SlideShare a Scribd company logo
1 of 95
SAFETY MEASURES IN CONSTRUCTION
Importance of safety
• Safety in construction is a prime requirement but it is often
neglected on work site.
• The range of construction and building activities involving
complex techniques have led to many new problems of safety
measures at site result in a better work environment, higher
productivity and greater contentment among workers.
Safety measures
• Prevention of accidents is a major aim of construction
management, both for human and financial consideration..
• Whatever the nature of construction projects, accidents are likely to
occur causing physical injury, casualties and loss of money.
• In order to prevent accidents at construction site, certain safety
measures are to be taken in the following major activities which are
prone to risk of accidents.
1) Excavation
2) Drilling and blasting
3) Storage
4) Hot bituminous works
5) Scaffolding, ladders, formwork and handling of equipment’s
6) Fabrication and erection
7) Demolition
Safety measures for excavation
 Before doing the excavation, a complete knowledge of underground
structures, such as sewers, water pipe lines, gas mains etc. is
essential and suitable precautions should be taken to prevent
accident to the workers engaged in excavation work.
 Personal safety equipment’s such as safety shoes, Safety helmets
etc. should be worn by all persons entering a trench where hazards
from falling stones or other material exists.
 Whenever the workman to excavate in trenches in soft soil or
fissured rock or hard soil exceeding 2m in depth, the trenches
should be sufficiently shored and timbered.
 At place where public is likely to trespass fencing or barricades
should be erected to avoid accidents, during nights adequate lighting
should be provided.
Safety measures for Drilling and blasting
 Drilling and blasting is the controlled use of explosives and other
methods such as gas pressure blasting to break rock for excavation.
 It is practiced more often in mining, quarrying and civil engineering
such as dam and road construction.
 Drilling and blasting utilizes many different varieties of explosives
with different compositions and performance properties.
 High velocity explosives are used for relatively hard rock in order
to shatter and break the rock, while low velocity explosives can be
used in soft rocks to generate pressure and heave effect.
 Vehicles to be used for transporting explosives should be good in
condition with tight wooden or non-sparkling metal floor and
sides.
 Explosives should be stored only in a magazine which is clean, dry,
well ventilated, and reasonably cool.
 Leaves, grass or broken pieces of any kind should not be allowed
to accumulate within 8m of magazine.
 No person should allow touching the wires and opening the bare
leading wires of the electrical blasting caps during dust storms.
 Smoking should be strictly prohibited at places where explosives
are used.
 Explosives and fuse lighters should not be stored in a damp or wet
place or near oil, gas or steam pipes or other sources of heat.
 Before blasting all clear signal is given.
 After blasting operations, it is necessary to check the entire area of
the exploded explosives, which shall be safety removed away
from the work site.
Safety measures for storage of materials
 Adequate firefighting arrangements should be provided at site
particularly in areas where petroleum products and timber are
stored.
 Explosives must be stored in proper magazines and the prescribed
safety measures for handling and storage of explosives should be
observed.
 Petroleum products should be separately stored.
 Smoking and other fires should be strictly prohibited where these
products are stored.
 Only required quantities of such products should be stored at site.
Safety measures for hot bituminous works
 Workers engaged on job involving handling of hot bituminous
works should use protective wares such as boots, gloves, goggles
and helmets.
 When bitumen plants are working on a public road, an adequate
traffic control system must be established.
 Compressors, electrical installations and other equipment’s such as
elevators and conveyors should be adequately protected from
weather, mechanical damage and dust particles.
• When heating and handling of hot bituminous materials is to be
done in the open, sufficient stocks of clean dry sand or loose earth
should be kept ready at the work site to cope with any resultant fire.
• Bitumen plant should be provided with the safe means of access to
working platforms, hand rails, pulley, belts and drive mechanisms
should be protected by suitable guards.
Safety measures for fabrications and erections
 Fabrication is the process of bending, cutting and moulding steel
structures to create beams, columns and steel members.
 Moving part of all the equipment’s should be provided with safety
guards.
 All equipment’s such as gas cutting and welding sets, drills and
power hacksaws, grinders etc. should be checked periodically to
ensure their safe working.
 Workers engaged in gas cutting and welding operations should wear
suitable gloves, aprons, goggles and use proper screens.
 Power cable for all equipment’s should be properly insulated and
protected from damage and cuts.
 Cut pieces and scrap should be stored at an appropriate place to
avoid accidents.
 Workers engaged in erection works should wear helmets and use
safety belts to avoid accidents.
 All erection equipment’s such as cranes, derricks, hoists, etc. should
be thoroughly checked before use.
Safety measures for Scaffolding, ladders, formwork and
other equipment’s
 Every scaffold should be firmly supported or suspended and
properly strutted or braced to ensure stability.
 The supporting bullies of formwork should be checked for each
individual member.
 The bullies should be properly braced. Many accidents occur due
to negligence of this aspect.
 When the work is been performed above a scaffold platform, a
protective overhead covering should be provided for the men
working on the scaffolds.
 The protection should not be more tan 3m above the scaffold
platforms and should be made of plants.
 During dismantling (take to pieces) of scaffolds, necessary
precautions should be taken to prevent injury to persons due to fall
of loose materials, bracings and other part of scaffolds.
 Care should be taken to see that no un-insulated electrical wires
exist within 3m of the working platforms, gangway etc. of the
scaffolds.
Safety provisions required for explosives
Anyone manufacturing or storing explosives to take appropriate
measures:
 To prevent fire or explosions
 To limit the extent of fire or explosion including measures to
prevent the spreading of fires and the communication of explosions
from one location to another
 To protect people from the effects of fire or explosion
 An explosive is a material, either a pure single substance or a
mixture of substances, which is capable of producing an explosion
by its own energy .
 It is not proper to define an explosive as a substance, or a mixture
of substances, which is capable of undergoing a sudden
transformation with the production of heat and gas.
 The production of heat alone by the inherent energy of the
substance which produces it will be enough to constitute the
substance an explosive.
SAFETY THROUGH LEGISLATION
Indian government has brought up number of legislations from time
to time to address the safety aspects of construction works.
Some of legislation are as follows.
 Factories act -1948
 Mines act -1952
 Indian explosives act – 1984
 Indian boilers act – 1923
 Petroleum act – 1934
 Petroleum and minerals pipeline act – 1962
 Indian electricity rules – 1956
 The electricity act – 2013
 Motor vehicle act – 1988
 Contract labor act – 1970
 Workman compensation act – 1923
 Building and other construction work act – 1996
 Occupational safety and health act – 1970
 However, we need to understand that legislations alone cannot
ensure safety in job construction / operations
 All of our effective approach towards prevention of accidents and
promotion of safety conscious is achieved
 Alertness levels are increased to practice safe working habits, the
rules and regulations remain the paper.
 At the time of an untimely accident people talk about safety rules
and flows in their implementations only to forget the same in one or
two days.
 Safety should be set up as an objective as implement as economic
gains and zero accidents in job performance should be motive.
 The safe working practices (such as 10000 accident free hours of
production etc.) should be rewarded and hailed within the
organization.
 Safety should be builder’s first responsibility since controlling of
accidents reduces the scrap of human and product.
• The losses on accident of unsafe working practices / accidents are
reduced output,
 wasted wages
 lost time
 lowered morals
 damaged property
 loss of experienced hands
 medical bills
 above all loss of good will.
Accidents add up to employer worries
SAFETY CAMPAIGN
• Safety campaign aims to reduce the number of injuries sustained by
workers performing basic construction works.
• Guidelines of National safety consist towards safe working practices
should be prominently displayed at work spot and precautions to be
