WORKS PROCUREMTN
EVALUATION OF BIDS
1
By Frew Bekele
Contents
1. Introduction
2. Works Contracts
3. Bidding Documents
4. Evaluation And Qualification Criteria Framework
5. Evaluation Of Bids
6. Procurement Complaint
2
C. Contents of Each Section of BD
Section 2- BDS (PIT)
Supplements the ITB by specifying individual bidding
document;
All clauses refer to Section 1 and are prepared for each
specific contract;
The BDS will not be part of the resulting contract document;
Any change/qualification to be made to the standard ITB is
made here and it is wise to see it with care.
Any information in the BDS precedence over the one in ITB;
3
A. Evaluation Procedure
i. Pre-Qualification
4
Submission of pre-qualification
document
Evaluation
Invitation for Bid
Bid Submission and Evaluation
Approval and award to the least
evaluated bidder
A. Evaluation Procedure
ii. Modified Post-Qualification (two envelope)
5
Submission of P.Q. Application and
Financial Offer
Evaluation of P.Q. Application
Document
Opening & evaluation of Financial
offer of Post Qualified Bidders
Approval and award of the least
evaluated Bidder
Evaluation Approval Procedure
6
Tender Analysis
Committee (TAC)
Endorsement of
Evaluation by Contract
Award Committee
Approval of Evaluation
Report by the Director
General of ERA
An Ad hoc committee
Comprise of three
professionals
Standing committee
No-objection from
financer incase of financed
projects
Standard Bid Evaluation procedures and
principles
Bids are Evaluated based on the information/criteria
contained in the bidding document (BD);
Confidentiality of the process until the successful
bidder is notified;
Written clarification on ambiguities or inconsistency
may be requested;
No circumstances shall justify meetings or
conversation between the Employer and Bidders
during the bid evaluation process;
No changes in the bid price or substance are allowed
7
C. Sequences of bid evaluation
Bid opening
Preliminary examination
Determination of bid
responsiveness
Detail Evaluation
8
C. Sequences of bid evaluation
Bid opening
Opening shall be the same time with the deadline for receipt
of bids;
Date, time and place as announced in the BD;
Bids shall be opened in public;
Bidders names, offer amounts, Currency of bid, any
modification/alternative…are read aloud,
Bid security is checked & read;
9
C. Sequences of bid evaluation
Bid opening cont…
Any envelope containing Substitutions, Modifications, or
Withdrawals must be read out, recorded;
Bids received after the time stipulated will not be opened;
No bid should be rejected at the bid opening except those
received after the deadline;
All records of bid opening are reported as a minute of bid
opening.
10
Bid Evaluation Committee
 A team of min. 3 experts (TAC) or a consultant
may carry out the tender evaluation;
 Qualified members preferably those who
participated in the preparation of BD;
 The competence and integrity of the members of
the TAC are crucial (specific knowledge)
 The members evaluate independently and discuss
on their findings
11
C. Sequences of bid evaluation
Preliminary examination
The purpose of preliminary examination is to eliminate any
bid from further and more complicated consideration if they
don't meet the minimum standard of acceptability – not
substantially responsive
12
C. Sequences of bid evaluation
Preliminary examination
Verification: Bids should be properly signed, sealed, valid,
Eligibility requirement;
Acceptable bid securities;
Bid should contain all required documents;
Changes should be initialed;
Bids should be complete;
The above are checks for substantial responsiveness. Bids
should not be rejected on trivial /minor deviations or
procedural ground.
13
C. Sequences of bid evaluation
Preliminary examination cont…
Examples of minor deviations
Failure to initial on few pages of supporting information;
Submitting less copies of BDs;
Not using the form supplied, but furnishing the required
information;
Missing of attaching existing documentations (without giving
any benefit to the bidder & without prejudice to the interest
of other bidders);
…etc
14
C. Sequences of bid evaluation
Preliminary examination cont…
Examples of Major deviations
Stipulating price adjustment in fixed price tenders
Proposing a different design or product that does not offer
equivalent performance/not meeting specifications
Programming of contract start-up, delivery, installation, or
construction that does not comply with required times
Subcontracting in a significantly different quantity or
method than that allowed
Declining to take vital responsibilities and liabilities, e.g.
performance guarantees and insurance coverage
Taking exception to critical provisions e.g. applicable law,
taxes and duties, and dispute resolution procedures; etc…
15
C. Sequences of bid evaluation
Determination of bid responsiveness
A substantially responsive Bid is one, which conforms to all the
terms, conditions, and specifications of the bidding
documents, without material deviation or reservation. A
material deviation or reservation is one ;
 (a) which affects in any substantial way the scope, quality, or
performance of the Works;
 (b) which limits in any substantial way, inconsistent with the
bidding documents, the Employer’s rights or the Bidder’s
obligations under the Contract; or
 (c) whose rectification would affect unfairly the competitive
position of other bidders presenting substantially responsive
bids
16
C. Sequences of bid evaluation
Detailed Examination of Bids
Correction for Errors;
Corrections for Provisional Sums;
Modifications and Discounts;
Evaluation currency;
Application of Domestic Preference;
Alternative Bids
Priced deviations;
17
C. Sequences of bid evaluation
Detailed Examination of Bids cont…
Correction of arithmetic error
Check for consistency of stated quantities and prices;
The quantities should be as stated in the BD;
Check for total bid price & for any discrepancy;
The bidder must accept such arithmetic corrections;
18
Corrections and
Unconditional Discounts
19
Bidder Read-out Bid Price(s) Corrections Corrected
Bid Price(s)
Unconditional
Discounts2
Corrected/Discou
nted Bid Price(s)
Currency(ie
s)
Amount(s
)
Computatio
nal Errors1
Provision
al Sums
Percen
t
Amount(s
)
(a) (b) (c) (d) (e) (f) = (c) +
(d) - (e)
(g) (h) (i) = (f) – (h)
etc.
Note: Only bids accepted for preliminary examination (Table 5, column g) should be included in this and
subsequent tables. Columns a, b, and c are from Table 4 (columns a, d, and e, respectively).
1 Corrections in column d may be positive or negative.
2 If the discount is offered as a percent, column h is normally the product of the amounts in columns f and
g. Refer to para. 6(c). If the discount is provided as an amount, it is entered directly in column h. A price
increase is a negative discount.
C. Sequences of bid evaluation
Detailed Examination of Bids cont…
Conversion to common currency
Convert to Borrower country’s currency at the selling rate
(for comparison purpose only);
Reference date for currency conversions & source to be
