Your Renovation Project:
A Timeline
Brought to you by
Vendors Needed
1) Expediter. An expediter is someone who is very familiar with the construction-filing
process in the five boroughs of NYC.
2) Architect/Engineer. A registered architect or professional engineer are required for a
Department of Buildings (DOB) submission. An architect will survey your property,
draft drawings, sign/seal the drawing and relevant forms, address any objections to
the drawings with your condo/co-op board and the DOB, and conduct a final
inspection when construction is complete.
3) Asbestos inspector. An asbestos inspection is required for all renovation jobs being
done in buildings built before April 1986.
4) Contractor. A fully insured contractor must be hired to pull the proper work permits.
Your contractor should have both worker’s compensation and disability on file with
the DOB. Your board may request additional insurance requirements.
Major Steps
1. Site survey by an architect and drawing plans
2. Meeting with a contractor
3. Condo/Co-op board submission
4. Asbestos inspection
5. Department of Buildings (DOB) submission
6. Pull work permits
7. Sign off the job with the DOB
Site Survey by an Architect
An architect needs to visit your space to measure all walls and
document the features of your unit. This is also a chance to
discuss the feasibility of your scope of work. An architect can
give you insight into what the board will approve and what they
won’t allow.
The architect will then draft drawings of the existing conditions
and produce a proposed layout after discussing the project with
your contractor.
Time: It takes a few days’ planning to do the survey and about a week to
finish the drawings.
Meeting with a Contractor
Like an architect, a contractor will give you even more insight on
the feasibility of your projected scope of work. Your board will
want to see a detailed scope of work from a contractor so it is a
good idea to settle on one at this point. We can arrange for you
to meet with contractors once an agreement for expediting
services has been signed.
Time: It takes a few days to set up an appointment with various
contractors to meet at your unit.
Condo/Co-op Board Submission
Your board must first approve your plans before we submit the
job to the DOB. This is due to the fact that your board must sign
the DOB forms as per your building’s alteration agreement.
Minimum requirements for a board submission:
1. Two sets of signed/sealed drawings
2. Letter of Intent from shareholder (you)
3. Detailed scope of work from a contractor
Time: It usually takes a board 2-3 weeks to review plans.
Asbestos Inspection
The DOB requires that all renovation projects in buildings built
before April 1986 submit an asbestos inspection report done
within the last year and specific to the project being submitted.
We’ll set up an inspection for you after the drawings have been
completed by the architect.
Time: It takes 2-3 days to set up an inspection and a few more days to
get the inspector’s samples analyzed so a report can be produced for the
DOB submission.
DOB Submission
The following items must be submitted to the DOB:
1. Three sets of signed/sealed drawings
2. Forms signed by all relevant shareholders (architect, board
officers, you, etc.)
3. Asbestos inspection report
Time: The amount of time for approval depends on the filing method
used. See next slide for more details.
DOB Filing Methods
There are two main filing methods for a DOB submission:
1. Professional Certification. Super fast filing method but not
allowed by most condo/co-op boards.
2. Standard Plan Review. Much longer review process but you
can rest assured that your proposed work if up to code and
approved by the DOB.
More details about these two filing methods on the next two slides.
DOB Filing Methods:
Professional Certification
This method allows the architect to take responsibility for building code
compliance and zoning laws. The DOB doesn’t review the project beyond
taking a look at the scope of work and seeing if the estimated job costs
are reasonable. They do this because that is how they calculate their city
fees (~2% of the job costs).
• Approval time? One day.
• When can my contractor get his permits? Same day.
• Please note: Because the DOB doesn’t review your project,
most boards don’t allow for this method to be used.
Time: One week. Once we have your board’s approval, signed/sealed
drawings, an asbestos inspection , completed forms signed by everyone,
and city fee checks, we can submit our package to the DOB and get it
approved and permitted in just a few days (if all goes well).
DOB Filing Methods:
Standard Plan Review
This method is the most common filing method used. It requires that your job be assigned to a
plan examiner and reviewed for building code and zoning law compliance. Almost all jobs are
disapproved upon first review. The examiner’s objections tend to be unpredictable and for
simple things like a request for additional notes on the drawings.
• Approval time? 6-8 weeks. The first 3-4 weeks are spent waiting for the plan
examiner to review the project. Then it takes another 3-4 weeks to get in to see
the plan examiner to address the objections.
• Any way to speed this up? Yes there is. If the project is small enough, an
architect can do what is called a same-day review. This will shave 3-4 weeks off
the approval process because the job will be reviewed that day.
• When can my contactor get his permits? The day after the job is approved.
Time: Four to six weeks. Most of this time is spent waiting to see the
plan examiner to discuss the objections and get the job approved.
Pull Work Permits
Once your job is approved by the DOB, we’ll work with your
contractor to pull the required work permits. Your contractor
must be registered with the DOB and have a tracking number.
Their insurance file must also be up-to-date with at least
worker’s compensation and disability insurance. These are
requirements from your board as well.
Time: Just a day or two. Your contractor has to sign/notarize a form and
make sure his insurance file is up-to-date at the DOB.
Sign Off the Job
Once construction is complete, we must submit paperwork to sign off the job
with the DOB. This includes submitting a final cost affidavit showing the
actual job costs and the architect doing a final inspection to ensure the work
was done according to the approved plans.
Please note: If the actual costs are more than 5% of the estimated costs
submitted at time of approval, a Post-Approval Amendment (PAA) must be
submitted to increase the job costs. This additional step is not included in our
scope of work and will be billed separately. This step is not required for most
projects.
Time: Two to three weeks. You can use your newly renovated space
while we finish off the job by signing it off with the DOB.