taken to avoid accidents should be discussed in meeting.
• Safety works with visual presentations should be arranged at least
once in a month and all the workers need to be educated to become
aware of value of safety in engineering works.
• Use of protective clothing, safety helmets, face shields, safety
equipment’s for eyes, ears, hands, feet, legs ( such as gas
masks, gloves etc.) should be widely advertised and followed.
• Safe working employees should be rewarded and awarded to
raise the awareness levels among others.
The objectives of the campaign are as follows:-
To improve the capability of residential builders to control risks.
During the assessment, inspectors will focus on:-
 Fall prevention through voids, from ladders, and other work
platforms
 Site housekeeping
 Site security
 Site supervision
 Additional issues related to electrical.
• The campaign will also improve the health and safety of young
workers in the construction industry, who are over represented in
injury statistics than the older or more experienced workers.
• It aims to educate managers and supervisors to ensure they can
effectively manage the young workers safety in the site.
• The inspectors will keep visiting the workplace in order to create
awareness regarding to safety and health.
SAFETY INSURANCE
• Insurance laws are applicable only to regular employees.
• In construction industry most of the labor is of casual nature and
insurance laws are not applicable to them.
• For the welfare of casual labor, different Acts such as Minimum
wages Act, Compensation Act etc. are passed by the Government.
• Keeping in mind the intensity of a probable loss in case of
mishaps/unpleasant accidents in engineering works, construction
activities, deferent insurance covers are available.
• Owing the huge monetary and other losses in case of accidents/ loss
of lives in construction industry, any uninsured activity or job may
culminate into job termination.
Following are some relevant schemes or engineering project works.
• Contractors All risk insurance (CAR policies)
• Machinery breakdown insurance
• Loss of profit insurance following machinery breakdown
• Contractor’s plant and machinery insurance.
Contractors all risk insurance (CAR policy)
This is a comprehensive insurance cover and provides adequate
protection against loss of damages in respect of contract works, as
well as third party claims towards property damage or badly injuries
workman/general public.
The following items get covered in a CAR policy under normal
circumstances.
• Fire accidents, lighting and explosives
• Theft, burglary(illegal entry of a building with intent to commit a
crime).
• Bad workmanship, unintentional negligence, human errors
• Natural calamities (flood, earthquakes etc.) if specifically provide
in the insurance terms.
Unless otherwise specified, the following are not included in the
CAR policies.
• Loss or damage due to war or war like operations, strike riots.
• Loss or damage due to willful negligence.
• Losses due to nuclear reactions, radiations, radioactive
contaminators
Machinery breakdown insurance
• Normally this type of insurance covers installed working in fixed
premises.
• In special cases the insurance cover can be extended to include
equipment’s in transit and damages to third parties as well as
personal injuries arising out of breakdown of insured machinery.
Loss of profit insurance
• Often due to non- operations often due to malfunctioning of some
mall control parts, the functioning of the entire machinery comes to
stand still.
• In such cases, this policy covers consequential losses suffered by
the machine user.
• Sometimes machine repair may take a long time; in such cases
Machinery breakdown insurance policy above covers machine
repairs cost and this policy entitles him or consequential losses/
profit losses.
Contractor’s plant and machinery insurance (CPM Policy)
• CPM is a special insurance policy cover due to non-production of
plant and machinery not attributable to engineering reasons but to
other factors such as riots, strikes, malicious damages, breakdown
due to excess running’s etc.
MORALS
 Morals are the guiding principles that every citizen should hold.
 It is the foundational concepts defined at both at individual and
societal level.
 At the most basic level, morals are the knowledge of difference
between the right and wrong.
Moral reasons include,
• Respecting others and ourselves
• Respecting rights of others
• Keeping promises
• Avoiding unnecessary problems to others and avoiding cheating
and dishonesty,
• Showing gratitude to others and encourage them to work.
VALUES
 The word value is derived from French word “valoir” which means
worth, merit, usefulness or importance of a thing.
 Values are individual in nature.
 Values are comprised of personal concepts of responsibility,
entitlement and respect.
 Values are shaped by personal experience, may change over the span
of a lifetime and may be influenced by lessons learned.
 Values may vary according to an individual’s cultural, ethnic and/or
faith-based background. Integrity is one such value.
Characteristics of Values
1. Values represent an individual‘s highest priorities and
deeply held driving forces
2. Values are the hub of personality and it has a powerful
force of affecting behavior
3. Value varies according to time
4. Many values are relatively constant and durable
5. It contains a judgment element
6. Everyone does not hold the same values
7. Values are distinctly different from comforts. Comforts
bring in short term gains and long term pains whereas
values bring in short term pains and long term gains.
ETHICS
• Ethics is the study of the characteristics of morals.
• Ethics is defined as “a system of moral principles, by which human
actions and proposals may be judged good or bad, or right or
wrong.
• Ethics is used in determining what is right in a given situation and
then following through with actions to implement what is right.
There are three primary ethical directives:
1. loyalty
2. honesty
3. responsibility.
• We will be called upon to be loyal to friends, family, organization,
profession, and being loyal to one may mean being disloyal to
another.
• Honesty is telling the truth as you see it but it’s really much more. It
does involve not lying but also giving a true and complete
representation of one’s self, our actions and our views.
• Responsibility requires taking ownership of the consequences of
our actions and insuring no harm comes to someone because of
those consequences.
• Construction companies must gain and keep loyal customers
• Their ability to acquire and maintain customers is directly related to
how those customers see the company’s ethical standards from both
management and employees
• A company’s reputation for unethical behavior will affect its ability
to draw top notch employees.
• Ethics is treating everyone in a “fair” and “reasonable” manner and
both are subject to wide interpretation.
Moral Ethics
Refers only to personal
behavior.
Involves defining, analyzing,
evaluating and resolving
moral problems and
developing moral criteria to
guide human behavior
Refers to any aspect of
human action . .
Critical reflection on what
one does and why one does
it
Social conventions about
right or wrong conduct
Refers only to professional
behavior
INTEGRITY
 one of the major challenges in our construction business is to
complete any project we do on time and within budget.
 It requires a lot of morale and high productivity from our work
crews.
 In todays market it always seems that companies want the job done
better, faster and with better materials at lesser cost.
 The principles of integrity apply in all aspects of our lives;
personal, professional and economically.
 In the construction sphere, the principles of integrity are no
different. We should apply them in our daily work lives.
 In construction business, we should all feel a moral and ethical
responsibility to protect the lives of our workers and to construct a
project safely.
 Integrity is about doing your best with honesty, consideration and
with much ethical responsibility towards the work you do and the
people you influence.
 The key element of integrity is leadership. For construction this
means hardhat professionals we should find solutions to ourselves
without reliance on government for relief.
 Also of critical importance to integrity is building an ethical culture
within an organization.
 What should be taken into account when giving code of ethics
training to new employees/recruits is that , as with anything else in
life, how you act is about desire for change in your life.
 Hence everyone should understand that all it takes to be more
ethical in life is that you making a conscious decision to change the
way you live your life- that will be the first step in opening doors for
making a difference in other peoples lives through your actions.
TRUSTWORTHINESS
 Trustworthiness is a human quality and virtue. Trustworthiness:
enable others to believe in us and to rely on us without reservation
or fear.
 The values or qualities help us develop trustworthiness: honesty,
integrity, reliability, and loyalty.
 Integrity and trustworthiness are important concepts in the social
sciences, because each is said to enable and enhance cooperation