used are indicated in BDS.
20
Conversion to common
currency
21
Bidde
r
Corrected/Discou
nted
Payment Composition1 Exchang
e
Amounts
in
Exchang
e
Evaluation
Currency
Bid Price
(in specified
currency)
Currency
of
Payment
Percent
of Total
Bid
Amount
in
Evaluatio
n
Currency
Rate
Used by
Bidder1
Currency
of
Payment
Rate for
Evaluatio
n2
Bid
Prices
Total3
(a) (b) (c) (d) (e) = (b)
x (d)
(f) (g) = (e)
x (f)
(h) (i) = (g)
x (h)
(j)
etc.
Domestic Preference for
domestic bidders
allows a 7½ percent margin of preference for
domestic bidders.
Sub clause 32.3 states that a domestic bidder
is one that meets the following criteria:
for an individual firm:
(i) is registered in the country of the Employer;
(ii) has more than 50 percent ownership by nationals of the country
of the Employer;
(iii) Does not subcontract more than 10 percent of the Contract Price,
excluding Provisional Sums, to foreign contractors.
22
Domestic Preference for
domestic bidders
for a joint venture (JV) of domestic firms:
(i) individual member firms shall satisfy Sub-Paragraphs 32.3 (a) (i)
and (a) (ii) above;
(ii) the JV shall be registered in the country of the Employer;
(iii) the JV shall not subcontract more than 10 percent of the Contract
Price, excluding Provisional Sums, to foreign firms.
23
Domestic Preference for
domestic bidders
Bidder
Corrected/
Discounted Bid
Price
Domestic
Preference
Group
Total Evaluation
Currency
(converted in to
Single Currency)
Preference
(7½%)
Total Comparison
Price
(a) (b) (d) (e ) (f) (g) = (e) + (f)
24
C. Sequences of bid evaluation
Detailed Examination of Bids cont…
Application of qualification/evaluation criteria
Strictly apply only the evaluation and qualification criteria
specified in the BD;
In the case of Post qualification of bidders, the criteria for
post qualification should be clearly set out in the BD;
If the lowest evaluated bidder fails to meet minimum
qualification requirements, the bid is rejected and the next
lowest evaluated bidder is subject to post qualification. (in
case of one envelope system). Otherwise; will be rejected
before opening of the financial bid
25
C. Sequences of bid evaluation
Detailed Examination of Bids cont…
Comparison of bids
After all arithmetic corrections and conversion to common
currency is made, bids are compared:
 To determine the lowest evaluated bidder;
 With the engineer’s/Employer’s estimate;
26
Preparation of evaluation
report
It Is Good Practice To have “Table of
Contents”
Bid Evaluation Summary Checklist
The Report should record all necessary
information including:
 Background of the project and financing;
 Bid opening events & minute;
27
Preparation of evaluation
report
The report covers among other things
 Key dates and steps in the bidding process
 Bid prices, corrections, discounts & currency
conversion
 Deviations
 Domestic preference
 Qualification results
 Clarification process
 Name of bidders rejected & the reasons
 Proposed contract award
28
D. Common mistakes during Bid
evaluation
Rejecting proposals/bid during opening (Conducting
evaluation during bid opening);
Using criteria which is not communicated to bidders in the
bidding document
Rejecting proposals/bid on trivial procedural ground
Arithmetic checking using bidders quantity
Currency conversion using inappropriate exchange rate
Discount application
Eligibility or Exclusion for domestic preferences
29
E. Common mistakes of bidders
Missed to enclose the bid submission forms
Lack to indicate the bid validity period
Using unapproved format for bid security
Missed to signed and stamp the document
Missed to attached appropriate power of attorney
Missed to attached the required attachments
Providing incomplete information
Using other standard bidding documents as well as clauses
than the specific project
Deviation from the scope, and
others
30
8. Questions for discussions
1. A bidder has arrived a minute after
the deadline for submission. Will the
bid be accepted?
2. The bidders bid validity period has
been found 2 days short of the
specified 120 days. Is it minor or
major deviation?
31
9. Questions for discussions
3. In ICB bid, A bidder has not submitted
Renewed license. Will it be reason for
rejection? Why?
4. After bids were submitted, A bid
opening was postponed due to
unavailability of majority of the tender
committee. Is there any problem with
this? why
32
Questions for discussions
5. The bidder has forgotten to include his
renewed trade license in his bid:
1. Is it minor or major deviation?
2. The bidder was requested to submit the
missed document and submitted the
license which has been renewed after the
dead line for bid submission. Will you
reject the bidders bid?
33
Questions for discussions
6. List some of examples of major
deviations in bids;
7. A bidder has written in his bid the
following: “We would like an increase
in the amount of mobilization
advance”. Can this be considered as
deviation?
34
Questions for discussions
8. A bid document was found that the bidding
form was not signed, but the bidder’s
stamp is there. Is it material deviation?
9. The client has varied the quantity of items
to be purchase by more than 15% during
award. What technical & procedural
problems does this involve?
35
10.Cases for discussions
Cases 1:
During the bid evaluation of an ICB major works contract ( in which
only 4 bidders were shortlisted through prequalification process and
only 2 submitted their bids), a major unbalanced rate to one work
item was discovered in the bid of the lowest bidder. The procuring
entity has requested the bidder for clarifications and breakdowns of
the very exaggerated rate. The bidder had submitted his breakdowns
and during reviewing the submitted breakdowns, the client learned
that the bidder has made mistakes in the unit of measurement of the
work item whose rate was exaggerated. Correcting the unit of
measurement from LM to CM , as it is in the BD, would reduce the
price offered by about USD 6 Million. The client has made no change
to the breakdown except the unit of measurement and considered
this as “correction of arithmetic errors discovered by the client during
the evaluation of the bids, in accordance with ITB clause 31”. And
recommended the award with the corrected Price.
 Is this arithmetic corrections?
 Is the process fair, transparent, and acceptable??
36
Cases 2
EXCEPTIONALLY LOW BID
The six low bids for a road civil works contract have produced the following results after
evaluation: €
Bid A (Foreign) 4,880,243
Bid B (Local) 6,547,576
Bid C (JV Foreign) 6,841,782
Bid D (Local) 7,449,621
Bid E (JV Foreign/Local) 7,810,934
Bid F (Foreign) 8,075,122
The Employer’s estimate was €6,650,000. All of the above firms were pre-qualified.
If the lending institution financing this project required the contract to be awarded to the
bidder who was the “lowest evaluated, and met the appropriate standards of capability and
financial responsibility” it would appear that Firm A should be awarded the contract.
Questions:
(a) On the basis of the information above, what possible objections would you raise to
