Venkat
Terminology
BENCH: Ledge that forms a single level
of operation above which mineral or
waste materials are mined from the
bench face.




                                         2
Terminology
BENCH HEIGHT: Vertical distance between the
highest point on the bench (crest) and the lowest
point or the bench (toe). It is influenced by size of
the equipment, mining selectivity, government
regulations and safety.




                                                        2
Terminology

BENCH SLOPE or BANK ANGLE :
Horizontal angle of the line connecting
bench toe to the bench crest.




                                          2
Terminology
BERM: Horizontal shelf or ledge within the ultimate pit
wall slope left to enhance the stability of the a slope
within the pit and improve the safety. Berm interval,
berm width and berm slope angle are determined by the
geotechnical investigation.




                                                          5
Terminology
OVERALL PIT SLOPE ANGLE: The angle measured
from the bottom bench toe to the top bench crest. It is
the angle at which the wall of an open pit stands and it
is determined by rock strength, geologic structures and
water conditions.




                                                           5
Terminology

The overall pit slope angle is affected by the width and
grade of the haul road.




                                                           5
Terminology

HAUL ROADS: During the
life of the pit a haul road
must be maintained for
access.


HAUL ROAD - SPIRAL
SYSTEM: Haul road is
arranged spirally along the
perimeter walls of the pit.



                                    8
Terminology

HAUL ROAD – SWITCH BACK SYSTEM: Zigzag pattern on
one side of the pit.

HAUL ROAD WIDTH:
Function of capacity of
the road and the size
of the equipment. Haul
road width must be
considered      in  the
overall pit design.



                                                    9
Haul Road Effect on Pit Limits




                                 10
Terminology

ANGLE OF REPOSE: Maximum slope of the
broken material.

SUBCROP OR ORE DEPTH: Depth of waste
removed to reach initial ore.

PRE-PRODUCTION STRIPPING:     Stripping
done to reach initial ore.


                                          11
Terminology
ULTIMATE PIT LIMITS: Vertical and lateral extend of
the economically mineable pit boundary. Determined on
the basis of cost of removing overburden or waste
material vs. the mineable value of the ore.

PIT SCHEDULING: Material may be mined from the pit
either in:
1) sequential push backs
2) conventional push backs.




                                                        12
Terminology
STRIPPING RATIO: Expressed in tons of waste to tons
of ore in hard rock open pit operations. Critical and
important parameter in pit design and scheduling.

AVERAGE STRIP RATIO: Total waste divided by total
ore within the ultimate pit.

CUTOFF STRIPPING RATIO: Costs of mining a ton of
ore and associated waste equals to net revenue from the
ton of Ore.
Single Working Bench




                       14
Shovel in Working Bench




                          15
Two Working Benches




                      16
Final
 Pit
Limit



        17
Example Mine
2001         2007     2011




                             18
Pit
Sequence
   (1)




           21
Pit
Sequence
   (2)




           22
Pit
Sequence
   (3)




           23
Pit
Sequence
   (4)




           24
Section of Pit Sequence




                          25
25

Openpit fundamentals

  • 1.
  • 2.
    Terminology BENCH: Ledge thatforms a single level of operation above which mineral or waste materials are mined from the bench face. 2
  • 3.
    Terminology BENCH HEIGHT: Verticaldistance between the highest point on the bench (crest) and the lowest point or the bench (toe). It is influenced by size of the equipment, mining selectivity, government regulations and safety. 2
  • 4.
    Terminology BENCH SLOPE orBANK ANGLE : Horizontal angle of the line connecting bench toe to the bench crest. 2
  • 5.
    Terminology BERM: Horizontal shelfor ledge within the ultimate pit wall slope left to enhance the stability of the a slope within the pit and improve the safety. Berm interval, berm width and berm slope angle are determined by the geotechnical investigation. 5
  • 6.
    Terminology OVERALL PIT SLOPEANGLE: The angle measured from the bottom bench toe to the top bench crest. It is the angle at which the wall of an open pit stands and it is determined by rock strength, geologic structures and water conditions. 5
  • 7.
    Terminology The overall pitslope angle is affected by the width and grade of the haul road. 5
  • 8.
    Terminology HAUL ROADS: Duringthe life of the pit a haul road must be maintained for access. HAUL ROAD - SPIRAL SYSTEM: Haul road is arranged spirally along the perimeter walls of the pit. 8
  • 9.
    Terminology HAUL ROAD –SWITCH BACK SYSTEM: Zigzag pattern on one side of the pit. HAUL ROAD WIDTH: Function of capacity of the road and the size of the equipment. Haul road width must be considered in the overall pit design. 9
  • 10.
    Haul Road Effecton Pit Limits 10
  • 11.
    Terminology ANGLE OF REPOSE:Maximum slope of the broken material. SUBCROP OR ORE DEPTH: Depth of waste removed to reach initial ore. PRE-PRODUCTION STRIPPING: Stripping done to reach initial ore. 11
  • 12.
    Terminology ULTIMATE PIT LIMITS:Vertical and lateral extend of the economically mineable pit boundary. Determined on the basis of cost of removing overburden or waste material vs. the mineable value of the ore. PIT SCHEDULING: Material may be mined from the pit either in: 1) sequential push backs 2) conventional push backs. 12
  • 13.
    Terminology STRIPPING RATIO: Expressedin tons of waste to tons of ore in hard rock open pit operations. Critical and important parameter in pit design and scheduling. AVERAGE STRIP RATIO: Total waste divided by total ore within the ultimate pit. CUTOFF STRIPPING RATIO: Costs of mining a ton of ore and associated waste equals to net revenue from the ton of Ore.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
    Example Mine 2001 2007 2011 18
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
    Section of PitSequence 25
  • 24.