 There are different ways to build honesty, these are:
A. Truthfulness
B. Sincerity
C. Candor
ENGINEERING ETHICS
 Engineering ethics is the study of moral issues and decisions
confronting individuals and organizations involved in engineering.
 Engineering ethics is the study of related questions about moral
ideals, character, policies and relationships of people and
organizations involved in technological activity.
 Engineering ethics is comprised of some sets of beliefs, moral
principles and rules that determine what is right and what is
wrong or what is good and what is bad in the engineering
profession, which are commonly applied to all engineers.
Two important ethical codes that engineer must be aware of are
1. The national society of professional engineers (NSPE) code of
ethics
2. The American society of civil engineers (ASCE) code of ethics
 These codes are sets of rules that clearly lay out the ways that
professional engineers must conduct themselves in the workplace.
 If an engineer is found violating one of these codes, they may lose
their license and could possibly face legal charges.
Why Study Engineering Ethics?
 Engineering ethics is not only teaching moral behavior in
knowing about immoral and amoral in a set of beliefs, but also
increasing the ability of engineers and other professionals to face
boldly with the moral problems arising from technological
advancements, change and other related activities.
Study of ethics helps engineers develop a moral autonomy:
 Ability to think critically and independently about moral issue
 Ability to apply this moral thinking to situations that arise in the
course of professional engineering practice
 Ethical problems in engineering are often complex and involve
conflicting ethical principles.
 Engineers must be able to intelligently resolve these conflicts and
reach a defensible decision.
PROFESSIONAL RIGHTS
 The right to engage in the activities of professional societies
 The right to form and express one’s professional judgment freely
 The right to talk publicly about one’s work within bounds set by
confidentiality obligation
 The right to protect the clients and the public from the
dangers that might arise from one’s work
 The right to professional recognition of one’s services.
 The right to refuse to carry out illegal and unethical
activity.
EMPLOYEE RIGHTS
• The employee will not be deprived of any enjoyment of reasonable
privacy in his/her workplace.
• No personal information about employees will be collected or kept
other than what is necessary to manage the organization efficiently
and to meet the legal requirements.
• There should be no discrimination against an employee for
criticizing ethical, moral or legal policies and practices of the
organization.
• No employee who alleges her/his rights have been violated will be
discharged or penalized without a fair hearing by the employer
organization.
CONFIDENTIAL INFORMATION
 Information considered desirable to be kept secret.
 Any information that the employer or client would like to have kept
secret in order to compete effectively against business rivals.
 This information includes how business is run, its products, and
suppliers, which directly affects the ability of the company to
compete in the market place.
 Helps the competitor to gain advantage or catch up
PROPRIETARY INFORMATION
 It is information such as financial data, test results or trade secrets
that is viewed as the holders property and that they wish to keep
from becoming public knowledge.
 Information that a company owns or proprietors.
 This is primarily used in legal sense also called Trade Secret.
 A trade secret can be virtually any type of information that has not
become public and which an employer has taken steps to keep
secret.
 For information to be considered proprietary, it should not readily
available in public sources, it should provide some sort of
competitive advantage, and the company should take al reasonable
steps to maintain its confidentiality.
 More companies are now appointing information managers to
assume responsibility for keeping such information safe and secure.
 This can be issue on construction projects, where members of the
project team or client may learn information that one party wishes
to stay confidential.
 As a result, organizations or employees with access to such
information may be required to non disclosure agreements or
confidentiality agreements that can limit the use of ideas and
information for a specific purpose for a certain period of time.
 They may protect information recorded in a certain form, perhaps
marked as confidential, or they may protect information shared
under certain circumstances, such as in presentations or meetings or
during the course of consultancy.
 They can be used to prevent commercially sensitive information
from being shared or to prevent parties from communicating certain
information to press or other third parties.
Non disclosure agreements can cover information such as:-
 Intellectual property
 Commercial or trading information
 Technical drawings or designs
 Business plans
 Customer and potential customer lists
 Mathematical and chemical formulae
 Trade secrets which could include programmers or processes
 Personal information about individuals involved in a project
CONFLICT OF INTEREST CONFIDENTIALITY
 Confidential information is a information deemed desirable to keep
secret.
 Engineers are required to keep confidential certain information
belonging to their employer or client. Such information, if released,
might allow other companies or organizations to gain an unfair
competitive advantage.
 A “conflict of interest” is a situation in which a person, such as a
public official, an employee or a professional, has a private or
personal interest sufficient to appear to influence the objective
exercise or his or her official duties.
 Employees are not allowed to engage, either within or outside
working hours, in any other gainful employment or conduct
any form of business activity, either personally or through the
agency of another, unless prior approval is obtained from the
Managing Director and HR Department.
 A COI is a situation in which a person organization is involved in
multiple interests, financial or otherwise in situations where
serving one the interests could involve working against one of the
other interests.
 It is a set of circumstances that creates a risk that professional
judgment or actions regarding a primary interest will be unduly
influenced by a secondary interest.
GIFT AND BRIBE
• ‘If you think that your offer of acceptance of a particular gift
would have grave or merely embarrassing consequences for
your company if made public, then the gift should be
considered a bribe’.
• Bribe can be said to be a substantial amount of money or
goods offered beyond a stated business contract with the aim
of winning an advantage in gaining or keeping the contract.
Here ‘substantial’ means that which is sufficient to distort the
judgment of a typical person.
When does a gift become a bribe?
• Something offered or given to someone in a position of trust in
order to induce him/her to act dishonestly
PRICE FIXING
 An act was passed, which forbade (prevented) companies from
jointly setting prices in ways that restrain free competition and
trade.
 Unfortunately, many senior people, well respected and positioned
were of the opinion that ‘price fixing’ was good for their
organizations and the public.
 An acceptable mechanism for price fixing must be found by the
engineer with the help of the economist, scientist, lawyer and
politician which could protect the environment through self-
correcting procedures.
WHISTLE BLOWING
 Construction Industry employees are often required to report
improper, unsafe or illegal construction activities.
 Whistle blowing is an act of conveying information about a
significant moral problem by a present or former employee, outside
approved channels (or against strong pressure) to someone, in a
position to take action on the problem.
 The features of Whistle blowing are:
Act of disclosure, Topic, Agent and Recipient
• Act of Disclosure: Intentionally conveying information
outside approved organizational channels when the person is
under pressure not to do so from higher-ups.
• Topic: The information is believed to concern a significant
moral problem for the organization.
• Agent: The person disclosing the information is an employee
or former employee.
• Recipient: The information is conveyed to a person or
organization who can act on it.
Types of Whistle Blowing
 External Whistle blowing: The act of passing on information
outside the organization.
 Internal Whistle blowing: The act of passing on information to
someone within the organization but outside the approved channels.
 Either type is likely to be considered as disloyalty, but the second
one is often seen as less serious than the latter.
 From corporations’ point of view both are serious because it leads
to distrust, disharmony, and inability of the employees to work
together.
• Open Whistle blowing: Individuals openly revealing
their identity as they convey the information.
• Anonymous Whistle blowing: Individual conveying the
information conceals his/her identity.
END OF MODULE 3