an award to Firm A?
(b) If Firm A is awarded the contract, should the Performance Security be increased
above the stated 10%?
37
CASE NO. 3
38
QUALIFIED BID
The following conforming bids are received on a construction project:
A €m98 B €m100 C €m102
The bid validity period is 90 days.
B offers a price reduction of 5% (i.e. a bid of €95 million) if the bid evaluation can be
completed and the notification of award made within 60 days, because he is already
mobilized on a nearby site with construction nearing completion, and has his labor force
waiting.
Question 1:
Can the Employer consider B’s alternative offer?
Question 2:
What if (A) had made a similar offer?
CASE NO 4: QUANTIFIABLE QUALIFICATION
Bids were received on a works contract in a remote area. The bidding documents stated: “There is a
Class 3 public road providing access to the site.” [Road transport regulations in the country stated that
Class 3 roads were designed to carry 10 ton axle loading.]
The low bidder, in the amount of €100M, qualified his bid as follows: “My bid is based on the assumption
that the State or Employer, in order to provide access to the site, will strengthen any weak bridges as
necessary to carry my heavy equipment, which has maximum axle loading of 10 tons.”
One other bidder made a similar qualification; the remaining six bidders had no comment on access.
A quantification of the qualification, i.e. for the Employer to arrange for repair of the bridges, amounts to
€3 million, bringing the low bidder’s evaluated price to €103 million. The next low bidder (without
qualification) is €110 million.
Although originally designed for 10 ton axle loading, some bridges were now in poor condition. The
timing of the repair work might place the Employer at risk regarding claims from the Contractor for delay
in mobilization.
The Employer is faced with a number of alternatives:
1) ask the bidder to withdraw his qualification without any change in bid price;
2) reject the bid as non responsive (i.e. containing a material deviation) and award the contract to
the next low bidder at €110m;
3) accept the qualified bid in the amount of €100m (since it is the lowest evaluated at €103m), then
arrange for repair of the bridges himself, and risk claims from the Contractor subsequently for
delay;
4) accept the qualified bid in the amount of €100m, then issue an extra works order after award of
contract for the contractor to do the work, or
5)somehow, without infringing the Rules, or the bidding conditions, or being unfair to other bidders,
shift the responsibility for bridge repair to the Bidder/Contractor before award of contract, albeit at
increased cost.
Question:
How would you proceed as Employer?
39
Exercise
Subsequent to ERA invitation to participate for ICB project of Azezo-Metema road
project three bidders have submitted their bid. During bid opening, it has been
noted that the JV of Bidder A-K has offered ETB 101 million while Bidder B offered
ETB 102 Million and Bidder C offered ETB 94.5 Million. The tender document of the
subject project specifies that domestic preference of 7.5% is applicable. There is no
arithmetic error and all bidders fulfill the qualification requirement. Detail of the
bidders is as shown below.
The JV of Bidder A-k is joint venture partner of local firm (wholly owned by
locals and the firm is registered in Ethiopia) and foreign Firm (wholly owned by
foreigners and the firm is registered outside Ethiopia) with 70 % local to 30 %
foreign share, it has quoted in one foreign and local currency and the quoted
exchange rate is for 28 days prior to the bid submission.
Bidder B is a local firm wholly owned by locals, registered in Ethiopia and
quoted in ETB.
Bidder C is entirely owned by Chinese, it has quoted in two foreign and local
currencies and the quoted exchange rate is for 28 days prior to the bid
submission.
You are required to identify the least evaluated bidder? Why? Give short report on
the analysis.
40
6. Procurement complaint
41
A. Complaint Time
Complaints could be received at
different stages of the procurement
process:
 Bidding stage;
 Evaluation stage/before award;
 After Award of contract;
42
B. The right of complaint of a
candidate or a bidder
A candidate or a bidder aggrieved or is likely to be
aggrieved on account of a Public Body inviting a
bid not complying with the provisions of the
proclamation or the directive in conducting a bid
proceeding may present complaint to the head of the
Public Body or to the secretariat of the PPA Board to
have the bid proceeding reviewed or investigated.
43
C. Matters in respect of which
complaint may not be lodged
The selection of procurement method.
The selection of bidders for procurement to be made by
means of restricted tendering or request for quotation or on
the evaluation criteria set forth in the bidding document
beforehand.
the preference given to Domestic firms
Decisions given to reject bids, bid documents or price
quotation pursuant to article 30 of the proclamation.
After 5 working days have elapsed from the date on which the
Public Body disclosed the result of a bid evaluation
No complaint presented to the board after 5 working days
have elapsed from the date on which the Public Body
responded to the complaint shall be accepted
no complaint shall be accepted after a contract was signed,
provided that such contract was signed after seven working
days from the result of the bid evaluation being disclosed
44
D. Procedure for review of complaints
The Public Body conducting bid proceedings shall wait for
seven working days before contract signing or 5 days before
financial opening days after disclosing the result
A candidate or a bidder aggrieved in connection with a
procurement proceeding shall within 5 working days of when he
became aware of or should have been aware of the reason
giving rise to the grievance, may submit his complaint to
the head of the Public Body
Public Body shall give decision on the complaint in
writhing within ten working days from the date of
submission of the complaint
a procurement unit in a Public Body shall suspend a bid
proceeding if it ascertains that a complaint is presented
45
D. Procedure for review of complaints
A bidder may submit a complaint to the board with in
five (5) working days of notification in writing of the decision
of the head of the Public Body on that complaint if the bidder
is not satisfied by the decision of the head of the Public Body
or where the head of the Public Body does not give decision
on such complaint within ten working days
The board shall give its decision in writing to the
complainant and the Public Body within fifteen (15)
working days of receipt of the Public Body’s statement of
response
The secretariat of the board shall send forthwith copies of the
decision of the board to the complainant and the Public Body
A candidate, bidder or supplier aggrieved by a decision of a
Public Body, the board or the Agency, may take the matter
to a competent court
46
WORKS PROCUREMTN EVALUATION OF BIDS.ppt

