laying cable shifting, cable laying, cable glanding,
cable termination.
23
Layout Of Main Trench
24
Layout Of A Sub Trench
25
Layout Of SMB To Panel Connection
26
Layout Of Panel Connection To SMB
27
AC Cables Laying Task
• The AC cable is laid from the SMB to inverter and to transformer. The inverter
room consists of cable trays supported by L- angles, a pulling pit connecting the
DC cables and a pipe line to transformer.
• There are two types of trays used ladder type and a perforated type of tray. The
ladder type tray is used to provide maximum ventilation to heat. It is used to
support insulated electric cables for power distribution and communication.
• The perforated type cable tray have uniform holes. They are suitable for cables
that require both protection from external damage and ventilation.
• The dimension of a ladder type tray used is 600*150mm and the perforated tray
used is 300*150mm. The cables that are connected to inverter through ladder and
perforated trays.
• The inverter, HT panel is placed upon C- channel, which acts as a support.
• The C- channels are welded to provide a support to the inverter.
28
Ladder And Perforated Type Tray
29
30
Inverter trench Earthing (AC) Trench (DC) 2.2 MVa transformer
Pictures Of A Solar Plant Construction
String Monitoring Box Polycrystalline solar panel SMB Commissioning
31
Conclusion
Solar power systems derive clean, pure energy from the sun. Installing solar plants,
helps combat greenhouse gas emissions and reduces our collective dependence on
fossil fuel. Traditional electricity is sourced from fossil fuels such as coal and
natural gas, but production of electricity from solar cell is much more effective.
Solar energy systems generally don’t require a lot of maintenance. You only need to
keep them relatively clean, so cleaning them a couple of times per year will do the
job.Thus in this project after laying, glanding and terminating the cables with SMB,
inverter and with Transformer, the commissioning is done. The solar panels are
interconnected to form a closed loop. And it is checked to achieve the necessary
power. If the power is achieved then the power is distributed otherwise the power
cable is checked for its losses.The project was completed successfully as it achieved
3MWp / hour, and handed over to the client for distribution.
32

More Related Content

What's hot

BUILDING SERVICES-II (ELECTRICAL)
BUILDING SERVICES-II (ELECTRICAL)BUILDING SERVICES-II (ELECTRICAL)
BUILDING SERVICES-II (ELECTRICAL)Kethees Waran
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its typesJay Ranvir
 
UNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATIONUNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATIONPremanandDesai
 
Electrical design and estimating cost.
Electrical design and estimating cost.Electrical design and estimating cost.
Electrical design and estimating cost.Turja Deb
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
Elevators and its types
Elevators and its typesElevators and its types
Elevators and its typesRajat Nainwal
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Vijay Kumar
 
power supply or electric power
power supply or electric powerpower supply or electric power
power supply or electric powerMuhammad Muhyuddin
 
Swimming pool lighting.pptx.pdf
Swimming pool lighting.pptx.pdfSwimming pool lighting.pptx.pdf
Swimming pool lighting.pptx.pdfAyisha Shadha
 
Introduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designIntroduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designAsif Eqbal
 
Power System Modeling Techniques & Simulation Tools
Power System Modeling Techniques & Simulation ToolsPower System Modeling Techniques & Simulation Tools
Power System Modeling Techniques & Simulation ToolsPower System Operation
 
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDEINTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDEno suhaila
 
Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Mahesh Chandra Manav
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculationsPankaj Chavan
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
Illumination - Method of calculation
Illumination - Method of calculationIllumination - Method of calculation
Illumination - Method of calculationVijay Raskar
 

What's hot (20)

How capacitor bank works
How capacitor bank worksHow capacitor bank works
How capacitor bank works
 
Chap 7 ventilation and smoke purging system
Chap 7 ventilation and smoke purging systemChap 7 ventilation and smoke purging system
Chap 7 ventilation and smoke purging system
 
BUILDING SERVICES-II (ELECTRICAL)
BUILDING SERVICES-II (ELECTRICAL)BUILDING SERVICES-II (ELECTRICAL)
BUILDING SERVICES-II (ELECTRICAL)
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
 
UNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATIONUNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATION
 
Electrical design and estimating cost.
Electrical design and estimating cost.Electrical design and estimating cost.
Electrical design and estimating cost.
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
Elevators and its types
Elevators and its typesElevators and its types
Elevators and its types
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings
 
power supply or electric power
power supply or electric powerpower supply or electric power
power supply or electric power
 
Swimming pool lighting.pptx.pdf
Swimming pool lighting.pptx.pdfSwimming pool lighting.pptx.pdf
Swimming pool lighting.pptx.pdf
 
Introduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designIntroduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical design
 