More Related Content

Similar to TQM AND ETHICS.pptx

Construction safety
Construction  safetyConstruction  safety
Construction safetyRanty Poddar
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfJESUSBASILIOANTONIO
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codejaimin1702
 
Investigation into safety practices by automobile mechanics at siwdo kokompe
Investigation into safety practices by automobile mechanics at siwdo kokompeInvestigation into safety practices by automobile mechanics at siwdo kokompe
Investigation into safety practices by automobile mechanics at siwdo kokompeAlexander Decker
 
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Muizz Anibire
 
Safety and envirnomental issues in mechanization
Safety and envirnomental issues in mechanizationSafety and envirnomental issues in mechanization
Safety and envirnomental issues in mechanizationsneha tiwari
 
Building Construction I Project 1 Compilation
Building Construction I Project 1 CompilationBuilding Construction I Project 1 Compilation
Building Construction I Project 1 CompilationNatalie Yunxian
 
BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1Alexis Wei
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolitionHni Amiera
 
17._SGW-_Personal_Protective_Equipments_(PPEs).pptx
17._SGW-_Personal_Protective_Equipments_(PPEs).pptx17._SGW-_Personal_Protective_Equipments_(PPEs).pptx
17._SGW-_Personal_Protective_Equipments_(PPEs).pptxsafetygoodwe
 
Step 2 preparation & safety starters
Step 2 preparation & safety startersStep 2 preparation & safety starters
Step 2 preparation & safety startersfqf383
 
Construction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over WaterConstruction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over WaterMuizz Anibire
 
Tutor core 01 h&s regs and responsibilitioes
Tutor core 01 h&s regs and responsibilitioesTutor core 01 h&s regs and responsibilitioes
Tutor core 01 h&s regs and responsibilitioesLuke D'Arcy
 
Construction safety session 1 (new)
Construction safety session 1 (new)Construction safety session 1 (new)
Construction safety session 1 (new)VancityInstitute
 
Safety protocols of construction site.pptx
Safety protocols of construction site.pptxSafety protocols of construction site.pptx
Safety protocols of construction site.pptxZeeshan Yousaf
 

Similar to TQM AND ETHICS.pptx (20)

Construction safety
Construction  safetyConstruction  safety
Construction safety
 
STORAGE: Dust explosion protection
STORAGE: Dust explosion protectionSTORAGE: Dust explosion protection
STORAGE: Dust explosion protection
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS code
 
Investigation into safety practices by automobile mechanics at siwdo kokompe
Investigation into safety practices by automobile mechanics at siwdo kokompeInvestigation into safety practices by automobile mechanics at siwdo kokompe
Investigation into safety practices by automobile mechanics at siwdo kokompe
 
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
 
Occupational Health and Safety - Forest Smallholders
Occupational Health and Safety - Forest SmallholdersOccupational Health and Safety - Forest Smallholders
Occupational Health and Safety - Forest Smallholders
 
Safety and envirnomental issues in mechanization
Safety and envirnomental issues in mechanizationSafety and envirnomental issues in mechanization
Safety and envirnomental issues in mechanization
 
Safety plan
Safety planSafety plan
Safety plan
 
Building Construction I Project 1 Compilation
Building Construction I Project 1 CompilationBuilding Construction I Project 1 Compilation
Building Construction I Project 1 Compilation
 
BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
17._SGW-_Personal_Protective_Equipments_(PPEs).pptx
17._SGW-_Personal_Protective_Equipments_(PPEs).pptx17._SGW-_Personal_Protective_Equipments_(PPEs).pptx
17._SGW-_Personal_Protective_Equipments_(PPEs).pptx
 
Safety measures
Safety measuresSafety measures
Safety measures
 
Step 2 preparation & safety starters
Step 2 preparation & safety startersStep 2 preparation & safety starters
Step 2 preparation & safety starters
 
Construction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over WaterConstruction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over Water
 
Tutor core 01 h&s regs and responsibilitioes
Tutor core 01 h&s regs and responsibilitioesTutor core 01 h&s regs and responsibilitioes
Tutor core 01 h&s regs and responsibilitioes
 
Construction safety session 1 (new)
Construction safety session 1 (new)Construction safety session 1 (new)
Construction safety session 1 (new)
 
Construction Site Safety - Part II
Construction Site Safety - Part IIConstruction Site Safety - Part II
Construction Site Safety - Part II
 
Safety protocols of construction site.pptx
Safety protocols of construction site.pptxSafety protocols of construction site.pptx
Safety protocols of construction site.pptx
 

More from surekha1287

Module 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptxModule 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptxsurekha1287
 
LIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptxLIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptxsurekha1287
 
Drone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptxDrone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptxsurekha1287
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxsurekha1287
 
MS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptxMS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptxsurekha1287
 
Runoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation EngineeringRunoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation Engineeringsurekha1287
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxsurekha1287
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxsurekha1287
 
unionexecutive-.pptx
unionexecutive-.pptxunionexecutive-.pptx
unionexecutive-.pptxsurekha1287
 
unionexecutive-Module 3.pptx
unionexecutive-Module 3.pptxunionexecutive-Module 3.pptx
unionexecutive-Module 3.pptxsurekha1287
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptxsurekha1287
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptxsurekha1287
 
MODULE 1 continuation .pptx
MODULE 1 continuation .pptxMODULE 1 continuation .pptx
MODULE 1 continuation .pptxsurekha1287
 
module-1 CME.pptx
module-1 CME.pptxmodule-1 CME.pptx
module-1 CME.pptxsurekha1287
 

More from surekha1287 (20)

Module 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptxModule 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptx
 
LIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptxLIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptx
 
Drone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptxDrone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptx
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptx
 
MS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptxMS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptx
 
Runoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation EngineeringRunoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation Engineering
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptx
 
Ethics.ppt
Ethics.pptEthics.ppt
Ethics.ppt
 
Module-2.pptx
Module-2.pptxModule-2.pptx
Module-2.pptx
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptx
 
Economy.pptx
Economy.pptxEconomy.pptx
Economy.pptx
 
unionexecutive-.pptx
unionexecutive-.pptxunionexecutive-.pptx
unionexecutive-.pptx
 
Module-5.pptx
Module-5.pptxModule-5.pptx
Module-5.pptx
 
unionexecutive-Module 3.pptx
unionexecutive-Module 3.pptxunionexecutive-Module 3.pptx
unionexecutive-Module 3.pptx
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptx
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptx
 
MODULE 1 continuation .pptx
MODULE 1 continuation .pptxMODULE 1 continuation .pptx
MODULE 1 continuation .pptx
 
Hydrology.pptx
Hydrology.pptxHydrology.pptx
Hydrology.pptx
 
module-1 CME.pptx
module-1 CME.pptxmodule-1 CME.pptx
module-1 CME.pptx
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 