More Related Content

Similar to WORKS PROCUREMTN EVALUATION OF BIDS.ppt

Bid Evaluation
Bid EvaluationBid Evaluation
Bid EvaluationVj NiroSh
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Joy Irman
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfPSENTHILMURUGAN2
 
Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Mauricio Portugal Ribeiro
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptxDoctorOkelloBen
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...Helix Nebula The Science Cloud
 
An Introduction to Procurement in Social Housing
An Introduction to Procurement in Social HousingAn Introduction to Procurement in Social Housing
An Introduction to Procurement in Social HousingPeter Bird
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSGanesh Bhorkade
 
Tenders , Invitation of tender
Tenders , Invitation of tender Tenders , Invitation of tender
Tenders , Invitation of tender Arpit Sethia
 
Procurement and Subcontractors
Procurement and SubcontractorsProcurement and Subcontractors
Procurement and SubcontractorsSHKLaw
 
Tender Evaluation.pptx
Tender Evaluation.pptxTender Evaluation.pptx
Tender Evaluation.pptxssuser328a4d
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1Joy Irman
 
1 ITT- PG3.ppt
1 ITT- PG3.ppt1 ITT- PG3.ppt
1 ITT- PG3.pptHumayun29
 

Similar to WORKS PROCUREMTN EVALUATION OF BIDS.ppt (20)

Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
TEA checklist
TEA checklistTEA checklist
TEA checklist
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdf
 
Tenders.ppt
 Tenders.ppt Tenders.ppt
Tenders.ppt
 
Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
dgs&d
dgs&ddgs&d
dgs&d
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
 
An Introduction to Procurement in Social Housing
An Introduction to Procurement in Social HousingAn Introduction to Procurement in Social Housing
An Introduction to Procurement in Social Housing
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
 
Tenders , Invitation of tender
Tenders , Invitation of tender Tenders , Invitation of tender
Tenders , Invitation of tender
 
Final standard tender doc
Final standard tender docFinal standard tender doc
Final standard tender doc
 
Procurement and Subcontractors
Procurement and SubcontractorsProcurement and Subcontractors
Procurement and Subcontractors
 
Tender Evaluation.pptx
Tender Evaluation.pptxTender Evaluation.pptx
Tender Evaluation.pptx
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
 
1 ITT- PG3.ppt
1 ITT- PG3.ppt1 ITT- PG3.ppt
1 ITT- PG3.ppt
 

More from Jaafar47

የማሽከርከር ሥነ ባህሪ.pptx
የማሽከርከር ሥነ ባህሪ.pptxየማሽከርከር ሥነ ባህሪ.pptx
የማሽከርከር ሥነ ባህሪ.pptxJaafar47
 
hubannoo_daldala_seeraa_alaa.pptx
hubannoo_daldala_seeraa_alaa.pptxhubannoo_daldala_seeraa_alaa.pptx
hubannoo_daldala_seeraa_alaa.pptxJaafar47
 
Leenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptx
Leenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptxLeenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptx
Leenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptxJaafar47
 
Bitootessa 2015,PMS-Training-2.pptx
Bitootessa 2015,PMS-Training-2.pptxBitootessa 2015,PMS-Training-2.pptx
Bitootessa 2015,PMS-Training-2.pptxJaafar47
 
International Trade.pptx
International Trade.pptxInternational Trade.pptx
International Trade.pptxJaafar47
 
INTEREST RATE DETERMINATION(1).pptx
INTEREST RATE DETERMINATION(1).pptxINTEREST RATE DETERMINATION(1).pptx
INTEREST RATE DETERMINATION(1).pptxJaafar47
 
Micro Theory of Consumer Behavior and Demand.pptx
Micro Theory of Consumer Behavior and Demand.pptxMicro Theory of Consumer Behavior and Demand.pptx
Micro Theory of Consumer Behavior and Demand.pptxJaafar47
 
Chapter 5. Comparative statistics.pdf
Chapter 5. Comparative statistics.pdfChapter 5. Comparative statistics.pdf
Chapter 5. Comparative statistics.pdfJaafar47
 
Haala fi Kallattii KT MNO 2015 summery.pptx
Haala  fi Kallattii KT MNO 2015 summery.pptxHaala  fi Kallattii KT MNO 2015 summery.pptx
Haala fi Kallattii KT MNO 2015 summery.pptxJaafar47
 
Formaatii_walii_galtee.ppt
Formaatii_walii_galtee.pptFormaatii_walii_galtee.ppt
Formaatii_walii_galtee.pptJaafar47
 
Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...
Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...
Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...Jaafar47
 
COMMERCIAL BANKING.pptx
COMMERCIAL BANKING.pptxCOMMERCIAL BANKING.pptx
COMMERCIAL BANKING.pptxJaafar47
 
Education.pptx
Education.pptxEducation.pptx
Education.pptxJaafar47
 
Qajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptx
Qajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptxQajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptx
Qajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptxJaafar47
 
Meeshaalee To annoo(legesse) 2014.pptx
Meeshaalee To annoo(legesse) 2014.pptxMeeshaalee To annoo(legesse) 2014.pptx
Meeshaalee To annoo(legesse) 2014.pptxJaafar47
 
GEQIP E -SG new.pptx
GEQIP E -SG new.pptxGEQIP E -SG new.pptx
GEQIP E -SG new.pptxJaafar47
 