More Related Content

What's hot

Owner Big Picture Repair Legal Issues
Owner Big Picture Repair Legal IssuesOwner Big Picture Repair Legal Issues
Owner Big Picture Repair Legal IssuesConstruction Cicerone
 
Sample architectural drafting contract
Sample architectural drafting contractSample architectural drafting contract
Sample architectural drafting contract
Maysam Ghaffari
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
Farah Sham
 
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
Galala University
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
Pang Khai Shuen
 
All About Construction Cash Allowances v1.2
All About Construction Cash Allowances v1.2All About Construction Cash Allowances v1.2
All About Construction Cash Allowances v1.2
Peter Vander Klippe
 

What's hot (6)

Owner Big Picture Repair Legal Issues
Owner Big Picture Repair Legal IssuesOwner Big Picture Repair Legal Issues
Owner Big Picture Repair Legal Issues
 
Sample architectural drafting contract
Sample architectural drafting contractSample architectural drafting contract
Sample architectural drafting contract
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
All About Construction Cash Allowances v1.2
All About Construction Cash Allowances v1.2All About Construction Cash Allowances v1.2
All About Construction Cash Allowances v1.2
 

Viewers also liked

Organizational Renovation
Organizational RenovationOrganizational Renovation
Organizational Renovation
Jason Little
 
Renovation & Modernization - Practices in India against Global
Renovation & Modernization - Practices in India against GlobalRenovation & Modernization - Practices in India against Global
Renovation & Modernization - Practices in India against GlobalSayan Aich PE, MIET(UK)
 
Digital Transformation Innovation or Renovation
Digital Transformation Innovation or RenovationDigital Transformation Innovation or Renovation
Digital Transformation Innovation or Renovation
Information Services Group (ISG)
 
Hotel Renovation
Hotel RenovationHotel Renovation
Hotel Renovation
Ottis Bunning
 
The Digital Journey
The Digital JourneyThe Digital Journey

Viewers also liked (6)

Organizational Renovation
Organizational RenovationOrganizational Renovation
Organizational Renovation
 
Renovation & Modernization - Practices in India against Global
Renovation & Modernization - Practices in India against GlobalRenovation & Modernization - Practices in India against Global
Renovation & Modernization - Practices in India against Global
 
Digital Transformation Innovation or Renovation
Digital Transformation Innovation or RenovationDigital Transformation Innovation or Renovation
Digital Transformation Innovation or Renovation
 
