This weekly status report summarizes the progress of the Resource Scheduling Web Application project from September 14-20, 2013. It indicates that the project is on schedule and on track to meet key milestones. Work completed this week included graphic design, database architecture, and initial development of the super admin module. Top priorities for next week are continuing development of subscription and tenant management sections. No significant risks, issues or change requests were noted.
Sow conversion of windows executable program to web interface
1. Weekly Status Report
Serial No. 2 Prepared by Santosh
Project Name Resource Scheduling Web Application Client’s Name Brian Kidd
Date
20/09/2013
Status Period
14/09/2013 -20/09/2013
Project Performance Rating (Red/Yellow/Green):
Schedule Adherence to Project Proposal
Key Milestones:
ID Title
Original planned
completion date
(this date should not
change)
Current forecast
completion date
Actual completion date
1 Graphic designing of the website and HTML
conversion of the same, creating responsive layout,
Designing the database and architecture of the
website, Registration and Subscription module,
Creating static pages for frontend, Starting
development of Super admin module, Super admin-
manage subscriptions and registered clients
2013-09-23 2013-09-23
2 Tenant Admin account creation, payment
processing, Payment gateway integration,
assignment creation, team management, schedule
creation, starting development of Calendar Admin
module- Creation of assignments, Assigning
resources, and Support module on backend
2013-10-14 2013-10-14
3 Completion of Calendar admin- creating schedules
and recipes, creating and managing Teams,
Creating Calendar view, Integrating Twilio API for
SMS and voice call, Completion of Super admin
module and other remaining modules and features.
2013-11-11 2013-11-11
4 Bug Fixing 2013-12-11 2013-12-11
2. Priority # Descriptio
n
Owner
1 Complete First Milestone Work
Santosh
ID Type Description Probabili
ty
(L/M/H)
Impact
(L/M/H)
Notes for the week:
ID Activity Owner Remarks
1 SRS Approval Santosh Complete
2 Work start on home page and internal super admin
pages
Santosh Complete
3 Manage Subscription and tenant section Santosh In progress
Top Priorities for the coming week:
Risks / Issues
Change Request History:
CR
ID#
Title or Description Schedule
change (if any)
Status (in
review, agreed,
withdrawn)
Comments