Malaammaltummaafi Barnoota 2015.ppt
Malaammaltummaafi Barnoota 2015.pptMalaammaltummaafi Barnoota 2015.ppt
Malaammaltummaafi Barnoota 2015.pptJaafar47
 
Education.pptx
Education.pptxEducation.pptx
Education.pptxJaafar47
 
CENTRAL BANKING.pptx
CENTRAL BANKING.pptxCENTRAL BANKING.pptx
CENTRAL BANKING.pptxJaafar47
 
Tumaalee Ijoo Seera Bittaa Mootummaa.ppt
Tumaalee Ijoo Seera Bittaa Mootummaa.pptTumaalee Ijoo Seera Bittaa Mootummaa.ppt
Tumaalee Ijoo Seera Bittaa Mootummaa.pptJaafar47
 

More from Jaafar47 (20)

የማሽከርከር ሥነ ባህሪ.pptx
የማሽከርከር ሥነ ባህሪ.pptxየማሽከርከር ሥነ ባህሪ.pptx
የማሽከርከር ሥነ ባህሪ.pptx
 
hubannoo_daldala_seeraa_alaa.pptx
hubannoo_daldala_seeraa_alaa.pptxhubannoo_daldala_seeraa_alaa.pptx
hubannoo_daldala_seeraa_alaa.pptx
 
Leenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptx
Leenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptxLeenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptx
Leenjii Sooftiweerii Bulchiinsa Qabeenyaa Bara 2015 Bitootessa.pptx
 
Bitootessa 2015,PMS-Training-2.pptx
Bitootessa 2015,PMS-Training-2.pptxBitootessa 2015,PMS-Training-2.pptx
Bitootessa 2015,PMS-Training-2.pptx
 
International Trade.pptx
International Trade.pptxInternational Trade.pptx
International Trade.pptx
 
INTEREST RATE DETERMINATION(1).pptx
INTEREST RATE DETERMINATION(1).pptxINTEREST RATE DETERMINATION(1).pptx
INTEREST RATE DETERMINATION(1).pptx
 
Micro Theory of Consumer Behavior and Demand.pptx
Micro Theory of Consumer Behavior and Demand.pptxMicro Theory of Consumer Behavior and Demand.pptx
Micro Theory of Consumer Behavior and Demand.pptx
 
Chapter 5. Comparative statistics.pdf
Chapter 5. Comparative statistics.pdfChapter 5. Comparative statistics.pdf
Chapter 5. Comparative statistics.pdf
 
Haala fi Kallattii KT MNO 2015 summery.pptx
Haala  fi Kallattii KT MNO 2015 summery.pptxHaala  fi Kallattii KT MNO 2015 summery.pptx
Haala fi Kallattii KT MNO 2015 summery.pptx
 
Formaatii_walii_galtee.ppt
Formaatii_walii_galtee.pptFormaatii_walii_galtee.ppt
Formaatii_walii_galtee.ppt
 
Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...
Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...
Biiroo Pabliik Sarviisii fi Misooma Qabeenya Namaa Oromiyaa Wixinee Qajeelfam...
 
COMMERCIAL BANKING.pptx
COMMERCIAL BANKING.pptxCOMMERCIAL BANKING.pptx
COMMERCIAL BANKING.pptx
 
Education.pptx
Education.pptxEducation.pptx
Education.pptx
 
Qajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptx
Qajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptxQajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptx
Qajeelfama_gahee_hojii_suparvaayizaroota_manneen_barnootaa_naann.pptx
 
Meeshaalee To annoo(legesse) 2014.pptx
Meeshaalee To annoo(legesse) 2014.pptxMeeshaalee To annoo(legesse) 2014.pptx
Meeshaalee To annoo(legesse) 2014.pptx
 
GEQIP E -SG new.pptx
GEQIP E -SG new.pptxGEQIP E -SG new.pptx
GEQIP E -SG new.pptx
 
Malaammaltummaafi Barnoota 2015.ppt
Malaammaltummaafi Barnoota 2015.pptMalaammaltummaafi Barnoota 2015.ppt
Malaammaltummaafi Barnoota 2015.ppt
 
Education.pptx
Education.pptxEducation.pptx
Education.pptx
 
CENTRAL BANKING.pptx
CENTRAL BANKING.pptxCENTRAL BANKING.pptx
CENTRAL BANKING.pptx
 
Tumaalee Ijoo Seera Bittaa Mootummaa.ppt
Tumaalee Ijoo Seera Bittaa Mootummaa.pptTumaalee Ijoo Seera Bittaa Mootummaa.ppt
Tumaalee Ijoo Seera Bittaa Mootummaa.ppt
 

Recently uploaded

(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...shivangimorya083
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptx03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptxFinTech Belgium
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Modelshematsharma006
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxhiddenlevers
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdfFinTech Belgium
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfGale Pooley
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...ssifa0344
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Pooja Nehwal
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptxFinTech Belgium
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfGale Pooley
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure servicePooja Nehwal
 

Recently uploaded (20)

(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(DIYA) Bhumkar Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
Russian Call Girls In Gtb Nagar (Delhi) 9711199012 💋✔💕😘 Naughty Call Girls Se...
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptx03_Emmanuel Ndiaye_Degroof Petercam.pptx
03_Emmanuel Ndiaye_Degroof Petercam.pptx
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024
 
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsHigh Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
High Class Call Girls Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Andheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot ModelsAndheri Call Girls In 9825968104 Mumbai Hot Models
Andheri Call Girls In 9825968104 Mumbai Hot Models
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANIKA) Budhwar Peth Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptxOAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
OAT_RI_Ep19 WeighingTheRisks_Apr24_TheYellowMetal.pptx
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdf
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx
 
Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024Commercial Bank Economic Capsule - April 2024
Commercial Bank Economic Capsule - April 2024
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdf
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
 