Recently uploaded

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

TQM AND ETHICS.pptx

  • 1.
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 31. SAFETY MEASURES IN CONSTRUCTION Importance of safety • Safety in construction is a prime requirement but it is often neglected on work site. • The range of construction and building activities involving complex techniques have led to many new problems of safety measures at site result in a better work environment, higher productivity and greater contentment among workers. Safety measures • Prevention of accidents is a major aim of construction management, both for human and financial consideration..
  • 32. • Whatever the nature of construction projects, accidents are likely to occur causing physical injury, casualties and loss of money. • In order to prevent accidents at construction site, certain safety measures are to be taken in the following major activities which are prone to risk of accidents. 1) Excavation 2) Drilling and blasting 3) Storage 4) Hot bituminous works 5) Scaffolding, ladders, formwork and handling of equipment’s 6) Fabrication and erection 7) Demolition
  • 33.
  • 34. Safety measures for excavation  Before doing the excavation, a complete knowledge of underground structures, such as sewers, water pipe lines, gas mains etc. is essential and suitable precautions should be taken to prevent accident to the workers engaged in excavation work.  Personal safety equipment’s such as safety shoes, Safety helmets etc. should be worn by all persons entering a trench where hazards from falling stones or other material exists.  Whenever the workman to excavate in trenches in soft soil or fissured rock or hard soil exceeding 2m in depth, the trenches should be sufficiently shored and timbered.
  • 35.  At place where public is likely to trespass fencing or barricades should be erected to avoid accidents, during nights adequate lighting should be provided. Safety measures for Drilling and blasting  Drilling and blasting is the controlled use of explosives and other methods such as gas pressure blasting to break rock for excavation.  It is practiced more often in mining, quarrying and civil engineering such as dam and road construction.  Drilling and blasting utilizes many different varieties of explosives with different compositions and performance properties.
  • 36.  High velocity explosives are used for relatively hard rock in order to shatter and break the rock, while low velocity explosives can be used in soft rocks to generate pressure and heave effect.  Vehicles to be used for transporting explosives should be good in condition with tight wooden or non-sparkling metal floor and sides.  Explosives should be stored only in a magazine which is clean, dry, well ventilated, and reasonably cool.  Leaves, grass or broken pieces of any kind should not be allowed to accumulate within 8m of magazine.
  • 37.
  • 38.  No person should allow touching the wires and opening the bare leading wires of the electrical blasting caps during dust storms.  Smoking should be strictly prohibited at places where explosives are used.  Explosives and fuse lighters should not be stored in a damp or wet place or near oil, gas or steam pipes or other sources of heat.  Before blasting all clear signal is given.  After blasting operations, it is necessary to check the entire area of the exploded explosives, which shall be safety removed away from the work site.
  • 39. Safety measures for storage of materials  Adequate firefighting arrangements should be provided at site particularly in areas where petroleum products and timber are stored.  Explosives must be stored in proper magazines and the prescribed safety measures for handling and storage of explosives should be observed.  Petroleum products should be separately stored.  Smoking and other fires should be strictly prohibited where these products are stored.  Only required quantities of such products should be stored at site.
  • 40.
  • 41. Safety measures for hot bituminous works  Workers engaged on job involving handling of hot bituminous works should use protective wares such as boots, gloves, goggles and helmets.  When bitumen plants are working on a public road, an adequate traffic control system must be established.  Compressors, electrical installations and other equipment’s such as elevators and conveyors should be adequately protected from weather, mechanical damage and dust particles.
  • 42. • When heating and handling of hot bituminous materials is to be done in the open, sufficient stocks of clean dry sand or loose earth should be kept ready at the work site to cope with any resultant fire. • Bitumen plant should be provided with the safe means of access to working platforms, hand rails, pulley, belts and drive mechanisms should be protected by suitable guards.
  • 43. Safety measures for fabrications and erections  Fabrication is the process of bending, cutting and moulding steel structures to create beams, columns and steel members.  Moving part of all the equipment’s should be provided with safety guards.  All equipment’s such as gas cutting and welding sets, drills and power hacksaws, grinders etc. should be checked periodically to ensure their safe working.  Workers engaged in gas cutting and welding operations should wear suitable gloves, aprons, goggles and use proper screens.  Power cable for all equipment’s should be properly insulated and protected from damage and cuts.
  • 44.
  • 45.  Cut pieces and scrap should be stored at an appropriate place to avoid accidents.  Workers engaged in erection works should wear helmets and use safety belts to avoid accidents.  All erection equipment’s such as cranes, derricks, hoists, etc. should be thoroughly checked before use.
  • 46. Safety measures for Scaffolding, ladders, formwork and other equipment’s  Every scaffold should be firmly supported or suspended and properly strutted or braced to ensure stability.  The supporting bullies of formwork should be checked for each individual member.  The bullies should be properly braced. Many accidents occur due to negligence of this aspect.  When the work is been performed above a scaffold platform, a protective overhead covering should be provided for the men working on the scaffolds.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.  The protection should not be more tan 3m above the scaffold platforms and should be made of plants.  During dismantling (take to pieces) of scaffolds, necessary precautions should be taken to prevent injury to persons due to fall of loose materials, bracings and other part of scaffolds.  Care should be taken to see that no un-insulated electrical wires exist within 3m of the working platforms, gangway etc. of the scaffolds.
  • 52. Safety provisions required for explosives Anyone manufacturing or storing explosives to take appropriate measures:  To prevent fire or explosions  To limit the extent of fire or explosion including measures to prevent the spreading of fires and the communication of explosions from one location to another  To protect people from the effects of fire or explosion
  • 53.  An explosive is a material, either a pure single substance or a mixture of substances, which is capable of producing an explosion by its own energy .  It is not proper to define an explosive as a substance, or a mixture of substances, which is capable of undergoing a sudden transformation with the production of heat and gas.  The production of heat alone by the inherent energy of the substance which produces it will be enough to constitute the substance an explosive.
  • 54. SAFETY THROUGH LEGISLATION Indian government has brought up number of legislations from time to time to address the safety aspects of construction works. Some of legislation are as follows.  Factories act -1948  Mines act -1952  Indian explosives act – 1984  Indian boilers act – 1923  Petroleum act – 1934  Petroleum and minerals pipeline act – 1962  Indian electricity rules – 1956  The electricity act – 2013
  • 55.  Motor vehicle act – 1988  Contract labor act – 1970  Workman compensation act – 1923  Building and other construction work act – 1996  Occupational safety and health act – 1970  However, we need to understand that legislations alone cannot ensure safety in job construction / operations  All of our effective approach towards prevention of accidents and promotion of safety conscious is achieved  Alertness levels are increased to practice safe working habits, the rules and regulations remain the paper.
  • 56.  At the time of an untimely accident people talk about safety rules and flows in their implementations only to forget the same in one or two days.  Safety should be set up as an objective as implement as economic gains and zero accidents in job performance should be motive.  The safe working practices (such as 10000 accident free hours of production etc.) should be rewarded and hailed within the organization.  Safety should be builder’s first responsibility since controlling of accidents reduces the scrap of human and product.
  • 57. • The losses on accident of unsafe working practices / accidents are reduced output,  wasted wages  lost time  lowered morals  damaged property  loss of experienced hands  medical bills  above all loss of good will. Accidents add up to employer worries