Power System Modeling Techniques & Simulation Tools
Power System Modeling Techniques & Simulation ToolsPower System Modeling Techniques & Simulation Tools
Power System Modeling Techniques & Simulation Tools
 
MEP- Building services
MEP- Building servicesMEP- Building services
MEP- Building services
 
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDEINTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
 
Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Illumination - Method of calculation
Illumination - Method of calculationIllumination - Method of calculation
Illumination - Method of calculation
 

Similar to Solar Power Plant At Dindigul

UNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSUNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSPremanandDesai
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing Praveen Sharma
 
Nexans high-voltage.pdf
Nexans high-voltage.pdfNexans high-voltage.pdf
Nexans high-voltage.pdfprse
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptAshish585772
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution ZunAib Ali
 
ALBA MANUFACTURING OF TRANSFORMERS.pptx
ALBA MANUFACTURING OF TRANSFORMERS.pptxALBA MANUFACTURING OF TRANSFORMERS.pptx
ALBA MANUFACTURING OF TRANSFORMERS.pptxsfQyoom
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptxTalhaAbdulRehman2
 
#Building wiring system#presentation#Wire is a single electrical conductor, w...
#Building wiring system#presentation#Wire is a single electrical conductor, w...#Building wiring system#presentation#Wire is a single electrical conductor, w...
#Building wiring system#presentation#Wire is a single electrical conductor, w...Bint Shameem
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptxssuser1b3e431
 
DC-GENERATOR-UNIT-II.ppt
DC-GENERATOR-UNIT-II.pptDC-GENERATOR-UNIT-II.ppt
DC-GENERATOR-UNIT-II.pptprajwaleswa2004
 
Transformer bpt students in physiotherapy
Transformer  bpt students in physiotherapy Transformer  bpt students in physiotherapy
Transformer bpt students in physiotherapy Vishalsahu61
 
transformer_design.pdf
transformer_design.pdftransformer_design.pdf
transformer_design.pdfNerupaSharma
 

Similar to Solar Power Plant At Dindigul (20)

TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit Report
 
UNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSUNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONS
 
E&C-elearn.pdf
E&C-elearn.pdfE&C-elearn.pdf
E&C-elearn.pdf
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 
Nexans high-voltage.pdf
Nexans high-voltage.pdfNexans high-voltage.pdf
Nexans high-voltage.pdf
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
 
Rural electrification
Rural electrificationRural electrification
Rural electrification
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution
 
ALBA MANUFACTURING OF TRANSFORMERS.pptx
ALBA MANUFACTURING OF TRANSFORMERS.pptxALBA MANUFACTURING OF TRANSFORMERS.pptx
ALBA MANUFACTURING OF TRANSFORMERS.pptx
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
#Building wiring system#presentation#Wire is a single electrical conductor, w...
#Building wiring system#presentation#Wire is a single electrical conductor, w...#Building wiring system#presentation#Wire is a single electrical conductor, w...
#Building wiring system#presentation#Wire is a single electrical conductor, w...
 
ALTERNATOR DESIGN
ALTERNATOR DESIGNALTERNATOR DESIGN
ALTERNATOR DESIGN
 
CESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORTCESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORT
 
Emt megatherm a site visit report
Emt megatherm a site visit reportEmt megatherm a site visit report
Emt megatherm a site visit report
 
Electrical services
Electrical servicesElectrical services
Electrical services
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
1133 powell[2]
1133 powell[2]1133 powell[2]
1133 powell[2]
 
DC-GENERATOR-UNIT-II.ppt
DC-GENERATOR-UNIT-II.pptDC-GENERATOR-UNIT-II.ppt
DC-GENERATOR-UNIT-II.ppt
 
Transformer bpt students in physiotherapy
Transformer  bpt students in physiotherapy Transformer  bpt students in physiotherapy
Transformer bpt students in physiotherapy
 
transformer_design.pdf
transformer_design.pdftransformer_design.pdf
transformer_design.pdf
 

Recently uploaded

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 

Recently uploaded (20)