WORKS PROCUREMTN EVALUATION OF BIDS.ppt

  • 1. WORKS PROCUREMTN EVALUATION OF BIDS 1 By Frew Bekele
  • 2. Contents 1. Introduction 2. Works Contracts 3. Bidding Documents 4. Evaluation And Qualification Criteria Framework 5. Evaluation Of Bids 6. Procurement Complaint 2
  • 3. C. Contents of Each Section of BD Section 2- BDS (PIT) Supplements the ITB by specifying individual bidding document; All clauses refer to Section 1 and are prepared for each specific contract; The BDS will not be part of the resulting contract document; Any change/qualification to be made to the standard ITB is made here and it is wise to see it with care. Any information in the BDS precedence over the one in ITB; 3
  • 4. A. Evaluation Procedure i. Pre-Qualification 4 Submission of pre-qualification document Evaluation Invitation for Bid Bid Submission and Evaluation Approval and award to the least evaluated bidder
  • 5. A. Evaluation Procedure ii. Modified Post-Qualification (two envelope) 5 Submission of P.Q. Application and Financial Offer Evaluation of P.Q. Application Document Opening & evaluation of Financial offer of Post Qualified Bidders Approval and award of the least evaluated Bidder
  • 6. Evaluation Approval Procedure 6 Tender Analysis Committee (TAC) Endorsement of Evaluation by Contract Award Committee Approval of Evaluation Report by the Director General of ERA An Ad hoc committee Comprise of three professionals Standing committee No-objection from financer incase of financed projects
  • 7. Standard Bid Evaluation procedures and principles Bids are Evaluated based on the information/criteria contained in the bidding document (BD); Confidentiality of the process until the successful bidder is notified; Written clarification on ambiguities or inconsistency may be requested; No circumstances shall justify meetings or conversation between the Employer and Bidders during the bid evaluation process; No changes in the bid price or substance are allowed 7
  • 8. C. Sequences of bid evaluation Bid opening Preliminary examination Determination of bid responsiveness Detail Evaluation 8
  • 9. C. Sequences of bid evaluation Bid opening Opening shall be the same time with the deadline for receipt of bids; Date, time and place as announced in the BD; Bids shall be opened in public; Bidders names, offer amounts, Currency of bid, any modification/alternative…are read aloud, Bid security is checked & read; 9
  • 10. C. Sequences of bid evaluation Bid opening cont… Any envelope containing Substitutions, Modifications, or Withdrawals must be read out, recorded; Bids received after the time stipulated will not be opened; No bid should be rejected at the bid opening except those received after the deadline; All records of bid opening are reported as a minute of bid opening. 10
  • 11. Bid Evaluation Committee  A team of min. 3 experts (TAC) or a consultant may carry out the tender evaluation;  Qualified members preferably those who participated in the preparation of BD;  The competence and integrity of the members of the TAC are crucial (specific knowledge)  The members evaluate independently and discuss on their findings 11
  • 12. C. Sequences of bid evaluation Preliminary examination The purpose of preliminary examination is to eliminate any bid from further and more complicated consideration if they don't meet the minimum standard of acceptability – not substantially responsive 12
  • 13. C. Sequences of bid evaluation Preliminary examination Verification: Bids should be properly signed, sealed, valid, Eligibility requirement; Acceptable bid securities; Bid should contain all required documents; Changes should be initialed; Bids should be complete; The above are checks for substantial responsiveness. Bids should not be rejected on trivial /minor deviations or procedural ground. 13
  • 14. C. Sequences of bid evaluation Preliminary examination cont… Examples of minor deviations Failure to initial on few pages of supporting information; Submitting less copies of BDs; Not using the form supplied, but furnishing the required information; Missing of attaching existing documentations (without giving any benefit to the bidder & without prejudice to the interest of other bidders); …etc 14
  • 15. C. Sequences of bid evaluation Preliminary examination cont… Examples of Major deviations Stipulating price adjustment in fixed price tenders Proposing a different design or product that does not offer equivalent performance/not meeting specifications Programming of contract start-up, delivery, installation, or construction that does not comply with required times Subcontracting in a significantly different quantity or method than that allowed Declining to take vital responsibilities and liabilities, e.g. performance guarantees and insurance coverage Taking exception to critical provisions e.g. applicable law, taxes and duties, and dispute resolution procedures; etc… 15
  • 16. C. Sequences of bid evaluation Determination of bid responsiveness A substantially responsive Bid is one, which conforms to all the terms, conditions, and specifications of the bidding documents, without material deviation or reservation. A material deviation or reservation is one ;  (a) which affects in any substantial way the scope, quality, or performance of the Works;  (b) which limits in any substantial way, inconsistent with the bidding documents, the Employer’s rights or the Bidder’s obligations under the Contract; or  (c) whose rectification would affect unfairly the competitive position of other bidders presenting substantially responsive bids 16
  • 17. C. Sequences of bid evaluation Detailed Examination of Bids Correction for Errors; Corrections for Provisional Sums; Modifications and Discounts; Evaluation currency; Application of Domestic Preference; Alternative Bids Priced deviations; 17
  • 18. C. Sequences of bid evaluation Detailed Examination of Bids cont… Correction of arithmetic error Check for consistency of stated quantities and prices; The quantities should be as stated in the BD; Check for total bid price & for any discrepancy; The bidder must accept such arithmetic corrections; 18
  • 19. Corrections and Unconditional Discounts 19 Bidder Read-out Bid Price(s) Corrections Corrected Bid Price(s) Unconditional Discounts2 Corrected/Discou nted Bid Price(s) Currency(ie s) Amount(s ) Computatio nal Errors1 Provision al Sums Percen t Amount(s ) (a) (b) (c) (d) (e) (f) = (c) + (d) - (e) (g) (h) (i) = (f) – (h) etc. Note: Only bids accepted for preliminary examination (Table 5, column g) should be included in this and subsequent tables. Columns a, b, and c are from Table 4 (columns a, d, and e, respectively). 1 Corrections in column d may be positive or negative. 2 If the discount is offered as a percent, column h is normally the product of the amounts in columns f and g. Refer to para. 6(c). If the discount is provided as an amount, it is entered directly in column h. A price increase is a negative discount.
  • 20. C. Sequences of bid evaluation Detailed Examination of Bids cont… Conversion to common currency Convert to Borrower country’s currency at the selling rate (for comparison purpose only); Reference date for currency conversions & source to be used are indicated in BDS. 20