  • 58. SAFETY CAMPAIGN • Safety campaign aims to reduce the number of injuries sustained by workers performing basic construction works. • Guidelines of National safety consist towards safe working practices should be prominently displayed at work spot and precautions to be taken to avoid accidents should be discussed in meeting. • Safety works with visual presentations should be arranged at least once in a month and all the workers need to be educated to become aware of value of safety in engineering works.
  • 59. • Use of protective clothing, safety helmets, face shields, safety equipment’s for eyes, ears, hands, feet, legs ( such as gas masks, gloves etc.) should be widely advertised and followed. • Safe working employees should be rewarded and awarded to raise the awareness levels among others. The objectives of the campaign are as follows:- To improve the capability of residential builders to control risks. During the assessment, inspectors will focus on:-  Fall prevention through voids, from ladders, and other work platforms
  • 60.  Site housekeeping  Site security  Site supervision  Additional issues related to electrical. • The campaign will also improve the health and safety of young workers in the construction industry, who are over represented in injury statistics than the older or more experienced workers. • It aims to educate managers and supervisors to ensure they can effectively manage the young workers safety in the site. • The inspectors will keep visiting the workplace in order to create awareness regarding to safety and health.
  • 61. SAFETY INSURANCE • Insurance laws are applicable only to regular employees. • In construction industry most of the labor is of casual nature and insurance laws are not applicable to them. • For the welfare of casual labor, different Acts such as Minimum wages Act, Compensation Act etc. are passed by the Government. • Keeping in mind the intensity of a probable loss in case of mishaps/unpleasant accidents in engineering works, construction activities, deferent insurance covers are available. • Owing the huge monetary and other losses in case of accidents/ loss of lives in construction industry, any uninsured activity or job may culminate into job termination.
  • 62. Following are some relevant schemes or engineering project works. • Contractors All risk insurance (CAR policies) • Machinery breakdown insurance • Loss of profit insurance following machinery breakdown • Contractor’s plant and machinery insurance. Contractors all risk insurance (CAR policy) This is a comprehensive insurance cover and provides adequate protection against loss of damages in respect of contract works, as well as third party claims towards property damage or badly injuries workman/general public.
  • 63. The following items get covered in a CAR policy under normal circumstances. • Fire accidents, lighting and explosives • Theft, burglary(illegal entry of a building with intent to commit a crime). • Bad workmanship, unintentional negligence, human errors • Natural calamities (flood, earthquakes etc.) if specifically provide in the insurance terms. Unless otherwise specified, the following are not included in the CAR policies. • Loss or damage due to war or war like operations, strike riots. • Loss or damage due to willful negligence. • Losses due to nuclear reactions, radiations, radioactive contaminators
  • 64. Machinery breakdown insurance • Normally this type of insurance covers installed working in fixed premises. • In special cases the insurance cover can be extended to include equipment’s in transit and damages to third parties as well as personal injuries arising out of breakdown of insured machinery. Loss of profit insurance • Often due to non- operations often due to malfunctioning of some mall control parts, the functioning of the entire machinery comes to stand still.
  • 65. • In such cases, this policy covers consequential losses suffered by the machine user. • Sometimes machine repair may take a long time; in such cases Machinery breakdown insurance policy above covers machine repairs cost and this policy entitles him or consequential losses/ profit losses. Contractor’s plant and machinery insurance (CPM Policy) • CPM is a special insurance policy cover due to non-production of plant and machinery not attributable to engineering reasons but to other factors such as riots, strikes, malicious damages, breakdown due to excess running’s etc.
  • 66. MORALS  Morals are the guiding principles that every citizen should hold.  It is the foundational concepts defined at both at individual and societal level.  At the most basic level, morals are the knowledge of difference between the right and wrong. Moral reasons include, • Respecting others and ourselves • Respecting rights of others • Keeping promises • Avoiding unnecessary problems to others and avoiding cheating and dishonesty, • Showing gratitude to others and encourage them to work.
  • 67. VALUES  The word value is derived from French word “valoir” which means worth, merit, usefulness or importance of a thing.  Values are individual in nature.  Values are comprised of personal concepts of responsibility, entitlement and respect.  Values are shaped by personal experience, may change over the span of a lifetime and may be influenced by lessons learned.  Values may vary according to an individual’s cultural, ethnic and/or faith-based background. Integrity is one such value.
  • 68. Characteristics of Values 1. Values represent an individual‘s highest priorities and deeply held driving forces 2. Values are the hub of personality and it has a powerful force of affecting behavior 3. Value varies according to time 4. Many values are relatively constant and durable 5. It contains a judgment element 6. Everyone does not hold the same values 7. Values are distinctly different from comforts. Comforts bring in short term gains and long term pains whereas values bring in short term pains and long term gains.
  • 69. ETHICS • Ethics is the study of the characteristics of morals. • Ethics is defined as “a system of moral principles, by which human actions and proposals may be judged good or bad, or right or wrong. • Ethics is used in determining what is right in a given situation and then following through with actions to implement what is right. There are three primary ethical directives: 1. loyalty 2. honesty 3. responsibility.
  • 70. • We will be called upon to be loyal to friends, family, organization, profession, and being loyal to one may mean being disloyal to another. • Honesty is telling the truth as you see it but it’s really much more. It does involve not lying but also giving a true and complete representation of one’s self, our actions and our views. • Responsibility requires taking ownership of the consequences of our actions and insuring no harm comes to someone because of those consequences. • Construction companies must gain and keep loyal customers
  • 71. • Their ability to acquire and maintain customers is directly related to how those customers see the company’s ethical standards from both management and employees • A company’s reputation for unethical behavior will affect its ability to draw top notch employees. • Ethics is treating everyone in a “fair” and “reasonable” manner and both are subject to wide interpretation.
  • 72. Moral Ethics Refers only to personal behavior. Involves defining, analyzing, evaluating and resolving moral problems and developing moral criteria to guide human behavior Refers to any aspect of human action . . Critical reflection on what one does and why one does it Social conventions about right or wrong conduct Refers only to professional behavior
  • 73. INTEGRITY  one of the major challenges in our construction business is to complete any project we do on time and within budget.  It requires a lot of morale and high productivity from our work crews.  In todays market it always seems that companies want the job done better, faster and with better materials at lesser cost.  The principles of integrity apply in all aspects of our lives; personal, professional and economically.  In the construction sphere, the principles of integrity are no different. We should apply them in our daily work lives.
  • 74.  In construction business, we should all feel a moral and ethical responsibility to protect the lives of our workers and to construct a project safely.  Integrity is about doing your best with honesty, consideration and with much ethical responsibility towards the work you do and the people you influence.  The key element of integrity is leadership. For construction this means hardhat professionals we should find solutions to ourselves without reliance on government for relief.
  • 75.  Also of critical importance to integrity is building an ethical culture within an organization.  What should be taken into account when giving code of ethics training to new employees/recruits is that , as with anything else in life, how you act is about desire for change in your life.  Hence everyone should understand that all it takes to be more ethical in life is that you making a conscious decision to change the way you live your life- that will be the first step in opening doors for making a difference in other peoples lives through your actions.
  • 76. TRUSTWORTHINESS  Trustworthiness is a human quality and virtue. Trustworthiness: enable others to believe in us and to rely on us without reservation or fear.  The values or qualities help us develop trustworthiness: honesty, integrity, reliability, and loyalty.  Integrity and trustworthiness are important concepts in the social sciences, because each is said to enable and enhance cooperation  There are different ways to build honesty, these are: A. Truthfulness B. Sincerity C. Candor