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 

Solar Power Plant At Dindigul

  • 1. SOLAR POWER PLANT PROJECT 3MW SOLAR POWER PLANT VEDHAAH POWER PLANT - DINDIGUL CONTRACT : LARSEN & TOUBRO – POWER TRANSMISSION AND DISTRIBUTION SUB CONTRACT : RP STRUCTURAL SOLUTIONS PRODUCED BY A.WAJID SHARIEFF – FRONTLINE ENGINEER 1
  • 2. EXECUTIVE SUMMARY 2 PROJECT DETAILS ENGINEERS 05 LABOURS 46 TOTAL PILES 1158 (2MW) & 570 (1MW) INVESTMENT Inr 50,00,000 PROJECT DURATION 07 months TOTAL PANELS 7720 (2MW) & 3800 (1MW)
  • 3. Layout Drawing Of 2MW 3 EXISTING PLANT EXISTING PLANT
  • 5. Type Of Solar Panel Used 5 Types Of Solar Cell Efficiency Selection criteria Monocrystalline 20% Expensive Polycrystalline 15% Lower price Thin-Film: Amorphous 10% Shorter life span Concentrated PV 41% Cooling needed to reach high efficency Selected
  • 6. Specification Of TSM-315PC14 6 Specification Of Solar Panel MAXIMUM POWER ( Pmax) 315W MAXIMUM POWER VOLTAGE (Vmp) 37.1V MAXIMUM POWER CURRENT (Imp) 8.51A OPEN CIRCUIT VOLTAGE (Voc) 45.6V SORT CIRCUIT CURRENT(Isc) 9.00A MAXMIMUM SYSTEM VOLTAGE DC 1000V MAXIMUM SERIES FUSE 15A MODULE APPLICATION CLASS A EFFICIENCY 16-20% SIZE 1.94 x 1.94 metres
  • 7. Life Span Of Polycrystalline Solar Cell 7
  • 8. Type Of Transformer Used 8 Specification Of Transformer TYPE OF TRANSFORMER Regulating Transformer MAXIMUM CURRENT 25MVa MAXIMUM VOLTAGE 33kV PURPOSE Regulation PHASE USED Three phase
  • 9. Type Of Inverter Used - ABB central inverters CORE-500.0/1000.0-TL 500 to 1000 kW 9 Specification Of Inverter TYPE OF INVETRER Indoor inverter MAXIMUM POWER 500 – 1000 kW OPEN CIRCUIT VOLTAGE VOLTAGE 1000Voc PURPOSE For solar, operation in any weather and environment PHASE USED Three phase DC INPUTS 12 pairs of inputs ADVANTAGE Compact size and weight SUPPLY CONNECTION 3 – phase EFFICIENCY 98.7%
  • 10. Layout Of A Solar Power Plant 10 Solar Panels String Monitoring Box 69120 panels 40 panels = 1 Table 1728 Tables 26 Boxes 10 tables connected to 1 SMB INVERTER 3 inverters TRANSFORMER 2 transformers POWER DISTRIBUTION
  • 11. Design Calculation Of A Solar Power Plant Total power needed = 3MWp / hour • Maximum power obtained from each panel = 315W Since 6 piles are connected to form a table, 40 panels are placed in a table. So, power obtained per table = 315*40 = 12600W / hour power obtained for 193 tables = 12600*193 = 2.431MW (DC) / hour Power needed for 95 tables = 12600*95 = 1.197MW (DC) / hour So as per the requirement the power obtained is 2.4318+1.197 = 3.6288(DC) / hour Upon conversion from DC through inverter to AC some power is lost which is then boosted by a transformer. 11
  • 12. Work Content In Constructing A Solar Plant • Civil department • Mechanical department • Electrical department 12 The above departments are interconnected to each other. First comes civil, then mechanical and finally electrical.
  • 13. Work Content Of A Civil Department • The civil department consists of surveying, pile casting and inverter room construction. The pile marking is done by a surveyor and pile alignment is done. • The pile alignment is done as depth of 1200 millimetres and diameter of 300 millimetres as per drawing by L&T. • A single table consists of 6 piles and the distance of each pile is 3500mm and 6500mm horizontally. • The pile casting is done by filling the hole by concrete in the ratio 1:2:3, that is cement : sand : blue metal. • Then coping is done of 75mm height and 150mm diameter ( as per the drawing). • After the field work, the inverter room is constructed. The inverter room ids constructed with ventilators and ducts. • The inverter room is constructed as one inverter for each room. For example 1MW=1 inverter and a transformer. • Further finishing is done by interior works and painting. 13
  • 15. Diagram Of Civil Work Content 15 Pile Coping Concrete casting
  • 16. Schematic Function Of A Civil Department 16 Land clearing Survey marking and pile drilling Pile alignment Pile castingInverter room construction
  • 17. Work Content Of A Mechanical Department • The rafter is to be place at 8 – 9 degrees. The structure is made of galvanised iron which is iron coated with zinc. This prevents corrosion. • The purlin, rafter, brazing channel, connecting channel are connected to the stub. • The grade of the nut bolt and washer used is M8 for a fixed type solar bed. Two plain washer and one spring washer is used. • The nut is of M8 * 25mm, the plain washer is of M8 * 2.5mm and spring washer M8 * 2.5mm. • The torque value is 58 N – mm for tightening the purlin and rafter with the stub. • the nut, bolt and washer is made up of GI material. • The length is of 1027mm and purlin is of 3957mm. 17
  • 18. Structure Of A Solar Panel Mounting The following components are used in a fixed type solar plant • Purlin ( 3Nos.) • Brazing connecting channel (1Nos.) • Cleat plate (6Nos.) • Brazing (2Nos.) • Rafter (1Nos.) 18 Purlin Cleat plate Rafter Brazing connecting channel Stub Concrete Brazing