  • 21. Conversion to common currency 21 Bidde r Corrected/Discou nted Payment Composition1 Exchang e Amounts in Exchang e Evaluation Currency Bid Price (in specified currency) Currency of Payment Percent of Total Bid Amount in Evaluatio n Currency Rate Used by Bidder1 Currency of Payment Rate for Evaluatio n2 Bid Prices Total3 (a) (b) (c) (d) (e) = (b) x (d) (f) (g) = (e) x (f) (h) (i) = (g) x (h) (j) etc.
  • 22. Domestic Preference for domestic bidders allows a 7½ percent margin of preference for domestic bidders. Sub clause 32.3 states that a domestic bidder is one that meets the following criteria: for an individual firm: (i) is registered in the country of the Employer; (ii) has more than 50 percent ownership by nationals of the country of the Employer; (iii) Does not subcontract more than 10 percent of the Contract Price, excluding Provisional Sums, to foreign contractors. 22
  • 23. Domestic Preference for domestic bidders for a joint venture (JV) of domestic firms: (i) individual member firms shall satisfy Sub-Paragraphs 32.3 (a) (i) and (a) (ii) above; (ii) the JV shall be registered in the country of the Employer; (iii) the JV shall not subcontract more than 10 percent of the Contract Price, excluding Provisional Sums, to foreign firms. 23
  • 24. Domestic Preference for domestic bidders Bidder Corrected/ Discounted Bid Price Domestic Preference Group Total Evaluation Currency (converted in to Single Currency) Preference (7½%) Total Comparison Price (a) (b) (d) (e ) (f) (g) = (e) + (f) 24
  • 25. C. Sequences of bid evaluation Detailed Examination of Bids cont… Application of qualification/evaluation criteria Strictly apply only the evaluation and qualification criteria specified in the BD; In the case of Post qualification of bidders, the criteria for post qualification should be clearly set out in the BD; If the lowest evaluated bidder fails to meet minimum qualification requirements, the bid is rejected and the next lowest evaluated bidder is subject to post qualification. (in case of one envelope system). Otherwise; will be rejected before opening of the financial bid 25
  • 26. C. Sequences of bid evaluation Detailed Examination of Bids cont… Comparison of bids After all arithmetic corrections and conversion to common currency is made, bids are compared:  To determine the lowest evaluated bidder;  With the engineer’s/Employer’s estimate; 26
  • 27. Preparation of evaluation report It Is Good Practice To have “Table of Contents” Bid Evaluation Summary Checklist The Report should record all necessary information including:  Background of the project and financing;  Bid opening events & minute; 27
  • 28. Preparation of evaluation report The report covers among other things  Key dates and steps in the bidding process  Bid prices, corrections, discounts & currency conversion  Deviations  Domestic preference  Qualification results  Clarification process  Name of bidders rejected & the reasons  Proposed contract award 28
  • 29. D. Common mistakes during Bid evaluation Rejecting proposals/bid during opening (Conducting evaluation during bid opening); Using criteria which is not communicated to bidders in the bidding document Rejecting proposals/bid on trivial procedural ground Arithmetic checking using bidders quantity Currency conversion using inappropriate exchange rate Discount application Eligibility or Exclusion for domestic preferences 29
  • 30. E. Common mistakes of bidders Missed to enclose the bid submission forms Lack to indicate the bid validity period Using unapproved format for bid security Missed to signed and stamp the document Missed to attached appropriate power of attorney Missed to attached the required attachments Providing incomplete information Using other standard bidding documents as well as clauses than the specific project Deviation from the scope, and others 30
  • 31. 8. Questions for discussions 1. A bidder has arrived a minute after the deadline for submission. Will the bid be accepted? 2. The bidders bid validity period has been found 2 days short of the specified 120 days. Is it minor or major deviation? 31
  • 32. 9. Questions for discussions 3. In ICB bid, A bidder has not submitted Renewed license. Will it be reason for rejection? Why? 4. After bids were submitted, A bid opening was postponed due to unavailability of majority of the tender committee. Is there any problem with this? why 32
  • 33. Questions for discussions 5. The bidder has forgotten to include his renewed trade license in his bid: 1. Is it minor or major deviation? 2. The bidder was requested to submit the missed document and submitted the license which has been renewed after the dead line for bid submission. Will you reject the bidders bid? 33
  • 34. Questions for discussions 6. List some of examples of major deviations in bids; 7. A bidder has written in his bid the following: “We would like an increase in the amount of mobilization advance”. Can this be considered as deviation? 34
  • 35. Questions for discussions 8. A bid document was found that the bidding form was not signed, but the bidder’s stamp is there. Is it material deviation? 9. The client has varied the quantity of items to be purchase by more than 15% during award. What technical & procedural problems does this involve? 35
  • 36. 10.Cases for discussions Cases 1: During the bid evaluation of an ICB major works contract ( in which only 4 bidders were shortlisted through prequalification process and only 2 submitted their bids), a major unbalanced rate to one work item was discovered in the bid of the lowest bidder. The procuring entity has requested the bidder for clarifications and breakdowns of the very exaggerated rate. The bidder had submitted his breakdowns and during reviewing the submitted breakdowns, the client learned that the bidder has made mistakes in the unit of measurement of the work item whose rate was exaggerated. Correcting the unit of measurement from LM to CM , as it is in the BD, would reduce the price offered by about USD 6 Million. The client has made no change to the breakdown except the unit of measurement and considered this as “correction of arithmetic errors discovered by the client during the evaluation of the bids, in accordance with ITB clause 31”. And recommended the award with the corrected Price.  Is this arithmetic corrections?  Is the process fair, transparent, and acceptable?? 36
  • 37. Cases 2 EXCEPTIONALLY LOW BID The six low bids for a road civil works contract have produced the following results after evaluation: € Bid A (Foreign) 4,880,243 Bid B (Local) 6,547,576 Bid C (JV Foreign) 6,841,782 Bid D (Local) 7,449,621 Bid E (JV Foreign/Local) 7,810,934 Bid F (Foreign) 8,075,122 The Employer’s estimate was €6,650,000. All of the above firms were pre-qualified. If the lending institution financing this project required the contract to be awarded to the bidder who was the “lowest evaluated, and met the appropriate standards of capability and financial responsibility” it would appear that Firm A should be awarded the contract. Questions: (a) On the basis of the information above, what possible objections would you raise to an award to Firm A? (b) If Firm A is awarded the contract, should the Performance Security be increased above the stated 10%? 37