  • 77. ENGINEERING ETHICS  Engineering ethics is the study of moral issues and decisions confronting individuals and organizations involved in engineering.  Engineering ethics is the study of related questions about moral ideals, character, policies and relationships of people and organizations involved in technological activity.  Engineering ethics is comprised of some sets of beliefs, moral principles and rules that determine what is right and what is wrong or what is good and what is bad in the engineering profession, which are commonly applied to all engineers.
  • 78. Two important ethical codes that engineer must be aware of are 1. The national society of professional engineers (NSPE) code of ethics 2. The American society of civil engineers (ASCE) code of ethics  These codes are sets of rules that clearly lay out the ways that professional engineers must conduct themselves in the workplace.  If an engineer is found violating one of these codes, they may lose their license and could possibly face legal charges.
  • 79. Why Study Engineering Ethics?  Engineering ethics is not only teaching moral behavior in knowing about immoral and amoral in a set of beliefs, but also increasing the ability of engineers and other professionals to face boldly with the moral problems arising from technological advancements, change and other related activities. Study of ethics helps engineers develop a moral autonomy:  Ability to think critically and independently about moral issue  Ability to apply this moral thinking to situations that arise in the course of professional engineering practice
  • 80.  Ethical problems in engineering are often complex and involve conflicting ethical principles.  Engineers must be able to intelligently resolve these conflicts and reach a defensible decision. PROFESSIONAL RIGHTS  The right to engage in the activities of professional societies  The right to form and express one’s professional judgment freely  The right to talk publicly about one’s work within bounds set by confidentiality obligation
  • 81.  The right to protect the clients and the public from the dangers that might arise from one’s work  The right to professional recognition of one’s services.  The right to refuse to carry out illegal and unethical activity.
  • 82. EMPLOYEE RIGHTS • The employee will not be deprived of any enjoyment of reasonable privacy in his/her workplace. • No personal information about employees will be collected or kept other than what is necessary to manage the organization efficiently and to meet the legal requirements. • There should be no discrimination against an employee for criticizing ethical, moral or legal policies and practices of the organization. • No employee who alleges her/his rights have been violated will be discharged or penalized without a fair hearing by the employer organization.
  • 83. CONFIDENTIAL INFORMATION  Information considered desirable to be kept secret.  Any information that the employer or client would like to have kept secret in order to compete effectively against business rivals.  This information includes how business is run, its products, and suppliers, which directly affects the ability of the company to compete in the market place.  Helps the competitor to gain advantage or catch up
  • 84. PROPRIETARY INFORMATION  It is information such as financial data, test results or trade secrets that is viewed as the holders property and that they wish to keep from becoming public knowledge.  Information that a company owns or proprietors.  This is primarily used in legal sense also called Trade Secret.  A trade secret can be virtually any type of information that has not become public and which an employer has taken steps to keep secret.
  • 85.  For information to be considered proprietary, it should not readily available in public sources, it should provide some sort of competitive advantage, and the company should take al reasonable steps to maintain its confidentiality.  More companies are now appointing information managers to assume responsibility for keeping such information safe and secure.  This can be issue on construction projects, where members of the project team or client may learn information that one party wishes to stay confidential.
  • 86.  As a result, organizations or employees with access to such information may be required to non disclosure agreements or confidentiality agreements that can limit the use of ideas and information for a specific purpose for a certain period of time.  They may protect information recorded in a certain form, perhaps marked as confidential, or they may protect information shared under certain circumstances, such as in presentations or meetings or during the course of consultancy.  They can be used to prevent commercially sensitive information from being shared or to prevent parties from communicating certain information to press or other third parties.
  • 87. Non disclosure agreements can cover information such as:-  Intellectual property  Commercial or trading information  Technical drawings or designs  Business plans  Customer and potential customer lists  Mathematical and chemical formulae  Trade secrets which could include programmers or processes  Personal information about individuals involved in a project
  • 88. CONFLICT OF INTEREST CONFIDENTIALITY  Confidential information is a information deemed desirable to keep secret.  Engineers are required to keep confidential certain information belonging to their employer or client. Such information, if released, might allow other companies or organizations to gain an unfair competitive advantage.  A “conflict of interest” is a situation in which a person, such as a public official, an employee or a professional, has a private or personal interest sufficient to appear to influence the objective exercise or his or her official duties.
  • 89.  Employees are not allowed to engage, either within or outside working hours, in any other gainful employment or conduct any form of business activity, either personally or through the agency of another, unless prior approval is obtained from the Managing Director and HR Department.  A COI is a situation in which a person organization is involved in multiple interests, financial or otherwise in situations where serving one the interests could involve working against one of the other interests.  It is a set of circumstances that creates a risk that professional judgment or actions regarding a primary interest will be unduly influenced by a secondary interest.
  • 90. GIFT AND BRIBE • ‘If you think that your offer of acceptance of a particular gift would have grave or merely embarrassing consequences for your company if made public, then the gift should be considered a bribe’. • Bribe can be said to be a substantial amount of money or goods offered beyond a stated business contract with the aim of winning an advantage in gaining or keeping the contract. Here ‘substantial’ means that which is sufficient to distort the judgment of a typical person. When does a gift become a bribe? • Something offered or given to someone in a position of trust in order to induce him/her to act dishonestly
  • 91. PRICE FIXING  An act was passed, which forbade (prevented) companies from jointly setting prices in ways that restrain free competition and trade.  Unfortunately, many senior people, well respected and positioned were of the opinion that ‘price fixing’ was good for their organizations and the public.  An acceptable mechanism for price fixing must be found by the engineer with the help of the economist, scientist, lawyer and politician which could protect the environment through self- correcting procedures.
  • 92. WHISTLE BLOWING  Construction Industry employees are often required to report improper, unsafe or illegal construction activities.  Whistle blowing is an act of conveying information about a significant moral problem by a present or former employee, outside approved channels (or against strong pressure) to someone, in a position to take action on the problem.  The features of Whistle blowing are: Act of disclosure, Topic, Agent and Recipient
  • 93. • Act of Disclosure: Intentionally conveying information outside approved organizational channels when the person is under pressure not to do so from higher-ups. • Topic: The information is believed to concern a significant moral problem for the organization. • Agent: The person disclosing the information is an employee or former employee. • Recipient: The information is conveyed to a person or organization who can act on it.
  • 94. Types of Whistle Blowing  External Whistle blowing: The act of passing on information outside the organization.  Internal Whistle blowing: The act of passing on information to someone within the organization but outside the approved channels.  Either type is likely to be considered as disloyalty, but the second one is often seen as less serious than the latter.  From corporations’ point of view both are serious because it leads to distrust, disharmony, and inability of the employees to work together.
  • 95. • Open Whistle blowing: Individuals openly revealing their identity as they convey the information. • Anonymous Whistle blowing: Individual conveying the information conceals his/her identity. END OF MODULE 3