  • 19. Work Content Of A Electrical Department • The electrical work content consisted of two parts, AC and DC. • The power from solar panel is DC and the power from inverter to distribution is AC. • The DC work starts with digging trench of depth 900mm as per the diagram. Through these trench the DC cable, string cable and communication cable passes. • The trench connects all the SMBs. For every 10 tables one SMB is connected. • The power ( DC cable) from each and every table connects a SMB and from SMB the communication connects the inverter in the inverter room. • The SMB is connected by a string cable of 4sq.mm specification and DC cable of 300sq.mm specification. • From inverter to the distribution line AC passes. The inverter room consists of a inverter/MW a high tension panel and a transformer. 19
  • 20. • The type of inverter used is of three phase string inverter from ABB • The transformer used is of 2.2 MVa. • The inverter room carries AC cables that are placed on a separate trays called cable trays. • There are two types of trays used one is ladder trays and another, perforated trays. • Perforated trays contain communication cables and ladder trays contain other AC cables that are to be connected to the inverter to transformer. • The size of those cables is 1core 300sq.mm. • The inverter room consists of pulling pits having two holes through which the cables from the field enters the room. • The use of a string monitoring box is to collect all the information from the panels and send it for monitoring. A SCADA software is used to monitor the exact power production from the field. • Then the power production is distributed to the destiny. • The trench diagram is shown in the next slide. The blue line indicates the trench across the field. 20
  • 21. Layout Drawing Of 2MW Sub Trench Main trench 1 Table consisting of 40 panels EXISTING PLANT EXISTING PLANT Inverter room
  • 22. Layout Drawing Of 1MW 22 Sub trench Main trenchFencing Inverter room
  • 23. DC Cables Laying Task • The DC cable is laid across the trench. Main trench and the sub trench has to laid with different type of cables. • The sub trench is to be laid with a conduit pipe of radius 500mm and length 1000mts along with 1core 4 sq. mm of length varying from 1000-2000mts. The conduit pipe connects the SMB. • From SMB the 1core 300 sq. mm connects the inverter. • There are four layers in a trench, first will be the rammed sand of 75mm and next will be the conduit pipe (in case of a sub trench) or other DC cables ( in case of a main trench), and then will be dry sand and one layer of brick of 75 mm height. • Then the communication cable of type (RS485) and then warning tape is laid. • Then the sand is filled. And a warning tape is provided as a caution. The whole height of the trench is 900m. • There are three steps in cable laying cable shifting, cable laying, cable glanding, cable termination. 23
  • 24. Layout Of Main Trench 24
  • 25. Layout Of A Sub Trench 25
  • 26. Layout Of SMB To Panel Connection 26
  • 27. Layout Of Panel Connection To SMB 27
  • 28. AC Cables Laying Task • The AC cable is laid from the SMB to inverter and to transformer. The inverter room consists of cable trays supported by L- angles, a pulling pit connecting the DC cables and a pipe line to transformer. • There are two types of trays used ladder type and a perforated type of tray. The ladder type tray is used to provide maximum ventilation to heat. It is used to support insulated electric cables for power distribution and communication. • The perforated type cable tray have uniform holes. They are suitable for cables that require both protection from external damage and ventilation. • The dimension of a ladder type tray used is 600*150mm and the perforated tray used is 300*150mm. The cables that are connected to inverter through ladder and perforated trays. • The inverter, HT panel is placed upon C- channel, which acts as a support. • The C- channels are welded to provide a support to the inverter. 28
  • 29. Ladder And Perforated Type Tray 29
  • 30. 30 Inverter trench Earthing (AC) Trench (DC) 2.2 MVa transformer Pictures Of A Solar Plant Construction
  • 31. String Monitoring Box Polycrystalline solar panel SMB Commissioning 31
  • 32. Conclusion Solar power systems derive clean, pure energy from the sun. Installing solar plants, helps combat greenhouse gas emissions and reduces our collective dependence on fossil fuel. Traditional electricity is sourced from fossil fuels such as coal and natural gas, but production of electricity from solar cell is much more effective. Solar energy systems generally don’t require a lot of maintenance. You only need to keep them relatively clean, so cleaning them a couple of times per year will do the job.Thus in this project after laying, glanding and terminating the cables with SMB, inverter and with Transformer, the commissioning is done. The solar panels are interconnected to form a closed loop. And it is checked to achieve the necessary power. If the power is achieved then the power is distributed otherwise the power cable is checked for its losses.The project was completed successfully as it achieved 3MWp / hour, and handed over to the client for distribution. 32