  • 38. CASE NO. 3 38 QUALIFIED BID The following conforming bids are received on a construction project: A €m98 B €m100 C €m102 The bid validity period is 90 days. B offers a price reduction of 5% (i.e. a bid of €95 million) if the bid evaluation can be completed and the notification of award made within 60 days, because he is already mobilized on a nearby site with construction nearing completion, and has his labor force waiting. Question 1: Can the Employer consider B’s alternative offer? Question 2: What if (A) had made a similar offer?
  • 39. CASE NO 4: QUANTIFIABLE QUALIFICATION Bids were received on a works contract in a remote area. The bidding documents stated: “There is a Class 3 public road providing access to the site.” [Road transport regulations in the country stated that Class 3 roads were designed to carry 10 ton axle loading.] The low bidder, in the amount of €100M, qualified his bid as follows: “My bid is based on the assumption that the State or Employer, in order to provide access to the site, will strengthen any weak bridges as necessary to carry my heavy equipment, which has maximum axle loading of 10 tons.” One other bidder made a similar qualification; the remaining six bidders had no comment on access. A quantification of the qualification, i.e. for the Employer to arrange for repair of the bridges, amounts to €3 million, bringing the low bidder’s evaluated price to €103 million. The next low bidder (without qualification) is €110 million. Although originally designed for 10 ton axle loading, some bridges were now in poor condition. The timing of the repair work might place the Employer at risk regarding claims from the Contractor for delay in mobilization. The Employer is faced with a number of alternatives: 1) ask the bidder to withdraw his qualification without any change in bid price; 2) reject the bid as non responsive (i.e. containing a material deviation) and award the contract to the next low bidder at €110m; 3) accept the qualified bid in the amount of €100m (since it is the lowest evaluated at €103m), then arrange for repair of the bridges himself, and risk claims from the Contractor subsequently for delay; 4) accept the qualified bid in the amount of €100m, then issue an extra works order after award of contract for the contractor to do the work, or 5)somehow, without infringing the Rules, or the bidding conditions, or being unfair to other bidders, shift the responsibility for bridge repair to the Bidder/Contractor before award of contract, albeit at increased cost. Question: How would you proceed as Employer? 39
  • 40. Exercise Subsequent to ERA invitation to participate for ICB project of Azezo-Metema road project three bidders have submitted their bid. During bid opening, it has been noted that the JV of Bidder A-K has offered ETB 101 million while Bidder B offered ETB 102 Million and Bidder C offered ETB 94.5 Million. The tender document of the subject project specifies that domestic preference of 7.5% is applicable. There is no arithmetic error and all bidders fulfill the qualification requirement. Detail of the bidders is as shown below. The JV of Bidder A-k is joint venture partner of local firm (wholly owned by locals and the firm is registered in Ethiopia) and foreign Firm (wholly owned by foreigners and the firm is registered outside Ethiopia) with 70 % local to 30 % foreign share, it has quoted in one foreign and local currency and the quoted exchange rate is for 28 days prior to the bid submission. Bidder B is a local firm wholly owned by locals, registered in Ethiopia and quoted in ETB. Bidder C is entirely owned by Chinese, it has quoted in two foreign and local currencies and the quoted exchange rate is for 28 days prior to the bid submission. You are required to identify the least evaluated bidder? Why? Give short report on the analysis. 40
  • 42. A. Complaint Time Complaints could be received at different stages of the procurement process:  Bidding stage;  Evaluation stage/before award;  After Award of contract; 42
  • 43. B. The right of complaint of a candidate or a bidder A candidate or a bidder aggrieved or is likely to be aggrieved on account of a Public Body inviting a bid not complying with the provisions of the proclamation or the directive in conducting a bid proceeding may present complaint to the head of the Public Body or to the secretariat of the PPA Board to have the bid proceeding reviewed or investigated. 43
  • 44. C. Matters in respect of which complaint may not be lodged The selection of procurement method. The selection of bidders for procurement to be made by means of restricted tendering or request for quotation or on the evaluation criteria set forth in the bidding document beforehand. the preference given to Domestic firms Decisions given to reject bids, bid documents or price quotation pursuant to article 30 of the proclamation. After 5 working days have elapsed from the date on which the Public Body disclosed the result of a bid evaluation No complaint presented to the board after 5 working days have elapsed from the date on which the Public Body responded to the complaint shall be accepted no complaint shall be accepted after a contract was signed, provided that such contract was signed after seven working days from the result of the bid evaluation being disclosed 44
  • 45. D. Procedure for review of complaints The Public Body conducting bid proceedings shall wait for seven working days before contract signing or 5 days before financial opening days after disclosing the result A candidate or a bidder aggrieved in connection with a procurement proceeding shall within 5 working days of when he became aware of or should have been aware of the reason giving rise to the grievance, may submit his complaint to the head of the Public Body Public Body shall give decision on the complaint in writhing within ten working days from the date of submission of the complaint a procurement unit in a Public Body shall suspend a bid proceeding if it ascertains that a complaint is presented 45
  • 46. D. Procedure for review of complaints A bidder may submit a complaint to the board with in five (5) working days of notification in writing of the decision of the head of the Public Body on that complaint if the bidder is not satisfied by the decision of the head of the Public Body or where the head of the Public Body does not give decision on such complaint within ten working days The board shall give its decision in writing to the complainant and the Public Body within fifteen (15) working days of receipt of the Public Body’s statement of response The secretariat of the board shall send forthwith copies of the decision of the board to the complainant and the Public Body A candidate, bidder or supplier aggrieved by a decision of a Public Body, the board or the Agency, may take the matter to a competent court 46