The document provides an update on the Waller Creek Tunnel Project, including summaries of progress on sub-projects such as the Lady Bird Lake Trail Bridge, PARD Boat Facility, Tunnel/4th Street Inlet, and restoration projects. Most sub-projects are currently in design or construction phases. The Tunnel/4th Street Inlet is scheduled to begin construction in late February 2011. Public outreach efforts include flyers and signage around construction sites and planning a groundbreaking for the tunnel.