Hotel Renovation
Hotel RenovationHotel Renovation
Hotel Renovation
 
The Digital Journey
The Digital JourneyThe Digital Journey
The Digital Journey
 
Arrow Consulting PMP
Arrow Consulting PMPArrow Consulting PMP
Arrow Consulting PMP
 

Similar to Your Renovation Project 2014

Coordinated project information (cpi)
Coordinated project information (cpi)Coordinated project information (cpi)
Coordinated project information (cpi)
Abdullahi MohammedLawal
 
Partnering For Success In 2015
Partnering For Success In 2015Partnering For Success In 2015
Partnering For Success In 2015Lance Moseley
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
Sithick Mohamed .
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
Shivam Sood
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
Research development
Research developmentResearch development
Research developmentJ-Sern Phua
 
Commercial Building Construction: What Goes Into a New Construction Project
Commercial Building Construction: What Goes Into a New Construction ProjectCommercial Building Construction: What Goes Into a New Construction Project
Commercial Building Construction: What Goes Into a New Construction Project
comelectricalonline
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
brainquisitive
 
Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Sam
 
Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction Project
Melissa Brumback
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
6 Steps to Smarter Construction Procurement | ezIQC Infographic
6 Steps to Smarter Construction Procurement | ezIQC Infographic6 Steps to Smarter Construction Procurement | ezIQC Infographic
6 Steps to Smarter Construction Procurement | ezIQC Infographic
Gordian
 
Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11Jack Tan Kiah Kee
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
EyobMiteku
 

Similar to Your Renovation Project 2014 (20)

Coordinated project information (cpi)
Coordinated project information (cpi)Coordinated project information (cpi)
Coordinated project information (cpi)
 
Partnering For Success In 2015
Partnering For Success In 2015Partnering For Success In 2015
Partnering For Success In 2015
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Research development
Research developmentResearch development
Research development
 
nancyevangelista CV
nancyevangelista CVnancyevangelista CV
nancyevangelista CV
 
Commercial Building Construction: What Goes Into a New Construction Project
Commercial Building Construction: What Goes Into a New Construction ProjectCommercial Building Construction: What Goes Into a New Construction Project
Commercial Building Construction: What Goes Into a New Construction Project
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Resume ( Proc)
Bonny Resume ( Proc)
 
Contractor
ContractorContractor
Contractor
 
Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction Project
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
6 Steps to Smarter Construction Procurement | ezIQC Infographic
6 Steps to Smarter Construction Procurement | ezIQC Infographic6 Steps to Smarter Construction Procurement | ezIQC Infographic
6 Steps to Smarter Construction Procurement | ezIQC Infographic
 
Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
 

Recently uploaded

Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 

Recently uploaded (20)

Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 

Your Renovation Project 2014

  • 1. Your Renovation Project: A Timeline Brought to you by
  • 2. Vendors Needed 1) Expediter. An expediter is someone who is very familiar with the construction-filing process in the five boroughs of NYC. 2) Architect/Engineer. A registered architect or professional engineer are required for a Department of Buildings (DOB) submission. An architect will survey your property, draft drawings, sign/seal the drawing and relevant forms, address any objections to the drawings with your condo/co-op board and the DOB, and conduct a final inspection when construction is complete. 3) Asbestos inspector. An asbestos inspection is required for all renovation jobs being done in buildings built before April 1986. 4) Contractor. A fully insured contractor must be hired to pull the proper work permits. Your contractor should have both worker’s compensation and disability on file with the DOB. Your board may request additional insurance requirements.
  • 3. Major Steps 1. Site survey by an architect and drawing plans 2. Meeting with a contractor 3. Condo/Co-op board submission 4. Asbestos inspection 5. Department of Buildings (DOB) submission 6. Pull work permits 7. Sign off the job with the DOB
  • 4. Site Survey by an Architect An architect needs to visit your space to measure all walls and document the features of your unit. This is also a chance to discuss the feasibility of your scope of work. An architect can give you insight into what the board will approve and what they won’t allow. The architect will then draft drawings of the existing conditions and produce a proposed layout after discussing the project with your contractor. Time: It takes a few days’ planning to do the survey and about a week to finish the drawings.
  • 5. Meeting with a Contractor Like an architect, a contractor will give you even more insight on the feasibility of your projected scope of work. Your board will want to see a detailed scope of work from a contractor so it is a good idea to settle on one at this point. We can arrange for you to meet with contractors once an agreement for expediting services has been signed. Time: It takes a few days to set up an appointment with various contractors to meet at your unit.
  • 6. Condo/Co-op Board Submission Your board must first approve your plans before we submit the job to the DOB. This is due to the fact that your board must sign the DOB forms as per your building’s alteration agreement. Minimum requirements for a board submission: 1. Two sets of signed/sealed drawings 2. Letter of Intent from shareholder (you) 3. Detailed scope of work from a contractor Time: It usually takes a board 2-3 weeks to review plans.
  • 7. Asbestos Inspection The DOB requires that all renovation projects in buildings built before April 1986 submit an asbestos inspection report done within the last year and specific to the project being submitted. We’ll set up an inspection for you after the drawings have been completed by the architect. Time: It takes 2-3 days to set up an inspection and a few more days to get the inspector’s samples analyzed so a report can be produced for the DOB submission.
  • 8. DOB Submission The following items must be submitted to the DOB: 1. Three sets of signed/sealed drawings 2. Forms signed by all relevant shareholders (architect, board officers, you, etc.) 3. Asbestos inspection report Time: The amount of time for approval depends on the filing method used. See next slide for more details.
  • 9. DOB Filing Methods There are two main filing methods for a DOB submission: 1. Professional Certification. Super fast filing method but not allowed by most condo/co-op boards. 2. Standard Plan Review. Much longer review process but you can rest assured that your proposed work if up to code and approved by the DOB. More details about these two filing methods on the next two slides.
  • 10. DOB Filing Methods: Professional Certification This method allows the architect to take responsibility for building code compliance and zoning laws. The DOB doesn’t review the project beyond taking a look at the scope of work and seeing if the estimated job costs are reasonable. They do this because that is how they calculate their city fees (~2% of the job costs). • Approval time? One day. • When can my contractor get his permits? Same day. • Please note: Because the DOB doesn’t review your project, most boards don’t allow for this method to be used. Time: One week. Once we have your board’s approval, signed/sealed drawings, an asbestos inspection , completed forms signed by everyone, and city fee checks, we can submit our package to the DOB and get it approved and permitted in just a few days (if all goes well).
  • 11. DOB Filing Methods: Standard Plan Review This method is the most common filing method used. It requires that your job be assigned to a plan examiner and reviewed for building code and zoning law compliance. Almost all jobs are disapproved upon first review. The examiner’s objections tend to be unpredictable and for simple things like a request for additional notes on the drawings. • Approval time? 6-8 weeks. The first 3-4 weeks are spent waiting for the plan examiner to review the project. Then it takes another 3-4 weeks to get in to see the plan examiner to address the objections. • Any way to speed this up? Yes there is. If the project is small enough, an architect can do what is called a same-day review. This will shave 3-4 weeks off the approval process because the job will be reviewed that day. • When can my contactor get his permits? The day after the job is approved. Time: Four to six weeks. Most of this time is spent waiting to see the plan examiner to discuss the objections and get the job approved.
  • 12. Pull Work Permits Once your job is approved by the DOB, we’ll work with your contractor to pull the required work permits. Your contractor must be registered with the DOB and have a tracking number. Their insurance file must also be up-to-date with at least worker’s compensation and disability insurance. These are requirements from your board as well. Time: Just a day or two. Your contractor has to sign/notarize a form and make sure his insurance file is up-to-date at the DOB.
  • 13. Sign Off the Job Once construction is complete, we must submit paperwork to sign off the job with the DOB. This includes submitting a final cost affidavit showing the actual job costs and the architect doing a final inspection to ensure the work was done according to the approved plans. Please note: If the actual costs are more than 5% of the estimated costs submitted at time of approval, a Post-Approval Amendment (PAA) must be submitted to increase the job costs. This additional step is not included in our scope of work and will be billed separately. This step is not required for most projects. Time: Two to three weeks. You can use your newly renovated space while we finish off the job by signing it off with the DOB.